Escolar Documentos
Profissional Documentos
Cultura Documentos
CHAPTER 3
PROJECT CONTROL AND MONITORING
INTRODUCTION
Mrs. Maria, your blood pressure is quite high. But. dont
worry, I will ask my assistant to monitor the pressure hourly.
And please take medicine that will given to you shortly to control
your pressure. Said Dr Allan to Mrs. Maria.
INTRODUCTION
Monitoring and controlling processes are very important
in our life. Monitoring involves determining what
information to collect; how, when and who will collect
the information; analysis of the info; and reporting
current progress.
Scheduling Techniques
Planning, Scheduling
And controlling Techniques
Bar
Charts
Linear Balance
Method
Progress Curve or
S-Curves
Matrix
Schedules
Critical Path
Method (CPM)
14
15
June
% Complete 1 2
3
100% 100%
100%
100%
July
5 6
August
September
October
Nov ember
December
January
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
ID
1
Task Name
Site posession
Setting Out
Excav ate
100%
Pad F ooting
100%
Column Stump
100%
Ground Beam
100%
100%
100%
10
100%
11
100%
100%
12
Roof Beam
70%
70%
13
40%
14
60%
15
0%
16
0%
17
0%
18
0%
19
0%
20
21
22
Site C learing
0%
23
0%
24
Ramp
25
Earthworks
26
65%
27
95%
28
70%
29
0%
30
20%
31
Fire protection
0%
32
Air conditioner
0%
33
0%
100%
100%
100%
100%
100%
0%
100%
100%
0%
30%
0%
100%
100%
65%
95%
0%
20%
Bar Charts
ADVANTAGES
- Simple graphical
- Easy for general
comprehension
- Wide spread used in industry
- Mostly used in small project
- Fairly broad planning and
scheduling tools, so they
require less revision and
updating than more
sophisticated systems
DISADVANTAGES
- Very cumbersome as the number
of line activities, or bars
increases
- Logical interconnections and
constraints of the various
activities is not expressed
- Difficult to use it for
forecasting the effects that
changes in a particular
activity will have on the
overall schedule
10
17
It is very difficult to find out the alternative courses of action they might be taken
and effect of each on project completion is exercised in case of variation of the
construction programme from the planned programme. The length and position
can not be adjusted.
18
NO.
MONTH
DESCRIPTION
1
1
2
3
4
5
6
7
8
9
10
11
12
Mobilization
Foundation Excavation
Diversion Stage
Foundation Grouting
Dam Concrete
Install Outlet Gates
Install Trash Racks
Prestress
Radial Gates
Spillway Bridge
Curtain Grout
Dismantle Plant, Clean Up
10
Original Schedule
Actual
progress
13
Bar Charts
Example 3.1
A project consist of six activities that should be done in a period of time. Try to create a bar
chart to ease the project planning and scheduling.
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
Bar Chart
STEP 1: Identify start date & finish date for all activities
Activity
A: 1 week, starting from 1 Oct 2013
B: 2 week, starting from 5 Oct 2013
C: 3 week, starting from 15 Oct 2013
D: 2 week, starting from 25 Oct 2013
E: 2 week, starting from 29 Oct 2013
F: 1 week, starting from 5 Nov 2013
(1/10/13 - 8/10/13)
(5/10/13 - 19/10/13)
(15/10/13 - 5/11/13)
(25/10/13 - 8/11/13)
(29/10/13 - 12/11/13)
(5/11/13 - 12/11/13)
21
Bar Chart
STEP 2: Draw outline of Bar Chart
Bar Chart for Example 1
No1/10
8/10
15/10
Activity
22/10
29/10
5/11
Duration
Week
1
1/10
1
8/10
15/10
22/10
29/10
5/11
12/11
22
Bar Chart
A:(1/10/13 - 8/10/13)
B:(5/10/13 - 19/10/13)
C:(15/10/13 - 5/11/13)
D:(25/10/13 - 8/11/13)
E:(29/10/13 - 12/11/13)
F: (5/11/13 - 12/11/13)
8/10
15/10
22/10
29/10
5/11
Week
No
Activity
Duration
1
1/10
2
8/10
3
15/10
4
22/10
5
29/10
6
5/11
12/11
23
Activity
Duration
(week)
01 October 2013
H, I
08 October 2013
10 October 2013
15
22 October 2013
05 November 2013
Starting
date
Human
Resources
(people)
Successor
18
Activity
Duration
Starting
Human Resources
(Week)
Date
(People)
Successor
01 October 2013
H, I
08 October 2013
10 October 2013
15
22 October 2013
05 November 2013
G:(1/10/13 - 8/10/13)
H:(8/10/13 - 22/10/13)
I:(10/10/13 - 31/10/13)
J:(22/10/13 - 5/11/13)
K:(5/11/13 - 12/11/13)
25
Activity
Duration
(week)
Human Resources
(people)
15
1/10
8/10
3
15/10
22/10
29/10
5/11
12/11
26
Activity
Duration
(week)
Human Resources
(people)
15
1
1/10
2
8/10
15/10
22/10
6
29/10
5/11
12/11
27
Activity
Duration
(week)
Human Resources
(people)
15
1/10
8/10
3
15/10
22/10
29/10
5/11
12/11
28
Activity
Duration
(week)
Human Resources
(people)
15
G:(1/10/13 - 8/10/13)
H:(8/10/13 - 22/10/13)
I:(10/10/13 - 31/10/13)
J:(22/10/13 - 5/11/13)
K:(5/11/13 - 12/11/13)
1
1/10
2
5
8/10
3
15/10
4
22/10
5
29/10
6
5/11
12/11
29
Activity
Duration
(week)
Human Resources
(people)
15
G:(1/10/13 - 8/10/13)
H:(8/10/13 - 22/10/13)
I:(10/10/13 - 31/10/13)
J:(22/10/13 - 5/11/13)
K:(5/11/13 - 12/11/13)
1/10
8/10
3
15/10
22/10
29/10
5/11
12/11
30
Week
No
Activity
Duration
(week)
Human Resources
(people)
11/10
28/10
3
15/10
4
22/10
29/10
5
65/11
12/11
5
1
15
G:(1/10/13 - 8/10/13)
H:(8/10/13 - 22/10/13)
I:(10/10/13 - 31/10/13)
J:(22/10/13 - 5/11/13)
K:(5/11/13 - 12/11/13)
31
Week
No
Activity
Duration
(week)
Human Resources
(people)
15
G:(1/10/13 - 8/10/13)
H:(8/10/13 - 22/10/13)
I:(10/10/13 - 31/10/13)
J:(22/10/13 - 5/11/13)
K:(5/11/13 - 12/11/13)
1
1/10
2
5
8/10
15/10
22/10
29/10
5/11
12/11
4
4
5
2
1
2
3
32
Week
No
Activity
Duration
(week)
Human Resources
(people)
15
1
1/10
2
5
8/10
15/10
22/10
29/10
5/11
12/11
4
4
5
2
2
3
33
Week
No
Activity
Duration
(week)
Human Resources
(people)
1/10
8/10
3
15/10
22/10
29/10
5/11
12/11
15
4
4
1
2
Resources
(People)
10
5
0
Duration (week)
Progress Curves
Table 4.2 Combination between S-Curves and Bar Charts
Month
Description
1
Mobilization
Foundation Excavation
Diversion Stage
Foundation Grouting
Dam Concrete
Prestress
Radial Gates
10
Spillway Bridge
11
Curtain Grout
12
10
100
Original Schedule
No.
Actual progress
0
29
Progress Curves
Step by step to make s-curve
- Calculate cost for each activity
- Calculate total cost for all activity
- Calculate the progress ratio between cost for each
activity and total cost
- Divide those progress ratio equally for each activity
according to its duration
- Add the progress ratio which already divided for each
unit of time
- Calculate the cumulative progress ratio
- Draw S-Curve as a relationship between cumulative
progress ratio and duration of a project
Figure 4.4 Step by Step to Make Progress or S-Curve
30
Progress Curves
Example 3.3
As a bar chart is created in Example 3.1, try to draw a
progress or S-Curve of the project with additional data as
follow :
WORK
PROGRESS
RATIO (%)
No
ACTIVITY
DURATION
(WEEK)
COST
(RM)
A
B
C
D
E
F
1
2
3
2
2
1
1600
2000
6000
4900
3600
2000
8
10
30
24
18
10
20000
100%
2
3
4
5
6
TOTAL
31
Progress Curves
Table 4.3 Progress or S-Curve
activity
duration
(week)
progress
ratio
(%)
10
30
24
18
10
week
1
1/10
2
8/10
3
15/10
5
29/10
22/10
6
5/11
100
8
2.1
2.9
10
10
10
6.9
12
9
50
5.1
9
10
10.1
12.9
16.9
31
24.1
10.1
15.1
28
44.9
75.9
100
32
No
33
NETWORKING TECHNIQUE
Activity on Arrow - ARROW DIAGRAM
Activity on Node
- PRECEDENCE DIAGRAM
Fabricate Rebar
Fixed
Rebar
Excavate
Trench
Fabricate
formwork
Fixed
Formwork
Pour
Concrete
Excavate
Trench
Fabricate
formwork
Fixed
Formwork
Fixed
Rebar
Pour
Concrete
DISADVANTAGES
TYPES OF CPM
- Arrow Diagram Method (ADM)
- Precedence Diagram Method
(PDM)
37
Item
ADM (AOA)
PDM (AON)
ES
EF
D
A
LS
TF
LF
Activity
ES: Early Start LS: Late Start
EF: Early Finish LF: Late Finish
D : Duration
TF: Total Float
ES
Event
LS
EF
A
2
ES
EF
ES
A
LF
LS
TF
EF
B
LF
LS
TF
LF
40
Item
ADM
PDM
Definition
Dummy
Activity
Function
If there is a situation where one
D
or
41
Item
ADM
False
True
Dummy
Activity
D
or
A
42
Item
ADM
PDM
F-S
FS
FF
SS
S-F
Relationship
Critical Path
: A path consist of few activities which will determine the overall project
duration.
Critical path
1.
2.
3.
Es = Ef, or
Ls = Lf, or
Total Float (TF) = 0
Item
ADM
PDM
- Total float
Total float
: The maximum amount of time that the activity can be delayed without
extending the completion time of the overall project.
Estimating
duration
: To establish the earliest expected start and finish times for each
activity in the network. (ES n EF)
- BACKWARD PASS select small number (duration)
: To establish the latest allowable start and finish times for each activity
in the network. (LS n LF)
45
Forward pass
a
b
A
X
backward pass
c
2 d
B
3
Y
e
f
a
b
c
d
e
d
X
Y
:
:
:
:
:
:
:
:
forward pass
Backward pass
a = 0
c = a + X
e = c + Y
f = e
d = f Y
b = d - X
Figure 4.6 Estimating Project Duration using Arrow Diagram Method (ADM)
46
A
B
C
D
E
F
G
H
Event
1-2
2-3
2-4
3-5
4-6
5-7
6-7
7-8
Successor
Duration
(week)
B, C
D
E
F
G
H
H
-
2
3
2
4
3
2
3
1
47
3
B
9
9
2
3
0
1
0
2
2
11
11
12
8
4
4
5
E
3
7
8
12
Event
Activity
Duration
ES
LS
EF
LF
Total Float
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8) = 7-3-4
1-2
2-3
2-4
3-5
4-6
5-7
6-7
7-8
A
B
C
D
E
F
G
H
2
3
2
4
3
2
3
1
0
2
2
5
4
9
7
11
0
2
2
5
5
9
8
11
2
5
4
9
7
11
11
12
2
5
5
9
8
11
11
12
0*
0*
1
0*
1
0*
1
0*
Critical Path : A B D F H
49
No
week
Activity
1
3
4
C
D
10
11
50
12
EVENT
DURATION
(DAY)
PREDECESSOR
START
1-2
START
1-3
START
1-4
START
2-7
3-6
F (DUMMY)
4-6
4-5
7-8
7-9
6-9
E,F
5-9
9-10
I,J,K
8-10
FINISH
M,L
B
5
J
5
C
4
F
K
4
4
G
7
10
2
7
18
M
13
12
11
E
6
C
4
J
10
9
15
L
15
10
20
F
K
4
4
4
G
4
5
11
11
Total Project Duration = 20 weeks
Critical Path = C-G-K-L
20
ACTIVITY
EVENT
DURATION
ES
LS
EF
LF
FF
TF
START
1-2
1-3
1-4
2-7
11
12
3-6
10
F (DUMMY)
4-6
4-5
11
11
7-8
11
12
13
18
7-9
11
12
15
15
6-9
10
15
15
5-9
11
11
15
15
9-10
15
15
20
20
8-10
13
18
20
20
FINISH
54
Activity
DURATION (DAY)
Total
Float
10
11
12
10
11
12
13
14
15
16
17
18
19
20
55
Event
Predecessor
Duration
(week)
A
B
C
D
E
F
1-2
1-3
1-4
2-5
3-6
4-7
5-6
5-8
6-7
6-9
A
B
C
D
D, E
2
1
3
1
3
2
4
1
7-10
D, E, F
8-11
9-11
10-11
DUMMY
G
DUMMY
56
7
9
J
10
11
3
C
4
3
3
F
7
2
7
10
10
Activity
Duration
ES
LS
EF
LF
Total Float
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8) = 7-4-3
1-2
1-3
1-4
2-5
3-6
4-7
5-8
6-9
7-10
8-11
A
B
C
D
E
F
G
H
I
J
2
1
3
1
3
2
4
1
3
3
0
0
0
2
1
3
3
4
5
7
0
0
0
4
2
3
5
5
5
9
2
1
3
3
4
5
7
5
7
10
4
2
3
5
5
5
9
8
7
10
2
1
0*
2
1
0*
2
3
0*
0*
9-11
10-11
K
L
2
3
5
7
8
7
10
10
10
10
3
0*
58
1
2
3
4
5
6
7
8
9
10
11
12
Activity
A
B
C
D
E
F
G
H
I
J
K
L
Total
Float
week
1
2
1
0
2
1
0
2
3
0
2
3
0
10
59
A-B (F-S)
A-C (S-S)
LA-B
A
b
B
f
F-S
ESA
EFA
=a+X
ESB
= c + LA-B
EFB
=e+Y
ESC
= a + LA-C
EFC
=i+Z
LA-C
S-S
C
j
LFB
=g
LSB
=h-Y
LFA
= f - LA-B
LSA
=d-X
LFC
=k
LSC
=l-Z
= j - LA-C
A
b
LA-C
S-F
C
j
A-C (S-F)
A-B (F-F)
B
d
item
LA-B
l
F-F
ESA
EFA
=a+X
ESB
EFB
=e+Y
EFC
= a + LA-C
= g + LA-B
ESC
=kZ
=kZ
=k
LSC
=l-Z
LSA
= l - LA-C
LFA
=b+X
LFB
= l - LA-B
LSB
=h-Y
61
Activity
duration
successor
relationship
(week)
Lag (l)
(week)
B,D
A-B (F-S)
A-D (S-S)
0
1
B-C (F-S)
D-E (F-S)
E-C (F-S)
L=0
A
0
L=1
B
2
C
4
L=0
1
L=0
L=1
D
3
Note
Total Float (TF):
TF
Critical Path :
63
No
week
Activity
1
3
4
C
D
L=1
L=1
64
ACTIVITY
DURATION
(WEEKS)
SUCCESSOR
B, C, D, E
C, H
F, G
D, K
I, J
H, M
M, K
10
L, O, P, N
NIL
65
Total 3Project
Period
: 51 weeks
Chapter
- Project
Planning,
Scheduling and Controlling
Critical path : A-E-D-G-J-J-K-N-P-Q
66
Scheduling Technique
Line of Balance
Piling
Pile-cap
Piers
Deck
Quantity
20
Time
34
LINE OF BALANCE
CONCEPT OF CONTROLING
Project Controls can be defined as
Management action, either preplanned to achieve the desired
result or taken as a corrective measure prompted by the
monitoring process. Project controls is mainly concerned with
the metrics of the project, such as quantities, time, cost, and
other resources; however, also project revenues and cash flow
can be part of the project metrics under control. Thus, we
believe an effective Project Controls process can be applied in a
collaboration of its various sub-disciplines, such as:
69
CONCEPT OF CONTROLING
1) Planning, Scheduling & Project Reporting
Scope management;
Project deliverables:
Schedule management;
Schedule forecasting;
Corrective action;
70
CONCEPT OF CONTROLING
3) Cost Engineering & Estimating
Estimating;
Cost management;
Cost control;
Cost forecasting
4) Change Management & Controls
Trend Analysis;
5) Risk and Delay Claims
71
72
Quality management has equal priority with cost and schedule management.
However, the direct measurement of quality may be the responsibility of the
quality assurance department or the assistant project manager for quality.
73
74
75
Quality assurance is the collective term for the formal activities and managerial processes that
attempt to ensure that products and services meet the required quality level. Quality assurance also
includes efforts external to these processes that provide information for improving the internal
processes. It is the quality assurance function that attempts to ensure that the project scope, cost,
and time functions are fully integrated.
The Project Management Institute Guide to the Body of Knowledge (PMBOK) refers to quality
assurance as the management section of quality management. This is the area where the project
manager can have the greatest impact on the quality of his project. The project manager needs to
establish the administrative processes and procedures necessary to ensure and, often, prove that
the scope statement conforms to the actual requirements of the customer. The project manager
must work with his team to determine which processes they will use to ensure that all stakeholders
have confidence that the quality activities will be properly performed. All relevant legal and
regulatory requirements must also be met.
76
77
78