CRONOGRAMA FÍSICO FINANCEIRO - CONSTRUÇÃO

COD. DESCRIÇÃO UNID. ORÇAMENTO MÊS 1 MÊS 2 MÊS 3 MÊS 4 MÊS 5 MÊS 6 MÊS 7 MÊS 8 MÊS 9 MÊS 10 MÊS 11 MÊS 12

% 100% 100.00%
1 SERVIÇOS PRELIMINARES / MOVIMENTO DE TERRA
R$ 400 400.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
% 100% 50.00% 50.00%
2 INFRA ESTRUTURA
R$ 900 0.00 450.00 450.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
% 100% 40.00% 60.00%
3 SUPRA ESTRUTURA
R$ 1,900 0.00 0.00 760.00 1,140.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
% 100% 45.00% 45.00% 10.00%
4 ESTRUTURA METÁLICA
R$ 1,100 0.00 0.00 0.00 495.00 495.00 110.00 0.00 0.00 0.00 0.00 0.00 0.00
% 100% 30.00% 20.00% 15.00% 15.00% 10.00% 10.00%
5 ACABAMENTO
R$ 800 0.00 0.00 0.00 0.00 240.00 160.00 120.00 120.00 80.00 80.00 0.00 0.00
% 100% 10.00% 40.00% 20.00% 15.00% 10.00% 5.00%
6 INSTALAÇÕES
R$ 2,000 0.00 200.00 0.00 0.00 0.00 800.00 400.00 300.00 200.00 100.00 0.00 0.00
% 100% 70.00% 30.00%
7 LOGÍSTICA
R$ 1,200 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 840.00 360.00
% 100% 5.00% 55.00% 20.00% 20.00%
8 TI - INFORMÁTICA
R$ 500 0.00 25.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 275.00 100.00 100.00

ADMINISTRAÇÃO LOCAL, MOBILIZAÇÃO, % 100% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33% 8.33%
9
DESMOBILIZAÇÃO E APOIO TENOLÓGICO R$ 1,200 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00

MENSAL (%) 5.00% 7.75% 13.10% 17.35% 8.35% 11.70% 6.20% 5.20% 3.80% 5.55% 10.40% 5.60%

MENSAL (R$) 500 775 1,310 1,735 835 1,170 620 520 380 555 1,040 560
TOTAL (X 1.000)
ACUMULADO (%) 5.00% 12.75% 25.85% 43.20% 51.55% 63.25% 69.45% 74.65% 78.45% 84.00% 94.40% 100.00%

ACUMULADO (R$) 500 1,275 2,585 4,320 5,155 6,325 6,945 7,465 7,845 8,400 9,440 10,000

31935776.xls - Cronograma Físico Financeiro - 11/04/2021 Página 1 de 2


Orçamento - Construção Armazem "Built-to-Suit"
11,000

10,000

9,000

8,000

7,000

R$
x 1000
6,000

5,000

4,000

3,000

2,000

1,000

0