Escolar Documentos
Profissional Documentos
Cultura Documentos
Abstract
Well completion design is critical for the life cycle of a well. This includes expected loads during drilling,
production, and work overs as well as metallurgical compatibility with production fluids. Any failure in
the completion has the potential to jeopardize well integrity, delay production and can potentially impact
the economics of the field development plan. There are long term studies on reliability of specific type
well completion equipment which includes over 30 years of operational experience for well systems. This
has provided a comprehensive database on well completion equipment with thousands of well-years of
production experience and downhole failures. However, no such data base is available for well completions with high Ni CRA metallurgy for high sour gas field development.
Al Hosn gas commenced development drilling in one of the Southwest sour gas field, located 180 km
southwest of Abu Dhabi in 2011. Phase-1 gas wells were drilled and completed in December 2014. The
well design is a single lateral, open hole reservoir completion, with the laterals being approximately up
to 15,000ft long. The well test data and logs were used to establish some of the completion equipment
design parameters including H2S 20 30%, CO2 8 12%, salinity 160,000 220,000 ppm, BHT 275 -325
deg F, FTHT 225250 deg F.
This paper highlights the work that went into completion design as well as choosing the metallurgy,
connections type, elastomers, and the completion components. In some cases, this was the first application
of the equipment in such an extreme environment. The process for designing a completion with high Ni
CRA Metallurgy included: 1) literature survey; 2) identifying the required standards & procedures; 3)
selection of required CRA metallurgies for required grades based on standards; 4) CRA vendor prequalification; 5) validation of all CRA metallurgies by lab tests for required conditions; 6) selection of
connections; 7) validation test for CRA connections; 8) input from other operators & equipment providers;
9) strict management of change process for any deviation from specifications; 10) third party QAQC
during manufacturing and make up of sub-assemblies. The completion design integrity has been proven
under flowing condition during the well cleanups and flow testing on Phase 1 wells.
SPE-177557-MS
Water production was initially anticipated to be very unlikely. However, one lower formation has
shown a high degree of natural fractures. This, in conjunction with possible acid fracturing stimulation
process increases the risk of water production occurring sometime in the well life. If water is produced,
there is uncertainty on the maximum expected level of chlorides. Offset data from other fields show
examples of up to 220,000 ppm salinity. This high water salinity will be expected to be at the saturation
limit and poses significant selection challenges for suitable CRA metallurgy at 300 deg F.
Well completion technology providers had limited tested or validated equipment and know-how for
such reservoir conditions. Some critical technology and service personnel competence gaps were identified. Additionally, no similar case histories were available for some of the equipment selection and
design process. Some of these field proven requirements were addressed with properly tailored qualification programs. However, some of these associated limitations for such extreme reservoir conditions
increased the uncertainties and risk. These limitations were mitigated through the detailed design and
SPE-177557-MS
selection process. The remaining risks were managed by appropriately modifying the completion & well
intervention procedures.
Figure 1
The 2nd type consisted of 7 CRA production liner and upper completion with tie back liner top PBR:
This completion type is used for dual lateral wells and for wells requiring isolation of specific reservoir
zones for selective production (Figure-2).
SPE-177557-MS
Figure 2
SPE-177557-MS
in similar extreme sour reservoir conditions, which could have been used for the completion design
process base case, was very limited.
The Well Completion and Intervention scope was very challenging to achieve a long sustained life
cycle with full well integrity. The critical aspects are summarized below;
Completion BOD requirements
Maximum production rate of 100 200 MMSCFD per well with a life of 25 years; Flow from all open
zones to be comingled; Minimize well interventions for CRA string & sour exposure; Memory type
down-hole quartz gauges installation provision off flow path; Condensate production of 20 80 bbl /
MMSCFD; No wax or asphaltene production is expected; No water production is expected in early
life-of-field; No down hole hydrate risk is expected; No elemental sulphur is expected; refer table-1 for
the wells and reservoir parameters for basis of design.
Project management approach
Pre-qualification reviews of well completion technology providers equipment were carried out for such
extreme conditions. The tender technical evaluation process was expected to take more time with several
rounds of clarifications to reduce uncertainty. The type of metallurgy, seals and equipment required for
the well completion were not available off the shelf from the technology providers. The lead-times for
such raw materials are very high in the range of 9 to 15 months. Some of the requested product
qualifications procedures required a timeframe of 4 to 6 months due to the execution process and facility
availability.
The manufacturing product specifications were required to be modified for different metallurgy and
seals. The critical path method (CPM), a step-by-step project management technique, was used for process
planning that defined critical and non-critical tasks for total time optimization. The goal was to identify
and focus on critical time-frame tasks. Problems and process bottlenecks for critical items were reviewed
at every stage with the intent to prevent any escalation and to optimize the next critical item on the path.
This approach allowed validation and qualification requirements to be conducted concurrently with
manufacturing, significantly reducing the overall closure time.
Metallurgy selection for well completion equipment & tubular
As a first step, standard ISO15156-part 3 was used to select the metallurgies required for tubing,
production liner and well completion equipment. High Nickel-Chromium-Molybdenum Alloy UNS
N08028 & UNS N08825 were selected for tubing, while UNS N08825 & UNS N07725 were selected for
downhole completion equipment. Since there were no case histories available within ADNOC OPCOs for
the required metallurgy in comparable reservoir conditions, an extensive literature survey was pursued to
find similar case histories globally.
Analysis and appraisal well data had proven down-hole conditions to be in the region of 5000 -5600
psia at 275325F with 20 30% H2S and 8 12% CO2. Within the industry, there are very limited
completion design standards and papers available for this extreme environment. A few case histories
matched some parameters but not the combination of all critical parameters for metallurgy selection. In
such cases, laboratory testing became inevitable to meet the standard guideline for quality assurance and
to manage the potential high risk level with metallurgy suitability. A number of alloys were tested at a
variety of downhole and flowing conditions. Qualified labs were selected to conduct a corrosion testing
program for material qualification and establish suitability for use under reservoir and surface flowing
conditions.
Three types of tests (constant load C ring bent beam and slow strain rate) were conducted for full
evaluation. Testing had shown that alloys UNS N08028 and UNS N08825 were functionally equivalent
at design conditions. Additional testing was carried out on other alloys including SM 2535, SM 2550,
UNS N07718, UNS N07725, and UNS N09925. There was no commercial advantage for either SM 2535
or SM 2550 over UNS N08028 or UNS N08825, so these alloys were not tested to the full range of
SPE-177557-MS
conditions used for testing alloys UNS N08028 and UNS N08825. Alloys UNS N07718, UNS N07725,
and UNS N09925 were tested and qualified for use as tubing hangers, sub-surface safety valves,
production packer, profile set plugs and other well completion equipment. Some limitations were
identified for alloys UNS N08028, UNS N07718 and UNS N09925 by this testing program. Review of
the laboratory and literature data were conducted to support selection of the suitable alloys for the given
condition.
NACE type 4c and 4d tubular materials provided acceptable SCC behavior in the simulated service
environments: Type 4c UNS N08028, N08825, SM2535 and Type 4d SM 2550. This program
involved the use of three different types of tests (C-ring, bent beam and SSR) and multiple heats of the
Type 4c materials (UNS N08028, N08825 and SM 2535) were used. All NACE Type 4c tubular materials
included in the evaluation program exhibited similar SCC resistance as would be expected from their
listing in NACE MR0175/ISO15156 Part 3 Table A.12. In fact, all three materials evaluated in the
program actually exhibited greater SCC resistance in terms of higher temperature and H2S partial pressure
limits than the limits indicated in NACE MR0175/ISO15156 Table A.16.
Similar tests were conducted with another laboratory to independently validate the results and further
close the uncertainty when more detailed reservoir parameters were established. Reservoir data indicated
elemental sulfur would remain dissolved in hydrocarbon condensate and max expected salinity up to
220,000 ppm. For this salinity and expected temperature, both alloy UNS N08028 and Alloy UNS N07718
were not found fully suitable. After all these tests, the final selections were made:
Nickel alloy UNS N08825 recommended and used for 7 and 5 production tubing material.
Nickel alloy UNS N07725 and alloy 625 plus (N07716) are recommended and used for the
completion equipment & accessories.
SPE-177557-MS
temperature suitability. Other mechanical parameters of these connections were unchanged and the
metallurgy remained in the same NACE type 4c materials class. Hence, with this rationale and with a
limited timeframe before the start of the drilling campaign, the connections with UNS N08825 were
accepted to allow tubing and completion equipment to be delivered in time. Operational data to date have
shown that these connections have performed satisfactory during completion running, completion testing
and well production phases. Some galling issues have been observed during retrieving for work over jobs,
but these have been limited to only a few joints.
Rubber Elastomeric Seals
To establish suitable rubber elements & elastomeric seals for this extreme environment coupled with high
mechanical loading was very challenging. For the given well and reservoir fluid parameters, the required
rubber elements and seals according to ASTM D1418 designation are FEPM, FFKM & PEEK type. All
elastomer or rubber materials were tested in accordance to the latest editions of the ASTM D for tear
resistance, tension, hardness and environmental effect for the confirmed conditions. Equivalent elastomers
with different trade names were used from qualified providers. One seal system with a good track record
is either Kalrez or Aflas moulded onto a deformable body with Chemraz and peek for v seals. All these
seals were tested to V2 or V0 class to qualify as required on the specific items.
Tubing stress and load analysis
The Tubing stress analysis was conducted using the industrys standard Landmarks wellcat software Build 5000.1.7.0.11180. The initial tubing stress analysis was conducted with 5 20ppf & 7 29ppf 110
CRA UNS N08825 tubing with VAM TOP HC and Tenaris blue connections. Initial tubing stress analysis
was further verified with external engineering specialists for the well and completion design. The work
evaluated the effect of transient temperature, pressure, tensile and compressive loads. It was ensured that
the selected tubing remain within the acceptable tri-axial, axial, burst and collapse design safety factors
for all expected combined loads. The design limit plot and tri-axial stress safety factors plot are shown at
figure-3 and figure-4 for reference.
SPE-177557-MS
Key design parameters and assumptions for various load cases were as follows: Well-path of
approximately 50 to 55 degree well deviation at 9 5/8 production packer setting depth used for
approximate well trajectory; 2 degree dogleg superimposed over the full well profile; kill weight brine of
11.7 ppg; packer fluid of 11.7 ppg brine; frac fluid of 11.7 ppg; acid density of 8.82 ppg; ambient
temperature of 80 deg F; setting depth 11,938ft MD / 10,880ft TVD (upper completion); well temperature
of 275325 deg F at 11,000ft TVD; maximum reservoir pressure of 5,500psi; CGR of 20 80 bbl /
MMSCFD; WGR of 3 bbl / MMSCFD (this is the minimum water of condensation calculated by flow
modelling software); maximum production rate of 100 MMSCFD / well; surface bullhead acid stimulation
required at maximum possible rate of 45 BPM.
Some technical challenges were observed for stress and load analysis in this type of extreme
environment with high end Ni CRA alloys. The critical aspect is that the design process is based on
assumption that material mechanical properties behave in uniform manner, i.e. the yield point of material
is same in all directions. Many CRA materials exhibit an-isotropic properties, i.e. different mechanical
properties in different directions. This variation becomes wider for high nickel alloys and the cold worked
alloys. The variation is also manufacturer dependent due to variances in manufacturing processes and end
treatment. The axial yield stress can be determined by lab testing. However, the tangential and radial
properties are lower and a dedicated specific experimental process is required to establish these properties.
Selected CRA metallurgy suitable for the corrosion aspect in this environment is UNS N08825. This
metallurgy cant be heat treated and only cold worked to achieve the required mechanical yield strength.
In general, longitudinal tensile is the standard method to determine the mechanical properties of the
material. Experience and actual tests show that cold worked CRA materials may show longitudinal
compressive yield strength as low as 80% of the longitudinal tensile measurement. This anisotropy
property of CRA metallurgy poses a lower compression strength working envelope with no expansion &
contraction manipulating devices like free floating PBR or expansion joints. The mechanical strength and
properties of CRA materials are temperature dependent and varies for each CRA metallurgy from different
vendors. The yield strength and density variation were required to be experimentally established and used
for design. The yield strength rating of UNS N08825 varied from 100% at ambient temperature to about
86% at 300 deg F.
A sensitivity analysis was carried out to determine the maximum expected flowing wellhead temperature. This was initially conducted to verify down-hole material grade specification. However, it was also
important for surface system design and surface system flow modelling. As the CGR increases, the flow
SPE-177557-MS
rate will drop for a given reservoir pressure. As the CGR increases the U value will decrease thereby
giving a lower average tubing temperature. This in turn will result in lower axial compression in the
tubing. For this reason, a CGR of 20bbl/MMSCFD was assumed as worst case load.
Packer forces and movement analysis
The completion strategy for these extreme sour gas wells was not to use the commonly installed free
moving dynamic PBR type seal system due to significant expansion and contraction of the completion
string across the operating envelope. In the first type of completion design chosen, the production packer
was integral to the production tubing with thread connection. In second type of the completion design, the
seal assembly of the PBR is anchored with shear latch rated at 200,000 lb. Tubing to packer force analysis
was carried out by two different teams to ensure all the loads were considered and also provide cross
validation for worst case design loads (Figure-5).
Figure 5
The max expected tensile and compression loads from these two independent analyses were calculated
by design models and are listed in below table-2;
Table 2
Max expected Loads
Compressive loads:
Tensile Loads:
10
SPE-177557-MS
The Design Factor of 1.6 has been used for both tensile and compression rating of the packers.
However, the actual Safety Factor is 2.9 for tensile loading and 2.67 for compression rating for the
permanent HPHT packers used for the completion of phase-1 development wells. Additionally, external
verification was obtained on inputs for the expected packer loads with the Cyber-String application. The
result indicated no issues with all expected load conditions.
The primary results from the stress and load analysis
The selected tubing and completion components from the tubing hanger to the top of the production
packer were designed within the required design factors for tri-axial, axial, burst and collapse loadings.
The designed acid stimulation job required high pressure pumping to achieve the maximum rate required
for longer open-hole lateral sections. However, the tubing connected packer design allowed only 3000psi
differential pressure from tubing to annulus. The operational procedure was implemented to include the
application of pressure in the A-annulus during stimulation and also installing PRVs on both annulus and
tubing side.
Production packer qualification
Type 1 - Hydraulic set tubing connected permanent production packer: Single-trip, hydraulic set,
permanent production packer (material alloy UNS N07725). Run on production tubing size 5 1/2, 20ppf,
Tenaris blue or Vam top HC connection, alloy UNS N08825-110 grade. Set inside production casing 9
5/8, 53.5 ppf, alloy UNS N08028-110. A 6.5k psi differential pressure rating in both directions.
Temperature rating of 350 deg F, suitable for extreme sour environment gas with 26% H2S, 10% CO2,
220,000 ppm chloride. An integral one piece mandrel to minimize leak points with the elastomer qualified
for extended sour service exposure, barrel type upper & lower slips for CRA casing, expanding extrusion
barrier, milled & retrieved on packer picker. A three piece multi duro packer element with large packer
ID to minimum of tubing ID and minimum number of pressure seals points on piston. The tubing to packer
force safe working envelope for 275,000 lb in compression (tubing evacuation) & 275,000 lb tensile
(stimulation & well kill). The primary criteria for the 9 5/8 production packer was to have high enough
tensile and compressive strength to meet worst case load scenario during stimulation and production phase
for life cycle of the wells.
Type 2 - Mechanical packer and anchored PBR seal assembly system: The seal anchor shear rating was
limited by the drilling or work-over rig safe over pulling capability. For this reason the seal anchor latch
shear was limited to 200,000 lb plus tolerance of - 25,000 lb. Although the mechanical production
packer was designed for full load of 275,000 lb, the seal anchor latch limited the tensile load capability
to 200,000 lb plus tolerance of - 25,000 lb.
It was desired to use field proven production packers. However, none of the technology providers had
field proven 9 5/8 production packers with alloy UNS N07725 in similar environment or with qualification tested to V0. Bids were invited from pre-qualified completion equipment providers with condition
that successful bidder will qualify these packers for V0 environment. The qualification time was included
in the delivery periods with no impact to overall project time for well delivery. Packer qualified operating
envelop with V0 testing example Figure-6 as below.
SPE-177557-MS
11
Figure 6
12
SPE-177557-MS
NaCl-NaBr brine for this weight and temperature range. However NaCl-NaBr brine is preferred and for
economic reason was selected for packer fluid.
High Ni CRA Intervention tools and down-hole gauges
With Phase-1 strategy to use minimum penetrators and seals in the completion string and wellhead,
down-hole memory gauges were required. For increased such intervention runs in the well, it was critical
to minimize CRA contact to carbon steel. Hence it was selected to use high Ni CRA tools and accessories,
CRA Deep set profile plugs, CRA soft set gauge hanger and CRA down hole memory gauges for the CRA
completion. The reservoir / well surveillance campaign was initiated successfully and learnings were
captured on handling of the CRA tools for sustained operation. Based on these learnings, it is being
proposed to primarily use permanent down-hole gauges for phase-2 development.
Equipment suitability & integrity with rigorous QAQC program
Reliability was the key driving factor for these high value critical wells in such extreme sour conditions.
A rigorous QAQC program was essential for successful well completion operations and long term well
integrity. This applied to all four phases of well completion delivery process which are Design,
Manufacturing, Installation and Operation. The completion design was analyzed, reviewed and verified
internally. The design was further vetted by external engineering specialists and also by the technology
providers. Q1 quality level with third party inspection requirements were applied to manufacturing stage
and the assembly process. For installation phase, sub-assemblies were prepared in workshop with
dedicated supervision, tested for the required conditions and all parameters recorded for future reviews if
required. Field completion specialists were utilized at the rig site to oversee installation. The completion
well on paper exercise was carried out involving all the service providers with office and field
representatives to capture and address any design or operational gaps. The completion was designed for
minimum interventions in the wells and only interventions planned were for well integrity and minimized
pressure surveys.
Long and uncertain lead times were faced for the specific materials availability and for the
qualification tests process with all the global pre-qualified technology providers.
Limited or no field proven data was available for some high Ni CRA metallurgy equipment for the
expected load conditions and environment experienced by a well completion (for example
production packer, connections, intervention tools, lateral access tools etc).
No coiled tubing manufacturers were known to produce coiled tubing reels made from this class
of CRA materials. There were few case histories where chrome CRA coiled tubing had been used
in completion jobs, but none for intervention operations like those proposed for these wells. The
reason was due to the poor pipe fatigue life for high Ni CRA pipe. For the sour environments,
Operators and CT service providers usually use carbon steel CT pipe (normally grade 80 ksi)
equivalent metallurgy manufactured under the recommended guidelines for the material with
manufacturing and testing process controls as per API specifications 5ST for sour service
conditions. This was used with some applied limiting factors like reduced CT pipe life, real time
monitoring of CT pipe condition, limited available exposure time in down-hole condition based on
actual lab tests data, etc. The sour service carbon steel 2 3/8 coil tubing pipe grade T95 was
extensively lab tested for this high sour environment. However, the lab test results provided only
maximum 6 hours exposure time for acid stimulation which drastically reduced intervention scope
in the long lateral horizontal section.
High CRA alloys are known for heterogeneous and anisotropy behavior under different conditions
like tensile, compression, temperature etc. This necessitates establishing the actual mechanical
resistance of the selected CRA metallurgies for required operating condition envelope. These
SPE-177557-MS
13
parameters were not readily available and were vendor specific. These properties needed to be
established to a high degree of confidence through experiments and testing, which incur additional
cost and time. These accurate values of anisotropic change and temperature were required to be
applied to mechanical properties to achieve more accurate mechanical design analysis with respect
to varying mechanical resistance of that particular CRA metallurgy for different load cases.
Limitations of effective corrosion inhibition were faced for stimulation with high strength acid in
sour gas environment at high temperature. Lab tests were conducted with various corrosion
inhibitors for given conditions at high temperatures. The inhibition was effective for the majority
of the well depth, but did not provide effective inhibition at static bottom hole temperatures in the
reservoir section in presence of high sour environment.
Acknowledgement
The author would like to thank Al Hosn Gas, ADNOC and Occidental management for the permission and
encouragement to publish and share this paper with the industry. The author would also like to thank Tod
Stephens for all clarifications from drilling perspective and to Medhat Al Habsi for sharing his regional
sour wells experience from other ADNOC OPCOs.
Nomenclature
A-annulus Annular space between production tubing and production casing.
ADNOC
Abu Dhabi National Oil Company.
ALARP
As low as reasonably practical.
Bbl
Barrel.
BHT
Bottom hole temperature.
BOD
Basis of design.
CaBr2
Calcium bromide.
CaCl2
Calcium chloride.
CGR
Condensate gas ratio.
CO2
Carbon Dioxide gas.
CPM
Critical path method.
CRA
Corrosion Resistant Alloy.
CT
Coil tubing.
Deg
Degree.
EAC
Environment assisted cracking.
F
Farenheight
H2S
Hydrogen Sulfide sour gas.
14
HCl
HPHT
ID
Ksi
Lb
MD
MMSCFD
MTM
NaCl
NaBr
Ni
NOC
OPCO
PI
PBR
PBTD
Ppg
Ppm
Pp
PRV
Psi
QAQC
SCC
TD
TRSCSSV
TSA
TVD
UAE
WRM
SPE-177557-MS
Hydrochloric acid.
High Pressure High Temperature
Internal diameter.
Thousand pound per square inch.
Pound.
Measured depth.
- Million standard cubic feet per day rate
Metal to metal .
Sodium chloride.
Sodium bromide.
Nickel.
National oil company.
Operating company.
Productivity Index
Polish bore receptacle.
Plug back target depth.
Pound per gallon.
Part Per Million
Partial Pressure
Pressure relief valve.
Pound per square inch.
Quality assurance and quality control.
Stress corrosion cracking.
Target depth.
Tubing Retrievable Surface Controlled Subsurface Safety Valve
Tubing Stress Analysis.
True vertical depth.
United Arab Emirates.
Wells and reservoir monitoring.