Approved by:

(Signature)

Hazard Identification And Risk Assessment


Reviewed by :Jaypal Solanki
______
Review Date :02 Feb 2015__
Next review :01 Feb 2016___

Business Unit: _____CDT Division_____________________________________


Division/Department/Location:_______CDT Division______________________

Hazard Identification (HI)


No

Area / Activity / Process /


Machine / Material

Risk Assessment (RA)


Hazard

Oil spillage causing


tripping hazard

Noise Hazard

Equipment Preparation
(Servicing of Engine/Water
pumps Gearbox changing
of engine/gear oil)

Bodily injuries

Noise induced
deafness

Pinch point &


Mechanical
Hazard

Cuts & bruises

Environment
Hazard - oil
spill to the
drain ways

Contaminate
waterways

Human FactorLack of focus


and
competency
resulting in
accident

F-SP-HSE06-01 Rev. 03

Possible injury/
Ill-health

Bodily injuries/
Noise induced
deafness/ Cuts
& bruises/
Contaminate
waterways

Existing Risk Controls

Wear safety shoe


Use oil absorbent
rags to clean away
the spill oil
Use oil tray to contain
the leak
Wear ear plugs or
mufflers
Exhaust silencer
installed
Staffs are advised to
stay focus
Staffs attended inhouse training and
have hand-on
experience onsite
Wear gloves where
applicable
Have to use a suitable
container to contain
the oil for transferring
to storage drum
Health & Safety brief
performed prior to
commencement of job
Only competent staffs
are allowed perform
the task

Name: Swapnil Patil


Date: 02 Feb 2015

Risk Control (RC)


S

Risk
level

4
Low

All crew

4
Low

All crew

12
Medium

All crew

4
Low

All crew

24
Medium

Project
Supervisor

Issue date: July 14, 2011

Additional Controls

Risk
Level

Responsible
person

Remarks

Page 1 of 18

Approved by:
(Signature)

Hazard Identification And Risk Assessment


Reviewed by :Jaypal Solanki
______
Review Date :02 Feb 2015__
Next review :01 Feb 2016___

Business Unit: _____CDT Division_____________________________________


Division/Department/Location:_______CDT Division______________________

Hazard Identification (HI)


No

Area / Activity / Process /


Machine / Material

Risk Assessment (RA)


Hazard

Slipping of
hand tool due
to oiliness and
cost hand
injury

Pinch point &


Mechanical
Hazard

Equipment Preparation
(Servicing of Engine
changing of oil filters)

Environment
Hazard - oil
spill to the
drain ways

Human FactorLack of focus


and
competency
resulting in
accident

Equipment Preparation
(Test running of water
F-SP-HSE06-01 Rev. 03

Noise Hazard
due to engine

Possible injury/
Ill-health

Existing Risk Controls

Need to remove the


oil from the surface of
the filter so that it will
Sprains /bruises
have a good grib.
Wear proper PPE
(cotton glove)

Cuts & bruises

Contaminate
waterways

Staffs are advised to


stay focus
Staffs attended inhouse training and
have hand-on
experience onsite
Wear gloves where
applicable
Use oil absorbent
rags to clean away
the spill oil & dispose
stain rag appropriately

Bodily injuries/
Cuts & bruises/
Contaminate

waterways

Noise induced
deafness

Health & Safety brief


performed prior to
commencement of job
Only competent staffs
are allowed perform
the task

Wear ear plugs or


mufflers

Name: Swapnil Patil


Date: 02 Feb 2015

Risk Control (RC)


S

Risk
level

8
Low

All crew

8
Low

All crew

4
Low

All crew

12
Medium

Project
Supervisor

4
Low

All crew

Issue date: July 14, 2011

Additional Controls

Risk
Level

Responsible
person

Remarks

Page 2 of 18

Approved by:
(Signature)

Hazard Identification And Risk Assessment


Reviewed by :Jaypal Solanki
______
Review Date :02 Feb 2015__
Next review :01 Feb 2016___

Business Unit: _____CDT Division_____________________________________


Division/Department/Location:_______CDT Division______________________

Hazard Identification (HI)


No

Area / Activity / Process /


Machine / Material

pump)

Risk Assessment (RA)


Hazard

Pinch point &


Mechanical
Hazard
Human FactorLack of focus
and
competency
resulting in
accident

F-SP-HSE06-01 Rev. 03

Existing Risk Controls

Risk Control (RC)


Risk
level

Additional Controls

Risk
Level

Responsible
person

8
Low

All crew

12
Medium

Project
Supervisor

4
Low

All crew

24
Medium

All crew

Remarks

running

Slip & Trip


hazard due to
water leakage

Mobilisation/demobilisation
from yard to & fro client
site/ lifting of pigging
machine to trailer

Possible injury/
Ill-health

Name: Swapnil Patil


Date: 02 Feb 2015

Bodily injuries

Cuts & bruises

Wear safety shoe


Use water absorbent
mat or rags to clean
away the water
leakage
Staffs are advised to
stay focus
Wear gloves where
applicable

Health & Safety brief


Noise induced
performed prior to
deafness/ Bodily
commencement of job
injuries/ Cuts &
Only competent staffs
bruises/
are allowed perform
Contaminate
the task
waterways
Staff are to ensure the
hoses are well
secured
To ensure whip
checks are connected
They are instructed to
maintain a safe
distance when system
is pressurised

Whipping
reaction from
pressurised
hose may
cause injuries

Bodily injuries

Crane
dropping
Machine
container to

Equipment and Ensure routine


property
maintenance is
damage
carried out by crane

Issue date: July 14, 2011

24
Medium

All crew

Page 3 of 18

Approved by:
(Signature)

Hazard Identification And Risk Assessment


Reviewed by :Jaypal Solanki
______
Review Date :02 Feb 2015__
Next review :01 Feb 2016___

Business Unit: _____CDT Division_____________________________________


Division/Department/Location:_______CDT Division______________________

Hazard Identification (HI)


No

Area / Activity / Process /


Machine / Material

Risk Assessment (RA)


Hazard

Possible injury/
Ill-health

Existing Risk Controls

the ground

Human Factor
lack of
competency
and
coordination
error

Mobilisation/demobilisation
from yard to & fro client
site/ crane and trailer
driving in/out the yard

F-SP-HSE06-01 Rev. 03

Crane/trailer
can damage
equipment or
injuring
personnel
while driven
Pinch Point
Hazard while
mobilising &

Bodily injuries

Damage to
equipment or
injuring
personnel

Cuts & bruises

Name: Swapnil Patil


Date: 02 Feb 2015

Risk Control (RC)


S

Risk
level

Additional Controls

16
Medium

Project
Supervisor

16
Medium

Crane
operator

8
Low

All crew

Risk
Level

Responsible
person

Remarks

contractor by doing a
spot check on his
equipments
Check the physical
condition of the lifting
slings and lugs
Barricade off area of
operation
Ensure every part of
Machine container is
well secured prior to
lifting operation
Control the movement
of the container
machine via ropes
while it sling in the air

Check the crane


driver licence to
ensure he is a
qualified operator
Our staff are to
discuss and confirm
the way the whole
process should be
handled prior to
commencement of job
All traffic rules must
be followed strictly.
Brief the drivers
properly
Staffs are advised to
stay focus
Wear gloves where

Issue date: July 14, 2011

Page 4 of 18

Approved by:
(Signature)

Hazard Identification And Risk Assessment


Reviewed by :Jaypal Solanki
______
Review Date :02 Feb 2015__
Next review :01 Feb 2016

Business Unit: _____CDT Division_____________________________________


Division/Department/Location:_______CDT Division______________________

Hazard Identification (HI)


No

Area / Activity / Process /


Machine / Material

Risk Assessment (RA)


Hazard

Possible injury/
Ill-health

Existing Risk Controls

demobilising
from crane &
trailer

Name: Swapnil Patil


Date: 02 Feb 2015

Risk Control (RC)


S

Risk
level

Additional Controls

16
Medium

Driver &
project
Supervisors

16
Medium

Crane/
Trailer driver

8
Low

Lifting
Supervisor

8
Low

Lifting
Supervisor

Risk
Level

Responsible
person

Remarks

applicable

Human Factor
lack of
competency
and
coordination
error

Damage to
equipment /
Cuts & bruises

Crane/trailer
movement can
damage plant
equipment and
injuring person

Damage to
equipment or
injuring
personnel

Drivers must have


applicable licences
Our staff are to
discuss and confirm
the way the whole
process should be
handled prior to
commencement of
job
All traffic rules in the
refinery must be
followed strictly.
Drivers must have
applicable licences.

Mobilise/demobilise
equipment in & out job
site/driving to site/lifting
operation

Equipment or
material falling
from height
causing injury
to personnel or
damage to
client property
and our
equipment

Crane topple
due to soft
ground or
overloading

F-SP-HSE06-01 Rev. 03

Bodily injuries /
damage to
equipments

damaging our
equipment &
client property

Lifting crew or
personal is to
barricade the lifting
zone and display
signage before lifting
work start.
All personal to keep
a safe distance and
not to walk under
any load.

Conduct lifting plan &


pre-lifting operation
checklist for any lifting
activities. Inform all
crew on the intention
of the load.
All drivers must be
extremely careful

Issue date: July 14, 2011

Page 5 of 18

Approved by:
(Signature)

Hazard Identification And Risk Assessment


Reviewed by :Jaypal Solanki
______
Review Date :02 Feb 2015__
Next review :01 Feb 2016

Business Unit: _____CDT Division_____________________________________


Division/Department/Location:_______CDT Division______________________

Hazard Identification (HI)


No

Area / Activity / Process /


Machine / Material

Risk Assessment (RA)


Hazard

Possible injury/
Ill-health

Existing Risk Controls

Pinch Point
Hazard

Human Factor
lack of
competency
and
coordination
error

F-SP-HSE06-01 Rev. 03

when operating their


crane and trailer in
the plant area
Area of operation
must be barricaded.
Ensure lifting safety
factor for crane is
specified to crane
provider before hiring
them.
Ensure lifting permit is
obtained before lifting.
Ensure crane and
lifting gear checklist is
checked before lifting.
Crane driver and
supervisor must
assess the ground
condition. Put metal
on ground to
distribute the load.
Must have good
knowledge of the
weight of the load
Staffs are advised to
stay focus
Wear gloves where
applicable

Cuts & bruises

Bodily injuries/
damaging our
equipment &
client property

Ensure qualified lifting


supervisors are at site
Our staff are to
discuss and confirm
the way the whole
process should be
handled prior to
commencement of job

Name: Swapnil Patil


Date: 02 Feb 2015

Risk Control (RC)


S

Risk
level

8
Low

All crew

16
Medium

Project
Supervisor &
Lifting
Supervisor

Issue date: July 14, 2011

Additional Controls

Risk
Level

Responsible
person

Remarks

Page 6 of 18

Approved by:
(Signature)

Hazard Identification And Risk Assessment


Reviewed by :Jaypal Solanki
______
Review Date :02 Feb 2015__
Next review :01 Feb 2016

Business Unit: _____CDT Division_____________________________________


Division/Department/Location:_______CDT Division______________________

Hazard Identification (HI)


No

Area / Activity / Process /


Machine / Material

Risk Assessment (RA)


Hazard

Hoses can
break loose
due to not
securing
properly
causing
property
damage and
bodily injury.
7

Rigging up of hoses to the


top of the platform

Frames where
the hoses are
secured may
break

Human Factor
lack of
knowledge

During entire pigging job


execution

Falling through
the opening in
the handrail
that is used to
access the cat
ladder.
Poor visibility
at night may
fall from
vertical ladder

F-SP-HSE06-01 Rev. 03

Possible injury/
Ill-health

Bodily injuries

Bodily injuries

Bodily injuries

Bodily injuries

Bodily injuries

Existing Risk Controls

Must ensure that


proper securing is
done through training.
Only competent staffs
are allowed perform
the task
Check and ensure the
frames are strong to
withstand the weight
and whipping action.
Inform client if any
deformities are
observed on the
frames
Staff must be trained
on the rope tying
methods
Always keep the
safety arm in the
horizontal position
when not in use.
Conduct safety talk
Mobile floodlights
must be used to
illuminate work area.
Always maintain a
3point contact while
accessing the ladder

Name: Swapnil Patil


Date: 02 Feb 2015

Risk Control (RC)


S

Risk
level

4
Low

Lifting
Supervisor

24
Medium

All crew

4
Low

Project
Supervisor

16
Medium

All crew

16
Medium

All crew

Issue date: July 14, 2011

Additional Controls

Risk
Level

Responsible
person

Remarks

Page 7 of 18

Approved by:
(Signature)

Hazard Identification And Risk Assessment


Reviewed by :Jaypal Solanki
______
Review Date :02 Feb 2015__
Next review :01 Feb 2016

Business Unit: _____CDT Division_____________________________________


Division/Department/Location:_______CDT Division______________________

Hazard Identification (HI)


No

Area / Activity / Process /


Machine / Material

Risk Assessment (RA)


Hazard

Possible injury/
Ill-health

Existing Risk Controls

Name: Swapnil Patil


Date: 02 Feb 2015

Risk Control (RC)


S

Risk
level

Additional Controls

16
Medium

4
Low

16
Medium

All crew

16
Medium

All crew

16
Medium

Project
Supervisor

Risk
Level

Responsible
person

Remarks

Conduct safety talk

Working during
dangerous
working
conditions,
getting hit by
lightning. Slip
and fall on wet
surface.
Unauthorised
people
entering area
of operation
Human Factor
- Accident
caused by miscommunication
between
operator and
the helpers

Fall from
height when
working on the
scaffolding
platform

Human factor
lack of focus
on assigned
task
F-SP-HSE06-01 Rev. 03

Fatal/ Bodily
injuries

Bodily injuries

Bodily injuries

Bodily injuries

Bodily injuries

Stop work during


dangerous weather
conditions

Barricade area of
operation
Place signboards
Must have a briefing
to all the personnel
onsite and ensure
they understand CDT
Furnace decoking
procedure
All working at height
above 1.8m from
ground level must don
safety harness
Must obtain Permit To
Work before start
work
Conduct safety talk
Must check the
scaffoldings validity
Health & Safety brief
performed prior to
commencement of job
Attended the in-house

Issue date: July 14, 2011

All crew

Page 8 of 18

Approved by:
(Signature)

Hazard Identification And Risk Assessment


Reviewed by :Jaypal Solanki
______
Review Date :02 Feb 2015__
Next review :01 Feb 2016

Business Unit: _____CDT Division_____________________________________


Division/Department/Location:_______CDT Division______________________

Hazard Identification (HI)


No

Area / Activity / Process /


Machine / Material

Risk Assessment (RA)


Hazard

Possible injury/
Ill-health

Existing Risk Controls

Name: Swapnil Patil


Date: 02 Feb 2015

Risk Control (RC)


S

Risk
level

Additional Controls

16
Medium

All crew

24
Medium

All crew

Risk
Level

Responsible
person

Remarks

SIC

Hazards
arising from
external
activities

Hoses may
burst and
cause injury to
personnel

F-SP-HSE06-01 Rev. 03

Bodily injuries

Bodily injuries

Receive all
information from client
on the expected
works that are
performed together
with our task and
keep our staff inform
of those.
Staff to ensure they
are vigilant at all times
and report any
abnormal activities
sighted at site
Stop work if sighted
unsafe activities
Perform physical
inspection on the
hoses prior to utilising
it
Always maintain a
safe distance from the
pressurised hose
Maintain
communication with
rest of the staff thru
walkie talkie and hand
signals
Alert and warn staff to
keep clear if needed
to increase pressure
on the pump

Issue date: July 14, 2011

Page 9 of 18

Approved by:
(Signature)

Hazard Identification And Risk Assessment


Reviewed by :Jaypal Solanki
______
Review Date :02 Feb 2015__
Next review :01 Feb 2016

Business Unit: _____CDT Division_____________________________________


Division/Department/Location:_______CDT Division______________________

Hazard Identification (HI)


No

Area / Activity / Process /


Machine / Material

Risk Assessment (RA)


Hazard

Hoses may
burst and
cause injury to
personnel
9

Bodily injuries

Process to unlodge pigg


when it is being stucked in
the heater
Human factorToo confident
behaviour &
lack of
knowledge

10

Possible injury/
Ill-health

Non-routine activits
(maintenance work)
Removing Water
pump/Gearbox/other
equipment from the
Pigging Container (using
Forklift)

F-SP-HSE06-01 Rev. 03

Forklift
damaging
other
equipment and
facilities

Bodily injuries

Bodily injuries/
damaging our
equipment &
client property

Injuring
personnel by
wrong
operation

Bodily injuries

Injuring
personnel
when dropping
load

Bodily injuries/
damaging our
equipment &
client property

Existing Risk Controls

barricade off area of


operation
inform client on the
situation & the action
we are taking before
start operation.
have to clear off other
interested parties
before start operation
Health & Safety brief
performed prior to
commencement of job
Only competent staffs
are allowed perform
the task
Driver must have
forklift license
Slow & careful lifting
with someone guiding
the driver.
Conduct toolbox
before starting lifting
operation
Driver must have
forklift license
Slow & careful lifting
with someone guiding
the driver
To ensure all staff
involved in the
operation are vigilant
To ensure staff
involves in the

Name: Swapnil Patil


Date: 02 Feb 2015

Risk Control (RC)


S

Risk
level

8
Low

All crew

24
Medium

Project
Supervisor

16
Medium

Forklift
Operator

16
Medium

Forklift
Operator

24
Medium

Forklift
Operator

Issue date: July 14, 2011

Additional Controls

Risk
Level

Responsible
person

Remarks

Page 10 of 18

Approved by:
(Signature)

Hazard Identification And Risk Assessment


Reviewed by :Jaypal Solanki
______
Review Date :02 Feb 2015__
Next review :01 Feb 2016___

Business Unit: _____CDT Division_____________________________________


Division/Department/Location:_______CDT Division______________________

Hazard Identification (HI)


No

Area / Activity / Process /


Machine / Material

Risk Assessment (RA)


Hazard

Possible injury/
Ill-health

Existing Risk Controls

Name: Swapnil Patil


Date: 02 Feb 2015

Risk Control (RC)


S

Risk
level

Additional Controls

24
Medium

Project
Supervisor

24
Medium

All crew

16
Medium

All crew

Risk
Level

Responsible
person

Remarks

operation a re
donning the
appropriate PPE

Human Factor
lack of focus
and
coordination
error

Hazards
arising from
external
activities

11

Non-routine activits
(maintenance work on job
site)
Removing Water
pump/Gearbox/other
equipment from the
Pigging Container (using
chainblock)

F-SP-HSE06-01 Rev. 03

Dropping load
- damaging
equipment &
injuring
personnel

Bodily injuries/
damaging our
equipment &
client property

Bodily injuries/
damaging our
equipment &
client property

Bodily injuries/
damaging our
equipment &
client property

Health & Safety brief


performed prior to
commencement of job
Our staff are to
discuss and confirm
the way the whole
process should be
handled prior to
commencement of job
Receive all
informations on the
expected works that
are performed at yard
by other contractors
and keep our staff
inform of those.
Staff to ensure they
are vigilant at all times
and report any
abnormal activities
sighted at site
Ensure chainblock is
hooked on a strong
point before lifting.
Ensure there is more
than one person
doing this lifting.
Ensure the correct
capacity chainblock is
utilized

Issue date: July 14, 2011

Page 11 of 18

Approved by:
(Signature)

Hazard Identification And Risk Assessment


Reviewed by :Jaypal Solanki
______
Review Date :02 Feb 2015__
Next review :01 Feb 2016

Business Unit: _____CDT Division_____________________________________


Division/Department/Location:_______CDT Division______________________

Hazard Identification (HI)


No

Area / Activity / Process /


Machine / Material

Risk Assessment (RA)


Hazard

Ergonomic
hazard (Heavy
load)

Pinch point
Hazards

Human Factorlack of focus &


knowledge

12

Non-routine activits
(maintenance work)
Using grinding power tool
during repair
activities/cleaning part
activity

F-SP-HSE06-01 Rev. 03

Electrical
hazard

Possible injury/
Ill-health

Body strains

Cuts & Bruises

Bodily injuries/
damaging our
equipment &
client property

Burns

Existing Risk Controls

Ensure correct
posture are used to
carry heavy items
Put up signs to
remind staff of correct
lifting posture
Staffs are advised to
stay focus
Wear gloves where
applicable
Health & Safety brief
performed prior to
commencement of job
Only the competent
staff are allowed to
choose the type of
chainblock for the
operation
Ensure electrical tool
has its inspection tag
updated before using.
Ensure hand is not
wet before using the
tool
Ensure the tool do not
get in contact with
water
Ensure proper PPE is
donned before start
work
Remind staff on
electric hazard via
safety meeting

Name: Swapnil Patil


Date: 02 Feb 2015

Risk Control (RC)


S

Risk
level

8
Low

All crew

16
Medium

All crew

16
Medium

Project
Supervisor

8
Low

All crew

Issue date: July 14, 2011

Additional Controls

Risk
Level

Responsible
person

Remarks

Page 12 of 18

Approved by:
(Signature)

Hazard Identification And Risk Assessment


Reviewed by :Jaypal Solanki
______
Review Date :02 Feb 2015__
Next review :01 Feb 2016

Business Unit: _____CDT Division_____________________________________


Division/Department/Location:_______CDT Division______________________

Hazard Identification (HI)


No

Area / Activity / Process /


Machine / Material

Risk Assessment (RA)


Hazard

Dust inhalant

Dismantling pipe fittings

F-SP-HSE06-01 Rev. 03

Respiratory
problems

Grinding disc
may break and
cause severe
injury

Cuts & Bruises

Chemical
contact (using
chemical for
cleaning)

Skin irritation

Hazards
arising from
external
activities

Bodily injuries

Human Factor
lack of focus

13

Possible injury/
Ill-health

Fire hazard
due to usage
of gas cutter to
expand the
tight fittings

Existing Risk Controls

Ensure proper PPE is


donned before start
work
Ensure there is proper
guard on the grinder
before using it
Work with extreme
care
Supervisor to conduct
safety talk before start
work
Ensure proper PPE is
donned before start
work
Supervisor to conduct
safety toolbox talk
before start work
Receive all
information on the
expected works that
are perfomed at yard.
Staff to ensure they
are vigilant at all times
while performing task

Burns/
Respiratory
Health & Safety brief
problems/ Cuts
performed prior to
& Bruises/ Skin
commencement of job
irritation/ Bodily
injuries
Use the appropriate
PPE
Adequate ventilation
Burns
provided
Perform physical
check on gas cutter

Name: Swapnil Patil


Date: 02 Feb 2015

Risk Control (RC)


S

Risk
level

8
Low

All crew

16
Medium

All crew

8
Low

All crew

16
Medium

All crew

16
Medium

Project
Supervisor

8
Low

All crew

Issue date: July 14, 2011

Additional Controls

Risk
Level

Responsible
person

Remarks

Page 13 of 18

Approved by:
(Signature)

Hazard Identification And Risk Assessment


Reviewed by :Jaypal Solanki
______
Review Date :02 Feb 2015__
Next review :01 Feb 2016

Business Unit: _____CDT Division_____________________________________


Division/Department/Location:_______CDT Division______________________

Hazard Identification (HI)


No

Area / Activity / Process /


Machine / Material

Risk Assessment (RA)


Hazard

Possible injury/
Ill-health

Existing Risk Controls

Name: Swapnil Patil


Date: 02 Feb 2015

Risk Control (RC)


S

Risk
level

Additional Controls

4
Low

All crew

8
Low

Project
Supervisor

8
Low

All crew

8
Low

All crew

16
Medium

All crew

8
Low

All crew

Risk
Level

Responsible
person

Remarks

equipment

14

15

16

Non-routine activits
(maintenance work)
Painting work

Awareness of the
emergency call points
such as fire assembly
area, Fire & emergency
control room number,
emergency telephone
points & etc

Placement of stowage
items

F-SP-HSE06-01 Rev. 03

Pinch point
hazard

Cuts & Bruises

Human factor
lack of focus

Burns/ Cuts &


Bruises

Chemical
contact
Toxic Fume
hazard

Human Factor
Lack of
knowledge

Pinch point
hazards

Skin Irritation

Respratory
problems

Burns / Fatal

Cuts & bruises

Staffs are advised to


stay focus
Wear gloves where
applicable
Health & Safety brief
performed prior to
commencement of job
Ensure proper PPE is
donned before start
work
Painting done in a
properly ventilated
space or outdoors
Collate all information
from client on
emergency response
prior to start of job
Disemminate the
information to all our
staff involved in the
job
Post the information
in prominent place so
that information can
be easily refered
when in need
Place all items neatly
Ensure all items are
kept at safe distance
away from operational
machinery

Issue date: July 14, 2011

Page 14 of 18

Approved by:
(Signature)

Hazard Identification And Risk Assessment


Reviewed by :Jaypal Solanki
______
Review Date :02 Feb 2015__
Next review :01 Feb 2016___

Business Unit: _____CDT Division_____________________________________


Division/Department/Location:_______CDT Division______________________

Hazard Identification (HI)


No

17

18

19

20

Area / Activity / Process /


Machine / Material

Communication between
DDT team members
during operation

Team member monitoring


the launcher at the top
level

Pressurising the hoses for


pigging operation

Temporary recruitment of
foreign General workers
from manpower agencies.

F-SP-HSE06-01 Rev. 03

Risk Assessment (RA)


Hazard

Human Factor
Lack of coordination

Physical
hazard Pig
can burst out
from luancher
if the launcher
cover isnt
closed
properly
Physical
hazard Hose
may burst due
to over
pressure or
due to wear &
tear

Human factor
Lack of
knowledge on
task

Possible injury/
Ill-health

Name: Swapnil Patil


Date: 02 Feb 2015

Risk Control (RC)


S

Risk
level

Bodily injuries

CDT requires to carry


2 walkie talkies for
communication
between DDT
operator and the staff
at the top of reactor
CDT team should be
trained on common
hand signals

16
Medium

All crew

Bodily injuries

Staff near to the


launcher should
maintain a safe
distance away from
the line of fire

8
Low

All crew

Bodily injuries/
damage to
equipments

Presure test on the


water hoses is
required to be
performed by staff
prior to deployment to
site

8
Low

All crew

Bodily injuries

Advise manpower
agencies to provide
all their deployed
workers to CR with
proper PPE
Employment agencies
to ensure the workers
know general safety
CDT Team to brief the
workers on process of
their activity and its
safety requirement

24
Medium

Project
Supervisor

Existing Risk Controls

Issue date: July 14, 2011

Additional Controls

Risk
Level

Responsible
person

Remarks

Page 15 of 18

Approved by:
(Signature)

Hazard Identification And Risk Assessment


Reviewed by :Jaypal Solanki
______
Review Date :02 Feb 2015__
Next review :01 Feb 2016

Business Unit: _____CDT Division_____________________________________


Division/Department/Location:_______CDT Division______________________

Hazard Identification (HI)

Risk Assessment (RA)

No

Area / Activity / Process /


Machine / Material

21

Boarding taxis at foreign


countries

Dangerous
driving by taxi
drivers

22

Toolbag being lowered


thru ropes from heights

Physical
hazard items
from the
toolbag can fall
down from
height if it isnt
properly
zipped or
secured to a
rope

23

Physically carrying the


heavy hoses from the
machines with bare hands

Ergonomic
hazard

24

Laying of hoses at
worksite

Trip & Fall


Hazard

25

During Entire Job Working at Height

F-SP-HSE06-01 Rev. 03

Hazard

Falling from
height

Possible injury/
Ill-health

Bodily injuries /
fatal

Existing Risk Controls

Brief the driver about


safe driving prior to
boarding his taxi

All toolbags must be


completedly zipped
prior to lowering
Ropes must be
secured tightly to
Bodily injuries /
toolbag sling before
fatal
lowering
Staff receiving the
toolbag at the bottom
of reactor to maintain
a safe distance away
from the line of fire
Utilise Chain Blocks
to lift the hoses
Body strains
Utilize sufficient
manpower to lift the
hoses
A frame warning
signage be posted at
Bodily injuries
the work area to warn
others of the trip & fall
hazard
All workers working
at height are trained
on how to use and
wear the safety
harness.
Housekeeping is
Fatality or Bodily
injuries
done accordingly to
prevent tripping
hazard.
Ensure the snap
hook is hooked to a
strong Anchorage

Name: Swapnil Patil


Date: 02 Feb 2015

Risk Control (RC)


S

Risk
level

24
Medium

All crew

8
Low

All crew

8
Low

All crew

8
Low

All crew

Issue date: July 14, 2011

24
Med

Additional Controls

All project
supervisors must
attend the MOM
Work at Height
for Supervisors
course
Goh SP, Tint
Zaw & Manny
have attended

Risk
Level

Responsible
person

Remarks

All crew

Page 16 of 18

Approved by:
(Signature)

Hazard Identification And Risk Assessment


Reviewed by :Jaypal Solanki
______
Review Date :02 Feb 2015__
Next review :01 Feb 2016

Business Unit: _____CDT Division_____________________________________


Division/Department/Location:_______CDT Division______________________

Hazard Identification (HI)


No

Area / Activity / Process /


Machine / Material

Risk Assessment (RA)


Hazard

Possible injury/
Ill-health

Existing Risk Controls

F-SP-HSE06-01 Rev. 03

Name: Swapnil Patil


Date: 02 Feb 2015

Risk Control (RC)


S

Risk
level

Additional Controls

Risk
Level

Responsible
person

Remarks

point eg 4 process
pipe or secured
scaffold pipe)
All workers put on
the appropriate
PPE(eg Safety
helmet with chin
strap, safety
harness) at areas
which has spelled for
such requirement.
Self retractable
Lanyard(SRL)be
utilized when working
at height which are
less than 5.6 meters
from the ground
Guardrails are
provided at work
areas where chances
of falling is evident
Ladders, fall
prevention and fall
protection
equipments& tools
are inspected prior to
use
Check on the
scaffoldings(7day)
validity status
Check the suitability
of safety harness
based on F-CRASHSE-04 Rev 00
Safety harrness
Lanyard Shock
Absorber Daily
Checklist
Issue date: July 14, 2011