Escolar Documentos
Profissional Documentos
Cultura Documentos
Engineering
Master of E n g i n e e r i n g S y s t e m s
ENCOR 7010
Research Proposal
CONTENTS
Chapter -1
INTRODUCTION
Chapter -2
Aim and purpose
Chapter -3
Background and literature review
hydraulic fill into the voids created. At Mount Isa Mines alone during the
6 3
1991/1992 financial year, approximately 4.2 x10 m of void was filled
underground with approximately 6.1 million tonnes of minefill material (Grice
et al., 1993). With the industry under continual pressure as a result of the
increased demand for minerals, as well as improved environmental awareness,
the necessity for better understanding of the hydraulic fill behaviour and
disposal techniques is of paramount importance to our society.
In mining, mine fill refers to any waste material that is placed into the voids
created by underground ore extraction. Mine fill is predominantly placed
underground for the purpose of either waste disposal, or to perform an
engineering function. In a keynote presentation, Mr. Cowling succinctly quotes a
description of the purpose of underground mine fill given by Wilson (1979), as
the material, or materials used:
to fill the cavities created by mining so as to establish and retain safe working
conditions economically.
Materials used in mine fill include one or more of the following: waste
development rock, deslimed and whole mill tailings, quarried and crushed
aggregate, sand and occasionally ice or salt. Very small quantities of binder
material, normally Portland cement, or a blend of Portland cement with another
pozzolan such as fly ash, gypsum or blast furnace slag may be added to the waste
material to improve strength properties.
Most commonly, mine fills are transported through pipes to the stope as a slurry.
Typically, the point in which the slurry is discharged from the pipe into the stope
is through the roof (which is referred to in the mining industry as the back) in
the center or at the far end of the stope. These pipe systems are typically gravity
driven, and the flow can range from laminar with low pressures (less than 1 MPa)
through to turbulent with pressures exceeding 5 MPa within the pipes, depending
on the mine fill material (Grice, 1998 b).
An essential requirement in optimising mine efficiency is that the mine fill being
used is of lowest possible cost, without compromising the required engineering
properties of the material. Typical mine fill costs may range anywhere from $2 to
$20 per cubic meter depending on the function for which it is being used (Grice
1998 b).
Mining Methods that Use Mine fill:
Underground mining methods may be divided into two distinct types: stable stope
and caving, with a complete spectrum of methods available between these two
extremes. The three stable stope methods which use mine fill include open
stoping, room and pillar, and cut and fill mining methods. Caving is a mining
method whereby ore is allowed to collapse under its own weight through prolific
natural fracturing and failures. In caving, the ore will fail where undermined and
will continue to fail while there is a void and sufficient fracturing of the ore body.
A comprehensive description of each of the mining methods is given by Hamrin
(1982), Budavari (1983) and Brady and Brown (1985). This research will be
based on the open stoping mining method in conjunction with hydraulic fill.
Purpose of Mine fill
Mine fill may be used for economic, environmental or engineering purposes. The
purpose of mine fill may be for any one or combination of the following:
- To reduce the need for large tailings dams.
- To provide higher rates of ore recovery.
- To lessen the environmental impact through effective waste
disposal
- To provide local and regional stability to the ore body.The
increased stability is not due to direct transfer of rock stresses into the mine fill
mass, the mine fill is significantly softer than the surround intact rock. The
increased stability is a result of reduced levels of relaxation in the rock, ensuring
the integrity of the load carrying capacity of the rock (Barrett et al., 1978). Using
the results of a finite element analysis, Yamaguchi and Yamatomi (1983), agree
that the effect of mine fill is to limit the deformation of the surrounding rock,
and suggest that mine fill restricts failure progression and as a consequence
generates a slow and moderate dilatant failure in the rock mass around the
void. Ultimately, these measures provide significant cost savings by optimising
safe and economic mine functioning and the longevity of the mine.
A trend in Canadian mines has been described, where environmental legislations
required the maximum quantity of mine waste to be returned to the underground
workings (Nantel, 1998). The obvious limit of this mining direction was reached
when the Australian Federal Government recommended approving an alternative
for the proposed Jabiluka Mine (JMA) whereby all mill wastes were required to
be placed underground. At first glance this seems very reasonable, and may be
2.
3.
4.
In order to minimise loading on barricades, the mine fill may also require high
early strength in the case of pastefill and cemented fills (Grice, 2001).
Dynamic Stability Requirements
Close proximity blasting from production or development sized excavation is
the main dynamic loading which the minefill must be capable of enduring.
Although not common in Australia, the other type of dynamic loadings the fill
material must be able to withstand are those associated with regional seismic
events.
Drainage Requirements
Excess water within the mine fill may come from either groundwater, service
water or water used in the placement of mine fill. Generally the majority of the
water requiring drainage through the mine fill mass comes from the water used
to transport the fill to the site of deposition (i.e., the water used to suspend the
particles as a hydraulic fill). Once placed, the solid particles settle, leaving some
water on top of the solidified material as decant water to percolate through the
fill mass.
To reduce the risks associated with large pore pressures, the water should be
removed from the stope as quickly as practically possible. A rule-of-thumb
design specification, established and used throughout the mining industry to
ensure hydraulic fill permeabilities are of sufficient value to achieve this, is that
the grain size distribution of the hydraulic fills should not have more than 10%
less than 10 m (Grice and Fountain, 1991; Grice et al., 1993; Bloss and Chen,
1998; Grice, 1998 a). A general range for the permeability of hydraulically
placed backfills is between 20 mm/hr to 100 mm/hr, Paste fill, by definition,
retains the water used for transportation purposes, and therefore this mine fill
type does not have drainage requirements.
The fill barricades that are constructed in the drives to contain the mine fills as
they are being placed underground, are also typically designed to allow for the
drainage of water from stopes. The barricades must be constructed such that they
do not restrict the flow of water from the stope and contribute to consequential
pore pressure build up. Cowling (2002) suggests this is typically achieved by
designing the barricades to be ten times more permeable than the fill mass.
Yumli and gureci (2007) implemented monitoring on bulkhead of paste backfill
and tried to improvise it.
Research timetable:
March 2014 extensive research on barricades
April 2014 developing numerical models for simulation
May 2014 understanding 2 dimensional and 3 dimensional hydraulic fills for
simulation