Escolar Documentos
Profissional Documentos
Cultura Documentos
This i s a r e p r i n t of t h e c h a p t e r on I r r i g a t i o n from
l i s t e d i n t h e Bibliography f o r t h e l a t e s t s t a n d a r d p r a c t i c e s
i n t h e f i e l d of I r r i g a t i o n .
P u s a t L a t i h a n Kakitangan,
J a b a t a n P a r i t dan T a l i A i r ,
Ampang.
February, 1981.
CONTENTS
Pass
<'HAPIER 111 -- IRRIGATION
SH TION I O B JTS~ ~AND G ~ N E R AREQUIREMENTS
I o f . IRRIGATION ... 109
Irr~gatlonRequ~rementsfor R ~ c eCultivation .. 111
General Descrlptlon of an Irrigation System . 111
Figure\
I 1 111 Irrigation System, General ... 112
I 1 - APPI.I(ATION o b WATERTO T H ~LAND
SEC'TION ... 114
Application of Water to Rice Land . . .. . .. 114
Appl~cation of Water to the Land for C r o p
other than Rice ... ... 123
18. The recommended water duties for rice cultivation for single and double
cropping are tabled below: --
I . Double Cropping System
Off-season
~ncheslmonths Acres[Cusec L.!Seclha
a. Presaturation period 40 days . . . 15 48 1.5
b. Normal itrigation period ... 10 71 1 .O
Main-season
a. Presaturation period 40 days ... 13 55 1.3
b. Normal irrigation period .. 9 79 0.9
2. Single Cropping S.wtem
a. Presaturation . . ... ... 12 60 1.2
b. Normal irrigation period ... 9 79 0.9
GENERAL DESCRIPTION OF .4N IRRIGATION SYSTEM
19. The objects and general requirements of itrigation have been considered
In the foregoing. The object of the irrigation system is to meet these requirements.
The system and its parts are considered in the following.
20. First let us look at an irrigation scheme as a whole and name its
principal parts. Fig. 1 11111 shows a hypothetical scheme in which the area to be
irrigated is shown hatched. The souice of supply (in this case) is a river. Water
from the river is backed up by a weir (or by a gate-controlled weir which is
called a "barrage") and diverted through a head regulator into the main canal
~f the scheme. The weir or barrage. together with the head regulator. is called
the headworks.
21. Water is conveyed to the area to be irrigated by means of the main
canal, which may divide into branch canals, each branch feeding a different part
of the area. The branch canals may supply feeder canals, each of which supplies
a number of distributary canals, or it may supply directly to the distributaries.
The distributaries supply water to the field channels, and it is normally from the
F I G . I/I/DI
field channels that water is supplied to the surface of the land. There is not always
a clear distinction between the various classes of canal. and some may be omitted
altogether. In a very small scheme there may be one canal only, which serves
all purposes. Usually it is inadvisable to pass water to the field except from a
field channel. as any other practice results in maintenance difficulties and loss of
water control.
22. Broadly speaking, canals can be divided into two classes: those
concerned primarily with conveying water to the areas to be irrigated, and those
concerned with distributing it over the areas to be imgated. The former do not
need to flow above ground level, whereas obviously the latter must "command"
the land to be irrigated, or it will be impossible for the water to pass from the
canal to the land. Distributaries and field channels fall into the "distribution"
category. The main, branch and feeder canals falls into the "conveyance"
category .
23. At the headworks, water in the river is backed up to a level which is
lower than bank level. Consequently, the hydraulic gradient of the conveyance
canals must be flatter than the slope of the land, in order that command may
be obtained at the head of the area to be irrigated. This, in fact, is usually the
reason for the substantial length of the main or branch canals.
24. At all canal divisions and at the heads of subsidiary canals, there must
be water controls of some kind. Canal controls may be provided also to fiatten
steep hydraulic gradients which would result in destruction of canals on account
of excessive velocities of flow, and to ensure command at critical points. Canal
design and control will be discussed in much more detail later.
25. In many cases it is necessary to provide a complementary drainage
system, this being shown in Fig. l/I/III in broken lines. More will be said about
this later.
26. In the hypothetical example considered above, water is diverted from
the river by means of a weir or barrage. In cases where the area to be supplied
is small in relation to the fiver, it will be uaaconomical to build such a structure.
however, and it may be better to raise water to the head of the main canal by
pumping.
27. Where the total annual or seasonal flow of a river is sufacient fot irriga-
tion of a required area, but the low flow of the river is insufficient to m a t the
maximum demand (which will often occur when the river flow is lowest), then the
only solution is to impound the flow. For efficient irrigation the water should be
~mpoundedin the river valley above the area to
this is impossible, and then some attempt is
on the land itself. The Pahang Paya systems,
systems which allow flush irrigation fall into
valley impounding scheme in Malaya at present is the Krian Irrigation Scheme.
SECTION 11 -APPLICATION OF WATER TO THE LAND
F I G 1/11/111
Double lines across the batas indicate small diameter pipes. Water can move
freely through the openings in the batas, but flow through the small pipes is
restricted. It will be seen that the strings of petak along the ridges shown shaded,
act in fact as very broad and shallow field channels, from which water is tapped
off, by pipes, as required, to the lower petak. In a similar way, strings of petak
3t lower elevations can be connected together for redistribution of concentrations
of water.
12. With the greater farmer co-operation and awareness which may emerge
under the community development drive, the method just described may often
ptove to be best; it dispenses with the necessity for field channel upkeep, it
provides no obstacle to movement of flood water, and no land has to be reserved
for field channels. It i s unsuitable, however. for irrigation of crops other than
rice.
13. With care and attention, these small valley schemes can be made to
work quite well. Without attention, however, they can be complete failures. The
most important point to note perhaps is that water needs no engineer effort
to make it move straight down the slope. It needs endless patience and attention.
however. to make it move across the slope. It stands to reason then that water
should never be encouraged to move across the slope unnecessarily. Quite enough
effort will be expended in making it do so when it is necessary. And when it is
necessary a whole hearted effort will be essential to get results.
14. At the other end of the scale. in contrast to the small valley areas. are
the broad flat areas of heavy soil such as are found in the lower parts of Krian.
Such areas are, in effect, broad shallow pans. There is no difficulty about distri-
bution, so long as there is enough watef to meet plant requirements, evaporation
and percolation losses. All that is really necessary is to supply water at convenient
points in ordet to keep the pan topped up. The supply points must not be too
far from any part of the area, because if they are, supply at the beginning of the
season to remote parts will be too long delayed. It is difficult to prescribe limits.
but it is suggested that no part of a level bendang should be more than half a
mile from a supply point.
15. Drainage in such flat areas may be more of a ptoblem than irrigation
distribution. It must be possible to remove flood water reasonably quickly. and
it must be possible to drain oii quickly at the appropriate time before harvest.
Flat land is not conducive to quick drainage, so it is suggested that no land should
be more tRan about a quarter of a mile from its drain. To prevent loss of water
during the *igation season, drains should be provided with gates to hold up
water levels in the drains.
16. A general arrangement as in Fig. 5NIIrII would be quite suitable for rice
~rrigationon heavy Bat land. The arrangement would not be adequate for other
crops.
17. Intermediate in type between the small, steep. narrow valley a l a s and
the broad flat areas just described, there are the extensive, even areas of gentle
slope. such as are found in Tanjong Karang and Kubang Pasu. The slope of these
areas may be a foot or so in the mile. They are too steep to be treated as flat.
yet their slope is so small that the detailed atlention accorded to small valley
areas would be quite out of place and very untconomica!.
18. Flg. 6'IIIIII shows the peneta1 pattern of imgation and drainage in
Tanjong Karang. The general arrangement of lots is also indicated. The land is
near]? enough level for it to be possible to irrigate across the slope. as opposed
to down the slope. without special difficulty. and the arrangement works quite
satisfactoril? and has the advantage of cheapness. There is of course a general
tendency for water to move downhill towards the sea, but this is countered by the
cross bunds. Such bunds are constructed to stop movement of watef towards the
lower part of the arza. and therefore they should not be pefforated by pipes and
MAIN CANAL
the like. except in special circumstances. As such perforations go contiary to the
design intentions, such "special circumstances" should be discussed with the
designer, before any action is taken. This point is most important. The purpose of
ctoss bund will be completely defeated if the bund is riddled with pipes. It will be
found impractical to remove pipes again after they have been allowed, so it is
imperative that pipes be not put in except with the designer's authority.
19. The general artangement in Kubang Pasu is similar in principle to that
in Tanjong Karang, but is complicated by the fact that an irrigation system had
10 be superimposed on an existing, though inefficient, drainage system. The water-
ways running from the main canal to the sea have to setve the dual purpose of
migation and drainage. They are much larger than at Tanjong Karang, and it is
ndt practical to ptovide numerous offstake points in their banks. They are also
too far apart to allow irrigation across the contour. Irrigation is actually "uphill"
from distributaties lying immediately above the cross bunds. This uphill irrigation
:s possible for two reasons. Firstly the land is nearly enough flat that a maximum
dlowable depth of water at the distributaty ponds back a long way towards the
next distributary on the uphill side. Secondly. the presence of contour bands of
\rater. positi~ei) heid and topped up as necessary, makes it much easier to
,onserve water reaching the land in the form of rain. Rainfall in the North Kedah
Plain is favoutable for wet season rice production, and conservation of rain water
1s as important as provision of irrigation water. Were it not for this fact, the
method would not have much to commend it. The distributaties can be used also
d\ d r a m . to discharge excess water. Again attention is drawn to the fact that
perforation of the cross bunds would defeat the purpose of the bunds, which is
to prevent water moving downhill towards the sea. Fig. 7IIIIIII shows the general
irrangement on a section at right angles to the sea.
$0. The atrangements at Tanjong Karang and at Kubang Pasu are suitable
for rice cultivation but would not be at all suitable for irrigation of crops not
tolerant to standing water and waterlogged soil. It is doubtful whether the system
a: Kubang Pasu would be adequate for off-season rice cultivation, because, as
explained already. it depends largely on combination with direct rainfall.
1 The system adopted in Sungei Manik and in Trans Perak Stage I is
more su~tablefor steeper and less even land. It is illustrated in Fig. 8/1I/III. Every
lclt on the distributary frontage has a supply point, and every lot on the drain
fmntage can discharge to the drain. Thus each pair of lots can work more or
Ic*s independently of other pairs, as regards irrigation and as regards drainage.
lu practice. individual drainage may be difficult, as water level in the drain is
usually regulated for the common good.
22. The arrangement just described is quite a good one. It could not be
improved on much except by making individual lots natrower and longer, so that
tach lot ran the whole way from the supply canal to the drain. Each farmer would
then be independent of other farmets. This is not so important where only rice
is grown. But it IS important where other crops are to be idigated, as will be
explained later.
23. With reasonably favourable rainfall, a great deal can be done on flat.
heavy land. merely by careful conservation of rain water. Such schemes are called
' controlled dtainage schemes". because they conserve water by controlling the
drainage within them and from them, to the best advantage. Where there is no
.:deqcate sources of irrigation water. a controlled drainage scheme is the best that
can be done. Some schemes, destined finally for irrigation, start off, however, as
controlled drainage schemes. The reason is that in the tirst few years of opening
up an area from swamp jungle. a great measure of success can be obtained without
irrigation. and it is cheaper and quicker to open up initially for controlled drainage.
Tanjong Karang and Kubang Pasu are examples of areas developed in this way.
The layout of such schemes is as described fot Tanjong Karang or Kubang Pasu,
but without any irrigation supply.
FIG. 7/11/111
ARRANGEMENT
OF LOTS
I I I I I
h-I-7-r
DRAIN
24. The Pahang Paya system of irrigation is peculiar to Pahang; and it is
likely to remain so, for few ateas outside Pahang would be suited by the system.
The Fahang Paya is generally a shallow basin-shaped depression lying near the
Pahang River, with a narrow outlet to the river. When the river rises in flood,
the payas are inundated. Consequently the rice crop hasato;be harvested before
the annual tise of the river. It follows that planting must.start in the dry season,
and that little reliance for irrigation can be placed od small streams passing
through the payas. The system is illustrated in Fig.9/II/Iq. The paya outlet is
blocked by an earth dam, and a conttol gate and culvert &re-provided for drainage.
Before the planting season. water is impounded in the p y a and allowed to
thoroughly saturate the soil to a great depth. At the appropriate time, planting
starts round the edge of the paya, and follows the receding water as this is slowly
lowered. In the higher part of the paya, short stemmed v rieties are planted; and
in the lower parts. long stemmed varieties. When plantin!% complete, the water
level in the paya is allowed to rise, but at a rate not gfeater than the rate of
growth of the plants in the lower parts of the paya. Thus the crop depends for
its growth on water held in the soil and in the petak, on such rain as may fall
and on such water as may be safely impounded in the paya as growth proceeds.
A detailed description of Pahang paya cultivation is at Enclosute No. (1) in
DDI. 215'55.
APPLIC.4TION OF WATER TO THE LAND FOR CROPS OTHER THAN RICE
35. At present. no serious attempt is made to irrigate crops other than rice.
except by a thousand Chinese vegetable gatdeners who hump the water in watering
cans. There is little doubt, however. that there will be a call, sooner or later. for
irrigation of other crops. Therefore a little is said about the subject here, if only
to avoid rice irrigation layouts which will be unsuitable when the demand for
irrigation of other ctops comes.
26. The aim of such irrigation will be to keep the moisture content of the
soil. in the root zone of the crop being gtown, within the limits of moisture content
acceptable to the plant. If too little water is supplied the plant will wilt, If too
much is supplied, so that the water table rises into the root zone, the plant will
drown. If the soil is free dtaining, so that the water table does not rise in spite of
excessive irrigation, water will be lost by deep percolation and this water may
reappeat elsewhere in a manner which may do damage to other agriculture. Also.
plant foods will be carried away by the percolating water. Thus it is necessarv
to apply the right amount of water at the ptoper intervals of time, and this is
impossible unless the irrigation layout is correct.
28. For irrigation of field crops, the land is usually divided into long narrow
beds with a gentle slope. The beds are commonly from about 30 ft. to 100 ft. wide.
and from 300 ft. to 2,000 ft. or 3,000 ft. in length. The method of irrigation is
to supply water at the top end of the strip, and ta let it run down to the bottom
end, wetting the gtound as it flows. Usually a shallow drain is provided at the
bottom end of the strip. but this is not meant to remove excess irrigation water.
There should not be a@ excess irrigation watet. The general arrangement is shown
in Fig. lO'II/III.
29. In Fig. lOIIIIIII, assume that the irrigation supply is turned into the bed
shown, and that after a certain time the sheet of watet flowing between the batas
has reached line B. Of the water being supplied at the head of the bed, some is now
percolating into the soil over the area A1. which has been covered, and only the
balance is available f a ' moving on. When the water has advanced to line C, water
SCALE: OF MILES
'/r o II~UILC
is percolating into the soil oyel;@e g Az, and still less is available for moving
86
on beyond line C. Thus the rate of a vance of the water down the bed is steadily
getting less. Eventually if the bed is long enough, when the rate of percolation
into the ground is equal to the rate of supply at the head of the bed, the water
will stop advancing. Thus it is seen that the longer the bed which is to be irrigated
by a stream of a certain size, the greater will be the average depth of water
supplied before the advancing water reaches the end of the field. If the bed is
too long fot the size of the irrigation stream, the average depth of water supplied
is too great, and there wilI be waterlogging or loss of irrigation water and plant
nutrients by deep petcolation. For a bed of a given width and length, the average
depth of water can be reduced by increasing the rate of application. Evidently
light soils to which water infiltrates freely require higher rates of application or
shorter beds. Beds can be somewhat longer if they slope more steeply, as the
water then advances mote rapidly and irrigation is completed more quickly. But
~f the slope is too steep. the irrigation water may erode the surface. On the other
hand, for heavy soils, longet beds, flatter slopes and lower rates of application are
appropriate. The science and art of application of irrigation water to land for ctops
other than rice, aims to get the right combination of bed size, dope and rate of
application. for the crop being grown. It is not normally feasible to change the
layout for different ctops. The layout will usually be determined once and for
all on consideration of the nature of the soil, the crops likely to be grown and
the maximum size of irrigation stteam which may be available. Latitude in
operation can be obtained by varying the size of stream for the purpose required
(e.g. a relatively small rate of application would be used for a deep rooted crop).
or by controlling the rate of movement and percolation of water by the use of
furrows or by checks, etc.
30. We have little knowledge in Malaya at present on the subject of irriga-
tion of other crops. It is suggested, howevet, that if we lay out our new irrigation
schemes on the lines shown in Fig. 11/II/III, where thisl is possible, we shall have
schemes which are suitable for rice and for most other field crops, and which
will not be unduly expensive.
31. The suggested length of field channel is not irrelevant. It is based on
an assumed channel capacity of 2 cusecs, it being assumed that, when crops other
than rice being grown, the whole of this is applied in turn to each bed, and that
this is as much water as can be handled comfortably by a single farmer. If the
channel capacity is 2 cusecs, and the duty is 60 acres per cusec, then the total
area served by the field channel must not exceed 120 acres. Hence the length of
the channel.
32. The arrangement suggested would give a rate of application of 0.4 acres
per cusec, if each lot were tteated as a single bed. The lots could be longitudinally
subdivided, however, thus increasing the rate of application to any figure which
proved to be desirable.
33. The lot length proposed, i.e. 30 chains. is a comptomise with economy
and practicability. To reduce the length to 20 chains would result in an expensive
layout and one in which too much land was used for canals and drains. Lots
40 chains long, on the other hand, might be difficult on account of irregulatities
in the land surface.
FIELD CHANNEL
----
DRAIN
SECTION Ill - SOURCES OF IRRIGATION WATER
1. There are three sources from 'which water can be obtained for the
irrigation of padi. namely direct rainfall ovef the padi fields, from rivers, streams
or lakes, and from underground water.
DIRECT RAINFALL
2. The traditional padi fields in Kedah, Perlis, Kelantan, Perak, Negeri
Sembilan and Malacca otiginally depended on rainfall for padi cultivation, and
the fanners planned their ploughing and planting of nurseries at the beginning
of the wet season. The planting dates and other agricultural activities would
therefore be dependent on the start of the rains, and one of the most important
features in these areas is the existence of well formed batasses between lots laid
out on contours. These batasses are absolutely necessary for the retention of rain
water within each lot for the successful cultivation of padi, and even to-day there
are many small sized padi areas scattered throughout Malaya where the farmers
use this method for padi cultivation. The success or failure of a crop depends
on the availability of rainfall.
SURFACE WATER
3. The second source of irrigation supply. i.e.. from rivers and streams has
been most extensively used in Malaya.
4. In Malaya. the existence of a mountain range running roughly along
the centre of the peninsula has resulted in large numbers of rivers or streams
flowing eastwards and westwards to the sea. This feature coupled with the heavy
rainfall and thick forest cover has ptoduced conditions where streams seldom run
dry and provides excellent sources for irrigation and other water supply purposes.
5. The most common methods of abstracting water for ifrigation from
surface water are listed below: -
(a) Direct tap off from a river by means of a side intake.
( b ) Barrage or headworks across a river or stream.
(c) Dam across a valley to form a sforage reservoir.
(dl Pumping from a wide river.
(e) Low bunds across a valley to inundate the padi fields within the valley.
or control structures across rivers to regulate the water levels and
inundate the surrounding padi fields.
6. Where physical conditions permit it is most economical to abstract wate-
from a river by a side intake suitably located along a river bank. The important
factors to be taken into consideration are :-
(a) Flow in the river during dry periods and quantity to be abstracted.
( b ) Water levels in the river at abstraction point. and whether these are
stable.
(c) Amount of silt load and suitability of water for irrigation purposes.
. - Flood levels and exclusion of flood flows from t h e iniake canal.
fd)
This can be catered for by judicious bundin? and provision of gates
at the intake structure.
7. It is generally advisable to carry out detailed surveys of the river 1 mile
upstream and f mile downstream of tne proposed abstraction point and collect
hydrological data covering discharges and corresponding water levels to enable
the conduct of a model study of the intake to verify the hydraulic performance of
the structure.
8. A typical side intake structure used for extraction of 600 cusecs from
the Sg. Perak for irrigating the Trans Perak Stage IV scheme is shown as
Figure 1/III/III.
9. The most extensively used method of extraction of water from a river is
by means of a batrage across the river with an intake of suitable size to meet
irrigation requirements. The structure usually consists of a reinforced concrete
Boot slab with side walls and a steel segmental gate.
10. During irrigation seasons, the gate is lowered in order to raise the river
level so that this is high enough to command the irrigation area. Normally the
structure is large enough to pass the flood waters when the gate is lifted. Sometimes
for reason of economy, a headworks structure is built with a limited flood
discharge capacity and an earth flood spillway provided along side to cater for
excess flood waters.
11, The selection of sites for headworks structures should be based on the
following considerations: water level command; suitable foundation soils; ease
of access to facilitate construction and also the minimum compensation for loss of
agricultural or village land as a tesult of inundation due to the raised water
levels upstream.
12. A typical headworks structure is shown in Figure 2/III/III, where two
numbers of 3'-0" x 12'4" segmental gates are provided.
13. For small structures where it is not economical to station a gate keeper
to operate the headworks and off-take gates, an automatic type of gate of the trip
type or a bear trap gate can be provided. Fig. 3/III/III shows a 20 feet wide Bear
Trap Gate.
14. It is usual to incorporate a drop in the headworks structure to cater for
the tetrogression of the downstream river bed, especially in steep riverine valleys.
Fig. 2/1II 1111 shows the 14th mile Terachi Headworks with a 9 feet drop.
15. Where the dry weather flow of a rivet is insufficient to meet irrigation
requirements, particulatly in the case of double cropping, then the solution will
be to study the possibility of constructing a dam across the valley of sufficient
storage capacity to meet the demand, based on water requirements for padi
cultivation.
16. In this case, studies will need be made from existing top0 maps, aerial
photographs and actual surveys including geological studies to locate a suitable
site for a dam. The site should be across a narrow valley with high ground on
both flanks and with a reasonably large reservoir capacity upstream.
17. Detailed soil investigations should be carried out at the proposed site
to determine the most suitable type of dam and its height, and in most cases of
low dams up to 50 feet high, earth filled dams would be most suitable, in which
event the source of fill material will also require investigation.
18. Hydrological data including rainfall, mean fiver discharges and
maximum flood discharges will be required for studies on irrigation storage and
flood spillway designs.
19. An earth dam with the intake and flood spillway at Bukit Merah in
Krian is shown as Fig. 4a/III/III & 4b/III/III.
20. A reinforced concrete buttress dam of 100 feet high on the Sg. Muda
and a rolled rock fill dam 200 feet high on the Sg. Pedu for the, Muda Irtigation
Project, with a concrete lined canal 44 mile long connecting the two reservoifs
is shown in Fig. S/III/III.
21. Should a river from which water is to be abstiacted for irrigation be
very large, or where a considetable rise in water level will be necessary to enable
gravity irrigation, then pumping will be the best method of abstraction. For this
reason, pumping stations are mainly located at the lower reaches of larger rivers
in the country.
18. When a padi area I S located in a flat valley and there is no reliable
water supply either from a stream or from a suitable source of water nearb,c.
then an inundation scheme consisting of a low bund across the valley provided
with a control gate i s the most suitable method. This type of schemes are exclu-
sively located in Pahang within the Pahang River Basin.
29. The irrigat~onareas are usually small ranging from 50 acres to 500 acres
and the stream catchments are of I to 10 square miles in area. Earth bunds are
formed to heishts of 4 to I2 feet with a control gate to discharge flood waters.
Sometimes an earth spillwa) I S also provided alongside the gate to facilitate the
passage of flood flows
30. These schemes are generally considered as "sub-standard" schemes and
are not ~dzal. During the monsoon periods the gate is closed and water is retained
behind the bund to soak the field. As planting takes place, the stored water is
gradually released and from then on the padi plants depend only on rainfall for
growth. as the stream generally runs dry. Yields for this type of scheme are very
low and only one crop can be planted out a year.
3 1 . A typrcal layout of an inundation scheme is shown on Fig. 9;III '111.
32. Similar to these. but embracing larger areas and located on coastal
plains are the so called controlled drainage schemes. Noteable among these are
the Panchang Bedina Scheme in Selangor. the Wan Mat Saman Area and the
Kubang Pasu Areas in Kedah.
33. A main feature of these areas is that the latge tract of padi land has
relatively small fall. One or more rivers may traverse the area, part of which
may be subject to saline intrusion. Structutes are built across suitable sections of
the river with gates to regulate the water level and cause backing up thus inun-
dating the adjacent fields to varying depths. During floods the gates are opened
to let out the flood waters. Gates are also opened during harvesting and ofheason
period to drain out water from the fields.
34. These schemes lack assured water supply, as during dry years river
flaws may not be sufficient for flooding the higher fields. Watet depth in the
fields is not uniform, with the lower fields flooded to greater depths than higher
fields. Drainage during rainy seasons often presents problems.
However these schemes are cheap and during years with well distributed
rainfall reasonably good yields have been obtained.
GROUND WATER
35. Hitherto irrigation using ground water has not yet been done in
Malaya, because of the availability of surface water in the majority of cases.
and the inadequate knowledge of ground water resources potential.
36. In places where the exploitation of available surface water is approaching
its limit, there will be a need to look for possible ground water resources for
fuither irrigation development. Much work remains to be done in this connection.
SECTION A - A
D ~ S ELEVATION
FIG. 2/%/m
SECTIONAL ELEVATION QPSTREAM ELEVATION
-
PLAN -.
mrw IMTAUE ,
I R R I G A T I O N RESERVOIR
\
GENERAL P L A ~OF INTAKE
1 REMOVABLE
105 C T . U l C Y
6 0 , 0 0 0 C U YO). COMCRETE
MUDA IRRIGATION PROJECT
,/2
0
CAST !N S I T 0 R t l N F 0 R C € O C O N C R E T E
SCABS OM TOP OF Y E U ~ ~ A U
ART~CULATED
FOR S C U C C U RAKE R A I L S . FOR ORTAILS 2
' cn
S E E D R A W I N G No 2 0 9 1
2
Q SPILLWAY CREST
DOWNSTREAM SLAB
UP' S T R E A M S L A B
TAlNlNG WALL
C U T O F F WALL-\
IVLCAIL
V ALV8 AUO
VA~
L ~U -
C ITSI V ~ LU ~
A CO
U nu. Cob
I ~4111
M ~ AWN D SECTION THROUGH DAM S E E D R A W ~ H CNO 212
J
REGULATOR VALVE B L O C K F O R D E T A I L S
SfILL
C U T OFF*
WA L L
1 DOWNSTREAM ELEVATION
CA? L A W =
UPANSWN JOIN?
WA?CR STOP
CONCRETE
L.
-
PLAN
SECTION A - A
FIG. 4 / ~ / l l l
SLOPE I : I
C-
13:O"
SECTION A-A.
1 SLOPE I : (
OFFTAKE
...... .,..04
...,. :..L
'
/
I....
"1
CULVERT
L i
T
.. . -
...,:.-.. <. .,.-,....- --.-
, .:
'd
..........
,.:.-.i
O MAIN CANAL
+ 2.2- ...0:0.. -..-.
i....
E X I S T I N G R.C S L A B
TANJONG
BERNAM RIVER
SECTION
KARANG
8-6
IRRIGATION
HEADWORKS SILT
A
SCHEME
86:0"
EXCLUDER
SECTION 1V.-DISTRIBUTION
10. As a conveyance canal does not normally have to have direct command
of the land. it should be placed in cut whenever possible. as there can then be no
breached banks.
I I. In hydraulically designing a conveyance canal it is necessary to ensure:
( a ) that its capacity is sufficient. and
( h ) that it will be stable.
By stability is meant that there is no progressive change of slope or of cross
section. In fact. the channel should be in regime. For a given discharge and
sediment charge. there will be stability only .if width. depth and slope are
acceptable. taking into account the material of which the channel banks arc
formed. An appreciation of this fact is important. Two examples will make the
principles clear.
12. Consider a channel which is in regime with a certain discharge and
sediment charge. Let the discharge remain the same but increase the sediment
charge. The additional sediment will deposit at the head of the channel and a
steeper slope will build up progressively till the higher velocity over the new slope
can carry forward the whole of the new charge. With increase in velocity. the
drag of the water on the wetted perimeter increases, and this may now exceed the
permissible intens~tyof tractive force on the banks of the channel. The banks
will then erode and fall. thus causing the channel to become wider and shaIlower.
until--as a result of decrease in velocity and in depth in the wider and shallower
section-the attack on the banks ceases and stability is once more achieved.
A new regime has been attained in which all dimensions are different. Thus it is
seen that discharge. sediment charge. bank material, slope and cross section are
all interrelated.
13. Again. consider an excessively wide channel carrying suspended
sediment. Drag at the sides will be so low that some of the sediment is deposited.
causing the channel to become narrower and deeper.
14. It is interesting to note too that where the sediment consists of coarse
particles only, the channel may be able to silt its bed, but it will not silt its banks
because the coarse sediment is travelling along or close to the bottom. Similarly
a channel carrying fine sediment only may grow narrower by deposition on its
banks. but will not silt its bed unless velocities are very low. Thus a channe!
carrying turbid water but no sand tends to be narrow and deep. and vice versa.
15. Canal regime theory, developed in pre-partitioned India, expresses these
principles quantitatively. Blench's exposition in "Civil Engineering Reference
Book". Han. 62 1 in D.I.D. HQ. library. is brief and readable. and is recommended
for study.
16. The formulae given by Blench, cast in convenient form are:
The most important point to note from the table is that regime sections
are far removed from the "most efficient" channel sections of conventional rigid
boundary hydraulics.
19. To what extent is regime theory applicable in Malaya? The question
is worth asking, for we have generally managed quite well without it. At any
rate, this is probably the belief of many. who have just regarded the misbehaviour
of a canal as "one of those things". There is no doubt that the theory is applicable
to canal systems taking off from sediment laden streams. Also there is no doubt
that in the past a numbet of our canals have been constructed to non-regime
dimensions and slopes. Probably the most common fault has been to make
sections too deep and too narrow, so that there has been a tendency to silt and
to erode banks. It is suggested that regime theory is worth applying in the case
of canal systems supplied from sandy tiver headworks, at least in the main canal
and in all canals to which bed sediment has access.
20. For pumping schemes and systems supplied from impounding reservoirs,
there will be no bed sediment in the canals unless it is brought in by streams
entering the canal system or by bank or bed erosion. If sediment does become
present, the canal will attempt to acquire a regime section and slope. To avoid
erosion of banks in small canals of this kind, the following are the mean velocities.
beyond which trouble will almost certainly occur:
Sandy loams ... ... 2 ftlsec.
Clay loams ... ... 3 ftlsec.
Stiff clays ... ... 4 ftlsec.
For larger canals, a regime theory check is advisable.
21. It is safer and better to err on the side of excessive width, if in doubt.
With a little care, a canal which is initially of too wide a section will build itself
tough berms, if there is a reasonable amount of sediment in suspension, and these
berms will be beneficial. If, on the other hand, the canal is made too narrow, it will
scour its banks and silt its bed, and permanent repairs will be impossible unless
the faulty bank alignment is rectified by setting back. This may be difficult and
expensive.
22. Whether or not regime theory is applied in any pafflcular case, there
is much less possibility of blundering if the principles have been digested.
23. It is probably appropriate to mention here that except when a canal
is in cut, the initial cross section of waterway is not usually determined by
hydraulic considerations at all. Usually the banks of a canal which is requited to
command the land will require more spoil than can be obtained from a hydraulic
section of waterway. Therefore the section is excavated large enough to obtain
the required amount of bank spoil. It is better in such cases to excavate wide and
shallow rather than deep and narrow. In developed areas, however, land acquisition
will be expensive if this principle is pressed too far.
24. The capacity of any particular canal must depend on its place in the
system and the type of system. The main canal obviously has to carry the
maximum demand of the scheme, taking into account any losses which are
likely to occur.
25. It does not follow, however, that the sum of the capacities of branch
canals should be equal to the capacity of the parent canal. If the system is
a rotational one, in which rotation is practised as between different parts of
the system, then the canals supplying the different parts must have sufficient
capacity to supply the maximum demand of the parts served. For example,
if a feeder supplies three distributaries, and rotation is to be practised between
the three distributaries, then each of the distributaries must be of the same
capacity as the feeder.
26. Losses from canals may be by evaporation and transpiration, by per-
colation, or by plain leakage. Loss by leakage should not be allowed for. Tho
correct course is to stop the leaks. Transpiration and evaporation losses from
canals in Malaya do not seem to be at all serious, and can be ignored. Per-
colation losses from canals in heavy clay are negligible. It is only percolation
losses from conveyance canals on sandy or sidelong ground that may be serious
Each case will have to be examined on its own merits. Rule of thumb cannot
be applied. Where loss is serious, lining may be necessary. Canals may be
lined with a skin of concrete or mortar, or bitumastic or plastic membranes may
be placed in the soil, around or under the section. Usually in Malaya, canal
losses are not serious, and in this we are fortunate.
27. Where possible, canals should be in cut, in order to reduce recurrent
maintenance costs.
28. Where a canal cannot be put in cut, the water must run between
banks. Fundamentally, the banks of a canal are for retaining water in the
canal, and must be stable when regarded as dams. They must also be reason,
ably watertight.
29. Rather arbitrarily, a percolation gradient of 4 to 1 is generally accepted
in Malaya as good enough, for average good clayey bank material. See Fi8.
2/IV/III. Each case should be considered on its merits, however. If a bank
shows seepage generally at its outside toe, then the percolation gradient is too
steep for the bank material, and in all probability bank failures by piping wit1
be frequent.
33. The dimensions obtained by considerations of percolation may not bo
the governing ones, however. Experience has shown that a bank which is to b
maintained departmentally must have certain minimum dimensions. Down to
and including distributaries, the following are the minimum requirements, which
must not be set aside on any consideration of expediency.
Top width must never be less than 4 feet. where only pedestrian
traffic is to be allowed. Where cycle traffic is to be allowed, this shouid
be increased to 6 feet. For large canals and where special maintenance
methods are to be used, (e.g. tractor weedin,.) the top width should be
further increased.
Freeboard for distributaries and small canals must be maintained
at not less than 18 inches. 2 feet or 3 feet of freeboard is appropriate
for larger canals.
Side slopes for banks in the best materials should never be steeper
than If to 1. For less good materials, side slopes of 2 to 1 or evaq
3 to 1 should be adopted.
31. It is debateable whether or not berms should be provided. Fig.
3aiIVIIII shows, in full lines, a canal bank set back from the channel, leaving
a berm between. The dotted line shows an alternative bank slope on a flatter
gradient. On the face of it, it appears that the dotted line would be better
than the arrangement with a benn. In practice, however, a flat bank slope
below water level seems to be peculiarly susceptible to attack; and very aeqrly
always, the section finishes up as in Fig. 3bINIIII. This, clearly, is less stable
C A N A L BANK
-
-
--
--
-
WATER LEVf L
GROUND,
-
FIG. 2/1V/ll1
FIG . 3 b/lVlllI
than the berm arrangement, and bank repairs will be more difficult and expensive.
Berms are very useful as walkways for excavators on desilting and repair
work. At a pinch. berm material can also be used for emergency bank repair
work. On the whole then, it seems preferable to provide berms, if space permits.
Unfortunately it does not always permit. Where provided, berms should pre-
ferably be wide enough to run an excavator, appropriate in size to the main-
tenance work which may be required on the canal.
CANAL CONTROLS
11 . - -. PLAN
FIG.
SECTION
PLAN
FIG. 5/1~/lll
OVERSHOT CONTROL
(USUALLY A LONG WEIR)
R
UNDERSHOT CONTROL
USUALLY A GATED
MAJOR CONVEYANCE C A N A L
(VARIABLE DISCHARGE)
/DISTRIBUTARY
(CONSTANT DISCHARGE)
SECTION A-A. SECTION -
B 8.
39. Similarly, command and gradient controls along the length of a dis-
tributary should be weir type controls, and field channel head controls should
be undershot types.
40. A system in which main canal discharge varies will work smoothly
and nearly independentIy with overshot main and branch controls and undershot
distributary and field channel controls. With types reversed, it will need con-
stant fiddling, with great sensitivity in one part as a result of fiddling in
another.
41. In some schemes, a constant proportionate division of water is
required, as between two or more branch canals. This can be achieved by
setting weir type controls with equal crest levels at the head of the branches.
(Orifice types are not suitable for this purpose, as they are sensitive to down-
stream water levels, which may vary in the branches). So long as the bi-
furcation control is not also a command control, the matched weirs can be
narrow and deep, for economy, provided they are of streamlined section, as
shown in Fig. 7/IV/III. Weirs of this type are not affected by downstream
water level, provided the depth of submergence does not exceed 80 per cent.
That is to say, if the head over the weir was 1.0 ft. the discharge would
not be affected by tailwater level, so long as this did not stand more than
0.8 ft. above crest level. In fact the discharge is not seriously affected till
over 90 per cent submergence. So long as a clear hydraulic jump forms, it
can be taken that the discharge is not appreciably affected.
42. The undershot distributary head control already described is a very
rudimentary form of "module". a module being a control aiming to give
constant discharge notwithstanding differences in head. There are a number
of more efficient types, but economic circumstances have not yet favoured
their use in Malaya. A very simple type is the NEYRPIC module, developed
by the NEYRPIC Research Laboratories at Grenoble. Details of this patent
type are available at D.I.D. HQ. NEYRPIC has also developed a number of
automatic control gates, which are in use in systems in other countries where
water is very scarce. These might be useful in Malaya when more value is
placed on water than at present. These types include automatic gates designed
to hold constant upstream or constant downstream water levels.
43. The control regulating entry of water from the source 'of supply to
the canal is called the canal head regulator. Where supply is from a sandy
river, the location of the head regulator requires special attention. It must
be placed at a point on the river bank where the surface movement of the
water is towards the bank and the bottom water is moving away from the
bank. This, of course. implies a corkscrew motion of the water as it travels
down the river. and this motion is found on bends. The surface water moves
towards the outside of the bend, and is clean, apart possibly from floating
trash. The bottom water is moving towards the inside of the bend, and is
sweeping the bed sediment towards the inside of the bend. The sediment is
deposited on the inside of the bend, as we all know. If the canal head were
on the inside of the bend, this sediment would be drawn into the canal.
Hence, the canal head regulator should be put on the outside of a bend and
must in no circumstances be put on the inside. Where possible, the bend
should be gentle, as the bank may be unstable on a sharp bend. Also, the
current may not follow closely round a sharp bend, but may bounce off
the side, creating a reverse eddy which might lift sand, at certain parts of
the bend. (This has happened, in fact, at the Muda River intake. The main
current bounces off the outside bank a short way upstream of the intake, and
a reverse corkscrew current lifts sand into the intake mouth). It is recognised
nowadays that correct curvature of flow at intake is the most important factor
in prevention of entry of bed sediment to a canal.
44. The corkscrew motion of water round a bend results from an unequal
tendency of top water and bottom water to back up on the outside of the
bend as a result of centrifugal force. The top water is going faster and tends
to back up more than the bottom water which is going more slowly as it is
subjected to bed drag. Hence the top water tends to back up more than
the bottom water. The unbalanced head cannot be sustained however, so at
the outside of t h e bed there is a downward flow, and at the inside there is
an upward flow. Consequently there must also be a flow at the surface from
h i d e to outside, and from outside to inside at the bottom.
45. A further point about the canal head regulator is that it will draw
a greater proportion of clean top water if its crest is high and its length is
substantial.
46. As intakes are usually put immediately above weirs or barrages (these
being of course river command controls), it foIlows that weirs and banages
should be sited if possible on bends of correct curvature. Straight reaches of
rivers are not so good, as the current inay tend to swing, thus setting up
corkscrew currents with the wrong direction of rotation. The same principles
apply to location of pump intakes.
47. Miscellaneous canal structures include syphons, flumes and bridges.
No special comment is called for here. Approved types can be seen by
arrangement with the A.D. Planning.
48. It is to be noted that most canal controls are energy dissipating
structures and that they are also subjected to percolation pressures. They
should be designed on the principles explained later in comexion with weirs
and barrages.
SECTION V.-DESIGN PRINCIPLES FOR WEIRS (INCLUDING BARRAGES)
DlSCnARGL
FREQUPNCY i
AMOUNT OF BED SEDIMENT
0 g 0 SEDIMENT LOAD
MOVED.
FIG. I/Y/III
flow, which may cause troublesome scour or erosion. And weirs mu& in
excess of normal river width cause local bed instability.
8. So it is apparent that the level and length of the fixed weir are
arrived at by compromise. Usually an acceptable solution is found with a
crest length approximately equal to the bed width of the river.
THE WEIR STRUCTURE
9. When fixed weir crest level has been decided, the height of the etes
will follow automatically if the desired F.S.L. is known. Thus we arrive at
the basic proportions of the bar which is to be put in the river, and we
now have to consider the structure which will surround and sustain this
bar. It is not the intention to go into details of design, but only to outline
the principles involved.
10. As already seen, the function of the weir (barrages will be included
generally in the following) is to raise water levels upstream. Evidently then
there must be a fall of water through the structure at certain stages of flow.
The fall results in conversion of potential energy to kinetic energy, and this
energy must be destroyed within the solid boundaries of the structure or it
will destroy the river channel downstream of the structure. If the river channel
IS destroyed. the structure is likely to fail also. structurally, or as a result of
undermining by piping.
11. If some upstream bed aggradation takes place as a result of the
construction of the weir, there will be corresponding downstream retrogressioh.
at least until normal sediment movement is once more restored. Thus, for a
while, the downstream stage discharge curve of the river will be lower than
previously, and this will result in release of still more energy which must
be killed within the structure. Allowance may have to be made also for
permanent downstream bed retrogression. resulting from removal of old brush-
wood dams or other obstructions.
12. The weir is also a dam, and is subject to overturning, sliding and
uplift forces. It must be stable against these under all conditions. Most river
dwersion structures. in Malaya at any rate, are low, and are built on per-
meable foundations requirbg substantial length. There is usually no danger
of sliding or overturning, and in design we do not generally have to consider
these. Uplift is important. however, for unless proper provision is made, the
structure, or part of it, may be lifted bodily by the pressure underneath it.
13. Provision must be made also to preveilt failure by progressive wash-
out of the soil beneath the structure. This is known as "piping".
14. The surface flow aspect of design will be considered first, and then
uplift pressures and piping.
SURFACE FLOW AND ENERGY DISSIPATION
1 2 3 4 5 10 25
FIG 8
MINIMUM DISTANCE AT WHICH SLOIIWG WOE W4LL MAV
CUT DCWUSTRCAM WATER SURFACE LEVEL -
4.5 0 2
FIG. 9/~/11l
32. As will be seen later, the point of formation of the jump and the
jump profile are essential also in determining unbalanced uplift pressures.
33. It might be expected that small values of H, (or H,,) would result
in a small tendeacy to scour. In fact this is not so. For a given intensity
of flow, the greater is HL,the greater must be the tailwater depth to
accommodate the jump. Consequently the lower the velocity of the tailwater
off the end of the structure: and vice versa. D.I.D. research has shown that
undesirable scour will not take place at the end of the structure if the Froude
number. F at the end of the structure does not exceed about 0.3. That is
to say v does not exceed about 0.3. Therefore, not only must the down-
43
a t e jump for all conditions
stream floor level be low enough to a ~ ~ ~ r n m o dthe
of flow: it should also be low enough to ensure that the safe value of F io
not exceeded at any stage of flow. If for any reason the floor canaot be
put low enough to give the safe value of F, then spacial bed protection must
be provided ia the form of a loose rubble apron. This problem docs not
often arise in Malaya. In cases where it does, however, reference should
be made to the Chapter on "Canals, Channels and Rivers", by Blench. in
"Civil Engineering Reference Book", Butterworth, or to other standard worka
which treat this subject.
34. Even if the dowhstream floor is low enough, there will be a tendency
to formation of undesirable vortices, where the water passes off the end of
the downstream floor. For this reason, a "Rehbock sill" is used at the end
of D.I.D. structures. This is illustrated in Fig. 10/V/lII. Note the double
height tooth. adjacent to the wall. Note also that the vertical face of the
teeth is upstream, not downstream. The tooth height is not critical and may
be about one tenth of the downstream depth of water at the stage at which
there is maximum energy dissipation. That is to say, when qXH, is a
maximum.
35. Downstream apron floor blocks are used sometimes as aa aid ta
shortening the jump. Their size and position is empirical, but the proportions
shown in Fig. I I /V/III are known to work quite well.
36. The shape and location of side walls at the downstream end of weir
structures has come ib for a good deal of attention in the D.I.D. Research
has shown that straight side walls. sloping down at 23 to 1 or 3 to 1 are
satisfactory and economical. Further. a splay of 1 in 10 on each side is
beneficial, as this stops the play of secondary vortices over erodible bank
materials adjacent to the side walls. The general arrangement is shown in
Fig. 12/V/In. The location of the side wall slope in relation to the hydraulic
jumps profile is shown in Fig. 9/V/III. It will be seen that the surface
slope is allowed to cut the wing wall at a distance 4.5 4 downstream from
the point of formation of the jump. This results in a lazy vortex, which is
not objectionable and may be beneficial to the sides of the walls. Various
conditions of flow will be checked, of course, and the worst will be taka.
37. The form of outlet is non-scouring provided that an "onion" of
adequate size is formed in the downstream channel at its junction with the
structure. This is shown in Fig. 13/V/m. It is emphasised that this onion
is a vital part of the design. In spite of repeated reminders, engineers go
on putting in weirs without onions and then go to endless trouble in attempt-
ing to stop erosion which must and will occur if the onions are omitted.
ln this comexion, see also D.I.D. Technical Circular No. 1. "Outlets from
Structures".
SECTION
WALL ,
P A R T PLAN
F I G . 11/V/111
PART PLAN
however, unless the side wall extension beyond the end of the floor slab is
structurally separate from the more upstream point of the wall. Consequently
it is the practice at present to use sheet piling with a sloping capping beam
to continue the falling side wall line beyond the end of the floor slab. The
side walls are returned at right angles, and are continuous with the drop
wall or beam at the end of the apron, thus forming a U beam which gives
rigidity to the end of the structuie. The arrangement is illustrated in - ~ i ~ .
14/V/III.
39. Before leaving the subject of downstream end design for structures
of this type, it might be as well to point out that there are many "trick"
devices for shortening and cheapening structures containing hydraulic jumps.
Careful study shows, however, that none of these devices is effective for
I \
I v '
jumps occurring at low Froude numbers. .( ! . such as are normal in D.I.D.
I Jgd I
work. This comment goes for all manner of cunningly shaped buckets and
teeth. Their place is in structures containing jumps occurring at high Froude
Numbers, where they can be very effective. For detailed and comprehensive
information on these types. refer to Papers Nos. 1401 to 1406 (October
1957) of the American Society of Civil Engineers.
40. Upstream end design requires consideration also. If the upstream end
of the floor of the structure is at weir crest level, there will be drawdown
of the water surface and increase in normal velocity over the river bed up-
stream of the structure This will result in bed scour and exposure of the
upstream end of the floor. This exposure will cause additional turbulence. and
a considerable scour hole will develop immediately upstream of the structure.
41. Again, unless the side walls at entry are streamlined, turbulence.
which results in bed and bank scour, will be generated. Also the effective
width of the structure will be reduced as a result of end contractions.
42. Therefore. the upstream floor is ramped up to the weir crest, and
the side wails at entry are flared. The proportions shown in Fig. IS/V/III
have been found, by experiment, to be satisfactory. It has been found hydrau-
lically unnecessary to catry the curve of the flare beyond the point shown;
and to do so would only result in additional cost and structural complication.
43. The normal D.I.D. weir is built in an alluvial valley and is constructed
on sediments which have been deposited' by water and which are more or less
permeable. Hence water percolates underneath the structure from the upstream
end to the downstream end. driven by the difference in head of water at the
two ends. As the water passes beneath the structure, it loses pressure. The
pressure at entry to the soil beneath the structure is equal to the upstream
head of water, and the pressure at exit is equal to the downstream head of
water. Between these two points (or areas) the percolation pressure becomes
less at a rate which is not constant, but depends on the shape of the bottom
of the structure and on variations in the permeability of the soil. The present
object is to explain the principles involved, so it will be assumed for the
time being that the permeability of the soil is uniform.
44. The percolation pressure in the soil in contact with the base of the
structure acts upwards on the structure and tends to float it off. This tendency
has to be resisted by the weight of the structure plus the weight of any water
contained inside the structure. Sufficient weight must be built into the structure
to hold it down against the uplift forces. Hence the importance of knowing
the percolation pressure distribution.
\\- RIVER BED
RECOMMENDED PROPORTIONS
FOR INLET FLARES AND
-
UPSTREAM FLOOR.
R.C. PILE
LINE AND
GAPPINQ
I-
SLOPE 3 TO I .
45. Flow of water through permeable soils is according to Darcy's Law
L
where V = velocity
H = head
L = length of path of flow.
K is the "transmission constant"
Thus the flow pattern and the pressure beneath a structure on a permeable
foundation can be represented by a flow net, consisting of streamlines and
equipotential lines.
46. There are a number of ways of preparing flow nets, e.g. sketching.
mathematical, electrical analogy and viscous fluid. There is plenty of standard
literature on this subject, and method of preparation of nets will not be dis-
cussed further here. The D.I.D. has equipment for preparation of nets by the
electrical analogy method, using Teledeltos paper.
47. Sketching and study of flow nets brings out the influence of arrange-
ment and dimensions of the common elements of the' undersides of weirs.
That is to say, floors and pile lines or drop walls. A few cases are examined
in the following paragraphs.
0
48. Fig. 16/V/III shows a hypothetical structure which has length,
n o depth. From the flow net it will be seen that there is a concentratioMof
lines in the immediate vicinity of the ends of the floor, indicating a igh
pressure gradient in these regions. Except near the ends the stream-lines $ld
equipotential lines are fairly widely and evenly spaced, indicating a relati*ely
low pressure gradient and one which is not changing rapidly. The preslure
distribution is as sketched. It will be noted that the percolation pressure
diagram starts at upstream water level and finishes at downstream water level.
49. The pressure gradient of the percolating water emerging at the down-
stream end of the structure is called the "exit gradient". With a high con-
ceiltration of flow-net lines at "exit". as in this case, there must be a high
exit gradient. High exit gradients are very objectionable because they lift the
unsupported surface soil, thus uncovering more soil at a lower level, and this
in turn lifts. Thus a "pipe" develops under the structure by progressive
action, and the structure will eventually collapse when the pipe gets big enough.
"Safe" exit gradients will be considered a little later.
50. The exit gradient at the end of a structure .with no depth, as in the
case now being considered, is very high (in theory it is infinite) and the
chances of such a structure standing for long are negligible. Nobody with
any appreciation of the problem will design a structure like this.
51. Fig. 17!V 111 sketches a structure with depth but no length, consisting
of a single pile line. It will be seen that the concentration of flow net lines
is round the base of the pile line and the net is well spread at entry and
exit. Thus the pressure gradient is high where the soil is well supported, and
the exit gradient is low. As the structure has no length, an uplift diagram
cannot be drawn. A pile line is thus a satisfactory structure so far as exit
gradient and uplift is concerned. But unless well supported it has unsatis-
factory resistance t o overturning. And if water passed over its top, the bed
on the downstream side would be eroded away rapidly. Thus a single pile
line would not make a satisfactory weir structure. As a water stop in a
structure such as a coffer dam, it is of course excellent.
52. Fig. 18/VIIII shows a structure with length and with an upstream
pile line. It will be seen that the pile line has the effect of reducing the
TOP OF OATL OR
WEIR CRfSt X = UPLIFT PRESSURE
A T POINT A.
P E R C O L A T I O N PRESSURE LINE
pOWNSTREkU W.L..
-
U.S.W.L. 3
----- -
FIG. 1 7 / ~ / 1 ~
+,-
J5.W L
- , P E R C O L A T I O M PRESSURE LINE
stvlrtr
PERCOLATION PRESSURE L I N E
\X
Y' , , j--II - ' .1 /
F I 6 . 2 O/v/lJJ
percolation pressures beneath the structure and thus it is beneficial. The structure
can be made lighter and cheaper. There is. however, a concentration of flow
lines round the downstream end of the floor, indicating a high and dangerous
exit gradient.
53. Fig. I9/V/III shows a structure with length and with a downstream
pile line. The exif gradient is now satisfactory, but the uplift has been greatly
increased.
54. Fig. 20/V/III shows a structure with a pile line at each end. The
downstream pile line reduces the exit gradient but increases the uplift. The
upstream pile line reduces the uplift. This is the usual compromise solution.
55. By similar reasoning, it will be seen that a pile placed under the
centre of the structure will not have a very marked effect, unless it is very
deep.
56. A further point to note and which is important, is that vertical
surfaces (terminal ones at any rate) are far more important in changing the
flow pattern and pressure distribution than horizontal surfaces.
57. Summarising then, it can be said that in permeable soils of indefinite
depth, a downstream drop wall is essential to ensure a reasonably low exit
gradient. If it is too long, however, uplift pressures will be greatly increased.
Upstream pile lines reduce uplift pressures, but do not have much effect oh
exit gradients. The downstream pile line should not be deeper then than is
necessary to ensure a satisfactory exit gradient, and the upstream pile line
should be as deep as economically possibIe in order to reduce percolation
pressures. and thus to lighten and cheapen the main part of the structure.
58. While percolation pressure distribution is best studied by means of
flow nets. it will be more convenient in practice, in many cases, to use the
curves given in Fig. 21 /V/III to determine the percolation pressures inside
the pile lines at the ends of the structure. The curves are self explanatory.
Between the two points at which the pressures are thus determined, the pressure
distribution on the underside of the structure can be represented, with sufficient
accuracy. by a straight line. These curves are based on Khosla's "Method
of Ihdependent Variables" and apply to the case where there are pile lines
of equal depth at each end of the structure, Khosla's method embraces more
complicated cases also, and curves for solution of these may be found in
modern standard reference books.
59. A favourable condition arises if the upstream pile line can pierce an
impermeable stratum; say clay. Subsoil flow is then cut off, and theoretically
there is neither uplift pressure nor exit gradieat.
60. If on the other hand the downstream pile line pierces clay and the
upstream does not, full upstream head pressure will develop under the whole
of the underside of the structure, and this may easily float off, unless it is
very heavy indeed, or unless the pressure under the structure is artificially
relieved. This is not a recommended procedure.
61. The necessity for a low exit gradient has been mentioned. Let us
examine this a little more closely. Consider the equilibrium of the bed material
in a length L at the end of a "stream tube" emerging at the tail end of a
structure.-Fig. 22/V/III. Let the cross sectional area of this short length
L bed A. Also, %r simplicity, aBsume that the bed is horizontal so that
the flow emerges vertically. Then the force pushing out the plug of bed
material in the stream tube is dp XLXdA
7
dL
LENGTH OF FLOOR
OF Oc = DEPTH OF PILE
c RIVER BED
STREAM TUBE
where dp is the pressure gradient at exit.
--
dL
The force preventing the plug from blowing out is the weight in water of
the solid material in the plug. For normal bed sands with normal pore space,
the submerged weight of the sand in the plug is about equal to the weight of
an equal volume of water. It follows that for the plug to be in equilibrium.
the head of water on its underside must be about equal to the length of the
plug. That is to say. the pressure gradient. dp, must be about unity.
dL
62. Clearly a factor of safety must be applied, for conditions are not
entirely stable. For example, pressure gradients can be temporarily upset by
local surging in the river or by sudden operation of gates. The following
factors of safetv have been found appropriate.
Shingle ... ... ... 4to5
Coarse sand ... ... ... St06
Fine sand ... ... 6to7
Clayey soil ... . . .. 3to5
Submerged densities do vary considerably, however. according to the material
and the pore space: so in unusual cases, the factor of safety should be
applied. not to an exit gradient of unity. but to the properly determined
"flntation gradient" for the material of which the bed is composed.
63. So far as exit gradients are concerned, the practical design problem
will be to ensure that the exit gradient is kept sufficiently low. The length
of structure will have been determined from surface flow considerations. The
exit gradient will be reduced then to the required value. by provision of a
downstream pile line or drop wall of sufficient depth. This is a matter of
trial and error. Some depth will be assumed, and exit gradient for that
depth will be determined from the flow net. or perhaps more conveniently
from the standard curves shown in Fig. 23/VIITI.
64. As has been shown, the water percolating under the structure is
under pressure and this pressure exerts an upward force on the bottom of
the structure. Thus there is a force trying to lift up the structure. This
upward force is resisted by the weight of the structure and the water inside
the structure, which try to push it down. Obviously the downward forces
must exceed the upward ones or the structure will float away. Usually. how-
ever. the percolation forces under some parts of the structure exceed the weight
of the water in the structure together with the weight of concrete necessary
for purely structural purposes. It is necessary then to add weight to the
structure to produce a favourahle balance. As a weir is not a particularly
rigid form of structure. ~t i s not assured to act as a rigid whole: the additional
weight required is put where it is needed.
65. The tirst step is to draw out. for the various conditions of flow.
the water profiles and the corresponding percolation pressure diagrams. From
previous considerations. we shall already know the longitudinal section of the
floor surface and the depth of the terminal pile lines. so all this can be done.
The unbalanced hydraulic uplift pressure then at any point is the difference in
level between the percolation pressure at that point and the water surface level
In the structure This difference has to be balailced by the weight of concrete
In the floor of the structure. taken at its submerged weight, assisted by the
weight of adjnccnt piers and walls taken at submerged or unsubmerged weight
as appropriate.
66. By wav of example, consider the weir in Fig. 24alV:III. which is
retaining water, without thrnu~h flow. by means of a crest gate. The un-
25
CALCULATED FOR
20
15
\O
0
10 20 30 40 50
V A L U E S O F OC
LENGTH OF FLOOR
?s
DEPTH OF PILE
NO SURFACE FLOW
FIG. 2 4 d / ~ / n l
67. Fig. 24b/V/III illustrates a case where water is flowing over the weir.
Thc water surface profile will have been obtained as previously described. It
will be seen that the uplift pressure diagram is different from the case for no
flow. According to circumstances. either the flow condition. or the no flow
condition, can be more severe, so both should be checked. There is of course
a variety of cases for the flow condition, and enough cases should be checked
to ensure that the worst for every cross section has been allowed for.
68. The thickness of the floor should not slavishly follow the requirements
of uplift. Provided there is adequate stiffness in the floor slab. the mass can
bo dispersed within reason in a structurally satisfactory manner. As noted.
might of walls and piers can also be taken into account: and it is worth
nnting that concrete above water level can and should be taken at its full
weight. It is therefore more economical of material than additional weisht
In the floor
69. Adjustment of floor thickness will of course affect the flow net slightly.
and hence the pressure distribution. It is usual therefore to assume a reasonable
floor thickness. based on experience. when drawing the flow net. Minor changes
in floor thickness will then have no practical effect on the flow net.
70. The factor of safety assumed for uplift is generally small or unity.
€or the following reasons :
( a ) Gravity is not in doubt.
( h ) The tendency of the structure to overturn throws additional weight
where weight is required. i.e. at the downstream end.
(c) There is considerable friction between side walls and backfilling.
and this would come into play if the structure tried to lift.
fd) The soil at the upstream end of the structure tends to become
less permeable as a result of inwash and lodging of fine sediment
carried in the river water. The downstream pressures thus tend
to be lower than estimated.
71. So far we have considered the weir to be on a theoretically perfect
and pcrmetrble foundation. Usually foundations are not perfect. At least they
are likely to be more permeable horizontally than vertically. This can be
dowad for by distortion of the flow net. Reference on this point should be
made to standard literature. Vcry ofien the ground is stratified. and then
good judgement. based on appreciation of the principles involved. is necessary
Fig. 2SIVIIII illustrates a simple example. The uplift pressure at B will be
as high as that at A.
72. In a case like that illustrated in Fig. 25/V/II1. pressure to B could
be cut off by an intermediate pile line near A. and to guard against leakage
through this pile line. a "reversed filter" could be provided at B for pressure
(if any) relief. The use of filters under impermeable structures on permeable
foundations is not really recommended. however They should not be used
except in consultation with the A.D. Planning. If filters must be used. the
following points must be noted
FIG. 25/~/lll
BBLE
I LARGE
WEAD
FIG. 26/~/111
(a) The filter must be capable of passlng, wlthout appreciable loss of
head. the water reaching it Otherwise there will be a pressure
build up
( k ) Filters placed under an area over whrch water surface level is
not constant. should have only one t d e t Otherw~se there may
develop a circulation through the filter. and the filter my be-
come choked w~th fine sediment
fc, Filter materials should be graded according t o D 1.D Technical
Circular No. 2. which is based on standard workb on the subject
73 Wem may also be constructed on lmpermeable sods. such as clays
I'he determ~nat~onof uplift 1s then vet! pmblemat~c in fact estimates are
yulte arbitrary It 15 suggested that 11 is safe to assume that uplift pressures
will not exceed 5 0 per cent of the uplift pressures which would be expected
< I n permeable soils. prcwded end cwt offs are good and prov~ded there is an
adequate filter for lnterceptlon of water percolating along the junct~on between
the concrete floor and the ground below ~t Somet~mes the subso11 draws
slightly away from the slab. leaving a path along wh~ch water can move
relatrvelq freely Thls IS known as "roofing" Theoretically. cuch a filter
cannot he designed, as the clay part~cles wh~ch 11 would be expected to retam
are too fine The filter should really be regarded as a temporary safeguard
and as a "tell-tale" of impending trouble If. one day. the filter were found
t t ) be d~scharging. a welr grouting operation would be rnd~cated
Bifurcation
Overshot
...
...
. Undershot ...
Controlled Drainage Schemes . . .
Crest . . . . . . . . . . . .
Crops other than rice. Irrigation of ...
Cross Bunds .........
.. Section
Darcy's Law
. . . . . . .
. . . . . . . .
Demand. maximum ......
Design of weim . . . . . .
.. Canals . . . . . . . . .
Dimensions of Banks .....
.
Discharge . . . . . . . . . . . .
Hydrograph . . . . . .
Distributaries .........
n ,..
Distribution Systems Narrow Valley
Flat Plains
Gentle Slopes
Drainage Systems ...
Dry weather flow ...
Duty ......
Energy dissipation
Evaporation ...
n ...
Exit Gradients ...
Falls, notched ...
Field Channels ...
n n ...
Filters rrtrerse ...
noor blocks ...
.
..
levels
thicw
...
...
Flow naets . . . . . .
Formative Stgp ...
Froude nember ...
Gradicnt .....
Head Regulator ...
Section Paragraphs
Headworks 1
111
18 21
1-79
.
Hydraulic Jump 111 16-39
Intakes I1 43-46
lrrigatlon Continuous ... I 27
.. Crops other than rice I 50.58
.. Definition ot I 1
.. Systems I 17-25
.. Flat Pla~ns . 1 39-41
.. Gentle slopes I 4247
.. Narrow Valley I 31-38
. Pahang Paya I 49
.. Rotational I 27-29
I1 25
Jump Hydraulic 111 16-39
..
Leakage
Length of 111
II
27 29
26
.
Length of Jump 111 27 29 .
Maximum Demand I 10-14
Method of independent variables 111 58
Module I1 42
Notched falls 11 34
Nurser~es I 3
Offtakes II 6
"Onions" ... 111 37
Overshot Controls Il 34. 40
Pahang Paya System I 49
Percolation I 7-9
I1 26
.. Gradients 11 29
.. Pressures IT1 43-73
.. diagrams 111 65 66 .
Piping 111 13
Pumping Schemes
Regime
1 13 24 .
11 11-22
Rehbock sills 111 34
Reservoir Schemes
Retrogression
I I4 25 .
Ill I1. 2 4
Reverse filters
R ~ c ecultivation
111
I
72 73 .
2.4 . 2 6
Roofing 111 73
Rubble weirs 111 79
Sediment I1 12-21
111 3
.. Extraction and Exclusion 111 74-78
Seepage I1 29
Side factor I1 16
.. walls downstream IT1 36-39
.... upstream 111 40-42
Slope. channel 11 11.16 . 3 3
.
Stage bank full 111 6 26.
StageDischarge 111 24-26
Surface flow 111 15-42
Transpiration . 1 6. 7 9 .
11 26
Undershot Controls . I1 . .
36 40 42
Uplift
Velocity
111 .
12 43-73
. II 12.16 . 2 0
Water requirement ... C 8
Thavaraj , S.H. -
"The Necessity of Terminal Facilities for
Water Management at the Farm Level" -
Bulletin No. 139.
Proceedings of the National Seminar on Water Management
and Control at Farm Level.