Escolar Documentos
Profissional Documentos
Cultura Documentos
Doc. No
Rev. No.
PROJECT NAME
DOCUMENT NO.
: KP-00+++-CY712-B7209
TITLE
OWNER
01.11.2015
Rev.
No.
DATE
For Approval
DESCRIPTION
A
Sayfa 1 / 6
Page
Method of Statement
for
CT
KP-00+++-CY712-B7204
TOTAL 5 PAGES
(Including Cover)
Purpose
For Information
For Review
For Approval
For Construction
As-Built
U.K.
C.A.
M.E.K.
M..
PREPARED
CHECKED
REVIEWED
APPROVED
Owner
POSCO ENGINEERING
& CONSTRUCTION CO., LTD.
Main Subcontractor
Doc. No
Rev. No.
Page
SUMMARY
1.
Test Objectives
1.1.
General Requirements
1.2.
Specific Requirements
1.3.
2.
3.
4.
PRELIMINARY CHECKS
4.1.
5.
KP-00+++-CY712-B7204
A
Sayfa 2 / 6
Doc. No
Rev. No.
Page
KP-00+++-CY712-B7204
A
Sayfa 3 / 6
1. Test Objectives
1.1.
General Requirements
1.2.
Specific Requirements
The following discussion outlines the specific requirements and test intervals for
testing Westerns ground mats:
Field Offices should establish benchmark data for all substation ground mats.
Ground mats from new electrical facilities will be tested to verify their intended design and
adequacy.
Whenever the ground mat is modified, the ground mat should be tested.
Ground mats should be tested whenever there is a concern about the continued performance of
the grounding system
Doc. No
Rev. No.
1.1.
KP-00+++-CY712-B7204
Page
A
Sayfa 4 / 6
The grounding system is an essential element for the electrical system security and it is required
to:
Allow for protective devices activation when there is an insulation fault. Equalize the potential of
conductive parts that can be accessed simultaneously, with the potential in the surrounding soil in
order to prevent people from being exposed to hazardous voltages. Allow the lightning strike
energy to be safely dissipated. To Reduce electromagnetic interferences.
Doc. No
Rev. No.
Page
KP-00+++-CY712-B7204
A
Sayfa 5 / 6
1. PRELIMINARY CHECKS
Before continuing, personnel should make the following preliminary checks to assure a proper
test setup (a flow chart of the Biddle DET-2 tester operation is illustrated in figure 2):
(1) With P1 disconnected and the CURRENT RANGE switch OFF, connect both P2 and C2 probe
leads to their respective terminals on the tester.
(2) Using linemans gloves, clamp the P1 and C1 tester leads to the ground mat riser cable.
(3) Place the TEST CURRENT dial to NORMAL and FILTER dial to OUT.
(4) Turn the RANGE dial to the 2-ohm position.
(5) If the INPUT NOISE light and the SPIKE RESISTANCE light are off, and the digital numbers
are steady (not flickering), then the test setup is good. Turn the RANGE switch to OFF
(6) If the INPUT NOISE light is lit, increase the TEST CURRENT.
(7) If the INPUT NOISE light stays lit at all current levels, the test probe (spike) arrangement
must be corrected.
Note: To correct the test probes, one or more of the following steps must be taken:
(a) Moisten the ground around the remote test probes.
(b) Reposition the probes slightly.
(c) Drive one or two additional probes and jumper from probe to probe.
(8) If the SPIKE RESISTANCE light is lit, the test current must be reduced.
Doc. No
Rev. No.
KP-00+++-CY712-B7204
Page
A
Sayfa 6 / 6
(9) If the digital readout flickers, the FILTER switch should be turned to the IN position.
(10) When the tester indicates the setup is good, turn the RANGE switch to OFF
1.1.
Measure the ac and dc background voltages as follows to assess any existing stray voltages and
currents:
(1) Leave the P1 and C1 leads connected to the ground mat, but disconnect them from the tester
(see figure 3).
(2) CONNECT THE AC-DC VOLTMETER BETWEEN THE C2 PROBE LEAD AND THE C1
LEAD. SET IT FOR THE 0- TO 10-VOLT AC SCALE.