TCS-P-104.01, Rev. 0
TABLE OF CONTENTS
1.0
PURPOSE
2.0
SCOPE
3.0
4.0
ORDER OF PRECEDENCE
5.0
DEVIATIONS
TCSP10401R0/YM
PAGE NO. 2 OF 5
1.0
TCS-P-104.01, Rev. 0
PURPOSE
This standard is an introductory to the Underground Power Cable Construction
Standards (TCS-P-104). It provides information on the requirements and practices
which serve as the basis for the handling, storing, construction, installation and
testing of underground HV & EHV power cable systems in the network of Saudi
Electricity Company (SEC), Saudi Arabia.
2.0
SCOPE
The Underground Power Cable Construction Standards (TCS-P-104):
2.1
2.2
LV Cables (XLPE/PVC):
0.6/1 kV
2.2.2
2.2.3
2.3
2.4
Covers the installation procedures and the techniques for handling LPOF
or XLPE power cables.
2.5
2.6
Indicates the proper techniques for handling and storing of cable reels.
2.7
Covers the applicable AC or DC tests as the effective method for the fieldtesting of the power cable.
TCSP10401R0/YM
PAGE NO. 3 OF 5
3.0
4.0
TCS-P-104.01, Rev. 0
2.8
Covers the tests requirements after the installation of the power cable.
2.9
2.10
3.2
It shall be the responsibility of the Design Engineer to ensure that the base
design or detailed design includes the requirements of the latest Industry
Codes and Standards. He can/may bring to the attention of SEC, any latest
revisions of these Codes and Standards which may have an impact on the
technical requirements of TCS-P-104.
3.3
Whenever different Codes and Standards are used, SEC approval to the
same shall be obtained before proceeding with the design. These Codes
and Standards shall be equal to or better than those specified in TCS-P104.
ORDER OF PRECEDENCE
In case of any conflict between various documents and standards or specifications
for U/G power cable projects, the order of precedence shall be as follows:
4.1
4.2
4.3
4.4
4.5
4.6
4.7
TCSP10401R0/YM
PAGE NO. 4 OF 5
5.0
TCS-P-104.01, Rev. 0
DEVIATIONS
5.1
The Design Engineer who prepares the SOW/TS for the U/G power cable
project is responsible to obtain an appropriate waiver from the (TS&SD)
for any specific deviation from this Standard (TCS-P-104). This waiver
shall be taken for the deviation which is over-specification or underspecification.
5.2
In case of any deviations from this Standard (TCS-P-104) during the Base
Design and detailed design of any U/G power cable project, it is the
responsibility of the engineer preparing the base design or detailed design
to obtain appropriate waiver from TS&SD, through concerned SEC
departments, before finalizing the design.