Escolar Documentos
Profissional Documentos
Cultura Documentos
Distribution Systems
C.H. Fujisawa and C.A. Castro, Senior Member, IEEE
o
Fig. 1.
SIe == Vs4
(1)
{ -rPe - xQe
= v2
[2 (xP
e -
rQe)2]
(2)
For other operating points (A =I 1), Eqs. (1) and (2) are
used by replacing Pe and Qe respectively by APe and AQe.
It was also shown in [6] that it is possible to obtain a
two-bus equivalent system from any radial DS, by keeping
the substation bus s and some particular load bus k. The
impedance of the equivalent line that connects bus s to k is
given by
(3)
where Z sk is the equivalent impedance between the substation
bus s and the bus k, f is the set of branches of the path that
connects bus s to bus k, Jk is the current injected at bus k, and
Zi and Ji are the impedance and the current through branch
i.
In method I, A* is iteratively obtained for any radial DS.
The procedure can be summarized as follows.
(a) Compute the voltage stability index for all load buses
using (1).
(b) Obtain the two-bus equivalent system containing the
substation and the weakest bus (which has the smallest
voltage stability index), using (3).
(c) Compute the maximum load factor for the equivalent
system using (2).
(d) Perform steps (a)-(c) until the maximum load factor
converges to A*.
For the sake of illustrating the performance of method I, Fig.
2 shows the evolution of the iterative process for the 33-bus
distribution system [5].
380,----------.------.---...---------r------.------.-----r-------.----.
370
~360
"'"
B
u 350
~
""0
...J 340
I
I
330
II
I
- - -
Maximum loadability
Method I
320 L---L_--I.---=:::i::::===::L:::=:::::==:t:===::::::::t:===:t====:::L==::J
1
5
6
8
10
1
Fig. 2.
Iteration
Method I - 33-bus distribution system.
D.() ] n+ == [ D.() ] n
.
D.V
+M
[ D.V
-1 n
(J)
D.P ] n+
D.Q
' (4)
where D.() and D. V are the voltage phase angle and magnitude
corrections, D.P and D.Q are the real and reactive power mismatches, and J is the Jacobian matrix. The optimal multiplier
J1 is added to the conventional load flow formulation, being
computed to minimize a quadratic function based on the power
mismatches. The derivation of M is shown in [9], where it is
clear that second order information is used to improve the
performance of the load flow method.
For well-conditioned systems, M is close to one, and does
not affect the iterative process significantly. For ill-conditioned
systems, M assumes different values to minimize the illconditioning effects, providing the correct solution for the
problem. For infeasible systems (those for which there are
no solutions for the load flow equations) M tends to zero in
a few iterations, indicating that the power mismatches cannot
be decreased further and the best possible solution has been
reached. Also, Overbye [11] showed that, for infeasible cases,
LFSSO leads to a point on the feasibility boundary rather than
to simply diverge. These features are of particular interest for
voltage stability.
1------1---
Substation
CD
Load
P2
+ jQ2
A.-'
Fig. 3. Example of two-bus system and its respective parameter (load) space.
C. Proposed method
The proposed method comprises three basic steps: load
increase, load shedding and binary search.
In the first step, method I [6] is used to obtain the values
of the load factor ,\ corresponding to the load increase. Since
LFSSO is very robust and deals properly with infeasible cases,
the idea is to use its powerful characteristics to increase the
load very quickly, intentionally seeking a load factor larger
than the real maximum loading (in the infeasible region), but
not too far from it. In order to achieve this goal, method I is
slightly modified, by multiplying the computed load factor in
(2) by an arbitrarily chosen scalar. In this paper, this scalar was
set to 1.1 (in other words, the load increase will be 10% larger
than the one determined by method I). This step is carried out
iteratively until an infeasible point is found, for which LFSSO
does not converge (M tends to zero), but provides an operating
point on the feasibility boundary.
(f) From the most recent feasible point and the last infeasible point, perform binary search until a point on the
feasibility boundary is obtained. A threshold is defined
to stop the binary search.
not null do
(2.1) Divide the real and reactive powers by their respective base case values, obtaining an estimate for the
load factor.
(2.2) Add the computed values to () and increment n,
except
(i) if the computed real (and/or reactive) power is
larger than its respective specified power, or
(ii) if the real (and/or reactive) power is null or
generated.
(3) Compute the average of the n estimated valid load
factors, obtaining .xest == () In.
III.
Simulation tests have been carried out for several distribution systems. In this paper the results for a 33-bus system and
a 202-bus system will be shown only, due to space constraints.
Also, the results for other systems lead to the same conclusions
as far as the performance of the proposed method is concerned.
The data of the 33-bus system can be found in [5]. The 202bus system is a realistic primary distribution system in the
State of Sao Paulo, Brazil.
Simulations with the 33-bus system considered two scenarios, namely (a) considering the original data, without
distributed generation, and (b) with the insertion of an independent generator of 2MW, with regulated voltage at 1.0pu,
and reactive power limits of -O.8MVAr and 1.0MVAr at bus
12. The evolution of the load factors obtained by applying
method I [6] can be observed in Fig. 2. Figs. 4 and 5 illustrate
the results provided by the proposed method, respectively
without and with distributed generation. Tables I and II show
the same results in detail.
From Figs. 4 and 5, note that a few iterations are necessary
(six and eight) for reaching a load factor very close to the
expected one with errors smaller than 1%. The values in
italics in Tables I and II indicate load factors larger than
the expected one. The presence of distributed generation with
voltage regulation leads method I to estimate large, infeasible
load factors. The proposed method provides an appropriate
way to manage this situation, and an accurate solution is found.
The 202-bus system was also tested considering two scenarios, namely (a) without distributed generation, and (b) with the
insertion of an independent generator of 14MW, with regulated
voltage at 1.0pu, and reactive power limits of -5.5MVAr and
6.8MVAr at bus 202. The evolution of the load factors for the
two scenarios provided by the proposed method can be seen
in the Fig. 6. Table III shows the same results in more detail.
395,--------.------,-------,.---------.--------,
...
1\
390
\
\
385
~380
....
1:) 375
~
'.
"'0
"-
~ 370
"-
I
I
365
"-
"-
"-
360
355
Fig. 4.
Maximum loadabI1lty
Proposed Method
1=-=-=
Iteration
520
\
\
500 \
\
~480
.s
~ 460
\
\
"'0
~ 440
i\
\
\\
~---.-\-----,...------:\--~-..::.--,--__=__----<'1-~______=4
420
400
\/ ./
\/ 1/
\/
Maximum loadablhty
- ..- - Proposed Method
380 L-._L_---L-===::L:::::::::::=:L::===:L====~==::J
1
Fig. 5.
Iteration
M
'
I oa d'IDe = 37077%0
aXlmum
Iteration
1
2
3
4
5
6
7
8
9
10
Method I
Error
A
322.94%
-12.95%
-06.730/0
345.80%
-04.85%
352.790/0
-03.96%
356.10%
357.82,/0
-03.490/0
-03.200/0
358.900/0
-02.91 %
359.990/0
360.450/0
-02.780/0
-02.660/0
360.91%
361.36%
-02.540/0
Proposed Method
Error
A
-4.19%
355.230/0
393.08%
6.020/0
374.15%
0.910/0
364.690/0
-1.640/0
369.420/0
-0.360/0
371.79%
0.280/0
TABLE II
COMPARISON OF METHODS FOR THE 33-BUS SYSTEM WITH DISTRIBUTED
GENERATION.
Iteration
1
2
3
4
5
6
7
8
V.
690~------r-----r----.----,------.,
680
670
~660
B
650
u
r.a 640
"'0
ro
o
630
620
610
-e-
Maximum loadability
Proposed Method
Maximum loadability (DG)
Proposed Method (DG)
600'---------'----...L..-----'------'----~
Iteration
Fig. 6.
Proposed method: 202-bus system without and with distributed
generation (DG).
TABLE III
EVOLUTION OF THE PROPOSED METHOD FOR THE 202-BUS SYSTEM.
Without distributed
generation
With distributed
generation
A*=632.72%
A*=634.730/0
Iteration
.x
Error
1
623.52%
-1.450/0
686.10%
8.440/0
2
654.81%
3.49%
3
4
639.17%
1.02%
631.340/0
-0.22%
5
6
635.25%
0.400/0
A* IS the maXImum loadmg.
efficient procedure.
.x
625.24%
688.03%
656.63%
640.94%
633.090/0
637.01%
Error
-1.50%
8.400/0
3.450/0
0.98%
-0.26%
0.36%
IV. CONCLUSION
REFERENCES
[1] W.H. Kersting, Distribution System Modeling and Analysis, CRC Press,
2nd ed., 2007.
[2] 1. Northcote-Green and R. Wilson, Control and Automation of Electrical
Power Distribution Systems, Taylor & Francis, 2007.
[3] G. Brownell and H. Clark, Analysis and Solutions for Bulk System
Voltage Instability, IEEE Computer Applications in Power, 1989.
[4] M. Chakravorty and D. Das, Voltage stability analysis of radial distribution networks, Electrical Power & Energy Systems, vol.23, 2001.
[5] D. Das, Maximum Loading and Cost of Energy Loss of Radial Distribution Feeders, Electrical Power & Energy Systems, vol.26, 2004.
[6] A. Augugliaro, L. Dusonchet, S. Favuzza, M.G. Ippolito and E.R. Sanseverino, A Simple Method to Assess Loadability of Radial Distribution
Networks, IEEE Powertech, S1. Petersburg, Russia, 2005.
[7] T. Ackermann, G. Andersson and L. Soder, Distributed generation: a
definition, Electric Power Systems Research, vol.57, 2001.
[8] S. Iwamoto and Y. Tamura, A Load Flow Calculation Method for 111Conditioned Power Systems, IEEE Trans. on Power Apparatus and Syst.,
vol. PAS-I00, 1981.
[9] L.M.C. Braz, C.A. Castro and C.A.F. Murari, A critical evaluation of
step size optimization based load flow methods, IEEE Trans. Power Syst.,
vol. 15, 2000.
[10] J.E. Tate and TJ. Overbye, A comparison of the optimal multiplier in
polar and rectangular coordinates, IEEE Trans. Power Syst., vol.20, 2005.
[11] T.J. Overbye, A power flow measure for unsolvable cases, IEEE Trans.
Power Syst., vol.9, 1994.