1.

The strength of material is defined as:


a) Ability of material to resist external forces.
b) Ability of material to resist deformation.
c) Ability of material to with stand external loads.
d) None of the above.
2. Stress means:
a) Is the internal forces developed in material due to external forces.
b) Ability to resist external forces
c) Deformation in material caused of external forces.
d) Forces applied perpendicular to the longitudinal axis of a member.
3. The SPT-N values of Dense sand is equal to:
a) 0 20
b) 20 40
c) Larger than 50
d) 100

4. In above truss. If the temp of member B-C changed by 100 F. the displacement of point E
is equal to :
a) 3.52 mm
b) 9.83 mm
c) 8.3 mm
d) None of the above.
5. Critical path means:
a) Longest sequence of activities path in a project.
b) Shortest sequence of activities path in a project.
c) The path that have the maximum resources assigned.
d) The path with the longest tasks in project.

6. Add-Mixture are used in concrete for:


1. Increasing strength of concrete.
2. Reduce heat of concrete.
3. To increase workability of concrete.
4. Increase air content.
a) 1 & 2
b) 2 & 3
c) 3 & 4
d) 1 & 4
7. In pert chart the time estimate of activity is calculated by:
a) Normal.
b) Binomial.
c) Logarithmic.
d) None of the above.
8. The value of concrete cube strength is given at:
a) 1 day.
b) 8 days.
c) 28 days.
d) 35 days.
9. For simply supported beam the shear and flexural stresses will equal to Zero at:
a) End supports.
b) Middle of the span and above neutral axis.
c) Middle of the span and on the neutral axis.
d) End Supports and below neutral axis.
10. The summation of internal angles of 6 sides polygon:
a) 360.
b) 540.
c) 720.
d) None of the above.
11. Ministry of urban planning need to construct an exhibition center the location of this
center should be next to:
a) Airport
b) Buses stations.
c) In a high population area.
d) In a remote area.
12. ASHGAL responsible for:
a) Responsible of public housing.
b) Responsible of electrical and water services.
c) Responsible of urban planning.
d) None of the above.

13. Compaction in backfilling is used for:


a) Reducing water content in backfilled material.
b) Reducing air content in backfilled material.
c) Crushing of stones in backfilled material.
d) None of the above.
14. Last component that is added to cement production process is:
a) Silica.
b) Alumina.
c) Calcium sulfate.
d) None of the above.
15.
1)
2)
3)
4)

Ultra sonic pulse test is:


None destructive test.
Used in smooth concrete surfaces
A destructive test.
Used for testing of soil.
a) 1 & 2
b) 3 only
c) 3 & 4
d) None of the above.

16. 1) Concrete pouring.


2) Shutter striking.
3) Shutter erection.
4) Curing.
The correct sequence of work for concrete work is given by:
a) 4-1-2-3
b) 3-1-4-2
c) 3-4-1-2
d) 2-1-3-4
17. Slump test is used for:
a) Testing of workability of concrete.
b) Monitoring heat of dehydrated concrete.
c) Used to calculate strength of concrete.
d) None of the above.

18. How many layers of concrete is required in slump test:


a) 4 layers.
b) 2 layers.
c) 3 layers.
d) 7 layers.

19. One of the following is not a gypsum board characteristic:


a) Low coast in construction.
b) Can be easily formed in deferent shapes.
c) Can be recycled.
d) Fire resistance.
20. Super elevation is used at:
a) Straight Highways.
b) Car parkings.
c) Bus stations.
d) Horizontal curves.
21. 5 meter high retaining walls is back filled with sand (Unit weight = 19 KN/M3) with angle of
30. Earth lateral pressure will equal to:
a) 95 KN/m.
b) 55 KN/m.
c) 45 KN/m.
d) None of the above.
22. A car going on a speed of 60 mile/Hr on a curve highway. After passing midpoint the driver
saw an accident in front of him. The distance that will be passed from the moment the
driver saw the accident until he hit the brakes equal to:
a) 45 ft
b) 90 ft
c) 180 ft
d) None of the above.
23. Moisture Content range for timber that Is used in construction is equal to:
a) 0 to 2%.
b) 2 to 4%.
c) 10%.
d) None of the above.
24. Fast Track project means:
a) Project that starts before design is completed.
b) Cost plus fee project
c) Starts project with huge man power.
d) None of the above.

25. What is the meaning of crashing in project:


a) To increase project resources in order to reduce Project total duration.
b) Project will not finish on time.
c) Project will not achieve its scope.
d) None of the above.

26. What I the meaning of resource leveling:


a) Technique used to examine unbalanced use of resources over time.
b) Technique used to determine required resources for project tasks.
c) Report given to project manager about resources.
d) None of the above.
27. Minor limit design method for rectangular section will provide:
a) Minimum steel area, Minimum section dimension.
b) Minimum steel area, Maximum section dimension.
c) Maximum steel area, Maximum section dimension.
d) Maximum steel area, Minimum section dimension.
28. UPVC Pipe with station 0.00 and box culvert with station 163.666 ft. calculate the back
filling above the culvert:
a) 3 ft.
b) 4.7 ft.
c) 5.93 ft.
d) 2.5 ft.
29. Nominal moment for rectangular concrete cross section is given by:
a)
=
( )
b)

c)

d)

( )

(1 0.59

( )
)

30. A sample of 200 ml wastewater is given in a container (Weight of container = 22.00 g) and
was inserted in oven, after water evaporated the weight of sample was given as = 24.502 g
then the sample was inserted in a burning oven and the weight changed to = 22.606 g , the
volatile solids content for this sample is equal to:
a) 0.0095 g/ml.
b) 0.0584 g/ml.
c) 0.0081 g/ml.
d) None of the above.
31. The un-drained shear strength for clay is equal to:
a) Half of the unconfined compressive strength of clay.
b) Twice the unconfined compressive strength of clay.
c) One and a half the unconfined compressive strength of clay.
d) None of the above.