Você está na página 1de 101

BSC6910 GSM

V100R015C00

Installation Guide
Issue

03

Date

2013-07-30

HUAWEI TECHNOLOGIES CO., LTD.

Copyright Huawei Technologies Co., Ltd. 2013. All rights reserved.


No part of this document may be reproduced or transmitted in any form or by any means without prior written
consent of Huawei Technologies Co., Ltd.

Trademarks and Permissions


and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective holders.

Notice
The purchased products, services and features are stipulated by the contract made between Huawei and the
customer. All or part of the products, services and features described in this document may not be within the
purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information,
and recommendations in this document are provided "AS IS" without warranties, guarantees or representations
of any kind, either express or implied.
The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but all statements, information, and
recommendations in this document do not constitute a warranty of any kind, express or implied.

Huawei Technologies Co., Ltd.


Address:

Huawei Industrial Base


Bantian, Longgang
Shenzhen 518129
People's Republic of China

Website:

http://www.huawei.com

Email:

support@huawei.com

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

BSC6910 GSM
Installation Guide

About This Document

About This Document

Overview
This document describes how to install the BSC6910. The components to be installed include
power cables, PGND cables, boards, signal cables, cabinet fittings, the computer serving as the
local maintenance terminal (LMT), and the alarm box. This document also describes how to
check the installed hardware, constructing connectors for power cables and signal cables, and
making and attaching engineering labels. Finally, this document provides requirements for the
operational environment of the equipment.

Product Version
The following table lists the product versions related to this document.
Product Name

Product Version

BSC6910

V100R015C00

Intended Audience
This document is intended for installation personnel.

Organization
1 Changes in the BSC6910 GSM Installation Guide
This section describes the changes to the BSC6910 GSM Installation Guide.
2 Preparations for Installation Tools
The tools required for installing the BSC are tools for measuring, marking, drilling, and
fastening, small tools, auxiliary tools, instruments, and special tools.
3 Installation Process
Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

ii

BSC6910 GSM
Installation Guide

About This Document

The BSC6910 installation process includes the installation of the cabinet and its fittings, power
cables and PGND cables, EOMUa boards, signal cables, LMT computers, and alarm boxes.
4 Installing Power Cables and PGND Cables
This section describes how to install power cables between subracks and the PDF, PGND cables
between a cabinet and the PDF,and PGND cables between cabinets. For items and specifications
for checking the installation of the power cables and PGND cables, see 11.1 Checklist for
BSC6910 Cable Installation.
5 Checking and Setting DIP Switches on Subracks
This section describes how to check and set the DIP switch on a subrack. In general, subracks
are installed in the cabinet before delivery.
6 Checking the Power-On Performance of Subracks
This section describes how to check the power supply to subracks, fan assembly, and boards.
7 Installing and Setting Boards
Most boards except the EOMUa/ESAUa boards are installed in subracks before the delivery.
Install the EOMUa/ESAUa boards onsite.
8 Installing the Signal Cables
This chapter describes how to install the signal cables according to the layout requirements. The
signal cables to be installed include clock signal cables, Ethernet cables and optical cables. For
items and specifications for checking the installation of signal cables, see 11.1 Checklist for
BSC6910 Cable Installation.
9 Installing the Alarm Box and the Computer Serving as the LMT
This section describes how to install an alarm box and a computer serving as the LMT. If you
are installing the computer and the alarm box in the equipment room, you can install them along
with the BSC6910 equipment. For items and specifications for checking the installation of the
LMT computer and the alarm box, see 11.3 Checklist for the Installation of the LMT
Computer and Alarm Box.
10 Attaching the Engineering Labels to the Cables
This chapter describes how to attach engineering labels to the power, PGND, and signal cables
after the cables are installed
11 Checklist for the Hardware Installation
This chapter describes how to check the hardware installation. The hardware consists of cables,
Local Maintenance Terminal (LMT) PC, and alarm box. In addition, you should check the
installation environment.
12 Installation Illustrations
This chapter describes the exploded views of cabinet, cabinet assembly diagrams, and cable
connections of cabinets.
13 Installation Records
The table is used to record the BSC6910 hardware installation information.
Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

iii

BSC6910 GSM
Installation Guide

About This Document

Conventions
Symbol Conventions
The symbols that may be found in this document are defined as follows.
Symbol

Description
Indicates an imminently hazardous situation which, if not
avoided, will result in death or serious injury.
Indicates a potentially hazardous situation which, if not
avoided, could result in death or serious injury.
Indicates a potentially hazardous situation which, if not
avoided, may result in minor or moderate injury.
Indicates a potentially hazardous situation which, if not
avoided, could result in equipment damage, data loss,
performance deterioration, or unanticipated results.
NOTICE is used to address practices not related to personal
injury.
Calls attention to important information, best practices and
tips.
NOTE is used to address information not related to personal
injury, equipment damage, and environment deterioration.

General Conventions
The general conventions that may be found in this document are defined as follows.
Convention

Description

Times New Roman

Normal paragraphs are in Times New Roman.

Boldface

Names of files, directories, folders, and users are in


boldface. For example, log in as user root.

Italic

Book titles are in italics.

Courier New

Examples of information displayed on the screen are in


Courier New.

Command Conventions
The command conventions that may be found in this document are defined as follows.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

iv

BSC6910 GSM
Installation Guide

About This Document

Convention

Description

Boldface

The keywords of a command line are in boldface.

Italic

Command arguments are in italics.

[]

Items (keywords or arguments) in brackets [ ] are optional.

{ x | y | ... }

Optional items are grouped in braces and separated by


vertical bars. One item is selected.

[ x | y | ... ]

Optional items are grouped in brackets and separated by


vertical bars. One item is selected or no item is selected.

{ x | y | ... }*

Optional items are grouped in braces and separated by


vertical bars. A minimum of one item or a maximum of all
items can be selected.

[ x | y | ... ]*

Optional items are grouped in brackets and separated by


vertical bars. Several items or no item can be selected.

GUI Conventions
The GUI conventions that may be found in this document are defined as follows.
Convention

Description

Boldface

Buttons, menus, parameters, tabs, window, and dialog titles


are in boldface. For example, click OK.

>

Multi-level menus are in boldface and separated by the ">"


signs. For example, choose File > Create > Folder.

Keyboard Operations
The keyboard operations that may be found in this document are defined as follows.
Format

Description

Key

Press the key. For example, press Enter and press Tab.

Key 1+Key 2

Press the keys concurrently. For example, pressing Ctrl+Alt


+A means the three keys should be pressed concurrently.

Key 1, Key 2

Press the keys in turn. For example, pressing Alt, A means


the two keys should be pressed in turn.

Mouse Operations
The mouse operations that may be found in this document are defined as follows.
Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

BSC6910 GSM
Installation Guide

Issue 03 (2013-07-30)

About This Document

Action

Description

Click

Select and release the primary mouse button without moving


the pointer.

Double-click

Press the primary mouse button twice continuously and


quickly without moving the pointer.

Drag

Press and hold the primary mouse button and move the
pointer to a certain position.

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

vi

BSC6910 GSM
Installation Guide

Contents

Contents
About This Document.....................................................................................................................ii
1 Changes in the BSC6910 GSM Installation Guide.................................................................1
2 Preparations for Installation Tools............................................................................................3
3 Installation Process.......................................................................................................................5
4 Installing Power Cables and PGND Cables.............................................................................7
4.1 Power Cables and PGND Cables to Be Installed...........................................................................................................8
4.2 Connections of Power Cables and PGND Cables..........................................................................................................9
4.3 Principles for Installing Power Cables and PGND Cables...........................................................................................10
4.4 Installing Power Cables and PGND Cables Between a BSC6910 Cabinet and the PDF.............................................11
4.4.1 Installing Power Cables and PGND cable Between the BSC6910 and the PDF in Overhead Cabling Mode..........11
4.4.2 Installing Power Cables and PGND Cable Between the BSC6910 and the PDF in Underfloor Cabling Mode
............................................................................................................................................................................................15
4.5 Installing the PGND Cables Between Adjacent Cabinets............................................................................................20

5 Checking and Setting DIP Switches on Subracks................................................................22


6 Checking the Power-On Performance of Subracks..............................................................27
7 Installing and Setting Boards....................................................................................................29
7.1 Safety Precautions for Board Installation.....................................................................................................................30
7.2 Installing the EOMUa/ESAUa Boards.........................................................................................................................30

8 Installing the Signal Cables......................................................................................................33


8.1 Signal Cables to Be Installed........................................................................................................................................35
8.2 Principles of Installing the Signal Cables.....................................................................................................................36
8.3 Installing the Clock Signal Cables................................................................................................................................41
8.3.1 Installing the Y-Shaped Clock Cables.......................................................................................................................41
8.3.2 Installing the BITS Clock Signal Cables...................................................................................................................43
8.4 Installing the Ethernet Cables.......................................................................................................................................45
8.4.1 Arranging the Ethernet Cables..................................................................................................................................46
8.4.2 Installing Ethernet Cables Between the EOMUa and the LAN................................................................................46
8.4.3 Installing the Ethernet Cables Between the ESAUa Board and the LAN.................................................................53
8.4.4 Installing the Ethernet Cables Between the FG2c/FG2d Board and the Other Equipment.......................................55
Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

vii

BSC6910 GSM
Installation Guide

Contents

8.5 Installing the Inter-SCUb SFP+ High-Speed Cables Between Different Subracks.....................................................56
8.6 Installing the Optical Cables.........................................................................................................................................60
8.6.1 Using the Accessories of the Optical Cable..............................................................................................................60
8.6.2 Arranging the Optical Cables....................................................................................................................................63
8.6.3 Installing the Optical Cables Between the EXOUa/GOUc/GOUd/POUc Boards and the Other Equipment...........64
8.7 Installing the EMU RS485 Communication Cables.....................................................................................................66
8.8 Connecting the GPS Surge Protector to the GCGa Board............................................................................................68

9 Installing the Alarm Box and the Computer Serving as the LMT.....................................73
9.1 Installing the Computer Serving as the LMT...............................................................................................................74
9.2 Installing the Alarm Box..............................................................................................................................................74

10 Attaching the Engineering Labels to the Cables.................................................................76


10.1 Attaching the Engineering Labels to the Power Cables and PGND Cables...............................................................77
10.2 Attaching the Engineering Labels to the Signal Cables.............................................................................................77

11 Checklist for the Hardware Installation...............................................................................80


11.1 Checklist for BSC6910 Cable Installation..................................................................................................................81
11.2 Checklist for the Installation of the BSC6910 GPS Antenna System........................................................................81
11.3 Checklist for the Installation of the LMT Computer and Alarm Box........................................................................81
11.4 Checklist for Field Cleanliness of BSC6910 Installation...........................................................................................81

12 Installation Illustrations...........................................................................................................82
12.1 Components of a Cabinet...........................................................................................................................................83
12.2 Cable Connections of the Cabinet..............................................................................................................................84
12.2.1 Connections of Power Cables for the Subrack and PGND Cables for the Cabinet.................................................84
12.2.2 Connections of Signal Cables for the MPR.............................................................................................................86
12.2.3 Connections of Signal Cables for the EPR..............................................................................................................89

13 Installation Records..................................................................................................................92

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

viii

BSC6910 GSM
Installation Guide

1 Changes in the BSC6910 GSM Installation Guide

Changes in the BSC6910 GSM Installation


Guide
This section describes the changes to the BSC6910 GSM Installation Guide.

03 (2013-07-30)
This is the third release of V100R015C00.
Compared with issue 02 (2013-06-25), this issue does not include new information.
Compared with issue 02 (2013-06-25), this issue includes the following changes:
Changes

Change Description

8.7 Installing the EMU RS485


Communication Cables

The description of reserved port ELU is adeed


in Context and the picture Connections of
cables between the EMU and the PEM is
optimized.

8.4.2 Installing Ethernet Cables Between


the EOMUa and the LAN

The scenario for BSC6910 and ECO6910 are


configured in different subracks in one
cabinet is added.

Compared with issue 02 (2013-06-25), this issue does not exclude any topics.

02 (2013-06-25)
This is the second release of V100R015C00.
Compared with issue 01 (2013-05-04), this issue does not include new information.
Compared with issue 01 (2013-05-04), this issue includes the following changes:

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

BSC6910 GSM
Installation Guide

1 Changes in the BSC6910 GSM Installation Guide

Changes

Change Description

8.7 Installing the EMU


RS485
Communication
Cables

The description of EMU style is adeed in Context .

Compared with issue 01 (2013-05-04), this issue does not exclude any topics.

01 (2013-05-04)
This is the first release of V100R015C00.
Compared issue with Draft A (2013-02-27), this issue does not include new information.
Compared issue with Draft A (2013-02-27), this issue includes the following changes:
Changes

Change Description

7.2 Installing the


EOMUa/ESAUa
Boards

A description is adeed in Context .

Compared with issue Draft A (2013-02-27), this issue does not exclude any topics.

Draft A (2013-02-27)
This is the Draft A release of V100R015C00.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

BSC6910 GSM
Installation Guide

2 Preparations for Installation Tools

Preparations for Installation Tools

The tools required for installing the BSC are tools for measuring, marking, drilling, and
fastening, small tools, auxiliary tools, instruments, and special tools.

NOTICE
Electronic devices are prone to electrostatic discharge (ESD). Wear an ESD wrist strap correctly
and touch only the edges of the boards, especially when dealing with components such as boards.
Table 2-1 lists the tools required for installation.
Table 2-1 Tools required for installation
Common Tools

Measuring tools

Long measuring tape, ruler (1 m), angle square,


industrial horizontal ruler, and plumb

Marking tools

Marking pen or ink fountain

Drilling tools

Percussion drill (16 drill bit) and vacuum cleaner

Fastening tools

M3-M6 straight screwdrivers


M3-M6 Phillips screwdrivers
Adjustable wrench
Socket wrenches M6, M8, M12, M14, M17, and M19
Double offset ring wrenches M6, M8, M12, M14,
M17, and M19
Long-arm wrench

Small tools

Issue 03 (2013-07-30)

Sharp-nose pliers, diagonal pliers, pliers, hand-held


electric drill, file, handsaw, crowbar, rubber hammer,
and claw hammer

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

BSC6910 GSM
Installation Guide

2 Preparations for Installation Tools

Auxiliary tools

Issue 03 (2013-07-30)

Tweezers, brush, bellows, paper knife, bellows,


electric iron, solder wires, ladder, pallet truck, panel
lifter, heat gun, and electric outlet (with three 2-phase
sockets and three 3-phase sockets, rated current higher
than 15 A)

Meters

Earth resistance tester, Ethernet cable tester, multimeter, 500 V


megohmmeter, optical multimeter, and optical power meter

Special tools

ESD wrist strap, glove, cable peeler, clamp pincer, feeder cutter, SMB
crimping pliers, RJ-45 crimping pliers, and wire cutter

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

BSC6910 GSM
Installation Guide

3 Installation Process

Installation Process

The BSC6910 installation process includes the installation of the cabinet and its fittings, power
cables and PGND cables, EOMUa boards, signal cables, LMT computers, and alarm boxes.

Prerequisites
l

The equipment has been unpacked and accepted.

The tools required for the installation are available.

Procedure
Step 1 Install the cabinet and its fittings.
If...

Then...

An N68E-22 cabinet is to be installed

See the N68E-22 Cabinet Installation Guide for


detailed operations.

An N68E-21-N cabinet is to be installed See the N68E-21-N Cabinet Installation Guide for
detailed operations.
Step 2 Install power cables and PGND cables. For details, see 4 Installing Power Cables and PGND
Cables.
Step 3 Check and Set the Subrack DIP Switch. For details, see 5 Checking and Setting DIP Switches
on Subracks.
Step 4 Check the Power-On Performance. For details, see 6 Checking the Power-On Performance
of Subracks.
Step 5 Install the EOMUa board. For details, see Installing the EOMUa Board.
Step 6 Optional: Install the ESAUa board. For details, see Installing the ESAUa Board.
Step 7 Install signal cables. For details, see 8 Installing the Signal Cables.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

BSC6910 GSM
Installation Guide

3 Installation Process
NOTE

The same method is used to install signal cables in both the N68E-22 and N68E-21-N cabinets. This
document uses the N68E-22 cabinet as an example.

Step 8 Optional: Install the GPS antenna system. For details, see the GPS Satellite Antenna System
Quick Installation Guide.
Step 9 Install the computer serving as the LMT and the alarm box. For details, see 9 Installing the
Alarm Box and the Computer Serving as the LMT.
Step 10 Attach engineering labels to the cables. For details, see 10 Attaching the Engineering Labels
to the Cables.
Step 11 Check the installed hardware. For details, see 11 Checklist for the Hardware Installation.
----End

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

BSC6910 GSM
Installation Guide

4 Installing Power Cables and PGND Cables

Installing Power Cables and PGND Cables

About This Chapter


This section describes how to install power cables between subracks and the PDF, PGND cables
between a cabinet and the PDF,and PGND cables between cabinets. For items and specifications
for checking the installation of the power cables and PGND cables, see 11.1 Checklist for
BSC6910 Cable Installation.
4.1 Power Cables and PGND Cables to Be Installed
Power cables and PGND cables to be installed include -48 V power cables for subracks, RTN
power cables for subracks, external PGND cables for cabinets, and inter-cabinet PGND cables.
4.2 Connections of Power Cables and PGND Cables
This section describes the connections of power cables and PGND cables between a BSC6910
cabinet and the PDF and the connections of inter-cabinet PGND cables.
4.3 Principles for Installing Power Cables and PGND Cables
This section describes the principles for installing power cables and PGND cables. When you
install power cables and PGND cables, follow the routing and binding principles.
4.4 Installing Power Cables and PGND Cables Between a BSC6910 Cabinet and the PDF
This section describes how to install power cables and PGND cables for BSC6910 cabinets in
both overhead cabling and underfloor cabling modes.
4.5 Installing the PGND Cables Between Adjacent Cabinets
This section describes how to connect the upper, middle, and lower parts of the PGND busbar
of one cabinet to those of its adjacent cabinet through PGND cables. PGND cables need to be
installed in adjacent cabinets only when they are installed in combined mode.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

BSC6910 GSM
Installation Guide

4 Installing Power Cables and PGND Cables

4.1 Power Cables and PGND Cables to Be Installed


Power cables and PGND cables to be installed include -48 V power cables for subracks, RTN
power cables for subracks, external PGND cables for cabinets, and inter-cabinet PGND cables.
Table 4-1 lists the power cables for each subrack and PGND cables for each cabinet.
Table 4-1 Power cables and PGND cables to be installed
Item

Color

CrossSection
al Area
(mm2)

Allowed
Bending
Radius
(mm)

Connector
Type/
Installatio
n Position

Connector
Type/
Installatio
n Position

Number

-48 V
power
cable for
the
subrack

Blue

25/35

30

OT terminal/
NEG input
on the PEM
in the
subrack

OT
terminal/-48
V output on
the PDF

RTN
power
cable for
the
subrack

Black

25/35

30

OT terminal/
RTN input
on the PEM
in the
subrack

OT terminal/
RTN output
on the PDF

External
PGND
cable

Green
and
yellow

25/35

30

OT terminal/
PGND input
on the
cabinet

OT terminal/
PGND
output on the
PDF

Intercabinet
PGND
cable

Green
and
yellow

15

OT terminal/
PGND
busbar in the
cabinet

OT terminal/ 3
PGND
busbar in the
cabinet

NOTE

The required length of power cables and PGND cables is specified in the site survey report. Cut an
appropriate length of cables and crimp terminals onsite.
l

The colors of power cables and PGND cables must meet the customer requirements. Table 4-1 lists
only their default colors.

Whether to use one-hole OT terminals or two-hole OT terminals for power cables and PGND cables
is determined based on customer requirements. Table 1-2 lists the one-hole OT terminals.

For details about power cables, see Power Cables. For details about PGND cables, see PGND Cables.

NOTE

To facilitate the crimping of OT terminals, crimp them on the ground with hydraulic pliers, and then place
them in the installation positions.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

BSC6910 GSM
Installation Guide

4 Installing Power Cables and PGND Cables


NOTE

To facilitate the crimping of OT terminals, crimp them on the ground with hydraulic pliers, and then place
them in the installation positions.

4.2 Connections of Power Cables and PGND Cables


This section describes the connections of power cables and PGND cables between a BSC6910
cabinet and the PDF and the connections of inter-cabinet PGND cables.
Figure 4-1 shows the connections of subrack power cables and cabinet PGND cables.
Figure 4-1 Connections of power cables and PGND cables

NOTE

In each cabinet, A1 and B1 form a pair of active and standby power supply ports, as do A3 and B3. As
shown in the preceding figure, to create a hot backup, connect ports A1 and A3 to one power supply group
in the PDF, and ports B1 and B3 to a different power supply group.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

BSC6910 GSM
Installation Guide

4 Installing Power Cables and PGND Cables


NOTE

PEM 01 and PEM 00 work in active and standby mode. As shown in the preceding figure, to create a hot
backup, connect OUTPUT A and OUTPUT B to a different power supply group.
Circuit breakers used on the PDF must be larger than 60 A.
NOTE

Connect the PGND cables for a cabinet to the nearest ground bar. If the PDF is located a great distance
from the cabinet (for example, they are not in the same equipment room), connect the PGND cables to the
nearest ground bar that is co-grounded with the PDF instead of connecting them directly to the PDF. In
this case, the methods of installing and routing PGND cables are the same as those of connecting PGND
cables directly to the PDF. In practice, PGND cables must be connected based on customer requirements.

4.3 Principles for Installing Power Cables and PGND


Cables
This section describes the principles for installing power cables and PGND cables. When you
install power cables and PGND cables, follow the routing and binding principles.

Minimum Bending Radius of Power Cables


Table 4-2 lists the requirements for bending radius of power cables.
Table 4-2 Bending radius of power cables
Cross-Sectional Area (mm2)

Radius

25

50 mm or larger

35

55 mm or larger

Cable Layout Requirements


l

Lay out power cables and PGND cables with future capacity expansion in mind.

When laying out power cables and PGND cables, separate them from signal cables. Lay
out power cables along outer columns. When you lay out power cables and PGND cables
parallel to signal cables, the space between them must be at least 30 mm.

The bending radius of a cable must be five times larger than the diameter of the cable.

When connecting power cables to the terminals on the PEM in the subrack, lay out the
cables straightly and smoothly.

Cable Binding Requirements


l

When binding power cables and PGND cables, separate them from signal cables.

Keep a 200 mm space between cable ties.

When using the underfloor cabling mode, route the PGND cables along the middle standing
pillar on one side of the cabinet.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

10

BSC6910 GSM
Installation Guide

4 Installing Power Cables and PGND Cables

Select the appropriate cable ties, either 150 mm or 300 mm according to the diameter and
number of cables.

Bind the cable ties in the same direction. Cut any excess from the cable ties, cutting surfaces
smoothly without sharp edges.

4.4 Installing Power Cables and PGND Cables Between a


BSC6910 Cabinet and the PDF
This section describes how to install power cables and PGND cables for BSC6910 cabinets in
both overhead cabling and underfloor cabling modes.

4.4.1 Installing Power Cables and PGND cable Between the


BSC6910 and the PDF in Overhead Cabling Mode
This section describes how to install power cables between subracks and the PDF and PGND
cable between a cabinet and the PDF in overhead cabling mode.

Prerequisites
l

The cabinet to be connected with power cables and PGND cable has been installed.

On the PDF, the power distribution switches for the relevant output terminals have been
set to OFF.

All power distribution switches on the PEM in the subrack have been set to OFF.

Power cables and PGND cable are available.

The materials required for the installation are available. The materials include cable ties,
wax strings, and PVC insulation tape.

The tools required for the installation are available. These tools include a handsaw, a cable
cutter, a wrench, a Phillips screwdriver, a flat-head screwdriver, an electric Phillips
screwdriver (> 5 Nm = 44.25 lbfin.), diagonal pliers, and hydraulic pliers.

Context
If you are using the overhead cabling mode, route the cables from the PDF through the upper
cable hole into the cable tray and then the power cables to each subrack,the PGND cable to the
top of each cabinet along the cable tray. Figure 4-2 shows how to install power cables and PGND
cable between a cabinet and the PDF in overhead cabling mode.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

11

BSC6910 GSM
Installation Guide

4 Installing Power Cables and PGND Cables

Figure 4-2 Installing power cables and PGND cable in overhead cabling mode

Procedure
Step 1 Determine the length of each power cable and PGND cable by referring to the related engineering
design documents or by measuring the actual cabling route.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

12

BSC6910 GSM
Installation Guide

4 Installing Power Cables and PGND Cables

Step 2 Uncoil the power cable roll and the PGND cable roll onsite. Measure an appropriate length of
cables with a measuring tape or other measuring tools. Then, cut the cables with a cable cutter
(KT35) or a handsaw with 0.8 mm of teeth space. When cutting the cables, leave sufficient slack.

NOTICE
If you find the slack insufficient, replace the cables. Do not make connectors or solder joints.
Step 3 Attach temporary labels to both ends of the cables. The contents on these temporary labels are
not necessarily the same as those on the formal labels because they are only for easy
identification.
Step 4 Lay out power cables and PGND cable between a cabinet and the PDF. Routed the power cables
from the PDF through the upper cable hole into the cable tray and then to each subrack along
the cable tray.
NOTE

l If the space between a cable tray and the top of a cabinet exceeds 800 mm, use a cable ladder to facilitate
the cable layout.
l The bending radius of a cable must be five times larger than the diameter of the cable.

Step 5 Connect the power cables and PGND cable for the cabinet.
1.

According to the installation position of each cable, determine the exact length required,
and cut off any excess.

2.

Obtain the cable terminals delivered with the cabinet. For details, see Assembling the OT
Terminal and the Power Cable. Crimp the OT terminals of the power cable and OT terminals
of PGND cable for the subrack and the cabinet, respectively.
NOTE

OT terminals (M6) are used for the -48 V and RTN power cables while OT terminals (M8) are used
for PGND cable on the cabinet side. The type of OT terminals used on the PDF side is determined
by the actual situation.
NOTE

To facilitate the crimping of OT terminals, crimp them on the ground with hydraulic pliers, and then
place them in the installation positions.

3.

Optional: (Applicable to the top subrack) Remove the left and right plastic cover plates
from the top rear of the cabinet and cut holes on the cover plates, matching the holes to the
power cable inlets on the power distribution box.

4.

Optional: (Applicable to the top subrack) Place both cover plates back to their original
positions.

5.

Optional: (Applicable to the top subrack) Lead the OT terminals of the -48 V power cable
and the RTN power cable through the cover plate to the wiring terminals of the subracks.

6.

Optional: (Applicable to the subracks other than the top subrack) Lead the OT terminals
of the -48 V power cable and the RTN power cable through the left and right sides of the
cabinet to the wiring terminals of the subracks.

7.

Connect the OT terminals of the -48 V power cable and RTN power cable to the wiring
terminals in the PEM on subracks. Connect the -48 V power cable to the wiring terminal
labeled "NEG(-)", and connect the RTN power cable to the wiring terminal labeled "RTN

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

13

BSC6910 GSM
Installation Guide

4 Installing Power Cables and PGND Cables

(+)". Figure 4-3 shows how to connect an one-hole OT terminal,Figure 4-4 shows how to
connect an two-hole OT terminal.
Figure 4-3 Connecting an one-hole OT terminal

Figure 4-4 Connecting an two-hole OT terminal

NOTE

Use an electric Phillips screwdriver (> 5 Nm = 44.25 lbfin.) to install OT terminals.

8.

Secure the OT terminal of PGND cableto the ground bolt at the rear of the cabinet top.

Step 6 Connect power cables and PGND cable to the PDF output terminals.
Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

14

BSC6910 GSM
Installation Guide

4 Installing Power Cables and PGND Cables

1.

According to the installation position of each cable, determine the exact length required,
and cut off any excess.

2.

Obtain the cable terminals delivered with the cabinet. For details, see Assembling the OT
Terminal and the Power Cable. Crimp the OT terminals of power cables and PGND cable.

3.

Connect the -48 V power cables, RTN power cables, and PGND cable to the corresponding
wiring terminals on the power distribution box.
NOTE

When connecting OT terminals to the wiring terminals, add flat washers and spring washers, and
assemble them in order.

Figure 4-5 shows how to install an OT terminal.


Figure 4-5 Installing an OT terminal

4.

(1) Cable

(2) Heat shrink tubing

(3) Nut

(4) Spring washer

(5) Flat washer

(6) Wiring terminal

Record the installation results in 13 Installation Records.

----End

4.4.2 Installing Power Cables and PGND Cable Between the


BSC6910 and the PDF in Underfloor Cabling Mode
This section describes how to install power cables between subracks and the PDF and PGND
Cable between a cabinet and the PDF for the BSC6910 in underfloor cabling mode.
Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

15

BSC6910 GSM
Installation Guide

4 Installing Power Cables and PGND Cables

Prerequisites
l

The cabinet to be connected with power cables and PGND Cable has been installed.

On the PDF, the power distribution switches for the relevant output terminals have been
set to OFF.

All power distribution switches on the PEM in the subrack have been set to OFF.

Power cables and PGND Cable are available.

The materials required for the installation are available. The materials include cable ties,
wax strings, PVC insulation tape, and lifting sling.

The tools required for the installation are available. These tools include a handsaw, a cable
cutter, a wrench, a Phillips screwdriver, a flat-head screwdriver, an electric Phillips
screwdriver (> 5 Nm = 44.25 lbfin.), diagonal pliers, and hydraulic pliers.

Context
If you are using the underfloor cabling mode, route the cables from the PDF through the cable
hole under the PDF, to the bottom of the cabinet beneath the ESD floor. Route the power cables
to the subrack and route PGND Cable to the top of the cabinet along the middle standing pillar.
Figure 4-6 shows how to install power cables and PGND Cable between a cabinet and the PDF
in underfloor cabling mode.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

16

BSC6910 GSM
Installation Guide

4 Installing Power Cables and PGND Cables

Figure 4-6 Installing power cables and PGND Cable in underfloor cabling mode

Procedure
Step 1 Determine the length of each power cable and PGND cable by referring to the related engineering
design documents or by measuring the actual cabling route.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

17

BSC6910 GSM
Installation Guide

4 Installing Power Cables and PGND Cables

Step 2 Uncoil the power cable roll and the PGND cable roll onsite. Measure an appropriate length of
cables with a measuring tape or other measuring tools. Then, cut the cables with a cable cutter
(KT35) or a handsaw with 0.8 mm of teeth space. When cutting the cables, leave sufficient slack.

NOTICE
If you find the slack insufficient, replace the cables. Do not make connectors or solder joints.
Step 3 Attach temporary labels to both ends of the cables. The contents on these temporary labels are
not necessarily the same as those on the formal labels because they are only for easy
identification.
Step 4 Lay out power cables and PGND Cable according to cable routing and engineering requirements.
1.

Route four pairs of power cables for each subrack and one PGND cable from the cable
outlet at the bottom of the PDF. Then route the cables under the ESD floor for the cabinet.

2.

Divide the power cables for each subrack into two groups and separate them on the left and
right sides of the cabinet. Use a temporary cable tie to bind one group with the PGND cable.
Repeat this procedure with the other group. Route the two groups of cables to each subrack
along the left and right sides of the cabinet, and route the PGND cable to the middle standing
pillar.

3.

Place one end of the lifting sling on the top of the middle standing pillar. Route the other
end of the lifting sling to the bottom of the cabinet through the middle standing pillar, and
bind it to the PGND cable at the bottom of the middle standing pillar.

4.

Pull the upper end of the lifting sling to lift the PGND cable to the top of the cabinet along
the middle standing pillar.

5.

Remove the lifting sling and the temporary cable ties on the PGND cable.

Step 5 Connect power cables to the subrack and connect the PGND cable to the cabinet.
1.

According to the installation position of each cable, determine the exact length required,
and cut off any excess.

2.

Obtain the cable terminals delivered with the cabinet. For details, see Assembling the OT
Terminal and the Power Cable. Crimp the OT terminals of the power cable and OT terminals
of the PGND cable for the subrack and the cabinet, respectively.
NOTE

OT terminals (M6) are used for the -48 V and RTN power cables on the cabinet side. OT terminals
(M8) are used for PGND Cable. The type of OT terminals used on the PDF side is determined by the
actual situation.
NOTE

To facilitate the crimping of OT terminals, crimp them on the ground with hydraulic pliers, and then
place them in the installation positions.

3.

Issue 03 (2013-07-30)

Connect the OT terminals of the -48 V power cable and RTN power cable to the wiring
terminals in the PEM on subracks. Connect the -48 V power cable to the wiring terminal
labeled "NEG(-)", and connect the RTN power cable to the wiring terminal labeled "RTN
(+)". Figure 4-7 shows how to connect an one-hole OT terminal,Figure 4-8 shows how to
connect an two-hole OT terminal.

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

18

BSC6910 GSM
Installation Guide

4 Installing Power Cables and PGND Cables

Figure 4-7 Connecting an one-hole OT terminal

Figure 4-8 Connecting an two-hole OT terminal

NOTE

Use an electric Phillips screwdriver (> 5 Nm = 44.25 lbfin.) to install OT terminals.

4.

Secure the OT terminals of PGND Cable to the ground bolt at the rear of the cabinet top.

Step 6 Connect power cables and PGND Cable to the PDF output terminals.
1.

According to the installation position of each cable, determine the exact length required,
and cut off any excess.

2.

Obtain the cable terminals delivered with the cabinet. For details, see Assembling the OT
Terminal and the Power Cable. Crimp the OT terminals of power cables and PGND Cable.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

19

BSC6910 GSM
Installation Guide

4 Installing Power Cables and PGND Cables

3.

Connect the -48 V power cables, RTN power cables, and PGND Cable to the corresponding
wiring terminals on the power distribution box.
NOTE

When connecting OT terminals to the wiring terminals, add flat washers and spring washers, and
assemble them in order.

Figure 4-9 shows how to install an OT terminal.


Figure 4-9 Installing an OT terminal

4.

(1) Cable

(2) Heat shrink tubing

(3) Nut

(4) Spring washer

(5) Flat washer

(6) Wiring terminal

Record the installation results in 13 Installation Records.

----End

4.5 Installing the PGND Cables Between Adjacent Cabinets


This section describes how to connect the upper, middle, and lower parts of the PGND busbar
of one cabinet to those of its adjacent cabinet through PGND cables. PGND cables need to be
installed in adjacent cabinets only when they are installed in combined mode.

Prerequisites
The power distribution switches for the relevant output terminals have been set to OFF.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

20

BSC6910 GSM
Installation Guide

4 Installing Power Cables and PGND Cables

Procedure
Step 1 As described in 4.2 Connections of Power Cables and PGND Cables, use inter-cabinet PGND
cables to connect the upper, middle, and lower PGND busbars on the mounting bar of adjacent
cabinets as shown in Figure 4-10.
Figure 4-10 Installing PGND cables for adjacent cabinets

----End

Follow-up Procedure
Record the installation results in 13 Installation Records.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

21

BSC6910 GSM
Installation Guide

5 Checking and Setting DIP Switches on Subracks

Checking and Setting DIP Switches on


Subracks

This section describes how to check and set the DIP switch on a subrack. In general, subracks
are installed in the cabinet before delivery.

Prerequisites
Subracks have been installed in the cabinet.

Context

NOTICE
l Wear an ESD wrist strap and connect it to the ESD connector on the cabinet before performing
any operations. For details, see Wearing an ESD Wrist Strap.
l DIP switches cannot be set after the subrack is powered on. Therefore, check and set the DIP
switches before powering on the cabinet.
The DIP switch is used to set the subrack number. Figure 5-1 shows the position of a DIP
switch.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

22

BSC6910 GSM
Installation Guide

5 Checking and Setting DIP Switches on Subracks

Figure 5-1 Position of a DIP switch

The bit 0 indicates the ON state, and the bit 1 indicates the OFF state. The most significant bit
(MSB) of the DIP switch corresponds to the MSB of a byte. Table 5-1 provides the definition
of each bit.
Table 5-1 Definition of each DIP bit
DIP Bit

Definition

1 (the least significant bit)

Subrack number setting bit

Subrack number setting bit

Subrack number setting bit

Subrack number setting bit

Subrack number setting bit

Odd parity check bit

Reserved bit, generally set to ON

8 (the most significant bit)

Startup type of the subrack, must set to OFF

The DIP switch uses odd parity check, so the number of bits that are set to OFF must be odd.
The setting is as follows:
1.

Set bit 1 to bit 5.

2.

Set bit 7 to ON.

3.

Set bit 8 to OFF.

4.

Count the number of bits that are set to OFF.


l If the number of bits is even, set bit 6 to OFF.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

23

BSC6910 GSM
Installation Guide

5 Checking and Setting DIP Switches on Subracks

l If the number of bits is odd, set bit 6 to ON.


Table 5-2 lists the DIP switch setting.
Table 5-2 DIP switch setting
Subr
ack
No.

DIP Bit
1

ON

ON

ON

ON

ON

ON

ON

OFF

OFF

ON

ON

ON

ON

OFF

ON

OFF

ON

OFF

ON

ON

ON

OFF

ON

OFF

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

DIP Switch
Setting

24

BSC6910 GSM
Installation Guide

5 Checking and Setting DIP Switches on Subracks

Subr
ack
No.

DIP Bit
1

OFF

OFF

ON

ON

ON

ON

ON

OFF

ON

ON

OF
F

ON

ON

OFF

ON

OFF

OFF

ON

OF
F

ON

ON

ON

ON

OFF

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

DIP Switch
Setting

25

BSC6910 GSM
Installation Guide

5 Checking and Setting DIP Switches on Subracks

Procedure
Step 1 Set the DIP switch.
Step 2 Attach a formal label or temporary label to the subrack. The contents on the temporary label are
not necessarily the same as those on the formal labels because they are used for identifying a
subrack during BSC6910 software commissioning.
----End

Follow-up Procedure
Record the checking and setting results of the DIP switch in 13 Installation Records.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

26

BSC6910 GSM
Installation Guide

6 Checking the Power-On Performance of Subracks

Checking the Power-On Performance of


Subracks
This section describes how to check the power supply to subracks, fan assembly, and boards.

Prerequisites
l

Power cables and PGND cables between a cabinet and the PDF are installed.

Subracks, fan assemblies, and boards are installed.

A multimeter required for the installation is available.

Context
The cabinet uses a DC power supply. For details, see Technical Specifications of the PEM.

NOTICE
Wear an ESD wrist strap and connect it to the ESD connector on the cabinet before performing
any operations.
You need not to remove the board for performing the power-on check. During powering on a
subrack, do not insert a board into or remove a board from the subrack to avoid static damage
to boards.

Procedure
Step 1 Set the corresponding output switches on the PDF and all the output switches on the PEM in the
subrack to OFF.
Step 2 Use the multimeter to measure the resistance at the power output terminal for the PDF and at
the input terminals for the PEM in the subrack. Ensure that short-circuiting does not occur either
between the -48 V working power and the RTN working ground or between the -48 V working
power and the PGND protection ground.
Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

27

BSC6910 GSM
Installation Guide

6 Checking the Power-On Performance of Subracks

Step 3 Set the output switches on the PDF to ON and all the output switches on the PEM in the
subrack to OFF.
Step 4 Set the multimeter to the voltage scale. Use the multimeter to measure the output voltage of the
PDF or the input voltage of the PEM in the subrack. Ensure that the voltages range from -40 V
to -57 V.
NOTE

If the input voltage of the PEM is normal, the Power 1 and Power 2 indicators are on. If there is no power,
the Power 1 and Power 2 indicators are off. Power 1 indicates the status of Input 1, and Power 2 indicates
the status of Input 2.

Step 5 Set the corresponding two switches on the PEM in the subrack to ON.
Step 6 Check whether the output voltage of the subrack is normal.
l If a subrack is powered on and started normally, the green STATUS indicator on the panel
of the fan assembly blinks. If exceptions occur, turn off the switches on the PEM in the
subrack and the PDF immediately. Check whether the input voltage of the PEM in the
subrack is normal and the power cables are installed correctly. For details about the indicators
on the fan assembly, see Indicators on the Fan Assembly.
l If a subrack is powered on and started normally, the RUN indicator on the board panel is ON
or blinks. If all the indicators on a board are OFF, the board or its slot may be faulty. Contact
Huawei technical support to resolve this problem. For details about the indicators on the
board, see Indicators on Boards.
l If indicators on all the boards in a subrack are OFF, turn off the switches on the PEM in the
subrack and the PDF immediately. Check whether the input voltage of the PEM in the
subrack is normal and the power cables are installed correctly.
Step 7 Repeat Step 4 to Step 6 to check the power supply to all the PEMs in one cabinet.
Step 8 Repeat Step 1 to Step 7 to measure the power supply to each cabinet.
----End

Follow-up Procedure
Record the power-on check results in 13 Installation Records. Set the corresponding output
switches on the PDF and all the output switches on the PEM in the subrack to OFF.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

28

BSC6910 GSM
Installation Guide

7 Installing and Setting Boards

Installing and Setting Boards

About This Chapter


Most boards except the EOMUa/ESAUa boards are installed in subracks before the delivery.
Install the EOMUa/ESAUa boards onsite.
7.1 Safety Precautions for Board Installation
This section describes the precautions you must take when you install, remove, or replace the
boards, or perform any other operation that requires bodily contact with the boards.
7.2 Installing the EOMUa/ESAUa Boards
This section describes how to install the EOMUa/ESAUa board in the MPS.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

29

BSC6910 GSM
Installation Guide

7 Installing and Setting Boards

7.1 Safety Precautions for Board Installation


This section describes the precautions you must take when you install, remove, or replace the
boards, or perform any other operation that requires bodily contact with the boards.

Precautions Before Operation


l

Store materials for board installation (such as ESD boxes and bags) in the equipment room
for future use.

Keep the boards and other electrostatic-sensitive parts in ESD bags. Do not pack or hold
the boards or parts by using plastic foam, common plastic bags, or paper bags.

Ensure that the cabinet is well grounded before inserting the board into the subrack.
Otherwise, the board mill be severely damaged.

Ensure that the wrist strap is functioning. The value of the resistance measured by the
multimeter must range from 0.8 megohm to 1.2 megohms.

see Wearing an ESD Wrist Strap for the method of measuring the resistance.

Precautions During Operation


l

Wear an ESD wrist strap or gloves and ensure that the ESD wrist strap is well grounded.

See Wearing an ESD Wrist Strap for the procedure for wearing an ESD wrist strap or gloves.

Place the board on an ESD pad when replacing board hardware or chips. Use ESD tweezers
or extraction tools to replace chips. Do not touch board chips or pins with your bare hands.

Discharge the static electricity of the cables and protective sleeves before connecting them
to the ports.

Do not touch the PCB or any other part except jumpers and DIP switches during board
replacement.

Place the removed boards and components on an ESD pad or other ESD materials. Do not
pack or hold the boards or parts by using plastic foam, common plastic bags, or paper bags.

7.2 Installing the EOMUa/ESAUa Boards


This section describes how to install the EOMUa/ESAUa board in the MPS.

Prerequisites
l

The tools required for the installation are available. The tools include ESD wrist strap or
gloves and Phillips screwdriver.

The boards to be installed are available.

Context
For the position of the EOMUa/ESAUa board in the subrack, see Configuration of a Subrack
and Principles for Installing Boards.
Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

30

BSC6910 GSM
Installation Guide

7 Installing and Setting Boards

The BSC6910 can be installed in the same cabinet with the ECO6910.To avoid the confusion
of EOMUa/ESAUa board of the BSC6910 and that of ECO6910, determine whether the
EOMUa/ESAUa applies to the BSC6910 based on the print information on the box that houses
the EOMUa/ESAUa, and install the EOMUa/ESAUa in the corresponding subrack.

Procedure
Step 1 Remove the board from the ESD box, and then check the pins and sockets of the board.
In case of any bent, missing or broken pins, or any deformed sockets, contact Huawei engineers
to replace the board.
Step 2 As shown in part a of Figure 7-1, press the self-locking latches on the front panel and turn the
ejector levers outwards until the ejector levers cannot be turned further. Check that the ejector
levers are located in the positions shown in part 2 of Figure 7-1.
Step 3 Hold the panel of the board with one hand and support the board with the other. Then, slide the
board into the subrack along the guide rail until the ejector levers are half closed, as shown in
part 3 of Figure 7-1.

NOTICE
When inserting the board into the subrack, push the board slowly and steadily to avoid damaging
the pins on the backplane and the metal piece on the board.
Figure 7-1 Installing the board

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

31

BSC6910 GSM
Installation Guide

7 Installing and Setting Boards

Step 4 As shown in part 4 of Figure 7-1, turn the two ejector levers inwards at an angle of about 60
until they hook on to the self-locking latches on the front panel. Ensure that the board is in close
contact with the backplane and that the front panel is inserted into the subrack.
Step 5 Press and fasten the screws on the front panel to secure the board, as shown in part b of Figure
7-1.
NOTE

The screws on the front panel have springs. Therefore, the screws can touch the corresponding holes of the
subrack only when you press the screws.

----End

Follow-up Procedure
Record the installation result in the templates provided in 13 Installation Records.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

32

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Installing the Signal Cables

About This Chapter


This chapter describes how to install the signal cables according to the layout requirements. The
signal cables to be installed include clock signal cables, Ethernet cables and optical cables. For
items and specifications for checking the installation of signal cables, see 11.1 Checklist for
BSC6910 Cable Installation.
8.1 Signal Cables to Be Installed
This section describes the signal cables to be installed on site.
8.2 Principles of Installing the Signal Cables
This section describes the principles of installing the signal cables. The cables should meet the
requirements for minimum bending radius, the principles of laying out cables, the principles of
routing cables, and the principles of binding cables.
8.3 Installing the Clock Signal Cables
The clock signal cables refer to the Y-shaped clock signal cable and the BITS clock signal
cable.The BSC6910 GSM and BSC6910 UMTS support the co-cabinet solution, meaning their
boards can be installed in one cabinet. If two independent BSCs and RNCs are installed in one
cabinet, their clock boards are connected to the clock board of other subracks of this set of
equipment.
8.4 Installing the Ethernet Cables
This section describes how to install the Ethernet cables. These cables are the EOMUa board
and the M2000 or the LAN of the customer, the Ethernet cable between the FG2c/FG2d board
and the other device.
8.5 Installing the Inter-SCUb SFP+ High-Speed Cables Between Different Subracks
This section describes how to install the inter-SCUb SFP+ high-speed cables between subracks.
Inter-SCUb SFP+ high-speed cables have been pre-installed in the cabinet for a newly deployed
site. The cables needs to be installed at the site only if the cables need to be connected between
cabinets and the cables are used for a expanded site.
8.6 Installing the Optical Cables
This section describes how to install the optical cables between the GOUc/GOUd/POUc/
EXOUa board and the other equipment.
Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

33

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

8.7 Installing the EMU RS485 Communication Cables


This section describes how to install the EMU RS485 communication cable between the
BSC6910 and the EMU.
8.8 Connecting the GPS Surge Protector to the GCGa Board
For the cabinet that is equipped with the GCGa board, install an indoor surge protector on the
top of the cabinet, and then use the cable for the input of the satellite signals to connect the port
Protect of the GPS surge protector on the top of the cabinet and the port ANT on the GCGa
board. For items and specifications for checking the installation of the GPS antenna system, see
11.2 Checklist for the Installation of the BSC6910 GPS Antenna System.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

34

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

8.1 Signal Cables to Be Installed


This section describes the signal cables to be installed on site.
Table 8-1 lists the signal cables to be installed.
Table 8-1 Signal cable
Name

Cable Type

Function

Remarks

Clock
cables

Y-shaped clock
cable

Connects the GCUa board to the


SCUb board.

BITS clock
cable

Connects the GCUa board to the BITS


clock.

BSC6910 uses the


BITS clock cables to
transmit the reference
clock signals
extracted from the
BITS clock source,
see 8.3 Installing the
Clock Signal Cables.

Shielded
straightthrough cable

Connects the EOMUa/ESAUa board


to the M2000 or the LAN of the
customer.

The shielded straightthrough cables are


made before delivery.

Ethernet
cable

Ethernet cable

Optical
cable

Issue 03 (2013-07-30)

LC/PC-LC/PC
single-mode/
multimode
optical cable or
LC/PC-FC/PC
single-mode/
multimode
optical cable or
LC/PC-SC/PC
single-mode/
multimode
optical cable

Connects the FG2c/FG2d board to


other devices.
Connects the /GOUc/GOUd/POUc/
EXOUa board to the ODF, the SCUbs
in two subracks are interconnected if
the cable layout distance between two
subracks is longer than 10 m.

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

The single-mode
optical cables are
yellow, and the
multimode optical
cables are orange, see
8.6 Installing the
Optical Cables.

35

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Name

Cable Type

Function

Remarks

Highspeed
cable

SFP+ highspeed cable

Connects SCUb boards in different


subracks.

When a new site is


deployed, the interSCUb cables are
already installed on
the MPR cabinet
configured with two
or three subracks.
When the capacity of
a site is expanded, the
inter-SCUb cables
need to be made and
installed on site, see
8.5 Installing the
Inter-SCUb SFP+
High-Speed Cables
Between Different
Subracks.
NOTE
10GE ports numbered
from 8 to 11 are
recommended for the
interconnection
between SCUb boards.

Optical cables are


used if the cable
layout distance
between subracks in
different cabinets is
longer than 10 m.
Other
signal
cables

EMU RS485
Communicatio
n Cable

Connects the main subrack to the


EMU.

The crossover cables


are made before
delivery.

Signal cable of
the alarm box

Connects the alarm box to the Local


Maintenance Terminal (LMT) PC.

The crossover cables


are made before
delivery.

For details about the signal cables, see Cables.

8.2 Principles of Installing the Signal Cables


This section describes the principles of installing the signal cables. The cables should meet the
requirements for minimum bending radius, the principles of laying out cables, the principles of
routing cables, and the principles of binding cables.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

36

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Principles of Installing the Signal Cables


When installing the signal cables, take the following precautions:
l

The optical cable should not be stretched roughly or stepped on, and heavy objects should
not be placed on the cable to avoid damage.

The optical connector not in use must be covered with a dustproof cap.

If the connectors of the signal cables are made before delivery, you should pack the
connectors with soft and durable materials such as a packing bag during cabling.

Protect the jackets of the signal cables from being damaged during the routing.

When coiling the extra length of optical cables on the fiber management tray, apply proper
force to avoid damaging the optical.

The actual installation positions must meet the requirements of site survey and data
configuration.

When installing the signal cables, you should route the extra length of the interconnection
cables on both sides of the cabinet according to the requirement for the bending radius of
the cables.

The related operation guide is intended for only the installation method. The actual
installation position of cables should meet the requirements of site survey and should be
consistent with the data configuration scheme.

Minimum Bending Radius


The bending radius of the signal cable meets the requirements of all types of cables. Table
8-2 lists the bending radius of the signal cables.
Table 8-2 Bending radius of the signal cables
Wire

Bending Radius

BITS clock signal cable

Not less than 45 mm

Y-shaped clock cable

Not less than 25 mm

Ethernet cable

Not less than 25 mm

Optical cable

Not less than 40 mm

SFP+ high-speed cable

Not less than 40 mm

EMU RS485 Communication Cable

Not less than 25 mm

EOMUa serial port cable

Not less than 25 mm

NOTE
The port does not require a signal cable
or connection to other devices when the
system runs properly. Therefore,
equipment security is not affected.

Alarm box signal cable

Issue 03 (2013-07-30)

Not less than 25 mm

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

37

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Principles of Routing the Signal Cables


To facilitate maintenance and capacity expansion, follow these principles when routing cables.
The layout sequence in overhead and underfloor cabling modes must be the same.
While routing the cables at the back of the cabinet, you should route SFP+ high-speed cables
along the left side of the cabinet and clock signal cables along the right side of the cabinet. After
routing SFP+ high-speed cables and clock signal cables, route Ethernet cables from the middle
column to the external column, and then optical cables.For example, on the left side of the
cabinet, lay out the following cables from the middle standing pillar to the external standing
pillar: (1) SFP high-speed cable (2) Network cable (3) Optical fiber (4) Power cable, as shown
in Figure 8-1. On the right side of the cabinet, lay out the following cables from the middle
standing pillar to the external standing pillar: (1) Y-shaped clock cable (2) Network cable (3)
Optical fiber (4) Power cable, as shown in Figure 8-2.
Figure 8-1 Principles for laying out signal cables (on the left side of the cabinet)

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

38

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Figure 8-2 Principles for laying out signal cables (on the right side of the cabinet)

Requirements of Routing the Signal Cables


The requirements for routing signal cables are as follows:
l

Protect the jackets of the signal cables from being damaged during the routing.

Hold the connector when plugging out the signal cables to protect the signal cable from
damage.

When installing the signal cables, you should route the extra length of the interconnection
cables on both sides of the cabinet according to the requirement for the bending radius of
the cables.

For combined cabinets, the extra signal cable in front of the cabinet should be routed along
the cable ladder or at one side of the cabinet. It should not be placed in the gap between the
combined cabinets.

The signal cables must be separated from the power cables.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

39

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

The bending radius of the signal cable satisfies the requirements of all kinds of cables.
Table 8-2 lists the bending radius of the signal cables.

Extra length of the signal cable should be reserved near the connector.

The signal cables must be neatly laid in the rack, according to the engineering design.

If the height difference between the cable tray and the top of the cabinet exceeds 800 mm,
a vertical cable ladder must be used. The signal cables and the lower part of the downward
cable ladder must be bound together.

The routing should be in accordance with the engineering design.

The cabling is clear, proper, and smooth at the bends. The cables are laid in parallel.

The signal cable layout facilitates maintenance and future expansion.

Before routing cables outside the cabinet, coat cables with corrugated pipes to protect cables
from damages.

Requirements of Binding the Signal Cables


The requirements of binding the signal cables are as follows:
l

The signal cables and power cables must be bound separately. The spacing between cable
ties must be at least 150 mm.

The twine for binding the cables must be coated with wax.

The signal cables must be bound at the entrance and exit of the cable trough and at the
turning points, as shown in Figure 8-3.
Figure 8-3 Bending and binding signal cables

The optical cables must be neatly bound in pairs.

The cables on the cable tray must be bound neatly.

The cable ties must face the same direction and be tied with proper tightness.

The cable ties/binding strap must be placed at regular intervals, 200 mm for Ethernet
cables, and 150 mm for optical cables.

The extra length of the cable ties must be cut and the cut surface must be smooth.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

40

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

8.3 Installing the Clock Signal Cables


The clock signal cables refer to the Y-shaped clock signal cable and the BITS clock signal
cable.The BSC6910 GSM and BSC6910 UMTS support the co-cabinet solution, meaning their
boards can be installed in one cabinet. If two independent BSCs and RNCs are installed in one
cabinet, their clock boards are connected to the clock board of other subracks of this set of
equipment.

8.3.1 Installing the Y-Shaped Clock Cables


This section describes how to install the Y-shaped clock cables between the GCUa/GCGa board
in the MPS and the SCUa/SCUb board in the EPS. When a new site is deployed, the Y-shaped
clock cables are already installed on the MPR cabinet configured with two or three subracks.
When the capacity of a site is expanded, the Y-shaped clock cables need to be installed on site.

Prerequisites
l

The Y-shaped clock cables required for the installation are available.

The required cable ties and wax strings are available.

The tools required for the installation are available. The tools are ESD gloves or ESD wrist
strap, and wire cutter.

The wires in the Y-shaped clock cables are intact, the jacket of the cable is undamaged,
and the pins in the connector are straight.

Context

NOTICE
Wear an ESD wrist strap and connect it to the ESD connector on the cabinet before you perform
the operation. For details, see Wearing an ESD Wrist Strap.
For the installation positions of the Y-shaped clock cables in the cabinet, see Connections of
Signal Cables for the MPR.
The Y-shaped clock cable has three specifications in length: 2.0 m, 2.5 m, and 9.7 m. The 2.0
m cable is used to connect the GCUa/GCGa board to the SCUa/SCUb board in two adjacent
subracks in one cabinet. The 2.5 m cable is used to connect the GCUa/GCGa board to the SCUa/
SCUb board in different subracks in one cabinet. The 9.7 m cable is used to connect the GCUa/
GCGa board to the SCUa/SCUb board in different cabinets.

Procedure
Step 1 Attach formal labels to identify the signal cables of the same type when the number of signal
cables of the same type to be installed is more than one.
Step 2 Put one end with an RJ45 connector to the SCUa/SCUb board. Take one end of the cable that
has two RJ45 connectors and lead it from the SCUa/SCUb board to the distribution post in the
Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

41

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

cable trough. Estimate the length of the cable between the SCUa/SCUb board and the GCUa/
GCGa board. The bending radius must be at least 25 mm. Then, bind the cable and the distribution
post. Route the cable along the cable trough to the GCUa/GCGa board.
Step 3 Route the cable to the GCUa/GCGa according to the requirements specified in 8.2 Principles
of Installing the Signal Cables and the engineering requirements. The cabling of the Y-shaped
clock cables is described in Table 8-3.
Table 8-3 Cabling of the Y-shaped clock cables
Condition

Cabling mode

Action

The SCUa/SCUb and the


GCUa/GCGa are located in
the same cabinet.

Cabling within the cabinet

Lead the optical cables to the


GCUa/GCGa board through
the cable trough beneath the
MPS along the column of the
cabinet.

The SCUa/SCUb and the


GCUa/GCGa are located in
different cabinets.

Overhead cabling

1. Route the cable upwards


through the cable hole on
top of the cabinet and to
the cable tray. Then, lead
the cable along the cable
tray to the cable hole on
top of another cabinet.
2. Route the cable upwards
or downwards along the
column to the cable
trough under the subrack
that holds the board.
Then, lead the cable along
the cable trough to the
GCUa/GCGa board.

Underfloor cabling

1. Lead the cable out of the


cabinet along the column
through the lower cable
hole. Then, lead the cable
to the cabinet through the
lower cable hole
according to the cabling
and engineering
requirements.
2. Route the cable upwards
along the column to the
cable trough under the
subrack that holds the
board. Then, lead the
cable along the cable
trough to the GCUa/
GCGa board.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

42

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Step 4 Cut off the cable ties that are attached on the distribution post of the cable trough. Insert the
RJ45 connector at the SCUa/SCUb end of the clock cable into the corresponding port on the
SCUa/SCUb. Then, insert the two RJ45 connectors at the GCUa/GCGa end into the two ports
on the active and standby GCUa/GCGa boards, as shown in Figure 8-4.
Figure 8-4 Connecting the Y-shaped clock cables

----End

Follow-up Procedure
Record the installation results in the templates provided in 13 Installation Records.

8.3.2 Installing the BITS Clock Signal Cables


This section describes how to install the BITS clock signal cables between the GCUa/GCGa
board and the BITS clock source. Based on the impedance, the BITS clock signal cables are
classified into 75-ohm coaxial clock cable and 120-ohm clock conversion cable.
Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

43

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Prerequisites
l

The required 75-ohm coaxial clock cables or 120-ohm clock conversion cables are
available.

The required cable ties and wax strings are available.

The tools required for the installation are available. The tools are ESD gloves or ESD wrist
strap, and wire cutter.

Context

NOTICE
Wear an ESD wrist strap and connect it to the ESD connector on the cabinet before you perform
the operation. For details, see Wearing an ESD Wrist Strap.
The BITS clock signal cables are classified into 75-ohm coaxial clock signal cable and 120-ohm
clock conversion cable. The functions and connection modes of the clock cables are as follows:
l

75-ohm coaxial clock cable


One end of the 75-ohm coaxial clock cable is fixed to the GCUa/GCGa board through the
SMB connector. The other end is fixed to the BITS clock source through the connector
delivered with the clock source.

120-ohm clock conversion cable


The 120-ohm clock conversion cable completes the conversion from 75 ohms to 120 ohms.
One end of the 120-ohm clock conversion cable is fixed to the GCUa/GCGa board through
the SMB connector. The other end is fixed to the BITS clock source through the connector
delivered with the clock source.

For the installation positions of the 75-ohm coaxial clock signal cable and 120-ohm clock
conversion cable in the cabinet, see Connections of Signal Cables for the MPR.

Procedure
Step 1 Route one end of the 75-ohm coaxial clock signal cable or 120-ohm clock conversion cable to
the GCUa/GCGa board, and lead the other end to the distribution post in the cable trough.
Estimate the length of the cable between boards. Then, bind the cable and the distribution post,
and route the cable along the cable trough to the left side of the cabinet.
Step 2 Route the cable along the cable trayto the BITS clock according to the cabling and engineering
requirements.
Step 3 Insert one end of the 75-ohm coaxial clock signal cable or 120-ohm clock conversion cable into
the CLKIN 0 or CLKIN 1 port on the GCUa/GCGa board, and insert the other end into the port
of the BITS clock source, as shown in Figure 8-5. Ensure that the connectors of cables are
appropriately linked to the ports.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

44

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Figure 8-5 Connecting the cables between the GCUa/GCGa and the BITS clock

NOTE

The 120-ohm clock conversion cable contains two SMB connectors on one end. Only one SMB connector
is used for the connection with the GCUa/GCGa board. The other SMB connector is bound with the wire
bushing through cable ties. Pay attention to the connection when using the 120-ohm clock conversion cable.

----End

Follow-up Procedure
Record the installation results in the templates provided in 13 Installation Records.

8.4 Installing the Ethernet Cables


This section describes how to install the Ethernet cables. These cables are the EOMUa board
and the M2000 or the LAN of the customer, the Ethernet cable between the FG2c/FG2d board
and the other device.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

45

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

8.4.1 Arranging the Ethernet Cables


This section describes how to arrange the Ethernet cables. Before installation, you should obtain
the Ethernet cables of appropriate length and attach formal or temporary labels to the cables.

Prerequisites
l

The shielded cables to be installed are available.

The required cable ties and wax strings are available.

The tools required for the installation are available. The tools are ESD gloves or ESD wrist
strap, wire cutter, Ethernet cable tester, and long tape measure or ruler.

Context
NOTE

l The shielded straight-through Ethernet cables between the EOMUa /EGPUa /FG2c/FG2d board and
the other equipment. The Ethernet cables need to be only installed on site.

Procedure
Step 1 Measure the distance between Ethernet ports to be connected.
Step 2 Based on the measurement, obtain an Ethernet cable of appropriate length. The cable should be
a little longer than the required length.
Step 3 Attach formal or temporary labels to both ends of the cable for easy identification. The contents
on the temporary labels are not restricted because they are only for distinguishing the cables
after the layout.
----End

8.4.2 Installing Ethernet Cables Between the EOMUa and the LAN
One end of the Ethernet cables for the EOMUa is connected to the Ethernet ports on the
EOMUa, and the other end is connected to the Ethernet ports of the LAN.

Prerequisites
l

The straight-through cables to be installed are available.

Cable ties or wax strings are available.

Required tools are available, including an ESD wrist strap or gloves and a cable cutter.

Context

NOTICE
Wear an ESD wrist strap and connect it to the ESD connector on the cabinet before you perform
the operation. For details, see Wearing an ESD Wrist Strap.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

46

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Procedure
l

BSC6910 and ECO6910 are configured in different cabinets.


Scenario

Connections

Operation

Scenario 1: No
cable bridge is
installed on the
air defense frame
and air deflector.

The Ethernet cables are


connected to the
EOMUa board

1. Route the Ethernet cables on the


cable ladder or cable trough outside
the cabinet according to the
requirements for routing signal
cables and the cabling method on site.
2. Route one end of the Ethernet cables
to the peer equipment, and properly
insert the cables into the Ethernet
ports on the peer equipment.
3. Route the other end of the Ethernet
cables into the cabinet through the
cable hole at the top or bottom of the
cabinet.
4. Route the Ethernet cables to the air
defence subrack, and loosen the four
screws on the cover plate for the air
defence subrack to remove the cover
plate.
5. Route the Ethernet cables out of the
air defence subrack, and properly
insert the cables to the ports on the
EOMUa.
6. Use cable ties to bind the Ethernet
cables in the air defence frame.
7. Tighten the four screws on the cover
plate for the air defence subrack, as
shown in Figure 8-6.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

47

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Scenario

Connections

Operation

Scenario 2:
Cable bridges are
installed on the
air defense frame
and air deflector.

The Ethernet cables are


connected to the
EOMUa board

1. Route the Ethernet cables on the


cable ladder or cable trough outside
the cabinet according to the
requirements for routing signal
cables and the cabling method onsite.
2. Route one end of the Ethernet cables
to the peer equipment, and properly
insert the cables into the Ethernet
ports on the peer equipment.
3. Route the other end of the Ethernet
cables into the cabinet through the
cable hole at the top or bottom of the
cabinet.
4. Connect the cables to the EOMUa
board and tighten the cables.
5. Bind the cables to the cable bridge
and then route the cables out of the
cabinet, as shown in Figure 8-7

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

48

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Figure 8-6 Connections of Ethernet cables between the EOMUa and the LAN (taking the
air defense frame on which no cable bridge is installed as an example)

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

49

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Figure 8-7 Connections of Ethernet cables between the EOMUa and the LAN (taking the
air defense frame on which the cable bridge is installed as an example)

Issue 03 (2013-07-30)

BSC6910 and ECO6910 are configured in different subracks in one cabinet.

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

50

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Scenario

Connections

Operation

Scenario 1: No cable
bridge is installed on
the air defense frame
and air deflector.

The Ethernet cables are


connected to the
EOMUa board in the
middle subrack.

1. Route the Ethernet cables on the


cable ladder or cable trough
outside the cabinet according to
the requirements for routing
signal cables and the cabling
method on site.
2. Route one end of each Ethernet
cable to the air deflector along
one side of the cabinet.
3. Connect the cables to the
EOMUa board and tighten the
cables.
4. Bind the Ethernet cables on the
surface of the air deflector using
cable ties, as shown in Figure
8-8.

The Ethernet cables are


connected to the
EOMUa board in the
lower subrack.

Scenario 2: Cable
bridges are installed
on the air defense
frame and air
deflector.

Issue 03 (2013-07-30)

The Ethernet cables are


connected to the
EOMUa board in the
middle subrack.
The Ethernet cables are
connected to the
EOMUa board in the
lower subrack

For detailed operation about cable


connections, see BSC6910 and
ECO6910 are configured in
different cabinets Scenario 1: No
cable bridge is installed on the air
defense frame and air deflector.
For detailed operation about cable
connections, see BSC6910 and
ECO6910 are configured in
different cabinets Scenario 2:
Cable bridges are installed on the
air defense frame and air
deflector.

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

51

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Figure 8-8 Connections of Ethernet cables between the EOMUa and the LAN

NOTE

Two or four Ethernet cables can be used to connect active and standby EOMUa boards to the LAN,
depending on customer requirements.

----End

Follow-up Procedure
Record the installation result in 13 Installation Records.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

52

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

8.4.3 Installing the Ethernet Cables Between the ESAUa Board and
the LAN
This section describes how to install the Ethernet cables between the ESAUa board and the LAN.
You should route one end of the cable to the ESAUa board and lead the other end through the
Ethernet port on the ESAUa board.

Prerequisites
l

The straight-through cables to be installed are available.

The required cable ties and wax strings are available.

The tools required for the installation are available. The tools are ESD gloves or ESD wrist
strap, and wire cutter.

Context

NOTICE
Wear an ESD wrist strap and connect it to the ESD connector on the cabinet before you perform
the operation. For details, see Wearing an ESD Wrist Strap.

Procedure
Step 1 Lay the Ethernet cable on the cable ladder or in the cable trough outside the cabinet and route
the Ethernet cable according to the requirements for routing signal cables and the cabling method
onsite.
Step 2 Route one end of the Ethernet cables to the peer equipment, and properly insert the cables into
the Ethernet ports on the peer equipment.
Step 3 Route the other end of the Ethernet cables into the cabinet through the cable hole at the top or
bottom of the cabinet.
Step 4 Route the Ethernet cables to the air defence subrack, and loosen the four screws on the cover
plate for the air defence subrack to remove the cover plate.
Step 5 Route the Ethernet cables out of the air defence subrack, and properly insert the cables to the
ports on the ESAUa.
Step 6 Use cable ties to bind the Ethernet cables in the air defense subrack.
Step 7 Tighten the four screws on the cover plate for the air defence subrack, as shown in Figure 8-9.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

53

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Figure 8-9 Connections of Ethernet cables between the ESAUa board and the LAN

----End

Follow-up Procedure
Record the installation result in the templates provided in 13 Installation Records.
Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

54

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

8.4.4 Installing the Ethernet Cables Between the FG2c/FG2d Board


and the Other Equipment
This section describes how to install the Ethernet cables between the FG2c/FG2d board and the
other equipment.

Prerequisites
l

The straight-through cables to be installed are available.

The required cable ties and wax strings are available.

The tools required for the installation are available. The tools are ESD gloves or ESD wrist
strap, and wire cutter.

Context

NOTICE
Wear an ESD wrist strap and connect it to the ESD connector on the cabinet before you perform
the operation. For details, see Wearing an ESD Wrist Strap.

Procedure
Step 1 Lay the Ethernet cable on the cable ladder or in the cable trough outside the cabinet and route
the Ethernet cable according to the requirements for routing signal cables and the cabling method
onsite.
Step 2 Lead one end of the Ethernet cable to the Ethernet port on the peer equipment.
Step 3 According to the actual scenarios, lead the other end of the cable into the cabinet through the
cable hole either at the top of or at the bottom of the cabinet.
Step 4 Lead one end of the Ethernet cable along the middle standing pillar in the cabinet, lead the other
end of the Ethernet cable to the cable trough beneath the subrack where the FG2c/FG2d board
is installed, and then lead the cable to the Ethernet port on the FG2c/FG2d board along the cable
trough.
Step 5 Tightly insert the cables into the corresponding Ethernet ports on the FG2c/FG2d board and on
the peer equipment, as shown in Figure 8-10.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

55

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Figure 8-10 Connection between the FG2c/FG2d board and the other equipment

----End

Follow-up Procedure
Record the installation result in the templates provided in 13 Installation Records.

8.5 Installing the Inter-SCUb SFP+ High-Speed Cables


Between Different Subracks
This section describes how to install the inter-SCUb SFP+ high-speed cables between subracks.
Inter-SCUb SFP+ high-speed cables have been pre-installed in the cabinet for a newly deployed
site. The cables needs to be installed at the site only if the cables need to be connected between
cabinets and the cables are used for a expanded site.
Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

56

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Prerequisites
l

The straight-through cables to be installed are available.

The unshielded straight-through cables to be installed are available.

The required cable ties and wax strings are available.

The tools required for the installation are available. The tools are ESD gloves or ESD wrist
strap, and wire cutter.

Context
NOTE

The BSC6910 GSM and BSC6910 UMTS support the co-cabinet solution, meaning their boards can be
installed in one cabinet. If two independent BSCs and RNCs are installed in one cabinet, their clock boards
are connected to the SCU board of other subracks of this set of equipment.

Connections of Signal Cables for the MPR, Connections of Signal Cables for the EPR describe
the installation positions of the inter-SCUb SFP+ high-speed cables in the cabinet.
The Inter-SCUb SFP+ High-Speed Cables is classified into two types in length: 3 m, 10 m. The
3 m cable is used for the connection between subracks in the same cabinet. The 10 m cable is
used for the connection of subracks in different cabinets.
The crossed and straight connection principle is as follows in Figure 8-11.
Figure 8-11 Crossed and straight connections between two subracks

NOTE

l A pair of active and standby SCUb boards are installed in each subrack. Each SCUb has two ports for
inter-subrack connection. Therefore, each subrack has four ports for inter-subrack connection. The
ports are connected crossly or straightly, as shown in Figure-X. Ports 0 are used for straight connection
and ports 1 are used for crossed connection.
l Multi-mode optical cables are used when the cabling length between subracks is longer than 10 m.

Procedure
l

Issue 03 (2013-07-30)

1.

Lay one end of the cable to the SCUb board (usually starting from the SCUb boards
in the main surback, which is located at the bottom of the cabinet). Lead the other end
Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.

57

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

to the other SCUb board. Estimate the length of the cable between the SCUb boards.
The bending radius must be at least 25 mm. Then, bind the cable and the distribution
post in the cable trough.
2.

Route the cable to the SCUb board according to the requirements specified in 8.2
Principles of Installing the Signal Cables and the engineering requirements. The
cabling is described in Table 8-4.
Table 8-4 Cabling of the inter-SCUb cables when the TCS is configured locally
Condition

Cabling Mode

Action

The SCUb boards to be


connected are located in
the same cabinet.

Cabling within
the cabinet

Route the cable upwards along the


column to the cable trough under
the subrack where the SCUb board
is located. Then, lead the cable to
the SCUb board along the cable
trough.

The SCUb boards to be


connected are located in
different cabinets.

Overhead
cabling

1. Route the cable upwards


through the cable hole on top of
the cabinet and to the cable tray.
Then, lead the cable along the
cable tray to the cable hole on
top of another cabinet.
2. Route the cable downwards
along the column to the cable
trough under the subrack where
the SCUb board is located.
Then, lead the cable along the
cable trough to the SCUb board.

Under cabling

1. Lead the cable out of the cabinet


along the column through the
lower cable hole. Then, lead the
cable to the cabinet through the
lower cable hole according to
the cabling and engineering
requirements.
2. Route the cable along the
column to the cable trough
under the subrack where the
SCUb board is located. Then,
lead the cable along the cable
trough to the SCUb board.

3.

Issue 03 (2013-07-30)

Cut the cable tie that binds the cable and the distribution post in the cable trough. Then,
insert the two ends of the cable into the ports on the SCUb boards in slots 20 and 21,
as shown in Figure 8-12.

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

58

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Figure 8-12 Connection of the inter-SCUb cables in full configuration of two cabinets

NOTE

In Figure 8-12, blue lines are SFP+ high-speed cables.

4.

Bind the cables that are led out of the same board by using cable ties.

5.

Check all the ports connected with SFP+ High-Speed cables, and make sure both
crossed and straight connections correct, as show in Figure 8-11.

Connections of Signal Cables on the SCUb Board shows the connections of signal cables
for the SCUb board.

NOTICE
The inter-SCUb cables are installed close to the front door of the cabinet. After the cables
are installed, be careful not to remove them when you open the front door.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

59

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables


NOTE

l After installing SFP+ high-speed cables, check the indicators corresponding to ports 8 to 11 (10G
LINK) on the SCUb boards as follows:
l If the indicators corresponding to the 10G LINK ports on either SCUb board are on or blink, the
SFP+ high-speed cables are connected securely.
For example, after the SFP+ high-speed cables between subracks 0 and 1 are connected, check the
indicators corresponding to the 10G LINK ports on both ends of the cables. The cables are
connected securely if the indicators on the SCUb board in either subrack 0 or 1 are on or blinking.
l The corresponding indicators on the SCUb board can indicate the states of the SFP+ ports (ports 8 to
11) after the power-on check is finished. This does not require loading or configuration of data.

----End

8.6 Installing the Optical Cables


This section describes how to install the optical cables between the GOUc/GOUd/POUc/
EXOUa board and the other equipment.

8.6.1 Using the Accessories of the Optical Cable


This section describes how to use the SC/PC, VC/PC, and LC/PC adapters and also how to use
the fiber management tray.

Using the SC/PC Adapter


An SC/PC adapter connects to an optical cable that has an SC/PC connector.

Context
Figure 8-13 shows the appearance of an SC/PC adapter.
Figure 8-13 Appearance of an SC/PC adapter

Procedure
Step 1 Align one SC/PC connector of an optical cable with the SC/PC adapter, and feed the connector
into the adapter. If you hear a clicking sound, the connector is securely connected.
Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

60

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Step 2 Use the same method to connect another SC/PC connector of the optical cable to the other end
of the SC/PC adapter.
----End

Using the FC/PC Adapter


An FC/PC adapter connects to an optical cable that has an FC/PC connector.

Context
Figure 8-14 shows the appearance of an FC/PC adapter.
Figure 8-14 Appearance of an FC/PC adapter

Procedure
Step 1 Align one FC/PC connector of an optical cable with the FC/PC adapter, feed the connector into
the adapter, and then fasten the connector.
Step 2 Use the same method to connect another FC/PC connector of the optical cable to the other end
of the FC/PC adapter.
----End

Using the LC/PC Adapter


An LC/PC adapter connects to an optical cable that has an LC/PC connector.

Context
Figure 8-15 shows the appearance of an LC/PC adapter.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

61

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Figure 8-15 Appearance of an LC/PC adapter

Procedure
Step 1 Align one LC/PC connector of an optical cable with the LC/PC adapter, and feed the connector
into the adapter. If you hear a clicking sound, the connector is securely connected.
Step 2 Use the same method to connect another LC/PC connector of the optical cable to the other end
of the LC/PC adapter.
----End

Using the Fiber Management Tray


This section describes how to use the fiber management tray. When routing optical cables, coil
the redundant cables on the fiber management tray below the rear cable trough at the rear of the
cabinet.

Context
Figure 8-16 shows the installation position of the fiber management tray.
Figure 8-16 Installation position of the fiber management tray

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

62

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Procedure
Step 1 Route optical cables upwards or downwards to the undermount fiber management tray along the
middle standing pillar in the cabinet. If both optical cables and Ethernet cables are available,
route Ethernet cables along the side next to the middle standing pillar.
Step 2 Wrap redundant optical cables on the fiber management tray according to the operation method
printed on the cover of the fiber management tray.
NOTE

If only one optical cable is wrapped, the length of the wrapped cable is about 80 m. If 100 optical cables
are wrapped, the length of each wrapped cable is about 0.5 m. Extra cables can be wrapped onto the ODF.

----End

8.6.2 Arranging the Optical Cables


This section describes how to arrange the optical cables. Before installing optical cables, you
should unpack and check them, attach temporary labels to them, and keep the corrugated pipes
ready.

Prerequisites
l

The required optical cables, optical connectors, and corrugated pipes are delivered to the
site.

The tools required for the installation are available. The tools are the tape measure, wire
cutter, diagonal pliers, and cable ties.

Procedure
Step 1 Check the optical module. If the metal sheet is exposed, push the optical module until you hear
a click sound.
Step 2 Take the optical cables out of the package and sort them by length and installation position.
Step 3 Check each optical cable. If the optical cable is broken or the jacket of the cable is damaged,
contact technical support engineers of Huawei for replacement.
Step 4 Remove the protective caps from the optical connectors of the optical cable and check whether
the connectors are clean. If they are clean, put the protective caps onto the connectors. If they
are not clean, clean the optical connectors, and then put the protective caps on to the connectors.
For details about how to clean the connectors, see Cleaning Fiber Connectors.
Step 5 Attach temporary labels to both ends of the cables. The contents on the temporary labels are not
restricted because they are only for distinguishing the cables after the layout.
Step 6 Distribute the corrugated pipes according to the following aspects: the quantity of the optical
cables and the length of the delivered corrugated pipes.
NOTE

l All the optical cables outside the cabinet should be covered with corrugated pipe.
l All the optical cables inside the cabinet do not need to be coated with corrugated pipe.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

63

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Step 7 Cut the corrugated pipes, and then cover the cut surface with PVC insulation tape.
Step 8 Cover the optical cables with the corrugated pipes.
----End

8.6.3 Installing the Optical Cables Between the EXOUa/GOUc/


GOUd/POUc Boards and the Other Equipment
This section describes how to install the optical cables between the EXOUa/GOUc/GOUd/
POUc board and other equipment. The end of the optical cable connected to the BSC6910 uses
an LC/PC connector, and the other end uses a connector as required.

Prerequisites
l

The optical cables and corrugated pipes to be installed are available.

The required cable ties, wax strings, binding straps, and optical labels are available.

The tools required for the installation are available. The tools are ESD gloves or ESD wrist
strap, wire cutter, and diagonal pliers.

Context

NOTICE
Wear an ESD wrist strap and connect it to the ESD connector on the cabinet before you perform
the operation. For details, see Wearing an ESD Wrist Strap.
For the installation positions of the optical cables between the EXOUa/GOUc/GOUd/POUc
board and the other equipment, see Connections of Signal Cables for the MPR, Connections of
Signal Cables for the EPR.
NOTE

If you need to remove the optical cables during the installation, do as follows:
l For the IC/PC or SC/PC connector, press the tab on the connector and remove the optical cable.
l For the FC/PC connector, unscrew the optical connector counterclockwise.

Procedure
Step 1 Lead the optical cables from the optical port of the EXOUa/GOUc/GOUd/POUc board to the
back (the side near the subrack) of rear cable trough beneath the subrack. Use cable ties to bind
the optical cables to the rear cable trough.
Step 2 Put the optical cables to one side of the cabinet through the bottom of the rear cable trough. (The
optical cables on slots 20 through 27 are put on the left side and those on slots 14 through 19
are put on the right side.) Coil the extra length of the optical cables on the fiber management
trays below the rear cable trough.
Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

64

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Step 3 Route the optical cables to the other equipment along the cable tray according to the requirements
specified in 8.2 Principles of Installing the Signal Cables and the engineering requirements.
You can use either the overhead cabling or the underfloor cabling.
Step 4 Connect the optical cables to the optical ports, as shown in Figure 8-17.
Figure 8-17 Connection of the optical cables between the EXOUa/GOUc/GOUd/POUc and the
other equipment(taking the GOUc as an example)

1.

Remove the protective caps from the optical connectors and ports, and store the protective
caps for future use.

2.

Insert the LC/PC connectors into the ports labeled "TX" on the interface boards until you
hear a slight click.

3.

Repeat Step 4.2 to insert the LC/PC connectors at one end of another optical cable into the
ports labeled "RX" on the interface boards.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

65

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

4.

Record the relationship between the optical cables and the optical ports to help correctly
connect the optical cables to the peer equipment.

Step 5 Connect the other end of each optical cable to the peer equipment. For the detailed procedure,
refer to Table 8-5.
Table 8-5 Connecting different types of connectors to peer equipment
Peer Equipment

Connectors of
Optical Cables

Connection Method

ODF

SC/PC

Insert the connectors into the corresponding


optical ports on the flange of the ODF until you
hear a slight click.

LC/PC

Peer network element


(NE)

Optical cable of peer


equipment

FC/PC

Insert the connectors into the corresponding


optical ports on the flange of the ODF and
screw the connectors.

SC/PC

Insert the connectors into the corresponding


optical ports on the peer NE until you hear a
slight click.

LC/PC
FC/PC

Insert the connectors into the corresponding


optical ports on the peer NE and screw the
connectors.

SC/PC

Optical cable adapters are required to connect


the optical cables.

LC/PC
FC/PC

----End

Follow-up Procedure
Record the installation result in the templates provided in 13 Installation Records.

8.7 Installing the EMU RS485 Communication Cables


This section describes how to install the EMU RS485 communication cable between the
BSC6910 and the EMU.

Prerequisites
l

The RS485 communication cable to be installed is available.

The wires in the RS485 communication cable are intact, the jacket of the cable is
undamaged, and the pins in the connector are straight.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

66

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Context

NOTICE
The ELU port is a reserved port and is not used now. Please do not connect any cable to it.
NOTE

l The RS485 communication cable is used to connect the EMU environment monitoring instrument
(EMI) and main subrack.
l The EMU EMI has two types: type A and type B. Type A and B are wall-mounted. The methods of
installing the RS485 communication cable for type A and type B are the same. The following takes the
type-B EMI as an example to describe how to install the RS485 communication cable.

Procedure
Step 1 Attach the DB9 male connector at one end of the RS485 communication cable to the DB9 female
connector on the EMI.
Step 2 Attach the RJ45 connector at the other end of the RS485 communication cable to EMU terminal
of the main subrack, as shown in Figure 8-18.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

67

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Figure 8-18 Connections of cables between the EMU and the PEM

----End

8.8 Connecting the GPS Surge Protector to the GCGa Board


For the cabinet that is equipped with the GCGa board, install an indoor surge protector on the
top of the cabinet, and then use the cable for the input of the satellite signals to connect the port
Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

68

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Protect of the GPS surge protector on the top of the cabinet and the port ANT on the GCGa
board. For items and specifications for checking the installation of the GPS antenna system, see
11.2 Checklist for the Installation of the BSC6910 GPS Antenna System.

Prerequisites
l

The indoor surge protector to be installed, its fastener, and the signal cable used to connect
the GPS surge protector to the GCGa board are ready.

The tool required during the installation, that is, the crosshead screwdriver, is ready.

Context

NOTICE
Wear an ESD wrist strap and connect it to the ESD connector on the cabinet before you perform
the operation. For details, see Wearing an ESD Wrist Strap.
The signal cables refer to the 1 m and 2.5 m cables. Thus, a 3.5 m signal cable is made for the
input GPS signals. Figure 8-19 shows the connection between the GPS surge protector and the
GCGa board.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

69

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Figure 8-19 Connecting the GPS surge protector to the GCGa board

Procedure
Step 1 Install the surge protector to its fastener, as shown in Figure 8-20.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

70

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables

Figure 8-20 Installing the surge protector to its fastener

1.

Remove the retention screws at the GND and Surge ports from the indoor GPS surge
protector.

2.

Put the surge protector onto the fastener, and then tighten the retention screws on the GND
and Surge ports. Ensure that the GPS surge protector is well connected to the fastener.

Step 2 Use the bolt to fix the fastener to the top of the cabinet and ensure that the fastener is reliably
grounded. Refer to Figure 8-21.
Figure 8-21 Installing the fastener of the surge protector

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

71

BSC6910 GSM
Installation Guide

8 Installing the Signal Cables


NOTE

l You are advised to route the clock signal cable between the GCGa board and surge protector along the
right side of the cabinet, because the GCGa board is installed in a slot at the right side of the subrack.
l You are advised to route the feeder between the GPS antenna and surge protector along the left side
of the cabinet in the underfloor cabling mode. In addition, you must leave a clearance greater than 30
mm between the feeder and power cable, and between the feeder and signal cable. For details on the
underfloor cabling mode.

Step 3 Connect the N type female connector of the 1 meter long cable to the N type male connector of
the 2.5 meter long cable, and thus a 3.5 meter long cable is formed.
Step 4 Along the left side at the front of the cabinet, lead the end (with the elbow SMA connector) of
the cable to the cable trough beneath the MPS subrack, and then lead the end to port ANT on
the GCGa board along the cable trough.
Step 5 Lead the other end (with the N-type female connector) of the cable upwards along the mounting
bar on the left at the front of the cabinet and through the cabling holes on the top of the cabinet
until the cable end reaches the GPS surge protector.
Step 6 As shown in Figure 8-19, connect the elbow SMA connector to port ANT on the GCGa board.
Lead the N-type female connector to the port Protect of the surge protector on the top of the
cabinet, and then fasten the nut.
----End

Follow-up Procedure
Record the installation result in the templates provided in 13 Installation Records.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

72

BSC6910 GSM
Installation Guide

9 Installing the Alarm Box and the Computer Serving as the


LMT

Installing the Alarm Box and the Computer


Serving as the LMT

About This Chapter


This section describes how to install an alarm box and a computer serving as the LMT. If you
are installing the computer and the alarm box in the equipment room, you can install them along
with the BSC6910 equipment. For items and specifications for checking the installation of the
LMT computer and the alarm box, see 11.3 Checklist for the Installation of the LMT
Computer and Alarm Box.
9.1 Installing the Computer Serving as the LMT
This section describes how to install a computer serving as the LMT. If you are installing the
computer in the equipment room, you can install it along with the BSC6910 equipment.
9.2 Installing the Alarm Box
This section describes how to install an alarm box. If you are installing the alarm box in the
equipment room, you can install it along with the BSC6910 equipment.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

73

9 Installing the Alarm Box and the Computer Serving as the


LMT

BSC6910 GSM
Installation Guide

9.1 Installing the Computer Serving as the LMT


This section describes how to install a computer serving as the LMT. If you are installing the
computer in the equipment room, you can install it along with the BSC6910 equipment.

Prerequisites
l

The components required for the installation are available. The components include the
computer, power cables, and signal cables.

The tools required for the installation are available. These tools include a Phillips
screwdriver and a wrench.

Procedure
Step 1 Place the computer on the workbench.
Step 2 Connect the power cable for the computer and signal cables for the mouse, keyboard, and
monitor.
Step 3 Connect a network cable to the computer.
Step 4 Connect the PGND cable of the power socket for the computer to the ground bar of the PDF or
any nearby ground.
NOTE

The distance between the power socket and PDF ground bar or nearby ground must be equal to or less than
30 m. If the distance exceeds 30 m, find a closer ground bar. The cross-sectional area of the connecting
cable must be equal to or larger than 6 mm2.

----End

Follow-up Procedure
Record the installation results in 13 Installation Records.

9.2 Installing the Alarm Box


This section describes how to install an alarm box. If you are installing the alarm box in the
equipment room, you can install it along with the BSC6910 equipment.

Prerequisites
l

The components required for the installation are available. The components include the
alarm box, power cables, and signal cables.

The tools required for the installation are available. These tools include a Phillips
screwdriver and a PVC cable trough.

Context
For detailed operations for installing the alarm box and connecting power cables and signal
cables, see the accompanying documents.
Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

74

9 Installing the Alarm Box and the Computer Serving as the


LMT

BSC6910 GSM
Installation Guide

The alarm box requires a -48 V DC or 220 V AC power supply. Connect one end of the power
cable to the alarm box, and connect the other end to a nearby PDF or 220 V AC power output
terminal.

Procedure
Step 1 Install the alarm box.
Step 2 Route signal cables and power cables.
NOTE

l Route signal cables and power cables along with network cables for the alarm management system terminal.
l Route the power cables and signal cables through a PVC cable trough to protect and hide the cables.
l Connect the alarm box signal cable to the LMT computer.

Step 3 Install power cables for the alarm box.


Step 4 Install signal cables for the alarm box.
----End

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

75

BSC6910 GSM
Installation Guide

10

10 Attaching the Engineering Labels to the Cables

Attaching the Engineering Labels to the


Cables

About This Chapter


This chapter describes how to attach engineering labels to the power, PGND, and signal cables
after the cables are installed
10.1 Attaching the Engineering Labels to the Power Cables and PGND Cables
This section describes how to attach the engineering labels to the power cables and PGND cables.
After installing the power cables and PGND cables, replace the temporary labels with
engineering labels.
10.2 Attaching the Engineering Labels to the Signal Cables
This section describes how to attach the engineering labels to the signal cables after the signal
cables are installed.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

76

BSC6910 GSM
Installation Guide

10 Attaching the Engineering Labels to the Cables

10.1 Attaching the Engineering Labels to the Power Cables


and PGND Cables
This section describes how to attach the engineering labels to the power cables and PGND cables.
After installing the power cables and PGND cables, replace the temporary labels with
engineering labels.

Prerequisites
l

The power cables and PGND cables are installed.

The required materials are available. The required materials are pen and label paper.

Procedure
Step 1 Fill out the engineering labels of the power cables and PGND cable according to Labeling Power
Cables, referring to the temporary labels.
Step 2 Remove the temporary labels. Then, attach the engineering labels according to the specifications
described in Labeling Power Cables.
----End

Follow-up Procedure
Record the operation result in the templates provided in 13 Installation Records.

10.2 Attaching the Engineering Labels to the Signal Cables


This section describes how to attach the engineering labels to the signal cables after the signal
cables are installed.

Prerequisites
The signal cables are installed.

Procedure
Step 1 Arrange an engineering label and attach the long end of the label to the cable, as shown in Figure
10-1.
Figure 10-1 Attaching an engineering label

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

77

BSC6910 GSM
Installation Guide

10 Attaching the Engineering Labels to the Cables

Step 2 Attach the label 2 cm away from the connector, and turn over the long end. Ensure that the long
end is aligned with the label.
NOTE

By default, the label is attached 2 cm away from the connector. If required, you can change the position to
facilitate smooth installation. Consistency and neatness, however, must be maintained.

Step 3 There should be a 2 mm to 3 mm space between the label and the cable, as shown in Figure
10-2.
Figure 10-2 Required space between the label and the cable

Step 4 Fold the lower edge of the label upwards, and align the upper edge with the lower edge, as shown
in Figure 10-3 and Figure 10-4.
Figure 10-3 Folding the lower edge upwards

Figure 10-4 Installed label

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

78

BSC6910 GSM
Installation Guide

10 Attaching the Engineering Labels to the Cables

----End

Follow-up Procedure
Record the result of label attachment in the templates provided in 13 Installation Records.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

79

BSC6910 GSM
Installation Guide

11

11 Checklist for the Hardware Installation

Checklist for the Hardware Installation

About This Chapter


This chapter describes how to check the hardware installation. The hardware consists of cables,
Local Maintenance Terminal (LMT) PC, and alarm box. In addition, you should check the
installation environment.
11.1 Checklist for BSC6910 Cable Installation
This lists the items and specifications for checking the installation of the BSC6910 power cables,
PGND cables, and signal cables.
11.2 Checklist for the Installation of the BSC6910 GPS Antenna System
This lists the items and specifications for checking the installation of the BSC6910 GPS antenna
system.
11.3 Checklist for the Installation of the LMT Computer and Alarm Box
This lists the items and specifications for checking the installation of the LMT computer and the
alarm box.
11.4 Checklist for Field Cleanliness of BSC6910 Installation
This lists the items and specifications for checking the field cleanliness of BSC6910 installation.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

80

BSC6910 GSM
Installation Guide

11 Checklist for the Hardware Installation

11.1 Checklist for BSC6910 Cable Installation


This lists the items and specifications for checking the installation of the BSC6910 power cables,
PGND cables, and signal cables.
For details, see Checklist for the BSC6910 Cable Installation.

11.2 Checklist for the Installation of the BSC6910 GPS


Antenna System
This lists the items and specifications for checking the installation of the BSC6910 GPS antenna
system.
For details, see Checklist for the Installation of the BSC6910 GPS Antenna System.

11.3 Checklist for the Installation of the LMT Computer and


Alarm Box
This lists the items and specifications for checking the installation of the LMT computer and the
alarm box.
For details, see Checklist for the Installation of the LMT Computer and Alarm Box.

11.4 Checklist for Field Cleanliness of BSC6910 Installation


This lists the items and specifications for checking the field cleanliness of BSC6910 installation.
For details, see Checklist for Field Cleanliness of the Installation.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

81

BSC6910 GSM
Installation Guide

12 Installation Illustrations

12

Installation Illustrations

About This Chapter


This chapter describes the exploded views of cabinet, cabinet assembly diagrams, and cable
connections of cabinets.
12.1 Components of a Cabinet
The components of the MPR are the same as those of the EPR. The components are subracks,
air defense frame, rear cable troughs, and rack.
12.2 Cable Connections of the Cabinet
This section describes the connections of the power cables, PGND cables, and signal cables in
the cabinet.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

82

BSC6910 GSM
Installation Guide

12 Installation Illustrations

12.1 Components of a Cabinet


The components of the MPR are the same as those of the EPR. The components are subracks,
air defense frame, rear cable troughs, and rack.
Figure 12-1 shows the components of a BSC6910 cabinet (N68E-22).
Figure 12-1 Components of the MPR/EPR (N68E-22)

(1) Subrack

(2) Air deflector

(3) Fan assembly

(4) Air defense frame

(5) PEM

(6) Rear cable trough

Table 12-1 describes the components of the cabinet.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

83

BSC6910 GSM
Installation Guide

12 Installation Illustrations

Table 12-1 Components of the cabinet


Component

Configuration

Subracks

l An MPR is configured with one


Main Processing Subrack (MPS)
and depending on the traffic volume
zero to two Extended Processing
Subracks (EPSs).
l An EPR is configured with one to
three EPSs, depending on the traffic
volume

Air deflector

Two air deflectors are configured.

Air defense frame

One air defense frame is configured.

Rear cable trough

Three rear cable troughs are configured.

NOTE

Subracks are numbered from bottom to top. The subrack at the bottom of a cabinet is numbered 0.

12.2 Cable Connections of the Cabinet


This section describes the connections of the power cables, PGND cables, and signal cables in
the cabinet.

12.2.1 Connections of Power Cables for the Subrack and PGND


Cables for the Cabinet
This section describes the connections of power cables for the subrack and PGND cables for the
cabinet.
The PGND cables connect the cabinet and the ground bar in the equipment room, protecting the
cabinet from electrostatic discharge. Figure 12-2 shows the connections of power cables and
PGND cables for a BSC.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

84

BSC6910 GSM
Installation Guide

12 Installation Illustrations

Figure 12-2 Connections of power cables and PGND cables

Table 12-2 shows the connections of power cables and PGND cables for the BSC6910.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

85

BSC6910 GSM
Installation Guide

12 Installation Illustrations

Table 12-2 Connections of power cables and PGND cables for the BSC6910
Sequence Number

Description

1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12,


13, 14, 15, 16, 17, 18, 19, 20, 21,
22, 23, 24

Power cables connecting the PDF to the subracks

25, 26, 27, 28, 29, 30

PGND cables connecting the subracks to the mounting


bar

31, 32, 33

PGND cables connecting different cabinets

34, 35, 36, 37, 38, 39, 40, 41

PGND cables for cabinet doors and side panels

42

PGND cable for the cabinet

12.2.2 Connections of Signal Cables for the MPR


The signal cables for the MPR are the optical cable, straight-through cable, SFP+ high-speed
cable, BITS clock cable, Y-shaped clock cable, GPS signal transmission cable, and EMU RS485
communication cable.
For details about different types of signal cables, see Cables. Figure 12-3 shows the connections
of signal cables for the MPR that is configured with one MPS and five EPSs.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

86

BSC6910 GSM
Installation Guide

12 Installation Illustrations

Figure 12-3 Connections of signal cables for the MPR

NOTE

The types of interface boards, installation positions of cables, and quantity of cables shown in Figure 12-3 are
examples. The actual configurations depend on the site planning.

Table 12-3 describes the connections of signal cables for the MPR.
Table 12-3 Connections of signal cables for the MPR
Sequenc
e
Number
1, 2

Issue 03 (2013-07-30)

Description

Connector Type 1/
Connection Position 1

Connector Type 2/
Connection Position 2

Ethernet cable
connecting the EOMUa
board to the M2000 or
LAN

RJ45/Ethernet port on
the EOMUa board in
slots 10 and 11 in the
MPS

RJ45/Ethernet port on
the M2000 or of the LAN

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

87

BSC6910 GSM
Installation Guide

12 Installation Illustrations

Sequenc
e
Number

Issue 03 (2013-07-30)

Description

Connector Type 1/
Connection Position 1

Connector Type 2/
Connection Position 2

3, 4

Ethernet cable
connecting the EOMUa
board to the M2000 or
LAN

RJ45/Ethernet port on
the EOMUa board in
slots 12 and 13 in the
MPS

RJ45/Ethernet port on
the M2000 or of the LAN

5, 7

Y-shaped clock signal


cable connecting the
GCUa board to the SCUb
board

RJ45/CLKOUT port on
the GCUa board in slots
12 and 13 in the MPS

RJ45/CLKIN port on the


SCUb board in slot 20 in
the EPS

6, 8

Y-shaped clock signal


cable connecting the
GCUa board to the SCUb
board

RJ45/CLKOUT port on
the GCUa board in slots
12 and 13 in the MPS

RJ45/CLKIN port on the


SCUb board in slot 21 in
the EPS

9, 13

SFP+ high-speed cable


connecting SCUb boards
in different subracks

10G/10G port on the


SCUb board in slot 20 of
the MPS

10G/10G port on the


SCUb board in slot 20 of
the MPS

20, 24

SFP+ high-speed cable


connecting SCUb boards
in different subracks

10G/10G port on the


SCUb board in slot 20 of
the EPS

10G/10G port on the


SCUb board in slot 20 of
the EPS

12, 16

SFP+ high-speed cable


connecting SCUb boards
in different subracks

10G/10G port on the


SCUb board in slot 20 of
the MPS

10G/10G port on the


SCUb board in slot 21 of
the MPS

23, 27

SFP+ high-speed cable


connecting SCUb boards
in different subracks

10G/10G port on the


SCUb board in slot 20 of
the EPS

10G/10G port on the


SCUb board in slot 21 of
the EPS

10, 14

SFP+ high-speed cable


connecting SCUb boards
in different subracks

10G/10G port on the


SCUb board in slot 21 of
the MPS

10G/10G port on the


SCUb board in slot 21 of
the MPS

21, 25

SFP+ high-speed cable


connecting SCUb boards
in different subracks

10G/10G port on the


SCUb board in slot 21 of
the EPS

10G/10G port on the


SCUb board in slot 21 of
the EPS

11, 15

SFP+ high-speed cable


connecting SCUb boards
in different subracks

10G/10G port on the


SCUb board in slot 21 of
the MPS

10G/10G port on the


SCUb board in slot 20 of
the MPS

22, 26

SFP+ high-speed cable


connecting SCUb boards
in different subracks

10G/10G port on the


SCUb board in slot 21 of
the EPS

10G/10G port on the


SCUb board in slot 20 of
the EPS

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

88

BSC6910 GSM
Installation Guide

12 Installation Illustrations

Sequenc
e
Number

Description

Connector Type 1/
Connection Position 1

Connector Type 2/
Connection Position 2

17

75-ohm coaxial cable or


120-ohm twisted pair
cable connecting the
GCUa board to the BITS
clock

SMB male connector/


CLKIN1 port on the
GCUa board in slot 23 of
the MPS

Connector of the BITS


clock/BITS clock port

18

75-ohm coaxial cable or


120-ohm twisted pair
cable connecting the
GCUa board to the BITS
clock

SMB male connector/


CLKIN1 port on the
GCUa board in slot 22 of
the MPS

Connector of the BITS


clock/BITS clock port

19

Optical cable connecting


the EXOUa board to the
peer device

RX/TX of the LC optical


port on the EXOUa board

ODF

43

EMU RS485
communication cable

RJ45/Port on the EMU in


the MPS

DB9/Port on the EMU

12.2.3 Connections of Signal Cables for the EPR


The signal cables for the EPR are the optical cable, straight-through cable, SFP+ high-speed
cable, and Y-shaped clock signal cable.
For details about different types of signal cables, see Cables. Figure 12-4 shows the connections
of signal cables for the EPR that is configured with three EPSs.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

89

BSC6910 GSM
Installation Guide

12 Installation Illustrations

Figure 12-4 Connections of signal cables for the EPR

NOTE

The types of interface boards, installation positions of cables, and quantity of cables shown in Figure 12-4 are
examples. The actual configurations depend on the site planning.

Table 12-4 describes the connections of signal cables for the EPR.
Table 12-4 Connections of signal cables for the EPR
Sequenc
e
Number
20, 24, 28

Issue 03 (2013-07-30)

Description
Ethernet cable
connecting the
SCUb boards in
different subracks

Connector Type 1/
Connection Position 1

Connector Type 2/
Connection Position 2

RJ45/10G port on the SCUb


board in slot 20 of the EPS

RJ45/10G port on the


SCUb board in slot 20 of
the EPS

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

90

BSC6910 GSM
Installation Guide

12 Installation Illustrations

Sequenc
e
Number

Issue 03 (2013-07-30)

Description

Connector Type 1/
Connection Position 1

Connector Type 2/
Connection Position 2

22, 26, 31

Ethernet cable
connecting the
SCUb boards in
different subracks

RJ45/10G port on the SCUb


board in slot 20 of the EPS

RJ45/10G port on the


SCUb board in slot 21 of
the EPS

21, 25, 29

Ethernet cable
connecting the
SCUb boards in
different subracks

RJ45/10G port on the SCUb


board in slot 21 of the EPS

RJ45/10G port on the


SCUb board in slot 21 of
the EPS

23, 27. 30

Ethernet cable
connecting the
SCUb boards in
different subracks

RJ45/10G port on the SCUb


board in slot 21 of the EPS

RJ45/10G port on the


SCUb board in slot 20 of
the EPS

32

Optical cable
connecting the
EXOUa board to the
peer device

RX/TX of the LC optical


port on the EXOUa board

ODF

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

91

BSC6910 GSM
Installation Guide

13 Installation Records

13

Installation Records

The table is used to record the BSC6910 hardware installation information.


For details, see Hardware Installation Records and Installation Record of the Positions of
Signal Cables.

Issue 03 (2013-07-30)

Huawei Proprietary and Confidential


Copyright Huawei Technologies Co., Ltd.

92

Você também pode gostar