Escolar Documentos
Profissional Documentos
Cultura Documentos
Note:
Before and during this task ensure all applicable safety requirements are followed.
Only those contractors with approved accreditation from the infrastructure owner are permitted to work on the network.
Do not deviate from the specifications provided, without prior approval from NBN.
Do not conduct any hauling activities involving infrastructure carrying live services, without first raising a hazard notification and
gaining approval from the relevant operator(s).
Do not commence digging without first checking for other assets via the Dial Before You Dig website or 1100 phone number.
Preparation
Identify potential locations for laying up and back feeding activities, and change
of cable directions.
Ensure cable is installed in the correct duct as per the design plan.
Page 2 of 11
Route
Page 3 of 11
Page 4 of 11
Hauling Aids
Page 5 of 11
Page 6 of 11
Damage
they are removed as per the asbestos process and the cross
bars replaced
Page 7 of 11
Cable Handling
During installation the cable must not exceed the bend radius
stipulated by the manufacturer.
Page 8 of 11
Hauling Winches
When laying up cable, consider the size and type of cable, bend radius
of cable, area required to lay up, pedestrian and vehicle traffic, weight of
cable and if cable contains a drum memory (coiling capacity and recoil
risk).
Page 9 of 11
Page 10 of 11
This is not intended to be an exhaustive list of instructions. Please see your site supervisor for more detailed information.
NBN Co Limited | Uncontrolled when printed
Page 11 of 11