Escolar Documentos
Profissional Documentos
Cultura Documentos
INTRODUCTION .................................................................................................................................... 1
BACKGROUND ......................................................................................................................................................... 1
PURPOSE AND SCOPE OF WORK .................................................................................................................... 1
SITE STRATIGRAPHY ......................................................................................................................... 2
TYPE OF CLAY AND GENERAL GEOTECHNICAL CHARACTERISTICS ................................................. 2
GEOTECHNICAL PROPERTIES USED IN MODELLING ............................................................................... 2
STABILITY ANALYSIS ........................................................................................................................ 3
MODEL ....................................................................................................................................................................... 3
CALIBRATION OF MODEL FOR SHEAR STRENGTH .................................................................................... 3
DESIGN STABILITY IMPROVEMENTS ............................................................................................................... 3
TOE BERM STABILITY IMPROVEMENTS ......................................................................................................... 3
UPPER BANK OFFLOADING ................................................................................................................................ 3
ii
1.0 Introduction
1.1
Background
In August, 2009, the west bank of the Red River near a bridge to St. Adolphe was in a state
failure and in need of emergency engineering. SU3 had its piles sheared off and were
floating on the bank at a gradually increasing angle. Multiple retrogressive head scarps
immediately upslope of Pier SU 3 and beginning on the top of the bank were alarms of a
failure surface up to the west abutment. The lower banks were fully saturated. SU 3 shifted
horizontally and sunk about 2.5 m at the time of arrival of the engineer. The two spans
connecting at SU 3 were severely damaged and in danger of collapse. Emergency action
was taken in order to increase the factor of safety (FS) of the failing slopes.
1.2
2.2
Model
For this assignment, rotational failure was analyzed using the method of slices based on
Limit Equilibrium Method (LEM) and the Morgenstern-Price Method in SLOPE/W. It should
be noted that the methods used for modelling offer a measure of the average stress
mobilized in the slope and in reality this may not be exactly the actual shear stresses.
3.2
3.3
3.4
3.5
4.0 Conclusions
Given that SS1 was assumed initially to have a FS of 1 and through back analysis the residual friction
angle of the soil was calibrated to be 8 degrees. Moving forward using the governing residual friction
angle determined the first emergency action was to offload the approach embankment and upper bank in
1 m layers to reach a 20% improvement in FS which through interpolation shown in Table 1. The
estimated depth of 2.4 m is recommended for the contractor to remove to satisfy safety conditions and
working near the river bank. The second emergency action was to provide a rock fill berm at the toe of the
failure surface to provide a 30% increase in FS. The estimated depth of 5m toe berm for this problem
solution satisfied only a 13% increase the FS of SS1, and a 36% increase to the FS in SS2.
5.0 Recommendations
It is recommended that the berm offloading occur in 1 m layers initially extending approximately 10 m
back of the abutment. This offloading of the abutment and the upper bank should be completed up to at
least 2.4 m, and at least 5 m of rock fill should be placed to increase the overall stability of the failure
surfaces by at least 30% to accommodate the next stage of demolishing the damaged portion of the
bridge deck, and installing a shear key to further improve the FS to at least 1.5 for long term.
Tables
Table 1: Summary of Stability Characteristics
Case
Back Analysis
Interpolated for SS1 at FS = 1.0
Offloading Upper Bank (1m )
Offloading Upper Bank (2m)
Interpolated for delta FS = +20%
Offloading Upper Bank (3m)
Toe Berm (1m thick)
Toe Bern (3m thick)
Toe Berm (5m thick)
Height
(m)
SS#
1
1
1
1
1
2
2.4
2
1
1
1
3
1
1
3
3
5
5
1
1
2
1
2
1
2
Unit weight
(kN/m3)
c'
'r
(kPa) (deg)
2
5
2
8
2
10
2
15
FS
0.74
1.00
1.20
1.67
delta FS
(%)
2
2
2
2
8
8
8
8
1.07
1.11
1.22
1.29
4
14
20
20
20
20
20
20
20
2
0
0
0
0
0
0
8
35
35
35
35
35
35
1.41
1.02
1.19
1.02
1.31
1.13
1.45
32
2
11
2
22
13
36
Figures
Back Analysis - Sensitivity FS vs 'residual
2.00
1.50
F.S.
SS1
1.00
0.50
5
10
15
F.S. 1.20
SS2
1.00
0.80
1
Offloading (m)
Figure 3: Sensitivity - FS vs. Offloading
F.S. 1.20
SS1
1.10
SS2
1.00
0.90
0
10
11
12
References
[1]
Kenyon, Rob, University of Manitoba. CIVL 4230: Geotechnical Engineering Course Notes.
Winter 2016.
[2]
Kjartanson, B., Baracos, A., & Shields, D. (1983). Geological engineering report for urban
development of Winnipeg. Winnipeg, Man.: Dept. of Geological Engineering, University of
Manitoba.
13