Escolar Documentos
Profissional Documentos
Cultura Documentos
This report is commissioned by Action Against Hunger | ACF International. The comments contained herein
reflect the opinions of the Evaluator only.
TABLE OF CONTENTS
Executive Summary
4
4
4
5
Chapter 2: Methodology
Evaluation Questions
Evaluation Approach
Evaluation Constraints
Chapter 3: Findings
Targeting
Project Design
Project Implementation
Project Monitoring
Project Sustainability
Cross-Cutting Issues
Appendix
Damage in KP from 2010 Floods
Scoring Matrix
Acronyms
List of interviews
List of documents reviewed
Good practice case study
7
7
7
8
9
9
13
16
19
20
22
25
25
26
29
29
29
31
31
32
32
XECUTIVE SUMMARY
Over the last decade, Pakistan has experienced large-scale internal displacement
caused by a range of natural and human-made disasters. Structural poverty,
inappropriate development, rapid urbanization, inadequate infrastructures,
increased deterioration of the environment - deforestation, increased human
settlements in hazard prone areas, etc. have increased the vulnerability to disasters. Thus, even
a moderate flooding could have devastating effects in the future. An ACF DRM assessment
identified a lack of awareness amongst stakeholders concerning DRM, and thus a need for
capacity building. Thus, ACF carried out a DRM project funded by the Royal Norwegian
Embassy during 2011-12 to reduce morbidity and mortality risks by improving community
resilience to natural disasters in Nowsherra, Charsadda, Mardan and Lower Dir regions of KPK
province in northern Pakistan which are vulnerable to both serious floods and earthquakes.
At the end of 2012, ACF commissioned an evaluation to evaluate the impact and approach of
ACFs RNE funded DRM project. ACF subscribes to the Development Assistance Committee
(DAC) criteria for evaluation: Impact, Sustainability, Coherence, Coverage, Relevance /
Appropriateness, Effectiveness and Efficiency. ACF also promotes systematic analysis of the
monitoring system and cross cutting issues (gender, HIV/AIDS etc). These dimensions served
as the main evaluation criteria. The tools included documents review, interviews with ACF
international and national staff, government officials and partner staff and household interviews
(with 204 community members), Focus Group discussions and transect walks in 18 villages.
HAPTER 1: BACKGROUND
3. Project Details
Project General Objective
To reduce vulnerability and improve resilience to disasters in four districts of KPK, Pakistan
Specific Objectives
To enable communities to prepare for and mitigate the impacts of disasters using participatory
methods aimed at strengthening the self-reliance capacities of the population and reinforcing
or adapting infrastructure
Results
R.1- The ability to recognize hazard events and to cope with their effects is improved
R.2- The capacity to reduce the effect of hazards on communities and services is improved
R.3- The understanding/application of DRM at community and institutional level is improved
Programme Activities
R.1- The ability to recognize hazard events and to cope with their effects is improved
80% of intervention communities have functional local early warning systems
80% of target community can claim access to contingency stocks
90% of target communities are covered by disaster management plans.
R.2- The capacity to reduce the effect of hazard event on communities is improved
Facilities serving 60 communities are structurally strengthened to resist hazard events
90% of intervention communities have identified and equipped evacuation sites
R.3-The understanding/application of DRM at community/institutional level is improved
80% of intervention communities have disaster management units
240 individuals from local or district authorities receive DRM training
25500 individuals in the communities receive DRM Training
Specific Activities
Installation of Early Warning Systems in 48 Villages
Formation of 48 early warning groups in the community
Training of 48 early warning groups in the community
Development of emergency response plans and contingency stocks in 48 villages
5
HAPTER 2: METHODOLOGY
1. Evaluation Questions
The detailed evaluation questions are provided in chapter 3 and were grouped as follows:
Targeting
Project Design
Project Implementation
Project Monitoring
Project Sustainability
Cross cutting Issues
2. Evaluation Approach
Review of Relevant Documents
Prior to the field work, the evaluator reviewed the relevant documents, including those related to
this project, ACFs general work in Pakistan and DRM globally and documents related to DRM
and emergencies in Pakistan in order to gain a better understanding of the project and its
context and to help develop the evaluation methodology and instruments. Sufficient
documentation was available.
Initial Briefing
Prior to the field work, the evaluator participated in a teleconference with ACF New York HQ.
Indirect Information
Interviews were conducted with local authorities in Lower Dir, Mardan and Charsadda; project
expatriate and national staff in Islamabad and the districts; donor representatives and the
Director CDPM University of Peshawar.
Field activities
Household interviews with community members and Focus Group Discussions (FGDs) with
village committee members based on participatory evaluation methods were utilized. The
villages visited were selected randomly from lists provided by ACF while the community
members for household interviews were selected based on convenience sampling. Random
sampling for household interviews was not attempted since the project provided community7
FGDs
HH interviews
Charsadda
60
Mardan
36
Nowshera
60
Lower Dir
48
18
18
204
Total
3. Evaluation Constraints
A major evaluation constraint was the budget available for the evaluation which meant that while
the evaluation was conducted by an external evaluator, he was assisted in interviewing females
by two ACF female staff members from other ACF projects. In order to analyze the impact of the
participation of ACF staff in the data collection on the neutrality and objectivity of the findings,
the field data is presented separately by males (interviewed by external evaluator) and females
(interviewed by ACF staff). As seen later in chapter 3, except for one section of the household
questionnaire, the differences in the responses given to the external evaluator and internal ACF
staff were not found to be unusually different. However, for the future, it would be advisable for
ACF to recruit independent females for evaluations wherever possible even though the external
evaluator did accept the ACF proposition in this case. The budget implications of this strategy
could be managed by reducing the number of field visit days, which the external evaluator found
to be on the high side compared with other evaluations that he has conducted. Thus, the
additional villages visited did not necessarily add to the richness of the data collected and the
number of days in each district could easily have been reduced by one without affecting the
quality of data collection. Another constraint was the security situation in Pakistan as a result of
which the evaluator could not visit Peshawar due to the sudden deterioration of the security
situation during the evaluation. Field work on two particular days was also scaled back due to
security incidents. However, given the fact that the external evaluator is originally from Pakistan
and speaks the national language, the impact of security incidents on the evaluation activities
was minimized. Finally, timing was also a constraint as the evaluation was conducted near the
end of the year when some of the staff members were on leave, ACF was also focused on
finishing project activities and the Project Manager had finished his contract. However, despite
all these constraints, the evaluator succeeded in collecting adequate amounts of quality
information, mainly because of his strong background in conducing evaluations in Pakistan.
8
HAPTER 3: FINDINGS
This chapter provides the findings according to each question included in the
TORs under the headings mentioned in the last chapter. However, the
sequence of the questions and their placement under the headings has been
changed in some places to enhance readability. The findings under each
question are based on triangulation of information from the various sources of information
mentioned in the last chapter.
1. Targeting
This section focuses on the following questions
a) Did the communities selected for the project classify as being most vulnerable and
highly exposed to disaster risk, and did they meet the criteria established in the
project design? Could the PCVA process have been in any way improved to better
achieve this?
The evaluator visited 18 of the 60 villages targeted by the ACF for this project. All the villages in
all four districts were found to be vulnerable and those in Charsadda and Nowshera were also
among the most vulnerable villages in KP province highly exposed to disaster risk in the opinion
of the evaluator based on the numerous evaluations that he has conducted in Pakistan after the
2010 floods. The worst-affected villages were those where the floods destroyed most houses in
the village and most of the families in the villages were displaced for weeks or months, finally
returning to live in their villages in tents or makeshift houses for prolonged periods until they
could construct or received houses. Thus, the difference across the districts can be clearly seen
in the response of individual households to the following questions across the four districts:
Difference in disaster vulnerability across ACF districts
When was your village last affected by a major
disaster? (% identifying 2010 floods)
Was your family displaced in the disaster?
(% responding yes)
If yes, for how long? (no. of months)
Was your house damaged during this disaster?
(% responding yes)
Charsadda
Nowshera
Mardan
L. Dir
100%
100%
100%
100%
96%
92%
62%
10%
2.1
1.2
0.7
0.4
96%
92%
60%
40%
In all districts, the 2010 floods were identified by people as the most devastating disaster in
living history. FGDs revealed that the 2010 floods were viewed as more damaging than the
2005 earthquakes in the villages which experienced both mega-disasters. However, there is
significant difference in the damages experienced across the four districts. While 90%+ of the
families were displaced in Charsadda and Nowshera were displaced during the floods, only
10% of the families in Dir were displaced while 62% were displaced in Mardan. The period of
displacement ranged from a high of 2.1 months in Charsadda to 0.4 months in Dir. Finally, only
9
11
The NGO Code of Conduct asserts that agencies will distribute assistance based on objective
needs. The evaluator strongly feels that NGOs should have strong information within their files
to demonstrate that they are doing so for each project. It would also be advisable for ACF to
ensure that it does so for each project. Currently, while the targeting is excellent in Charsadda
and Nowshera, even for those districts, the corresponding information to reveal that these really
are the most vulnerable villages is not immediately available in project files. Having a map
immediately available in its files which shows that all the villages in Nowshera and Charsadda
are next to major villages along with information about the damage caused by the 2010 floods in
various districts, UCs and villages will help ACF in clearly demonstrating its adherence to this
NGO code of conduct principle. Currently, ACF has the maps with its project areas shown next
to rivers in Nowshera and Charsadda (see maps below) but not the information about 2010
damages. As can be seen in the maps below, the project areas in Dir and Mardan are not next
to major rivers. Similarly, if some areas are being left out due to security reasons, as in Dir, it
would be good to have a formal security report by its professional security team and a
subsequent SMT decision to back up this decision. If some areas are being left out because
12
b) Did the project strike the right balance between number of villages covered and the
amount of work done in each village? If not would it have been better to cover more
villages with less work, or fewer villages with a greater amount of work?
While detailed appropriateness of the software and hardware work done by ACF will be
discussed in the next section (project design), in order to answer this question, it can be
asserted briefly here that the evaluator finds the particular mix of such activities to be highly
appropriate and well-selected, which means that it would not be advisable to drop any of them
in order to increase the number of villages. At the same time, given Pakistans large size and
high vulnerability, the number of most vulnerable villages is very high compared with the 60
villages covered in this project and probably runs into hundreds if not thousands. At the same
time, the number of agencies undertaking DRM work is small. Thus, there is a clear need to
increase the number of villages from the present 60 in a future similar project without completely
dropping any category or even sub-category of work. This obviously poses a dilemma. As far
as the evaluator can see, the main bottleneck to increasing the number of villages is the number
of front-line field staff who work at the village level. Fortunately, such staff does no cost much
and an additional staff member could perhaps be hired for as little as 12,000-15,000 dollars per
year, which could easily be absorbed by some minor reconfiguration of the overall budget. The
other bottleneck is the cost of hardware work which is much higher. However, the evaluator also
noticed that in some villages more than one hardware activity was being implemented. By
keeping hardware activity down to one activity per village, it may be possible to cover more
villages. Also, ACF could overcome the hardware-related constraint and increase the number of
villages by trying to leverage its work by getting the government and other NGOs to cover some
of the hardware activities which may be beyond ACFs budget.
2. Project Design
a) Were the objectives, results and activities selected in the implementation of this
program relevant for the identified population needs? Was the participatory approach
used appropriate an effective in identifying and selecting specific interventions? Was
there sufficient consultation and participation of beneficiaries in the design, targeting,
implementation and post-implementation stages? Did the activities match with what
people wanted?
The starting point of ACFs work for this project is the Participatory Community Vulnerability
Analysis (PCVA) exercise which aims to view each villages vulnerability and possible steps to
reduce it through the eyes of the community by using participatory methods to understand the
main hazards, community strengths and weaknesses, and possible remedial measures for
strengthening the communitys resilience. The use of such an approach has helped ACF to
adopt a highly participatory process and identify the main components of the project in light of
community perspectives. While many of the project components, such as early warning
systems, contingency stocks and village plans, are obviously based on industry standards for
DRM work, their specific form in different villages has depended on community perspectives. To
13
Charsada
Nowshera
Mardan
98
96
92
95
95
96
97
Lwr
Dir
Male
Fem
ale
84
90
95
97
96
95
99
97
97
88
95
94
96
97
81
99
92
c) Did the project strike a good balance between hardware and software? If not, define
what the balance should have been? Was the scope of hardware activities sufficient?
If not, what other activities could have been added? Was the scope of software
activities sufficient? If not, what other activities could have been added?
The main hardware activities within the project consisted of the provision of contingency stock
for evacuation, rescue and relief activities and the construction of latrines, evacuation paths,
drainage and irrigation channels and flood protection walls to reduce the risk of disasters. The
main software activities were the setting up and training of village committees, development of
village disaster plans and early warning systems, awareness-raising about DRM among
communities and schools, training on DRM for construction workers and training of government
14
Purpose
Examples
Related ACF
activities
Prevention
To
reduce
the Global climate change None
occurrence
of advocacy;
riverbed
destructive hazards
dredging; reforestation
Mitigation
To
build
buffers Drainage
channels, Drainage
channels,
between hazards and flood protection walls
flood protection walls
communities
Community
capacity-building
To
enhance
the Livelihoods
work, Irrigation
channels;
resilience
of nutrition work, CBO VDMUs; community
communities
by strengthening
awareness-raising;
strengthening
their
Village disaster plans
socio-economic status
Evacuation
preparedness
Rescue
preparedness
Relief preparedness
With the understandable exception of prevention activities, which are generally out of the range
of NGO technical and financial capacities, ACF work is covering all the remaining categories of
DRM work. This reflects the comprehensive nature of the DRM package that ACF is providing.
On the software side, activities like village committee and disaster plan development, early
warning system and evacuation site identification do not cost much and can also be seen as
mandatory components of DRM work. Thus, those activities should all be retained. The real
issue is about hardware activities since they cost much more. The above framework can help in
making decisions about specific hardware work. Thus, the objective in each village should be to
select activities which fall in the highest possible category above while being relevant to the
village and affordable within the ACF budget. So for example, flood protection walls, drainage
channels and irrigation channels are much more durable forms of DRM work than activities such
as evacuation paths and latrines in evacuation centers since the former reduce the chances of
communities getting affected by disasters in the first place while the latter are about helping
communities once they have been struck by hazards. Flood protection walls tend to be
expensive and should preferably be built where benefiting large or several villages os that their
per beneficiary cost is closer to other mitigation activities. More specifically, the evacuation
paths built will not be helpful in major disasters as they will become fully submerged. Within
community capacity-building, especially those related to livelihoods strengthening, activities
which benefit the whole community, such as irrigation channels, are more beneficial than
activities which target individual families, such as provision of agricultural inputs to individual
households. Finally, ACFs contingency stocks packages are also a very useful input even
though they target the lower categories for the simple reason that they have a low cost but still
cover three DRM categories (evacuation, rescue and relief categories). In summary, the
software activities and contingency stocks should be mandatory components given their low
cost and wide-ranging coverage. Among the remaining hardware activities, those targeting
mitigation and community capacity-building are more useful than evacuation paths and latrines.
That said, it is recognized that the latter may be the best affordable option for some villages.
3. PROJECT IMPLEMENTATION
a) Evaluate the impact of the DRM training and disaster plans e.g. impact on capacity of
trained population to be better prepared through the training and preparedness plans.
Evaluate the effectiveness of the Early Warning system that was put in place.
DRM village committee and training: In all the villages visited in the four districts, the
evaluators found that both men and women village DRM committees had been formed and had
received training from ACF on DRM activities. The village committees seemed representatives
of all sections of the community in each village and seemed highly engaged in the DRM work
initiated by ACF. As a result of their DRM training, the committee members generally seemed
familiar with DRM concepts and fully geared up to play an active role in keeping their villages
safer during future disasters. They were highly appreciative of the DRM training and seemed
well aware about things like the values of early warning system, contingency stock and
16
in
Village disaster and contingency plans: Village disaster plans were seen hanging on the
walls in all the villages visited in Mardan, Charsadda and Nowshera although there was some
variation in the level of details contained by the plans across the villages. Thus, it would be
useful for ACF to develop a clear outline for the topics to be covered by such plans and ensure
that all villages complete all the topics. In Dir, the team had not yet engaged the villagers in any
village to complete such plans by the time of the evaluation which was undertaken during the
last two weeks of the project. The Dir team felt that they would still be able to complete the
plans in all the villages by December 31. However, clearly, even if they did so, it would seem to
be a rush, last moment job with little follow-up possible, which would affect the quality of the
whole exercise.
Early warning system: The early warning systems planned by ACF include linking the village
committees with governmental sources of information (by giving both parties the telephone
numbers of each other) about approaching hazards and also providing them with equipment,
such as megaphones and battery-operated loudspeakers for communicating the information
received from external sources within the villages. Most of the village committees had been
provided with the telephone numbers of relevant local authorities, such as police stations and
Civil Defence offices. However, the village committees had not been registered with government
departments so that those departments could proactively provide information to villagers. This
issue will be discussed in more detail under the sustainability section. Finally, due to some
delays in procurement, the equipment for intra-village dissemination of early warning systems
was being delivered in villages around the time of the evaluation. However, even so, such
systems would still be up and running before the 2013 flood season in July-August. However,
the success of ACFs EWS will of course depend on villages getting timely and accurate early
warning from government departments. Unfortunately, the technical and management capacity
of governments departments to provide such information is very low in Pakistan at the moment,
which is a major challenge for ACF. The final chapter will look at this issue in more detail.
17
18
Charsadda
Nowshera
Mardan
Lwr
Dir
Male
Female
98
98
97
95
94
100
75
61
73
50
38
94
94
74
73
30
48
85
64
58
56
21
68
5. Evacuation sites
89
85
61
52
55
100
6. DRM training
95
91
71
73
69
94
95
98
85
93
95
92
Overall, the communities generally felt that the project activities have benefited them in a variety
of ways, including increasing their self-reliance, ability to deal with crisis and physical dangers,
security of property knowledge about DRM and access to water and sanitation facilities. The
differences in responses across the four districts and the two sexes were minor with respect to
these issues. Communities mainly perceived these improvements due to their familiarity with the
establishment of the village committee, which they felt was a huge boon for the whole village,
and the visible DRM construction work that had occurred in all the villages and to a lesser extent
the other software activities with which their familiarity was lower as seen earlier.
Community perceptions about project impact
Has ACF DRM work
increased your:
(Percentage responding yes)
Charsadda
Nowshera
Mardan
Lwr
Dir
Male
Female
96
98
97
92
94
98
98
98
100
90
94
98
98
98
97
78
94
91
Security of property
98
95
97
80
93
90
92
88
78
75
69
100
96
98
97
95
95
98
4. Project Monitoring
a) How suitable and effective were the M&E systems in place through the duration of the
project and how could these have been improved? What systems were put in place to
ensure that outputs provided were of the highest quality possible and were
acceptable to beneficiaries?
19
5. Project Sustainability
a) Were the construction material and masonry techniques applied appropriate (were
they disaster-resilient?) What alternatives would have been better?
Since there was no technical person on the evaluation team, the analysis of technical
construction quality undertaken as part of the evaluation was limited and was based on three
dimensions. Firstly, the external evaluator observed the construction quality visually for the
following common construction problems in all villages and only minor, occasional problems
were found:
Are there any cracks or plaster falls in the construction?
Have the fixtures and fittings (e.g., doors and windows) been fixed properly?
Dampness on walls/floor?
Is the toilet design ok?
Does the foundation look straight?
Are any hinges and bolts loose?
Secondly, the evaluator reviewed the construction-related documents. ACF has qualified
engineers within its DRM teams who had developed detailed Bills of Quantities for each
20
b) Evaluate whether the maintenance requirements of the structures were within the
capacity of the beneficiary users, if ACF did enough to reinforce these local
capacities. Evaluate the willingness of communities to maintain the infrastructure and
propose how community ownership could have been improved or reinforced.
The main mechanism used by ACF to ensure maintenance of both the software and hardware
work is the setting up of village committees. While in a few villages, the committees already
existed, in most villages the committees set up by ACF were the first experience of communities
with such committees. Committee members seemed motivated and keen to maintain the
committees even after ACFs withdrawal while communities saw the committees as an
extremely helpful form of social capital developed for them by ACF. So, the chances seem high
that most committees will survive even after the withdrawal of ACF and will maintain the
software and hardware work. However, given the high migration in some areas in KP, turnover
within committees could be high and it would be a test of their endurance whether villagers keep
refilling the vacancies. In this regard, some additional steps by ACF could increase the chances
of committee continuation. Firstly, while ACF has trained committees on DRM issues, it would
also be useful to give them some basic training on management, CBO operations and
development issues. Second, it would also be advisable for ACF to see whether there are other
international or local NGOs working long-term in these areas which could adopt the committees
after ACFs withdrawal. Third, it would also be helpful for ACF to link committees of nearby
villages with each other for mutual support, information sharing and learning during floods and
even normal times. Finally, it would be important to link these committees more strongly with
government structures, as discussed in the next section.
c) Evaluate whether links between VDMUs and authorities are sufficiently reinforced.
Evaluate the impact of the DRM training for local and district authorities. What were
the main issues/weaknesses and how could this have been improved? Were the local
disaster authorities (PDMA and DDMU) sufficiently involved at all levels of the
project? If not, in what aspects of the project could their involvement have been
improved?
ACF organized DRM trainings from relevant district-level departments in all four districts though
some of the training in Mardan was still outstanding at the time of the evaluation. The evaluator
21
6. Cross-Cutting Issues
a) How realistic and appropriate was the budget of the project? Was it respected?
The table above provides information on the original budget, actual % expenditure by October
2012 and expected % expenditure by project end. This information reveals that almost all major
cost budget lines are being respected and will be fully utilized by the end of the project with an
overall burn rate of 97%. However, there were some budget issues due to the exchange rate
fluctuations given that three currencies (Nok, USD and PKR) were involved. Overall, ACF lost
budget of around $100,000 due to the depreciation of the USD against the Nok despite the fact
that the PKR has also depreciated significantly against the USD. According to the ACF Pakistan
Finance team, this loss was covered by a budget modification where district-level contingency
stock items were dropped. Overall, the Finance team felt that the DRM team had done good
budget management which helped in the budget being respected.
Budget
(Nok)
% SPENT
(oct 12)
Estimated %
Spent , 31-1222
475,953
84%
98%
Expatriates
238,076
87%
98%
Local staff
237,877
82%
97%
4,900
4%
104%
Equipment Procurement
17,164
100%
100%
Equipment Hire
64,445
89%
108%
External Evaluation
20,000
0%
50%
Project Costs
597,098
76%
97%
Construction mitigation
458,165
83%
97%
67,380
47%
125%
Capacity building
71,553
62%
69%
107,772
88%
97%
1,287,333
80%
97%
115,860
80%
97%
1,403,193
80%
97%
Other Costs
TOTAL DIRECT COSTS
Indirect Costs (9%)
TOTAL COSTS
b) Were ACFs rules on procurement adhered to? Have concerns relating to a zero
tolerance on corruption policy been adequately observed in the project
implementation?
ACF has a whistle-blower policy and an anti-corruption policy to reduce the chances of
corruption in the projects. Moreover, the approval limits of the Country Office and field offices
are much lower than that seen by the evaluator in other agencies with a view to reducing the
chances of corruption. The ACF Pakistan Finance team also diligently works to minimize the
chances of corruption by having a zero-tolerance policy against corruption so much so that a
driver was fired for a few hundred rupees violation. The team also calls additional suppliers by
telephone even where the logistics and field teams have sent in the three mandatory quotations
in order to further minimize the chances of fraud. All these steps ensure strong financial due
diligence and the evaluator did not come across any reports of corruption within villages or field
offices. However, this due diligence did slow up procurement to some extent with some of the
delays mentioned earlier being related to delays in procurement, which in turn were also
exacerbated by the lack of clarity among staff on procurement rules. ACF held a team workshop
recently to smoothen out these issues.
c) What measures were taken to ensure a gender balance at all stages of the project
(assessment, design and implementation)? How could this process have been
improved?
KP is an extremely conservative environment even by Pakistani standards where womens
rights are low and it is very difficult for NGOs to work with women to enhance their rights due to
23
24
This chapter summarizes the main findings and conclusions from the last
chapter and provides recommendations for enhancing the quality of the project
further in the future along each dimension of improvement identified in the
conclusions section. The emphasis is on providing recommendations which
would be feasible within the difficult working environment faced by ACF in Pakistan.
1. Conclusions
a) Did the program reach the intended results and objectives? If not, what were the main
constraints faced by the organization and were they a consequence of poor quality of
the initial assessment, poor project design or poor implementation? Did the project
sufficiently identify and manage risk related to the project activities?
Overall project achiovements
Results and related indicators
Status at time of
evaluation
Done
Trained
but
variable
absorption of concepts
25
2. Recommendations
Targeting: Targeting of the most vulnerable is excellent in Charsadda and Nowshera but is
less accurate in Mardan and Dir. Mardan has structural issues as very few people were affected
during the 2010 floods. In Lower Dir, a large number of people were affected, so the problem is
more about ensuring more thoroughly that ACF is focusing on the most vulnerable areas. It is
recommended to undertake a more thorough needs and security assessment in Dir. In general,
ACF is advised to focus on districts and villages which are vulnerable to major floods. To
identify such areas, the following three criteria are suggested: River and drainage channels
mapping; Damage incurred during 2010 floods and UNDP One DRM project list of most
vulnerable districts. Consider Sindh for DRM work too since it has recently become the most
repeatedly struck province in Pakistan.
Number of villages: Review the possibility of increasing the number of villages in the next
phase by increasing the number of field staff, covering each village with only one hardware
construction activity and linking with other NGOs and government agencies to cover some of
the construction work that ACF cannot afford in its budget.
Selection of hardware activities: Use the prevention-mitigation-capacity-evacuationrescue-relief continuum of DRM activities presented in Chapter 3 to select hardware activities.
The contingency stocks are an important hardware input given their relatively low cost and the
fact that they cover three categories in the continuum even though they are the three bottommost categories. Select other hardware construction activities from the highest possible
category of this continuum which is relevant and affordable. For example, wherever possible
26
Monitoring and accountability: Develop formal monitoring plans which clearly specify the
role for all relevant staff in the projects monitoring, including the frequency, modality, project
dimension and indicators for each relevant ACF staff. More importantly, the plan would also
specify how the information coming from the monitoring done by each staff will be analyzed and
summarized (preferably through a software-based monitoring application) and then fed to
progressively higher levels of the ACF Pakistan team, terminating with the Country Coordination
Team and what decisions and follow-up each level would undertake to ensure that the project
achieves its objectives on time. The presence of such a formal plan would make it much easier
to ensure timely achievement of objectives and avoid slippages. Also institute strong and
responsive accountability measures in future projects.
27
28
APPENDIX
1. Damage in KP from 2010 Floods
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
District
Abbottabad
Bannu
Battagram
Bunair
Charsadda
Chitral
D.I.Khan
Dir Lower
Dir Upper
Hangu
Haripur
Karak
Kohat
Kohistan
Lakki
Malakand
Mansehra
Mardan
Nowshera
Peshawar
Shangla
Swabi
Swat
Tank
Grand Total
Total_Population
Total_
UCs
1169904
971930
451340
738496
1492939
465075
1234706
1131676
753313
459275
1007960
622919
774318
684004
715139
660046
1431208
2123149
1174961
2860402
632670
1494583
1834756
349373
25234142
Affected_UCs
Affected_Population
HH_Damage
Aftec_pop_pec
51
49
20
27
49
24
47
37
28
19
45
21
32
38
33
28
59
75
47
92
28
56
65
16
49
9
24
34
12
26
7
14
19
42
21
32
38
26
6
12
43
27
16
7
11
42
16
54,473
10,416
5,614
502,732
69,164
394,608
180,686
210,498
45,841
56,646
50,935
38,716
464,333
28,092
45,086
22,870
19,992
499,818
237,068
83,649
15,389
634,654
148,890
7,782
1,488
802
71,819
9,881
56,373
25,812
30,071
6,549
8,092
7,276
5,531
66,333
4,013
6,441
3,267
2,856
71,403
33,867
11,950
2,198
90,665
21,270
0
6
2
1
34
15
32
16
28
10
6
8
5
68
4
7
2
1
43
8
13
1
35
43
986
533
3820170
545739
16%
2. Scoring Matrix
Criteria
Impact
Rating (1
Rationale
low, 5 high)
4 The data in chapter 3 from household interviews clearly
shows that over 90% of the respondents felt that the project
helped improve their resilience due to the committees set up
and the construction work. These aspects include:
Ability to stand on own feet
Ability to deal with crisis
Safety from physical dangers
29
Sustainability
Coherence
Coverage
Relevance
Effectiveness
Efficiency
3. Acronyms
BOQ
CBDRM
CBO
CDPM
DAC
DDMA
DRM
EWS
FGD
IDPs
KPK
NDMA
PCVA
RNE
UC
UNDP
VDMU
Bill of Quantities
Community-based Disaster Risk Management
Community-based Organization
Center for Disaster Prevention and Management
Development Assistance Committee
District Disaster Management Authority
Disaster Risk Management
Early Warning System
Focus Group Discussion
Internally Displaced Persons
Khyber-Pakhtunkhwa Province
National Disaster Management Authority
Participatory Community Vulnerability Analysis
Royal Norwegian Embassy
Union Council
United Nations Development Program
Village Disaster Management Unit
4. List of Interviews
Noor-Ul Amin
Abigail Chatagnon
Waheed-ul Haq
Dildar Hussain
Dr. Amir N Khan
Mr. Zahoor Khan
33