Você está na página 1de 70

The Importance of Stresses in

Petroleum Engineering

Approach

Chapter 2.1 - Mud Weight Selection

This presentation:
y

Approach

Drilling problems

Pressure Testing

Stresses as Design Criterion

Summary

Drilling Problems

Drilling Problems
y

Mud loss:

2.5 days

Tight hole:

0.3 days

Squeeze cmt:

2.5 days

Stuck csg.:

3.3 days

Fishing:

0.3 days

Lost time:

Cost:

Drilling Problems
If problems get worse:
 Stuck + sidetrack
 New well

9 days
+2 mill.$

Stress as Design Criterion

Stress as Design Criterion


y

EFFECTS OF HIGH MUD WEIGHT


Element

Advantage

Reduce borehole collapse

Reduce fill

Reduce pressure variations

Debatable

Reduce washouts

Reduce tight hole

Reduce clay swelling

Increase differential sticking

Increase lost circulation


Reduced drilling rate

Expensive mud
Poor pore pressure estimation

X
X

Disadvantage

From solid mechanics:

EH

Petroleum Rock Mechanics: Material


properties

Recent view: Stress dominated processes


 This leads to simplified design methods

Stress as Design Criterion


y

Stress as Design Criterion

Horizontal stresses from Kirch eqn.:


 V = (LOT+Pore Pressure)
 Mid-Line Principle

Stress as Design Criterion

Stress as Design Criterion

Example from the North Sea

Example of specific reaming time from


selected North Sea wells.

Stress as Design Criterion

Pressure Testing

Stress as Design Criterion

Summary
y

In-situ stresses important for well problems

LOT testing defines stress level

Borehole collapse not fully understood

Traditional approach: Rock mechanical data limited


by data available

Complementary approach: Stress analysis from


Mid-Line Principle

New principle demonstrated the past 8 years

2.2-Design of Well Barriers to


Combat Circulation Losses
-

Design of Well Barriers


y

This presentation:
 Introduction
 Experimental work
x Fracturing lab
x New fracture model
x Barrier stress model

 Design of fluid barriers


 Field case
 Summary

Introduction
y

Circulation losses and stuck pipe two unresolved


issues in drilling

Fracturing lab built at U. of Stavanger in 1996

 Yearly losses Billions US$ worldwide

Focus on basic mechanisms

 Operational factors important


y

Circulation losses:
 Geomechanics (stresses, lithology,.)
 Mud barrier (filtrate loss, bridging,)

Experimental work

Improvements depends on complementary processes


 Fundamental research
 Field application

 Fracturing of concrete cylinders


 Chemical effects(wettability,)
 Hole geometry (circular, oval, square, trianguler
holes,)
 Controlled loading(confining, axial, borehole stress)
 Many types of barriers

Experimental work, fracturing lab


Axial load

Fracturing cell

Mudcake strength cell

Pump 1
Test cell

Confining
Pressure

Pump 2

Hollow
Concrete
Core
Well Pressure

PC
Control
System

Pump 3

M ud circulation

Mud cell

Valve  2

Cell 6 Cell  5 Cell  4

Mudcake strength

Mudcake

Pump  1

Experimental work

LabView

Valve  3

Pump  2

Valve 1
M udcake

Cell 1 Cell  2 Cell  3

Example,
3 drilling muds:

Fracturing pressure, MPa..

Experimental work, new frac


model
60
M easured

40

Kirsch equation

20

Stone bridge principle

0
A

New Kirsch eqn.

Experimental work

Pw

B
Drilling fluids

2V  Po 

2V y

t
ln1 
3 a

Experimental work
Mechanical strength of mud cake important

Feldspar

60

60
New OMB

Quartz
Pressure, [Mpa]

Cake collapse pressure, [Mpa]

-particle yield strength (Mohs hardness)


-but also size , distribution and placement

45

30

CaCO3

Used Field OMB

45
30
15
0
0

15
1

Time, min

Moh's scale

3.Design of fluid barriers

3. Design of Fluid Barriers

Example of test program

Tested numerous commercial additives

Too many additives gave negative synergy

Minimum no. of additives gave best results

Some additives have no effect

Need more scientific approach to improve

PS:Have only studied fracturing, not

Additive:

Consists of:

CaCO3 coarse

Test
No.1
(ppb)
15

Test
No. 2

Test
No. 3

Test
No. 4

Test
No. 5

Test
No. 6

CaCO3 fine

15

Fine polymer

20

20

20

15

25

15

Medium polymer

20

20

20

20

25

20

Graphite

40

40

40

25

Mica fine

20

20

15

20

20

20

Mica medium

15

20

20

20

Cellulose

30

30

30

30

Cellulose

Feldspar

30

30

40

40

Good

Very
good

Very
good

Best

Result:

30

30

15

30

Ref.

Bad

formation damage

10

Design of Fluid Barrier

Field case

Small amounts of carbon fiber has good


effect

Offshore drilling operation


Mud tested at our lab during drilling

Replaces larger particles


Fracture - RKB
Gradient (s.g.)
1

1,05

1,1

1,15

1,2

1,25

1,3

350
400

Depth (m)

450
500

This well
Reference wells
Fracture curve

550
600
650
700

Example of proposed recipies


Additive:
Consists of:

Drilling mud

Our proposal
(6 ppb)

CaCO3
coarse
3

Graphite

Cellulose

Mica
fine
3

6. Summary

Carbon
fibre
-

Elastoplastic frac model developed based on


comprehensive lab experiments

Well barrier consist of placement + mechanical


strength of particles

Additive:

Lost circulation pill

Consists of:

Operators
recipie(ppb)
15

CaCO3 coarse

CaCO3 fine

15

Our
proposal(ppb)

Fine polymer

20

30

Med. polymer

20

20

Graphite

40
20

Mica fine

Mica medium

Cellulose

Carbon fibre

Some mud additives have zero or negative effect

New test equipment required to test barrier frac


efficiency

20
20

30

45
Some

Our approach is tested in the field.

Methodology
2.3 Hole Cleaning

Based on API RP 13D: Rheology and Hydraulics of Oilwell Drilling Fluids.

Based on BP research early 1990s

Mainly based on experimental correlations

Hole cleaning is a key issue, must control ROP to avoid


overloading annulus with cuttings

Mechanisms

Applications

Variables
 Mud flow rate
 ROP
 Mud rheology/flow regime
 Mud weight (buoyancy)
 Hole size and angle

Uncontrollable variables
 eccentricity
 cuttings size
 density

Transport index
 TI = RF (rheology factor) xMW (mud weight)x AF (angle factor)

If hole is washed out:


 CFRwashout = CFR (flow rate)

Example
y

8.5 horizontal well

Solution
y

From Fig. 2.16, RF = 0.91

From Table 2.5, AF = 1

 MW = 1.45 sg, PV = 25 CP,YP= 18 lbf/100 ft2

Questions:
 Maximum ROP if maximum flow is 480 gpm? (Correct book)
 If ROP = 20 m/hr, what is minimum flow?
 If hole is washed out 10 in, what flow rate is required?

From Eqn. 2.7,

Solution, cont.
y

From Fig. 2.16b: at TI=1.32, Q=480 gpm, ROPmax=23


m/hr

If ROP = 20 m/hr, Qmin=470 gpm

TI = 0.91x1.0x1.45 = 1.32

Solution, cont.
y

If hole is washed out, correction factor:

Minimum flow rate now:

CFRwashout = 1.38 x 470 = 649 gpm

Hydraulic System
Hydraulic Optimization
Chapter 2.4

P1 = pump pressure
P2 = nozzle pressure
P3 = system loss (parasitic)
P1 = P2 + P3

Hydraulic System

Pressure drop
y

Laminar flow

P v PQ

Turbulent flow

P v U fQ 2

Empirical flow equation

P CQ m

Hydraulic System

Hydraulic System
P3 = system loss
P3 = CQm
lnP3 = lnC + mlnQ

Nozzle pressure drop from Bernoulli


P2

UQ 2
2 gA2 0.952

System losses
P3

300bar  P2

Hydraulic Optimization

Hydraulic Optimization

Nozzle Horsepower
HP

P2Q

 Max. Hydraulic horsepower

( P1  P3 )

 Max. Jet impact

( P1  CQ m

Maximum

Classical criteria

Limitations
 Physically correct?

dHP
o P3
dQ

P1
m 1

 Adequate Q for hole cleaning?

Hydraulic Optimization

Application

1.

Determine hole cleaning rate Q

2.

Select performance index

3.

Compute system loss (P3) and bit loss


(P2)

4.

Compute nozzle area, A

Performance indices

Performance
index

Equation

Criterion

Fraction parasitic
pressure loss

Max. HP
qP2

2
q P2

3
4
5

q 3 2 P2
q 2 P2
q 5 2 P2

Max. Jet
impact
New A
New B
New C

Flow rate

1
m 1

P1
C (m  1)

2
m2

2 P1
C (m  2)

3
m3

3P1
C (m  3)

4
m4

4 P1
C (m  4)

5
m5

5P1
C (m  5)

Proposed criteria

Example
y

Proposed optimization criteria for typical 12-1/4 inch hole


Hole length

Vertical holes

Deviated wells
drilled with motor

Deviated wells
without motor

Stronger
requirements

Less than 2500 m

Max. Hydr. Horsepower


or max. Jet impact force

Max. HHP or
max. Jet impact

Max. Jet impact

New A

2500-4000 m

Max. HHP
or max. Jet impact

Max. Jet impact

New A

New B

Deep(5000m)

Max. HHP
or max. Jet impact

Max. Jet impact


or New A

New B

New C

Other data: Drill pipe: 675 m of 5 inch, rest 6-5/8 inch; Drill collars: 120 m 8-1/8 inch OD,
2.81 inch ID; Mud density: 1.65 s.g., Yield point: 32 lbf/100 sq.ft.; Plastic viscosity: 42 cP.

Determination
of flow ranges
and optimisation
criteria

Drill Pipe Size

Example
Hydraulic parameters for the field case
Criterion

Percent parasitic press. loss

Flow range (l/min)

Max. Hydraulic power

54

2800-2220

Max jet impact

52

2850-2280

New A

63

3070-2450

New B

69

3250-2580

New C

73

3370-2800

Optimal nozzle selection for New B criterion


Depth (m)

Nozzles (inch)

1200

Five 13/32, one 16/32

2200

Five 12/32, on 16/32

3200

Five 11/32, on 16/32

Example
Geomechanic Evaluation

Summary of earlier bit runs


Bit. No.

Nozzles

q (l/min)

ROP (m/hr)

Remarks

5 x 16, 1 x 12

2960

1.5

Plugged center nozzle

5 x 19, 1 x 12

2660

9.8

5 x 16, 1 x 12

2600

13.6

5 x 19, 1 x 12

2300

18.2

5 x 18, 1 x 12

2400

14.9

6 x 12

2600

18.3

5 x 14, 1 x 12

2400

15.4

5 x 15, 1 x 12

2450

24

5 x 14, 1 x 12

2400

4.8

10

5 x 14, 1 x 12

2530

23.8

11

5 x 19, 1 x 12

20

12

5 x 19, 1 x 12

30

13

5 x 18, 1 x 12

10

14

5 x 18, 1 x 12

22

Plugged center nozzle

15

5 x 19, 1 x 12

Plugged center nozzle

16

5 x 18, 1 x 12

27

Plugged center nozzle

17

5 x 19, 1 x 12

16

Plugged center nozzle

18

5 x 19, 1 x 12

19

Plugged center nozzle

Plugged center nozzle

Plugged center nozzle

Chapter 3.1 - Data Normalization

Data Normalization

Data Normalization

Example, pore pressure at 1000m:

Example, continued:
New gradient from RKB

P(bar)= 0.098d(s.g)D(m)
= 0.0981.03 1000
= 100.9 bar

d MSL 1.03s.g.

d RKB

100.9bar
1.0s.g.
0.098 1025m

Data Normalization

Data Normalization

From sea level

d MSL

d RKB

d RKB

d MSL

d RKB1

D
D  hf

From RKB

From floater

d RKB 2

From platform

D  hf
D

D
D  Gh

d RKB 2

d RKB1

D  Gh
D

V o (sg )

Data Normalization
y

Data Normalization

Normalize to seafloor
1. Subtract water pressure

Well

Csg (in)

34/7-2

2. Subtract water depth


34/7-8

34/7-14

Depth (m) hw (m) hf (m) LOT(s.g.) P0 (s.g.) V0 (s.g.)

20

848

13 3/8

245

1.58

1.06

1.83

1549

1.69

1.42

2.00

9 5/8

2031

1.88

1.63

2.00

20

848

1.62

1.04

1.72

13 3/8

1859

1.83

1.42

1.93

20

491

1.49

1.00

1.49

13 3/8

1559

1.75

1.09

1.70

9 5/8

1988

1.80

1.53

1.92

286

148

25

25

25

Interpretation
Geomechanic Evaluation
Chapter 3.2 - Interpretation

Basic data
 Leak-Off-Pressure (LOT)
 Pore Pressure
 Overburden Stress
 Lithology
x Clays
x Sands, Chalks,

Interpretation

Interpretation

Simple modelling

Example

 Evaluate LOT data


 Effective stresses

Well

Dataset Depth(m)
A

 Horizontal stresses
 Effective horizontal stresses

 Depth normalize
 Effective depth normalized data

(s.g.)

o(s.g.)

899

1.46

1.04

1.63

1821

1.74

1.28

1.81

901

1.55

1.04

1.60

1153

1.56

1.04

1.73

1907

1.81

1.34

1.82

2753

1.95

1.52

1.96

Interpretation

Interpretation

Example: LOT Pressure

(s.g.)

Example
 LOT Gradient

Interpretation

Interpretation

Horizontal stresses,
depth normalized
Va
Va
Vo

LOT

KV o

Va

LOT  Po
2V o

y
y

Effective horizontal
stresses, depth
normalized
Va '
Vo '

LOT  Po
2 V o  Po

Horizontal stresses
2V a  Po
1
LOT  Po
2

Effective horizontal
stresses
V ' V  Po
Va '

1
LOT  Po
2

Interpretation
y

Best fit

1
Va '
LOT  Po 0.23
2
LOTPrognosis 0.46  Po

Test of model

Geomechanical Evaluation
Chapter 3.2.4 - Advanced Modelling

Advanced Modelling

Advanced Modelling

Principle: Normalize all data to same


reference, example:

Borehole inclination
 Normalize all LOTs to
vertical for comparison

 Borehole inclination

Pwf (0q)

 Compaction
 Inversion technique

Pwf (0q)

1
Po  Po* sin 2 J
3
1

Pwf (J )  V o  Po sin 2 J
2

1
1  sin 2 J
2

Pwf (J ) 

Advanced Modelling

Advanced Modelling

Compaction model
'V a
'Pwf

1  2Q
1 Q
1  3Q
'Po
1 Q

'Po

Applications
 Normalization
 Structural geology
 Lost circulation

Compaction model
 Example

Depth(m)

LOT (s.g.)

P0 (s.g.)

3885

2.10

1.79

3821

2.13

1.84

3818

1.98

1.44

3914

2.06

1.58

Advanced Modelling
y

Inversion Technique

Advanced Modelling
y

Relaxed Depositional Basin

Tectonic Stress

 Determines tectonic stress field that fits all


data sets
 Use this stress field to make prognosis for
new well
 Determines also stress directions as applied
to e.g. fracturing and stimulation

Advanced Modelling

Advanced Modelling

Data
set
1
2
3
4
5
6
7
8
9
10
11
12

Inversion Technique, Example

Well
A

New

Casing
20
13 3/8
9 5/8
20
13 3/8
9 5/8
20
13 3/8
9 5/8
20
13 3/8
9 5/8

Depth interval(m)
1100-1148
1607-1812
2320-2423

Depth
(m)
1101
1888
2423
1148
1812
2362
1141
1607
2320
1100
1700
2400

H/o
0.754
0.854
0.927

LOT
(s.g.)
1.53
1.84
1.82
1.47
1.78
1.87
1.49
1.64
1.84
?
?
?

h/o
0.750
0.814
0.906

P0
(s.g.)
1.03
1.39
1.53
1.03
1.25
1.57
1.03
1.05
1.53
1.03
1.19
1.55
Direction
44
96
90

o
(s.g.)
1.71
1.82
1.89
1.71
1.82
1.88
1.71
1.78
1.88
1.71
1.80
1.89


0
27
35
23
42
41
23
48
27
15
30
45

0
92
92
183
183
183
284
284
284
135
135
135

Leak-off, new well


1.53
1.71
1.86

Inversion Technique, Example

3.2.4 In-Situ Stress Modelling of the Snorre


Field

This Presentation
y

Local Map

Importance of fracture gradient


prediction in well planning

Applications
 Importance of in-situ stresses
 Experience from Snorre

Modelling

Gradients

30

Gradients

30
Frac

20

13 3/8

 Regional stress field

Mud
Frac

x Earthquake focal mechanisms

 Local stress field


x Borehole elongation
x Leak-off inversion

Conclusions

13 3/8

Pore

Pore
9 5/8
7
Depth

9 5/8
Mud

Casing seat selection using high frac. curve

7
Depth
Casing seat selection using low frac. curve

Experience from Snorre

Experience from Snorre, cont.


y

Fracture gradient and pore pressure gradient: Key


elements in well design.

Poor predictions
o simple design modifications
o deviations, including contingency solutions
o abandonment of well

Relaxed depositional basin

Optimization requires improved prognosis

Knowledge of the in-situ stress state is the key to improved


leak-off prediction

Anistropic stress field

In-situ stress directions from


earthquake data

In-situ stress directions from


borehole elongation data

Method: Inversion of focal mechanism data

Seismic profiles
Max. Horizontal stress directions
Maximum horizontal stress from borehole breakout

Horizontal stresses and directions


from borehole leak-off data
y

Method:

Parameters: Fracture pressure

Horizontal stresses and directions


from borehole leak-off data

Inversion of leak-off and minifrac data

Pore pressure
Overburden stress
Borehole inclination
Borehole azimuth direction

Stress fields at reservoir level from leak-off inversion

Horizontal stresses and directions


from borehole leak-off data
y

Conclusions

Summary, leak-off inversion:

The stress field at Snorre is anisotropic due to tectonics of the area

 For shallow depths (to 1500m), the horizontal stress


state has relaxed, nearly hydrostatic state.
 In the deeper parts (1500 3000m), the horizontal
stresses becomes anistropic with depth.

Focal mechanisms, borehole elongation and leak-off data have been

 The stress state varies both depthwise and areawise.


In certain places the max. horizontal stress exceeds
the overburden.
 The method gives realistic stress ratio. Also, the
directions are consistent with the fault pattern of the
area.

used to assess the in-situ stress levels and direction at Snorre.


y

The three methods shows consistency, but model various scales:


Focal mechanism

regional scale

Elongation data

local scale (one borehole)

Leak-off inversion

local scale (several boreholes)

Maximum horizontal stress is regionally in a North-West direction

Stresses near faults dominated by faults

The described approach has significantly improved fracture pressure


prediction

Field correlations

Borehole Collapse

Time model

Borehole Collapse

Borehole Collapse

Geomechanical Evaluation
Chapter 3.4 - Borehole Collapse

Vv = overburden = constant

VT = 2Va - Pw

Vr = Pw = borehole pressure

Borehole Stresses

Borehole Collapse
y
 Radial stress:

Po

 Vertical stress:
 Pore
P
pressure:

 Tangential stress:

 Mohr-Coulomb failure model

Collapse Mechanism

Borehole Collapse
y

Borehole Collapse

Borehole Collapse

Borehole collapse

Time model

Time dependency

Field correlations

Collapse Mechanism

Borehole Stresses

Borehole Collapse

Collapse Mechanism

Borehole Collapse

Field correlations

Borehole Collapse

03.06.2011

03.06.2011

Borehole Collapse

3.5 Drillability Evaluation

03.06.2011

ROP models
y

The d-exponent
y

The simplest ROP model is:

This model is used:


 Continuously in mudlogging units offshore
 Estimate pore pressure
 Assess bit wear with rollercone drillbits

A more common model is the

d- exponent:

 Various geological interpretation


y

It is actually a normalised ROP model, but the linear model works as well

The drillability is the only (?) measurement at the drillbit face. Other
measurements are behind in depth.

Drillability is always measured and provide a very important source of


information . Examples follows.

Clay diaper example


y

Tophole drilling found soft sediments

Relief well example


y

well was killed with a relief well.

that could not be detected on logs.


y

Drillability analysis performed

Found increase in drillability at a given depth


interval

Difficult to detect distance between wells at 5000 m

Breakthrough point critical as both wells could lose control

Relief well finished one year after initial blowout.

The blowing well had produced 18 000 bbls/day for one year leading
to reduced pore pressure and changes in in-situ stress.

Conclusion: Discovered an unidentified clay


diaper characterized by:
 High water content

An underground blowout in a HPHT

Comparing the two drillabilities defined proximity and also extent of


damage caused by underground flow. This was the only information at
that time.

 High porosity
 Easy drillable

Relief well example


y

Drillability summary

Examples shows the power of drillability information

Drillability should be further explored as a formation evaluation


tool and a well dignostic tool

Fracture Model for General


Offshore Applications
Chapter 3.6

Fracture Model for General Offshore


Applications

Objectives
y

Introduction

The overburden stress

Fracturing

Empirical model

Method to normalize data

Field cases

Summary and conclusions

Introduction

The overburden stress

Problems increase with water depth

Shallow water flow

Hole collapse

1.0

1.5

2.0

Eatons model

Overburden
stress grad. (s.g.)
Linear
approx.

Overburden stress

1000

V ob

Circulation losses
Fracture gradient decrease with increased
water depth

Dw

Linear
approx.

Depth (m)

Fracturing

2000

1500
1000
Water depth (m)

500

| d sw

1.0

1.5

2.0

Stress grad. (s.g.)

Stresses
Equal horizontal stresses

V v 3di  d j  P0  Py

VH Vh

Different horizontal stresses


VH !Vh

1000

Horizontal stress

Vv

V h, H V v

Vh

2000

Conclusion
d wf

KV v  P0  Py

V v

LOT

3000
Depth (m)

gd ob D

D  Dw  D f
Dw D  Dw  D f

2.0 

D
D
15 000

Fracture directions

Fracturing equation
d wf

1
d sw Dw  dbulk D dD
D
Dw

dob
3000

Overburden stress gradient

2000

Dw

g U sw dD  g Ubulk dD

VH

Fracturing Flow barriers


Non-penetrating fluids

Pwf
Pressure

Fracturing LOT testing

Penetrating fluids

2V  P0  Pt

Pwf

Pressure

Flow barrier

Pw

Water-based drilling fluid

V  1  2Q V  P0  1 Q V t

Oil-based drilling fluid

Pressure

Flow barrier

Pressure

Pw
Non-penetrating case
LOT

P0

P0
V
Penetrating case

Mud compressibility

Radius

Variation in break-down pressure:

Radius

Volume

Volume

2V  P0 t Pwf t V

Empirical fracture model

Method to normalize data

Leak-off (LOT) data studied from 175-2071m water


depth

All data normalized by subtracting water pressure


and depth

Data correlates well with overburden and


horizontal stress curves

New depth

Valid for all relaxed sedimentary depositional basins

New gradient

Depth
D1

D2

hf1
hw1

D1  'h f  'hw  'Dsb

P
P

K P
K P

d wf 2

d sw

N
fw1
N
fw 2

Fracture Model for General Offshore


Applications

hf 1  hw1  Dsb1

N
ob1
N
ob 2

PfwN 2

Dsb1
PfwN1

N
ob 2
N
ob1

P
P

Dwf 1
hw 2
h d D
 d wf 1
 d sw w1 b 2 sb 2
Dwf 2
Dwf 2
Dwf 2 db1 Dsb1

dwf1

dwf2

Empirical correlation

Field case 1

Ratio between leak-off data and overburden

Overburden

Five deep-water wells


selected for analysis

Ratio

d(LOT)/do
0.50

0.70

0.80

0.90

1,10

1,20

1,30

1,40

1,50

1,60

LOT data

1,70

1.00

1.10

1.20

1,80

1,90

2,00

Well used for empirical


correlation

1274m water depth

Variations in LOT influenced by:

1.30
500

Fracture prognosis of 98%


of overburden stress
gradient
Standard deviation of 0.05

0.60

Frac gradient

Average ratio
1,00

1000

500
1500

1000
2000

Depth (m)

1500

2500

2000

3000

 Rig procedures
 Interpretations of P-V-plots

3500

 Mud density

2500
4000

 Quality of mud cake

3000
4500

3500

5000

4000

5500

 Assessment of bulk density and


overburden stress

Fracture Model for General Offshore Applications

Field case 2 - Prognosis


Overburden

Fracture gradient

Peon FIT

s.g.
1

1,05

1,1

1,15

1,2

1,25

1,3

1,35

1,4

350

400

Fracture prognosis used for


planning of shallow penetration
gas well

Overburden gradient decreases with increasing water


depth

Fracture pressure governed by:

380m water depth

 Overburden stress

Good agreement between


prognosis and measured FIT

 Fluid barrier

Depth (m)

450

 Major contributor to the


success of the drilling operation

500

550

y
600

Summary and conclusions

Mud designed for strong mud


cake

Field data fits general model

Model presented to derive prognosis

Normalization method derived to adjust data for


arbitrary water depth

Key issues
3.6 General Fracturing Model

Important findings
 Overburden stress important
 Seabed penetration important as well

Overburden stress
y

In deepwater most overburden is water, leading to low


horizontal stress

This gives low fracture


pressure

Direct correlation between


LOT and water depth

A general fracturing model valid from land wells


to deepwater wells emerged from this

Seabed penetration
y

Using seabed reference by:


 Removing water pressure
 Removing water depth
 Led to a LOT correlation:

Normalization
y

Have data from Well 1. Prognose LOT for Well 2 by


normalizing to new water depth

Example 1
y

Well 1 is drilled in 400 m water, what is expected LOT if it drills

Equations
y

General equations:

Different but constant bulk densities:

Equal constant bulk densities:

Example 2
y

inn 1100 m water depth, assuming equal conditions?

Now we assume different bulk densities. Same data as in Example


1, except bulk densities are 2.05 sg and 1. 85 sg

 LOT1 = 1.5 sg at 900 m (RKB)

Solution, new depth: D2 = 900 + (1100-400)+(25-25) = 1600 m

Expected LOT at 1600 m:

Solution, new depth: D2 = 900 + (1100-400)+(25-25) = 1600 m

Expected LOT at 1600 m

Lower bulk density in well 2 leads to lower LOT

Field example
y

Well Design Premises

Well offshore Norway in water depth 1349 m:

Chapter 4

4.1 Well Integrity

4.1 Well Integrity


y

Full Well Integrity


 Required for Production Csg. Only
 Min. LOT to reach end open hole

Reduced Well Integrity


 All other Csg. strings (exept 30)
 Min. LOT to reach end open hole

Full well integrity

Reduced integrity
(Weak point below shoe)

Reduced integrity
(Weak point below wellhead)

 Max. LOT to ensure weak pt. below shoe


 Maximum kick size to ensure full integrity

4.1 Maximum LOT

4.2 Casing Setting Depth


y

Pressure Conditions

Shut-in Gas Filled Well

Wellhead Press. 200 bar =


Burst Strength Csg.

 Frac. Pressure at Shoe

Shoe Pressure 200 bar (2.02


s.g.)

 Pore Pressure Open Hole

If LOT>2.02 s.g. Weak point


wellhead.
UNACCEPTABLE

Operational Conditions
 Borehole Stability, Collapse Mud Loss
 Completion Conditions
 Drilling conditions, No. Of Bits/Trips

Example 1: Mud Weight

Casing size Depth Mud weight


(inch)
(m)
(s.g.)
7

2700

1.60

9 5/8

2400

1.60

13 3/8

1300

1.30

18 5/8

700

1.20

30

400

Sea water

Example 2: Riser Margin

Example 2: Riser Margin

Casing size Depth Mud weight


(inch)
(m)
(s.g.)

Example 3: Kick Criteria

Casing size Depth Mud weight


(inch)
(m)
(s.g.)

2700

1.69

2700

1.69

9 5/8

2400

1.69

9 5/8

2400

1.69

13 3/8

1700

1.40

13 3/8

1700

1.40

18 5/8

900

1.20

18 5/8

900

1.20

30

440

Sea water

30

440

Sea water

Summary, Csg. Seat Selection

4.3 Completion and Production


Requirements

Determine depth requirements from Mud


Weight (frac pressure and pore pressures)

Wellhead design pressure (i.e. 5000 psi)

Bullheading pressures

Determine operational factors based on


experience

Design alternatives

Determine riser margins on floaters

Only production csg. Need full integrity.

Use kick margin for other strings.

 Drilling only, or drilling and testing

Other effects
 Temperature
 Time
 Perforation, stimulation,

Temperature expansion

Temperature expansion

Burst Design
Casing Design
Chapter 5

Gas filled casing

Burst Design

Burst Design

Leaking tubing

Gas Filled Casing


 For all csgs. except 30 in. and production csg.

Leaking Tubing
 For production csg.

Maximum gas kick


 Max. vol. reservoir fluid without breaking
down shoe

Burst Design

Burst Design
y

Governed by tangential stress:


Pburst = 2Vtensilet/D

Vt

Ft
At

1 Di
P
2 t

Va

Fa
Aa

1 Di
P
4 t

Vt=2Va

Parameters: Vtensile and t/D

Use manufacturers data

Use equation for wear assessment

Burst Design

Kick Scenario

Casing wear

 Proportionality, Example:

 Conservative criterion

x Burst pressure: 419 bar


x Csg. wall worn from 8.92 to 5 mm

Gas filled casing


Leaking tubing
 For the production casing

Maximum gas kick


 For all casings except production casing
 Relates to csg. shoe strength

x Compute reduced burst strength

x Minimum LOT to reach next shoe


x Maximum LOT to ensure weak point at shoe
x Maximum influx volume

Collapse Design
y

More complicated than burst

Collapse design
y

Wear example: same as burst example

Collapse reduction from 169bar to 80

 Yield collapse, plastic collapse,


transitional collapse and elastic
collapse depend on t/D ratio

Elastic collapse:

bar appears unrealistic


y

Collapse criteria
 Mud losses to a thief zone
 Collapse during cementing

Collapse criteria
y

Thief zone

Tension design
y

Major design criteria:


 Weight of casing including buoyancy
 Casing stretch caused by pressure testing
while bumping cement plug

y
y

 Dynamic loads, difficult to assess


 Bending effects

During cementation

Temperature effects
y

Example of B-annulus pressure in Chapter 4.3.4

If temperature exceeds 80-100C (200F)

Yield strength reduces


 Tensile strength

Other criteria:

Bi-axial loading
y

From von Mises yield criterion:

Elliptic equation:

Combination collapse and tension

 Burst strength

leads to reduced strength

Other criteria
y

Common design criteria

Sour service
 Weight loss corrosion
 Hydrogen embrittlement (H2S)

Time scenario
 Exploration wells short life
 Production wells long life

Casing wear
 Wear and damage reduces well integrity

5.2 Casing test pressure


y

Requirements, casing must:

Pressure tests critical wells


y

Sometimes the casing is tested only in one end, e.g. at the


wellhead

Critical wells like HPHT wells may require testing of the


entire casing from top to bottom

Problem: Kick scenario assumes reservoir gas in annulus.


During testing the annulus is filled with mud.

Possible approaches:

 Be pressure tested for


expected loading
 Not exceed 90% of yield strength (SF=1.11)

Example surface casing and


deeper casing

 Bump plug during cementing - Assume pressure exceeding


saltwater behind casing - Set packer in the middle of the casing
and test both sides - Establish back pressure behind casing Evacuate upper part to seawater, example to follow

HPHT pressure test


y

Design basis:

HPHT pressure test


y

Test load with 1.9 sg mud in


well
 OK in top
 Overloaded at bottom

HPHT pressure test


y

Upper half displaced to


seawater

Test is unacceptable

HPHT pressure test


y

When displacing upper half


to seawater, always check for
casing collapse

Test is OK throughout
well

Introduction
5.3 Casing design example

y
y
y
y
y

Summary
y

Summary
Setting depth
Design basis
Casing design
Summary

Casing depths
y

Design basis
y

Describe all assumptions for each casing string

18-5/8 Casing design


y

 Collapse
 Burst
 tension,
 Cementation
 Wellbore stability
 Fluid densities
 Bullheading
 Wear and corrosion
 And so on.

18-5/8 Casing design


y

Collapse loading during


cementation:

18-5/8 Casing design


y

Summary
y

5.4 Fully 3D Well Design Improves

Results:

Margins in Critical Wells

Based on:
 Wateroutside
 Oil inside
 Chapter 6 will assume mud
outside and gas inside

Overview

Background

Uniaxial, biaxial and triaxial well design

Evolution of long, deep and hot wells

Conventional triaxial design

Design margins have become small

Fully three-dimensional well design

A need for an accurate model to calculate

Well examples

Conclusions

burst and collapse

Current technology

Uniaxial well design

Most well designs are based on one- and


two-dimensional mechanics

Recent design packages include a three-

stresses
y

dimensional model
y

Accurate only for certain conditions

Consider one of the three principal

Axial load design neglects pressure load


effects

Pressure load design neglects axial load


effects

Biaxial well design

Triaxial well design

Consider two of the three principal

Consider all three principal stresses

stresses

Combine these stresses to a single

Hoop and axial stresses dominate

Neglect radial stress

equivalent stress
y

Classical von Mises distortion energy


theory is used in the industry

Conventional triaxial design

Fully 3D well design

Simplifications give practical design method

For burst calculations, assume zero outside


pressure

For collapse calculations, assume zero inside

New dimensionless solution that include


all three principal stresses

Use actual pressures inside and outside


the pipe

pressure
y

Use pressure differentials instead of actual


inside and outside pressures

Dimensionless pipe analysis


y

3D yield surface

Group 1 (x) Inside pressure, axial stress, yield


strength

Group 2 (y) Inside pressure, outside pressure,


yield strength, diameter

Group 3 (z) Equivalent von Mises stress, yield


strength

z V y / V VME
y

Group 4 () Outside diameter, wall thickness


x ( pi  V a ) / V y

E ( pi  po ) / V y

2D design factors

Example cases

1.5

DF = 1.00
DF = 1.10
DF = 1.20
DF = 1.30

1.0

0.5

E ( pi  po ) / V y

HP/HT wells offshore Norway

Well 1 Subsea wellhead


- Pressure integrity of 10 x 9 production casing
- Two burst cases and one collapse case

0.0

-0.5

 Case 1
Case 2
S Case 3
Case 4

-1.0

Well 2 Platform
- Collapse of snubbing pipe during live well intervention

-1.5
-1.5

-1.0

-0.5

0.0

0.5

1.0

1.5

x ( pi  V a ) / V y

Pressure/load matrix

Case #1 Burst below wellhead

New 3D model
DF = 1.37
Conventional triaxial
model
DF = 1.36
Biaxial model
DF = 1.37
Uniaxial model
DF = 1.44

Case #2 Burst on top of packer

Case #3
Thief zone

New 3D model
DF = 1.10

New 3D model
DF = 2.14

Conventional triaxial model


DF = 1.06

Conventional triaxial model


DF = 2.14

Biaxial model
DF = 1.04

Biaxial model
DF = 2.04

Uniaxial model
DF = 1.17

Case #4
Snubbing

2D design factors
1.5

New 3D model
DF = 1.69

DF = 1.00
DF = 1.10
DF = 1.20
DF = 1.30

1.0

0.5

Conventional triaxial model


DF = 1.69
y

E ( pi  po ) / V y

0.0

Biaxial model
DF = 1.64
-0.5

Case 1
Case 2
S Case 3
Case 4

-1.0

-1.5
-1.5

-1.0

-0.5

0.0

x ( pi  V a ) / V y

0.5

1.0

1.5

Conclusions
y

6.6 Casing design


Conventional triaxial design for burst and

collapse is in error under certain


conditions
y

An accurate 3D model is developed

Improvement in design margins is


achieved using 3D model

24 Surface casing

Production casing

y
y
y

Collapse during cementation


 installation

Burst, gas filled casing next section


 Post installation

Integrity:
 Shoe weak, no kick margin, wellhead weak
point

2 Types of tubing
Temperature derating
Tieback and liner designs

Design summary

Important issues

These factors are most important







Reservoir pressure
Reservoir fluid density
Fracture pressure
Density of fluid behind casing

Assume gas inside


and mud outside

Content
6. Design of HPHT wells
-

The following subjects are covered:


 HPHT definitions
 Design premises
 Geomechanical design
 Mud weight design
 Production casing considerations
 Design of shallow casing strings
 Intermediate casing design
 Design of the production casing

HPHT Definitions
y

A HPHT well is:


 Temperature higher than 150 C (294F)
 Pressure exceeding 10 000 psi

Design premises
y

Objectives:
 Flow test Jurassic reservoir
 Drill through reservoir
 Core or samle data

1 of the above makes it HPHT

Well depth 5000 m but due to geological uncertainty, design depth is 5100 m

Consider sour service conditions

Two designs due to uncertinty of flow testing


 Integrated design. Well can handle both drilling and well test phases
 Separate drilling and testing. In the unlikely event of flow testing, install a tie-back casing.
This was chosen.

Casing alternatives
y

Prognosis

Alternatives

Most important design input

 1: No finds

Key HPHT problem, narrow


margin at top reservoir

Long openhole sections with


wellbore stability issues

Heavy production casing


requiring large drilling rig

2011 cost: 150 M$

 2: Run liner
 3. Flow test using tie-back
 4: Use liner too early
 5: Use contingency to reach target
 6: Flow test using tie-back casing

Geomechanic design
y

Shallow gas require careful placement of upper casing strings

Shall gas followed by losses below may give problems

Riserless preferable from this point of view

Geomechanic-Deep Fracturing
y

Detailed analysis of 70 HPHT wells

Based modeling on Compaction Model,


Modern Well Design page 62.

Established frac model

Problem is too much spread

Must consider groups of data


 LOT
 Pore pressure
 Overburden
 Depth
 Lithology

LOT vs Pore pressure


y

Trend: High LOT high Po


Low LOT low Po

We will in the following


normalize all LOTs to a
pore pressure of 1.8 sg

Resulting Frac Model

Stress regimes

Resulting frac prognosis

Stress regimes in Central Graben

Frac from LOT data

Resulting frac model

Lost circulation from daily


drilling reports during loss
events

y
y

Process repeated

Large uncertainty below 4700


m, design must assume worst
case

Tiny pressure window the


largest challenge

Approximately 50% of total


time spent in reservoir

for circulation
loss data

Mud weight design


y

Drilling problems Well A

MW design cont.
y

Many drilling problems in


Well B

3 sidetracks in the 17-1/2


section

MW gradually increased to
above median-line

Compare Drilling problems with


median-line.

Too low MW in top of well?

MW design cont.
y

Few drilling problems in Well C

MW selection
y

MW criteria
 Top hole lower than median-line
(ML) because of weak csg. shoes
 1000 3000 m, approx. ML

 Bottom lower than ML because:

MW roughly around median-

x Need to tag pore pressure to

line
y

seaarch for production csg. Seat

Well was reasonably well

x Accept som collapse in chalk


x Increase MW gradually to
minimize tight hole

Production casing considerations


y

Setting point critical

Dont know what is below

If losses, must use contingency


liners

Operational strategy:
 Perform LOTs
 Kick simulation tools
 Drillability analysis
 Careful hydraulic monitoring

Casing Setting Depths


y

7.1 Wellheads
Chapter 7
Drilling Operations and Well Issues

7.2 The 36 in. hole and the 30 in.

The 26 in. hole and the 20 in. surface

conductor casing
Operation:
Set anchors and pretension
Ballast rig down.Make up BHA no. 1 and 1300 m drillpipe

casing

Hours used:
24
20

Stab into well


Drill 50 m of 36 in hole
Circulate hole clean
Perform wiper trip
Displace to hivis mud, pull back to mudline
Position rig using thrusters
Rig up for running 30 in conductor
Make up 3,5 in cement stinger and run in hole
Run in 30 in. conductor
Circulate and cement 30 in., wait on cement
Pull out cement tools and drillpipe
Position rig using thrusters

1,3
9
2
1
2

Total hours

32

0,5
2
6
4
4
0

Operation:
Pull out and rack 36 in BHA
Break down 36 in BHA
Pull out and rack cement head in derrick
Make up 26 in BHA and run to template
Position rig w/thrusters, stab in and run to shoe
Drill 150 m of 26 in hole
Circulate hole clean
Wiper trip, run to bottom and displace to hivis mud
Pull out to seabed
Pull to surface and rack pipes
Position rig using thrusters
Rig up and run 145 m 20 in casing
Circulate and cement 20 in csg.
Release running tool and pull out of hole
Total hours:

Hours used :
1
1
1
1,5
1
12
3
4
2
4
12
4
2
49

The 17.5 in. hole and the 13-3/8 in.


intermediate casing
Running BOP
Operation:
Position rig using thrusters
Rig up for running BOP stack
Run marine riser and BOP
Land BOP
Rig down riser handling equipment
Prepare test plug for running in the hole
Run in hole with test plug
Test connector
Test BOP
Pull out BOP test tool
Lay down test tool

Hours used:
4
16
4
4
0,5
3
1
3
3
0,5

Total hours:

39

Operation:
Make up 17,5 in BHA
Run in hole with BHA
Drill 20 in cement, plugs and shoetrack
Circulate contaminated mud and perform
Pick up drillpipe
Drill 700 m of directional 17,5 in hole.
Circulate hole clean, wiper trip, pull out of hole
Run log
Rig up for running of 13-3/8 in. casing
Set back cementing head, retrieve seat protector
Run 500 m of 13-3/8 in casing
Circulate and cement 13-3/8 in casing
Set seal assembly and pressure test
Perform BOP test and pull out
Run and set 13-3/8 in wear bushing
Lay down 17-1/2 in BHA
Service cement head

Hours used:
3
3
3
2
1
24
10
8
3
6
10
3
1
6
6
3
1

Total hours:

93

The 12,25 in. hole and the 9-5/8 in.


production casing
Operation:
Make up 12,25 in. BHA
Run in hole to 900 m
Drill 1100 m of 12,25 in hole
Circulate, wipertrip, circulate
Pull out and rack 12,25 in. BHA
Lay out 12,25 in BHA
Retrieve wear bushing
Rig up for running 9-5/8 in casing
Run in 680 m of 9-5/8 in casing
Circulate and cement casing, pressure test.
Set and test seal assembly
Pull out of well
Run in wear bushing. Temporary P/A. Establish barrier
Disconnect and secure BOP
Total hours:

Wellhead

Hours used:
4
6
86
8
5
2
6
3
14
6
1
3
4
8
156

Operation:
Pull marine riser and BOP
Prepare for X-mas tree running
Run and install X-mas tree
Pull running tool
Run marine riser and BOP
Position and latch
Total hours:

Hours used:
8
8
24
4
9
2
55

Install Lower Completion

The 8.5 in. hole through the reservoir


Operation:
Make up drillcollars and heavy weight drillpipe
Pick up and make 8,5 in BHA
Run in hole to 800 m
Drill composite bridge plug
Run in hole to 810 m
Drill shoe, circulate, perform FIT
Drill 1000 m horizontal section

Hours used:
4
6
7
2
6
12
160

Total hours:

197

Operation:
Clear rig floor
Make up scraper and magnet assy.
Pick up heavy weight drill pipe
Make scraper run
Rig up tubing tongs
Make up wirewrap screens, blanks and swellpackers
Install screen packer/hanger and running tool
Rig down tubing tongs
Run screens on drill pipe
Drop ball, pump down and set packer
Test packer from above
Release running tool and flowcheck
Displace well above packer to brine
Pull out and lay down running tool
Make up anchor packer assy.
Run in assembly on drill pipe
Orient and set anchor packer
Pull out and lay down running tool

Hours used:
0,8
1,6
12
18,9
3,1
27,2
1,6
0,8
15,7
3,1
1,6
1,6
0
7,9
4,7
15,7
1,6
7,9

Total hours:

126

Install Upper Completion


Start well for production
Operation:
Pull bore protector
Install lateral zone assemblies
Splice and terminate el. cable
Make up main completion assembly
Run in 5,5 in. tubing
Install TRSCSSV, splice cables
Run in 5,5 in tubing
Make up tubing hanger
Make up THRT and STT??
Run in on WOR??
Install lifting frame, flow head
Land and lock tubing hanger, test seals
Drop ball, press. Tubing, set and test packer
Close TRSCSSV, inflow test,equalize and open
Rig up wirelin, pull packer setting plug
Pull plug
Press. Up annulus and test packer from above
Total hours:

Hours used:
3,1
7,9
15,7
6,3
29,9
6,3
1,9
6,3
6,3
18,9
9,4
1,6
3,1
1,6
12,6
3,1
1,6
136

Operation:
Prepare rig for well flow
Displace WOR to nitrogen
Flow out brine and mud and oil
Bullhead tubing with diesel and wax inhibitor
Displace WOR to brine
Close TRSCSSV
Install tubing head crown plug and test on wireline
Close HXT valves and test
Remove and lay-out WOR, SST etc.
Install tree cap, test, pull and lay down running tool
Pull BOP and marine riser
Install corrosion cap
Deballast and prepare to move rig
Total hours:

Hours used:
3,1
9,4
12,6
3,1
3,1
0,8
12,6
3,1
12,6
9,4
15,7
6
6,3
98

7.3 Torque and Drag in 3D


y

Dogleg

Summary of well construction time


Operation:
36 in. hole
26 in. hole
Running BOP
17,5 in hole
12,25 in. hole
Wellhead
8,5 in. hole
Lower completion
Upper completion
Start well

Hours used:

Total hours:

cos T sin D 1 sin D 2 cos I1  I 2  cos D 1 cos D 2

Percent time:
32
49
39
93
156
55
197
126
136
98

3.3
5
4
9.5
15.9
5.6
20
12.8
13.9
10

981
40,9 days

100%

180
T rad
S

DL( $ )

D2
I2 2

T T

D1
I1

Friction vs. geometry


y

2D Example

Straight sections

500

1000

1500

Horizontal
Re ach ( m)

F2

F1  E'Lw^cos D r P sin D`

PrE w'L sin D

Curved sections
F2

F1e

335

170
45q

455

500

45q

1000

r P T 2  T1

sin D 2  sin D1
 E w'L

D 2  D1

PrN PrF1 T2  T1

13
08

1380

1500
1661

Depth (m)

45q
170

286kN

2D Results

2D Results
Torque (kNm )

Table7.1:Forcesinthedrillstring duringhoistingandlowering

Torque

Static weight(kN)

Hoisting (kN)

( kNm )

10

Lowering(kN)

10

20

20

500
500

15 . 54

1000

491 . 1

641 . 4

840 . 3

13 15.54 22

Force ( kN )

Position

Without
Bit Torque

1000

90kN

641.4

Force (kN )

With
Bit Torque

Vertical

Vertical

Well Bottom

286

286

286

335
335

Build-Up
455

Build-Up

Bottom dropoff section


Bottom sail section
Top sail section
Top buildup section
Top well

286+0.237x120=
286+28.4=314.4

286x1.17+28.4=363

314.4+0.237x925=
=314.4+219.2=533.6

363+0.237x1308(cos 45+0.20sin45)=626

272.9+0.237x1308(cos 45-0.20sin45)=448.3

533.6+0.237x120=
533.6+28.4=562

626x1.17+28.4=760.9

448.3x0.855+28.4=411.7

562+0.237x335=
562+79.4=641.4

760.9+79.4=840.3

411.7+79.4=491.1

500

455

500

Static Weight (Off-Bottom)

286x0.855+28.4=272.9

Hoisting

Torque

Static Weight (On-Bottom)

Static

Straight
Inclined

1000

Straight
Inclined

Off
Bottom

1000

Lowering

1380

1380

Drop-Off

1500

Drop-Off

1500

BHA
Vertical

1661

BHA
Vertical

1661

WOB

TOB 9kNm

Depth ( m )

Depth (m )

3D Example

3D Results
Torque ( kNm )

0
0

10

20
13 . 5

463

500

1000
576

StaticTorq ue

768

Lowering

Static

Pure
Lowering

Build-up

Build-up
with
Right Side Bend

Build-up
with
Left Side Bend

3000

40

2000

1512

1752
73

2063
2104

Build-up

Build-up
with
Right Side Bend

2075
Build-up
with
Left Side Bend

Straight Inclined
BHA

2865

1052
25

Pure
Hoisting

Straight Inclined

1700

3000

Force (kN )

Combined
Hoisting

1100

2075

2865

768

1000
Straight Inclined

500

1000
661

StaticWeight

Hoisting

1100

1700

513 576

Vertical
Combined
Lowering

500

1000

2000

463

Vertical

500

500

0
Force ( kN )

MD ( m )

MD (m)

Straight Inclined
BHA

Friction Analysis for LongReach Wells

This presentation
y

Introduction

Analytical models for torque and drag

Field case

Friction analysis for ultra-long wells

Summary

Introduction

Analytical models for torque and drag

Significance of well friction

Basic model: Coulomb friction


Linear hole sections

Numerical simulators:
 Availability
 Limitations

Closed form models:


 Increase availability
 Analytical approach

Drag:
Torque:

F2 = F1 + w's(cosD r PsinD)
T = Pw'srsinD

Analytical models for torque and drag

Analytical models for torque and drag

Drop-off section

Modified catenary profile


Forces:
6Fx = 0
6Fz = 0

Results:
Well path coordinates:
F1 sin D1
w

Tension during hoisting:


F2

F1e

P (D 2 D1 )

wR

1 P 2

P D 2 D1
2
sin D1 )
(1  P )(sin D 2  e

P D 2 D1
2
P
(cos
D
cos D1 )


e
2

F1 e

 P D 2 D1

 wR sin D  e  P D 2 D1 sin D


2
1

P r ^F1  wR sin D1` D 2 D1  P rwR cos D 2  cos D1

ws  F1 cos D1

F1 sin D1

Torque:

ws  F1 cos D1

F1 sin D1

P r 'F tan 1

'Tcat
Note: Entrance condition to modified catenary

Analytical models for torque and drag

P'F tan 1

'Fcat

Torque:
T

wx

F1
 sinh 1 cot D1  cos D1
sin D1 sinh
w

F1 sin D1

Deviation from ideal


tension: 'F
Drag:

Tension during lowering:


F2

wx

 sinh 1 cot D1  cosh ^sinh 1 cot D1 `


cosh
F1 sin D1

Analytical models for torque and drag


Combied rotation and axial movement

Side bend
Tension:
F2



1
1 wR e 2 1
2
r P I I
F1  F12  wR e 2 1 
2
2 F  F 2  wR 2
1
1
2

# P I I

Torque:
T

Pr F12  wR 2 I2  I1


a) Drag and torque for a pipe.
b) Combined friction from rotation
and axial movement.
T
r

 F2

P w's

Analytical models for torque and


drag

Analytical models for torque and drag


Downhole motor torque
Bit power during rotary drilling:
Bit power with downhole motor:
Protary

CTrotary nrotary

Pmotor

CTmotor nmotor

Assuming equal power, the torque relation is:


Tmotor

nrotary
nmotor

Application:
Trotary

Split the well into geometries:


e.g.

This is the gearbox principle.


Downhole motor may significantly reduce bit torque.

vertical section
-

Analytical models for torque and


drag
Applications:
3-Dimensional well path.

Total solution:

straight section bottom


build-up section

Adding the equations for these geo metries gives total torque and drag

Field case
Long-reach well in the Yme field:
Depth: 2950 mTVD top reservoir
3100 mTVD total depth

Drag:

Drag:
F2

F22 build_or_drop  F22sidebend

Torque:
T= 6 T from bottom to top

Torque:
F2

Horizontal reach: 7528 m

F=6 F2 from bottom to top

T build_or_drop  T sidebend
2

Rig limitations:
Hoist:

4540 kN (1.mill. lbs)

Top drive:

35 kNm (25.800 lb-ft)

Field case

Field case

Well profile investigated

Results
Hoist
Well
Profile

Top-drive:

Static hook Pick-up


load (kN) load (kN)

Modified
catenary
Minimum
dog-leg
Undersection
Standard

Slack-off
load (kNm)

845

1360

593

843

1332

609

842

1321

568

858

1350

543

Well
Profile
Modified
catenary
Minimum
dog-leg
Undersection
Standard

Surface
Torque build-up Torque
torque (kNm) bnd (kNm)D
hold
28.57

7,11

21,46

30.91

11,04

19,87

29.51

6,88

22,63

30.42

9,05

21,37

Conclutions:

Friction analysis for ultra long wells


Example: Prolong Yme well to a horizontal reach of 12 km

Drill string tension not critical

Torque limiting element

Modified catenary profile best

Summary
y

Analytical expression for torque and drag are derived in this paper.

The models are valid for straight sections, build-up, drop-off and side
bends.

Equations for geometry and torque and drag for a modified catenary
profile is also given.

Torque and drag analysis can be performed by adding equations for each
hole section.

A field case from Yme demonstrates the application. A modified catenary


profile was chosen to minimize torque.

An ultra-long well was studied with the models. By using light-weight drill
pipe in the sail section a 12 km(or longer) well can be drilled with existing
rig equipment.

Dominating limiting parameters:

Conclusions:
Well can be drilled if light drill pipe
is used in the sail section
Tension allowable for all cases
Torque limiting factor
Other elements within permissible
limits, like hydraulics, hole cleaning,
borehole stability,

Results
Drillpipe
Pulling
Steel
Titanium
Composite

179
133
102

Hook load(kN)
Static
Lowering
175
130
101

60
60
60

Build-up
10,2
6,2
3,7

Torque(kNm)
Hold
Total
section
43.7
53.9
26,90
33.1
16.0
19,70

 Friction
 Drill pipe weight
 Mud density

7.4 Stuck pipe in deviated


wellbores

Friction analysis for ultra-long wells


y

Guidelines to obtain a low-friction well:

 High inclination in the sail section.


 Minimum weight BHA.
 Heaviest DP in top of string.
 Select modified catenary or another profile.
 Minimizing dog-leg and tortuosity.
 Downhole motor reduce torque.
 Reduce friction by:
x Low DP weight
x Small tool joint
x Self-lubricant matrix.

Content

Introduction

y
y
y
y
y
y
y

Introduction
Industry practice
Deviated wells and friction
Depth to stuck point
Field case
Methods to free pipe
Final comments

Two most costly drilling problems:


 Circulation losses
 Stuck pipe

Causes high economic risk for long wells


 Sidetrack often consequence

Operational aspects important


 Often stuck after static period

Industry practice
y
y
y

If stuck drillstring, apply pull test


Alternatively, run free point indicator
Pull test estimate free pipe length from
elongation
 Current models neglects well friction
 Therefore strictly applicable for vertical wells
only

Deviated wells and friction


y

This analysis valid for differential sticking


 Differential pressure
 Area exposed
 Permeable formation

Friction in curved bends and


straight inclined sections

Depth to stuck point


Depth to stuck point,
vertical well

Field case
y

DP stuck in long deviated well

Friction coefficient causes uncertainty

Results:

Depth to stuck point,


deviated well(vertical, build, sail)

 Frictionless:

5097 m

 New model:

5693 m

 Torsion test:

5675 m

Torsion is independent of friction as


pipe is not pulled

Torsion test
y

Torsion test should be included in rig


procedures

Methods to free pipe


y

Maximum mechanical force

Final comments
y

differential pressure wellbore/formation is the critical element.

 Pull/twist DP towards limit


y

Minimum density method


 Displace well to minimum density mud to reduce
bottomhole pressure. Also reduces buoyancy

This analysis is valid for cases with differential sticking. The

If the string is mechanically stuck, the differential pressure is no


longer a factor. For this case reducing MW has no positive effect.
We recommend that the Maximum Mechanical Force method, the

Maximum buoyancy method

Maximum Buoyancy method and the Torsion method to be used

 Displace DP to seawater. Buoyancy increases giveing higher pull margin

here.

Results:

This presentation

7.5 Well-Integrity Issues


Offshore Norway

Birgit Vignes, Petroleum Safety Authority Norway


Bernt S. Aadnoy, Univ. of Stavanger
Paper IADC/SPE 112535 presented at the 2008
IADC/SPE Drilling Conference, Orlando

1. Introduction of the pilot well integrity study


2. Regulation and standards
3. Results of the study
4. Examples of well failures
5. Continued work in 2008
Summary

1. Introduction - Background for the survey

Several well integrity incidents


Several shortfalls
Missing critical information
Insufficient openness and access to well-data
Competence issues
Well conversions
Varying management of changes

1. Introduction - Well Categorization


Scope: How comprehensive is the
well integrity problem on the NCS,
and what are the main issues/ challenges?
Selection of wells for pilot examination
What kind of barrier/
Yes
barrier element
failure/ issue/ uncertainty ?

The Primary Well Barrier is the first object to prevent


unintentional flow from the source
The Secondary Well Barrier prevents further
unintentional flow if the primary well barrier should fail

Well barrier
intact

(or uncertainty)

Yes

No

Impact?

Yes

Shut in well ?

No

Cat. B:

Well is
shut In,

Working
under

Cat. C:

E.g.: Leaks, conditions/


over criteria, exemptions
well contr., E.g.: No gas lift

Insignificant
deviation
for current
operation

Cat. F:
Cat.G:
Cat. E:
Shut in
Shut in
Shut in
because of
while
on the
E.g.:
topsides
awaiting
basis of
weather
P&A
reservoar bottlenecks,
conditions,
planned
related
other
testing and
issues
activities,
union dispute, E.g.: high maintenance
water cut
Incl.: SD&P
Cat. D:
External
conditions

3. Results - Wells with integrity issues


18% of 406 the assessed production- and injection wells were reported to have well
integrity failures/ shortfalls or uncertainty.
We lls with inte grity failure , issue or unce rtanty

Ref: Activities Regulation 76 w/ref. to NORSOK D010


80
Number of wells

70

Primary Well Barrier


Secondary Well Barrier

75

60
50
40
30

48

20
10

27

Production

Source

Common production well


with the 2 barrier envelopes

Injection

Total

P roduct ion, inject ion and t ot al

Well issues are related to 33% of the injectors, and 15% of the producers.
Ref. Swiss cheese
model

Well
OK /
active

Cat. A:

Determine injury/ damage/


production impact/
financial loss

2. Regulation and standards

No

Well integrity
failure / issue ?

3. Results Well integrity impact

3. Results - Well integrity issues by age

Well integrity impact

Well integrity failure/issue distribution by well age, per 1.3.2006

25

Number of wells

20
22
15

18

Producer

16

Injector

10
10
8

Number of wells with failure/issue

30
25
26
20
24
15
16
10
5

6
1

0 to 4

A: Shut in

B: Working under
conditions

C: Insignificant deviattion
for current operations

5 to 9

10 to 14

15 to 19

20 to 24

25 to 29

Age in years

Well integrity impact category A, B and C

The frequency of wells with integrity issues in age group 0-14 years is twice as
high as for well group 15-29 years.
WAG wells and recently optimized well design have caused challenges
P&A wells are not included in this survey

7% wells were shut in


9% wells were working under conditions/exemptions
2% wells had an insignificant deviation for current operations

3. Results - Well barrier element

3. Results - Areas for improvement:

Num ber of w ells w ith w ell integrity problem

9
4

8
4

W
el
lh
ea
d
D
C H
on S
V
du
ct
or
AS
Tu V
bi
ng
G
LV
C
as
C ing
em
e
Pa n t
ck
C
he P
e
m ac r
i ca k
o
l i ff
nj
.l
in
Fl T R e
ui
S
d
ba V
rr
D ier
e
Fo sig
rm n
at
io
n

Number of wells

29

C a t e r or y ba r r i e r e l e me nt f a i l ur e

35
30
25
20
15
10
5
0

Areas of high priority: Well documentation


Handover documentation
Regular monitoring
Competence and training

4. Example I: Surface Casing collapsed


Event:
18-5/8 csg. broke due to
corrosion
Wellhead dropped 44 cm
Platform structure
arrested further drop,
reducing the damage
potential

Reasons:
Cement return port left
open
Fresh seawater and tide
caused severe corrosion
in splash zone

Event:
Casing and tubing hanger
and running tool failed
during operations
Overloaded during
pressure testing

Consequences:
Platform production
stopped
High cost of event
Initiated monitoring
program

4. Example III: Lost wellbore


Events:
Severe lost circulation
Plugged drill pipe
Wellcontrol problem
Open well in periods

4. Example II: Production Casing Failure

Reasons:
Depleted reservoirs
Gunk pill plugged off DP
Less good operational
decisions
Consequences:
Sidetracked well
High cost
Improved procedures

Reasons:
Hangers uprated 50%
Manufacturers up-rating
failed
Accepted uprating as OK
Poor equipment design
Consequences:
Cost of well problems
Many installations, cannot
replace
Reduce max. allowable
loading

4. Example IV: Gas Leaks in Tubings


Events:
Leaks in prod. tubings in
14 wells

Reasons:
Leaks in PBR
Corrosion
Consequences:
Increased monitoring
Constraints for availability
and flexibility

4. Example V: Production Casing Failure


Events:
Prod. csg. and tubing
collapsed
Well control incident
during repair operation

Reasons:
Wrong csg. joint installed
Leaks through PBR
Uncertain pressure
integrity of well
Consequences:
High cost
Clarify well integrity
Improve workover
procedures

5. Continued work in 2008


Industry:
Operators studies confirm PSA 2006 results
OLF workshop initiative and founding of operators well integrity forum (WIF)
Operators increased focus on well integrity issues and personnel competance
Profile issue in Risk Level Project (KPIs & healthy wells)
International Authorities:
Information and documents requested in PSA 2006 study and auditing of
operators
Information to NOPSA (Australia) in meetings with PSA and Statoil
Cooperation with SSM (Netherlands) 2007-2008 with similar approach as PSA
2006
PSA:
Well integrity meeting and auditing of Marathon Norway in June 2007
Well integrity challenges of CO2-injection to be studied by SINTEF
Survey of temporary abandoned wells incl. well barrier schematic
Well integrity issues related to GLV & ASV to be discussed with industry during
2008

Summary

The wells were a representative selection


A high number of well-related failures and shortfalls
18 % of the wells had well integrity issues or uncertainty
7 % of the wells were shut in
The barrier issues are within tubing, ASV, casing and cement
The impairments represents a high potential for HSE
improvement
Examples of well failures presented

EXTRA VIEWGRAPHS

Initial Questionnaire for PSAs survey


A.
B.
C.
D.
E.
F.
G.
H.

I.
J.
K.

Is the well picture/ outcome of the XLS- forms representing the typical situation
on the facility ?
Are key design premises, well history and current technical condition validated
and easy accessible for key personnel?
Does hand-over documents include sufficient well data with premises/ limits,
including updated schematics, exposures, technical condition and changes/
deviations/ precautions with regard to well integrity and well control issues?
Are there established technical requirements to well barrier envelopes /elements,
regular condition monitoring, and systematic management of well integrity issues
?
Are the company requirements for well barriers consistent with Norsok D-010 ?
Is there a consistent practise within the company for managing well integrity
issues?
Are management of change and non-conformance handling consistently practised
?
Are requirements to competence and training defined and implemented for
common understanding of the well barrier concept, barrier performance
requirements, records assurance, and actions required upon indications of
failures ?
How is openness and reporting of undesirable well incident encouraged, including
exchange of experience internally and externally ?
Any specific performance indicators pertaining to well integrity ?
Other issues relating to the subject

Você também pode gostar