Você está na página 1de 2

Inspection Test Record

M08A Pedestal Crane


SOUTH ACIS

Client: Murphy Sarawak Oil Ltd.

Date: 21-Feb-2013

TagNo:

Description:

System:

Sub System:

SubSubSystem:

Package:

Area:

Location:

Drawing Ref No:


Manufacturer:
SerialNo:
Item

Model:

Description
Check vendors instruction, dossier, associated equipment catalogue and test certificate
01
are provided.
02
Nameplate is provided and details are correct in accordance with the data sheet.
03
Check equipment for any damage or sign of lack of preservation.
Equipment is installed according to installation drawing and manufacturer's instructions
04
and specification.
05
All access ladders and platforms are secure
06
All equipment removed for transportation has been refitted
Check A frame, boom chord and lacing members for any distortion and physical
07
damage.
08
Boom assembly bolting is correct to spec.
09
Boom pivot flange bolting correct to spec.
10
Check and grease pivot joints of boom.
Check the following at cab :
1. Cab windows and wipers.
2. Cab door are acceptable and free from any damages.
3. Load/radius charts are provided.
11
4. Load and radius indicators are provided.
5. Alarm horn is provided.
6. Air conditioning is working and in good condition.
12
Upper flange face of pedestal is flat and level for slew ring installation
Witness and record tightening of slew ring bolts and ensure that they are tightened to
13
correct torque. *W*
Torque value:
Check slew gear is free of grid or foreign particles and ensure proper greasing of slew
14
gear and turn table bearing.
15
Check that the hydraulic system is correct to drawing and specification
16
Check aligment of hydraulic pump and driver.
Check hydraulic tank for cleanliness, the filling arrangement, strainer, sigh glass and
17
drain valve.
18
Check hydraulic hose connections and hoses are neatly dressed.
Check that all lubricant/hydraulic oil and coolant are filled to the correct level and
19
specification.
Check crankcase lube oil for contamination. *W*
20
Grade of lube oil / Quantity:
Confirm that all hydraulic accumulators have been pre-charged to vendors
21
recommended pre-charge pressure
Confirm that all pulsation dampers have been pre-charged to vendors recommended pre
22
-charge pressure
All ropes are greased and reeved correctly and the manufacturer's certificates are
23
available, seen and filed. *W*
Check that wire rope is wound properly on drum and rope end anchorage is done
24
properly.
25
Ensure that brake band adjustment is checked according to vendors instruction.
26
Manufacturer's certificates for the hook and all sheaves are available, seen and filed
Fit sign on diesel tank manway stating Manway must not be closed until completion of
27
Pedestal Crane loadCompleted
test and subsequent
NDT of pedestal
By Construction
Certified By QA/QC
Confirm that tag numbers have been allocated to all PSVs in the pneumatic and hydraulic
28
Signature:
systems, and their certification is up to date.
29
Confirm boom rest construction is complete
Print Name:
30
Confirm earth bonding completed.
31 ofVerify
that electrical check on motor, cabling and Motor Control Center are completed.
Date
Signing:
All installation checks have been completed in accordance with vendors installation
32 by: Soh, Gerald. 21-Feb-2013 16:36, (ID=28922).
Printed
check sheet

Type:
NA

OK

PL

Output /Remarks

Accepted By BDEWC COMM.

16

Check aligment of hydraulic pump and driver.


Check hydraulic tank for cleanliness, the filling arrangement, strainer, sigh glass and
17
drain valve.
Inspection
Test Record
18
Check hydraulic hose connections and hoses are neatly dressed.
M08A
Pedestal
Crane
Check
that all lubricant/hydraulic
oil and coolant are filled to the correct level and
19
specification.
SOUTH ACIS
Check crankcase lube oil for contamination. *W*
20
Grade of lube oil / Quantity:
Confirm that all hydraulic accumulators have been pre-charged to vendors
21
recommended pre-charge pressure
Client:
Sarawak
Oil Ltd.
Date: 21-Feb-2013
Confirm
thatMurphy
all pulsation
dampers
have been pre-charged to vendors recommended
pre
22
-charge
pressure
TagNo:
Description:
All ropes are greased and reeved correctly and the manufacturer's certificates are
23
System: seen and filed. *W*
Sub System:
available,
Check that wire rope is wound properly on drum and rope end anchoragePackage:
is done
SubSubSystem:
24
properly.
Area:
Location:
25
Ensure that brake band adjustment is checked according to vendors instruction.
Drawing
Ref No:
26
Manufacturer's
certificates for the hook and all sheaves are available, seen and filed
Fit sign on diesel tank manway stating Manway must not be closed until completion of
27
Pedestal Crane load test and subsequent NDT of pedestal
Confirm that tag numbers have been allocated to all PSVs in the pneumatic and hydraulic
28
systems, and their certification is up to date.
29
Confirm boom rest construction is complete
30
Confirm earth bonding completed.
31
Verify that electrical check on motor, cabling and Motor Control Center are completed.
All installation checks have been completed in accordance with vendors installation
32
check sheet
Note:
*W* MOC rep. Witness points
___________________________________________________________________________________________________________________
Remarks:

Completed By Construction
Signature:
Print Name:
Date of Signing:
Printed by: Soh, Gerald. 21-Feb-2013 16:36, (ID=28922).

Certified By QA/QC

Accepted By BDEWC COMM.