Escolar Documentos
Profissional Documentos
Cultura Documentos
2
CONTENTS
Introduction, 1
Background, 3
Findings, 4
Conclusions, 8
Suggested Further Research, 9
APPENDIX A Results of Field Tests, Observations, and Analyses, 9
APPENDIX B Comparison of Measured and Calculated Vertical Track Receptances, 17
APPENDIX C Wheel Set Test and Modeling Results, 22
APPENDIX D Results from Corrugation Initiation Model, 24
APPENDIX E Suggested Corrugation Mitigation Measures, 27
APPENDIX F Simple Economic Analysis of Potential Corrugation Mitigation Measures, 30
was essential not to have a rebound hit. The input force and
body response for each strike were recorded using a laptop
computer loaded with a commercial data collection
software package. The transfer function was then reviewed
and, if it looked reasonable, it was saved and the procedure
repeated so that at least 10 acceptable responses were
collected. The transfer functions were then averaged and
converted into a receptance.
Wheel set receptances were determined for radial,
lateral, and torsional excitation. The radial response was
determined by mounting an accelerometer on the wheel
tread and hitting the tread with the instrumented hammer at
a location opposite the accelerometer location. Lateral
response of the wheel set was determined by placing the
accelerometer on the face of the rim and striking the rim
laterally with the instrumented hammer. The accelerometer
was rotated through 90 degrees and mounted on the tread to
measure the torsional response of the wheel set. AC-clamp
was then attached to the rim to provide a location for
excitation by the hammer. In the frequency range 0 to 500
Hz, there was a fundamental torsional mode of the wheels
rotating out of phase with each other and a second torsional
mode where the wheels move in phase with each other but
out of phase with the traction motor drive gear.
Track receptances were found for both vertical and
lateral excitation. These were obtained by mounting an
accelerometer on the rail and hitting it with the
instrumented hammer in the appropriate place. Track
receptances were used to find the pad characteristics for
direct fixation track and the tie pad, as well as ballast
characteristics for concrete and wood tie track.
As far as the vehicle is concerned, any contribution to
rail corrugation is likely to come directly from the vehicle
unsprung mass. This includes primarily the wheel set, a
component from the traction motor, and in some cases, part
of the axle bearing boxes and brakes. The unsprung mass
becomes increasingly isolated from the rest of the vehicle
at frequencies above those of the truck on primary
suspension. This is the case for not only vertical motions
but also lateral and longitudinal motions of the wheel set.
As a result, in the frequency range where corrugations
occur, the remainder of the vehicle provides essentially
steady forces through the primary suspension. These forces
include the vertical load on the wheel set, a lateral force,
and yaw moment during curve negotiation, along with any
traction or braking torques. Thus, the dynamic modeling of
the vehicle's role in rail corrugations was confined to the
wheel set in this project.
Previous work on corrugation has produced several
theories. Of these, the most promising hypotheses are based
on the assumption that corrugation is essentially a periodic
wear process. When new rail is laid, the surface roughness
is broad band random with no predominant wavelengths
present. Any surface roughness can be represented as a
combination of sinusoidally varying components with
appropriate amplitude and phase relationships. This is the
fundamental concept of Fourier Analysis. Fluctuations will
occur in
4
the wheel/rail forces and creepages if a wheel set passes
over any one of these constant wavelength components in
the rail surface roughness. These fluctuations are
influenced by the dynamic characteristics of the wheel set
and the track at the resulting frequency. This frequency is
defined by the wavelength of the irregularity and the
velocity of the wheel set. The fluctuations in wheel/rail
force and creepage cause fluctuations in the rate of wear of
the rail surface, which will be at the same frequency as the
component of surface roughness. If the phase relationship
of the fluctuations in wear is such that the peaks of
maximum wear correspond to the troughs in the surface
irregularity, then the irregularity in the rail surface at that
wavelength will grow and corrugations will form at the
corresponding wavelength.
A corrugation initiation model was developed using
the AAR's NUCARS general rail vehicle dynamics
program based on the corrugation formation hypothesis
described above. Essential features of the model were as
follows:
FINDINGS
As a result of visits made to the various transit systems
(see Appendix A), it was observed that corrugations were
associated primarily with curves, particularly on the low
rail in curves, and with sites where vehicles were
accelerating or braking (i.e. , at sites where there would be
a significant longitudinal traction or creep force). The
general appearance of the corrugations was a rut lying
across the rail, the troughs of which were relatively dull,
while the peak was distinguished by a fine shiny line across
the railhead (Figure 1). It was common to find evidence of
longitudinal slip in the corrugation troughs. The only
exceptions to this were in locations where a restraining rail
was present or where rubber, booted ties (twin block tie
mounted in a resilient boot) were used. However, these
sites represented a relatively small percentage of the total
track length investigated. Consequently, it was apparent to
the research team that longitudinal slip and wear are
responsible for most corrugations on transit track. The
wavelength of the observed corrugations varied from 25 to
100 mm (1 to 4 in.), with a preponderance at around 50 mm
(2 in.).
The frequencies associated with the observed
corrugations were calculated from the measured
wavelengths by estimating the average operating speed of
the trains over the corrugated track section. Results showed
that most of the longitudinal corrugation frequencies are
clustered about the wheel set second torsional mode (Figure
2). Corrugations at one transit system where longer
wavelength corrugations were measured showed that the
corrugation frequency was similar to the P2 resonance
(wheel set bouncing on track stiffness). On another system,
the corrugation frequency was similar to the rail "pinnedpinned" bending mode (Figure 3).
Figure 4.
7
rim of each wheel was separated from the wheel web by a
circle of rubber pads.
Examination of the corrugations on the heavy rail
systems indicated that, apart from several sites with a
restraining rail and a site with rubber booted ties, the
corrugations were remarkably similar and the surface
markings were primarily longitudinal. Further, the
corrugation patterns were perpendicular to the longitudinal
axis of the rail, indicating that the principal direction of
relative wheel/rail motion during corrugation formation
was longitudinal. As a result, the wheel set model that was
developed included only torsional flexibilities.
The RTD corrugations were also perpendicular to the
longitudinal rail axis and showed longitudinal surface
markings. However, the frequency of these corrugationsabout 600 Hz-was considerably higher than those on the
heavy rail systems.
Receptance measurements showed that, for all of the
heavy rail systems, there was a fundamental wheel set
torsion mode in the range of 50 to 100 Hz and another
torsion mode was evident at about 300 to 350 Hz. At 300
Hz, the wheel set is almost certainly decoupled in torsion
from the motor armature by the contact flexibility of the
gear train. However, the rotational inertia of the final drive
gear is rigidly attached to the axle shaft approximately onethird the distance between the wheels. A model of wheel
set torsional behavior was developed using NUCARS
(Figure 5).
Wheel set drawings of a typical axle shaft and wheel
were analyzed to determine shaft stiffness and mass, as
well as wheel rotational inertia about the wheel set axis of
rotation. In addition, an estimated rotational inertia was
used for the final drive gear. The model incorporated the
rotational degrees of freedom of the two wheels and the
final drive gear connected by the torsional stiffness of the
axle shaft. All of the heavy rail systems used basically the
same traction system. Their wheel set and primary
suspension arrangements were of the following types:
Figure 5.
sets.
CONCLUSIONS
A combination of field observations, measurements,
and computer modeling has been used to characterize the
types of rail corrugation occurring on U. S. transit system
track. On the Sacramento RTD, the only light rail system
investigated, a type of corrugation was found that was
different from anything seen at the heavy rail systems. This
type of corrugation occurred at all RTD sites and had a
relatively short wavelength with the appearance of the socalled "roaring rail" corrugations. However, several
different corrugation mechanisms were found at the heavy
rail sites; these could be categorized as follows:
9
of addressing this type of corrugation. Reducing
longitudinal forces resulting from traction and braking
would involve decreasing the current maximum
acceleration and stopping rates. This would almost
certainly be unacceptable to transit agencies.
This leaves the following possibilities for alleviating
the development of Type 2 corrugations:
APPENDIX A
RESULTS OF FIELD TESTS, OBSERVATIONS, AND
ANALYSES
TEST SITES AND GENERAL OBSERVATIONS
The general comments and observations made in this
appendix derive largely from conversations with the transit
system personnel who assisted the AAR measuring team
and selected the measuring sites. Quantitative
measurements have not been made to check statements
regarding matters such as the prevalence of corrugation on
different types of track form.
10
TABLE A-1 CTA
characteristics
track
site
and
corrugation
11
Lubrication at MTA is primarily by solid lubricant
sticks on the vehicles. This is supplemented by manual
greasing of the high rail only in severe curves. Manual
greasing is undertaken weekly by spreading about a 0.3-mlong bead of grease every 30.5 m; more frequent or more
generous greasing can cause problems with wheel slip.
There is one in-track lubricator, near some switches at
Johns Hopkins Station.
The track at MTA is almost entirely of 115RE rail
with a 0.76-m tie or fastening spacing. Sites 1 and 2 are on
adjacent concrete viaducts with different track forms on the
same 1,550-m radius. At the first site, there are Hixon
direct fixation fasteners at a spacing of 0.91 m; at the
second site, there are monoblock concrete ties in ballast
with a spacing of 0.76 m. The corrugation wavelengths at
the two sites were very different-70 mm at the first site and
28 mm at the second. Corrugation ran continuously on the
high rail through the first site, and from about 10 m from
the end of the bridge on the low rail (Figure A-5). The
corrugation differs in appearance from that of the
corrugation on CTA, for example, and is apparent more
from discontinuities in the martensitic white phase on the
railhead, rather than from there being thin shiny bands
lying fully across the railhead. Nevertheless, such marks as
did exist on the railhead were primarily longitudinal.
Corrugation at Site 2 was less pronounced.
The third measuring site at MTA is on twin block
concrete ties mounted in resilient boots. This track form on
the MTA has been associated by Ahlbeck and Daniels (2)
with a particular type of corrugation arising in part because
of there being lightly damped resonances of the concrete
blocks and the resilient boots, giving rise to the high
amplitude of response to lateral excitation at the railhead.
The corrugation noted at Site 3 had a rather scalloped
appearance (Figure A-6) which differs significantly from
that of the corrugation on CTA- However, this appearance
is typical of corrugation on booted ties (2, 3).
The fourth site at MTA is only a few chains from the
third site on the same track, but the corrugations here were
of significantly different appearance, with much more
evidence of longitudinal slip in the corrugation troughs
(Figure A-7). The track here is, however, laid on direct
fixation fasteners. This is consistent with the type of
corrugation at Site 3 being associated with the booted-tie
track form. Corrugation wavelengths differed slightly at the
two sites--71 mm at Site 3 and 53 mm at Site 4. The
corrugation at Site 4 is strikingly similar in appearance to
that seen at CTA (Figures A-1 through A-4).
Corrugation at Sites 5 and 6 at MTA was similar in
appearance to that at Site 4. At Site 6, which was on the
approach to Johns Hopkins Station, the average wavelength
was 75 mm, but decreased closer to the station. This is
consistent with the corrugation being formed by a constant
frequency phenomenon, with a wavelength which
accordingly decreases as the vehicle speed decreases.
12
TABLE A-2 MTA track site and corrugation characteristics
Figure A-5.
Figure A-7.
13
TABLE A-3 WMATA track site and corrugation characteristics
Figure A-8.
14
TABLE A-4 BART track site and corrugation characteristics
15
TABLE A-5 RTD track site and corrugation characteristics
16
17
2. Ahlbeck, D.R and Daniels, L.E. "Investigation of Rail
Corrugations on the Baltimore Metro." Wear 144, pp. 197210, 1991.
3. Daniels, L.D. "Rail Transit Corrugations, Final
Report"
FTA-MD-06-0141-93-1,
Federal
Transit
Administration, U.S. Department of Transportation,
Washington, DC, 1993.
APPENDIX B
COMPARISON OF MEASURED AND
CALCULATED VERTICAL TRACK
RECEPTANCES
The measured track receptances were determined
using an impulsive excitation with an instrumented
hammer. Track receptances were calculated by applying inphase swept sinewave vertical forces applied to both rails at
the longitudinal midpoint. Forcing point receptances were
then calculated using the same technique as for the hammer
blows. This process used Fourier Transform techniques.
Track sup.
18
TABLE B-1 Direct fixation track characteristics
Figure B-2 Measured vertical track receptance -RTD Site 5 (Wood ties in ballast, loaded)
19
Figure B-3 Measurement vertical track receptance-RTD Site 2 (Wood in ballast, unloaded)
CONCRETE TIE BALLASTED TRACK
Two sites with concrete tie ballasted track were
measured-one at MTA and the other at BART. As a vehicle
was not available to load the track, the ballast stiffness and
damping in particular are probably not representative of
those under a vehicle. Figure B-4 provides a comparison of
the track model and experimental receptance for this case
and Table B-3 shows the track characteristics.
BOOTED TIE TRACK
Only one example of a booted tie system was
encountered (at MTA) during the track measurements.
Figure B-5 shows a comparison of the track model and
experimental
EMBEDDED RAIL
Embedded rails are usually only found on light rail or
streetcar systems. The only system of this type visited was
RTD. The track construction is actually wood tie track with
asphalt laid over the track up to the height of the railhead.
One example of this type of track was measured and Figure
B-6 shows the measured track receptance compared with
the track model. Table B-5 shows the track characteristics.
The tie spacing is not known because the ties are not
visible. However, for the purposes of the analysis, the ties
are presumed to be at the same 0.61-m spacing as the other
wood tie track at RTD.
20
21
TABLE B-4 Booted tie track characteristics
Figure B-6.
22
TORSIONAL EXCITATION
RADIAL EXCITATION
Figure C-1.
response.
APPENDIX C
WHEEL SET TEST AND MODELING RESULTS
BART
powered
wheel
Figure C-2.
sets.
set
23
arrangements at the other properties all have inboard
bearings with a cylindrical rubber bushing forming the
primary suspension. As a result, the wheel sets in CTA and
RTD have higher effective radial wheel masses at high
frequency than those at the other properties. The
fundamental axle bending frequencies are very similar,
except for RTD, which is somewhat lower as a result of a
significantly smaller diameter axle. This is a direct result of
the lower axle load of this light rail vehicle.
LATERAL EXCITATION
Figure C-4.
Figure C-5.
set.
Figure C-6.
Figure C-7.
24
TABLE C-3 Heavy rail wheel set lateral characteristics
REFERENCES
1.
APPENDIX D
transfer
25
transfer
transfer
transfer
26
force/irregularity
VARIATION
VELOCITY
ROTATIONAL
IN
WHEEL
SET
wear/irregularity
rail wear are proportional to the work done. Work done per
unit distance traveled along the track is equal to the sum of
the longitudinal force multiplied by the longitudinal
slippage and the lateral force multiplied by the lateral
slippage.
In this particular case, each wheel is subject primarily
to longitudinal forces due to tractive effort or to steering
forces in curves. Accordingly, contributions to rail surface
wear come almost entirely from longitudinal slippage.
Figure D-8 shows the magnitude of the transfer function of
wheel wear with respect to track irregularity.
Figure D-9 indicates the real part of the right wheel
wear to track irregularity transfer function. When the real
27
APPENDIX E
SUGGESTED CORRUGATION MITIGATION
MEASURES
TREATMENTS PERTAINING TO THE TRACK
Treatments for Existing or New Track
REFERENCES
1.
2.
28
Type 4 corrugation). There is also good reason to believe
that, because resilient rail pads reduce vertical dynamic
loading, they would also alleviate all types of corrugation
whose development is exacerbated by vertical dynamic
loading (e.g., corrugation arising from the pinned-pinned
resonance/ anti-resonance [Type 5 corrugation]).
A treatment which has been demonstrably successful
in reducing corrugation on the low rail in curves is to
lubricate the gage face of the high rail. Indeed, this
treatment is probably the singular most effective and most
widely adopted treatment of corrugation in curves. Not
only has its effectiveness been documented (1, 2, 3), but
also the authors are aware of work which has demonstrated
significant reduction in corrugation in the S-Bahn system in
Copenhagen and in an underground tramway in Tokyo
largely as a result of providing adequate high rail
lubrication. Although the reasons why this treatment is
effective are not entirely clear, the effectiveness of gage
face lubrication has been demonstrated sufficiently
compelling in practice for it to be plain that further
examination of the reasons is required. One possibility is
that lubricant on the gage face is carried over onto the
railhead, with a consequent reduction in railhead friction.
The damage mechanism for all types of corrugation
described here is wear, with the areas which become
corrugation troughs worn more rapidly than the peaks.
Because the wear rate can be reduced significantly using
head-hardened rails, the adoption of such rails should, ipso
facto, reduce corrugation formation. It would be expensive
and difficult commercially to justify premature replacement
of rails, even in corrugation-prone areas, with headhardened rails. However, if the rails are to be replaced in
such areas during routine maintenance, it is highly likely
that their replacement with head-hardened rails would be
cost-effective in view of the small premium in the cost of
such rails. Headhardened rails have been installed in some
curves of the S-Bahn system in Copenhagen and have
brought sufficient reduction in the rate of corrugation
formation for the railway system to believe that this is a
useful treatment. It would certainly be advisable to install
head-hardened rails in curves: on the low rail these will
reduce the rate of corrugation formation, while in the high
rail they will bring about a reduction in wear.
For Site 2 at BART, a very pronounced corrugation
occurred which was associated with lateral resonance of the
wheel set. This was apparently excited in some fashion by
the presence of a guard rail, whereas at an adjacent site
where there was no guard rail and only a slightly greater
curve radius, there was no such pronounced corrugation. It
would accordingly be reasonable to remove the guard rail
from Site 2, grind through the site to remove existing
corrugation, and then monitor the track periodically to
determine whether the severe corrugation recurred or
whether a different, less pronounced type of corrugation
occurred.
There are two further treatments which should
alleviate corrugation in the longer term. The first of these is
the use of
29
TABLE E-1 Treatments of corrugation involving changes to track form
there
are
many
treatments
involving
30
TABLE E-2 Treatments of corrugation involving changes to vehicles
REFERENCES
1.
2.
3.
4.
CONCLUSIONS
APPENDIX F
Various treatments of corrugation have been identified
which could be implemented by making changes to either
the track or the vehicles. Whereas most track-form-oriented
treatments could be adopted on existing track, most
treatments involving changes to vehicles could be
implemented satisfactorily only on new vehicles. The
principal exception to this is the novel treatment proposed
by the research team of attaching a tuned torsional dynamic
vibration absorber to the driven axles of a vehicle. The
principal objective of such an absorber would be to
attenuate and give damping in the second torsional mode of
the wheel sets.
Most track-form-oriented changes have been
implemented by transit systems interested in reducing the
costs of corrugation mitigation by regular maintenance
grinding; however, very little information is available
regarding the costs and benefits of these changes.
Nevertheless, some changes made by one or more transit
systems show promise. Considerable research would be
required in order to under-
31
TABLE F-1 Measures for existing track
32
General
1.
2.
3.
4.
5.
6.
2.
3.
Profile Grinding
4.
1.
2.
3.
4.
5.
6.
7.
1.
1.
2.
3.
4.
2.
3.
4.
5.
6.
Head-Hardened Rail
3.
33
Again, because of the unique characteristics of individual
transit systems, the assumptions were made in order to
provide a generic assessment of cost orders of magnitude.
The sources of the assumptions vary from surveys of
railway equipment suppliers, surveys of railway
maintenance contractors, surveys of individual railroads,
and
documented
industry
experience
to
professional/technical judgment. As can be expected, the
costs and efficacy of individual products or techniques
varies depending on whom one speaks with. In such cases,
compromises are made in an attempt to develop reasonable
assumptions without bias to any one railway company or
supplier.
Individual mitigation measures require either initial
costs, periodic costs, incremental costs, non-periodic
interim costs, or all of the above. To provide an "annual
cost" assessment, the following conventions apply:
Several of the mitigation measures are too designspecific to be able to assess the cost of order-ofmagnitude data within any reasonable degree. These
measures are indicated in the following tables with the
words "design-specific." In addition, some of the
measures cannot be economically assessed until
further work is carried out. These measures are
indicated in the tables with a question mark.