Escolar Documentos
Profissional Documentos
Cultura Documentos
BTS Document
Commissioning Manual
Release B9
Status
RELEASED
Short title
COM
All rights reserved. Passing on and copying of this document, use
and communication of its contents not permitted without written
authorization from Alcatel/Evolium.
2 / 74
Contents
Contents
Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1
General Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.1
Hardware Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.1.1
Configurations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.1.2
Weight and Dimensions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.2
Restrictions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.3
Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.4
Initial State . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.5
Final State . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.6
Operating Principle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.7
Time Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.8
Information Required . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1.9
Conventions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Preliminary Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.1
Before Going to the Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.2
Before You Start (On Arrival at the Site) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing the Micro - BTS Units . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.1
Case A: Installation With the Manual Lift . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.2
Case B: Installation With the Crane . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.2.1
Specific Safety Instructions for Craning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.2.2
Installation of the Crane on MOFRA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.2.3
Preparation for Craning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.2.4
Installing the Micro-BTS on MOCO . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Making the Connections to the BTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.1
OPTION: Installing the Integrated Antenna . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.2
OPTION: Installing the VSWR Detector . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.2.1
Mechanics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.2.2
Fixing the VSWR Detector . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.2.3
Connecting the Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.3
Making the Connections to the BTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Checking Power Supply and Powering Up . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.1
Case 1: A9110-E BTS Without SSC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.2
Case 2: A9110-E BTS With SSC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Commissioning Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.1
BTS Software Downloading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.2
BTS Initialization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.3
Performing BTS Inventory . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.4
Setting and Checking the External Alarms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.4.1
Set and Check the Alarm Mapping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.4.2
Test the External Alarms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.5
Checking the Status of Modules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.6
VSWR Check . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.7
Abis Loop Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6.8
End of Commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Setting Transmission Module Parameters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Finishing Commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61
9
10
10
13
13
13
13
13
15
16
17
17
19
20
20
21
22
26
26
26
28
29
33
34
35
35
36
37
38
41
42
42
45
46
48
49
49
49
50
52
52
55
55
57
Appendix A : Abbreviations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63
Appendix B : List of Items Required . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65
3 / 74
Contents
4 / 74
Figures
Figures
Figure 1: Example of 6 Modules with Single Antenna . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Figure 2: Example Low-Loss Configuration With Antenna Diversity (6 sectors) . . . . . . . . . . . . . . . . . . . . . . . . 11
Figure 3: Evolium A9110-E Pure Configuration (Maximum 6 Evolium A9110-E Modules, 12 TREs) . . . . . . 11
Figure 4: Evolium A9110-E / Evolium A9110 Mixed Configuration (5 Modules: 4 Evolium A9110-E +1 Evolium
A9110, 10 TREs in total) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Figure 5: Evolium A9110-E / Evolium A9110 Mixed Configuration (3 Modules: 1 Evolium A9110-E + 2 Evolium
A9110, 6 TREs in total ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Figure 6: Example of A9110-E BTS ( Maximum 6 Evolium A9110-E Configuration With Cover ) . . . . . . . . . 14
Figure 7: Example of A9110-E BTS (3 modules with SSC Option) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Figure 8: Installation and Arrangement of the Threaded Bolt . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Figure 9: Installation of the Handwheel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
Figure 10: Installing the Gallows . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
Figure 11: Installing the BTS Handle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
Figure 12: BTS Handle Fixed on the Module . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
Figure 13: Putting the A9110-E BTS in Position . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
Figure 14: Fixing the Unit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
Figure 15: Mounting the Lifting Ring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
Figure 16: Installing the Crane . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
Figure 17: ACout BTS Power Connector of ACCO Board is Used to Power the Crane . . . . . . . . . . . . . . . . . . 28
Figure 18: Lifting and Plugging in the Micro-BTS Unit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
Figure 19: Fixing the Micro-BTS to MOCO . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
Figure 20: Installation of Integrated Antenna (GSM and DCS) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
Figure 21: The VSWR Detector . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
Figure 22: VSWR Detector - RF Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
Figure 23: Connecting the ALARM / VCC Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
Figure 24: Connection of IEB PG 11 Glands to COBO for All Modules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
Figure 25: ACCO Board . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
Figure 26: SSC Switch Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
Figure 27: Sector Mapping Micro BTS Window . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
Figure 28: ABISCO Board for A9110-E . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
Figure 29: ABISCO Board for A9110 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
Figure 30: Connectors and LEDs on ABISCO . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69
Figure 31: Mechanical Drawing of ACCO . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70
Figure 32: Electrical Drawing of ACCO . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70
Figure 33: Application part Window . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74
5 / 74
Figures
6 / 74
Preface
Preface
Purpose
Whats New
In Edition 02
Editorial improvement.
In Edition 01
Creation in B9.
Audience
Assumed Knowledge
7 / 74
Preface
8 / 74
1 General Information
1 General Information
This chapter provides general information concerning the operating principle
and requirements of the procedure:
Hardware description
Prerequisites
Restrictions
Initial state
Final state
Tasks sequences
Time schedule
Information required
Conventions.
9 / 74
1 General Information
10 / 74
1 General Information
M5 M
Master
M5M
M5 M
Upper Slave 1
Upper Slave 2
M5M
M5M
M5M
Lower Slave 11
Lower Slave 12
Lower Slave 21
Figure 3: Evolium A9110-E Pure Configuration (Maximum 6 Evolium A9110-E Modules, 12 TREs)
Evolium A9110 module allowed only as upper slave, no lower slaves can
connect to it.
11 / 74
1 General Information
M5 M
Master
M5M
M4M
Upper Slave 1
Upper Slave 2
M5M
M5M
Lower Slave 11
Lower Slave 12
Figure 4: Evolium A9110-E / Evolium A9110 Mixed Configuration (5 Modules: 4 Evolium A9110-E +1 Evolium
A9110, 10 TREs in total)
M5 M
Master
M4M
M 4M
Upper Slave 1
Upper Slave 2
Figure 5: Evolium A9110-E / Evolium A9110 Mixed Configuration (3 Modules: 1 Evolium A9110-E + 2
Evolium A9110, 6 TREs in total )
12 / 74
1 General Information
(2TRX, 2 ANT)
(2TRX, 2 ANT)
Width (mm)
450
385
Height (mm)
Characteristics
190
162
26
26
7-9
5.6
5.6
38.6 - 40.6
31.6
1.2 Restrictions
None.
1.3 Prerequisites
The following prerequisites apply:
The site must comply with the Safety rules ( See BSS Methods Handbook
)
The BSC must be operational and ready for BTS connection
The following requirement is not mandatory: antenna connected.
13 / 74
1 General Information
Figure 6: Example of A9110-E BTS ( Maximum 6 Evolium A9110-E Configuration With Cover )
Alarm points
for Customer
SLAVE 2
MASTER
SLAVE 1
Customer
Alarm
Box
230 VAC
Wire braid
1.5 m
Ground
Plate
14 / 74
1 General Information
NO
15 / 74
1 General Information
1st person
2nd person
10
10
10 / unit
10 / unit
15 / unit
15 / unit
5 / unit
5 / unit
10 / unit
10 / unit
5 / unit
5 / unit
10
10
BTS initialization
VSWR check
5 / unit
5 / unit
3(2)
3(2)
End of commissioning
5-10
Finishing commissioning
1h 32 - 2h 50
1h 08 - 2h 15
Preliminary checks
(3)
(1)
(2)
(3)
16 / 74
1 General Information
The times given are based on technical constraints, not taking into account
safety considerations.
Equipment configuration
Other
Software version
Test frequencies
Transmission configuration
Qmux address
OML TS and signalling rate (optional).
Antennas connected or not.
1.9 Conventions
The following list gives the conventions used in this document:
Press [ Enter ] means press the Enter key
Click [ OK ] means click the button OK with the mouse
Operator input is indicated after a double right-pointing arrow in Courier font
Operator input
To describe a menu path, the menu options are linked as follows:
Tools Options Printer ...
17 / 74
1 General Information
18 / 74
2 Preliminary Checks
2 Preliminary Checks
This chapter describes the preparation of the operation in two steps:
At base
On arrival at the site.
19 / 74
2 Preliminary Checks
20 / 74
Before the installation of the BTS units, check the lead seal.
If damaged, make a note in the CCL.
The installation procedure is the same for master and slave units.
21 / 74
1. The threaded bolt must be screwed into the M8 thread on top of the A9110-E
BTS housing, down to the internal screw-thread stop (See Figure 8 )
2. Do not tighten
3. Arrange the bolt with the flattened sides to the left and right.
22 / 74
1. The handwheel must be screwed down to the threaded bolt stop (See
Figure 9 )
2. Make sure the handwheel and bolt are not damaged
1. The gallows are plugged into the Mounting Frame (MOFRA) (See Figure 10 )
2. The safety catch (1) keeps the gallows in place.
23 / 74
1. Fix the metal pieces (3) with screws (4 two at each side) to each side of
the BTS Handle (2), see figure 11
2. Fix the assembly to the the hinge flanges, with one screw (4) at each
side (picture 12 )
1
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
123456789012345678
24 / 74
1. Fix the housing on the mounting frame with the two screws on top of
housing (See Figure 14 )
2. Fix the housing on COBO with the two screws left and right of COBO.
25 / 74
Check availability of the completed " Security control - check list and report
", enclosed with the crane (see " A9110 Crane Instruction Manual " ) the check
must be carried out every six months, note the check date in the CCL.
1. Check that the lifting ring and the two screws for fixing to MOFRA are
available
2. Mount the lifting ring onto the top part of the micro-BTS unit. The ring must
be screwed completely (See Figure 15 )
3. Put the crane on top of MOFRA. The small safety blade keeps the crane
in place (See Figure 16 )
4. Open the COBO door
5. Connect the crane power cable to the ACout BTS power connector (See
Figure 17 )
6. Hook the cables as shown in the drawings.
26 / 74
Crane
MOFRA
Power cable
27 / 74
Figure 17: ACout BTS Power Connector of ACCO Board is Used to Power the Crane
28 / 74
29 / 74
1. Lift the micro-BTS unit to an appropriate level for mounting (See Figure 18 )
2. Remove the bottom protection cover of the micro-BTS unit (3BK 08555 AA).
3. Fit the handle on the reel of the crane, on the left side
4. Move the micro-BTS nearer to the MOFRA (by pushing the handle) and fit it
onto the guide bolts (there are two guide bolts on MOFRA that must fit into
the back part of the micro-BTS unit)
5. Plug the micro-BTS unit into the COBO by slowly releasing the unit and
fitting the two guide pins of the COBO into the corresponding holes in the
micro-BTS housing
6. Fix the micro-BTS onto the MOCO using the four screws provided (See
Figure 19 )
7. Unhook the micro-BTS
8. Unplug the crane power cable
9. Remove the crane from MOFRA
10. Unscrew the lifting ring and put it with the crane to avoid losing it.
30 / 74
31 / 74
32 / 74
33 / 74
34 / 74
To install the VSWR detector on each micro-BTS unit (master and slaves)
This procedure is the same for master and slave units.
4.2.1 Mechanics
35 / 74
Procedure
1. Unlock the bottom section of the front protective cover, open it upwards and
fix it at the front cover by the installed magnetic snap-on fastening
2. Connect the VSWR detector to the antenna output connector of the A9110-E
by screwing the N male connector (See Figure 22 )
3. Connect the VSWR RF jumper cable to the RF output N-female connector of
the VSWR detector
4. Connect the standard antenna cable to the RF jumper cable.
Evolium
BTS A9110E
Antenna Jumper
COBO
VSWR
detector
F M
RF Jumper Cable
F M
M : Nmale connector
F : N female connector
Figure 22: VSWR Detector - RF Installation
36 / 74
37 / 74
38 / 74
SLAVE 1
MASTER
To SLAVE 2
From MASTER
To SLAVE 11
To SLAVE 12
To SLAVE 1
SLAVE 11
From SLAVE 1
SLAVE 2
From MASTER
SLAVE 12
To SLAVE 21
SLAVE 21
From SLAVE 2
From SLAVE 1
39 / 74
40 / 74
Before checking the power supply and powering up the micro-BTS, ensure
that the safety instructions in the SAF procedure are followed ( See BSS
Methods Handbook ). It is essential that:
The protective earth is connected to the equipment earth terminal
The ACout BTS connectors in the COBOs (Figure 25 ) that feed the
micro-BTS units are disconnected.
41 / 74
1. Check the power panel to make sure the breakers are OFF
2. Using a multimeter, check at each COBO that there is no voltage between L
(line) and N (neutral) , N and PE (protective earth), L and PE (See Figure 25 )
3. Close the circuit breakers at the power panel
4. Check the voltage (220 V AC) between line (L) and neutral (N) on the
ACout BTS connector of each COBO
5. Check that there is no voltage between N and PE
6. Power up the unit by plugging in their ACout BTS connectors.
FIRST power up the master unit, THEN power up the slave units!
The slave units MUST be powered up within seconds after powering
up the master unit.
1. Check the power panel to make sure the SSC breakers are OFF
2. Check the SSC to make sure main AC switch S1 is off and no green LEDs
are lit (See Figure 26 )
3. Close the circuit breakers at the site power panel
4. Close main switch S1, the AC mains breaker then the BTS1, BTS2,
BTS3 circuit breakers in the SSC
5. Check the 220 V AC voltage between line (L) and neutral (N) on the ACout
BTS connector (X401) of each COBO (See Figure 25 )
6. Check that there is no voltage between N and PE
7. Check that the Mains Power supply 1 and 2 and Charger LEDs are lit on
the SSC front panel
8. Push (if necessary) the Battery backup button to on (red LED is not lit)
9. Power up the A9110-E units by plugging in their ACout BTS connectors.
FIRST power up the master unit, THEN power up the slave units!
The slave units MUST be powered up within seconds after powering
up the master unit.
10. Check that the BTS remains on battery supply if main switch S1 is
disconnected, then set the switch S1 to ON
11. Push and hold down the Fan Test button and check that the SSC top fans
are working.
42 / 74
If the BTS must be powered down, disconnect the batteries first by pushing
the Back-up Off switch to ON (red LED is lit), then set the main power
switch S1 to OFF.
ACout
BTS
IEC Conn.
X402
FAN
BTS fuses
X401
X400
ACin, Mains
(T=2.5 A)
L
PE
N
L PE N
N
FAN fuses
(T=2.5 A)
L PEN
L PEN
SLAVE 2
SLAVE 1
X404
X403
Fan Test
PS1
PS2
PS3
Power Supply 1
Power Supply 2
Battery
backUp
button
Charger
Mains
BackUp
Off
Battery unit
S1
Power 230V AC
Socket
AC Connection Area 230V AC
AC BTS1 BTS3
mains
BTS2
43 / 74
44 / 74
6 Commissioning Tests
6 Commissioning Tests
This chapter describes the following operations:
BTS software downloading
Setting antenna mapping
BTS initialization
Performing BTS inventory
Setting and checking the external alarms
Checking status of modules
Checking the antenna VSWR
Abis loop test
End of commissioning.
Use the antistatic wrist strap when working with the ABISCO board.
Check that the BTS is isolated :
At the DDF side by disconnecting terminals, from the PCM link coming
from the network.
For installation with SSC, by disconnecting connectors X2, X3 and X4
on the connection area.
45 / 74
6 Commissioning Tests
1. Connect the BTS Terminal cable between the COM1 port of the PC and
the MMI connector (X100) on the ABISCO board of the master unit (See
Figure 28 )
2. Launch the BTS Terminal according to the OS used (Windows 2000/XP)
3. At the BTS Terminal enter:
If software upgrade must be performed during commissioning:
User/Group name :
UPGRAD
Password :
SUMSUP
If only commissioning must be performed:
User/Group name :
COMMTE
Password :
COMMTE
Click [ Logon ].
The Setup Information window usually appears.
If not already done, set the baud rate of the connection and the path
to the Inventar software
1. If the Setup Information window is displayed:
Click [ Baudrate ] or choose:
Settings Terminal
2. Select 115200 and the port under the Serial Interface tab in the BTS
Terminal part of the window
3. Select the Misc tab and if not already done, click [ Browse ] and select the
path to INVENTAR (usually c:\WINVENT\Program\pwinvent.exe)
4. Click [ Ok ].
46 / 74
6 Commissioning Tests
BE PATIENT:
47 / 74
6 Commissioning Tests
Workaround:
48 / 74
6 Commissioning Tests
Loop the External Alarm Inputs that are not Connected to Their Sensors
1. On the DDF loop the external alarms that are not connected to their sensors
to avoid reporting of alarms to the OMC-R
2. On the ABISCO board of each unit (master or slave) loop the declared alarm
inputs that do not reach the DDF and are not yet connected to their sensors.
49 / 74
6 Commissioning Tests
Note:
3. Plug in the fan power supply cable and check that the alarm is cleared.
Note:
Note:
50 / 74
6 Commissioning Tests
51 / 74
6 Commissioning Tests
Click [ Stop ]
Wait for MTRE to stop transmission.
After pressing the [ Stop ] button wait until MTRE stops transmission.
Follow the messages that appear in the bottom part of the window,
which indicates the state of MTRE.
3. Repeat the actions from step 2 for all the antenna outputs of all BTS
units (master and slaves).
Connect the power meter/ reflectometer between the BTS antenna jumper
and antenna or load as appropiate
1. For A9110-E BTS units with one antenna output:
connect the power meter/ reflectometer to the antenna jumper connected
to ANT A and use the following MTREs for transmission:
UT_TRE 18 or UT_TRE 19 for master
UT_TRE 38 or UT_TRE 39 for slave 1
UT_TRE 54 or UT_TRE 55 for slave 2.
UT_TRE 42 or UT_TRE 43 for slave 11.
52 / 74
6 Commissioning Tests
Measure the VSWR of the antenna (VSWR1) or across the load (VSWR2) if
there is no antenna
53 / 74
6 Commissioning Tests
Do not disconnect the power meter, the antenna or the load during MTRE
transmission. After pressing the [ Stop ] button wait until MTRE stops
transmission.
Follow the messages that appear in the bottom part of the window,
which indicates the state of MTRE.
If antenna VSWR 1 > 1.3 measure the VSWR (VSWR 2) using a load
1. Instead of antennas use 50 ohm loads
2. Measure the VSWR 2 values with the BTS TE in the same way as in
Measure the VSWR of the antenna (VSWR1)
3. Analyze the results: (See Table 1 )
VSWR 1 is the VSWR value measured in Measure the VSWR of
the antenna (VSWR1)
VSWR 2 is the VSWR value measured in Measure the VSWR (VSWR
2) Using a Load.
Value
Sanction
Action
VSWR 2 >1.2
VSWR 1 1.5
VSWR 2 1.2 and
VSWR 1 >1.5
54 / 74
6 Commissioning Tests
To test the PCM cabling between the master unit and DDF.
For Microwave or TNL installation in SSC for PCM connection, do not perform
Abis loop test.
Procedure
3. At BTS Terminal:
Click [ Ok ]
Remove the loops when the respective message window appears and
then click [ Ok ]
Wait for the test to finish
Check that the list of tests shown in the Station Unit Test window is Ok
Click [ Cancel ].
1. At BTS Terminal :
Commissioning End
commissioning
55 / 74
6 Commissioning Tests
56 / 74
57 / 74
Purpose
To set the Qmux address
To set the OML TS and signalling rate, if this information is provided.
Make sure the BTS is isolated at the DDF from the network before
proceeding.
Procedure
58 / 74
59 / 74
Purpose
To connect the BTS to the BSC and check the OML status.
Procedure
60 / 74
9 Finishing Commissioning
9 Finishing Commissioning
This chapter describes the final operations before leaving the site.
61 / 74
9 Finishing Commissioning
Purpose
To leave the site
To return the commissioning report and inventory files to base.
Procedure
62 / 74
Appendix A : Abbreviations
Appendix A: Abbreviations
Abis
ABISCO
AC
Alternating Current
ACCO
AN
Antenna Network
BCB
BCCH
BSC
BSS
BTS
CLK
Clock
COBO
COnnection BOx
CPF
DC
Direct Current
DDF
Dual Rate
E-GSM
ETS
FIT
Failure In Time
GSM
IEB
MD
Multi Drop
MDT
MMI
MOCO
MOFRA+COBO
MOFRA
MOunting FRAme
MSC
63 / 74
Appendix A : Abbreviations
MSUMA
MTRE
Micro-BTS Transceiver
MUX
Multiplexer
O&M
OMC
OMC-R
OML
OMU
PCM
RF
Radio Frequency
RI
Remote Inventory
RIT
Replaceable ITem
RSL
SDCCH
SBL
Security BLock
SSC
TCH
Traffic Channel
TRE
TRansceiver Equipment
TREA
TRED
VSWR
XBCB
XIN
External Input
64 / 74
The following table is used to check, on site, the mandatory or optional delivery
item kits.
The used symbols are:
mandatory kit
technical choice kit
customer option kit
Mnemo
Reference
Qty
PUIT - ANTG
1/ unit
PUIT - ANTD
1/ unit
VSWG
1/ ant
VSWD
1/ ant
List of Documents
Required
The following table is used to check, at base, the availability of the necessary
documents.
65 / 74
List of Software
Required
The following table is used to check, at base, the availability and version of
the necessary software;refer to corresponding document for checking the
SW version.
Name
Version checking
Operating system
BTS-Terminal
A9110 BTS-SW
Tools Required
The following table is used to check, at base, the availability of the necessary
tools (See Tools Catalogue for content checking).
Kit name
Reference
Calibration
Utility PC
DES 002
NO
Power/ reflectometer
DES 003
YES
Basic toolkit
OUT 001
NO
OUT 006
NO
OUT 013
NO
OUT 014
NO
66 / 74
67 / 74
LED2: SLAVE2
LED1: SLAVE1
X210
ABISTRACE
LED3: MASTER
X211 HDSL
LED4
BTS_LMT OK
LED8 :
X109
CALCLK
MPS
ON
X108
FCLK
X104,
X115
X105,
X112
X100: MMI
X200
LED5: ABIS1
X106,
X110
X107,
X102
LED6: ABIS2
LED7*
see table
68 / 74
Connectors Description
69 / 74
ACCO Board
ACout
BTS
IEC Conn.
FAN
X401
X402
X400
BTS fuses
ACin, Mains
(T=2.5 A)
L
PE
N
L PE N
N
FAN fuses
(T=2.5 A)
L PEN
L PEN
SLAVE 2
SLAVE 1
X404
X403
IEC connector
(cable lenght ~ 10 cm)
X400
LP
X401
AC in
AC BTS
(FFKDSA/V1 7.62)
T=2 x 2.5 A
X403
T=2 x 1.25 A
X402
ACo1
AC
FFKDSA/V1 7.62
ACo2
FFKDSA/V1 7.62
70 / 74
Master port B: 1
Example 2:
Master-slave configuration 3x4, no diversity
Master port A: 1
Master port B: 0
Slave 1 port A: 1
Slave 1 port B: 0
Slave 11 port A: 2
Slave 11 port B: 0
Slave 12 port A: 2
Slave 12 port B: 0
Slave 2 port A: 3
Slave 2 port B: 0
Slave 21 port A: 3
Slave 21 port B: 0
Example 3:
Master-slave configuration 2x6, with diversity
Master port A: 1
Master port B: 1
Slave 1 port A: 2
Slave 1 port B: 2
Slave 11 port A: 2
Slave 11 port B: 2
Slave 12 port A: 2
Slave 12 port B: 2
Slave 2 port A: 1
Slave 2 port B: 1
Slave 21 port A: 1
Slave 21 port B: 1
71 / 74
All the alarms that are not used are set to 255 . This means that they are
disabled.
Select each external alarm 1- 56 (See Figure 28 ) and modify the logical
number as required.
If you select [ Default Setting ] in the Remote Inventory window of
UT_BCB_17, the good values will be directly mapped for the alarms, detailed in
the following tables.
Note:
Note:
72 / 74
If the Fan Option was chosen, typical mapping of the fan alarms is:
Ext. alarm
(physical)
Number (logical) to be
mapped for dedicated
external alarm reporting
Refers to...
08
234
16
235
24
236
32
237
40
238
48
239
56
240
If the SSC Option was chosen, typical mapping of the SSC alarms is:
Ext. alarm
(physical)
Number (logical) to be
mapped
Refers to...
01
11
02
02
03
03
Note:
Note:
If the VSWR Option was chosen, typical mapping of the fan alarms is:
Ext. alarm
(physical)
Number (logical) to be
mapped
Refers to...
06
241
07
242
09
243
10
244
17
245
18
246
25
247
26
248
33
249
34
250
41
251
42
252
49
253
50
254
Refers to...
04
04
05
05
12
12
13
13
20
20
21
21
28
28
29
29
36
36
37
37
73 / 74
Refers to...
44
44
45
45
52
52
53
53
255
Disabled
74 / 74