PURPOSE:
This document defines the process of preparing HVAC ducting layout with
respect to ITB specification and good engineering practice.
2.
SCOPE:
This Work Instruction indicates basic technical requirements to design HVAC
Ducting Layout.
3.
REFERENCES:
4.
DEFINITIONS:
RCP
BOD
IDC
IFA
IFC
ASHRAE
SMACNA
5.
INSTRUCTIONS:
5.1 The HVAC duct routing, sizing, and levelling (BOD) to be decided based on
the ITB specification, good engineering practice (ASHRAE & SMACNA
standards) maintainability, constructability and the space available in the
building. Ducting layout to be prepared based on constant friction method.
The air velocity consideration as follows.
8-10m/s in plant room
6-8m/s in main ducting
5.2 Fittings
Duct fittings selection should be based on ITB requirement & good
engineering practice.
General fittings for HVAC ducting:
Gas tight Damper:- To prevent outsides hazardous gas enter as fresh air
in the system, Gas tight damper require in the fresh air inlet line.
Fire Damper: - Fire Damper to be installed in ducting that crosses any fire
rated wall or plant room wall to prevent fire to spread.
Duct Heater: - Duct Heater to be installed in supply duct for heating of air.
Diffuser, Grille etc: - Grille, diffusers are used to distribute required air in
side the room.
5.6.
Project Phases
5.6.1 IDC
Information (layout Dwg.) to be given to other discipline (CSA,
Electrical, Instrumentation, Piping layout etc.) for comments and
considerations.
5.6.2 IFA
Incorporating IDC comments in layout, the drawing to be issued for
approval to Client, Consultant and other discipline.
5.6.3 IFC
Approved layout to be issued to PMC and Client for approval to proceed
construction activities.
6. ATTACHMENTS:
1. Reference HVAC Ducting layout
7. REVISION HISTORY
No.
Date
Page
: Piping Speciality-HVAC
2013. 06. 14
New Issue
Reviewed by : Pradeep Kumar Suman
Approved by : Rakesh Kumar
- Department
: Piping Speciality-HVAC
2014. 02. 03
1-5