Contents

1.

CHAPTER 1: CONTRACT STATUS & PROJECT PARTIES................................5


1.0.
1.1.
1.2.
1.3.
1.4.

2.

CONTRACT STATUS.............................................................................................5
PROJECT PARTIES................................................................................................5
INSURANCES AND BONDS...................................................................................6
VALUATION.......................................................................................................... 7
CONTRACTOR SITE ORGANIZATION CHART....................................................................8

CHAPTER 2: OVERVIEW..........................................................................9
2.0.
2.1.
2.2.
2.3.

PROJECT SCOPE..................................................................................................9
PROGRESS UP TO 01/25/2016...........................................................................10
REASONS OF DELAY............................................................................................... 10
PROJECT LOCATION........................................................................................... 11

3. CHAPTER 3: NOTIFICATIONS, SITE INSTRUCTIONS, CLAIMS AND VARIATION


ORDERS..................................................................................................... 12
3.0.
3.1.
3.2.
3.3.

NOTIFICATIONS................................................................................................. 12
SITE INSTRUCTIONS.......................................................................................... 14
CLAIMS.............................................................................................................. 15
VARIATION ORDER............................................................................................ 16

4. CHAPTER 4 HSE MONTHLY DETAILED REPORT FOR THE MONTH OF JANUARY


2016.......................................................................................................... 17
4.0.
4.1.
4.2.
4.3.

4.3.1.

Details of First aid injuries:..............................................................20

4.3.2.

Traffic / Road Incidents:...................................................................21

4.4.
4.5.
4.6.
4.7.
4.8.
5.

ACTIVITIES PERFORMED....................................................................................24
ACTIVITIES TO PERFORM NEXT MONTH.............................................................24
HOT POINTS...................................................................................................... 24
BLOCKING POINTS............................................................................................. 24

CHAPTER 6 MATERIAL...........................................................................25
6.0.
6.1.
6.2.
6.3.

7.

SAFETY INSPECTIONS CONDUCTED DURING THE MONTH:................................................21


H & S STATISTICS REPORT. (25TH DECEMBER 25TH JANUARY 2016)...............................22
SAFETY TRAININGS............................................................................................... 22
SAFETY VIOLATIONS:.............................................................................................. 23
COMPLIANCE WITH LABOR LAW.................................................................................23

CHAPTER 5 ENGINEERING......................................................................24
5.0.
5.1.
5.2.
5.3.

6.

HIGHLIGHTS:........................................................................................................ 17
STATUS OF H & S ACTIVITIES DONE IN JANUARY 2016.................................................17
H & S ACTION PLAN FOR NEXT MONTH FEBRUARY 2016..............................................18
RECORD OF INCIDENTS / ACCIDENTS DETAILS OF INCIDENTS..........................................19

ACTIVITIES PEFORMED......................................................................................25
ACTIVITIES TO PERFORM NEXT MONTH.............................................................25
HOT POINTS...................................................................................................... 25
BLOCKING POINTS............................................................................................. 25

CHAPTER 7: CONSTRUCTION..................................................................26
7.0.
7.1.

ACTIVITIES PERFORMED....................................................................................26
ACTIVITIES TO PERFORM NEXT MONTH.............................................................27

7.2.
7.3.
7.4.
7.5.
7.6.
7.7.
7.8.
7.9.
7.10.
7.11.
8.

HOT POINTS...................................................................................................... 27
BLOCKING POINTS............................................................................................. 27
AREA OF CONCERN........................................................................................... 28
PROGRESS........................................................................................................ 29
QUANTITIES PROGRESS........................................................................................... 30
PROGRESS S CURVE.......................................................................................... 31
DIRECT MANPOWER DISTRIBUTION...................................................................32
MANPOWER HISTOGRAM...................................................................................33
EQUIPMENT DISTRIBUTION................................................................................34
EQUIPMENT HISTOGRAM...................................................................................35

CHAPTER 8 QUALITY.............................................................................36
8.0.
8.1.
8.2.
8.3.

9.

ACTIVITY PERFORMED.......................................................................................36
ACTIVITY TO PERFORM NEXT MONTH................................................................37
HOT POINTS...................................................................................................... 39
BLOCKING POINTS............................................................................................. 39

CHAPTER 9: LOG & REGISTERS...............................................................40


9.0.
9.1.
9.2.
9.3.
9.4.
9.5.
9.6.
9.7.

10.

SUBMITTAL STATUS SUMMARY...........................................................................41


REQUEST FOR INSPECTION (RFI).......................................................................42
MATERIAL SUBMITTAL REGISTER.......................................................................43
METHOD STATEMENT REGISTER........................................................................44
CORRESPONDENCES REGISTER........................................................................45
SHOP DRAWINGS REGISTER..............................................................................46
NCR REGISTER.................................................................................................. 47
RO (ROAD OPENING) STATUS............................................................................48
APPENDIX A.......................................................................................49

10.0.
10.1.
10.2.
10.3.
10.4.

EXECUTION PROGRAMME UPDATE....................................................................50


THREE MONTHS ROLLING PROGRAMME............................................................51
PROGRESS DETAILS STATUS..............................................................................52
PROGRESS DRAWING UP TO 01/25/2016...........................................................53
PROGRESS S-CURVE.......................................................................................... 54

10.5. EXPECTED CASH FLOW.....................................................................................55


11.

APPENDIX B.......................................................................................56

11.0. PHOTOGRAPHIC RECORDS FROM 25TH DECEMBER 25THJANUARY PERIOD..............57

1.

CHAPTER 1: CONTRACT STATUS & PROJECT PARTIES

1.1.

CONTRACT STATUS

PROJECT START DATE:

ORIGINAL PROJECT
COMPLETION DATE
PROJECT COMPLETION
DATE AS PER VARIATION
No 3
PROJECT DURATION:
REVISED PROJECT
DURATION:
MAINTENANCE PERIOD:

4th May 2015

PROJECT BUDGET (QR):

313,000,000.00 QAR

REVISED PROJECT
BUDGET AS PER
BASELINE REV 6.0

327,653,158.00 QAR

1.2.

th

January 2014

16th February 2016


485 CALENDAR DAYS
773 CALENDAR DAYS
400 CALENDAR DAYS

PROJECT PARTIES

CLIENT:

CONSULTANT:

CONTRACTOR

INSURANCES AND BONDS

1.3.

Documents
Contractors All Risks Insurance Policy

Workmen Compensation Insurance


Policy
Professional Indemnity Insurance

Performance Bond

Advance Payment Guarantee

Retention Guarantee

Validity

19th May 2016 plus


400
days
maintenance period

31st May 2016

19th May 2016 plus


400
days
maintenance period

20th June 2017

Valid till PWA receive


full payment of the
advance
payment
amount

16th May 2016

1.4.

VALUATION

1.5.

CONTRACTOR SITE ORGANIZATION CHART

2.

CHAPTER 2: OVERVIEW

2.1.

PROJECT SCOPE

The ALKHEESA North and East Package 01 C2013/73 is located in


the Al RAWDAT AL HAMANA District .Once completed, the project will
provide infrastructure including a sewage network, a new road network,
traffic signals and street landscaping for the residents of Rawdat.
The project has started in 5th January 2014 and will end in May 2015.
The works has been
extended recently to 16th of February 2016.
The Project scope of work are as follows :
Demolition, Site Clearance and Earthworks
Storm Water Drainage
o Microtunneling
Foul Sewer
o Microtunneling
Treatment Sewage Effluents
Balancing & Attenuation Tanks
Electrical Works
Utility com Services Works
Roads and Pavement
Traffic Sign and Roads Marking
Street light Works
Landscaping and Irrigation
8

PROGRESS UP TO 01/25/2016

2.2.

TITLES

PREVIOUS

CURRENT

Overall Progress %

Act %
68.21%

Pl %
72.06%

Act %
3.47%

Overall Progress *%

67.16%

99.48%

4.63%

Variance %
Variance *%
Delay (days )
Delay *(days )

-24.39%
-32.84%
-138
-219

Pl %
7.40
%
0.39
%

Act %
71.68%

7.94
%
0.47
%

71.89%

16.61%
4.76%
-50
4

Construction
Progress %

68.20%

72.35%

3.69%

Construction
Progress* %

67.05%

99.52%

5.08%

Variance %
-24.50%
16.10%
Variance *%
-32.95%
5.09%
Expected Delay
-138
-50
(days)
Expected Delay*
-219
15
(days)
Expected
3-Jul-16
Completion date
Expected
16-Oct-16
Completion date*
*The symbol (*) indicates the progress & delay from the Original Baseline
2.3.

TOTAL
Pl %
79.46
%
71.79%
99.87
%
-7.78%
-28.08%
-188
-215
80.29
%
72.13%
99.99
%
-8.40%
-27.86%
-188
-204
22-Aug-16
18-Sep-16

REASONS OF DELAY

1. Electrical scheme which will prevent to issue SIS


2. Reinforcement for TSE Chambers
3. Ooredoo scope of Works
4. Site instruction approval
5. Waterline protection
9

6. Street parking maximization

10

2.4.

PROJECT LOCATION

Roads and Infrastructure in Al-Kheesa (Rawdat Al-Hamana District), Package 01

11

3.

CHAPTER 3: NOTIFICATIONS, SITE INSTRUCTIONS, CLAIMS AND


VARIATION ORDERS
NOTIFICATIONS

3.1.

#
1

CONTENT

LETTER REFERENCE

DATE

Interference of another Contractor


water lines works with the project
Combined Trench

DN07-P01-CGC-SACYRHYD-LET-00169-14
DN071-P01-CGC-SACYRHYD-LET-00179-14

11/05/2014

Third Party Obstructing works at


site

DN071-P01-CGC-SACYRHYD-LET-00255

02/08/2014

Grouting of cavity between shafts


SH1/40/021 and SH1/40/020

DN071-P01-CGC-SACYRHYD-LET-00265

08/08/2014

Clashing of shafts excavation with


third party works

DN071-P01-CGC-SACYRHYD-LET-00274

13/09/2014

Relocation /Diversion of Electrical


Cables

DN071-P01-CGC-SACYRHYD-LET-00346

09/09/2014

Material Submittals Delay

DN071-P01-CGC-HYDLET-A10071

11/19/2014

TSE Chambers Reinforcement


Drawings

DN071-P01-CGC-HYDLET-A10071

11/22/2014

Flow Control Manholes

DN071-P01-CGC-HYDLET-A10094

12/04/2014

Road 55

DN071-P01-CGC-HYDLET-A10098

12/06/2014

1
0
1
1

Provisional Sum

LDN071-P01-CGC-HYDLET-A10102

12/07/2014

Geotextile membrane for foul sewer


trenches

DN071-P01-CGC-HYDLET-A10103

12/08/2014

1
4

Rework (Foul sewer house


connection relocated to next
manhole in road D47)
Shortage of washed sand /concrete
price's hike

DN071-P01-CGC-HYDLET-A10119

20/12/2014

DN071-P01-CGC-HYDLET-A10121

12/21/2014

Notice of claim N09-Car parking


Maximization

DN071-P01-CGC-HYDLET-A10153

01/03/2015

Road Work s& Duct Crossing

DN071-P01-CGC-HYDLET-A10163

01/07/2015

KAHRAMAA Notice to stop the works

DN071-P01-CGC-HYDLET-A10171

01/10/2015

Site Instruction N06

DN071-P01-CGC-HYDLET-A10200

01/28/2015

1
5
1
7
1
8
1
9
2
0

06/08/2014

12

2
1

Notice of claim No10 Replacement


of site concrete barriers
CONTENT

2
2
2
3
2
4
2
6
2
7
2
8
2
9
3
0
3
4
3
5
3
6
3
7
3
8
3
9

DN071-P01-CGC-HYDLET-A10204
LETTER REFERENCE

01/30/2015

DATE

Diesel price hike

DN071-P01-CGC-HYDLET-A10205

01/31/2015

Cost of processed (crushing &


screening) backfilling material

DN071-P01-CGC-HYDLET-A10206

01/31/2015

On Street parking maximization

DN071-P01-CGC-HYDLET-A10222

02/09/2015

DN071-P01-CGC-HYDLET-A10489

06/08/2015

Concrete Interlock tiles with granite


Effect

DN071-P01-CGC-HYDLET-A10294

03/12/2015

Missing Item of excavation in bill N0


7
(half perforated )
Notice of claim 14-Revised Cost of
balancing Tank

DN071-P01-CGC-HYDLET-A10376
DN071-P01-CGC-HYDLET-A10424

05/13/2015

Notice of claim No15-tack coat for


2nd layer of Asphalt base course

DN071-P01-CGC-HYDLET-A10428

05/14/2015

Additional cost of project Insurance,


bond renewed for extended period

DN071-P01-CGC-HYDLET-A10463

05/28/2015

Project prelim for extended period

DN071-P01-CGC-HYDLET-A10464

05/28/2015

Street Lighting Luminaires

DN071-P01-CGC-HYDLET-A10504

06/14/2015

Road 65 and Drainage layout plan


sheet 37

DN071-P01-CGC-HYDLET-A10526

06/28/2015

Claim for 2nd layer of tack coat in


Asphalt base course

DN071-P01-CGC-HYDLET-A10663

10/18/2015

Missing Item in BOQ4Cx25mm2cable for road Lighting


Distribution

DN071-P01-CGC-HYDLET-A10678

26/10/2015

D65 5

th

reminder

23/04/2015

13

3.2.

CONTENT

SITE INSTRUCTIONS

LETTER REF.
DN071-P01-CGCSACYR-HYD-LET00350
DN071-P01-CGCSACYR-HYD-LET00397
DN071-P01-CGCSACYR-HYD-LET00257

DATE

CGCSACYR
REPLY

2/25/2014

9/11/2014

6/14/2014

10/2/2014

7/3/2014

8/3/2014

Deleting 6nos Attenuation tank including


modular unit

Epoxy coating for storm water structure

Revised site boundary/ limit of /works ,


additional ground investigation field works

Balancing tanks on hold

Cancelled

Add Electrical ducts

DN071-P01-CGC-HYDLET-A10435

1/28/2015

8/19/2015

Change As per CB Drawings Revision

DN071-P01-CGC-HYDLET-A10540

1/28/2015

7/5/2015

Add extra Bore Holes

DN071-P01-CGC-HYDLET-A10589

10/21/2014

8/13/2015

Changing Street Lighting LUMINAIRES


HPS TO LED

DN071-P01-CGC-HYDLET-A10688

5/17/2015

11/2/2015

Add # 6N0s Attenuation Tanks

DN071-P01-CGC-HYDLET-A10356

12/29/2015

4/13/2015

1
0

Add #3N0s Attenuation Tanks

Cancelled

11 Ooredoo scope of works

Cancelled

1
2
1
3
1
4
1
5
1
6

Maximization of street parking

DN071-P01-CGC-HYDLET-A10802

3/1/2015

1/21/2016

Changes of pavements Type B under non


traffic Areas

DN071-P01-CGC-HYDLET-A10242

2/4/2015

2/17/2015

Water ducts and protections

DN071-P01-CGC-HYDLET-A10502

5/21/2015

6/14/2015

Additional IFC drawings for Attenuation


Tanks

DN071-P01-HYD-CGCLET-A10531

5/23/2015

8/26/2015

Duct crossing for future utility connection of


potable water

DN071-P01-CGC-HYDLET-A10483

5/23/2015

6/8/2015

14

3.3.
#

CLAIMS
CONTENT

SUBMITTED
DATE

Balancing tank

11/29/2014

Obstruction at Road D55 (EOT & Prolongation Cost)

Not submitted

TSE Chambers Reinforcement (Construction Cost)

6/20/2015

Sikkat lighting

Not submitted

Geotextile membrane for Foul Sewer Tranches

11/23/2015

Re-work (Foul sewer house connection relocated to next manhole


in road D47)

12/20/2014

Shortage of washed sand and concrete price hike

Not submitted

Add 6 Nos of Attenuation

6/20/2015

Maximization of street parking

3/19/2015

Cost of replacement of site concrete barriers

3/29/2015

Increase of Diesel price

Not submitted

Backfill material as crushing for backfilling (Cost)

Not submitted

Missing Item of Excavation in Bill No.7 (Half Perforated) ESVC


Pipe all dia

6/21/2015

Revised Rate of Balancing Tank

Not submitted

1
0
1
1
1
2
1
3
1
4
1
5
1
6
1
7
1
8
1
9
2
0
2
1
2
2
2
3
2
4
2
5

Tack Coat missing quantity in Bill No.4 for 2nd Layer of Asphalt
Base Course
Additional Cost of Project Insurances, Bonds Renewed for
Extended Period

COMMEN
TS

5/20/2015
Not submitted

Project Prelims for Extended Period

Not submitted

Missing Item in BOQ 4Cx25mm2 Cable for Road Lighting


Distribution

11/23/2015

RC 1200MM dia pipe

10/9/2014

Unit rate of the Item's not included in the BOQ of storm water

9/6/2014

Back / Ramp drop item's

12/21/2014

Upvc gully connections

2/7/2015

Street lighting duct type (SL-2)

3/23/2015

Providing Metering for all Feeder Pillar & LV loads as per KM


requirements

Not submitted

Unit rate of the Item's not included in the BOQ of Foul Sewer

6/9/2014

15

2
6
2
7
2
8
2
9
3
0

Additional Excavation + Separation Wall + Backfilling in


Combined Trenches

Not submitted

Cavity at balancing tank (Excavation+Disposal+Concrete Filling)

2/3/2015

Additional Excavation + Separation Wall + Backing in Combined


Trenches

4/21/2015

Cavity at balancing tank (Excavation+Disposal+Backfilling)

8/27/2015

Acceleration cost of the works at Roads D21 & D22

5/30/2015

VARIATION ORDER

3.4.

CONTENT

Changes as per CB drawing (cost)

Changes as per CB drawing


(prolongation cost)

DATE

COSTS

07/05/2015

28273.82

Add Extra N0 Bore Holes

21/10/2014

77102.99

Add Epoxy coating & Delete


bituminous painting

09/11/2014

401,270.02

23/11/2015

4565924.09

20/05/2015

92610.75

Missing Item of excavation in bill


N0 7
(half perforated )
Tack coat missing quantity in bill
N0.4
For 2nd layer of asphalt base
course
RC pipes 1200 mm

09/10/2014

398791.63

Street lighting Ducts Sl2

23/03/2015

249,930.36

Item's not in the BOQ of storm


water & foul sewer

09/06/2014

291,899.39

10

Back / Ramp drop item's

21/12/2014

350000.00

11

Upvc gully connections

07/02/2015

139463.76

12

Reduction in verges subgrade


layer

17/02/2015

3785993.25

13

Protection slab for existing


potable water pipe crossing
asphalt
Additional IFC drawings for
Attenuation Tanks (Hydrodynamic
Separator Details)

14/06/2015

924,505.84

08/09/2015

288,738.94

14

16

15
16
17
18
19

Providing Metering for all Feeder


Pillar & LV loads
as per KM requirements
Duct crossing for future utility
connection of potable water

23/11/2015

499,648.51

06/07/2015

1,287,320.06

Missing Item in BOQ 4Cx25mm2


Cable for Road
Lighting Distribution
Missing Item of Excavation in Bill
No.7 (Half Perforated) ESVC Pipe
all dia
Replacement of HPS Luminaires
with LED Luminaires

23/11/2015

499,648.51

21/06/2015

4,565,924.09

17

4.

CHAPTER 4 HSE MONTHLY DETAILED REPORT FOR THE MONTH OF


MARCH 2016

HIGHLIGHTS:

4.1.

Continues repair of public protection fences and installation of edge


protection for trenches.
Conducted internal training sections as per training matrix.
Conducted confined space recue drill.
Safety activities conducted as per the action plan for the month of
March 2016; to ensure safe site conditions, implementation of safe
working procedures during construction activities, and for
enhancing safety culture among all site employees.

STATUS OF H & S ACTIVITIES DONE IN MARCH

4.2.

2016.
Sl #

Objectives

To identify and control unsafe acts, unsafe


conditions, hazards and risks on site
during on-going activities.

To discuss safety lapses and to enhance


coordination between construction staff
and HSE dept. for implementation of safety
requirements
To inculcate safety culture and enhance
Safety Awareness on among all site
employees.

To inspect housekeeping issues at site.

To ensure Traffic diversion are as per T D


P & regular maintenance
To ensure all workers getting cool water for

STATUS

OF ACTION TAKEN

(MARCH

2016)
HSE Inspection of site were carried out by
HSE Officers, lapses will be discussed
with Foremen and corrective actions
ensured.
Inspection Reports submitted on major
issues to Project Director, and Ensure
corrective actions.
HSE Meetings for Construction staff
conducted on weekly basis.
Safety Inductions for all New employees,
and visitors.
Safety training as per training matrix.
Tool box meetings - weekly
Regular Inspections conducted.
Regular Inspections conducted.
Conducted through monitoring.
18

drinking during working hours.


To identify and control unsafe acts, unsafe
conditions, hazards and risks on site
during on-going activities.

Conducted through monitoring and routine


inspections.

Sl #

Objectives

Status of action taken (March 2016)

All rescue equipment and full body harness


must be inspected.

All rescue equipment and full body


harness inspected.

First aid training


operatives.

Conducted.

10
11

13

Emergency evacuation drill for excavation.


To ensure scaffolding is properly erected
with trained workers for work at height
activities
Placing of concrete barriers in front of
Qatari residences
Reward system for workers.

14

MSDS training for store related personals

12

4.3.

for

24

staff

and

Conducted.
Conducted through monitoring and
daily/weekly inspections.
And scafftag
systems implemented.
On-going.
2 foremen and 2 workers were selected
for monthly HSE award system.
Conducted.

H & S ACTION PLAN FOR NEXT MONTH APRIL

2016
Sl #
1

Objectives
To identify and control unsafe acts, unsafe
conditions, hazards and risks on site
during on-going activities.

To discuss safety lapses and to enhance


coordination between construction staff
and HSE dept. for implementation of safety
requirements
To inculcate safety culture and enhance
Safety Awareness on among all site
employees.

4
5
6

To inspect housekeeping issues at site.


To ensure Traffic diversion are as per T D
P & regular maintenance
To ensure all workers getting cool water for
drinking during working hours.

Status of action Planned (April 2016)


HSE Inspection of site will be carried out by
HSE Officers, lapses will be discussed with
Foremen and corrective actions will be
ensured.
Inspection Reports will be submitted on
major issues to Project Director, Ensure
corrective actions.
HSE Meetings for Construction staff to be
conducted.
Safety Inductions for all New employees, and
visitors.
Safety training as per training matrix.
Tool box meetings - weekly
Regular Inspections to be conducted.
Regular Inspections to be conducted.
Conduct through monitoring.

19

To identify and control unsafe acts, unsafe


conditions, hazards and risks on site
during on-going activities.

HSE Inspection of site will be carried out by


HSE Officers, lapses will be discussed with
Foremen and corrective actions will be
ensured.
Inspection Reports will be submitted on
major issues to Project Director, Ensure
corrective actions.

Sl #

Objectives

Status of action planned (APRIL 2016)

All rescue equipment and full body harness


must be inspected.

All rescue equipment and full body harness


will be inspected.

Confined space training for 4 operatives.


Emergency evacuation drill for work at
height.
To ensure scaffolding is properly erected
with trained workers for work at height
activities
Placing of concrete barriers in front of
Qatari residences
Reward system for workers.
Oil spillage response training for store
related personals

To be conducted.
To be conducted.

9
10
11
12
13
14

4.4.

Conduct through monitoring and daily/weekly


inspections. And scafftag systems have to
be implemented.
To be done.
Monthly Once.
To be conducted.

RECORD OF INCIDENTS / ACCIDENTS DETAILS

OF INCIDENTS

Description of incidents /
accidents
Man-hours worked till date
First Aid injuries
Sickness spells
Loss Time Injuries
Fatalities
Near Miss
Property Damage
Fire Incidents
Environmental incidents

Reported / Recorded.
3124265
202
03
1
0
22
4
0
0

20

4.4.1.

Details of First aid injuries:

Nature
of
Injury

Nos

Body part affected

Root Cause Identified


1.

1. Head

2. Left hand middle


finger
0
1

3. Left leg knee


Abrasion

05
4. Right hand
thump

5. Right hand index


finger.

0
2

0
3

0
4

Laceratio
n

Bruising

1.

Right leg bellow


knee

2.

Right leg bellow


knee

02

01

1. Right leg feet

1. Right leg foot


Puncture

02
2. Right leg foot

Abrasion on back side of


head, he got hit with steel
while he was sleeping in
rest area.
2. Mild abrasion on left hand
middle finger. He got hit
with hammer, while he was
fixing nail.
3. Mild abrasion on left leg
knee, he tripped and fell on
the floor.
4. Mild abrasion on right hand
thump. He got hit with
pipe, while he was placing
the pipe on the floor.
5. Abrasion on right index
finger, he got hit with steel,
while he was working at the
site.

1. Lacerated wound on right


leg bellow knee. He got hit
with stone while he was
cutting stone with hammer.
2. Laceration on right leg
bellow knee, he got hit with
steel while he was
transferring steel from the
vehicle.
1. Bruising on right leg feet
generator fell on his leg,
while he was trying to
lifting the generator.
1. Nail prick on right leg under
the feet, while he stepped
over the plywood.
2. Nail prick on right leg feet,
he got hit with nail while he
stepped over the plywood.

21

1. Head
0
5

Others

02
2. Right leg

4.4.2.

1. Pain and swelling on left


side check. He got hit with
shutter while he was
transferring from vehicle.
2. Pain and swelling on right
Lower leg, due to hit by
plywood.

Traffic / Road Incidents:

Incident
Vehicle accidents
Property Damage
Fatal Accident
First Aid cases

Recorded Incidents
0
0
0
12

Ref: Report No.


Not applicable
Not applicable
Not applicable
Not applicable

SAFETY INSPECTIONS CONDUCTED DURING

4.5.
THE MONTH:

Sr. No
8.5.1
1
2
3
4
5
6
7
8

Equipment
Heavy Mobile Equipment
Excavator equipment(Jack hammer / bucket)
Loader / shovel
Backhoe
Drum Cutter
Truck mounted crane
Equipment
Roller
Bobcat
Mobile Crane

Quantity
00
02
02
00
00
Quantity

05
04
02

Portable / Stationary equipment

8.5.2

Generators
Welding Machine
Tower light
Plate Compactor
Power tools
Fire Extinguishers
Inspection of Site clinic and welfare facilities
Site Inspection (observation) Reports
Total number of inspections during the month

1
2
3
4
5
6
7
8

9
01
01
02
20
44
4 times
10
106

22

23

H & S STATISTICS REPORT. (25TH FEBRUARY

4.6.

25TH MARCH 2016)


Sl #

1
2
3
4
5
7
8
9
10
11
12
13
14
15
16
17
18
19

Description

1
1
2
3
4
5

2995961

Total Man hours worked


Incidents
No. of Lost time incident (LTI )
Medical Treatment cases
First Aid cases
Sickness spells
Restricted work duty cases
Fatal accidents
Near-miss
Fire Incidents.
Road Traffic Accidents (RTA)
Property Damage
(Other than Fire incidents)
Subcontractor accidents
Environmental incidents
Dangerous occurrences
Statistics
LTI Frequency Rate
LTI Severity Rate
Man hours worked without LTI

This
Month

Total

3124265

12

128304
1

13

1
2
197
3
0
0
20
0
5
4

0
0
5
0
0
0
2
0
0
0

1
2
202
3
0
0
22
0
5
4

0
0
1

0
0
0

0
0
1

0.0350
1.158
1989854

0
0

0.0320
1.056
2118158

128304

SAFETY TRAININGS

4.7.

Sl #

Till last
month

Description

Till last
month

This
Month

Total

No. of employees attended safety


induction
No. of safety Internal trainings
conducted

1625

12

1637

65

68

No. of external trainings attended by


CGC Jv Sacyr employees.
Emergency mock drill
No. of tool box meetings
No. HSE Meetings conducted

22

25

10
223
28

1
4
1

11
227
29
24

4.8.

SAFETY VIOLATIONS:

58

4.9.

61

COMPLIANCE WITH LABOR LAW

Company is complying with all the relevant requirements. A copy of legal


requirements is readily available at the CGC-Sacyr JV site office.
Qatar Labor Law
Qatar Construction Specification 2010
Ministry of Environment Act, Qatar

The company will continue to ensure compliance with legal and other
requirements and update them referring government orders and
websites.

Prepared By

Reviewed By

Approved By

Mr.Faizal Butt

Eng.Loveson
Glariyans

Eng. Ruben Estraviz

25

5.

CHAPTER 5 ENGINEERING
ACTIVITIES PERFORMED

5.1.

Re Submitting Production shop drawing Road works due to gate relocation


Submitting production shop drawing of Electrical Ducts
Re Submitting production shop drawing of Gullies due to additional parking
maximization.
Re Submitting production shop drawing of Street Lighting Ducts due to
additional parking maximization
QAF & Ooredoo due to additional parking maximization

ACTIVITIES TO PERFORM NEXT MONTH

5.2.

Submitting FCR for utilities clashes at site


Some gate location as per site (FCR)
Starting AS build drawings

HOT POINTS

5.3.

Road work as per additional parking

FCR for Storm water and Gully


FCR for house connections
Soft landscaping, Irrigation drawing are on hold due to issue
CB drawings
Hard landscaping drawings are an hold due to issue CB
drawings
5.4.

BLOCKING POINTS

NIL

26

6.

CHAPTER 6 MATERIAL
6.1.

ACTIVITIES PEFORMED

Material submittal ( 0 Nos)


Material delivery(Sub Base Class-C & B, Aggregate 10mm & 20mm, Kerbstone,
Granite Affect Paving Blocks, 60 & 80mm Red Paving Blocks, Hydro Brake-Flow
Control, Hydrodynamic Separators)
Material ordered (Sub Base Class-B Material, Sub base Class-C Material )
Material testing (Sub Base Class-C & B Suitability Tests, In-situ Density testing
for Backfill, Subgrade & Sub base , Cube Compressive Strength & Durability,
Selected Fill Suitability Testing , Interlock Tiles Crushing Strength & Water
Absorption, Asphalt Marshall , Extraction & Compaction)
6.2.

ACTIVITIES TO PERFORM NEXT MONTH

Material submittal ( 2 Nos )


Material delivery (Sub Base Class-C, Sub Base Class-B, Short Blasted Granite
Effect Paving Block, Aggregate 20mm & 10mm, Kerbstones, 60mm & 80mm
Red Interlock Tiles, Traffic Signs).
Material testing (Sub Base Class-C & B Suitability Tests, In-situ Density
testing for Backfill, Subgrade & Sub base , Cube Compressive Strength &
Durability, Aggregate Pipe Bedding & Surround, Selected Fill Suitability
Testing , Interlock Tiles Crushing Strength & Water Absorption, Asphalt
Marshall, Extraction & Compaction)
6.3.

HOT POINTS

NIL

6.4.

BLOCKING POINTS

NIL

27

7.

CHAPTER 7: CONSTRUCTION
ACTIVITIES PERFORMED

7.1.

MANHOLES WORKS
1. Blinding/Waterproofing Membrane/protective screed
2. Concrete casting (Fix Forms, Rebars & Water stop) - Manhole Base
3. Concrete casting (Fix Forms, Rebars & Water stop) - Wall (1st. Lift)
HOUSE CONNECTION WORKS :RD86, RD27, RD37 ;RD107

GULLIES CONNECTION WORKS :


RD37; RD29; RD32, RD30, RD24; RD27; RD30; RD25; RD58;

RD86
DUCTS WORKS
RD37; RD29; RD32, RD24; RD27; RD30; RD25, RD28; RD86
RD104; RD105; RD106; RD118, RD119, RD113; RD58
SUBGRADE WORKS
RD37; RD58; RD26; RD86; RD31; RD32; RD25
RD29; RD35; RD28; RD25; RD24; RD30
SUBBASE FOR ROAD :
RD37; RD58; RD26;
RD29; RD35; RD28; RD30
ASPHALT FOR ROAD BASE :
RD64, RD63, RD37, RD29; RD35, RD58
PARKING TILES WORKS (ON HOLD )
EDGE KERBSTONE WORKS (ON HOLD)
STREET LIGTHING WORKS
KERBSTONE.WORKS
FOOTWAY TILES (ON HOLD)
SHAFT WORKS
MANHOLES CLEANING
ATTENUATION TANKS WORKS 47 : WATERPROOFING
28

ATTENUATION TANKS WORKS 4 : LEAKAGE TEST


ATTENUATION TANKS WORKS 63 : CLEANNING
ATTENUATION TANKS WORKS 39 : WATERPROOFING
BALANCING

TANKS WORKS

ATTENUATION TANKS WORKS ACCESSORIES


7.2.

HOT POINTS

7.3.

BLOCKING POINTS

NIL

29

ACTIVITIES TO PERFORM NEXT MONTH

7.4.

MANHOLES WORKS
4. Blinding/Waterproofing Membrane/protective screed
5. Concrete casting (Fix Forms, Rebars & Water stop) - Manhole Base
6. Concrete casting (Fix Forms, Rebars & Water stop) - Wall (1st. Lift)
HOUSE CONNECTION WORKS :RD86, RD27, RD37

GULLIES CONNECTION WORKS :


RD37; RD29; RD32, RD33, RD24; RD27; RD30; RD25;RD26

SUBBASE FOR ROAD :


RD37; RD58; RD26
RD29; RD27; RD 61; RD35; RD28; RD25; RD24; RD30,RD107
ASPHALTFOR ROAD BASE :
RD62; RD61; RD60, RD64, RD63, RD37, RD26, RD104,
RD105, RD107
RD29;

RD27;

RD

61;

RD35;

RD28;

RD25;

RD24;

RD30,RD110,RD58
PARKING TILES WORKS
EDGE KERBSTONE WORKS (ON HOLD)
STREET LIGTHING WORKS
KERBSTONE.WORKS
FOOTWAY TILES (ON HOLD)
SHAFT WORKS
ATTENUATION TANKS WORKS 63 : LEAKAGE TEST
ATTENUATION TANKS WORKS 4 : LEAKAGE TEST
ATTENUATION TANKS WORKS 39 : LEAKAGE TEST
ATTENUATION TANKS WORKS ACCESSORIES
7.5.

HOT POINTS

NIL
30

7.6.

BLOCKING POINTS

NIL

31

7.7.

AREA OF CONCERN

32

PROGRESS

7.8.

Progress %
Previous month
GROUPS

GROUP 01
GROUP 02
GROUP 03
GROUP 04
GROUP 05
GROUP 06
GROUP 07
Overall

Act*.
%

54.6
1%
47.7
0%
56.5
0%
37.6
3%
43.8
8%
49.2
9%
90.1
7%
67.0
5%

Act. %

55.48
%
48.17
%
59.04
%
36.85
%
47.28
%
50.72
%
90.26
%
68.20
%

P.l. %

63.6
6%
60.8
7%
64.0
5%
43.8
6%
55.7
0%
58.5
3%
91.6
0%
72.3
5%

Current month
Act*.
%

7.72
%
5.58
%
5.05
%
1.65
%
0.00
%
6.01
%
0.00
%
5.08
%

Act. %

6.42
%
4.66
%
3.88
%
1.92
%
4.72
%
3.13
%
0.00
%
3.69
%

P.l. %

12.5
3%
10.6
9%
5.24
%
8.52
%
12.5
5%
7.42
%
2.30
%
7.94
%

Total Completed
Act*.
%

62.3
3%
53.2
8%
61.5
5%
39.2
8%
43.8
8%
55.3
0%
90.1
7%
72.1
3%

Act. %

61.9
0%
52.8
3%
62.9
2%
38.7
7%
52.0
0%
53.8
5%
90.2
6%
71.8
9%

P.l. %

76.1
9%
71.5
6%
69.2
9%
52.3
8%
68.2
5%
65.9
5%
93.9
0%
80.2
9%

Delay
(**)

14.29
%
18.73
%
6.37%
13.61
%
16.25
%
12.10
%
3.64%
8.40%

(*) the symbol indicates the progress based on the baseline programme

33

QUANTITIES PROGRESS

7.9.

Previous
Month
January
Storm water

Foul Sewer

TSE

House
connections
Gullies
Manholes Storm
water
Manholes Foul
sewer
Chamber
QAf Duct
Electrical Duct
Pipelaying
Subgrade
Kerbs LayingKerbs
Subbase
HardscapingInstal
ling Edgine kerbs
Paving - Laying
200x100x80mm
Precast Concrete
Block Pavers
Laying of Precast
Concrete Blocks@
Verges
Road Base - Apply
Prime Coat &
Asphalt

Current
Month

Completed
total

Trade
Excavation
Pipe
laying
Backfilling
Excavation
Pipe
laying
Backfilling
Excavation
Pipe
laying
Backfilling
Excavation

Act
95.85%
95.24%

Pl
100.00%
100.00%

Act
0.53%
1.23%

Pl
0.00%
0.00%

Act
96.38%
96.47%

Pl
100.00%
100.00%

93.02%
99.68%
99.40%

100.00%
100.00%
100.00%

0.18%
0.08%
0.00%

0.00%
0.00%
0.00%

93.20%
99.76%
99.40%

100.00%
100.00%
100.00%

99.41%
87.21%
70.59%

100.00%
100.00%
100.00%

0.00%
2.69%
5.84%

0.00%
0.00%
0.00%

99.41%
89.90%
76.43%

100.00%
100.00%
100.00%

68.97%
88.38%

100.00%
100.00%

5.95%
0.39%

0.00%
0.00%

74.92%
88.77%

100.00%
100.00%

Excavation
Walls

67.94%
94.90%

100.00%
100.00%

3.09%
0.55%

0.00%
0.00%

71.03%
95.45%

100.00%
100.00%

Walls

94.94%

100.00%

0.00%

0.00%

94.94%

100.00%

Walls
Laying
Laying

52.56%
49.06%
50.75%

100.00%
100.00%
100.00%

9.03%
5.66%
1.68%

0.00%
0.00%
0.00%

61.59%
54.72%
52.43%

100.00%
100.00%
100.00%

Laying

79.60%
50.08%

100.00%
100.00%

1.02%
4.34%

0.00%
0.00%

80.62%
54.42%

100.00%
100.00%

Laying

45.82%
20.28%

100.00%
100.00%

11.10%
1.75%

0.00%
0.00%

56.92%
22.03%

100.00%
100.00%

Laying

21.64%

100.00%

2.33%

0.00%

23.97%

100.00%

Laying

9.85%

100.00%

8.77%

0.00%

18.62%

100.00%

45.35%

100.00%

1.91%

0.00%

47.26%

100.00%

34

Wearing Course Apply Tact Coat &


Asphalt
Roads Marking
Road Signs

0.00%

100.00%

0.00%

0.00%

0.00%

100.00%

100.00%
100.00%

0.00%
0.00%

100.00%
100.00%

35

7.10.

PROGRESS S CURVE

See Appendix A

36

7.11.

DIRECT MANPOWER DISTRIBUTION

37

7.12.

MANPOWER HISTOGRAM

38

7.13.

EQUIPMENT DISTRIBUTION

39

7.14.

EQUIPMENT HISTOGRAM

40

8.

CHAPTER 8 QUALITY
8.1.

ACTIVITY PERFORMED

Inspection Request for the following activities for Foul Sewer, Storm water
& House connection, attenuation tanks concrete, Balancing Tank, TSE &
Roadwork.
Inspection Request for the following activities for Foul Sewer, Storm water & House
connection, attenuation tanks concrete, Balancing Tank, TSE & Roadwork.

1. Trench Excavation
2. Formation level
3. Installation of Geotextile
4. Gravel bedding
5. VC pipe laying
6. Air Test
7. Gravel surround pipe
8. Back filling works for trenches
9. Compaction Test (FDT)
10. Manholes Excavation for house connection
11. Blinding Concrete
12. Bitumen Primer
13. Tanking Membrane
14. Protection Board
15. Formworks and Reinforcement
16. Concrete of base slab & Wall Manhole
17. Backfilling works for manholes
18. Installation of manhole cover
19. Rocker Pipes Connection
20. Backdrop Pipe Installation
21. House Connection Pipeline
22. Roadwork (Sub-grade, Formation, Sub-base)
23. Kerbstone foundation
24. Installation of Kerbstone
Micro-Tunneling shaft concrete blinding
Micro-Tunneling shaft formworks & reinforcement installation
Micro-Tunneling shaft Concrete Manhole
Manholes base and wall concrete with cover slab (Group 1,2,3,4,5 & 6)
TSE Pipeline (Road D-20, 21, 22, 23, 24, 27, 28, 29, 31, 32, 37, 40, 51,55, 56, 58, 60, 62, ,
63, ,64, 65, 86, 103, 113, 114)
1. Excavation/Formation Level
2. Geotextile Installation
3. Gravel Bedding
4. Pipe Laying
5. Granular surround
6. Pressure testing of pipeline
7. Backfill visual checking
41

8. Compaction (FDT)
TSE Chamber (Road D-20, 21, 22, 23, 24, 27, 28, 29, 31, 32, 37, 40, 51, 56, 58, 60, 62, ,63,
64, 65, 86, 103, 113, 114)
1. Excavation
2. Blinding Concrete
3. Water proofing
4. Concrete screed
5. Base slab
6. Concrete wall
7. Cover slab
8. Protection board Cover Slab)
9. Compaction test (FDT)
Gully Pot & Pipe connection (Group 1, 2, 3, 4 & 5)
1. Excavation
2. Precast gully pot installation
3. Precast manhole cover slab installation
4. Backfilling
Street Lighting (D-45, 50, D-49, D-48, D-51, D-53, D-56, D-54, D-57, 108, 109, 111,103,
115, 107, 114, 116, 119, )
1. Excavation
2. Bedding, Cable laying, Dune sand surround
3. Precast Foundation Installation
4. Electrical pole installation
Asphalting Works (Sub-grade, Sub-base & Base coarse) D-20, 21, 22, 39, 40, 41, 45, 46, 47,
48, 49, 50, 51, 53, 54, 56, 57, 103, 105, 106, 107, 108, 109, 111, 112, 113, 114, 115, 116,
118, 119
Cube Crushing at QIL Lab.
Installation of Precast Manholes Concrete Cover
Balancing Tank
Dewatering
House Keeping
Attenuation Tank (Activities)
AT - 23/000
Grout filling for tie rod hole
Application for joint sealant for construction joint
Water filling
AT 4/000
Grout filling for tie rod hole
Application of joint sealant for construction joint
Water filling
AT 75/000
Water tightness test
AT 63/000
Water filling
AT 39/000
Water filling
AT 47/000
42

8.2.

Water tightness test

ACTIVITY TO PERFORM NEXT MONTH


Method Statement:
1. ITP & Checklist for Traffic Signs
2. ITP & Checklist for Micro tunnelling Joint filling
Inspection for the following activities for Group 1, 2,3,4, 5 and Group 6
1. Trench Excavation
2. Formation level
3. Installation of Geotextile
4. Gravel bedding
5. VC pipe laying
6. Air test
7. Gravel surround pipe
8. Backfilling works for trenches
9. Compaction Test (FDT)
10. Manholes Construction Excavation
11. Blinding Concrete
12. Waterproofing
13. Protection Board
14. Reinforcement
15. Formwork
16. Concrete
17. Rocker Pipes
18. Backdrop pipes Installation
19. Primer Coat
20. Backfilling works for manholes
21. House Connection Pipeline
22. Roadwork (Sub-grade, Sub-base)
23. Concrete paving block works
24. Kerbstone Installation
Concrete blinding of manhole for Group 1, 2, 3, 4, 5 & 6
Concrete of manhole base & walls for Group 1, 2, 3, 4, 5 & 6
Backfilling of Trench
FDT and Test result
Rocker Pipe
Prime coat
Water proofing
TSE Pipeline and Chamber Works (Group 1, 2, 3, 4, 5 & 6)
Gully pot & Pipe connection (Group 1, 2, 3, 4, & 5)
Precast Concrete Cover Slab for Manhole
Street Lighting Activities (Group 1, 2, 3, 4, & 5)
1. Excavation
2. Bedding, Cable Laying, Dune sand surround
3. Precast Foundation Installation
4. Electrical pole installation
43

Sub-grade & Sub-base preparation (Group 1, 2, 3, 4, 5 & 6)


Asphalting work (Base Coarse) Group 1, 2, 3, 4, 5, & 6
Cube Crushing at QIL Lab.
Micro-tunneling Shaft
Concrete Blinding
Water Proofing membrane installation
Concrete Manhole
Balancing Tank
Application of bitumen primer
Installation of Tanking membrane and protection board
Backfilling
Attenuation Tank (Activities)
AT - 23/000
Water tightness Test
Application of bitumen primer
Installation of tanking membrane and protection board
backfilling
AT 4/000
Water tightness Test
Application of bitumen primer
Installation of tanking membrane and protection board
backfilling
AT 75/000
Application of bitumen primer
Installation of tanking membrane and protection board
backfilling
AT 63/000
Water tightness Test
Application of bitumen primer
Installation of tanking membrane and protection board
backfilling
AT 39/000
Water tightness Test
Application of bitumen primer
Installation of tanking membrane and protection board
backfilling
AT 47/000
Application of bitumen primer
Installation of tanking membrane and protection board
Backfilling

8.3.

HOT POINTS

NIL
44

8.4.

BLOCKING POINTS

NIL

45

9.

CHAPTER 9: LOG & REGISTERS

46

9.1.

SUBMITTAL STATUS SUMMARY

47

9.2.

REQUEST FOR INSPECTION (RFI)

48

9.3.

MATERIAL SUBMITTAL REGISTER

49

9.4.

METHOD STATEMENT REGISTER

50

9.5.

CORRESPONDENCES REGISTER

51

9.6.

SHOP DRAWINGS REGISTER

52

9.7.

NCR REGISTER

53

9.8.

RO (ROAD OPENING) STATUS

54

10. APPENDIX A

55

10.1.

EXECUTION PROGRAMME UPDATE

56

10.2.

THREE MONTHS ROLLING

PROGRAMME

57

10.3.

PROGRESS DETAILS STATUS

58

10.4.

PROGRESS DRAWING UP TO 01/25/2016

59

10.5.

PROGRESS S-CURVE

60

10.6.

EXPECTED CASH FLOW

61

11.

APPENDIX B

62

11.1.

PHOTOGRAPHIC RECORDS FROM


25TH DECEMBER 25THJANUARY PERIOD

63