Escolar Documentos
Profissional Documentos
Cultura Documentos
Petroleum Engineering
Approach
This presentation:
y
Approach
Drilling problems
Pressure Testing
Summary
Drilling Problems
Drilling Problems
y
Mud loss:
2.5 days
Tight hole:
0.3 days
Squeeze cmt:
2.5 days
Stuck csg.:
3.3 days
Fishing:
0.3 days
Lost time:
Cost:
Drilling Problems
If problems get worse:
Stuck + sidetrack
New well
9 days
+2 mill.$
Advantage
Reduce fill
Debatable
Reduce washouts
Expensive mud
Poor pore pressure estimation
X
X
Disadvantage
EH
Pressure Testing
Summary
y
This presentation:
Introduction
Experimental work
x Fracturing lab
x New fracture model
x Barrier stress model
Introduction
y
Circulation losses:
Geomechanics (stresses, lithology,.)
Mud barrier (filtrate loss, bridging,)
Experimental work
Fracturing cell
Pump 1
Test cell
Confining
Pressure
Pump 2
Hollow
Concrete
Core
Well Pressure
PC
Control
System
Pump 3
M ud circulation
Mud cell
Valve 2
Mudcake strength
Mudcake
Pump 1
Experimental work
LabView
Valve 3
Pump 2
Valve 1
M udcake
Example,
3 drilling muds:
40
Kirsch equation
20
0
A
Experimental work
Pw
B
Drilling fluids
2V Po
2V y
t
ln1
3 a
Experimental work
Mechanical strength of mud cake important
Feldspar
60
60
New OMB
Quartz
Pressure, [Mpa]
45
30
CaCO3
45
30
15
0
0
15
1
Time, min
Moh's scale
Additive:
Consists of:
CaCO3 coarse
Test
No.1
(ppb)
15
Test
No. 2
Test
No. 3
Test
No. 4
Test
No. 5
Test
No. 6
CaCO3 fine
15
Fine polymer
20
20
20
15
25
15
Medium polymer
20
20
20
20
25
20
Graphite
40
40
40
25
Mica fine
20
20
15
20
20
20
Mica medium
15
20
20
20
Cellulose
30
30
30
30
Cellulose
Feldspar
30
30
40
40
Good
Very
good
Very
good
Best
Result:
30
30
15
30
Ref.
Bad
formation damage
10
Field case
1,05
1,1
1,15
1,2
1,25
1,3
350
400
Depth (m)
450
500
This well
Reference wells
Fracture curve
550
600
650
700
Drilling mud
Our proposal
(6 ppb)
CaCO3
coarse
3
Graphite
Cellulose
Mica
fine
3
6. Summary
Carbon
fibre
-
Additive:
Consists of:
Operators
recipie(ppb)
15
CaCO3 coarse
CaCO3 fine
15
Our
proposal(ppb)
Fine polymer
20
30
Med. polymer
20
20
Graphite
40
20
Mica fine
Mica medium
Cellulose
Carbon fibre
20
20
30
45
Some
Methodology
2.3 Hole Cleaning
Mechanisms
Applications
Variables
Mud flow rate
ROP
Mud rheology/flow regime
Mud weight (buoyancy)
Hole size and angle
Uncontrollable variables
eccentricity
cuttings size
density
Transport index
TI = RF (rheology factor) xMW (mud weight)x AF (angle factor)
Example
y
Solution
y
Questions:
Maximum ROP if maximum flow is 480 gpm? (Correct book)
If ROP = 20 m/hr, what is minimum flow?
If hole is washed out 10 in, what flow rate is required?
Solution, cont.
y
TI = 0.91x1.0x1.45 = 1.32
Solution, cont.
y
Hydraulic System
Hydraulic Optimization
Chapter 2.4
P1 = pump pressure
P2 = nozzle pressure
P3 = system loss (parasitic)
P1 = P2 + P3
Hydraulic System
Pressure drop
y
Laminar flow
P v PQ
Turbulent flow
P v U fQ 2
P CQ m
Hydraulic System
Hydraulic System
P3 = system loss
P3 = CQm
lnP3 = lnC + mlnQ
UQ 2
2 gA2 0.952
System losses
P3
300bar P2
Hydraulic Optimization
Hydraulic Optimization
Nozzle Horsepower
HP
P2Q
( P1 P3 )
( P1 CQ m
Maximum
Classical criteria
Limitations
Physically correct?
dHP
o P3
dQ
P1
m 1
Hydraulic Optimization
Application
1.
2.
3.
4.
Performance indices
Performance
index
Equation
Criterion
Fraction parasitic
pressure loss
Max. HP
qP2
2
q P2
3
4
5
q 3 2 P2
q 2 P2
q 5 2 P2
Max. Jet
impact
New A
New B
New C
Flow rate
1
m 1
P1
C (m 1)
2
m2
2 P1
C (m 2)
3
m3
3P1
C (m 3)
4
m4
4 P1
C (m 4)
5
m5
5P1
C (m 5)
Proposed criteria
Example
y
Vertical holes
Deviated wells
drilled with motor
Deviated wells
without motor
Stronger
requirements
Max. HHP or
max. Jet impact
New A
2500-4000 m
Max. HHP
or max. Jet impact
New A
New B
Deep(5000m)
Max. HHP
or max. Jet impact
New B
New C
Other data: Drill pipe: 675 m of 5 inch, rest 6-5/8 inch; Drill collars: 120 m 8-1/8 inch OD,
2.81 inch ID; Mud density: 1.65 s.g., Yield point: 32 lbf/100 sq.ft.; Plastic viscosity: 42 cP.
Determination
of flow ranges
and optimisation
criteria
Example
Hydraulic parameters for the field case
Criterion
54
2800-2220
52
2850-2280
New A
63
3070-2450
New B
69
3250-2580
New C
73
3370-2800
Nozzles (inch)
1200
2200
3200
Example
Geomechanic Evaluation
Nozzles
q (l/min)
ROP (m/hr)
Remarks
5 x 16, 1 x 12
2960
1.5
5 x 19, 1 x 12
2660
9.8
5 x 16, 1 x 12
2600
13.6
5 x 19, 1 x 12
2300
18.2
5 x 18, 1 x 12
2400
14.9
6 x 12
2600
18.3
5 x 14, 1 x 12
2400
15.4
5 x 15, 1 x 12
2450
24
5 x 14, 1 x 12
2400
4.8
10
5 x 14, 1 x 12
2530
23.8
11
5 x 19, 1 x 12
20
12
5 x 19, 1 x 12
30
13
5 x 18, 1 x 12
10
14
5 x 18, 1 x 12
22
15
5 x 19, 1 x 12
16
5 x 18, 1 x 12
27
17
5 x 19, 1 x 12
16
18
5 x 19, 1 x 12
19
Data Normalization
Data Normalization
Example, continued:
New gradient from RKB
P(bar)= 0.098d(s.g)D(m)
= 0.0981.03 1000
= 100.9 bar
d MSL 1.03s.g.
d RKB
100.9bar
1.0s.g.
0.098 1025m
Data Normalization
Data Normalization
d MSL
d RKB
d RKB
d MSL
d RKB1
D
D hf
From RKB
From floater
d RKB 2
From platform
D hf
D
D
D Gh
d RKB 2
d RKB1
D Gh
D
V o (sg )
Data Normalization
y
Data Normalization
Normalize to seafloor
1. Subtract water pressure
Well
Csg (in)
34/7-2
34/7-14
20
848
13 3/8
245
1.58
1.06
1.83
1549
1.69
1.42
2.00
9 5/8
2031
1.88
1.63
2.00
20
848
1.62
1.04
1.72
13 3/8
1859
1.83
1.42
1.93
20
491
1.49
1.00
1.49
13 3/8
1559
1.75
1.09
1.70
9 5/8
1988
1.80
1.53
1.92
286
148
25
25
25
Interpretation
Geomechanic Evaluation
Chapter 3.2 - Interpretation
Basic data
Leak-Off-Pressure (LOT)
Pore Pressure
Overburden Stress
Lithology
x Clays
x Sands, Chalks,
Interpretation
Interpretation
Simple modelling
Example
Well
Dataset Depth(m)
A
Horizontal stresses
Effective horizontal stresses
Depth normalize
Effective depth normalized data
(s.g.)
o(s.g.)
899
1.46
1.04
1.63
1821
1.74
1.28
1.81
901
1.55
1.04
1.60
1153
1.56
1.04
1.73
1907
1.81
1.34
1.82
2753
1.95
1.52
1.96
Interpretation
Interpretation
(s.g.)
Example
LOT Gradient
Interpretation
Interpretation
Horizontal stresses,
depth normalized
Va
Va
Vo
LOT
KV o
Va
LOT Po
2V o
y
y
Effective horizontal
stresses, depth
normalized
Va '
Vo '
LOT Po
2 V o Po
Horizontal stresses
2V a Po
1
LOT Po
2
Effective horizontal
stresses
V ' V Po
Va '
1
LOT Po
2
Interpretation
y
Best fit
1
Va '
LOT Po 0.23
2
LOTPrognosis 0.46 Po
Test of model
Geomechanical Evaluation
Chapter 3.2.4 - Advanced Modelling
Advanced Modelling
Advanced Modelling
Borehole inclination
Normalize all LOTs to
vertical for comparison
Borehole inclination
Pwf (0q)
Compaction
Inversion technique
Pwf (0q)
1
Po Po* sin 2 J
3
1
Pwf (J ) V o Po sin 2 J
2
1
1 sin 2 J
2
Pwf (J )
Advanced Modelling
Advanced Modelling
Compaction model
'V a
'Pwf
1 2Q
1 Q
1 3Q
'Po
1 Q
'Po
Applications
Normalization
Structural geology
Lost circulation
Compaction model
Example
Depth(m)
LOT (s.g.)
P0 (s.g.)
3885
2.10
1.79
3821
2.13
1.84
3818
1.98
1.44
3914
2.06
1.58
Advanced Modelling
y
Inversion Technique
Advanced Modelling
y
Tectonic Stress
Advanced Modelling
Advanced Modelling
Data
set
1
2
3
4
5
6
7
8
9
10
11
12
Well
A
New
Casing
20
13 3/8
9 5/8
20
13 3/8
9 5/8
20
13 3/8
9 5/8
20
13 3/8
9 5/8
Depth interval(m)
1100-1148
1607-1812
2320-2423
Depth
(m)
1101
1888
2423
1148
1812
2362
1141
1607
2320
1100
1700
2400
H/o
0.754
0.854
0.927
LOT
(s.g.)
1.53
1.84
1.82
1.47
1.78
1.87
1.49
1.64
1.84
?
?
?
h/o
0.750
0.814
0.906
P0
(s.g.)
1.03
1.39
1.53
1.03
1.25
1.57
1.03
1.05
1.53
1.03
1.19
1.55
Direction
44
96
90
o
(s.g.)
1.71
1.82
1.89
1.71
1.82
1.88
1.71
1.78
1.88
1.71
1.80
1.89
0
27
35
23
42
41
23
48
27
15
30
45
0
92
92
183
183
183
284
284
284
135
135
135
This Presentation
y
Local Map
Applications
Importance of in-situ stresses
Experience from Snorre
Modelling
Gradients
30
Gradients
30
Frac
20
13 3/8
Mud
Frac
Conclusions
13 3/8
Pore
Pore
9 5/8
7
Depth
9 5/8
Mud
7
Depth
Casing seat selection using low frac. curve
Poor predictions
o simple design modifications
o deviations, including contingency solutions
o abandonment of well
Seismic profiles
Max. Horizontal stress directions
Maximum horizontal stress from borehole breakout
Method:
Pore pressure
Overburden stress
Borehole inclination
Borehole azimuth direction
Conclusions
regional scale
Elongation data
Leak-off inversion
Field correlations
Borehole Collapse
Time model
Borehole Collapse
Borehole Collapse
Geomechanical Evaluation
Chapter 3.4 - Borehole Collapse
Vv = overburden = constant
VT = 2Va - Pw
Vr = Pw = borehole pressure
Borehole Stresses
Borehole Collapse
y
Radial stress:
Po
Vertical stress:
Pore
P
pressure:
Tangential stress:
Collapse Mechanism
Borehole Collapse
y
Borehole Collapse
Borehole Collapse
Borehole collapse
Time model
Time dependency
Field correlations
Collapse Mechanism
Borehole Stresses
Borehole Collapse
Collapse Mechanism
Borehole Collapse
Field correlations
Borehole Collapse
03.06.2011
03.06.2011
Borehole Collapse
03.06.2011
ROP models
y
The d-exponent
y
d- exponent:
It is actually a normalised ROP model, but the linear model works as well
The drillability is the only (?) measurement at the drillbit face. Other
measurements are behind in depth.
The blowing well had produced 18 000 bbls/day for one year leading
to reduced pore pressure and changes in in-situ stress.
High porosity
Easy drillable
Drillability summary
Objectives
y
Introduction
Fracturing
Empirical model
Field cases
Introduction
Hole collapse
1.0
1.5
2.0
Eatons model
Overburden
stress grad. (s.g.)
Linear
approx.
Overburden stress
1000
V ob
Circulation losses
Fracture gradient decrease with increased
water depth
Dw
Linear
approx.
Depth (m)
Fracturing
2000
1500
1000
Water depth (m)
500
| d sw
1.0
1.5
2.0
Stresses
Equal horizontal stresses
V v 3di d j P0 Py
VH Vh
1000
Horizontal stress
Vv
V h, H V v
Vh
2000
Conclusion
d wf
KV v P0 Py
V v
LOT
3000
Depth (m)
gd ob D
D Dw D f
Dw D Dw D f
2.0
D
D
15 000
Fracture directions
Fracturing equation
d wf
1
d sw Dw dbulk D dD
D
Dw
dob
3000
2000
Dw
g U sw dD g Ubulk dD
VH
Pwf
Pressure
Penetrating fluids
2V P0 Pt
Pwf
Pressure
Flow barrier
Pw
V 1 2Q V P0 1 Q V t
Pressure
Flow barrier
Pressure
Pw
Non-penetrating case
LOT
P0
P0
V
Penetrating case
Mud compressibility
Radius
Radius
Volume
Volume
2V P0 t Pwf t V
New depth
New gradient
Depth
D1
D2
hf1
hw1
P
P
K P
K P
d wf 2
d sw
N
fw1
N
fw 2
hf 1 hw1 Dsb1
N
ob1
N
ob 2
PfwN 2
Dsb1
PfwN1
N
ob 2
N
ob1
P
P
Dwf 1
hw 2
h d D
d wf 1
d sw w1 b 2 sb 2
Dwf 2
Dwf 2
Dwf 2 db1 Dsb1
dwf1
dwf2
Empirical correlation
Field case 1
Overburden
Ratio
d(LOT)/do
0.50
0.70
0.80
0.90
1,10
1,20
1,30
1,40
1,50
1,60
LOT data
1,70
1.00
1.10
1.20
1,80
1,90
2,00
1.30
500
0.60
Frac gradient
Average ratio
1,00
1000
500
1500
1000
2000
Depth (m)
1500
2500
2000
3000
Rig procedures
Interpretations of P-V-plots
3500
Mud density
2500
4000
3000
4500
3500
5000
4000
5500
Fracture gradient
Peon FIT
s.g.
1
1,05
1,1
1,15
1,2
1,25
1,3
1,35
1,4
350
400
Overburden stress
Fluid barrier
Depth (m)
450
500
550
y
600
Key issues
3.6 General Fracturing Model
Important findings
Overburden stress important
Seabed penetration important as well
Overburden stress
y
Seabed penetration
y
Normalization
y
Example 1
y
Equations
y
General equations:
Example 2
y
Field example
y
Chapter 4
Reduced integrity
(Weak point below shoe)
Reduced integrity
(Weak point below wellhead)
Pressure Conditions
Operational Conditions
Borehole Stability, Collapse Mud Loss
Completion Conditions
Drilling conditions, No. Of Bits/Trips
2700
1.60
9 5/8
2400
1.60
13 3/8
1300
1.30
18 5/8
700
1.20
30
400
Sea water
2700
1.69
2700
1.69
9 5/8
2400
1.69
9 5/8
2400
1.69
13 3/8
1700
1.40
13 3/8
1700
1.40
18 5/8
900
1.20
18 5/8
900
1.20
30
440
Sea water
30
440
Sea water
Bullheading pressures
Design alternatives
Other effects
Temperature
Time
Perforation, stimulation,
Temperature expansion
Temperature expansion
Burst Design
Casing Design
Chapter 5
Burst Design
Burst Design
Leaking tubing
Leaking Tubing
For production csg.
Burst Design
Burst Design
y
Vt
Ft
At
1 Di
P
2 t
Va
Fa
Aa
1 Di
P
4 t
Vt=2Va
Burst Design
Kick Scenario
Casing wear
Proportionality, Example:
Conservative criterion
Collapse Design
y
Collapse design
y
Elastic collapse:
Collapse criteria
Mud losses to a thief zone
Collapse during cementing
Collapse criteria
y
Thief zone
Tension design
y
y
y
During cementation
Temperature effects
y
Other criteria:
Bi-axial loading
y
Elliptic equation:
Burst strength
Other criteria
y
Sour service
Weight loss corrosion
Hydrogen embrittlement (H2S)
Time scenario
Exploration wells short life
Production wells long life
Casing wear
Wear and damage reduces well integrity
Possible approaches:
Design basis:
Test is unacceptable
Test is OK throughout
well
Introduction
5.3 Casing design example
y
y
y
y
y
Summary
y
Summary
Setting depth
Design basis
Casing design
Summary
Casing depths
y
Design basis
y
Collapse
Burst
tension,
Cementation
Wellbore stability
Fluid densities
Bullheading
Wear and corrosion
And so on.
Summary
y
Results:
Based on:
Wateroutside
Oil inside
Chapter 6 will assume mud
outside and gas inside
Overview
Background
Well examples
Conclusions
Current technology
stresses
y
dimensional model
y
stresses
equivalent stress
y
pressure
y
3D yield surface
z V y / V VME
y
E ( pi po ) / V y
2D design factors
Example cases
1.5
DF = 1.00
DF = 1.10
DF = 1.20
DF = 1.30
1.0
0.5
E ( pi po ) / V y
0.0
-0.5
Case 1
Case 2
S Case 3
Case 4
-1.0
Well 2 Platform
- Collapse of snubbing pipe during live well intervention
-1.5
-1.5
-1.0
-0.5
0.0
0.5
1.0
1.5
x ( pi V a ) / V y
Pressure/load matrix
New 3D model
DF = 1.37
Conventional triaxial
model
DF = 1.36
Biaxial model
DF = 1.37
Uniaxial model
DF = 1.44
Case #3
Thief zone
New 3D model
DF = 1.10
New 3D model
DF = 2.14
Biaxial model
DF = 1.04
Biaxial model
DF = 2.04
Uniaxial model
DF = 1.17
Case #4
Snubbing
2D design factors
1.5
New 3D model
DF = 1.69
DF = 1.00
DF = 1.10
DF = 1.20
DF = 1.30
1.0
0.5
E ( pi po ) / V y
0.0
Biaxial model
DF = 1.64
-0.5
Case 1
Case 2
S Case 3
Case 4
-1.0
-1.5
-1.5
-1.0
-0.5
0.0
x ( pi V a ) / V y
0.5
1.0
1.5
Conclusions
y
24 Surface casing
Production casing
y
y
y
Integrity:
Shoe weak, no kick margin, wellhead weak
point
2 Types of tubing
Temperature derating
Tieback and liner designs
Design summary
Important issues
Reservoir pressure
Reservoir fluid density
Fracture pressure
Density of fluid behind casing
Content
6. Design of HPHT wells
-
HPHT Definitions
y
Design premises
y
Objectives:
Flow test Jurassic reservoir
Drill through reservoir
Core or samle data
Well depth 5000 m but due to geological uncertainty, design depth is 5100 m
Casing alternatives
y
Prognosis
Alternatives
1: No finds
2: Run liner
3. Flow test using tie-back
4: Use liner too early
5: Use contingency to reach target
6: Flow test using tie-back casing
Geomechanic design
y
Geomechanic-Deep Fracturing
y
Stress regimes
y
y
Process repeated
for circulation
loss data
MW design cont.
y
MW gradually increased to
above median-line
MW design cont.
y
MW selection
y
MW criteria
Top hole lower than median-line
(ML) because of weak csg. shoes
1000 3000 m, approx. ML
line
y
Operational strategy:
Perform LOTs
Kick simulation tools
Drillability analysis
Careful hydraulic monitoring
7.1 Wellheads
Chapter 7
Drilling Operations and Well Issues
conductor casing
Operation:
Set anchors and pretension
Ballast rig down.Make up BHA no. 1 and 1300 m drillpipe
casing
Hours used:
24
20
1,3
9
2
1
2
Total hours
32
0,5
2
6
4
4
0
Operation:
Pull out and rack 36 in BHA
Break down 36 in BHA
Pull out and rack cement head in derrick
Make up 26 in BHA and run to template
Position rig w/thrusters, stab in and run to shoe
Drill 150 m of 26 in hole
Circulate hole clean
Wiper trip, run to bottom and displace to hivis mud
Pull out to seabed
Pull to surface and rack pipes
Position rig using thrusters
Rig up and run 145 m 20 in casing
Circulate and cement 20 in csg.
Release running tool and pull out of hole
Total hours:
Hours used :
1
1
1
1,5
1
12
3
4
2
4
12
4
2
49
Hours used:
4
16
4
4
0,5
3
1
3
3
0,5
Total hours:
39
Operation:
Make up 17,5 in BHA
Run in hole with BHA
Drill 20 in cement, plugs and shoetrack
Circulate contaminated mud and perform
Pick up drillpipe
Drill 700 m of directional 17,5 in hole.
Circulate hole clean, wiper trip, pull out of hole
Run log
Rig up for running of 13-3/8 in. casing
Set back cementing head, retrieve seat protector
Run 500 m of 13-3/8 in casing
Circulate and cement 13-3/8 in casing
Set seal assembly and pressure test
Perform BOP test and pull out
Run and set 13-3/8 in wear bushing
Lay down 17-1/2 in BHA
Service cement head
Hours used:
3
3
3
2
1
24
10
8
3
6
10
3
1
6
6
3
1
Total hours:
93
Wellhead
Hours used:
4
6
86
8
5
2
6
3
14
6
1
3
4
8
156
Operation:
Pull marine riser and BOP
Prepare for X-mas tree running
Run and install X-mas tree
Pull running tool
Run marine riser and BOP
Position and latch
Total hours:
Hours used:
8
8
24
4
9
2
55
Hours used:
4
6
7
2
6
12
160
Total hours:
197
Operation:
Clear rig floor
Make up scraper and magnet assy.
Pick up heavy weight drill pipe
Make scraper run
Rig up tubing tongs
Make up wirewrap screens, blanks and swellpackers
Install screen packer/hanger and running tool
Rig down tubing tongs
Run screens on drill pipe
Drop ball, pump down and set packer
Test packer from above
Release running tool and flowcheck
Displace well above packer to brine
Pull out and lay down running tool
Make up anchor packer assy.
Run in assembly on drill pipe
Orient and set anchor packer
Pull out and lay down running tool
Hours used:
0,8
1,6
12
18,9
3,1
27,2
1,6
0,8
15,7
3,1
1,6
1,6
0
7,9
4,7
15,7
1,6
7,9
Total hours:
126
Hours used:
3,1
7,9
15,7
6,3
29,9
6,3
1,9
6,3
6,3
18,9
9,4
1,6
3,1
1,6
12,6
3,1
1,6
136
Operation:
Prepare rig for well flow
Displace WOR to nitrogen
Flow out brine and mud and oil
Bullhead tubing with diesel and wax inhibitor
Displace WOR to brine
Close TRSCSSV
Install tubing head crown plug and test on wireline
Close HXT valves and test
Remove and lay-out WOR, SST etc.
Install tree cap, test, pull and lay down running tool
Pull BOP and marine riser
Install corrosion cap
Deballast and prepare to move rig
Total hours:
Hours used:
3,1
9,4
12,6
3,1
3,1
0,8
12,6
3,1
12,6
9,4
15,7
6
6,3
98
Dogleg
Hours used:
Total hours:
Percent time:
32
49
39
93
156
55
197
126
136
98
3.3
5
4
9.5
15.9
5.6
20
12.8
13.9
10
981
40,9 days
100%
180
Trad
S
DL( $ )
D2
I2 2
T T
D1
I1
2D Example
Straight sections
500
1000
1500
Horizontal
Re ach ( m)
F2
F1 E'Lw^cos D r P sin D`
Curved sections
F2
F1e
335
170
45q
455
500
45q
1000
r P T 2 T1
sin D 2 sin D1
E w'L
D 2 D1
PrN PrF1 T2 T1
13
08
1380
1500
1661
Depth (m)
45q
170
286kN
2D Results
2D Results
Torque (kNm )
Table7.1:Forcesinthedrillstring duringhoistingandlowering
Torque
Static weight(kN)
Hoisting (kN)
( kNm )
10
Lowering(kN)
10
20
20
500
500
15 . 54
1000
491 . 1
641 . 4
840 . 3
13 15.54 22
Force ( kN )
Position
Without
Bit Torque
1000
90kN
641.4
Force (kN )
With
Bit Torque
Vertical
Vertical
Well Bottom
286
286
286
335
335
Build-Up
455
Build-Up
286+0.237x120=
286+28.4=314.4
286x1.17+28.4=363
314.4+0.237x925=
=314.4+219.2=533.6
363+0.237x1308(cos 45+0.20sin45)=626
272.9+0.237x1308(cos 45-0.20sin45)=448.3
533.6+0.237x120=
533.6+28.4=562
626x1.17+28.4=760.9
448.3x0.855+28.4=411.7
562+0.237x335=
562+79.4=641.4
760.9+79.4=840.3
411.7+79.4=491.1
500
455
500
286x0.855+28.4=272.9
Hoisting
Torque
Static
Straight
Inclined
1000
Straight
Inclined
Off
Bottom
1000
Lowering
1380
1380
Drop-Off
1500
Drop-Off
1500
BHA
Vertical
1661
BHA
Vertical
1661
WOB
TOB 9kNm
Depth ( m )
Depth (m )
3D Example
3D Results
Torque ( kNm )
0
0
10
20
13 . 5
463
500
1000
576
StaticTorq ue
768
Lowering
Static
Pure
Lowering
Build-up
Build-up
with
Right Side Bend
Build-up
with
Left Side Bend
3000
40
2000
1512
1752
73
2063
2104
Build-up
Build-up
with
Right Side Bend
2075
Build-up
with
Left Side Bend
Straight Inclined
BHA
2865
1052
25
Pure
Hoisting
Straight Inclined
1700
3000
Force (kN )
Combined
Hoisting
1100
2075
2865
768
1000
Straight Inclined
500
1000
661
StaticWeight
Hoisting
1100
1700
513 576
Vertical
Combined
Lowering
500
1000
2000
463
Vertical
500
500
0
Force ( kN )
MD ( m )
MD (m)
Straight Inclined
BHA
This presentation
y
Introduction
Field case
Summary
Introduction
Numerical simulators:
Availability
Limitations
Drag:
Torque:
F2 = F1 + w's(cosD r PsinD)
T = Pw'srsinD
Drop-off section
Results:
Well path coordinates:
F1 sin D1
w
F1e
P (D 2 D1 )
wR
1 P 2
P D 2 D1
2
sin D1 )
(1 P )(sin D 2 e
P D 2 D1
2
P
(cos
D
cos D1 )
e
2
F1 e
P D 2 D1
ws F1 cos D1
F1 sin D1
Torque:
ws F1 cos D1
F1 sin D1
P r 'F tan 1
'Tcat
Note: Entrance condition to modified catenary
P'F tan 1
'Fcat
Torque:
T
wx
F1
sinh 1 cot D1 cos D1
sin D1 sinh
w
F1 sin D1
wx
Side bend
Tension:
F2
1
1 wR e 2 1
2
r P I I
F1 F12 wR e 2 1
2
2 F F 2 wR 2
1
1
2
# P I I
Torque:
T
Pr F12 wR 2 I2 I1
a) Drag and torque for a pipe.
b) Combined friction from rotation
and axial movement.
T
r
F2
P w's
CTrotary nrotary
Pmotor
CTmotor nmotor
nrotary
nmotor
Application:
Trotary
vertical section
-
Total solution:
Adding the equations for these geo metries gives total torque and drag
Field case
Long-reach well in the Yme field:
Depth: 2950 mTVD top reservoir
3100 mTVD total depth
Drag:
Drag:
F2
Torque:
T= 6 T from bottom to top
Torque:
F2
T build_or_drop T sidebend
2
Rig limitations:
Hoist:
Top drive:
Field case
Field case
Results
Hoist
Well
Profile
Top-drive:
Modified
catenary
Minimum
dog-leg
Undersection
Standard
Slack-off
load (kNm)
845
1360
593
843
1332
609
842
1321
568
858
1350
543
Well
Profile
Modified
catenary
Minimum
dog-leg
Undersection
Standard
Surface
Torque build-up Torque
torque (kNm) bnd (kNm)D
hold
28.57
7,11
21,46
30.91
11,04
19,87
29.51
6,88
22,63
30.42
9,05
21,37
Conclutions:
Summary
y
Analytical expression for torque and drag are derived in this paper.
The models are valid for straight sections, build-up, drop-off and side
bends.
Equations for geometry and torque and drag for a modified catenary
profile is also given.
Torque and drag analysis can be performed by adding equations for each
hole section.
An ultra-long well was studied with the models. By using light-weight drill
pipe in the sail section a 12 km(or longer) well can be drilled with existing
rig equipment.
Conclusions:
Well can be drilled if light drill pipe
is used in the sail section
Tension allowable for all cases
Torque limiting factor
Other elements within permissible
limits, like hydraulics, hole cleaning,
borehole stability,
Results
Drillpipe
Pulling
Steel
Titanium
Composite
179
133
102
Hook load(kN)
Static
Lowering
175
130
101
60
60
60
Build-up
10,2
6,2
3,7
Torque(kNm)
Hold
Total
section
43.7
53.9
26,90
33.1
16.0
19,70
Friction
Drill pipe weight
Mud density
Content
Introduction
y
y
y
y
y
y
y
Introduction
Industry practice
Deviated wells and friction
Depth to stuck point
Field case
Methods to free pipe
Final comments
Industry practice
y
y
y
Field case
y
Results:
Frictionless:
5097 m
New model:
5693 m
Torsion test:
5675 m
Torsion test
y
Final comments
y
here.
Results:
This presentation
Well barrier
intact
(or uncertainty)
Yes
No
Impact?
Yes
Shut in well ?
No
Cat. B:
Well is
shut In,
Working
under
Cat. C:
Insignificant
deviation
for current
operation
Cat. F:
Cat.G:
Cat. E:
Shut in
Shut in
Shut in
because of
while
on the
E.g.:
topsides
awaiting
basis of
weather
P&A
reservoar bottlenecks,
conditions,
planned
related
other
testing and
issues
activities,
union dispute, E.g.: high maintenance
water cut
Incl.: SD&P
Cat. D:
External
conditions
70
75
60
50
40
30
48
20
10
27
Production
Source
Injection
Total
Well issues are related to 33% of the injectors, and 15% of the producers.
Ref. Swiss cheese
model
Well
OK /
active
Cat. A:
No
Well integrity
failure / issue ?
25
Number of wells
20
22
15
18
Producer
16
Injector
10
10
8
30
25
26
20
24
15
16
10
5
6
1
0 to 4
A: Shut in
B: Working under
conditions
C: Insignificant deviattion
for current operations
5 to 9
10 to 14
15 to 19
20 to 24
25 to 29
Age in years
The frequency of wells with integrity issues in age group 0-14 years is twice as
high as for well group 15-29 years.
WAG wells and recently optimized well design have caused challenges
P&A wells are not included in this survey
9
4
8
4
W
el
lh
ea
d
D
C H
on S
V
du
ct
or
AS
Tu V
bi
ng
G
LV
C
as
C ing
em
e
Pa n t
ck
C
he P
e
m ac r
i ca k
o
l i ff
nj
.l
in
Fl T R e
ui
S
d
ba V
rr
D ier
e
Fo sig
rm n
at
io
n
Number of wells
29
C a t e r or y ba r r i e r e l e me nt f a i l ur e
35
30
25
20
15
10
5
0
Reasons:
Cement return port left
open
Fresh seawater and tide
caused severe corrosion
in splash zone
Event:
Casing and tubing hanger
and running tool failed
during operations
Overloaded during
pressure testing
Consequences:
Platform production
stopped
High cost of event
Initiated monitoring
program
Reasons:
Depleted reservoirs
Gunk pill plugged off DP
Less good operational
decisions
Consequences:
Sidetracked well
High cost
Improved procedures
Reasons:
Hangers uprated 50%
Manufacturers up-rating
failed
Accepted uprating as OK
Poor equipment design
Consequences:
Cost of well problems
Many installations, cannot
replace
Reduce max. allowable
loading
Reasons:
Leaks in PBR
Corrosion
Consequences:
Increased monitoring
Constraints for availability
and flexibility
Reasons:
Wrong csg. joint installed
Leaks through PBR
Uncertain pressure
integrity of well
Consequences:
High cost
Clarify well integrity
Improve workover
procedures
Summary
EXTRA VIEWGRAPHS
I.
J.
K.
Is the well picture/ outcome of the XLS- forms representing the typical situation
on the facility ?
Are key design premises, well history and current technical condition validated
and easy accessible for key personnel?
Does hand-over documents include sufficient well data with premises/ limits,
including updated schematics, exposures, technical condition and changes/
deviations/ precautions with regard to well integrity and well control issues?
Are there established technical requirements to well barrier envelopes /elements,
regular condition monitoring, and systematic management of well integrity issues
?
Are the company requirements for well barriers consistent with Norsok D-010 ?
Is there a consistent practise within the company for managing well integrity
issues?
Are management of change and non-conformance handling consistently practised
?
Are requirements to competence and training defined and implemented for
common understanding of the well barrier concept, barrier performance
requirements, records assurance, and actions required upon indications of
failures ?
How is openness and reporting of undesirable well incident encouraged, including
exchange of experience internally and externally ?
Any specific performance indicators pertaining to well integrity ?
Other issues relating to the subject