Escolar Documentos
Profissional Documentos
Cultura Documentos
Preprint 12-030
RISK RANKING IN TUNNELING PROJECTS WITH FUZZY ELECTRE METHOD
A. Yazadni-Chamzini, Islamic Azad Univ., Tehran, Iran
J. Brown, J. Reilly (2004) applied the cost and risk control for
tunneling and infrastructure projects. They identified the different kinds
of the risks as follows [2]:
ABSTRACT
Risk ranking of projects is one of the importance parts of the
complicated risk management procedure. Recognizing the riskiest
criteria enable the managers to plan for risk reduction. The first stage
for meeting this aim is defining the risky parameters and then working
to establish order between them. There are variety methods for risk
ranking. The ELECTRE method is one of the best among the multi
criteria decision making methods. In this paper with implementing the
fuzzy ELECTRE, The risky criteria in the Tehran Subway project are
being ranked. The result of this research presents damage and
accident of machineries as well as the lack of labor and equipment
safety is located in the first order. Collapse factors and local prices are
in second rank. Also wrong design, pollution, urban facilities
damageable are in third to fifth respectively. Delay and are located
in the last positions.
1234-
INTRODUCTION
At present, there are few approaches which solve the group
ranking problem with multiple criteria in a widely acceptable way.
Often, they rest on a poor heuristic which makes a decision about
consensus ranking difficult to support. The ELECTRE III multicriteria
outranking methodology may assist a group of decision makers with
different value systems to achieve a consensus on a set of possible
alternatives.
In many of the former studies for risk evaluation, only two criteria
were employed. In the other hand, since there is uncertainty in the
collected information, this risk should be taken into account.
Consequently fuzzy approach needed to meet this complicity. Due to
existing different criteria involved in risk ranking. It is a complicated
procedure.
FUZZY APPROACH
Fuzzy set was introduced by Zadeh in 1965 [10]. Fuzzy set theory
is a powerful tool to handle imprecise data and fuzzy expressions that
are more natural for humans than rigid mathematical rules and
equations [11].Since the decision makers are unable to determine the
A% = (a ,a ,a )
1
Where a1<a2<a3 and a1, a2, a3 are crisp numbers, Figure (1) show
triangular fuzzy number. As usual fuzzy numbers define by their
membership function. The membership function is a fuzzy number
between Zero and One. The membership function of a number such as
A% is as following:
0,
( x a1 ) / ( a2 a1 ) ,
f ( x) =
( a3 x ) / ( a3 a2 ) ,
0,
AHP METHOD
Analytic hierarchy process (AHP) is a multi attribute decisionmaking (MADM) technique [29]. The AHP method was first developed
by Saaty [30]. The AHP represents a potentially powerful and flexible
decision-making process to help set priorities and make the best
decision when both qualitative and quantitative aspects of a decision
need to be considered [31].
x< a
a1 < x < a2
a2 < x < a3
(1)
x > a3
C1
C2
x%11
x%
21
D% = .
.
x%m1
x%12
x%22
.
.
x%m 2
. .
. Ck
. . . x%1n
. . . x%2 n
. . . .
. . . .
. . . x%mn
A1
A2
.
(2)
.
Am
i= 1,2, , m; j=1,2, , k
w% = [ w%1 , w% 2 ,..., w% k ] , j= 1, 2, , k
Where
x%ij
w% j
x%ij
and
is
w% j are fuzzy
numbers.
Step 2- Normalization of fuzzy decision matrix (
N%
).
rij =
rij =
(3)
(4)
(5)
1
f ke =
0
In this step with having the weighted fuzzy decision matrix, and by
pair comparison of the alternatives this sets are constructed.
The concordance set (Ske) is a set of criteria in which the
alternative k is preferred to alternative e, and its complement set is non
concordance set (Ike). This formulated as follows:
%ej }
Ike = {j%kj
p %ej }
%ej }
Ike = {j%kj
f %ej }
k =1 e =1
k e e k
1
g ke =
0
(8)
hke = f ke .g ke
(14)
(15)
(9)
, d%ke d%
, d%ke < d%
d%ke =
D=
(13)
d%12 L d%1m
d%21 L d%2 m
M
M
M
d%
%
m1 d m 2
d%ke
m(m 1)
C=
D% =
(6)
c%12 L c%1m
%
c21 L c%2 m
M
M
M
c%m1 c%m 2
(12)
, c%ke c%
, c%ke < c%
(10)
jJ
C% =
k =1 e =1
k e ek
c%ke
m(m 1)
(11)
A8
A9
VH
VH
VH
Uncertainty (%) M
Ability
VL
VH
VH
Effect on
project goal
VH
VH
VH
Possibly (%)
Relation
Disagree
Agree
Relation
Disagree
Agree
A1 TO A2
A1 TO A3
A1 TO A4
A1 TO A5
A1 TO A6
A1 TO A7
A1 TO A8
A1 TO A9
A2 TO A1
A2 TO A3
A2 TO A4
A2 TO A5
A2 TO A6
A2 TO A7
A2 TO A8
A2 TO A9
A3 TO A1
A3 TO A2
A3 TO A4
A3 TO A5
A3 TO A6
A3 TO A7
A3 TO A8
A3 TO A9
A4 TO A1
A4 TO A2
A4 TO A3
A4 TO A5
A4 TO A6
A4 TO A7
A4 TO A8
A4 TO A9
A5 TO A1
A5 TO A2
A5 TO A3
A5 TO A4
{1,2}
{3}
{3,4
{3,4
{4
{}
{}
{1,4}
{3,4}
{3,4}
{3,4}
{3,4}
{3,4}
{3,4}
{4}
{1,4}
{1,4}
{1,2}
{3,4}
{1,4}
{4}
{4}
{4}
{1,4}
{1,2}
{1,2}
{1,2}
{1}
{1}
{2}
{1}
{1}
{1,2}
{1,2}
{2}
{2,3}
{ 3,4}
{1,2,4}
{1,2}
{1,2}
{1,2,3}
{1,2,3,4}
{1,2,3,4}
{2,3}
{1,2}
{1,2}
{1,2}
{1,2}
{1,2}
{1,2}
{1,2,3}
{2,3}
{3,2}
{3,4}
{1,2}
{2,3}
{1,2,3}
{1,2,3}
{1,2,3}
{2,3}
{3,4}
{3,4}
{3,4}
{2,3,4}
{2,3,4}
{1,3,4}
{2,3,4}
{2,3,4}
{3,4}
{3,4}
{1,4,3}
{1,4}
A5 TO A6
A5 TO A7
A5 TO A8
A5 TO A9
A6 TO A1
A6 TO A2
A6 TO A3
A6 TO A4
A6 TO A5
A6 TO A7
A6 TO A8
A6 TO A9
A7 TO A1
A7 TO A2
A7 TO A3
A7 TO A4
A7 TO A5
A7 TO A6
A7 TO A8
A7 TO A9
A8 TO A1
A8 TO A2
A8 TO A3
A8 TO A4
A8 TO A5
A8 TO A6
A8 TO A7
A8 TO A9
A9 TO A1
A9 TO A2
A9 TO A3
A9 TO A4
A9 TO A5
A9 TO A6
A9 TO A7
A9 TO A8
{2}
{2}
{2}
{1,2}
{1,2}
{1,2}
{1,2,3}
{2,3,4}
{1,3,4}
{2}
{1,2}
{1,2}
{1,3,4}
{1,2}
{1,3}
{3,4}
{1,3,4}
{1,3,4}
{1}
{1}
{1,2,3,4}
{1,2,3}
{1,2,3}
{2,3,4}
{1,3,4}
{3,4}
{2,3}
{1,2,3}
{2,3}
{2,3}
{2,3}
{2,3,4}
{3,4}
{3,4}
{2,3}
{}
{1,3,4}
{1,3,4}
{1,3,4}
{3,4}
{4,3}
{3,4}
{4}
{1}
{2}
{1,3,4}
{3,4}
{3,4}
{2}
{3,4}
{4,2}
{2,1}
{2}
{2}
{2,3,4}
{2,3,4}
{}
{4}
{4}
{1}
{2}
{1,2}
{1,4}
{4}
{1,4}
{1,4}
{1,4}
{1}
{1,2}
{1,2}
{1,4}
{1,2,3,4}
Step 5: the agreement matrix. Total weight for this purpose with
the criteria that have been agreed in the collection, Matrix agreed to be
the result. The resulting agreement matrix as Table7 (see Appendix) is
obtained
Step 6: The opposite matrix. The resulting matrix against is given
in Table 8.
A1
A2
A3
A4
A5
A6
A7
A8
A9
A1
0.00
0.05
0.65
1.00
1.00
0.75
0.00
0.00
0.42
A2
1.00
0.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
A3
1.00
0.25
0.00
1.00
1.00
1.00
0.68
0.38
0.43
A4
0.41
0.23
0.17
0.00
0.67
0.08
0.03
0.08
0.41
A5
0.40
0.11
0.16
1.00
0.00
0.08
0.25
0.05
0.32
A6
1.00
0.22
0.49
1.00
1.00
0.00
0.35
0.08
0.82
A7
1.00
0.35
1.00
1.00
1.00
1.00
0.00
0.24
1.00
A8
1.00
0.33
1.00
1.00
1.00
1.00
1.00
0.00
1.00
A9
1.00
0.21
1.00
1.00
1.00
1.00
0.65
0.00
0.00
A1
A2
A3
A4
A5
A6
A7
A8
A9
A1
0
0
1
1
1
0
0
1
A2
1
1
1
1
1
1
0
1
A3
1
0
1
1
0
0
0
1
A4
0
0
0
1
0
0
0
0
A5
0
0
0
1
0
0
0
0
A6
1
0
1
1
1
0
0
0
A7
1
0
1
1
1
1
1
1
A8
1
1
1
1
1
1
1
1
A9
0
0
0
1
1
1
1
0
-
REFERENCES
[1]
[2]
[3]
[4]
[5]
Merada, M.M., Verdel, T., Roy, B., Kouniali, S., (2004), Use of
multi-criteria decision-aids for risk zoning and management of
large area subjected to mining-induced hazards, Tunnelling and
Underground Space Technology 19, 125138.
[6]
[7]
[8]
[9]
A1
A2
A3
A4
A5
A6
A7
A8
A9
A1
A2
A3
A4
A5
A6
A7
A8
A9
A1
0
0
1
1
0
0
0
0
A1
0
0
1
1
0
0
0
0
A2
1
1
1
1
1
1
1
1
A2
1
1
1
1
1
1
0
1
A3
1
0
1
1
1
0
0
0
A3
1
0
1
1
0
0
0
0
A4
0
0
0
0
0
0
0
0
A4
0
0
0
0
0
0
0
0
A5
0
0
0
0
0
0
0
0
A5
0
0
0
0
0
0
0
0
A6
0
0
0
1
1
0
0
0
A6
0
0
0
1
1
0
0
0
A7
1
0
0
1
1
1
0
0
A7
1
0
0
1
1
1
0
0
A8
1
0
1
1
1
1
1
1
A8
1
0
1
1
1
1
1
1
A9
1
0
1
1
1
0
0
0
-
A9
0
0
0
1
1
0
0
0
-
CONCLUSION
Managing the risk in the projects with high level of investment
such as tunneling projects plays a central role. One of the main steps
in risk management is the evaluating the risk. Also ranking of risks is
one of the most important parts of risk evaluation.
[15] Selection of a Machine Tool for FMS Using ELECTRE III A Case
Study. The 5th Annual IEEE Conference on Automation Science
and Engineering. Bangalore, India, August 22-25, 2009 pp 171176
In fact the aim of risks ranking is dealing with the most important
risk among them because of limitation of financial resources. The multi
branches decision methods are the well known methods for ranking
the criteria. Also due to existence the uncertainties in ranking of
alternatives and criteria by decision makers as well as considering the
high ability of fuzzy approach facing with uncertainties, the using of
[21] Roy, B., (1978), ELECTRE III: algorithme de classement bas sur
une reprsentation floue des prfrences en prsence des
critres multiples, Cahiers du CERO, 20: 3-24
[29] Kazakidis, V.N., Mayer, Z., Scoble, M.J., (2004). Decision making
using the analytic hierarchy process in mining Engineering.
Mining Technology (Trans. Inst. Min. Metall. A) Vol. 113, pp. 3042.
[23] Roy, B., Skalka, J., (1984). Electre IS, Aspects Methodologiques
et Guide d,Utilisation. Document du Lamsade 30, Universite Paris
Dauphine.
Contractor
Wrong
Design
A3
Local
prices
A6
Environmental
pollution
A7
Equipments
break down
A8
Utilities
Damage
A9
0.70
0.63
0.30
0.56
0.85
0.78
0.45
0.71
A4
0.75
0.41
0.00
0.75
0.90
0.56
0.10
0.90
1.00
0.71
0.25
1.00
A5
0.47
0.00
0.15
0.75
0.63
0.21
0.30
0.90
0.78
0.37
0.45
1.00
A6
0.68
0.15
0.35
0.68
0.83
0.30
0.50
0.83
0.95
0.45
0.65
0.95
A7
0.75
0.47
0.47
0.55
0.90
0.63
0.63
0.70
1.00
0.78
0.78
0.85
A8
0.61
0.20
0.75
0.55
0.76
0.36
0.90
0.70
0.90
0.51
1.00
0.85
A9
0.15
0.35
0.68
0.55
0.30
0.50
0.83
0.70
0.45
0.65
0.95
0.85
0.82
0.91
0.45
0.64
A4
0.71
0.48
0.00
0.69
0.88
0.66
0.10
0.88
1.00
0.84
0.25
1.00
A5
0.38
0.00
0.15
0.69
0.56
0.24
0.30
0.88
0.74
0.44
0.45
1.00
A6
0.62
0.18
0.35
0.60
0.80
0.35
0.50
0.78
0.94
0.53
0.65
0.93
A7
0.71
0.56
0.47
0.44
0.88
0.74
0.63
0.63
1.00
0.91
0.78
0.81
A8
0.54
0.23
0.75
0.44
0.72
0.42
0.90
0.63
0.88
0.60
1.00
0.81
A9
0.00
0.41
0.68
0.44
0.18
0.59
0.83
0.63
0.35
0.76
0.95
0.81
A3
0.07
0.00
0.08
0.19
0.19
0.07
0.21
0.40
0.37
0.23
0.38
0.64
A4
0.11
0.00
0.00
0.52
0.26
0.07
0.07
0.79
0.45
0.21
0.21
1.00
A5
0.06
0.00
0.08
0.52
0.17
0.02
0.21
0.79
0.33
0.11
0.38
1.00
A6
0.09
0.00
0.19
0.45
0.24
0.04
0.35
0.71
0.42
0.13
0.55
0.93
A7
0.11
0.00
0.26
0.33
0.26
0.07
0.44
0.56
0.45
0.23
0.66
0.81
A8
0.08
0.00
0.41
0.33
0.22
0.04
0.63
0.56
0.40
0.15
0.85
0.81
A9
0.00
0.00
0.37
0.33
0.05
0.06
0.58
0.56
0.16
0.19
0.81
0.81
A3
0.45
0.08
0.65
0.73
0.38
0.38
0.38
0.45
0.65
0.20
0.80
0.95
0.45
0.50
0.45
0.60
0.85
0.35
0.93
1.15
0.50
0.63
0.50
0.73
A4
0.08
0.08
0.08
0.45
0.08
0.08
0.08
0.08
0.20
0.20
0.20
0.60
0.15
0.20
0.15
0.15
0.35
0.35
0.35
0.73
0.23
0.35
0.23
0.23
A5
0.08
0.08
0.28
0.65
0.00
0.00
0.00
0.08
0.20
0.20
0.40
0.85
0.05
0.05
0.05
0.20
0.35
0.35
0.55
1.05
0.13
0.13
0.13
0.35
A6
0.35
0.08
0.35
0.65
0.73
0.00
0.08
0.08
0.55
0.20
0.55
0.85
0.95
0.05
0.20
0.20
0.78
0.35
0.78
1.05
1.15
0.13
0.35
0.35
A7
0.73
0.08
0.35
0.73
0.73
0.73
0.45
0.45
1.00
0.20
0.55
0.95
0.95
0.95
0.60
0.60
1.28
0.35
0.78
1.15
1.15
1.15
0.73
0.73
A8
0.73
0.35
0.35
0.65
0.73
0.65
0.65
0.73
1.00
0.55
0.55
0.85
0.95
0.80
0.85
1.00
1.28
0.78
0.78
1.05
1.15
0.93
1.05
1.28
A9
0.28
0.28
0.28
0.65
0.65
0.65
0.65
0.38
-
0.40
0.40
0.40
0.85
0.80
0.80
0.85
0.45
-
0.55
0.55
0.55
1.05
0.93
0.93
1.05
0.50
-
0.65
0.85
0.85
0.51
A3
0.55
0.47
0.15
0.41