1. RA 9266, UAP Doc 200 to 208, 2006 Code of Ethics and 2010 Standards
of Professional Practice
It refers to person, firm, or corporation providing guarantee for
contractor's bonds.
A. Proposal
B. Guarantor
C. Bidder
D. Surety
satisfy
an
architectural
11.N
NOT included in the Project Construction Cost.
A.Site development plan elements designed by the Architect
B.Architectural interiors designed by the Architect
C.Alarm and Clock System indicated in the plans prepared by the Architect
D.Fees for the Architect
12. The value of extra work must NOTbe calculated using this method.
A.By estimate in lump sum
B.By unit prices not exceeding 25% of original work contract
C.By actual direct cost not exceeding 25% of original work
D.By actual direct cost + 15% profit, overhead and tax
13.
Repairs and corrective work must be done by the contractor within how
many days after written notice of owner.
A.5 days
B.10 days
C.15 days
D.7 days
14.Who does the architect approach for sound control?
A.Electronics Engineer
B.DJ
C. Acoustics Engineer
D.Electrical Engineer
15.
A type of Pre-Design Service where the Architect prepares the detailed
analysis of the site involving the identification of a site's development
potentials through the proper utilization of land. The analysis covers the
context of the site as well as that of the environment immediately outside
and the development controls that apply to the site and its environs.
A.Site Utilization and Land-Use Studies
B.Value Management
C.Consultation
D.Site Selection and Analysis
16.Doesn't represent work and doesn't involve duration and cost; it only
serves as dependency connector or sequence indicator.
A.Dummy activity
B.Critical path
C.Slack
D.Float
34.
Longest path in time through the network; delay in one of the activities
will increase the project duration.
A.Critical path
B.Slack
C.Dummy activity
D.Float
35. Can the term 'Architect' and 'Architect-of-Record' be used
interchangeably?
A.Yes, they are both the same
B.Can the term Architect and Architect-of-Record be used interchangeably?
C.Maybe, depending on the type of work
D.No, the Architect is a generic word while AoR is a specific function of a
professional architect.
36.NOT chargeable to the Client under Pre-Design Services.
A.Living and housing allowance of foreign consultants
B.Office overhead expenses
C.Cost of transportation
D.Out-of-town living and housing allowances of the local consultants and the like
37. How many percent completion of work shall the Architect inspect and
issue the Certificate of completion?
A.96%
B.98%
C.95%
D.97%
38.What government entity is responsible in regulating the practice of
architecture?
A.PRC-PRBoA
B.UAP-IAPOA
C.DTI/SEC
D.DOJ
39. The multiple of direct personnel expense is applicable to what type of
work?
A.Research
B.Creative work
C.Ocular site inspection
D.Government projects
40.In case of death of the Architect-on-Record, who can give official
provisions to reproduce his/her plans?
A.The courts
47.
The Client has already approved the designs of the typical house models
for a subdivision project. The Architect continued with the preparation of
the construction drawings. At this stage, the Client asked the Architect to
prepare also scale models of the different house models to be used in
selling the house and lot packages. How will the Architect charge for
them?
A.Determine the cost by arbitration.
B.It is part of the design studies required for presentation to the client and no
additional fee is to be charged.
C.The cost for each scale model will be charged in addition to the basic
fee.
D.It is already included in the Architects basic fee.
48.What is the difference between RA 545 and RA 9266 in terms of
architectural practice?
A.Corporate practice
B.Structural conceptualization
C.Authorship of documents
D.Two-years diversified experience
49.In what phase of the architectural design services does the feasibility
study is conducted?
A.Specialized Allied Services
B.Regular Design Services
C.Comprehensive Architectural Services
D.Pre-Design Services
50.Under comparative selection, the first step in the selection process
involves Invitation. The Client issues an invitation which includes the Terms of
Reference (ToR) for the project which is based on the ________ prepared
by another Architect.
A.Design Brief
B.Conceptual framework
C.Schematic design
D.Architectural program
51.NOT classified under Group 5 monumental buildings and other
facilities requiring consummate design skill and much precise detailing.
A.Mausoleums
B.Memorials
C.Exhibition halls
D.Exposition buildings
52.
This area of practice recommends the systematic process of ensuring that
a building/structure's array of systems is planned, designed, installed and
tested to perform according to the design intent and the building's
operational needs.
A.Building Systems Design
B.Building Testing and Commissioning
C.Facilities Maintenance Support
D.Security Evaluation and Planning
53.Method of selection of an Architect conducted by
representing institutions, corporations or public agencies.
A.Direct selection
B.Institutional method
committees
C.Comparative selection
D.Design competitions
54.
Mr. Juan de la Cruz commissioned you for a restaurant project last year.
Due to the success of the restaurant, he wants you to do a 2 ndrestaurant
using the same design. Based on the old 1979 SPP, what would be your
fee?
A.80% of Basic Fee
B.60% of Basic Fee
C.30% of Basic Fee
D.40% of Basic Fee
55.
For specialized allied services, what is the activity of total planning that
encompasses social, physical and environmental factors?
A.Comprehensive Architectural Services
B.Physical Planning
C.Environmental Planning
D.Comprehensive Planning
56. If an Architect assumes the function of going to the project site for
monitoring and supervision, what services is being provided?
A.Construction Inspector
B.Construction Management
C.Full-time Construction Supervision
D.Project Supervision
57.
When the Owner fails to implement the plans and documents for
construction as prepared by the Architect, the Architect is entitled to
receive as compensation the sum corresponding to ___ (%) percent of the
Architect's fee.
A.80
B.85
C.90
D.95
58. An architect suggested to the client that a blank wall in one of the
portion of the lobby be provided with a mural painting. The client agreed
and asked the Architect to present a design for the mural painting. The
Architect hired a popular painter to make the concept design. Who will pay
for the services of the mural painter?
A.Architect
B.Already included in the fees of the Architect
C.Client
D.To be decided by arbitration
59.You were commissioned to do a Master Plan. What should you do
Next
first?
A.Study the existing laws
B.Survey the location
C.Direct all department heads
D.Coordinate with the local government for tracing of history
60. Period for which claim for adjustment has to be asserted for changes
in the work.
A.10 days
B.20 days
C.15 days
D.5 days
Owner-Architect
D.1-1.5% of PCC
69.Archt. Steve explains his methodology to the selection committee
regarding how he would translate the plan/design requirements of the
proposed store renovation of CMG store in Rockwell. Under what stage in
the comparative selection process is this?
A.Verification
B.Interview
C.Evaluation and Ranking
D.Negotiation
70. Which of the following is a responsibility of the Architect in the
Construction Phase of the Regular Design Services?
A.Makes exhaustive on-site supervision
B.Makes periodic visits to the site
C.Be held responsible for failure of contractor to carry out work
D.Prepares shop drawings
71. Which is an unethical action with respect to the Architect's
responsibility to his colleagues and subordinates?
A.Donates to obtain advantage in a religious project
B.Serving as professional adviser, accepts employment as Design Architect
for a competition project.
C.Undertakes a commission from another Architect duly notified
D.Provides free professional service for a charitable project
72.Who is responsible for the soil investigation of the project?
A.Owner
B.Construction Manager
C.Project Manager
D.Contractor
73.
Instructions issued prior to bidding to supplement or modify previous
contract docs.
A.Instruction to Bidders
B.Special Provisions
C.General Conditions
D.Bid Documents
74. If there are two architects on a certain project, the Architect-of-Record
and the Architect-in-Charge of construction, the building collapses, who is
more liable?
A.Architect-of-Record
B.It depends on the investigation
C.Architect-in-charge of Construction
D.Both will be liable
75.Contract time starts how many days after receipt of Notice to Proceed.
A.5 days
B.10 days
C.15 days
D.7 days
76.
The Consulting Architect in this area of practice places value on the
building/ structure condition and defects, and on its repair and
maintenance, including the required improvements. Appraisal is
universally defined as an act or process of estimating value.
A.Building Components
B.Building Appraisal
C.Security Evaluation and Planning
D.Forensic Architecture
77.The Architect in this area of practice engages in methods of producing
building components in a highly engineered, efficient and cost-effective
manner, particularly for residential and commercial applications.
A.Forensic Architecture
B.Building Systems Design
C.Facilities Maintenance and Support
D.Building Environment Certification
78.Before submitting sketches to a client, what must the architect first
do?
A.Prepare the probable construction cost
B.Bill for downpayment
C.Discuss board for presentation
D.Sign a service agreement
79.The Consulting Architect in this area of practice must have much more
than the basic knowledge of Green Architecture and Environmental and/or
Sustainable Design and sufficient knowledge of the governing
environmental
laws
and
environmental
investigation
processes/
procedures under international protocols, the Philippine Solid Waste,
Clean Air and Clean Water Acts, DENR administrative issuances and the
like.
A.Forensic Architecture
B.Building Testing and Commissioning
C.Special Building/Facility Planning and Design
D.Building Environment Certification
80.No extension will be granted if no written request for materials
supplied by Owner is made by the contractor ____ days before it is needed.
A.10 days
B.15 days
C.20 days
D.5 days
81.In what type of services do making of brochures/leaflets/fliers/posters
and promotional & advertisement campaign are included?
A.Pre-Design Services
B.Specialized Allied Services
C.Comprehensive Architectural Services
D.Regular Design Services
82.NOT included in the Project Construction Cost.
A.Air-Conditioning System designed by an Engineer hired by the Architect
B.Site development plan elements designed by the Architect.
C.Fire Protection Systems designed by an Engineer hired by the Architect.
D.Architectural interiors design by another Architect.
83. How many sets of plan are to be given/submitted to the owner?
A.7
B.6
C.5
D.4
84.Project Development Cost shall include:
Construction Cost
Professional Fees
Permits
Lot Acquisition
Clearances
A.I, iii, iv, v
and
other