EPC for Rumaitha/Shanayel Facilities-Phase III

ADCO PROJECT No. P44010


ADCO CONTRACT No. 15678.01/EC 10884
DOCUMENT / DRAWING COMMENTS RESOLUTION SHEET

GS Transmittal Reference

Date

Honeywell Transmittal Reference

Date

T-GS-HW-P44010-0110

12-OCT-2015

T-HW-GS-P44010-0078

03-MAR-2016

Document / Drawing

Document / Drawing Number

HVAC Calculation-OSBL

44-21-39-3602_Rev.2

COMMENTS RESOLUTION SHEET


Serial No.

Page No./
Sheet No.

Honeywell / HISCO RESPONSE /


JUSTIFICATION

DS COMMENTS

Dodsal Comments
1

as per HVAC design basis these


factors and noise level all are
required and need to maintained
within specified value

Substaion or ITR?

Complied.

U factor calculation to be demonstrated for


wall,roof
sections and material of construction

Refer to Attachment #2.

1/1

Refer to Attachment #1.

REMARKS/STATUS

EPC for Rumaitha/Shanayel Facilities-Phase III


ADCO PROJECT No. P44010
ADCO CONTRACT No. 15678.01/EC 10884
DOCUMENT / DRAWING COMMENTS RESOLUTION SHEET
Attachment #1.
(Refer to 44-21-40-3601 HVAC System Data Sheet and Catalog OSBL)

1/1

EPC for Rumaitha/Shanayel Facilities-Phase III


ADCO PROJECT No. P44010
ADCO CONTRACT No. 15678.01/EC 10884
DOCUMENT / DRAWING COMMENTS RESOLUTION SHEET
Attachment #2.

1/1

RUMAITHA/SHANAYEL FACILITIES - PHASE III


ADCO Contract No. : 15678.01 / EC 10884
ADCO Project No. : P44010

HVAC CALCULATION - OSBL

CODE

DESCRIPTION & INSTRUCTIONS

APPROVED WITHOUT COMMENTS


VENDOR TO SUBMIT FOR FINAL

APPROVED WITH COMMENTS


VENDOR TO AMEND AND SUBMIT FOR FINAL

SIGN

APPROVED WITH COMMENTS


VENDOR TO AMEND AND
RE-SUBMIT FOR APPROVAL
NOT REVIEWED/CONSIDERED
UNACCEPTABLE QUALITY
VENDOR TO RE-SUBMIT FOR APPROVAL

3
4

03.MAR.2016

JS Lee

SS Moon

MS Kim

Issued for Final

09.SEP.2015

JS Lee

SS Moon

MS Kim

Issued for Final

05.JUN.2015

JS Lee

SS Moon

MS Kim

Issued for Approval

REV.

DATE

ORIGINATOR

REVIEWED

APPROVED

DESCRIPTION

THIS DOCUMENT IS INTENDED FOR USE BY ADCO AND ITS NOMINATED CONSULTANTS, CONTRACTORS, MANUFACTURERS AND
SUPPLIERS.

EQUIPMENT / ITEM NO.: Integrated Control and Safety System(ICSS)


CONTRACTOR: THE CONSORTIUM OF

VENDOR / SUB-CONTRACTOR:

ADCO DOC. No. 44-21-39-3602


ORIGINATOR No.
44-21-39-3602

PAGE 1 of 11
ADCO Project
No. P44010

Rev. 2

Date : 03.MAR.2016

DATE

RUMAITHA/SHANAYEL FACILITIES - PHASE III


HVAC CALCULATIONS -OSBL

Rev. 2

WARNING: Unauthorized use and misappropriation of this material is strictly prohibited. This material /
document contain Honeywell confidential information. You are hereby notified that any dissemination,
distribution of copying which amounts to misappropriation of this material, is strictly prohibited. If you have
received this material/document in error, please notify us immediately, and return the original
material/document without making any copies to us at:
Honeywell Co., Ltd.
HPS Project Operation,
4F, Sangam IT Tower B4-4Block 1590, DMC Sangam-Dong, Mapo-gu, Seoul, 121-835, Korea
Tel: +82-2-2129-7150.

Revision Status
Rev.

Description of Change

Date

Status

Prepared By

Issue for Approval

05 JUN 2015

J.S Lee

Issue for Final

09 SEP 2015

Lee. JunSeok

Issue for Final

03 MAR 2016

Lee. JunSeok

Honeywell Checked By :
SoonSic, Moon

Signed :

Date :
03 MAR 2015

Honeywell Approved By :
Kim, MyoungSoo

Signed :

Date :
03 MAR 2015

Doc. No. : 44-21-39-3602

Page 2 of 11

RUMAITHA/SHANAYEL FACILITIES - PHASE III


HVAC CALCULATIONS -OSBL

Rev. 2

TABLE OF CONTENT
1

General
1.1 Purpose
1.2 Reference Document

Description and System Operation of Air Conditioning System

Design Criteria
3.1 External Conditions
3.2 Indoor Conditions
3.3 Heat Dissipation & Safety factor

Air Conditioning System : Dimensioning

Selection of Air Conditioning Equipment

Doc. No. : 44-21-39-3602

Page 3 of 11

RUMAITHA/SHANAYEL FACILITIES - PHASE III


HVAC CALCULATIONS -OSBL

Rev. 2

General
1.1

Purpose
This specification is to define the basic engineering design data for use in the HVAC
system of the ITR of the Phase lll Development Project in Shanayel, comprising the general
requirements to be complied with in the project and a descriptive system.
The air conditioning systems are intended to ensure appropriate conditions for occupants
and equipment, through the cooling indoor air.

1.2

Reference Document
JOB Specification
30.99.53.2601_SPECIFICATION FOR ETR / ITR SKID_Rev.1
30.99.91.1685_HVAC DESIGN BASIS_RevE
Vendor Document
44-21-40-3601_HVAC SYSTEM DATA SHEET AND CATALOG OSBL
65-21-50-3603_HVAC LAYOUT DRAWINGS OSBL
65-21-50-3604_HVAC DETAIL DRAWINGS OSBL

Description and System Operation of Air Conditioning System


It is about an installation designed to cool the air with operation 24 hours per day, in an ITR.
The system will consist of single packaged air ACCU with high-capacity, mini split type, two
effective and two redundant. They will attend the entire area of the ITR.
It will be used as refrigerant R-410A and equipment operation will be cooling only. The ACCU
will be air-cooled, with direct expansion and will have a redundancy level (2x50%). The ACCU
will be installed internally on an appropriate basis. The air conditioning system will have a local
control panel.
The temperature control will be performed by a remote controller, with signals from temperature
sensors installed in the environment.
The HCP will provide the power control and the automation control of the ACCU. In case of fire
accident, the HVAC systems will automatically turn off. The actuation of the smoke detectors
shall result the HVAC operation in recirculation mode.

Design Criteria
Humidity, Over Pressure and Fresh air flow are not requirement for the ITR.
3.1

External Conditions
Design temperature

Doc. No. : 44-21-39-3602

Page 4 of 11

RUMAITHA/SHANAYEL FACILITIES - PHASE III


HVAC CALCULATIONS -OSBL

Rev. 2

Summer :

48 db / 30 wb

Winter :

6 db HR 90%

Outdoor daily range :

15

Summer ambient temperature for selection of external units : 52

The HVAC equipment will be selected to provide a down grated cooling capacity at maximum
outdoor dry bulb temperature (DBT) of 46 on condenser side.
3.2

Indoor Conditions
Design temperature

3.3

Summer required temperature :

25

Winter required temperature :

20

Heat Dissipation & Safety Factor


The calculation of the heat dissipation and the overall balance for the ITR will be done
taking into account :
44-21-40-3610_POWER CONSUMPTION & HEAT DISSIPATION OSBL_RevD ;
Latent and sensible heat gains due to people (0 people per ITR) ;
External heat losses due to Solar radiations, walls, ceiling and floor transmissions ;
Additionally, the cooling load calculation includes a 15% safety factor.

Doc. No. : 44-21-39-3602

Page 5 of 11

RUMAITHA/SHANAYEL FACILITIES - PHASE III


HVAC CALCULATIONS -OSBL

Rev. 2

Air Conditioning System : Dimensioning


To the air conditioning Dimensioning it was used the program Hourly Analysis Program v4.51
from Carrier.

Doc. No. : 44-21-39-3602

Page 6 of 11

RUMAITHA/SHANAYEL FACILITIES - PHASE III


HVAC CALCULATIONS -OSBL

Rev. 2

Zone Sizing Summary for Cluster for Shanayel

Doc. No. : 44-21-39-3602

Page 7 of 11

RUMAITHA/SHANAYEL FACILITIES - PHASE III


HVAC CALCULATIONS -OSBL

Rev. 2

Air System Design Load for Cluster for Shanayel

Doc. No. : 44-21-39-3602

Page 8 of 11

RUMAITHA/SHANAYEL FACILITIES - PHASE III


HVAC CALCULATIONS -OSBL

Rev. 2

Input Data for Cluster for Rumaitha

Doc. No. : 44-21-39-3602

Page 9 of 11

RUMAITHA/SHANAYEL FACILITIES - PHASE III


HVAC CALCULATIONS -OSBL

Rev. 2

Space Input Data for Cluster for Rumaitha

Doc. No. : 44-21-39-3602

Page 10 of 11

RUMAITHA/SHANAYEL FACILITIES - PHASE III


HVAC CALCULATIONS -OSBL

Rev. 2

Selection of Air Conditioning Equipment


The air conditioning units were selected based on heat dissipation calculation above.
More information about the equipment can be find in the data sheet.
(44-21-40-3601_HVAC SYSTEM DATA SHEET AND CATALOG OSBL_Rev.1)
Equipment Features
Supplier

YORK by Johnson Control

Model

Refer to Doc. No. 44-21-40-3601

Type

PACU Direct Expansion Cooling only

Heat Exchanger

Cross Fin Coil

Compressor Type

Inverter Rotary

Refrigerant

R410-A

Doc. No. : 44-21-39-3602

Page 11 of 11