Você está na página 1de 78

CC603: PROJECT MANAGEMENT

CHAPTER 3
PROJECT CONTROL AND MONITORING

Chapter 3 - Project Planning, Scheduling and Controlling

INTRODUCTION
Mrs. Maria, your blood pressure is quite high. But. dont
worry, I will ask my assistant to monitor the pressure hourly.
And please take medicine that will given to you shortly to control
your pressure. Said Dr Allan to Mrs. Maria.

INTRODUCTION
Monitoring and controlling processes are very important
in our life. Monitoring involves determining what
information to collect; how, when and who will collect
the information; analysis of the info; and reporting
current progress.

However controlling in terms of a project is a process of

comparing the actual performance with baseline


performance and discerning any deviation. The project
management team then deals with this deviation, analyses
it, and suggests solutions to bring the schedule back on
track, if possible. In simple words, it measures and
evaluates the progress and performance of a project.
4

Project Planning and Controlling


Objectives
To arrange the activities appropriately
To make a realistic time scheduling

To make a resources estimation and planning


To implement time and cost controlling
To ease the contract administration

Scheduling Techniques
Planning, Scheduling
And controlling Techniques

Bar
Charts

Linear Balance
Method

Progress Curve or
S-Curves

Matrix
Schedules

Critical Path
Method (CPM)

Figure 4.2 Techniques of Project Planning, Scheduling and Controlling

Project Scheduling Techniques


By charts
Gantt chart or bar chart.
Linked bar chart/ Modified Bar Chart

By net work Techniques


A-O-A (Activity on arrow)
o C.P.M (Critical path method)
o P.E.R.T (Programme evaluation Review Techniques)

A-O-N (Activity on node)


o P.D.M (Precedence Diagramming method)

L.B.S (Line of balance system)

14

Gantt Chart or Bar Chart


Bar Chart was developed by Henry Gantt in 1917
It is a graphical representation of work activities
Acts as planning-scheduling model and reporting-control model
The length of bar represents duration of activity

15

June
% Complete 1 2
3
100% 100%
100%
100%

July
5 6

August
September
October
Nov ember
December
January
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

ID
1

Task Name
Site posession

Setting Out

Excav ate

100%

Pad F ooting

100%

Column Stump

100%

Ground Beam

100%

Grd. Flr. Slab & D ocking Yard

100%

Apron Slab & Sub Soil & Parameter Drain

Grd. Flr. Column

100%

10

1st. F lr. Beam & Slab & Staggered Floor

100%

11

1st. F loor Column

100%

100%

12

Roof Beam

70%

70%

13

Roof Structure & C ov ering

40%

14

Ext. Wall & Int. Wall

60%

15

Door & Window & Glass

0%

16

Int. Wall & Ceiling Finishes

0%

17

Int. Flr. Finishes & Hand R ailing

0%

18

Ext. Wall & Ceiling Finishes

0%

19

Ext. Floor Finishes

0%

20

Plumbing & Sanitary Installation

21

Road & Carpark & Kerb

22

Site C learing

0%

23

Turf ing & Landscaping

0%

24

Ramp

25

Earthworks

26

Rubbish Bin Center & Pump House & Toilet

65%

27

Soil D rainage & Sewerage

95%

28

Surf ace Water Drainage

70%

29

Ext. Water R eticulation

0%

30

Electrical & Telephone

20%

31

Fire protection

0%

32

Air conditioner

0%

33

Handing Ov er - Practical C ompletion

0%

100%
100%
100%
100%
100%

0%
100%
100%

0%
30%

0%
100%

100%
65%
95%
0%

20%

Bar Charts
ADVANTAGES
- Simple graphical
- Easy for general
comprehension
- Wide spread used in industry
- Mostly used in small project
- Fairly broad planning and
scheduling tools, so they
require less revision and
updating than more
sophisticated systems

DISADVANTAGES
- Very cumbersome as the number
of line activities, or bars
increases
- Logical interconnections and
constraints of the various
activities is not expressed
- Difficult to use it for
forecasting the effects that
changes in a particular
activity will have on the
overall schedule

Figure 4.3 Techniques of Project Planning, Scheduling and Controlling

10

Advantages Gantt Chart or Bar Chart


Ability to clearly and quickly present the states of project.
To convey often to upper management, the over all status of a project.
No extensive training is required to learn how to extract in formation from them.
The period required for execution of each activity or operation can be observed.
Up date progress of each activity.
Resource aggregation.
Lagging of activities can be noticed to manage work.

17

Limitation/ Disadvantages Gantt Chart or


Bar Chart
Complicated inter- dependencies of various item of work can not be depicted
The critical activities can not be shown by bar charts.
Bars on chart do not show the actual progress because these only represent the
time elapsed in a particular activity. Hence it is not possible to detect till the
allotted is over and work remains in complete as the rate of progress is not shown
separately.

It is very difficult to find out the alternative courses of action they might be taken
and effect of each on project completion is exercised in case of variation of the
construction programme from the planned programme. The length and position
can not be adjusted.
18

Sample of Bar Charts


Table 4.1 Bar Chart for Concrete Gravity-Arch Dam

NO.

MONTH

DESCRIPTION
1

1
2
3
4
5
6
7
8
9
10
11
12

Mobilization
Foundation Excavation
Diversion Stage
Foundation Grouting
Dam Concrete
Install Outlet Gates
Install Trash Racks
Prestress
Radial Gates
Spillway Bridge
Curtain Grout
Dismantle Plant, Clean Up

10

Original Schedule

Actual
progress

13

Bar Charts
Example 3.1
A project consist of six activities that should be done in a period of time. Try to create a bar
chart to ease the project planning and scheduling.

Activity A

: 1 week, starting from 1 Oct 2013

Activity B

: 2 week, starting from 5 Oct 2013

Activity C

: 3 week, starting from 15 Oct 2013

Activity D

: 2 week, starting from 25 Oct 2013

Activity E

: 2 week, starting from 29 Oct 2013

Activity F

: 1 week, starting from 5 Nov 2013


14

Bar Chart

STEP 1: Identify start date & finish date for all activities
Activity
A: 1 week, starting from 1 Oct 2013
B: 2 week, starting from 5 Oct 2013
C: 3 week, starting from 15 Oct 2013
D: 2 week, starting from 25 Oct 2013
E: 2 week, starting from 29 Oct 2013
F: 1 week, starting from 5 Nov 2013

(1/10/13 - 8/10/13)
(5/10/13 - 19/10/13)
(15/10/13 - 5/11/13)
(25/10/13 - 8/11/13)
(29/10/13 - 12/11/13)
(5/11/13 - 12/11/13)

21

Bar Chart
STEP 2: Draw outline of Bar Chart
Bar Chart for Example 1
No1/10

8/10

15/10
Activity

22/10

29/10

5/11

Duration

Week
1

1/10
1

8/10

15/10

22/10

29/10

5/11

12/11

22

Bar Chart
A:(1/10/13 - 8/10/13)
B:(5/10/13 - 19/10/13)
C:(15/10/13 - 5/11/13)
D:(25/10/13 - 8/11/13)
E:(29/10/13 - 12/11/13)
F: (5/11/13 - 12/11/13)

STEP 3: Insert activity bars


Bar Chart for Example 1
1/10

8/10

15/10

22/10

29/10

5/11

Week

No

Activity

Duration
1
1/10

2
8/10

3
15/10

4
22/10

5
29/10

6
5/11

12/11

23

Modified Bar Charts


Example 3.2
Data of a project consist of four activities with their
duration and also amount of amount needed for this project.
Create a modified bar chart according to the data above.
No

Activity

Duration
(week)

01 October 2013

H, I

08 October 2013

10 October 2013

15

22 October 2013

05 November 2013

Starting
date

Human
Resources
(people)

Successor

18

MODIFIED BAR CHART


Step 1: Identify start & finish date for all activities
No

Activity

Duration

Starting

Human Resources

(Week)

Date

(People)

Successor

01 October 2013

H, I

08 October 2013

10 October 2013

15

22 October 2013

05 November 2013

G:(1/10/13 - 8/10/13)
H:(8/10/13 - 22/10/13)
I:(10/10/13 - 31/10/13)
J:(22/10/13 - 5/11/13)
K:(5/11/13 - 12/11/13)

25

MODIFIED BAR CHART


Step 2: Draw outline of Bar Char
Week
No

Activity

Duration
(week)

Human Resources
(people)

15

1/10

8/10

3
15/10

22/10

29/10

5/11

12/11

26

MODIFIED BAR CHART


Step 3: Insert activity bars
Modified Bar Chart for Example 2
Week
No

Activity

Duration
(week)

Human Resources
(people)

15

1
1/10

2
8/10

15/10

22/10

6
29/10

5/11

12/11

27

Modified Bar Chart


Step 4: Insert the relationship of all activities
Modified Bar Chart for Example 2
Week
No

Activity

Duration
(week)

Human Resources
(people)

15

1/10

8/10

3
15/10

22/10

29/10

5/11

12/11

28

Modified Bar Chart


Step 5: Calculate human resources for each week
Modified Bar Chart for Example 2
Week
No

Activity

Duration
(week)

Human Resources
(people)

15

G:(1/10/13 - 8/10/13)
H:(8/10/13 - 22/10/13)
I:(10/10/13 - 31/10/13)
J:(22/10/13 - 5/11/13)
K:(5/11/13 - 12/11/13)

1
1/10

2
5

8/10

3
15/10

4
22/10

5
29/10

6
5/11

12/11

29

Modified Bar Chart


Step 5: Calculate human resources for each week
Modified Bar Chart for Example 2
Week
No

Activity

Duration
(week)

Human Resources
(people)

15

G:(1/10/13 - 8/10/13)
H:(8/10/13 - 22/10/13)
I:(10/10/13 - 31/10/13)
J:(22/10/13 - 5/11/13)
K:(5/11/13 - 12/11/13)

1/10

8/10

3
15/10

22/10

29/10

5/11

12/11

30

Modified Bar Chart


Step 5: Calculate human resources for each week
Modified Bar Chart for Example 2

Week
No

Activity

Duration
(week)

Human Resources
(people)

11/10

28/10

3
15/10

4
22/10

29/10
5

65/11

12/11

5
1

15

G:(1/10/13 - 8/10/13)
H:(8/10/13 - 22/10/13)
I:(10/10/13 - 31/10/13)
J:(22/10/13 - 5/11/13)
K:(5/11/13 - 12/11/13)

31

Modified Bar Chart


Step 5: Calculate human resources for each week
Modified Bar Chart for Example 2

Week
No

Activity

Duration
(week)

Human Resources
(people)

15

G:(1/10/13 - 8/10/13)
H:(8/10/13 - 22/10/13)
I:(10/10/13 - 31/10/13)
J:(22/10/13 - 5/11/13)
K:(5/11/13 - 12/11/13)

1
1/10

2
5

8/10

15/10

22/10

29/10

5/11

12/11

4
4

5
2

1
2
3

32

Modified Bar Chart


Step 6: Calculate total amount of human resources for each week
Modified Bar Chart for Example 2

Week
No

Activity

Duration
(week)

Human Resources
(people)

15

TOTAL HUMAN RESOURCES

1
1/10

2
5

8/10

15/10

22/10

29/10

5/11

12/11

4
4

5
2

2
3

33

Modified Bar Chart


Step 7: Draw resource aggregation (histogram)
Modified Bar Chart for Example 2

Week

No

Activity

Duration
(week)

Human Resources
(people)

1/10

8/10

3
15/10

22/10

29/10

5/11

12/11

15

4
4

1
2

Resources
(People)

TOTAL HUMAN RESOURCES

10
5
0

Duration (week)

Progress Curves
Table 4.2 Combination between S-Curves and Bar Charts

Month

Description
1

Mobilization

Foundation Excavation

Diversion Stage

Foundation Grouting

Dam Concrete

Install Outlet Gates

Install Trash Racks

Prestress

Radial Gates

10

Spillway Bridge

11

Curtain Grout

12

Dismantle Plant, Clean Up

10
100

Original Schedule

Cumulative progress (%)

No.

Actual progress

0
29

Progress Curves
Step by step to make s-curve
- Calculate cost for each activity
- Calculate total cost for all activity
- Calculate the progress ratio between cost for each
activity and total cost
- Divide those progress ratio equally for each activity
according to its duration
- Add the progress ratio which already divided for each
unit of time
- Calculate the cumulative progress ratio
- Draw S-Curve as a relationship between cumulative
progress ratio and duration of a project
Figure 4.4 Step by Step to Make Progress or S-Curve

30

Progress Curves
Example 3.3
As a bar chart is created in Example 3.1, try to draw a
progress or S-Curve of the project with additional data as
follow :
WORK
PROGRESS
RATIO (%)

No

ACTIVITY

DURATION
(WEEK)

COST
(RM)

A
B
C
D
E
F

1
2
3
2
2
1

1600
2000
6000
4900
3600
2000

8
10
30
24
18
10

20000

100%

2
3
4
5
6

TOTAL

31

Progress Curves
Table 4.3 Progress or S-Curve

activity

duration
(week)

progress
ratio
(%)

10

30

24

18

10

week

1
1/10

2
8/10

3
15/10

5
29/10

22/10

6
5/11

100

8
2.1

2.9
10

10

10
6.9

12
9

50

5.1
9
10

Work progress ratio (%)

10.1

12.9

16.9

31

24.1

Cumulative wok progress ratio (%)

10.1

15.1

28

44.9

75.9

100
32

Cumulative progress (%)

No

Critical Path Method (CPM)

CPM provides the following benefits:


o Provides a graphical view of the project.
o Predicts the time required to complete the project.
o Shows which activities are critical to maintaining the

schedule and which are not.


CPM models the activities and events of a project as a
network.

33

NETWORKING TECHNIQUE
Activity on Arrow - ARROW DIAGRAM
Activity on Node

- PRECEDENCE DIAGRAM

TYPICAL ARROW DIAGRAM


(AOA)

Fabricate Rebar
Fixed
Rebar

Excavate
Trench

Fabricate
formwork

Fixed
Formwork

Pour
Concrete

TYPICAL PRECEDENCE DIAGRAM


(AON)
Fabricate
Rebar

Excavate
Trench

Fabricate
formwork

Fixed
Formwork

Fixed
Rebar

Pour
Concrete

Critical Path Method (CPM)


ADVANTAGES

DISADVANTAGES

- Networks can much more


concisely represent large
numbers of activities
- The logical interrelationships
and dependencies among
activities is really shown
- Much more useful for
forecasting and control
- It identify the most critical
elements in the project
schedule
- Easy to adjust if any delay is
happen in the project

- A little bit difficult to


understand the network system

TYPES OF CPM
- Arrow Diagram Method (ADM)
- Precedence Diagram Method
(PDM)

Figure 4.5 Advantages and Disadvantages of Critical Path Method

37

EARLY START (ES)


The earliest possible time to start an activity. It is determine by forward pass
calculation through every paths of the network
EARLY FINISH (EF)
The earliest possible time to finish an activity (ES+Duration)
LATE START (LS)
The latest possible time to start an activity without delaying the overall
completion of the project
LATE FINISH (LF)
The latest possible time to finish an activity without delaying the overall
completion of the project It is determine by backward pass calculation
through every paths of the network

TOTAL FLOAT (TF) APUNGAN KESELURUHAN


The time available to delay the start or finish of an activity
without delaying the completion of the project
Formula : LF ES D = TF

FREE FLOAT (FF) APUNGAN BEBAS


The time available to delay the start or finish of an activity
without delaying the EARLY START TIME (ES) of the
proceeding activity/ies
Formula : EF ES D = FF

ADM vs. PDM


Table 4.4 Differences between ADM and PDM Method

Item

ADM (AOA)

PDM (AON)
ES

EF

D
A

LS

TF

LF

Activity
ES: Early Start LS: Late Start
EF: Early Finish LF: Late Finish
D : Duration
TF: Total Float
ES

Event

LS

EF

A
2

ES

EF

ES

A
LF

LS

TF

EF

B
LF

LS

TF

LF

40

ADM vs. PDM


Table 4.4 Differences between ADM and PDM Method (cont.)

Item

ADM

PDM

Definition

Dummy
Activity

Activity which has not duration. It


is only used to show any
relationship between activities.

Dummy activity is not used in


Precedence Diagram Method
(PDM)

Function
If there is a situation where one

D
or

event is used to show


relationship more than one
activity.
To show a complicated
relationship clearly

41

ADM vs. PDM


Table 4.4 Differences between ADM and PDM Method (cont.)

Item

ADM

False

True

Dummy
Activity

D
or
A

42

ADM vs. PDM


Table 4.4 Differences between ADM and PDM Method (cont.)

Item

ADM

PDM

F-S

FS
FF
SS
S-F

Relationship

Critical Path

: A path consist of few activities which will determine the overall project
duration.
Critical path

1.
2.
3.

Es = Ef, or
Ls = Lf, or
Total Float (TF) = 0

- Possible to have more than one critical path


- Activities which lay on critical path cannot suffer any delay
44

ADM vs. PDM


Table 4.4 Differences between ADM and PDM Method (cont.)

Item

ADM

PDM

- Total float

Total float

: The maximum amount of time that the activity can be delayed without
extending the completion time of the overall project.

- FORWARD PASS select big number (duration)

Estimating
duration

: To establish the earliest expected start and finish times for each
activity in the network. (ES n EF)
- BACKWARD PASS select small number (duration)

: To establish the latest allowable start and finish times for each activity
in the network. (LS n LF)
45

Arrow Diagram Method (ADM)


Note

Forward pass

a
b

A
X

backward pass

c
2 d

B
3
Y

e
f

a
b
c
d
e
d
X
Y

:
:
:
:
:
:
:
:

Early Start (ES)A


Late Start (LS)A
Early Finish (EF)A = (ES)B
Late Finish (LF)A = (EF)B
Early Finish (EF)B
Late Finish (LF)B
Duration of activity A
Duration of activity B

forward pass

Backward pass

a = 0
c = a + X
e = c + Y

f = e
d = f Y
b = d - X

Figure 4.6 Estimating Project Duration using Arrow Diagram Method (ADM)

46

Arrow Diagram Method


Example 3.4
Activity

A
B
C
D
E
F
G
H

Event

1-2
2-3
2-4
3-5
4-6
5-7
6-7
7-8

Successor

Duration
(week)

B, C
D
E
F
G
H
H
-

2
3
2
4
3
2
3
1

Estimate the total project duration.


Calculate the total float for each activity in the project
Draw the bar chart according to your calculation

47

Arrow Diagram Method


Solution 3.4

3
B

9
9
2

3
0

1
0

2
2

11

11

12
8

4
4
5

E
3

7
8

Total Project Duration = 12 weeks


48

12

Arrow Diagram Method


Solution 3.4 (cont.)

Event

Activity

Duration

ES

LS

EF

LF

Total Float

(1)

(2)

(3)

(4)

(5)

(6)

(7)

(8) = 7-3-4

1-2
2-3
2-4
3-5
4-6
5-7
6-7
7-8

A
B
C
D
E
F
G
H

2
3
2
4
3
2
3
1

0
2
2
5
4
9
7
11

0
2
2
5
5
9
8
11

2
5
4
9
7
11
11
12

2
5
5
9
8
11
11
12

0*
0*
1
0*
1
0*
1
0*

Critical Path : A B D F H
49

Arrow Diagram Method


Solution 3.4 (cont.)

No

week

Activity
1

3
4

C
D

10

11

50

12

Example 2 on Activity-on-Arrow (A-O-A)


Estimate the total project duration.
Calculate the total float for each activity in the project
Draw the bar chart according to your calculation
ACTIVITY

EVENT

DURATION
(DAY)

PREDECESSOR

START

1-2

START

1-3

START

1-4

START

2-7

3-6

F (DUMMY)

4-6

4-5

7-8

7-9

6-9

E,F

5-9

9-10

I,J,K

8-10

FINISH

M,L

B
5

J
5

C
4

F
K

4
4

G
7

10

2
7

18
M

13

12

11

E
6

C
4

J
10

9
15

L
15

10
20

F
K

4
4
4

G
4

5
11

11
Total Project Duration = 20 weeks
Critical Path = C-G-K-L

20

ACTIVITY

EVENT

DURATION

ES

LS

EF

LF

FF

TF

START

1-2

1-3

1-4

2-7

11

12

3-6

10

F (DUMMY)

4-6

4-5

11

11

7-8

11

12

13

18

7-9

11

12

15

15

6-9

10

15

15

5-9

11

11

15

15

9-10

15

15

20

20

8-10

13

18

20

20

FINISH

54

Arrow Diagram Method


No

Activity

DURATION (DAY)

Total
Float

10

11

12

10

11

12

13

14

15

16

17

18

19

20

55

Arrow Diagram Method


Example 3.5
Activity

Event

Predecessor

Duration
(week)

A
B
C
D
E
F

1-2
1-3
1-4
2-5
3-6
4-7
5-6
5-8
6-7
6-9

A
B
C
D
D, E

2
1
3
1
3
2
4
1

7-10

D, E, F

8-11

9-11

10-11

DUMMY

G
DUMMY

Estimate the total project


duration.

Calculate the total float for


each activity in the project

Draw the bar chart according


to your calculation

56

Arrow Diagram Method


Solution 3.5 (cont.)

7
9
J

10
11

3
C
4

3
3

F
7
2

7
10

TOTAL PROJECT DURATION = 10 WEEKS


57

10

Arrow Diagram Method


Event

Activity

Duration

ES

LS

EF

LF

Total Float

(1)

(2)

(3)

(4)

(5)

(6)

(7)

(8) = 7-4-3

1-2
1-3
1-4
2-5
3-6
4-7
5-8
6-9
7-10
8-11

A
B
C
D
E
F
G
H
I
J

2
1
3
1
3
2
4
1
3
3

0
0
0
2
1
3
3
4
5
7

0
0
0
4
2
3
5
5
5
9

2
1
3
3
4
5
7
5
7
10

4
2
3
5
5
5
9
8
7
10

2
1
0*
2
1
0*
2
3
0*
0*

9-11
10-11

K
L

2
3

5
7

8
7

10
10

10
10

3
0*
58

Arrow Diagram Method


Solution 3.5 (cont.)
No

1
2
3
4
5
6
7
8
9
10
11
12

Activity

A
B
C
D
E
F
G
H
I
J
K
L

Total
Float

week
1

2
1
0
2
1
0
2
3
0
2
3
0

1. Total Project Duration = 10 weeks

10

59

Precedence Diagram Method (PDM)


Time calculation for f-s and s-s relationship
item

A-B (F-S)

A-C (S-S)

Forward Pass (choose the largest number, if >1)

LA-B

A
b

B
f

F-S

ESA

EFA

=a+X

ESB

= c + LA-B

EFB

=e+Y

ESC

= a + LA-C

EFC

=i+Z

Backward Pass (choose the lower number, if >1)

LA-C
S-S

C
j

Figure 4.6 Time Calculation for F-S and S-S


Relationship

LFB

=g

LSB

=h-Y

LFA

= f - LA-B

LSA

=d-X

LFC

=k

LSC

=l-Z

= j - LA-C

Table 4.7 Formula for Calculating Time F-S


60
and S-S

Precedence Diagram Method


Table 4.8 Formula for Calculating Time S-F
and F-F
a

A
b

LA-C
S-F

C
j

A-C (S-F)

A-B (F-F)

Forward Pass (choose the largest number, if >1)

B
d

item

LA-B

l
F-F

Figure 4.7 Time Calculation for S-F and F-F


Relationship

ESA

EFA

=a+X

ESB

EFB

=e+Y

EFC

= a + LA-C

= g + LA-B

ESC

=kZ

=kZ

Backward Pass (choose the lower number, if >1)


LFC

=k

LSC

=l-Z

LSA

= l - LA-C

LFA

=b+X

LFB

= l - LA-B

LSB

=h-Y

61

Precedence Diagram Method


Example 3.6
No

Activity

duration

successor

relationship

(week)

Lag (l)
(week)

B,D

A-B (F-S)
A-D (S-S)

0
1

B-C (F-S)

D-E (F-S)

E-C (F-S)

1. Estimate the total project duration.


2. Calculate the total float for each activity in the project
3. Draw the bar chart according to your calculation
62

Precedence Diagram Method


SOLUTION 3.6

L=0

A
0

L=1

B
2

C
4

L=0
1

L=0

L=1

D
3

Note
Total Float (TF):

Total Project Duration = 6 weeks

TF

Critical Path :

63

Precedence Diagram Method


SOLUTION 3.6 (CONT.)

No

week

Activity
1

3
4

C
D

L=1
L=1

64

Precedence Diagram Method


Estimate the total project duration.
Calculate the total float for each activity in the project
Draw the bar chart according to your calculation

ACTIVITY

DURATION
(WEEKS)

SUCCESSOR

B, C, D, E

C, H

F, G

D, K

I, J

H, M

M, K

10

L, O, P, N

NIL

65

Total 3Project
Period
: 51 weeks
Chapter
- Project
Planning,
Scheduling and Controlling
Critical path : A-E-D-G-J-J-K-N-P-Q

66

Scheduling Technique
Line of Balance
Piling

Pile-cap

Piers

Deck

Quantity

20

Time

34

LINE OF BALANCE

A scheduling technique suitable for repetitive nature of


activities project

Incorporate productivity rate


Originated from manufacturing

CONCEPT OF CONTROLING
Project Controls can be defined as
Management action, either preplanned to achieve the desired
result or taken as a corrective measure prompted by the
monitoring process. Project controls is mainly concerned with
the metrics of the project, such as quantities, time, cost, and
other resources; however, also project revenues and cash flow
can be part of the project metrics under control. Thus, we
believe an effective Project Controls process can be applied in a
collaboration of its various sub-disciplines, such as:

69

CONCEPT OF CONTROLING
1) Planning, Scheduling & Project Reporting

Scope management;

Project deliverables:

Work breakdown / Cost breakdown structures;

Schedule management;

Schedule forecasting;

Corrective action;

Progress measurement / reporting;

Productivity Analysis & Calculation;


2) Earned Value Analysis & Management

70

CONCEPT OF CONTROLING
3) Cost Engineering & Estimating

Estimating;

Cost management;

Cost control;

Cost forecasting
4) Change Management & Controls

Change order control;

Trend Analysis;
5) Risk and Delay Claims

Risk Assessment & management;

Delay Claims Quantification

Forensic Schedule Analysis

71

Quality management system

72

Quality management process and concept


The project manager has the ultimate responsibility for quality management on the
project.

Quality management has equal priority with cost and schedule management.
However, the direct measurement of quality may be the responsibility of the
quality assurance department or the assistant project manager for quality.

For a labor-intensive project, management support (i.e., the project office) is


typically 1215 percent of the total labor dollars of the project. Approximately 35
percent can be attributed to quality management. Therefore, as much as 2030
percent of all the labor in the project office could easily be attributed to quality
management.

73

Quality management process and concept


From a project managers perspective, there are three quality
management concepts that should exist support each and every
project. They include:
QUALITY PLANNING
The quality planning is created by the project manager and project team members by
breaking down the project objectives into a work breakdown structure. Using a
treelike diagramming technique, the project activities are broken down into lowerlevel activities until specific quality actions can be identified. The project manager
then ensures that these actions are documented and implemented in the sequence
that will meet the customers requirements and expectations. This enables the project
manager to assure the customer that he has a road map to delivering a quality
product or service and therefore will satisfy the customers needs.

74

Quality management process and concept


A good quality planning will:
Identify all of the organizations external and internal customers
Cause the design of a process that produces the features desired by
the customer
Bring in suppliers early in the process
Cause the organization to be responsive to changing customer needs
Prove that the process is working and that quality goals are being met

75

Quality management process and concept


QUALITY ASSURANCE

Quality assurance is the collective term for the formal activities and managerial processes that
attempt to ensure that products and services meet the required quality level. Quality assurance also
includes efforts external to these processes that provide information for improving the internal
processes. It is the quality assurance function that attempts to ensure that the project scope, cost,
and time functions are fully integrated.
The Project Management Institute Guide to the Body of Knowledge (PMBOK) refers to quality
assurance as the management section of quality management. This is the area where the project
manager can have the greatest impact on the quality of his project. The project manager needs to
establish the administrative processes and procedures necessary to ensure and, often, prove that
the scope statement conforms to the actual requirements of the customer. The project manager
must work with his team to determine which processes they will use to ensure that all stakeholders
have confidence that the quality activities will be properly performed. All relevant legal and
regulatory requirements must also be met.
76

Quality management process and concept


A good quality assurance system will:
Identify objectives and standards
Be multifunctional and prevention oriented
Plan for collection and use of data in a cycle of continuous
improvement
Plan for the establishment and maintenance of performance measures
Include quality audits

77

Quality management process and concept


QUALITY CONTROL
Quality control is a collective term for activities and techniques, within the process,
that are intended to create specific quality characteristics. Such activities include
continually monitoring processes, identifying and eliminating problem causes, use of
statistical process control to reduce the variability and to increase the efficiency of
processes. Quality control certifies that the organizations quality objectives are being
met.
The PMBOK refers to quality control as the technical aspect of quality
management. Project team members who have specific technical expertise on the
various aspects of the project play an active role in quality control. They set up the
technical processes and procedures that ensure that each step of the project provides
a quality output from design and development through implementation and
maintenance. Each steps output must conform to the overall quality standards and
quality plans, thus ensuring that quality is achieved.

78

Quality management process and concept


A good quality control system will:
Select what to control
Set standards that provide the basis for decisions regarding possible
corrective action
Establish the measurement methods used
Compare the actual results to the quality standards
Act to bring nonconforming processes and material back to the standard
based on the information collected
Monitor and calibrate measuring devices
Include detailed documentation for all processes
79

Você também pode gostar