Escolar Documentos
Profissional Documentos
Cultura Documentos
Abstract: The extensive restructuring process in the electric power industry has led to more demanding and different
usage of transmission grids irrespective of the designed limits. This has resulted in unanticipated congestion interfaces in
the regional transmission network. The system is however is not capable of withstanding the rapidly changing demands of
the competitive markets. Thus an efficient and sensible way of dealing with the congestion has become vital to maintain
the system reliability. This paper investigates the prediction of the optimal location and size of the Thyristor-Controlled
Series Capacitor (TCSC) so as to alleviate the congestion in a deregulated environment. The location of TCSC is identified
with the help of priority list based on the locational marginal price (LMP) difference between the buses. As LMP can be
easily calculated from the security constrained optimal power flow, this method reduces the computational difficulties.
Also the PSO algorithm fixes the optimal size of the TCSC which relieves the congestion thereby reduces the LMP and the
overall generation cost. The effectiveness of the proposed approach is tested in 6 bus and 30 bus systems under MATLAB
environment.
Keywords: Deregulated power systems, Thyristor-controlled series capacitor, Locational marginal price, Particle swarm
optimization, Congestion management.
approach to manage transmission line congestion for a
pool market model. FACTS devices like SVC and TCSC
I.
INTRODUCTION
were used to manage the function from single line
congestion case to three line congestion cases. The authors
have proved congestion cost was less after connecting
The restructuring process of the power industry
FACTS devices rather than without connecting. LMP
starts with the separation of the transmission activities
difference and congestion rent contribution methodologies
from the generation activities. The subsequent step was to
for locating series FACTS devices to manage congestion
introduce competition in generation activities, either
in deregulated electricity markets have been depicted in
through the creation of power pools, provision for direct
[4]. These methods were compared with sensitivity factor
bilateral transactions or bidding in the spot markets. On
method. The results proved that the best location of TCSC
the other hand, the transmission system having significant
was identified by proposed methods. The status of
economies of scale consequently had a tendency to
congestion after placing the TCSC was not addressed. In
become a monopoly. Thus it was felt necessary to
[5] an alleviation of overloads by redispatch of generators
introduce regulation in transmission so as to prevent it
with minimum rescheduling cost has been proposed. The
from overcharging for its services and to manage the
optimal rescheduling of active powers of generators was
congestion [1]. The condition where overloads in
selected based on the generator sensitivity to the congested
transmission lines or transformers occur is called
line, utilizing fuzzy adaptive bacterial foraging (FABF)
congestion. Congestion could prevent system operators
algorithm. In [6] particle swarm optimization based social
from dispatching additional power from a specific
welfare maximization and congestion management has
generator. Congestion may occur due to various reasons,
been presented. The congestions were managed by using
such as transmission line outages, generator outages,
rescheduling of generators. The participation of generators
changes in energy demand and uncoordinated transactions.
was selected using generator sensitivities to the power
Congestion may result in preventing new contracts,
flow on overloaded lines. In [7] the authors proposed a
infeasibility in existing and new contracts, additional
type of security-constrained OPF for minimizing total
outages and monopoly of prices in some regions of power
generation costs using FACTS devices. In [8] fuzzy
systems and damages to system components. Congestion
inference based generator active power rescheduling for
may be prevented by means of rights, reservations and
managing network congestion under normal and
congestion pricing. Also, it can be corrected by applying
contingency conditions has been discussed. The network
controls such as phase shifters, tap transformers, TCSC,
congestions were managed using counter flow information
redispatch of generation and load curtailment [2].
obtained from the tracing of network virtual flows due to
Several congestion management methods have
various sources. In [9] the authors proposed an optimal
been presented in the literature. In [3] the authors
congestion management approach in a deregulated
proposed a demand side based congestion management
ND
PGi
PL 0
(2)
Generator constraints
PGi, min PGi PGi, max
(3)
Dj
i 1
j 1
(4)
Sij Sij
(6)
(5)
max
(7)
The working range of TCSC is considered as follows.
(8)
0.8 X l X TCSC 0.2 X l
where
pi
x i pk 1
pk
Swarm
Influence
pk 1
PROBLEM FORMULATION
A. Objective Function
The objective of the proposed method is to minimize the
total generation cost. The problem is stated
mathematically as
(1)
Min
Ci ( PGi )
B j ( PDj )
PGi , PDj
NG
where, PGi and PDj are the active powers of pool generator
i with bid price Ci and pool load j with offer price Bj
respectively.
B. Problem constraints
Generation/load balance Equation
All Rights Reserved 2016 IJORAT
v i pk
Particle
Memory
Influence
x i pk
Current
Motion
Influence
Figure 1: Concept of modification of a searching point
by PSO
where,
searching
pk1
and
point,
v i pk current
velocity,
Vi (u 1) w Vi (u ) C1 rand ( ) ( pbesti Pi (u ) )
C2 rand ( ) ( gbesti Pi (u ) )
Pi (u 1) Pi (u ) Vi (u 1)
where
(9)
(10)
rand ( ) ( gbest i Pi (u ) )
th
is called swarm
must lie
in the range.
Vmin Vi (u ) Vmax
(11)
w wmin
w wmax max
iter max
iter
(12)
VS VR
sin
X
(13)
X eff (1 k ) X
(15)
Bus i
jBc
jBc
Bus
where
wmax Maximum
value
of
weighting
factor,
(TCSC)
Thyristor-controlled series capacitors (TCSC) are
connected in series with the lines. The effect of a TCSC on
the network can be seen as a controllable reactance
inserted in the related transmission line that compensates
for the inductive reactance of the line. This reduces the
transfer reactance between the buses to which the line is
All Rights Reserved 2016 IJORAT
V.
(17)
where
i Nodal price at bus i; ref Nodal price at the
SIMULATION RESULTS
VI.
LMP
($/MWhr)
Bus Number
LMP
($/MWhr)
12.4922
15.6741
11.5646
12.9389
11.8766
12.2062
LMP Difference
($/MWhr)
From i-j
LMP Difference
($/MWhr)
2-4
4.1095
5-6
0.7327
1-4
3.1819
2-6
0.6416
4-5
2.7352
1-5
0.4467
2-5
1.3743
3-6
0.3295
3-5
1.0623
2-3
0.3120
1-2
0.9276
From
i-j
without TCSC
MVA
limit
P
(MW)
Q
(MVAR)
From i-j
Reactance of TCSC
2-4
-0.0200
1-4
-0.1095
with TCSC
Status
P
(MW)
Q
(MVAR)
1-2
40
15.41
-9.58
-1.98
-1.21
1-4
60
33.95
22.50
34.69
32.63
1-5
40
27.86
12.80
17.29
14.41
2-3
40
0.29
-11.76
-0.93
-11.52
2-4
60
41.74
43.11
44.12
32.33
2-5
30
17.35
14.93
19.43
13.71
2-6
90
25.03
12.67
24.76
12.51
3-5
70
23.18
21.57
26.29
19.53
3-6
80
47.50
59.90
49.89
58.99
4-5
20
3.21
-4.71
6.32
-2.91
5-6
40
-0.90
-9.03
-3.01
-7.91
yes
Status
3245
3240
3235
3230
3225
10
20
30
40
50
60
70
80
90
100
Iteration Number
Figure 3 Generation cost convergence characteristics for the optimal TCSC size (6 bus system)
The LMP difference values between buses are
calculated and the priority list based on LMP differences is
shown in Table VI.
B. 30-Bus System Under Base Case Condition
The objective function in this case is to alleviate the
congestion in the network under base case conditions thereby
minimizing the total generation cost. Form the power flow
results of 30 bus system under base case before placing TCSC,
it is observed that the lines 6-8 and 25-27 get congested and
total generation cost of 576.89 $/h.
The locational marginal price (LMP) value of different
buses is shown in Table V.
LMP
($/MWhr)
Bus
Number
LMP
($/MWhr)
Bus
Number
LMP
($/MWhr)
3.6617
11
3.8232
21
3.8540
3.6891
12
3.8100
22
3.8425
3.7542
13
3.8100
23
3.8133
3.7709
14
3.8677
24
3.8844
3.7444
15
3.8561
25
3.9320
3.7791
16
3.8488
26
3.9987
3.8008
17
3.8625
27
3.9157
5.3827
18
3.9112
28
4.1058
3.8232
19
3.9262
29
3.9664
10
3.8462
20
3.9100
30
4.0508
LMP Difference
($/MWhr)
From i-j
LMP Difference
($/MWhr)
6-8
1.6037
15-23
0.0428
8-28
1.2769
22-24
0.0419
6-28
0.3267
4-12
0.0391
28-27
0.1901
12-16
27-30
0.1351
1-3
Line
limit
1-2
1-3
0.0388
1-2
0.0274
0.0925
9-10
0.0230
2-6
0.0900
6-7
29-30
0.0844
3-4
P
(MW)
Q
(MVAR)
130
21.04
130
20.50
2-4
65
3-4
2-5
0.0217
0.0167
2-4
0.0818
25-27
0.0164
23-24
0.0711
10-17
0.0163
with TCSC
P
(MW)
Q
(MVAR)
-2.34
22.44
-3.82
-3.10
21.35
2.49
18.63
-5.85
20.01
1.89
130
17.88
-3.22
18.73
2.65
130
14.36
-0.69
15.19
3.01
2-6
65
21.66
-4.21
23.41
4.44
4-6
90
17.58
5.68
19.64
11.64
5-7
70
14.25
0.96
15.08
4.92
6-7
130
8.70
8.46
6-8
32
23.82
21.37
6-9
65
7.27
Status
7.86
4.24
20.96
22.22
-8.27
8.28
-3.20
yes
6-10
0.0671
19-20
0.0162
25-26
0.0666
18-19
0.0151
6-10
32
4.15
-4.73
4.73
-1.83
10-20
0.0638
16-17
0.0137
9-11
65
12-14
0.0577
14-15
0.0116
9-10
65
7.27
-8.54
8.28
-3.35
65
11.06
-15.24
11.24
-7.31
5-7
0.0565
21-22
0.0114
4-12
2-5
0.0553
4-6
0.0082
12-13
65
-16.20
-34.01
-17.34
-25.36
15-18
0.0551
10-21
0.0078
12-14
32
4.68
2.08
4.89
2.14
12-15
32
6.07
3.18
6.84
3.55
12-16
32
5.31
5.04
5.65
4.42
14-15
16
-1.55
0.41
-1.34
0.48
16-17
16
1.76
3.14
2.10
2.53
15-18
16
7.20
3.75
7.26
3.19
18-19
16
3.93
2.70
4.0
2.16
19-20
32
-5.58
-0.73
-5.51
-1.26
10-20
32
7.85
1.58
7.78
2.11
10-17
32
7.27
2.73
6.92
3.34
10-21
32
-4.43
-11.56
-3.19
-7.10
10-22
32
-5.06
-8.39
-4.29
-5.75
27-29
0.0507
10-22
0.0037
24-25
0.0476
12-13
12-15
0.0461
9-11
6-9
0.0441
21-22
32
-21.97
-22.87
-20.71
-18.34
From i-j
Reactance of TCSC
15-23
16
-10.92
-2.72
-10.0
-1.74
6-8
-0.0080
22-24
16
-4.46
2.59
-2.03
4.60
8-28
-0.0903
23-24
16
2.03
2.39
3.51
3.54
24-25
16
-11.18
-1.75
-7.28
1.38
25-26
16
3.54
2.36
3.54
2.36
25-27
16
-14.96
-4.52
-10.92
-1.15
28-27
65
-11.45
-21.09
-8.37
-9,39
27-29
16
6.16
1.65
6.16
1.65
yes
Status
relieved
relieved
16
2930
16
7.10
1.63
7.10
1.64
3.68
0.60
3.68
0.60
8-28
6-28
32
32
-6.29
-5.05
-9.07
-14.50
-9.13
0.85
-8.06
-4.35
2.5
x 10
1.5
0.5
10
20
30
40
50
60
70
80
90
100
Iteration Number
Figure 4 Generation cost convergence characteristics for the optimal TCSC size (30 bus system)
VII.
CONCLUSION
Devices, IEEE Transactions on power systems, vol. 20, pp. 15971604, 2005.
[8] S.S.D. Thukaram, Network congestion management by fuzzy
inference using virtual flows, International conference on power and
energy systems, pp. 1-6, 2011.
[9] Panida Boonyaritdachochai, Chanwit Boonchuay and Weerakorn
Ongsakul, Optimal congestion management in an electricity market
using particle swarm optimization with time-varying acceleration
coefficients, Computers and Mathematics with Applications, vol.
60, pp. 1068-1077, 2010.
[10] Thanhlong Duong, Yao JianGang and Vietanh Truong, A new
method for secured optimal power flow under normal and network
contingencies via optimal location of TCSC, Electrical Power and
Energy Systems, vol. 52, pp. 68-80, 2013.
[11] Hadi Besharat and Seyed Abbas Taher, Congestion
management by determining optimal location of TCSC in deregulated
power systems, Electrical Power and Energy Systems, vol. 30, pp.
563-568, 2008.
[12] Masoud Esmaili, Heidar Ali Shayanfar and Ramin Moslemi,
Locating series FACTS devices for multi-objective congestion
management improving voltage and transient stability, European
Journal of Operational Research, vol. 236, pp. 763-773, 2014.
[13] Abouzar Samimi and Peyman Naderi, A new method for optimal
placement of TCSC based on sensitivity analysis for congestion
management, Smart grid and renewable energy, vol. 3, no. 1, pp. 1016, 2012.
[14] S. Rahimzadeh and M. Tavakoli Bina, Looking for optimal
number and placement of FACTS devices to manage the transmission
congestion, Energy conversion and management, vol. 52, pp. 43746, 2011.
[15] B.K. Panigrahi and V. Ravikumar Pandi, Congestion
management using adaptive bacterial foraging algorithm, Energy
Conversion and Management, vol. 50, pp. 1202-1209, 2009.
[16] J. Kennedy and R. Eberhart, Particle swarm optimization,
IEEE International Conference on Neural Networks, Perth, Australia,
vol. 4, pp.19421948,1995.
[17] H.Y. Fan, and Y. Shi, Study on Vmax of particle swarm
optimization, Proceedings on Workshop Particle Swarm
Optimization, Indianapolis, Purdue School of Engineering and
technology, India, 2001.