Jahra Governorate, Kuwait

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL


EQUIPMENT, FURNISHING, AND OPERATIONAL MAINTENANCE
OF

THE NEW JAHRA HOSPITAL


(RE-TENDER)

PRELIMINARY CONSTRUCTION METHOD STATEMENT


& MASTER CONSTRUCTION SCHEDULE
Employer:

AMIRI DIWAN
TENDER NO. (//)

Prepared by:

MOHAMMED ABDULMOHSIN AL-KHARAFI & SONS CO.

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL

TABLE OF CONTENTS
1

Narrative Description: ................................................................................................................ 4

1.1

Purpose ....................................................................................................................................... 4

1.2

Project Description ..................................................................................................................... 4

1.3

Project Location ......................................................................................................................... 4

1.4

Contract Data Summary ............................................................................................................. 4

Methodology .............................................................................................................................. 5

2.1

General ....................................................................................................................................... 5

2.2

Design & Construction of the project contains the following main items: ................................ 5

2.2.1 Design Stage............................................................................................................................... 5


2.2.2 Construction stage ...................................................................................................................... 6
2.3

Mobilization ............................................................................................................................... 6

2.4

Communication Control ............................................................................................................. 7

2.5

Coordination Meeting Strategy .................................................................................................. 7

2.6

Engineering Activities ................................................................................................................ 7

2.6.1 Subcontractors ............................................................................................................................ 7


2.6.2 Shop Drawings ........................................................................................................................... 8
2.6.3 Materials ..................................................................................................................................... 8
2.6.4 Procurement Planning and control ............................................................................................. 8
2.7

Work Activity and Construction stage ....................................................................................... 9

Buildings of the project ............................................................................................................ 11

3.1

Hospital HSP ............................................................................................................................ 11

3.2

Dental Clinic DNT ................................................................................................................... 17

3.3

Regional Health Admin RHA .................................................................................................. 19

3.4

Central Utility Plant CUP ......................................................................................................... 20

3.5

Staff Car Park CP1 ................................................................................................................... 21

3.6

Public Car Park CP2................................................................................................................. 23

General Construction Activities Civil/Finishing Works ....................................................... 25

4.1

Civil Works .............................................................................................................................. 25

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page2of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL


4.1.1 Shoring, Dewatering & Excavation ......................................................................................... 25
4.1.2 Concrete Works ........................................................................................................................ 25
4.1.3 Formwork ................................................................................................................................. 25
4.1.4 Steel Reinforcement ................................................................................................................. 26
4.2

Finishing Works ....................................................................................................................... 27

4.2.1 Walls Finishing ........................................................................................................................ 27


4.2.2 Work Sequence ........................................................................................................................ 27
4.2.3 Ceilings Finishing .................................................................................................................... 27
4.2.4 Floors Finishing ....................................................................................................................... 27
4.2.5 Metal Works ............................................................................................................................. 28
4.2.6 Roofing Works ......................................................................................................................... 28
4.2.7 Doors and Windows ................................................................................................................. 28
4.2.8 Glazed Aluminum Curtain Walls ............................................................................................. 29

Resources ................................................................................................................................. 30

5.1

Equipment ................................................................................................................................ 30

5.2

Cranes ....................................................................................................................................... 31

MAINTENANCE OF WORK ................................................................................................. 32

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page3of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL


1

Narrative Description:
1.1

Purpose

The Purpose of this preliminary method statement is to set out the general manpower,
equipment and sequence of work required to complete the project. This is a live document
which will be detailed at a later stage and extended at regular intervals as further method
statements for areas of work are prepared. The method statement is a quality controlled
document, reviewed and issued in accordance with the quality plan and will be audited and
updated as necessary.

1.2 Project Description


The main purpose of The New JAHRA Hospital Project is to enhance the provision of
Medical facilities for the people of Kuwait, the Amiri Diwan plans the construction of the
New Jahra Hospital. This shall provide a comprehensive range of services, and shall offer
exemplary care of the highest international standards.

1.3 Project Location

PROJECTLOCATION

1.4 Contract Data Summary


M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page4of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL


Contract Title:

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL


EQUIPMENT, FURNISHING, AND OPERATIONAL MAINTENANCE OF
THE NEW JAHRA HOSPITAL

Employer:

DIWAN AMIRI

Contract Duration:

730 Days

Methodology
2.1 General
TheContractorwillorganizeandimplementalltheactivitiesnecessarytoachieve
efficientandtimelycompletionoftheprojectbythefollowing:
Assuringcompliancewithcontractrequirementsandschedulecommitments
andworkingdrawingsandcompletionoftheprojectontime.

Overseeing interface and ensuring proper coordination with and between


subcontractorstocompletetheprojectontime.

Overseeingmaterialandshopdrawingsapprovalsandmaterialprocurement.

Ensuringavailabilityofmanpowerandequipmentresources.

Overseeingtheenforcementofthequalityandsafetycontrolprograms.

Ensuringavailabilityofmanpowerandequipmentresources.

2.2 Design & Construction of the project contains the following main items:
2.2.1 Design Stage
Tender of this project Includes (but not for all buildings) the final stage of buildings design
with Final Concrete Dimension and structure steel reinforcement, therefore the first step of this
project is completing design stage for all buildings which will done within two phases:
a- Design Development
b- Design Coordination and Details
Where coordination means primary coordination in design stage between Architecture,
Structure, Electro-Mechanical Services and other trades of the project items

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page5of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL


2.2.2 Construction stage
The New JAHRA Hospital Project comprise of 6 Buildings will be Built in construction
stage the following:
01HospitalHSP

02DentalClinicDNT

03RegionalHealthAdminRHA

04CentralUtilityPlantCUP

05StaffCarParkingCP1

06PublicCarParkingCP2

2.3 Mobilization

ThesitewillbeinspectedbytheContractortoidentifythevariousexistingservicesand
suchservicesshallbedirectedandsealedbeforestartingtheworkinaccordancewiththe
relatedauthorities,statutoryagencies,etc..Allrequiredqualitycontrol&safetyprocedures
shall be followed. Temporary site offices and facilities will be installed after obtaining
requiredgovernmentalpermitsandaccordingtotheapprovedconstructionschedule.Also
thetemporaryfenceandprojectsignboardswillbeinstalledinthisperiod.

OfficesandworkshopProposedPlaces

Mobilization Site Plan

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page6of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL


2.4 Communication Control
Communication Control is key to Management this project and keeping all stakeholders,
management,staffandprojectteaminformedandawareatallstagesoftheprojectisvital
tothesuccessoftheproject.Ourcommunicationmanagementmodelshallstreamlineand
integrate project information with all stakeholders and facilitate sharing and project
collaboration.Itshallprovidesecure,integratedaccesstoprojectwideperformancemetrics,
reportsandprojectdata.

2.5 Coordination Meeting Strategy


ThepurposeistodefinetheCoordinationprocedure,whichshallbeusedthroughoutthis
project. This is intended to facilitate clarifications of any nature related to drawing
coordination, Site coordination between the Coordinators of each Trade of the
Subcontractors.
1. PriortothestartoftheContractorsactivitiesaccordingtotheApprovedSchedule,
theMainContractorshallnotifyinadvancetheSubcontractorsoftheiranticipated
activitiesinthesite.
2. FollowingasiteinvestigationbetweentheSubcontractorsandtheMaincontractor
shallbecarriedouttoensurethecompatibilityofequipments,temporaryfacilities
andstorageofmaterialinthesite.
3. A construction progress meeting shall be arranged regularly between the Main
Contractor and the Subcontractors to discuss the different queries during the
constructionofwork.

2.6 Engineering Activities


2.6.1 Subcontractors
Thecontractorshallfollowtheregularrulesinappointingsubcontractorshewishestousein
theprojectwithprovisionthattheyhavethenecessaryexperiencetocarryouttheworksand
arespecifiedinaccordancewithParticularSpecificationsorequalalternative.Thecontractor
willsubmitthespecialistsubcontractorsforapprovalbytheconsultantandclient.

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page7of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL


2.6.2 Shop Drawings

Acomprehensivestudyofthecontractdesigndrawingsshallbemadebythecontractors
technicaldepartment.Coordinationbetweendrawingsshallbeperformedpriortotheissue
of shop drawings. Shop Drawings will be coordinated with other interfacing contractors
working in the area and signed off by each of them. The contractor will submit the shop
drawingslogforapprovalbytheconsultantforshopdrawingsprogressmonitoring.

2.6.3 Materials

The contractor will submit the materials log for approval by the consultant for materials
progressmonitoring.TheMaterialswillbesubmittedaccordingtothelogforapprovalbythe
consultantandMinistry.

2.6.4 Procurement Planning and control

Materialprocurementwillbeperformedaccordingtotheapprovedconstructionschedule.
Material needed for construction shall be procured and stored in the project site store, if
applicable, until it is executed onsite. The duration of material procurement will differ,
dependingonitsavailability,leadtimeandcountryoforigin.Longleaditemsshouldbegiven
specialattentionin ordertosubmitforapprovalasearlyaspossible.TheContractorshall
issuepurchaseordersand/ordeliveryordersinatimelymanner,consistentwiththeoverall
constructionschedule.Thecontractorshallmakearrangementsdirectlywiththetransporter
orthroughasuppliertohaveorderstransportedtothecontractor'ssitestore,ifapplicable,
orthecontractorswarehouse.Aftertheapprovalofmaterialsource,manufacturersdata
andsample,theContractorshallplaceordersforthematerialforeachportionofthebuilding
andworkslistedintheContractforapproval.Thesequencefororderingofmaterialsvisvis
thevariousapprovalsoftheEngineersRepresentativeshallbeasfollows:
1. ObtainapprovaltosourceofMaterial/manufacturerofproduct.
2. Obtainapprovaltotechnicaldata/manufacturerdataofmaterial/product.
3. ObtainapprovaltoSample.
4. Placeorder.

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page8of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL


2.7 Work Activity and Construction stage
The New JAHRA Hospital Project comprise of 6 Buildings will be Built in
construction stage the following:
01HospitalHSP
02DentalClinicDNT
03RegionalHealthAdminRHA
04CentralUtilityPlantCUP
05StaffCarParkingCP1
06PublicCarParkingCP2
07ExternalWorkEW

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page9of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL

6
2
1

Project Layout (The New JAHRA Hospital Buildings)

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page10of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL


3

Buildings of the project


3.1 Hospital HSP
ThisBuildingistheMainBuildingofthenewJAHRAhospitalprojectanditconsistsof
basementfloor,groundfloorand13floorsasthefollowingdetails:
TheHospitalBuildingDesignedwithtotalfloorsareaabout401,600m2
theconstructionofthisbuildingConsistsof:
BasementFloorRetainingWallsabout1,300mLx6mH=7,800m2

TowersAreaabout
270mx130m
Requiresshoringfor400meter

Theshoringwillcover1300meterlengthwithabout8metersheight
AnchoringMachineinstall5anchores/daywhichcover10meterlengthforonerow
Thismeansthatwerequires4anchoringmachinestocoverfirst400meterlengthshoringwithin25days
tostart(excava onandlevelingfortowerarea250x150m)
A erthatcon nuetheshoringwith2Machinesonlytocompleteshoring10m(5anchors/onerow)/day
foreachwhichrequiresabout135daystocompletetheshoringprocess

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page11of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL

BasementFloorSlabareaabout67,750m2

Inordertoconstructthisareawithin112dayswehavetoprovide45,000m2ofshutter
WhereweshallstartFormworkof1st22,500m2
1. NextstepstartFormworkof2nd22,500m2atthesametimeoffixingsteelrebarandconcretepouring
in1stpart
2. Nextstepstartfixingsteelof2nd22,500m2atthesame meofconcretetreatmentof1stpart
3. NextstepDismantling1stpartformworkandstartFormworkof3rdpart22,500m2atthesametimeof
completefixingsteelrebarandconcretepouringin2ndpart
4. Laststepfixingsteelrebarandpouringtheremainingpart

PART

PART

PART

(3)

(2)

(1)

Basement floor parts of shutters

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page12of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL

GroundFloor3rdFloorSlabareaabout42,375m2forEach
4thFloorSlab(Mechanical,AtriumandTowers)areaabout52,725m2

PART

PART

(2)

(1)

Ground Floor to 4th Floor parts of shutters and Procedure


Inordertoconstructthisareawithin112daysforeachFloorwehavetoprovidethehalfareaofshutter
whichisapproximatelyexistinbasementfloor(about22,500m2)andaftercompletingbasementfloor
shu erfor(45,000m2ofshutterwillbeavailabletousefornextfloors)
1. WhereweshallstartFormworkof1stHalffloorFormwork(22,500m2)
2. NextstepstartFormworkof2ndHalfofGroundFloorabout(22,500m2)atthesametimeoffixing
steelrebarandconcretepouringin1stpart.
3. Nextstepstartfixingsteelrebarandpouringof2ndpartabout(22,500m2)atthesametimeof
concretetreatmentof1stpart.
4. NextstepDismantling1stpartformworkandstartFormworkof1stpartof1stetc.uptocompletion
of4thfloor.

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page13of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL

TOWERS 14 FLOORS

Hospital Building with Required Tower Cranes

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page14of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL


Hospital Building with Required Tower Cranes

LowerBuildingDividedinto6PartsNeed(6CranesNos)
UpperBuildingsConsistsof4TowerNosNeed2CranesforEach,(8CranesNos)

FourNumberofTowers(A,B,C&D)Con nuefromLevel5toLevel13withtypical
floorAreaabout3750m2foreach(Total=15000m2)

Tower

Tower

Tower

Tower

(4)

(3)

(2)

(1)

ProvideoneworkmanshipcrewandonesetofshutterforColumnsandCore
wallstocoverHalfFloorsforeachtoweratthesametime(Fixing,Pouringand
Dismantle=12days)
Provide3SetsofSlabshu ertocover3Floorsforeachtower
(Formwork,SteelFixingandPouring=12days/HalfFloor)foreachtower
SlabFloorDuration(18+18=36Days)
ThatMeansOnetowerFloorSlabRequires:(12+18+18=48Days)
ConsideringLagtime10daysrequiredbetweeneachtowerstartingworkforraft
undereachtower(3x10=30Days)
Completefloorofalltowerstakes(30+48=78Days)forEachFloor.

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page15of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL


o

TotalshutterrequiresatthesametimeforComple ng3floors:
(3x15000=45,000m2)whichisavailablefrombasementfloorwork.

Tower

Tower

Tower

Tower

(4)

(3)

(2)

(1)

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page16of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL


3.2 Dental Clinic DNT
TheNewDentalBuildingbesideanExistingone,Designedwithtotalfloorsareaabout
29,800m2theconstructionofthisbuildingConsistsof:
BasementFloorSlabareaabout10,000m2
BasementRetainingWallsareaabout400mLx4mH=1,600m2
1anchoringmachinewillbeusedtocomplete400MLofshoringworkwithin60Days
whereMachinecanmake4anchorsforonerow/day(4anchorscover8meterLength)
Ground,1st,2ndFloorSlabsareaabout5,600x3=16,800m2
MechanicalRoofSlabareaabout3,000m2
PartofBasementFloorSlabisPrecastPrestressedDoubleTTSlab
MajorAreaofBasementFloorandOtherFloorsareHollowBlockSlabribbedSlab
Requiredshu erabout5000m2foroneFlooronly

HollowBlockSlabRibbedSlab

TTPrecastSlab

TTPrecastSlab

TTPrecastSlab

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page17of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page18of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL


3.3 Regional Health Admin RHA
TheRegionalHealthAdminBuildingoftheproject,Designedwithtotalfloorsareaabout
4,690m2theconstructionofthisbuildingConsistsof:
BF,GF,1STandROOF
1anchoringmachineswillbeusedtocomplete215MLofshoringworkwithin37Days
whereMachinecanmake4anchorsforonerow/day(4anchorscover8meterLength)

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page19of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL


3.4 Central Utility Plant CUP
TheCentralUtilityPlantCUPBuildingoftheproject,Designedwithtotalfloorsareaabout
8,270m2theconstructionofthisbuildingConsistsof:
BF,GF,1STandROOF

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page20of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL


3.5 Staff Car Park CP1
TheCarParkCP1Building,Designedwithtotalfloorsareaabout104,020m2
TheconstructionofthisbuildingConsistsof:
BasementFloorSlabareaabout14,860m2
BasementRetainingWallsareaabout700mLx4.5mH=3,150m2RetainingWalls
1anchoringmachinewillbeusedtocomplete500MLofshoringworkwithin50Days
whereMachinecanmake4anchorsforonerow/day(4anchorscover8meterLength)
Basementra willdividedinto3partsasshown
Eachpartwillbedividedinto2ZonesthroughServicePathRoadwhereequipmentwill
respectdirectionandsequenceasshowninfiguresbelow

Part
(1)

Part
(2)

Part
(3)

Weshallprovide50M.Lofshu erwithHeightof4MforRetainingWallsReuseEvery7
Days(7M.L/Day)whichmeans:tocompletethisitem(700M.Lofretainingwalls
Requirewithin100days)
GroundFloorSlaband5TypicalFloorSlabsareaabout14,860x6=89,160m2

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page21of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL

Stairs(11Nos)&Columns(120Nos)require30days,15/halffloorandthenstartfixing
DoubleTTprestressedslabsbyUsing2MobileCranestofix4piecesbyeach(8
pieces/day)whereitrequires42daystofix331pieces/floor
RoofSlabforstaircasesandotherareacoveredwithTentswhichrequirelightstructure
system.
FinishingItems(DrainageSystem,ConcreteTopping,Paving,Hardenersignageand
epoxyetc.)required135days/floor
Wallfinishingitemsandventilationsystemrequires180/floor
FireFighting,LTandSecuritySystemsrequires135days/floor

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page22of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL


3.6 Public Car Park CP2
TheCarParkCP1Building,Designedwithtotalfloorsareaabout65,320m2
TheconstructionofthisbuildingConsistsof:
BasementFloorSlabareaabout9,760m2
BasementRetainingWallsareaabout557mLx4.5mH=2,506m2
Shu ersRequiredis40MLwillReUsed/7Days(6ML/Day)requirewithin(90days)to
completeretainingwalls
GroundFloorSlaband5TypicalFloorSlabsareaabout9,260x6=55,560m2
RoofSlabforstaircasesandotherareacoveredwithTents
FinishingItems(DrainageSystem,ConcreteTopping,Paving,Hardenersignageand
epoxyetc.)required75days/floor
Wallfinishingitemsandven la onsystemrequires150days/floor
FireFighting,LTandSecuritySystemsrequires112days/floor

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page23of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page24of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL


4

General Construction Activities Civil/Finishing Works


4.1 Civil Works
4.1.1 Shoring, Dewatering & Excavation
Theequipmentwhichwillbeusedintheshoring,dewatering&excavation
works,varyinquantities&numbers,dependingontheworkvolumetobe
executed.
Floodlightswillbeusedtolightenthesiteatnightinthecaseoftheworks
beingcarriedatnight.Allsafetyrules&regulationsaspertheapproved
safety manual & local authorities requirements shall be strictly
implemented and monitored by installing all warnings & safety signs in
propervisiblelocationsalongthesite.

4.1.2 Concrete Works


Readymixconcretewillbeobtainedfromanapprovedreadymixplantas
perapproveddesignmixandwillbetransportedtositebytransitmixers
bysequencingtheirmovementinordertoavoidlongwaitingperiods.
Concretedischargetotherequiredformworkwillbearrangedbyconcrete
pumpsandcranes.
All precautions shall be taken during casting in hot weather in order to
guaranteequalityofconcreteasperspecifications.
Allconstructionjointsshallbecleanedandtheaggregateexposed.
Allconcretewillbevibratedandconcretewillbeprotectedandcuredas
perContractSpecifications.

4.1.3 Formwork
Formwork acceptable to the consultant will be used taking into
considerationsafetyandqualityControlrequirements.
Requiredshopdrawingsforformworkshallbesubmittedforapprovalby
theconsultant.
Adequatequantityofformworkwillbemadeavailableatsiteinorderto
ensure Speedy progress and meet the approved construction schedule
dates.
The figure below illustrates a typical vertical wall formwork placing and
bracing.

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page25of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL

4.1.4 Steel Reinforcement


TheContractorshallensurethatallsteeldeliveredtothesiteshallcome
from the source accepted by the Consultant who will be requested to
inspectallbatchesofsteelreinforcement.
Reinforcement shall be protected at all times from contamination and
corrosionfromthegroundandatmosphereduringallstorage,bendingand
handlingoperations.
Allreinforcementwillbeproperlystoredundercovertoavoidcontactwith
theground,moisture,dustandsaltsandtoavoiddistortiononcebentto
shape. Improper storage will be sufficient cause for rejection of
reinforcement.
Allsteel,beforebeingplacedinposition,shallbethoroughlycleanedof
looserust,scaleandanyothercoatingthatwilldestroyorreducebonding
withconcrete.Ifreinforcementhasbeenbadlyrustedorpitteditwillbe
rejected,Mechanicalbrushesshallbeusedincleaningthesteelbars.
Allreinforcementbarsshallbecutandbenttoshapeasperthecontract
drawingsortheapprovedshopdrawing/barbendingschedule.

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page26of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL

All reinforcement shall be transported taking into consideration safety


precautions and will be lifted and fixed into position as per approved
drawingsandContractSpecifications.

4.2 Finishing Works


4.2.1 Walls Finishing
Allmaterialofwallsfinishingsuchasconcreteblocks,plaster,partitions,
stone&ceramicswillbefromanapprovedsourceasperspecifications.All
materialswillbepackedandhandledinsuchawayaspermanufacture
instructions.
Thereshallbenostainsordamagestothesurfacesandexposededges.
Materialwillbestoredatthefactoryoratsiteonwoodenplatformsoras
recommendedbythemanufacturer.
Thefinishingmaterialonwallswillbeinstalled/erectedasperapproved
construction schedule, approved shop drawings, manufacturer
recommendationsandContractSpecifications.
4.2.2 Work Sequence
Before starting any walls finishing activities, all concrete works will be
checkedandapprovedbytheconsultantforembedded/concealeditems
likeconduits,sockets,accessories,etc.
Masonry works and successively plastering works should start after
removingtheslabformwork.
4.2.3 Ceilings Finishing
All material for ceilings like hangers, framing, supports, ceiling tiles and
specialfinisheswillbefromanapprovedsourceasperspecifications.
Allmaterialswillbeproperlystoredwithadequatemarkings.
Allceilingfinishesshallbecarriedoutinaccordanceandcoordinationwith
HVAC,Plumbing,firefightingandElectricalworksintheceiling.
Site fabrication and installation shall be as per approved construction
schedule,approvedshopdrawingsandContractSpecifications.
4.2.4 Floors Finishing
Allmaterialoffloorssuchasmortar,marble,ceramicandspecialfinishes
willbefromanapprovedsourceasperspecifications.
There shall be no stains or damage to the surfaces and exposed edges.
Materialwillbestoredatthefactoryoratsiteonwoodenplatformsoras
recommendedbythesupplier/manufacture.
Thefinishingmaterialonfloorswillbeapplied/erectedasperapproved
construction schedule, approved shop drawings, manufacturer
recommendationsandContractSpecifications.
WorkSequence:

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page27of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL

Before starting any floor finishing activity, all concrete works will be
checkedandapprovedbytheconsultantforembedded/concealeditems
likepipesorotherfixtures.
Flooring works shall start after heavy works are completed and ceiling
finishesareinthefinalstagestominimizetheuseofscaffoldsontopof
thefinishedfloors.

4.2.5 Metal Works


Allmetalitemssuchasrailingsandgratingswillbeobtained/fabricated
fromanapprovedfactory.
Allsteelfabricatedinthefactoryshallbepaintedandmarkedasrequired
inspecificationsandshallbedeliveredtomeettheapprovedconstruction
schedule.
Theerectionwillbeperformedmanuallyduetothelimitedweights.
Alldamagedareaswillbetouchedupasrequestedbytheconsultant.
AllactivitiesshallbeperformedasperContractSpecifications.
Wallmountedhandrailsshallbeinstalledoncewallsfinishingiscompleted
and/orthebasepaintcoatisapplied.
Floormounted handrails shall be installed once floors are finished and
protected.
Allrailingsshallbeproperlyprotectedtoavoidanydamage.
4.2.6 Roofing Works
Onceallheavyworksarecompletedontherooffloorandotherinsertsare
fixedinplace,theareawillbecleanedandroofingworkswillstart.
All roofing layers shall be as per approved shop drawings and contract
specifications.
After each layer is completed, it will be inspected/approved by the
consultantbeforeapplyingthenextlayer.
Afterroofworksarecompleted,rainwateroutletsandotherrooffixtures
shallbeerected.
Allworksshallbeasperapprovedconstructionschedule,approvedshop
drawingsandContractSpecifications.
4.2.7 Doors and Windows
All doors and windows will be supplied from an approved source and
manufacturedasperapprovedshopdrawingsandcontractspecifications.
Thedoors,framesandwindowswillbewrappedandprotectedwithplastic
andstoredinacoveredareaoncedeliveredtosite.
Asalldoorsandwindowsarefixedonframesandfinishedonbothsides,
theareaswillbecleanedfromallotheritems,sothatrooms/areascould
belockedforprotection.
All works shall be performed as per approved construction schedule,
approvedshopdrawingsandContractSpecifications.

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page28of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL


4.2.8 Glazed Aluminum Curtain Walls
Glazedaluminumcurtainwallswillbesuppliedfromanapprovedsourceand
manufacturedasperapprovedshopdrawingsandcontractspecifications.
Materialdeliverytositeshallbeinaccordancewiththeapprovedconstruction
schedule.
Thefollowinggeneralprocedureshallbefollowedforinstallationactivities:
o Embedmentclearancethesurfaceofembedmentshallbecleaned.All
fillingsintheslotsshallbeclearedoutcompletely.
o InstallBracketsSettingfirsttheironbrackets,thenthepadsandfinally
screwingthenutstightly.
o Bracketsadjustmentthedimensionaladjustmentforbracketsandthe
qualityofadjustedjointpiecesshallbeinspectedfromonelevelto
another.

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page29of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL

5 Resources
5.1 Equipment
EquipmentListedbelowarethemajorequipmenttypesthatwillbeusedduringtheexecutionof

theprojectwithinthesiteandassigneddurationsaccordingtotheapprovedconstruction.

TYPE OF EQUIPMENT

NO. REQUIRED

REMARKS
With concrete casting & Finishing items of
project buildings
With concrete casting & Finishing items of
project buildings
Till building weight equalizes uplift

Tower Cranes

as required

Mobile Crane

as required

Dewatering system

as required

Generator

as required

Trans Mixer

as required

Casting days

Conc. Pumps

Casting days

Excavator

as required
as required

Loader

as required

Excavation Period

Trucks

as required

Excavation Period

Welding machine

Metal fabrication -rebar work

Rebar Bender

as required
as required

Steel rebar & fabrication

Plate Compactor

as required

For soil compaction & grading

Water tanker

as required

Water supply

Electric Saw

as required

For formwork

Air compressor

as required

Cleaning before casting

Conc. Vibrators

as required

Casting days

Grinding Machine

as required

The numbers shall be assigned according to


the site requirements.

Threading Machine

as required

Test Pump for Pressure Tests

as required

Excavation when required

The numbers shall be assigned according to


the site requirements.
The numbers shall be assigned according to
the site requirements.

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page30of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL

5.2 Cranes

TowerandMobilecranesshallbearrangedtobeusedduringconstructionof
theworks.

TheTowerCraneswillbepermanentlyinHospitalMainBuilding,DentalClinic

RegionalHealthAdminandCentralUtilityBuildings

Mobilecranesshallbeindifferentcapacitiesandcoveragearea.Mobilecranes
shallbeselectedandallocatedaccordingtotheliftingcapacityofeachcrane
infullcoordinationwithactivitiesonsiterequirements.

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page31of32

DESIGN DEVELOPMENT, CONSTRUCTION, MEDICAL EQUIPMENT,


FURNISHING, AND OPERATIONAL MAINTENANCE OF

THE NEW JAHRA HOSPITAL

6 MAINTENANCE OF WORK

Operational, Preventive Maintenance, Running Maintenance and Guaranteed Maintenance of all the works
of the building, equipment and external works within the boundary of the Project Design Development,
Construction, Medical Equipment, Furniture and Operational Maintenance, Tested and Commissioned by
the Contractor as per the requirements of the Contract.
The Operational and Maintenance Duties/Works shall be carried out by the Contractor for 24 hours per
day; 7 days a week for a period of two years starting from the date/s the works are certified as substantially
complete comprising but not limited to the followings:
1. Administrative, logistical and supervisory requirements for coordinating activities during the said 2
years period.
2. Operational, Preventive Running and Guaranteed Maintenance as per the respective manufacturers
recommendation, including all materials, Tools and Selective Spare Parts (List approved by the
Engineer) required as per the respective manufacturers recommendation.
3. Operational Maintenance of Electrical systems shall be including but not limited to the followings: All
types of lighting, power, distribution network, electrical panels and switchboards, motor control centers,
lighting controls, cabling, raceways, conduits, ATS, emergency diesel generators, UPS, fire alarm
system, telecommunication system, IT and data transfer systems, video and audio-visual systems,
paging and public address systems central clock system, security control and monitoring system, nurse
call system and all other Low Voltage Electrical Equipment.
4. Operational Maintenance of the Mechanical systems shall be including but not limited to the
followings: HVAC systems including air handling units, chillers, pumps, cooling towers, fans, ducting,
dampers, air terminals, heaters, special laboratories exhaust, smoke exhaust and drainage system,
hydronic piping, valves, fittings and control devices, firefighting systems sprinklers, hose reel, FM 200
and foam systems, fire pumps etc, pneumatic piping system, complete plumbing systems including water
supply and drainage system, water heaters, pumps, water filters and treatment equipment, grease
interceptors, oil and sand separators, fuel oil piping, diesel exhaust and cooling systems, irrigation water
system, automatic control of all mechanical engineering services, cold rooms, DX units.
5. Operational Maintenance of the Special systems shall be including but not limited to the followings:
LPG system, Steam generation and distribution system, Compressed Air System, Medical Gas System
and Pneumatic System, Special HVAC system for labs, Clean and Environmental rooms etc. (if any)
6. Operational maintenance of Medical and Laboratory Equipment and other active components.
7. Operational Maintenance of Building Fabrics, Internal finishes, Doors and Windows, Furniture and
Furnishings, all Caseworks, Counters etc.
8. Operational Maintenance of all other systems shall be including but not limited to the followings:
Conveying system Passenger, Patient and Service Elevators, Escalators, Window Cleaning system,
Building Management System etc.
9. Carry out activities related to the performance of routine, preventive, predictive, scheduled actions
aimed at preventing equipment to prevent failure or decline in efficiency, reliability and safety of the
systems.
10. Provide spare parts as required under each section of the specifications. The Contractor may use the
spare parts during 2 year Operational Maintenance period but shall replenish with new one as soon as
possible. The Contractor may use the remaining Spare parts in the extended Operational Maintenance
period otherwise he shall hand over the spare parts as per list at the End of O & M period.

M.A.Kharafi&SonsCo.

General Construction Method Statement & Preliminary Master Construction Schedule

Page32of32