Você está na página 1de 29

Bengaluru Water Supply and

Sewerage Boards Wastewater


Management

B
B
M
P

K
E
Y

M
A
P

BWSSB Service Area 800.00 Sq.Km


BWSSB Service Area 800.29 Sq.Km

Yelahanka

Core area 245 Sq. Km


8 ULB
330 Sq. Km
110 Villages 225 Sq. Km

Byatrayanpura
K.R. Puram
Dasarahalli

Core Area

Kengeri
Mahadevapura

R.R. Nagar
Bommanahalli

Wastewater Generation Scenario


Bengaluru is supplied with 1400 MLD of water from

Cauvery River and approximately 250MLD water is


augmented from public/private Borewells.
80% of the water supplied will convert in to
wastewater i.e. 1650 x 0.80 = 1320 MLD
Out of which
Approximately 528 MLD (40%) will flow in V Valley
Approximately 528 MLD (40%) will flow in K & C Valley
Approximately 264 MLD (20%) will flow in Hebbal

Valley

Wastewater Conveyance Scenario


Core area 245 Sq. Kms. pipes were laid 45 to 50 years back
(i) Laterals 3300 Kms repaired/ replaced/ rehabilitated as and when needed
from the Board revenue
(ii) Sub Mains/ Mains/ Trunk Sewers 300 Kms repair/ replacement/
rehabilitation taken up in phases depending upon the receipt of funds from the
out side/ external agencies as Board is not in a position fund the projects. As of
now, out of 300 Kms sub mains replaced/ rehabilitated 51 Kms Works are
under progress and completed by end of 2017 (70 Kms) and recently
approved under AMRUT - 74 Kms costing Rs.500 Cr for which DPR is under
preparation and works are expected to be completed by end of 2019.
(1) EAP A completed (33 Kms at a cost of Rs.47 Cr)
(2) Hebbal Zero flow completed (18 Kms at a cost of Rs.45 Cr)
(3) EAP B rehabilitation work is under progress (70 Kms at a revised cost
of Rs.495 Cr) expected to be completed by end of 2017
(4) EAP C proposed at a cost of Rs.642.97 Cr - (EAP-C 74 Kms Rs.500
Cr + Pump House at Koramangala Sports Complex and Raising
main from Pump House to K & C Valley STP Rs.96.22 Cr +
Ranganatha Colony Rs.46.75 Cr) ) Approved under AMRUT
DPR is under preparation expected to be completed by 2019

Wastewater Conveyance Scenario contd.


Erstwhile CMC / TMC area 330 Sq. Kms. Added to BBMP in

2006 there was no UGD network during the formation of


BBMP BWSSB has initiated UGD works under KMRP/
JnNURUM/ State Funding/ BWSSB Funds at a cost of Rs.1200 Cr.
(i) Laterals 2400 Kms.
(ii) Sub Mains/ Mains/ Trunk Sewers 340 Kms
Now the 90% of the project is completed and balance will be
completed by end of 2016. Additional lateral network in two
erstwhile CMC/ TMC costing Rs.55 Cr was approved under AMRUT
expected to be completed by end of 2017

110 Village area 225 Sq. Kms. Added to BBMP in 2007 No


water supply and UGD facilities depend upon bore well water
supply and soak pits temporarily discharging into natural
drains BWSSB has initiated the project costing Rs.5100 Cr for
water and UGD facility Now with JICA for funding

Wastewater Treatment Scenario

Existing 14 Nos. 721 MLD capacity treating up to 80% capacity due to


connectivity problem works are under progress full capacity
utilization by end of 2016
Under Constructions 10 Nos. 336 MLD capacity expected to be
completed K & C Valley by March 2017 V Valley by end of 2018
Recently approved under
(1) Mega City Revolving Funds 4 Nos 440 MLD capacity cost
Rs.1209 Cr KUIDFC has sanctioned 50% of the project cost,
balance 50% will be shared by GoK and BWSSB expected to be
completed by 2019
(2) AMRUT 5 Nos. 75 MLD capacity Cost Rs.190 Cr expected to be
completed by end of 2018
In pipeline under
(1) Mega City Revolving Funds 1 STP 60 MLD capacity cost
Rs.131 Cr KUIDFC will sanction 50% of the project cost,
balance 50% will be shared by GoK and BWSSB once approved
expected to be completed by June 2019
(2) 110 Villages 16os. 129 MLD capacity Cost Rs.387 Cr awaiting Central/
JICA clearance expected to be completed by 2020

Wastewater Treatment Scenario contd.


Valley wise treatment plant capacities in MLD
Valley

Existing

Under
construction

Approved In pipe line

Total

1) Vrishbhavathi

276

105

190

60

631

2) Koramangala
and Challaghatta

305

150

205

90

750

3) Hebbal

140

81

120

39

380

721

336

515

189

1761

100%
Commissioned
utilization by K&C Valley by
end of 2016 March 2017 & V
Valley by end of
2018

Expected
to
be
completed
by 2019

Expected
to
be
completed
by 2020

Total

Existing Waste Water Treatment Plants


Sl.
No.

Location

Capacity in
MLD

Treatment Facility

1.

Vrishabhavathi Valley

180

Secondary Trickling filters

2.

K & C Valley I

248

Secondary: Activated sludge


process

3.

Hebbal Valley

60

Secondary: Activated sludge


process

4.

Madivala

04

Secondary: UASB + oxidation


ponds+ constructed wetlands

5.

Kempambudhi

01

Secondary: extended Aeration

6.

Yelahanka

10

Activated sludge process +


filtration+ chlorination (Tertiary)

Existing Waste Water Treatment Plants


Sl. No.

Location

Capacity in
MLD

Treatment Facility

7.

Mylasandra

75

Secondary Extended aeration

8.

Nagasandra

20

Secondary -Extended aeration

9.

Jakkur

10

Secondary UASB +Extended aeration

10.

K. R. Puram

20

Secondary UASB +Extended aeration

11.

Kadabeesanahalli

50

Secondary-Extended aeration

12.

Rajacanal

40

Secondary- Extended aeration

13.

Cubbon Park

1.5

Membrane

14.

Lalbagh

1.5

Extended Aeration + Plate Settlers +


UV disinfection

Grand Total

721

Location Of existing STPs 14 Nos of 721 MLD capacity


Yelahanka 10 MLD
Nagasandra 20 MLD

Jakkur 10 MLD
Hebbal 60 MLD

Raja Canal 40 MLD

K R Purum 20 MLD

Cubbon Park 1.50 MLD


Kadabeesanhalli 50 MLD
K & C Valley 248 MLD
Lalbagh1.50 MLD
Mailasandra 75 MLD
Madivala 4 MLD
V Valley 180 MLD
Kempambudhi 1 MLD

10

Construction of new wastewater Treatment plants


Name

Capacity in MLD Process (Including BNR)

Raja Canal

40

Extended Aeration (EA)

Horamavu Agara

20

Sequential Batch Reactor (SBR)

Nagasandra

20

SBR

Chikkabanavara

SBR

Kadugodi

SBR

Kengeri

60

Activated Sludge Process (ASP)

K & C Valley

60

ASP

Bellandur Amanikere

90

ASP

Doddabele

20

SBR

Yellemallappa Chetty Kere

15

SBR

Total

336

Location Of under construction STPs 10 Nos 336 MLD capacity

Chikkabanavara 5 MLD
Nagasandra 20 MLD
Raja Canal 40 MLD
Horamavu Agara 20 MLD
Kodugodi 6 MLD
Yelemallappa
chettykere 15 MLD

Bellandur Amanikere 90 MLD


Kengeri 60 MLD
K & C Valley 60 MLD

Doddabele 20 MLD

12

Proposed New Treatment Plants


The wastewater generation will go up in the coming days.
It is expected that the additional wastewater generated will
be about 300 MLD in the above valleys.
To bridge the gap following treatment plants are proposed
(1) V Valley
150 MLD
(2) Doddabele
40 MLD
(3) K & C Valley
150 MLD
(4) Hebbal
100 MLD
Total
440 MLD
Proposal of constructing STP at Bangalore University of 60
MLD capacity is yet to be approved

Location Of Proposed STPs

Hebbal
100 MLD STP

K.R.PURAM
20 MLD STP

Bangalore University
60 MLD STP
K& C Valley
150 MLD STP
Doddabele
40 MLD STP
V Valley
150 MLD STP

14

New Treatment Plants approved under AMRUT


It is proposed to construct 4 treatment plants on the
upstream side of Bellandur lake.
Government of India has approved the proposal in the 5th
Apex Committee Meeting held on 15-12-2015
Sl.
No.
1
2
3
4
5

Location
Sarakki
Hulimavu
ChikkaBegur
Agaram
K R Purum

Capacity in MLD
5
10
5
35
20
TOTAL

Cost in Rs.
Crore
15.00
30.00
15.00
105.00
33.00
188.00

Valley wise Wastewater


treatment capacities

Chikkabanavara 5 MLD
Nagasandra 20 MLD

Quantity of wastewater
generation 528 MLD

Nagasandra 20 MLD

Treatment Plants
Existing
276 MLD
Under Construction- 105MLD
Proposed 250 MLD
Total Treatment Plants 631 MLD

B University 60 MLD

Kempambudhi 1 MLD
V Valley 150 MLD

Kengari 60 MLD
Doddabele 20 MLD
Doddabele 40 MLD

V Valley 180 MLD


Mailasandra 75 MLD

Quantity of wastewater generation 528 MLD


Treatment Plants
Existing

305 MLD

Under Construction

150 MLD

Proposed

205 MLD

In Pipe line

90 MLD

Total Treatment Plants 750 MLD


Kadabeesanhalli 50 MLD
Cubbon Park 1.50 MLD
Lalbagh 1.50 MLD
Sarakki 5 MLD

Madivala 4 MLD

Begur 5 MLD
Hulimavu 10 MLD

Bellandur Amani Kere


90 MLD

K & C Valley 248 MLD


K & C Valley 60 MLD
K & C Valley 150 MLD

Agara 35 MLD

Yelahanka 10 MLD
Jakkur 10 MLD

Rajacanal 40 MLD
Rajacanal 40 MLD

Hebbal 60 MLD
Hebbal 100 MLD

Horamavu Agara 20 MLD


K R Purum 20 MLD
Kadugodi 6 MLD K R Purum 20 MLD

Quantity of wastewater generation 264 MLD


Treatment Plants
Existing

140 MLD

Under Construction

81 MLD

Proposed

120 MLD

In Pipe line

39 MLD

Total Treatment Plants 380 MLD

Yelemallappa Chetty
Kere 15 MLD

Other initiations of BWSSB for


abatement of pollution

Mandatory to install Sewage Treatment Plant (STP)


BWSSB has taken initiative to make mandatory to install STP and
reuse the treated water for

All residential group housing/ apartments with 20 units and above or


having total built up area of 2000 Sq M including basement
Commercial Complexes with total built up area of 2000 Sq M and
above
Educational Institutions with or without Hostel having total built
up area of 2000 Sq M and above
Township and area development projects with an area of 10 Acres
and above

Government Order has been issued on 19-01-2016 and published in

State Gazette on 20-01-2016


BWSSB has given time up to August 2016 to install STP, otherwise 25%
of the water bill will be charged as penalty and for commercial it will
be 50%
Publicity has been given to popularize the initiative

Government Order to install Sewage Treatment Plant

Advertisement to install Sewage Treatment Plant

Abatement of pollution in
Bellandur and Varthur Lakes

Varthur Lake Series

Bellandur Lake and Major Inlet Points


No.

9
10

11

12
13

17
16

15

14

Location

Flow in
MLD

Kempapura main Road

3.00

Kempapura 1st Cross

1.00

HAL Research Lab

10.00

Challaghatta

20.00

10

Nagasandra Slum

1.00

11

Nagasandra Colony

1.00

12

K & C Valley 30 MLD

30.00

13

K & C Valley 218 MLD

190.00

14

Ibalur

3.00

15

Agaram

1.00

16

Agaram Pump house

120.00

17

S T Bed

100.00

Total

Flow from inlet 3,4,5,6 & 7 no flow only during rains

480.00

Flow from inlet 1,2,10,11,14 &15 KMRP works completed by end of 2016
Flow from inlet 8 & 9 work is in progress completed by end of 2016
Flow from inlet 16 KMRP works completed by March 2017
Flow from inlet 17 Approved under AMRUT Cost Rs.95 Cr expected to be completed by 2018

Measures taken to abate pollution of Bellandur Lake


Short Term
Providing Sprinkler System
Providing Mesh on the sides of SWD
Providing ramp to the waste weir to smoothen the flow
in the SWD

Medium Term
Providing diversion channel for diverting dry weather
flow

Long Term

Construction of 4 treatment plants of 55 MLD capacity


costing Rs.165 Cr under AMRUT completed by June 18
Construction of 150 MLD STP at K & C Valley under Mega
City funding expected to be completed by end of 2019.

Measures taken to abate pollution of Varthur Lake


Varthur lake is on the down stream side of Bellandur
lake
The over flow from Bellandur lake and flow from the
catchment between Bellandur lake and Varthur lake
joins
The sewage flow from the catchment between these
two lakes is going to be addressed in 110 Village
project requires 4 years time once the project is
approved by 2020
As short term plan, sprinklers are deployed to
reduce the foam formation in the wasteweir

Thanks

Você também pode gostar