Escolar Documentos
Profissional Documentos
Cultura Documentos
7.
HIGH
VOLTAGE
INSTALLATIONS
7.1 General
Ensure that all connections to live voltages are
isolated and earthed before starting any tasks
concerning
equipment
with
dangerous
voltages.
7.2 Earthings
Protective earthing demands good binding frame
connections between the swichyard and to the
power plant grounding grid. HV cable sheaths and
25
The same or a separate distribution provides the
spring charging voltage for the HV breakers and a
third distribution may be used for powering
interlocking-freeing coils for the earthing switches.
Voltage and polarity should be checked for each
circuit. Spring charging functions should be
observed and checked for reliability (similar
charging speed for each breaker). Check that the
voltage of the circuit powering the breaker spring
charge does not drop below accepted limits or trip
the supply even when several breakers are
charged simultaneously if this is possible in normal
operation.
7.5 Controls
Check every tripping, closing, interlocking and
indicating function for full functionality. Trip signals
should be generated using a relay tester when
performing the protective relay tests, transformer
trips by pumping the Bucholz-relay etc. Check that
each protective device also releases the HV-load
breaker in addition to raising the signal. Check
close and trip commands for local controls as well
as for main/distributed control panel and control
system command functionality including necessary
interlockings. Where controlling devices cannot yet
be tested, the commands should be recorded for
later testing when that device or system is tested.
A preliminary test of a command signal circuit by
simulating commands from device connections
confirms the circuit but does not clear the test.
Closed / open indications should be tested using
the breakers in actual positions. Check that
indications correctly indicate at every location (local
indication, in central control desk/panel, on screen,
remote indication and on event report printer).
Checks for circuit breakers are:
-
7.6 Alarms
The alarms for following should be checked:
-Outgoing line bays, MW, MVAr, cos phi
-Breaker open, closed, tripped
-Earthing switch open, closed
-Earth-fault relay operated
-Overcurrent relay operated
-Diffrential protection relay operated
-Distance relay operated
-Gas relay alarm and trip
-etc.
Allmost all these are PLC based alarms.
26
7.8 Completing tests
The auxiliary and control voltage distribution is
connected for all activated equipment. The SF6filled breakers are checked for sufficient gas
pressures. No alarm signals are active. All lids and
cover sheets are closed and earthing isolators on
outgoing connections are not yet closed.
Finally the insulation test is performed for busbars
and the connected feeder line as described in the
chapter Insulation Tests. Any voltage transformers
connected directly to the busbars will have to be
disconnected for this test and reconnected after
the test voltage has been discharged. It is
recommended to move as many of the circuit
breakers as possible to normal operating positions
for them to be included with this test. These
breakers must be open and all phases of
connected outgoing cables must be earthed to
prevent distribution of leaking test voltages. The