Escolar Documentos
Profissional Documentos
Cultura Documentos
Abstract
Early stimulation work in Peat Field of Queensland, Australia
involved application of cavity completion techniques to
produce methane gas at commercial rates in the first wells
completed in the reservoir gas cap. Early in the project life,
cavity completion treatments resulted in promising and
acceptable gas flow rates. However, excessive cost associated
with this technique led to consideration of alternate
stimulation approaches by the design team. The main
objective was to achieve similar or better gas rates at the
lowest cost.
Multi-seam nitrogen-foam stimulation was conducted in
several wells of the Peat field to assess the effectiveness of
this technique in terms of: (1) production enhancement and
cost reduction; (2) location of the coal-seam intervals in the
gas cap (i..e. gas-saturated coals) and;
(3) improved
completion efficiency.
To minimise the effects of tortuosity and multiple far-field
fractures in addition to ensuring that each coal-seam interval
received adequate treatment, a staged stimulation approach in
combination with other remedies such as sand slugs and high
injection rates was adopted and successfully applied.
Zonal Isolation was achieved through the use of the newly
developed, easily drillable composite plugs that allow staged
treatment with flowback capabilities.
SPE 64493
SPE 64493
SPE 64493
SPE 64493
wells, diagnostic tests such as Injection/Breakdown, StepDown Rate Tests and the pumping of sand slugs were carried
out on the first wells to estimate the stress level, the leak-off
mechanism and parameters and to identify if any near
wellbore restrictions existed such as friction due to perforation
and tortuosity and to quantify these effects.
The G-function derivative approach following a diagnostic
injection test as proposed by Barree and Mukherjee18 was used
to identify the leak-off type and estimate the closure pressure
for each of the treated coal intervals. The data from the small
Injection/Breakdown tests was used for this purpose since
subsequent injections of fluids into the coal at times resulted in
an increase of the closure pressure. These effects are caused
by changes in the fracture geometry in addition to stress
dependent leak-off, the propagation of multiple fractures as
larger fluid volumes are pumped into the coal and the
possibility of creating a stress induced damage27 thus reducing
the permeability of the coal around the fracture plane.
Pressure dependent leak-off behavior was common to most
of the coal seam intervals as shown in Fig. 3, 9, 12, 16, 20, 23,
and 26. Pressure dependent leak-off19 is indicated by the large
hump in the superposition derivative (Gdp/dG) that lies
above a line through the normal leak-off data prior to
hydraulic fracture closure. Pressure dependent leak-off is a
result of cleats (fractures/fissures) that were dilated by the
injection test. As the pressure declines during the fall-off, the
fractures/fissures constrict until closure at the fissure opening
pressure.
However the G-function plot for Peat A well seam X2
(Fig. 6) indicated a fracture height recession. This leak-off
mechanism occurs19 when the fracture grows into high stress
relatively impermeable layer(s) adjacent to the permeable
zone. During the shut-in, the fracture begins to close in the
impermeable layer(s) first followed by the permeable interval.
The analysis of the injection tests shows that the ISIP vary
from 2322 psi for Well Peat B seam X3 (Fig. 20) to 837 psi
for well Peat A seam X3 (Fig. 9) or a fracture gradient of 1.45
psi/ft to 0.87 psi/ft and fracture closure pressure (Pc) ranging
from 1436 psi to 511 psi or a stress gradient of 1.07 psi/ft to
0.66 psi/ft for the same wells and coal intervals respectively.
Analysis of the Step-Down Rate tests carried out in Well
Peat B seam X1 and X2 (Fig. 13, 17) indicate that the friction
pressure contribution due to perforation and tortuosity was
moderate with a total friction of 402 psi and 389 psi
respectively with a 50-50 contribution form each.
The sand slugs though not a cure for all was pumped at a
concentration of 1 ppg for all the treated intervals and showed
that it can help reduce the friction pressure contribution due to
tortuosity (Fig. 7 and 21) in some cases and in others no
noticeable difference was indicated (Fig. 4, 10). However this
does not mean that higher sand concentration if used during
the sand slug stage would not have worked and since the
friction due to tortosity in most cases was low to moderate no
attempt was made to pump a second sand slug with an
increased sand concentration. The second goal of the sand slug
nitrogen foam frac fluid and by varying the number and timing
of the of multiple fractures till the observed net is close to the
modeled one (Fig. 5, 8, 11, 15, 19, 22, 25, 28, and 30).
Modeling of the net pressure using single-planar fractures
resulted in lower net pressures than observed and a fracture
half-length that is 3 to 4 times the one estimated from the post
fracture production tests. We have also tried to model the high
net pressure increase for the few cases treated in this paper by
using high fracture modulus to account for fracture tip
effects. This has resulted in very high fracture widths that
were inconsistent with the few cases where screenout (Fig.
19) occurred. Consequently we resorted to the use of multiple
fractures to model the high net pressure.
This approach was supported by the evidence of the creation
of multiple fractures through mine back experiments 15,16,17 and
the authors experience in the area where substantial decrease
in treating pressures of up to 1100 psi following the first
stages of the sand laden fluid past a critical sand
concentration (Fig. 15). This reduction in treating pressures is
the result of the screening out secondary wings of the
created multiple fractures thus leading to a less complicated
geometry or tortuous pathway and the pumping of the rest of
the fluid into the main branch. Another possible cause of the
decrease in treating pressures as discussed by Harris &
Pippen25 is the erosion of perforation tunnels with time caused
by the high pumping rates of the nitrogen foam fluid and sand.
The effects of perforation erosion may contribute to a certain
degree to the decrease in the net pressures, but we believe that
shutting off secondary fractures is a more possible cause.
More importantly the results of the post-fracture production
tests suggest that the resulting fracture(s) following a
treatment will be shorter and wider. The net pressure increase
may be the due to the existence of multiple fractures and tip
effects to a certain extent since these appear to be present in
almost all reservoirs. The results of the net pressure analysis
are summarized in Table 3.
Post-treatment Production Tests
An extended post-fracture production and pressure buildup
survey was conducted to evaluate the effectiveness of the
stimulation treatments in enhancing the production of the
selected wells and to formulate a strategy for the completion
of future wells in order to maximize production and or reduce
cost.
Production Logs were run on Peat Wells A, B, and C to
evaluate the flow contribution from the coal seams that were
hydraulically fractured in each of the wells. The gas flow,
water rate and surface pressures were monitored using a
surface separator. Downhole gauges were run to monitor flow
and build-up pressures which in combination with the flow
rates were used in well tests interpretations to estimate the
reservoir properties.
The lack of stabilization of the pressure derivative made
the well test interpretation difficult. This ambiguity would
have been eliminated if pre-fracture tests were conducted
where the effective permeability to gas estimates from the pre-
SPE 64493
SPE 64493
SPE 64493
SPE 64493
Fig.1 Map of the Peat Field indicating the gas cap, QLD, Australia
10
SPE 64493
10.00
2400
1500
BH Inject Rate
Observed Net (psi)
40.00
1500
8.00
1920
1200
32.00
1200
6.00
1440
900
24.00
900
4.00
960
600
16.00
600
2.00
480
300
8.00
300
0.00
0
0
24.90
37.50
50.10
Time (mins)
62.70
75.30
87.90
0.00
0
40.00
2400
2000
4.000
2000
32.00
1920
1600
3.200
1600
24.00
1440
1200
2.400
1200
16.00
960
800
1.600
800
8.00
480
400
0.800
400
0.00
0
0
36.90
42.90
48.90
Time (mins)
54.90
60.90
66.90
0.000
0
5.000
2000
1200
40.00
1200
4.000
1600
960
32.00
960
3.000
1200
720
24.00
720
2.000
800
480
16.00
480
1.000
400
240
8.00
240
0.000
0
0
11.90
17.90
23.90
Time (mins)
29.90
35.90
41.90
0.00
0
SPE 64493
4.000
6000
1500
BH Inject Rate
Observed Net (psi)
3.200
4800
1200
40.00
1200
2.400
3600
900
30.00
900
1.600
2400
600
20.00
600
0.800
1200
300
10.00
300
0.000
0
0
2.90
16.30
29.70
Time (mins)
43.10
56.50
69.90
14.00
6000
3000
50.00
1500
40.00
2400
8.40
3600
1800
30.00
1800
5.60
2400
1200
20.00
1200
2.80
1200
600
10.00
600
0.00
40.00
1500
3.200
1760
1200
32.00
1200
2.400
1320
900
24.00
900
1.600
880
600
16.00
600
0.800
440
300
8.00
300
0.000
0
0
0.00
0
23.30
28.70
Time (mins)
34.10
10.76
Time (mins)
16.14
39.50
44.90
800.0
500.0
21.52
26.90
0.00
0
800.0
640.0
400.0
640.0
480.0
300.0
480.0
320.0
200.0
320.0
160.0
100.0
160.0
0.0
0.0
17.90
5.38
50.00
3000
4.000
2200
1500
11.20
4800
2400
0.00
0
0
0.00
0
11
0.00
6.00
12.00
18.00
24.00
30.00
0.0
12
50.00
3500
3000
40.00
2800
2400
0.800
2400
30.00
2100
1800
0.600
1800
20.00
1400
1200
0.400
1200
10.00
700
600
0.200
600
500.0
500.0
1.000
3000
0.00
9.38
18.76
28.14
37.52
46.90
500.0
400.0
400.0
400.0
300.0
300.0
300.0
200.0
200.0
200.0
100.0
100.0
100.0
0.0
0.0
0.00
0
0
SPE 64493
0.00
5.00
0.000
0
10.00
15.00
20.00
25.00
0.0
Time (mins)
14.00
5000
2000
BH Inject Rate
Observed Net (psi)
35.00
2000
50.00
3700
3000
11.20
4000
1600
28.00
1600
40.00
2960
2400
0.800
2400
8.40
3000
1200
21.00
1200
30.00
2220
1800
0.600
1800
5.60
2000
800
14.00
800
20.00
1480
1200
0.400
1200
2.80
1000
400
7.00
400
10.00
740
600
0.200
600
0.00
0
0.00
0
0
0.00
0
0
0.00
14.98
29.96
Time (mins)
44.94
59.92
74.90
0.0
44.0
Time (mins)
65.9
87.9
109.9
0.000
0
10.00
7000
4000
BH Inject Rate
Observed Net (psi)
50.00
4000
8.00
5599
3200
40.00
3200
6.00
4198
2400
30.00
2400
4.00
2798
1600
20.00
1600
2.00
1397
800
10.00
800
0.00
-4
0
22.0
1.000
3000
0.00
11.98
23.96
Time (mins)
35.94
47.92
59.90
0.00
0
SPE 64493
4.000
4000
2000
40.00
2000
3.200
3200
1600
32.00
1600
2.400
2400
1200
24.00
1200
1.600
1600
800
16.00
800
0.800
800
400
8.00
400
0.000
0
0
41.9
55.5
69.1
Time (mins)
82.7
96.3
109.9
0.00
0
2000
1500
15.00
4000
2000
BH Inject Rate
Observed Net (psi)
40.00
2000
12.00
3200
1600
32.00
1600
9.00
2400
1200
24.00
1200
6.00
1600
800
16.00
800
3.00
800
400
8.00
400
0.00
0
0
0.00
0
4.90
19.10
33.30
Time (mins)
47.50
61.70
75.90
50.00
1500
1600
1200
40.00
1200
1200
900
30.00
900
800
600
20.00
600
400
300
10.00
300
0
0
0.00
4.38
8.76
13.14
17.52
21.90
0.00
0
Time (mins)
13
14.00
4000
3000
BH Inject Rate
Observed Net (psi)
50.00
3000
11.20
3200
2400
40.00
2400
8.40
2400
1800
30.00
1800
5.60
1600
1200
20.00
1200
2.80
800
600
10.00
600
0.00
0
0
0.00
13.98
27.96
41.94
55.92
69.90
0.00
0
Time (mins)
14
3000
2000
40.00
2000
2400
1600
32.00
1600
1800
1200
24.00
1200
1200
800
16.00
800
600
400
8.00
400
0
0
SPE 64493
0.000
1.580
3.160
Time (mins)
4.740
6.320
7.900
0.00
0
2400
2000
15.00
2000
1920
1600
12.00
1600
1440
1200
9.00
1200
960
800
6.00
800
480
400
3.00
400
0
0
0.00
0
0.00
4.18
8.36
Time (mins)
12.54
16.72
20.90
20.00
5700
5000
40.00
5000
16.00
4560
4000
32.00
4000
12.00
3420
3000
24.00
3000
8.00
2280
2000
16.00
2000
4.00
1140
1000
8.00
1000
15.00
4000
2500
BH Inject Rate
Observed Net (psi)
40.00
2500
12.00
3200
2000
32.00
2000
9.00
2400
1500
24.00
1500
6.00
1600
1000
16.00
1000
3.00
800
500
8.00
500
0.00
0
0
0.00
14.38
28.76
43.14
57.52
71.90
0.00
0
Time (mins)
0.00
10.98
21.96
Time (mins)
32.94
43.92
54.90
0.00
0
SPE 64493
15
550
1,000
kh
C
S
xf
Pavg
71 md-ft
0.5 bbl/psi
-6.6
500 feet
985 psia
500
100
10
400
kh
C
S
xf
Pavg
71 md-ft
0.5 bbl/psi
-6.6
500 feet
985 psia
350
1.00E-03
1.00E-02
1.00E-01
1.00E+00
1.00E+01
1.00E+02
300
Observed Horner data
Simulated Horner data
1.00E+03
250
25,000
20,000
15,000
10,000
5,000
1,000
400
Measured
kh
11 md-ft
-7.0
Simulated
350
300
250
10
200
150
1
kh
11 md-ft
-7.0
100
Simulated Derivative
0
1.00E-04
1.00E-03
1.00E-02
1.00E-01
1.00E+00
1.00E+01
1.00E+02
1.00E+03
1.00E+04
100
50
1.00E+05
1.00E+06
0
10,000
9,000
8,000
7,000
6,000
5,000
4,000
3,000
2,000
1,000
500
1,000
kh 1
176 m d-ft
kh 2
1 7.6 m d-ft
R1
200 feet
Skin
-5.8
Com pos ite M ode l
450
100
300
10
250
Observed pressure chang e
200
150
100
0
1.00E-04
50
1.00E-03
1.00E-02
1.00E-01
1.00E+00
1.00E+01
1.00E+02
1.00E+03
1.00E+04
1.00E+05
1.00E+06
0
14,000
12,000
10,000
8,000
6,000
4,000
2,000
350
450