TASK 1
BUDGET FORECAST
TASK 2
ELEMENTAL COST PLAN
CALCULATIONS
PREVIOUS PROJECT( Cost Data)
REFERENCES
BUDGET FORECAST
PROJECT TITLE : "Care for Kids" Child care centre and nursery.
CLIENT
: UNIVERSITY OF SALFORD
LOCATION
: COLOMBO - PITAKOTTE
DATE
: DECEMBER 2013
CONSTRUCTION PERIOD : 10 months
BUILDING COST
RISK ( PHYSICAL CONTINGENCIES)
PRICE CONTINGENCIES
LAND & LEGAL COSTS(finance for 18 months)
PROFESSIONAL FEES (finance for 20 months)
COSTS OF FINANCE
COST OF FINANCE FOR BUILDING COST
COST OF FINANCE FOR LAND & LEGAL COSTS
COST OF FINANCE FOR PROFESSIONAL FEES
TOTAL CAPITAL COST
Rs.
Assumption
Let's assume Building cost is finance for 24 moths
Expences
58,209,774.44
4,074,684.21
2,910,488.72
32,000,000.00
4,656,781.96
14,808,566.62
6,276,719.22
1,025,377.00
123,962,392.17
BUILDING WORKS
Substructure
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
Superstructure
Frame
Upper Floors
Roof
Stairs
External Walls
Windows & External Doors
Internal Walls & partitions
Internal Doors
Total Superstructure
3
3.1
3.2
3.3
Internal Finishes
Wall Finishes
Floor Finishes
Ceiling Finishes
Total Internal Finishes
5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
5.10
5.11
5.12
5.13
Services
Sanitary Installations
Services Equipment
Disposal Installations
Water Installations
Heat Source
Space Heating and Air Conditioning
Ventilation Systems
Electrical Installations
Fuel Installations
Lift and Conveyor Installations
Fire and Lightning Protection
Communication, Security and Control Installations
Specialist Installations
7,605.98
2,600.87
14,668.32
3,891.94
5,223.12
14,938.60
2,680.24
44,003.09
2,832.92
3,200.24
772.63
6,805.79
1,238.12
7,219.12
8,917.74
5.14
6
6.1
7
7.1
7.2
7.3
7.4
7.5
7.6
8
8.1
8.2
8.3
8.4
8.5
8.6
8.7
8.8
External works
Site Preparation Works
Roads, Paths, Pavings and Surfacings
Soft Landscaping, Planting and Irrigation Systems
Fencing, Railings and Walls
External Fixtures
External Drainage
External Services
Minor Building Works and Ancillary Buildings
Total external works
9
9.1
9.2
9.3
9.4
9.5
9.6
19,300.08
519.52
1,919.39
1,867.04
1,804.78
1,533.47
3,489.65
11,133.85
Facilitating works
Toxic/Hazardous/Contaminated Material Treatment
Major Demolition Works
Temporary Support to Adjacent Structures
Specialist Ground Works
Temporary Diversion Works
Extraordinary Site Investigation
SUB-TOTAL: BUILDING WORKS
10
10.1
10.2
1,925.10
88,848.79
1,776.98
4,442.44
6,219.42
95,068.20
11
11.1
11.2
9,506.82
7,605.46
17,112.28
112,180.48
13
14
14.1
14.2
14.3
14.4
Risks
Design development risks
Construction risks
Employer change risks
Employer other risks
TOTAL: RISK ALLOWANCE ESTIMATE (D)
Inflation
Tender inflation
Construction inflation
TOTAL: INFLATION ALLOWANCE (F)
3,365.41
2,243.61
3,365.41
8,974.44
121,154.92
2,423.10
2,423.10
1,817.32
1,817.32
8,480.84
129,635.76
1,296.36
1,309.32
2,605.68
VAT ASSESSMENT
132,241.44
15,868.97
nd nursery.
Total Cost of Element
(Target Cost)
5,308,974.67
1,815,403.95
10,238,484.85
2,716,571.83
3,645,741.01
10,427,142.86
1,870,810.56
30,714,155.05
1,977,374.79
2,233,768.24
539,299.00
4,750,442.04
864,209.85
5,038,946.42
6,224,580.87
1,343,719.05
13,471,456.19
362,627.47
1,339,732.13
1,303,192.48
1,259,736.61
1,070,364.44
2,435,773.18
7,771,426.31
62,016,454.25
1,240,329.08
3,100,822.71
4,341,151.80
66,357,606.05
6,635,760.60
5,308,608.48
11,944,369.09
78,301,975.13
2,349,059.25
1,566,039.50
2,349,059.25
6,264,158.01
84,566,133.14
1,691,322.66
1,691,322.66
1,268,492.00
1,268,492.00
5,919,629.32
90,485,762.47
904,857.62
913,906.20
1,818,763.83
92,304,526.29
11,076,543.15
TASK 1
Cost per m2 GIFA from previous cost annalysis of PreSchool project for Green volunteers at Nikawaratiya
75,545.12
493.8
573.9
16%
87,799.40
Location Adjustment
Previous project's location was Nikaweratiya and current project going to established in Colom
So Material and Labour prices of new project will be less than previous project
We assume that percentage as
Rate per GIFA after location adjustment
-5%
83,409.43
TASK 2
1
Substructure
Time adjustment (Inflation)
According to Table 4 of the ICTAD bulletin of construction statistics 2013 February
Previous Project 2011 Augest
New Project 2013 February
Percentage addition for inflation
Rate per GIFA after time adjustment
493.8
573.9
16%
8,006.30
Location Adjustment
Previous project's location was Nikaweratiya and current project going to established in Colom
So Material and Labour prices of new project will be less than previous project
We assume that percentage as
-5%
7,605.98
Superstructure
2.1
Frame
Time adjustment (Infltion)
Rate per GIFA after time adjustment
Location Adjustment
Rate per GIFA after location adjustment
2.3
2,600.87
Roof
Quantity adjustment
GIFA m2
Previous project
468
Roof Area m2
562
12,512.02
15,440.33
Location adjustment
Rate per GIFA after location adjustment
2.5
2,737.75
14,668.32
External walls
Quantity adjustment
GIFA m2
Ext. wall Area m2
Previous project
468
512
4,404.06
3,524.98
4,096.78
Location adjustment
Rate per GIFA after location adjustment
3,891.94
2.6
1810x1210 5nrs
1360x1210 1nr
2935x1210 1nr
1585x600
1nr
460x250
1nr
Assumption made for w1 and w3 hights as 600mm and 250mm
Doors
910x2100
3385x2100
2710x2100
1697x2100
3160x2100
3835x2100
1585x2100
6nrs
4nrs
2nrs
2nrs
2nrs
1nr
1nr
Quantity adjustment
GIFA m2
Ext. windows and doors Area m2
40
2,822.22
5,498.03
Location adjustment
Rate per GIFA after location adjustment
2,7
Previous project
468
5,223.12
Previous project
468
238
6,538.46
14,938.60
2.8
Internal Doors
Quantity adjustment
GIFA m2
Internal Doors nr
15
1,108.33
2,821.31
Internal Finishes
3.1
Wall finishes
Time adjustment (Infltion)
Rate per GIFA after time adjustment
Location Adjustment
Rate per GIFA after location adjustment
2,680.24
2,982.02
2,832.92
Floor finishes
Time adjustment (Infltion)
Rate per GIFA after time adjustment
Location Adjustment
Rate per GIFA after location adjustment
3.3
Previous project
468
Location adjustment
Rate per GIFA after location adjustment
3.2
14,938.60
3,368.67
3,200.24
Ceiling finishes
Time adjustment (Infltion)
Rate per GIFA after time adjustment
Location Adjustment
Rate per GIFA after location adjustment
813.30
772.63
Services
5.1
Sanitary appliances
Quantity adjustment
GIFA m2
Sanitary appliances nr
Cost per m2 GIFA Rs.
Time adjustment (inflation)
Rate per GIFA after time adjustment
Location adjustment
Rate per GIFA after location adjustment
Previous project
468
22
919.87
1,303.29
1,238.12
Water installations
Time adjustment (Infltion)
Rate per GIFA after time adjustment
Location Adjustment
Rate per GIFA after location adjustment
5.8
7,599.07
7,219.12
Electrical installations
Time adjustment (Infltion)
Rate per GIFA after time adjustment
Location Adjustment
Rate per GIFA after location adjustment
9,387.09
8,917.74
2,026.42
1,925.10
External Work
8.1
Site preparation
Quantity adjustment
GIFA m2
Site preparation m2
341.88
546.87
Location adjustment
Rate per GIFA after location adjustment
519.52
Previous project
468
205
1,335.47
2,020.41
Location adjustment
Rate per GIFA after location adjustment
8.3
1062
8.2
Previous project
468
1,919.39
Previous project
468
1062
1,228.63
1,965.30
Location adjustment
Rate per GIFA after location adjustment
8.4
8.6
Location Adjustment
Rate per GIFA after location adjustment
1,804.78
1,614.18
1,533.47
Assumptions made
1,899.77
External Drainage
Time adjustment (Infltion)
Rate per GIFA after time adjustment
8.8
1,867.04
3,673.31
3,489.65
12.2
Risks
Design development risks 2% of Base cost estimate
Construction risks 2% of Base cost estimate
Employer change risks 1.5% of Base cost estimate
15 Inflation
15.1 Tender inflation 1% of cost limit (excluding inflation)
Construction inflation 1% of cost limit (excluding
15.2
construction inflation)
16
VAT ASSESSMENT
Lets assume that Consultants and Main Contractors are
VAT registered and therefore Client has to pay 12% VAT
charges
13 February
g to established in Colombo
s project
13 February
g to established in Colombo
s project
New Project
698
890
13,285.30
New Project
698
382
2,203.11
1810
1360
2935
1585
460
910
3385
2710
1697
3160
3835
1585
New Project
698
100
4,730.66
New Project
698
811
14,938.60
1210 1810x1210
1210 1360x1210
1210 2935x1210
600 1585x600
250 460x250
2100 910x2100
2100 3385x2100
2100 2710x2100
2100 1697x2100
2100 3160x2100
2100 3835x2100
2100 1585x2100
5
1
1
1
1
6
4
2
2
2
1
1
New Project
698
49
2,427.54
New Project
698
40
1,121.39
ginal or equalent.
New Project
698
2180
470.54
New Project
698
398
1,738.42
New Project
698
2180
1,691.00
uction Industry)
10.9505
1.6456
3.55135
0.951
0.115
11.466
28.434
11.382
7.1274
13.272
8.0535
3.3285
100.27685
Element
Total cost
SUBSTRUCTURE
SUPERSTRUCTURE
Frame
Upper Floors
Roof
Stairs and Ramps
External Walls
Windows and External Doors
Internal Walls and Partitions
Internal Doors
Total Superstructure
INTERNAL FINISHES
Wall Finishes
Floor Finishes
Ceiling Finishes
Total Internal Finishes
FITTINGS, FURNISHINGS AND EQUIPMENT
SERVICES
Sanitary Installations
Services Equipment
Disposal Installations
Water Installations
Heat Source
Space Heating and Air Conditioning
Ventilation Systems
Electrical Installations
Fuel Installations
Lift and Conveyor Installations
Fire and Lightning Protection
Communication, Security and Control Installations
Specialist Installations
Builders Work in Connection with Services
Total Services
PREFABRICATED BUILDING AND BUILDING UNITS
WORK TO EXISTING BUILDING
Minor Demolition and Alteration Works
Total Work to Existing Building
BUILDING SUB-TOTAL
EXTERNAL WORKS
Site Preparation Works
Roads, Paths, Pavings and Surfacings
Soft Landscaping, Planting and Irrigation Systems
Fencing, Railings and Walls
3,223,980.00
1,102,440.00
5,855,625.00
2,061,100.00
1,320,800.00
556,500.00
518,700.00
11,415,165.00
1,200,800.00
1,356,500.00
327,500.00
2,884,800.00
430,500.00
3,060,000.00
3,780,000.00
816,000.00
8,086,500.00
160,000.00
625,000.00
575,000.00
765,000.00
External Fixtures
External Drainage
External Services
Minor Building Works and Ancillary Buildings
Total External Works
FACILITATING WORKS
Toxic/Hazardous/Contaminated Material Treatment
Major Demolition Works
Temporary Support to Adjacent Structures
Specialist Ground Works
Temporary Diversion Works
Extraordinary Site Investigation
Total Faciltating Work
650,000.00
1,479,171.50
4,094,171.50
29,704,616.50
5,650,500.00
35,355,116.50
1,767,755.83
42,773,372.33
2,355.64
12,512.02
4,404.06
2,822.22
1,189.10
1,108.33
24,391.38
2,565.81
2,898.50
699.79
6,164.10
919.87
6,538.46
8,076.92
1,743.59
17,278.85
341.88
1,335.47
1,228.63
1,634.62
1,388.89
3,160.62
8,748.23
63,471.40
12,073.72
75,545.12
3,777.26
91,396.09
REFERENCES
RICS ,2009, New Rules of Measurement, Coventry CV4 8JE, Royal Institution of Chartered
Surveyors (RICS)
Surveyor Court
RICS, 2012, Elemental Standard Form of Cost Analysis, 4th (NRM) Edition, London, BCIS
February-2013, ICTAD Bulletin of Construction Statistics, volume 23 No.02, Colombo 07, ICTAD