Rev. : 00
Date: 26.02.16
(Foundation)
1180 MW COMBINED CYCLE POWER PLANT, Bhikhi
Method Statement
1180 MW CCPP, Bhikhi
Central Control Room & Switchgear Building
Rev
R0
Signed
By
Date
Description
26.02.16
Foundation
of
Central
Control
Room & Switchgear
Building
Prepared by:
Engineer
Maj (Retd) Shahid Anwar
Checked by:
Approved by:
Status
For
Approval
Remarks
METHOD STATEMENT
Central Control Room & Switchgear Building
(Foundation)
1180 MW COMBINED CYCLE POWER PLANT, Bhikhi
Table of Contents
Rev. : 00
Date: 26.02.16
METHOD STATEMENT
Central Control Room & Switchgear Building
Rev. : 00
Date: 26.02.16
(Foundation)
1180 MW COMBINED CYCLE POWER PLANT, Bhikhi
1.
2.
Attachments:
1. Drawings of Central Control Room & Switchgear Building Foundation
3.
4.
Material:
Sr. Description
Wooden ply
1
Scaffolding Pipes
2
Cement
3
Steel
4
Concrete Admixture.
5
Standard
Equipment / Tools:
Sr #
Description
No. of Items
Remarks
02
1 Stand by
01
1 Stand by
Transit Mixer
09
2 stand by
Concrete Vibrator
06
02 Stand by
Dump Trucks
08
Flood Lights
08
METHOD STATEMENT
Central Control Room & Switchgear Building
Rev. : 00
Date: 26.02.16
(Foundation)
1180 MW COMBINED CYCLE POWER PLANT, Bhikhi
5. Pre-Start Checks
The pre-start checks must cover the following areas:
Ground conditions.
Ensure the construction area has been checked for overhead and underground
services prior to the commencement of work.
6.
Sequence of Work
i. Manual dressing and leveling / trimming will be done at the bottom of the excavation.
ii. Blinding concrete (Thickness = 100 mm) will be placed in one pour prior to commencing
foundation work.
iii. Steel rebar of pile cap and beams connecting the pile caps will be fixed with appropriate
overlapping as per approved drawing. Surveyor will inspect the required elevation of the
steel assembly. Inspection request for steel rebar shall be raised.
iv. Wooden formwork shall be erected for pile caps. Check request for formwork shall be
raised.
v. Site Engineer will ensure that the all the embedded parts (as per drawings) are in place
before commencing the concreting.
vi. Rectification will be carried out as per requirement.
vii. Concrete of desired specifications shall be produced at two Batching plants and
transported to the site in constantly rotating drums of Transit mixers, as per quality &
testing procedures.
viii. Height of fall of concrete shall in no way exceed 1500 mm. Concrete shall be placed in
layers, each having un-compacted thickness of approximately 300mm.
ix. Concreting of whole pile cap will be carried out in one pour.
METHOD STATEMENT
Central Control Room & Switchgear Building
Rev. : 00
Date: 26.02.16
(Foundation)
1180 MW COMBINED CYCLE POWER PLANT, Bhikhi
x. Concrete vibrators shall be used and the vibrating process at one point should not
prolong beyond 30~60 seconds in order to avoid bleeding of concrete. To ensure concrete
of homogeneous consistency, proper attention will be paid. Concrete slumps for wall
section shall be 150-200 mm. Collapse slumps shall be avoided.
xi. Steel fixing of piers will commence right after the formwork of pile cap is removed after 24
hours.
xii. Formwork fixing for piers will take place.
xiii. Concrete Pouring for piers will take place. Site engineer will ensure that the steel
assembly is properly placed at required level.
xiv. Top concrete surface of the piers will be rendered rough.
xv. The backfilling will take place.
METHOD STATEMENT
Central Control Room & Switchgear Building
Rev. : 00
Date: 26.02.16
(Foundation)
1180 MW COMBINED CYCLE POWER PLANT, Bhikhi
7.
8.
Contingency Plan
i.
Climate:
MET official web site shall be checked for the weather forecast. No concreting shall be
carried out during inclement weather (i.e. high temperatures, heavy rains etc).
ii.
Production:
a. Materials:
Sufficient stock of all materials shall be ensured.
b. Batching Plant:
Two Batching plants are ready, out of which one shall be operational whereas
the other shall remain stand by to meet any emergency requirement.
c. Transit Mixers:
08 Transit mixers are required to meet the pouring requirement. At least 02
transit mixers shall remain standby.
METHOD STATEMENT
Central Control Room & Switchgear Building
Rev. : 00
Date: 26.02.16
(Foundation)
1180 MW COMBINED CYCLE POWER PLANT, Bhikhi
iii. In Case Of Any Equipment Failure
Two mobile pumps shall be operational simultaneously. One mobile crane shall also be present at
the pouring point as contigency arrangement.
04 vibrators shall be required to compact the concrete at one time, 01additional vibrator shall be
stand by.
9.
METHOD STATEMENT
Rev. : 00
Date: 26.02.16
(Foundation)
1180 MW COMBINED CYCLE POWER PLANT, Bhikhi
The adjustment of the geometry of the concrete elements of the designed size.
Checking the consistency of fresh concrete on site.
12.
Site Engineer
QC Engineer
Assistant QCs
20 Steel Fixer
25 Carpenter
20 Scaffolder
20 Mason
20 Labor
02 Surveyor
Personal protective equipment: All operatives will wear the following: safety wellington
boots whilst working , safety helmet, high visibility vest and gloves.
Site rules: All operatives will be informed (via a site induction / toolbox talk) of and
expected to comply with the contractors site rules.
Specific site hazards: Any specific site hazards will be identified and dealt with prior to any
excavation work.
Access to the work area: The provision of a safe means of access to the work area is the
responsibility of the contractor / client.
Falls into excavation: The groundworks sub-contractor must provide and maintain fencing
to prevent operatives from falling into the excavation where required.
Welfare facilities: The contractor / client must provide access to the welfare facilities.
Risk assessment
Measures
Transportation of
Equipment
Area In charge
Mr. Malik Zafar(DPM)
Mr. Rashid (Electrical
Forman)
Mr. Shahid
HSE Officer
Mr. Malik Zafar(DPM)
METHOD STATEMENT
Rev. : 00
Date: 26.02.16
(Foundation)
1180 MW COMBINED CYCLE POWER PLANT, Bhikhi
Removal of Formwork
Cleaning of Construction
Area
Activity
Hazard
Cut, Bruises,
Electrocution, Slip,
Trip, Fall
Excavating
Employees working
in the ditch; Potential
for Cave-in, Potential
for atmospheric
hazard
Striking personnel
with in radius of
boom Hitting buried
utilities
Crushing, flying,
debris & noise
METHOD STATEMENT
Central Control Room & Switchgear Building
Rev. : 00
Date: 26.02.16
(Foundation)
1180 MW COMBINED CYCLE POWER PLANT, Bhikhi
Bad weather
Grading
Struck by,
Caught in between,
Noise
Deep Excavation
Wall collapse,
engulfment
Compacting
Elevated Crane
Operation
METHOD STATEMENT
Central Control Room & Switchgear Building
Rev. : 00
Date: 26.02.16
(Foundation)
1180 MW COMBINED CYCLE POWER PLANT, Bhikhi
10
11
12
Area Preparation
General Material
Lifting/Handling
Employee Protection
Slips, trips, falls,
uneven surfaces
Unauthorized access
by HRL populous
Ergonomic Injury
Impact Injury
Back injury-muscle
pulls
Sprains & strains
Lacerations
Hitting People Or
Obstacles On Site
With Truck
Unwanted loss of or
shifting load
Backing vehicle
striking worker
Slips, Nails In The
Foot, Tripping
13
Delivery Of Material
On Site
14
Unloading Trucks
15
Concrete Saw
Cutting and Drilling
METHOD STATEMENT
Central Control Room & Switchgear Building
Rev. : 00
Date: 26.02.16
(Foundation)
1180 MW COMBINED CYCLE POWER PLANT, Bhikhi
16
Site Maintenance
Personal Injury
Tripping & falling
Property Damage