Escolar Documentos
Profissional Documentos
Cultura Documentos
INTRODUCTION
Energy is basic input of every kind of activities associated with economic growth. Nowa-days rising industrialization, growing population and vast improvement in living standard
promotes more need of energy. Indias electricity demand increases by 4.8% of total generation
since 2010. But still India faces large energy deficit in total and peak power demand of 2.1% and
3.2 % respectively. [1] In India almost 80 % of power generation done by conventional sources
gives adverse environmental impact. In India, 65% of population is living in rural region and
engaged in agriculture and local activities. For productive improvement in agriculture sector
needs utilization of advance technology and surety of electricity for it. Big initiatives by
government through social schemes such as RGGVY, PMGY, KJP, AREP etc. which improve
percentage of electrification although 3.32 % of villages are unelectrified due to high cost in grid
expansion for low electricity demand. [1]
Day-by-day rise in energy requirement increases dependability of fossil fuels which
arises issues like global warming, loss in biodiversity, pollution and threat of diminishing energy
sources. Still India is fighting lack in energy demand for peak hours. Demand at load side varies
accordingly daily, monthly and also seasonally which indirectly affect generation output
efficiency.
Transmission system plays major role in terms of power system stability and
reliability in power delivery. Electricity act 2003 opens window for private players in era of
generation, transmission and distribution of power through grid interconnectivity. It provides
competitive environment in terms of profit and efficiency measures. But still in India occurs
23.04 % transmission and distribution loss. [1]
Only increment in generation capacities never fulfill energy demand. It requires proper
sizing of generation sources, maximum efficiency, low losses and stability of power system,
reliability in transmission, precise load side-demand side management and most important
environment sustainability. To overcome all circumstances of electricity demand and surety of 24
7 uninterrupted supply needs proper planning and management from load side to generation
systems. For that purpose require simple, user-friendly tool of energy planning which helps to
get optimum usage of available energy by lowering system losses with economic dispatch of
generated power to equalize required demand of load centre.
Page 1
2010-11
2011-12
2012-13
2013-14
2014-15
Average Demand
Availability
Peak
(MW)
(MW)
Shortfall(-)
344.8
409.9
500.6
628.7
689.4
/Surplus(+) MW
76.2
72.1
69.4
61.3
55.6
421
482
570
690
745
Page 2
300
200
100
0
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
Time
Page 3
OCT
NOV
development and detail information of SLD, load buses, transformers, shunt reactors etc.
mentioned as follows.
Table 2: HV Transmission substation and Cogeneration plant of Karveer Taluka
Substation Name
Mudshingi
110
Maximum Load
Grid Interconnected
(MW)
Generation (COGEN)
Jawahar
193.669
Renuka
Gokulshirgaon
110
66.72
Shahu
Puikhadi
110
83.089
Kumbhi
Kale
110
41.58
Bapat Camp
110
88.23
Shiroli
110
101.07
Chambukhadi
110
44.07
Asurle-Porle
The power transmitted inside Kolhapur from one station to another shown by SLD. It
also gives basic information about no. of buses, voltage rating, transformer, shunt reactor etc. It
uses in power flow analysis and computation of individual feeder and total power loss. The
following diagram shows SLD of Karveer Taluka. It consist 22 buses in which all cogeneration
plants connected to 110 kV grid. Among them 11 buses are load buses of voltage rating 33kV or
11 kV fed to distribution substation. In table 3 gives loading details of study area.
Page 4
Substation
s
No.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
Chambukhadi
Shiroli
Mudshingi
Bapat Camp
Puikhadi
Gokulshirgaon
Kale
Bus Voltage
Active Power
Reactive Power
Apparent
(kV)
(P)
(Q)
Power (S)
114
111
32
109
33
33
11
11
114
111
33
33
11
11
111
113
33
11
111
33
33
109
33
33
11
VIcos (MW)
115.06
48.67
16.83
105.47
27.1
17.6
9.32
8.27
195.869
92.33
36.05
37.03
7.79
8.54
87.989
13
29.29
25.689
70.32
28.76
40.00
46.28
19.735
17.535
7.12
VIsin (MVAr)
92.1956
51.068
16.6876
110.98
27.6389
18.599
9.6688
8.154
188.796
96.606
32.46
33.773
10.555
7.745
87.245
12.5305
26.373
22.705
70.716
26.908
37.586
46.012
18.78
16.359
5.151
VI (MVA)
147.513
70.536
23.704
153.0769
38.71
25.6186
13.429
11.6152
272.04
133.618
48.52
50.108
7.125
11.525
123.928
18.055
39.421
34.297
99.042
39.397
54.87
65.275
27.258
23.988
8.79
Sending End
MW
MVAr
195.869
188.796
Receiving End
MW
MVAr
193.669
187.6
Loss (MW)
2.2
Page 5
Gokulshirgaon
Puikhadi
Kale
Bapat Camp
Shiroli
Chambukhadi
70.32
87.989
46.28
92.33
105.47
48.67
70.716
87.245
46.018
96.606
110.98
51.068
66.72
83.089
41.58
88.23
101.07
44.07
69.48
86.23
44.38
94.39
108.24
49.09
3.6
4.9
4.7
4.1
4.4
4.6
Significance:
1.
2.
3.
4.
VsVr
Vr
= 0.7 lag
100 = 4.2 %
In 2014-15 Karveer experiences 2.74 % power deficit from total available power i.e. it
can reducible by upgrading additional generation capacity. Lagging (0.7) power factor consumes
more reactive power which leads to grater conductor size, increment in KVA rating, transmission
loss etc. It can be improved upto 0.85 to 0.9 by providing FACTS devices or tap changer in
between lines. It also beneficial for improvisation in quality of power
sinusoidal voltage and current input by reducing harmonics in system as well as excessive
reactive power. Here one more thing notified that average voltage regulation is more which
affects different magnitude in sending and receiving end at load center. It can obtain by placing
additional power transformer with facilitation of on-load tap setting in between transmission line.
Following fig. 4 shows monthly load curve of proposed study area (Karveer).
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
DEC
Page 6
= 0.815
Page 7
condensing, the efficiency of conventional power plants is only around 35%. But in a
cogeneration plant, very high efficiency levels, in the range of 75%90%, can be reached. [3]
This is so, because the low-pressure exhaust steam coming out of the turbine is not condensed,
but used for heating purposes in factories or houses. Following fig.5 shows operational layout of
cogeneration.
Page 8
and thermal energy from a single fuel source. By using waste heat recovery technology to
capture a significant proportion of this wasted heat, CHP systems typically achieve total
system efficiencies of 60 to 80 percent for producing electricity and thermal energy.
Because CHP is more efficient, less fuel is required to produce a given energy output than
benefits for large energy users. The economic benefits of CHP can include:
Reduced energy costs: The high efficiency of CHP technology can result in energy
savings when compared to conventional, separately purchased power and onsite thermal
energy systems.
Earning money to sell grid.
In Karveer, Cogeneration in sugar industry to produce excess power and exported to the
Maharashtra State Electricity Board grid has gained momentum and is the order of the day. In
fact, the profitability of a sugar plant is centered on the revenue from export of power. The
encouragement being given by the central and state government for promoting the use of biomass / non-conventional, Eco-friendly energy further encourages the implementation of
cogeneration plants in sugar industries. Today the catch word in the industry is to "to maximize
the export of power". In Maharashtra biomass fired cogeneration plants are existed 982.9 MW of
capacity. It provides around 636 MW power to Maharashtra.
Table No. :
M. Tech-II (Rural Technology), YCSRD, Shivaji University, Kolhapur
Page 9
Co-generation
Sugar Industry
Substation
Installed
Plant
Renuka
Deshbakta
Name
Mudshingi
Capacity (MW)
30
Jawahar
Kumbhi-Kasari
Mudshingi
Puikhadi and
27
17.5
Kale
Gokulshirgaon
Chambukhadi
12.5
23
Shahu
Asurle-Porle
172.4
MW
power
to
Page 10
/S
C
L
P
D
A
uM
tin
a
m
o
) E
rb
h
ia
t(v
u
p
lIn
e
d
o
O
N
T
R
M
D
L
W
K
DT
M
L
F
R
E
W
O
P
L
IO
M
S
N
A
R
EO
D
LC
E
D
N
A
Z
IM
T
P
E
N
T
A
P
H
D
O
IS
M
LD
T
N
U
Y
A
L
P
IS
Fig. 6: Process Flow diagram of Optimal Dispatch Model
SCADA Database Management System:
Page 11
Now-a-days data recording of power stations done with the help of digital instruments
equipped with PLC automation. It gives accurate and precise measurement in specified range.
The advantage of such instrument is large reduction in unskilled manpower and recording error
of analog instruments. SCADA system provides remote access for control and supervision. But it
require skilled technician to handle during operation and backup power supply for blackout
operation.
Input Model:
Large number of data recorded in mainframe (server) computer. For model only specific
inputs are required in unified nature i.e. per unit system. Inputs provided for proposed model are
bus data in which total number, real and reactive power loadings and bus voltage and shunt
compensation etc. , line data in which resistance and reactance of transmission line etc. One
thing is more important that entry of data should co-ordinate manner because if any mistake
happened then model shows wrong results or may error will form during programme execution.
Network Model:
Network model is used to calculate admittance matrix (Y bus) from individual feeder
resistance and reactance. It has done with node-voltage method applying KCL at each bus. The
network equations are complex non-linear algebraic equations in terms of node current. Network
model uses linedata from input model for computation of Ybus which further utilized in power
flow analysis. For n-bus network model demonstrated as follows;
Page 12
Ibus = Vector of the injected currents (the current is positive when flowing into the bus
and negative when flowing out of the bus)
Ybus = Admittance matrix.
Diagonal elements of Ybus matrix is known as self admittance or driving point admittance
LIMITATION
N
1.
TECHNIQUE
MODEL
Static Load flow Ritu
Parasher In most cases applicable for DC or radial AC
2.
Method
Guass-Seidal
(2013)
transmission network analysis
Raed Alqadi M. Large number of iteration required for complex
3.
Method
Newton-
4.
Page 13
Method
Kumkratug(2010
In the above equation j includes bus i , expressing equation in polar form, we have
By putting Ii we get
Separating real and imaginary part
Page 14
Above active and reactive power equations constitute a set of non linear algebraic equation in
terms of independent variable, voltage magnitude per unit and phase angle in radians.
By expanding using Taylor Series, and neglecting higher order term, get
Here bus 1 assumed as slack bus, Jacobian matrix gives linearized relationship between small
changes in voltage angle i(k) and voltage magnitude |Vi(k)| with small changes in real and
reactive power Pi(k) and Qi(k).
Page 15
The terms of Pi(k) and Qi(k) are difference between scheduled and calculated values, known as
power residuals, given by
From analysis get that Newton- Raphson method is best suited [9] for proposed study because
1. It usable for wide complex transmission network.
2. It is having high accuracy and not depends on type of bus.
3. It is programmable using simulation software.
Transmission Loss Model:
Transmitting electricity at high voltage reduces the fraction of energy lost to resistance,
which varies depending on the specific conductors, the current flowing, and the length of the
transmission line. For a given amount of power, a higher voltage reduces the current and thus the
resistive losses in the conductor. Even if the conductor size (cross-sectional area) is reduced the
I2R losses are also reduced. At extremely high voltages, more than 2,000 kV exists between
conductor and ground; corona discharge losses are so large that they can offset the lower
resistive losses in the line conductors. Measures to reduce corona losses include conductors
having larger diameters; often hollow to save weight or bundles of two or more conductors.
Page 16
To evaluate exact transmission losses of complex network uses Kron technique but it
requires all the entities associated with transmission network which can be obtained from power
flow model. It expresses system losses in terms of interconnected generators real power output.
It also called B-coefficient method. Total injected complex power at bus I, denoted by S i, is given
by Si= Pi + jQi= Vi Ii*.
The summation of power over all buses gives the total system loss
Where PL and QL are real and reactive power loss of system but
But active power loss plays major role in loss component hence it becomes;
Page 17
All above results are put in active power loss equation gives resultant equation;
Page 18
Optimization Model:
Optimization model of grid interconnected energy system is better way to fulfill power
demand of proposed study area because its having ability to expand output at certain limit and
also it operated at full capacity gives performance improvisation and better efficiency. The
objective function of optimization model is fulfill demand using local generation system with
their real power limit which reduces transmission losses due to overcapacity and long distance
transmission of power. In optimization model some constrained are put in terms of limit due to
grid require synchronous input from feeder such as frequency, voltage, reactive power so it
maintain efficiency of network and quality of delivered power. Generally following techniques
are preferred in optimization problem such as;
Table 8: Optimization Model
S.N
METHOD
REFERENCE
LIMITATION
Page 19
.
1.
2.
Lagranges Multiplier
Gradient Method
3.
4.
Linear Programming
5.
Dynamic Programming
6.
Sahu,
Genetic Algorithm
G.
7.
Swarm Intelligence
8.
FUZZY Model
Chauhan (2012)
decentralize and self organized system.
A. Chaibakhsh, It require special software (algorithm)
9.
ANN Model
(2011)
and compatible hardware
M. Chakraborty
(2012)
From above conclusion for proposed model calculus (Lagranges Multiplier) is employed due to
1. Power flow model gives non-linear algebraic equation can be solved only calculus
method.
2. Required model doesnt have dynamic behavior of input function i.e. inputs are steady
state condition.
3. Model is developed in MATLAB which able to formulate Lagranges Method easily
without any supporting package and posses transferable characteristic for user.
Economic Dispatch Model:
The tariff rate at which user purchase electricity from service provider accounts 2/3
rd
cost for generation. For gaining economic cost of operation need to reduce overwhelmed
generation charges. It also gives scope for earning profit to generation companies as well as
betterment in operating efficiency of generation system. The total generation cost consist capital
cost, fuel cost, labour cost, operation and maintenance cost etc. It used to get characteristic
M. Tech-II (Rural Technology), YCSRD, Shivaji University, Kolhapur
Page 20
equation from fuel-cost curve which further put in optimization constrain for minimization of
total cost and earn profit. In general fuel-cost curve of thermal generation as follows.
Ci = i + i Pi + i Pi2
Where as i i and i are constant and Pi is generated power in (MW)
Incremental fuel-cost curve is a measure of how costly it will be to produce to the next increment
of power. It can be obtained by taking derivative characteristic equation of fuel-cost curve.
dCi
= i+2 i Pi
dPi
Formulation of Economic Dispatch model considered transmission losses so obtained equations
are non-linear so it can be solved using gradient iterative method. From Kron loss formula,
The objective function is to minimize overall generating cost Ci which is function of plant output
subject to the constraint that generation should equal to demand plus losses i.e.
M. Tech-II (Rural Technology), YCSRD, Shivaji University, Kolhapur
Page 21
But generator provided minimum and maximum output power limit expressed as follows
Now for minimization cost take derivative of Lagranges multiplier equal to zero.
PL
Pi is the incremental transmission loss is a measure of what rate it will be to occur at next
increment of power.
Page 22
Expanding the left hand side of above equation in Taylors series about an operating point (k)
and neglecting higher order terms result in
Page 23
Page 24
FULFILL POWER
DEMAND?
OPTIMIZE
GENERATION?
ECONOMIC DISPATCH?
END
Page 25
Voltage Mag.
Angle Deg
Load
Generation
MW
MVAR
MW
MVAR
1.06
0.0
1.045
0.0
20
10
40
30
1.03
0.0
20
15
30
10
1.0
0.0
50
30
1.0
0.0
60
40
Page 26
Bus to
1
1
2
2
2
3
4
Bus from
2
3
3
4
5
4
5
Resistance ()
0.02
0.08
0.06
0.06
0.04
0.01
0.08
Reactance ()
0.06
0.24
0.18
0.18
0.12
0.03
0.24
Cap. Suceptance
0.030
0.025
0.020
0.020
0.015
0.010
0.025
Bus 1 Slack Bus, Bus 2 & 3 Generator Bus, Bus 4 & 5 Load bus.
Step 1: Computation of Network Model
Off-diagonal element
1. Y12=Y21=
1
=
-5 + j 15 = 15.82 L 108.4
0.02+ j 0.06
2. Y13=Y31 =
1
=
-1.25 + 3.75j = 3.95 L 108
0.08+ j 0.24
3. Y14=Y41 = 0
4. Y15=Y51= 0
5. Y23=Y32=
1
=
-1.67 + j 5 = 5.27 L 108.4
0.06+ j 0.18
6. Y24=Y42=
1
=
-1.67 + j 5 = 5.27 L 108.4
0.06+ j 0.18
7. Y25=Y52=
1
=
-2.5 + j7. 5 = 7.9 L 108.4
0.04+ j0.12
8. Y34=Y43 =
1
=
-10 + j 30 = 31.62 L 108.4
0.01+ j 0.13
9. Y35=Y53 = 0
10. Y45=Y54=
1
=
0.08+ j 0.24
Page 27
18.
19.
Y 11
Y 21
Y 31
Y 41
Y 51
Y 12
Y 22
Y 32
Y 42
Y 52
Y 13
Y 23
Y 33
Y 43
Y 53
Y 14
Y 24
Y 34
Y 44
Y 54
Y 15
Y 25
Y 35
Y 45
Y 55
6.2518.69 j
5+ j 15
1.25+ j 3.75
0+ j0
0+ j0
5+ j5
10.8 j32.4 1.67+ j 5
1.67+ j5
2.5+ j7.5
1.25+ j3.75 1.67+ j5 12.91 j 38.7
10+ j 30
0+ j0
0+ j0
1.67+ j5
10+ j 30
12.91 j38.7 1.25+ j3.75
0+ j0
Y 52
0+ j 0
1.25+ j 3.75 3.75 j 11.2
21.
19.71 L1.24
15.81 L1.8
3.95 L 1.89
0L0
0 L0
15.81 L1.8
34.17 L1.24
5.27 L 1.89
5.27 L1.89
7.98 L 1.89
3.95 L 1.89
5.27 L 1.89
40.79 L1.24 31.25 L 1.89
0 L0
0 L0
5.27 L 1.89
Y 43
40.79 L1.24 3.95 L 1.89
0 L0
Y 52
0 L0
3.95 L 1.89
11.8 L1.24
22.
23. Step 2: Power Flow Model
24. By using Newton Raphson Method
25. From SLD known quantity P2, P3, P4, P5, Q4 and Q5
26. Unknown qty get in power flow 2, 3, 4, 5, V4, V5
27. Given input V1= 1.06 pu, V2= 1.045 pu, V3= 1.03 pu, |V4|=|V5|= 1pu, 1= 2= 3=
4= 5=0
28. P2(0) = |V2| |V1| |Y21| cos (21- 2+ 1) + |V2| |V3| |Y23| cos (23- 2+ 3)+ |V2| |V4| |
Y24| cos (24- 2+ 4) + |V2| |V5| |Y25| cos (25- 2+ 5) + |V22| |Y22| cos (22).
29.
= 0.1436
Page 28
30.
P2
2
= |V2| |V1| |Y21| sin (21- 2+ 1) + |V2| |V3| |Y23| sin (23- 2+ 3)+ |V2| |
V4| |Y24|
sin (24- 2+ 4) + |V2| |V5| |Y25| sin (25- 2+ 5) + |V22| |Y22|
sin(22).
31.
= 35.059
32.
P2
=
33. 3
- |V2| |V3| |Y23| sin (23- 2+ 3) = - 5.3817
34.
P2
=
- |V2| |V4| |Y24| sin (24- 2+ 4) = - 5.225
4
35.
P2
=
- |V2| |V5| |Y25| sin (25- 2+ 5) = - 7.837
5
v 4=
P2
36.
- |V2| |Y24| cos (24- 2+ 4) = - 1.7417
v 4=
P2
37.
- |V2| |Y25| cos (25- 2+ 5) = - 2.6125
38.
39. P3(0) = |V3| |V1| |Y31| cos (31- 3+ 1) + |V3| |V2| |Y32| cos (32- 3+ 2)+ |V3| |V4| |
Y34| cos (34- 3+ 4) + |V32| |Y33| cos (33).
40.
= 0.245
41.
P3
=
42. 2
- |V3| |V2| |Y32| sin (32- 3+ 2) = - 5.3817
43.
P3
3
= |V3| |V1| |Y31| sin (31- 3+ 1) + |V3| |V2| |Y32| sin (32- 3+ 2)+ |V3| |
V4| |Y34|
sin (34- 3+ 4)
44.
= 40.376
45.
P3
=
46. 4
- |V3| |V4| |Y34| sin (34- 3+ 4) = - 30.9
M. Tech-II (Rural Technology), YCSRD, Shivaji University, Kolhapur
Page 29
47.
P3
=
0
5
V 4=
P3
48.
- |V3| |Y34| cos (34- 3+ 4) = - 10.3
v 5=
P3
49.
0
50.
51. P4(0) = |V4| |V3| |Y43| cos (43- 4+ 3) + |V4| |V2| |Y42| cos (42- 4+ 2)+ |V4| |V5| |
Y45| cos (45- 4+ 5) + |V42| |Y44| cos (44).
52.
= -0.375
53.
P4
=
54. 2
- |V4| |V2| |Y42| sin (42- 4+ 2) = - 5.23
55.
P4
=
- |V4| |V3| |Y43| sin (43- 4+ 3) = - 30.9
3
56.
P4
=
|V4| |V3| |Y43| sin (43- 4+ 3) + |V4| |V2| |Y42| sin (42- 4+ 2)+ |V4| |
4
V5| |Y45|
sin (45- 4+ 5) + |V42| |Y44| sin (44).
57.
= 39.87
58.
P4
=
59. 5
- |V4| |V5| |Y45| sin (45- 4+ 5) = - 3.75
V 4=
P4
60.
|V3| |V4| |Y34| cos (34- 3+ 4) + |V2| |Y42| cos (42- 4+ 2)+ |V3| |
Page 30
64.
65. P5(0)= |V5| |V2| |Y52| cos (52- 5+ 2) + |V5| |V4| |Y54| cos (54- 5+ 4)+ |V52| |Y55|
cos
(55).
66.
= -0.113
67.
P5
=
68. 2
- |V5| |V2| |Y52| sin (52- 5+ 2) = - 7.84
69.
P5
=
0
3
70.
P5
=
- |V5| |V4| |Y54| sin (54- 5+ 4) = -3.75
4
71.
P5
=
2
72.
|V5| |V2| |Y52| sin (52- 5+ 2) + |V5| |V4| |Y54| sin (54- 5+ 4)
= 11.59
V 4=
P5
73.
|V5| |Y54| cos (54- 5+ 4) = -1.25
V 5=
P5
74.
|V2| |Y52| cos (52- 5+ 2) + |V5| |V4| |Y54| cos (54- 5+ 4)+ 2|V5| |
Q 4
=
- |V4| |V2| |Y42| cos(42- 4+ 2) = 1.74
2
78.
Q 4
=
- |V4| |V3| |Y43| cos(43- 4+ 3) = 10.3
3
Page 31
79.
Q 4
=
-|V4| |V3| |Y43| cos (43- 4+ 3) + |V4| |V2| |Y42| cos (42- 4+ 2)+ |V4| |
4
87.
88. Q5 (0) = -|V5| |V2| |Y52| sin (52- 5+ 2) + |V5| |V4| |Y54| sin (54- 5+ 4)+ |V52| |
Y55| sin
(55).
89.
= - 0.38
90.
Q 5
=
91. 2
- |V5| |V2| |Y52| cos(52- 5+ 2) = 2.612
92.
Q 5
=
0
3
93.
Q 5
=
- |V5| |V4| |Y54| cos(54- 5+ 4) = 1.25
4
94.
Q 4
=
|V5| |V2| |Y52| cos(52- 4+ 2) + |V5| |V4| |Y54| cos(54- 5+ 4) = -3.862
2
95. Angle in
Radian
Degree
= -0.0127
= -0.729
Page 32
= -0.0197
= -1.128
= -0.0313
= - 1.79
= - 0.053
= -3.006
100.
= 1.018
101.
= 0.98
102.
1=0
103.
[ ]
2(1)
3(1)
4 (1)
5(1)
V 4(1)
V 5(1)
104.
0.051
0.038
0.0412 0.0492 0.00075 0.00079
0.03784 0.09197 0.0822 0.0527 0.0014
0.0013
0.0405
0.0811
0.0974 0.0604 0.063 0.00116
0.0477
0.052
0.0595
0.132 0.001 0.023
0.0001 0.0004 0.0085 0.0032 0.025
0.0084
0.0004 0.00018 0.0032 0.0317 0.0085
0.0085
105.
][ ]
0.0015
0.186
0.251
0.099
0.75
0.1598
[ ]
0.00039
0.00043
0.00058
0.000418
0.01904
0.00955
106.
107.
Angle in
Radian
Degree
108.
= -0.013
= -0.75
109.
= -0.02
= -1.152
Page 33
110.
= -0.032
= - 1.83
111.
= - 0.056
= -3.245
112.
= 1.037
113.
= 0.97
114.
1=0
115.
By taking 3rd iteration we get,
116.
[ ]
2(2)
3(2)
4 (2)
5(2)
V 4(2)
V 5(2)
117.
0.05
0.038
0.041
0.049
0.0007 0.0007
0.03785 0.09197 0.082
0.054
0.0014 0.0012
0.04
0.081
0.097
0.06
0.06 0.001
0.048
0.052
0.06
0.132 0.001 0.023
0.0001 0.0005 0.008 0.0035
0.025
0.008
0.0004 0.00017 0.0032 0.03206 0.0085 0.0085
118.
][ ]
0.006
0.189
0.243
0.056
0.75
0.176
[ ]
0.00017
0.00011
0.00013
0.00014
0.01903
0.00956
119.
120.
Angle in
Radian
Degree
121.
= -0.013
= -0.74
122.
= -0.02
= -1.142
Page 34
123.
= -0.032
= - 1.82
124.
= - 0.056
= -3.23
125.
= 1.056
126.
= 0.96
127.
1=0
128.
129.
v 4=
Q 4
-|V5| |Y54| sin (54- 5+ 4) = 3.75
130.
V 5=
Q4
= 10.83
131.
132.
P2 sch =
40
100
133.
S4 sch =
50+ j30
100
= - 0.5 - j 0.3 pu
134.
S5 sch =
60+ j 40
100
= - 0.6 - j 0.4 pu
135.
136.
137.
138.
139.
140.
141.
= 0.4 pu
P3 sch =
30
100
= 0.3 pu
Page 35
142.
143.
144.
145.
146.
147.
= 0.5521 L 2. 569
148.
= - 0.464 + j 0.298
149.
150.
151.
= 0.7507 L 2.49
152.
= - 0.60 + j 0.45
153.
154.
155.
156.
= 0.42404 L 0.04168
157.
=0.42367+j001763
158.
K5 = I5/I4+I5 = 0.57633-j0.01767
159.
160.
M1 = Z11/K4Z14+K5Z15
161.
= (0.0113-j3.418) / [(0.42404 L 3.46381)*(3.46381 L -1.56748)]+[(0.57660 L
0.03065)
(3.46371 L -1.57262)]
162.
=3.41082 L -1.57262/0.0639-j3.46375
163.
=0.98472 L 0.00515
164.
165.
Page 36
166.
167.
168.
1
0
0
0
0
1
0
0
0
0
1
0
K 4 M 1 K 4 M 2 K 4 M 3 K 4 M 1
K 5 M 1 K 5 M 2 K 5 M 3 K 5 M 1
= - 0.0007 - j3.4470
169.
170.
-K4M1 = -{0.42404 L 0.04168}{0.98472 L 0.00515} = {0.41756 L 0.04683} =
-0.41710-j
0.01955
171.
172.
K4M2 = -0.42159-j0.01827
175.
-K5M2 = -0.57357+j0.01665
173.
-K4M3 = -0.42333-j0.01777
176.
-K5M3 = -0.57587+j0.01750
174.
-K5M1 = -0.56761+j0.01448
177.
ZBUS = [ YBUS]-1
[
178.
0.0113
0.007
0.0054
0.0064
0.0064
0.0007
0.0041
0.0049
0.0050
0.0020
179.
180.
CT RBUS C* = E*C*F
0.0054
0.0049
0.0077
0.0033
0.0059
0.0064 0. .0064
0.0050 0.0026
0..0033 0.0059
0.0078
0.0044
0.0044
0.0199
181.
Page 37
182.
C=
1
0
0
1
0
0
0.4171 j 0.01955 0.42159 j0.01827
0.56761+ j 0.01448 0.57357+ j0.01665
0
0
0
0
1
0
0.42333 0.0177 0.4171 j 0.01955
0.5758+ j 0.01750 0.56761 j 0.01448
0
0
0
0
1
0
0.42333 0.0177 0.4171 j 0.01955
0.5758+ j 0.01750 0.56761 j 0.01448
183.
184.
C* =
1
0
0
1
0
0
0.4171 j 0.01955 0.42159 j0.01827
0.56761+ j 0.01448 0.57357+ j0.01665
185.
186.
CT =
187.
1
0
0
0
0
1
0
0
0
0
1
0
0.4171 j 0.01955
0.42159 j 0.01827
0.42333 0.0177
0.4171 j 0.01955
0.56761+ j 0.01448
0.57357+ j 0.01665
0.5758+ j 0.01750
0.56761 j 0.01448
188.
189.
190.
191.
192.
193.
194.
CT RBUS C* =
0.0296 j 0
0.0149 j 0.001 0.0086 j 0.0001 0.0118 + j 0.0001
0.0149 j 0.0001
0.0171+ j 0
0.0065 j 0.0002
0.0092+ j 0
0.0086 j 0.0001 0.0065+ j 0.0002
0.0175+ j 0
0.0078+ j 0.0001
0.0119+ j 0
0.0093+ j 0.0001 0.6077 j 0.0001
0. .0056+ j 0
Now In0 =
V /Z
1
11
= -1.06+j0/0.0113-j3.4108
= 1.06 L 3.14159/3.41082 L -1.56748
= 0.31078 L 1.57411
= - 0.00103+ j031078 PU
Page 38
195.
196.
197.
V1 = 1.06
202.
1 = 0
198.
V2 = 1.045
203.
2 = -0.03110 rad
199.
V3 = 1.03
204.
3 = -0.04650 rad
200.
V4 = 1.0514
205.
4 = -0.05660 rad
201.
V5 = 0.96003
206.
5 = -0.07688 rad
207.
208.
P1 = |V12||Y11|cos11+|V1||V2||Y12| cos(12-1+2)+|V1||V3||Y13|cos(13-1+3)
209.
= 22.14848*(0.31708)+17.51428*(0.28658)+4.31572*(-0.27179)
210.
= 0.83041
211.
212.
Q1 =- |V12||Y11|sin11-|V1||V2||Y12|sin(12-1+2)-|V1||V3||Y13|sin(13-1+3)
213.
= -22.14848*(-0.94840)-17.51428*(0.95806)-4.31572*(0.96236)
214.
= 0.07261
215.
Q2 = 0.34985
216.
Q3 = 0.24148
217.
218.
S1 = Q1/ P1 = -0.08722
219.
S2 = Q2/ P2 = 0.87463
220.
221.
222.
223.
224.
Page 39
225.
[
226.
0.9434 j0.08249
0
0
0
0
0.9301 j 0.86596
0
0
0
0
0.9335 j 0.82577
0
0
0
0
0.00103 j 0.31078
* =
0.9434+ j 0.08249
0
0
0
0
0.9301+ j 0.86596
0
0
0
0
0.9335+ j 0.82577
0
0
0
0
0.00103+ j 0.31078
227.
228.
[CTRBUSC*][ ] =
229.
0.0265+ j 0
0.0141+ j 0.011 0.0083+ j 0.0059 0.0003+ j 0. .0035
0.0141+ j0.011
0.0276+ j0
0.0103 j 0.0006 0.0025+ j 0.00027
0.0083 j0.0059 0.0103+ j0.0006
0.0272+ j0
0.0019+ j 0. .0023
0.0003 j0.0035 0.0025 j0.0027 0.0019 j 0.0023
0.0005+ j 0
230.
231.
232.
0.0265
0.0141
0.0063
0.0003
0.0141
0.0276
0.0103
0.0025
0.0083 0. .0003
0.0103 00025
0.0272 0.0019
0.0019 0.0005
233.
B=
234.
B0 = [0.00030.0025 0.0019]
235.
B00 = [0.0005]
Page 40
236.
method
237.
Given input
][ ]
JAWAHAR
173.58
223.322
274.22
326.28
379.5
433.88
489.92
546.12
603.98
663
[ ]
296.
297.
= 0.0265 P12 +0.0141 P1 P2 +0.0083 P1 P3 +0.0141P1 P2+0..0276 P22
+0.0103 P2 P3+0.0083P1 P3 +
0.0103P2P3+0.0019P32+0.0003P1+0.0025P2+0.0019P3+0.0005
298.
299.
By making loss in MW form
M. Tech-II (Rural Technology), YCSRD, Shivaji University, Kolhapur
Page 41
300.
301.
= 0.000265 P12 +0.000141 P1 P2 +0.000083 P1 P3 +0.000141P1
P2+0.000276 P22 +0.000103 P2 P3+0.000083P1 P3
+0.000103P2P3+0.000019P32+0.03P1+0.25P2+0.19P3+0.05
302.
303.
From above we get Bloss coefficient
304.
305.
0.0002651
306.
0.000141
307.
0.000083
308.
0.000141
309.
0.000276
318.
319.
B11 =
B12 =
B13 =
B21 =
B22 =
310.
0.000103
311.
0.000083
312.
0.000103
313.
0.000019
314.
315.
316.
317.
B23 =
B31 =
B32 =
B33 =
B01 = 0.031
B02 = 0.25
B03 = 0.19
B00 = 0.05
P1 =
320.
= {7(1-0.03)-5.2-2*7[0.000141 P2(1) +0.000083
P3(1)]}/2(0.0065+7*0.000265)
321.
322.
323.
324.
(1)
P2 =
325.
= {7(1-0.25)-4.3-2*7[0.000141 P1(1) +0.000103
P3(1)]}/2(0.0072+7*0.000276)
M. Tech-II (Rural Technology), YCSRD, Shivaji University, Kolhapur
Page 42
326.
327.
(1)
328.
P3 =
329.
= {7(1-0.19)-4.8-2*7[0.000083 P1(1) +0.000103
P2(1)]}/2(0.0058+7*0.000019)
= 1.162 P1(1)+1.442 P2 (1)+1.426 P3(1) = 870
330.
331.
332.
333.
][ ] [ ]
334.
335.
336.
X=A-1 B
337.
MW
P1(1) =92.32
340.
341.
PL(1) = 0.000265 P12 +0.000282 P1 P2 +0.000166 P1 P3 +0.000276 P22 +0.000206 P2
P3+0.0019P32+0.03P1+0.25P2+0.19P3+0.05 =6.9932 MW
342.
Since PD = 150 MW
343.
Error, P(1) =150+6.9932-(92.32+56.73+43.54)
344.
= -35.4368
345.
ng
346.
(
i=1
Pi
)
ng
i=1
2(i+ (k ) Bii)
j 0
2
ng
347.
( Pi )=
i=1
Page 43
=128.508
349.
350.
35.5968
= 128.508
351.
352.
353.
(1)
= -0.277
354.
P1(2) = 6.723(1-0.03)-5.2-2*6.723[0.000141 P2(2) +0.000083 P3(2)] /2(0.0065
+6.723*
0.000265)
355.
= 16.563 P1(2) + 1.896 P2(2 ) +1.116 P3(2 ) = 1321.31
356.
357.
P2(2) = 6.723(1-0.25)-4.3-2*6.723[0.000141 P1(2) +0.000103 P3(1) ] /2(0.0072 +6.723
*
0.000276)
358.
= 1.896 P1(2) + 18.11 P2(2 ) +1.385 P3(2 ) = 742.25
359.
360.
P2(2) = 6.723(1-0.19)-4.8-2*6.723[0.000083 P1(3) +0.000103 P2(2) ] /2 (0.0058
+6.723 *
0.000019)
(2)
361.
= 1.116 P1 + 1.385 P2(2 ) +11.855 P3(2 ) = 645.63
362.
363.
][ ] [ ]
364.
P1(2 ) =
84.284 MW
367.
365.
P2(2 ) =
40.569 MW
366.
MW
P3(2 ) = 30.46
368.
PL(2)= 0.000265(84.284)2 +0.000282 (84.284*40.569)+ 0.000166(84.284*30.46)+
0.000276
(40.569)2 +0.000206 (40.569*3046) +0.000019 (30.46)2 +0.03*84.284
+0.25*40.569 +0.19*30.46+0.05 = 4.590 MW
369.
Since PD = 150MW
370.
Page 44
371.
ng
( Pi )
372.
i=1
373.
376.
377.
374.
375.
(2)
378.
MW
P1(3 ) = 84.43
381.
382.
PL(3) =4.4277 MW
383.
384.
379.
MW
P2(3) = 40
380.
MW
P3(3 ) = 30
= -0.0623
ng
385.
386.
( Pi )
i=1
(3)
= 214.82
387.
Since (3) is very small hence equality constraints met in three iteration and
optimized dispatch incremented by
388.
= 6.595 $/MWh
389.
Total fuel cost = 190+5.2*84.49+0.0065*(84.49)2 +160 +4.3*40 +0.0072* (40)2
+125 +4.8*30
+0.0058*(30)2 =1293.1 $/h
Page 45
390.
391.
6. CONCLUSION
The efficient and optimum economic operation and planning of electric
power generation systems have occupied an important role in the generation companies.
The efficient use of the available generation is growing in importance, because to demand
increment issue cant be solved only installing or upgrading new capacity plants. A
savings in the operation of generating systems of a small percent represents a significant
reduction in operating cost which gives profit to generation companies as well as grows
the performance of generation system. From present study and analysis following
observations are obtained such as
1. Grid interconnected energy system model able to ensure delivery of maximum power as
per actual demand and available generation.
2. Optimized operation of existed generation push towards fulfillment of energy need and
boost overall efficiency of generation system due to generator operated at full rated
capacity.
3. Optimal Dispatch Model ensures equalization of deficit margin between actual demand
and available generation, economic cost of operation and consideration of transmission
losses while scheduling of load.
4. Proposed model is developed by focusing especially Karveer taluka due to multidimensional approach in context of rural and urban region as well as various sectoral
demand considerations i.e. agricultural, domestic, industrial, commercial etc. for planning
scheduling and management of power at demand side.
392.
system security, reliable and ensures power supply and most important fulfillment in load
demand. Another factor that influence the power generation at minimum cost is
transmission losses. The most efficient generator in the system does not guarantee
minimum cost as it may be located in an area where fuel cost is high. Also, if the plant is
located far from the load center, transmission loss may be higher and hence the plant may
be uneconomical.
different plants such that total operating cost is minimum. The operating cost plays an
important role in the economic scheduling.
393.
394.
7. REFERENCES:
[1].
[2].
[3].
Power Sector".
MAHATRANSCO LTD. (2014-15), State Transmission Utility Plan.
U.S. Environmental Protection Agency (EPA) (2007), Biomass Combined Heat and
[4].
[5].
[6].
[7].
[8].
Power Apparatus and Systems, Vol. PAS-103, No. 10, pp. 2864-2881.
Albert M. Sasson (1974),"Some Applications of Optimization Techniques to Power
[9].
[10].
[11].
[12].
[13].
Power Apparatus And Systems, Vol. Pas-87, NO. 10, pp. 1866-1877.
Modern Power System Analysis, D. P. Kothari, McGraw Hill Pub. New Delhi.
Power System Analysis, Prof. Hadi Saddat, McGraw Hill Pub. New Delhi.
www.wikipedia.com.
www.nptel.com/electrical engineering/powersytem.
395.
396.