To:
The Superintending Engineer
Public Health Circle,
Rajahmundry.
Lr.No. 25/TNK/UIDSSMT/TS-ATO/2013,
Dt.
10 -2013.
Sir,
Sub:- PH & ME Department Tanuku Municipality -Investigation, Survey,
Ref:-
The Government vide G.O. Ms. No. 83MA & UD Dept., Dated 18-01-2008
has accorded Administrative Sanction for Rs.2824.00 Lakhs under UIDSSMT Scheme to
take up the Tanuku Water Supply Impro vement Scheme with Narsapur - Mogaltur canal
as source. Accordingly technical Sanction was accorded by the Engineer-in-Chief (PH),
Hyderabad for Rs.2824.00 Lakhs and registered vide ENC (PH) R.No.37/2008-09 dated
11-06-2008.
The Technical parameters of the work such as scope, objective and final
deliverables of the project, Internal Bench Marks (IBM),approval of live bid
document were got approved by EPC Committee-I in June2008. The Committee
has approved the Internal Bench Mark for Rs.2186.62 Lakhs.
Tender for the above work was invited under EPC contract system. The
Tender was approved by the Committee-II in June2008 and work was awarded to
M/s. Ramky Infrastructure Ltd, Hyderabad. The firm has entered in to agreement
vide Superintending Engineer (PH), Rajahmundry. Agreement No.8/2008-09
Dated.26-11-2008 for Rs.22,94,85,769 at (+) 4.95% excess over Internal Bench
Mark value of Rs. 21, 86, 62,000=00.
The present status of work is as follows:
S.No Description
1
850 ML Capacity S.S.Tank
2
Status
Land acquisition to be taken up by
the Revenue Department.
Off-Take Chamber, Raw water collection 100% Completed and
3
4
5
6
7
commissioned.
100% Completed and commissioned.
100% Completed and commissioned.
100% Completed and commissioned.
100% Completed and commissioned.
100% Completed and commissioned.
Financial Progress:
The Physical and Financial Progress during the Agreement as well as Extension of
time Period.
Milestones as per the
Agreement
Sl.
No
Description
Financial In Lakhs
Physical
in %
Financial
In Lakhs
Initial
Cumul
ative
Initial
Cumu
lative
100
2294.86
0.00%
4.36 %
0.00
100.06
4.36%
29.50%
100.06
676.98
29.50%
54.40%
676.98
1248.40
54.40%
57.19%
1248.40 1312.36
Total
100
2294.86
57.19%
1312.36
At present except Summer Storage Tank all works are completed in the scheme and
the scheme was put in utilization.
The S.S Tank proposed at Peravali village in an extent of 64.00 Acres is not
commenced so far. Though an amount of Rs.4,50,46,000/-deposited to the RDO,
Kovvour, the land acquisition for the summer storage tank & allied components is not
completed till today by the Revenue Department since it was delayed initially due to court
cases, after clearance of court cases, the Draft notification was published on 08/03/2013
but it was stalled again due to the objections raised by the private land owners. The EPC
agency requested to delete the summer storage tank & allied components from their
scope of work vide their Lr.No.RIL/PH&MED/TNK-WSIS/UIDSSMT/2013, dt.3.10.2013
with reference to the letter 10th cited ENC (PH) Hyderabad has requested the
Government to close the scheme except S.S Tank since all works are completed and the
scheme is running. However in this connection permission from the Government is still
awaiting.
Further it is to submit that the entire work should be completed within the 2 nd
EOT period i.e 30-09-2012, but the EPC Agency has not completed the work within the
2nd EOT period and applied extension of time proposals along with revised programme
chart up to 30-09-2013 with the following reasons vide reference 9 th cited.
Due to the delay of payments of RA bills i.e especially 8th RA bill was submitted
on16-11-2011 and the bill was paid on 27-3-2012 after 5 months. Delays in
Delay in Construction of Raw Water Collection Well & Pump House & Site
Protection wall at off-take point @ Peravali due to objections of surrounded private
Delay in Laying of Raw Water Pumping Main due to objection by the Azzaram
Villagers for laying pipe line through their village from 23/06/2012 to 15/09/2012.
Delay in Laying of Clear Water Pumping Main across the NH-5 due to due to delay
In spite of the all above delays the EPC Agency has completed the
maximum components of the scheme excluding summer storage tank & allied
components till 30-09-2012 are as follows.
a. Off-take Chamber at Peravali (100%)
b. Raw Water Collection Well at off-take point (100%)
c. Raw Water Pump House at off-take point except finishing (100%)
d. Raw Water Pumping Main Laying & Testing (100%)
e. Stilling Chamber, Measuring Channel & Flash Mixer (100%)
f. Chemical House, Clariflocculator & Chlorine Room (100%)
g. 9 MLD Filter House (100%)
h. Clear Water Sump, Clear Water Pump House (100%)
i. Site Protection Wall around WTP (100%)
j. Clear Water Pumping Main Laying & Testing (100%)
K.1660KL ELSR at Santha Market with site protection wall (100%)
l. Distribution Network Laying & Testing (90%)
m. Road Restoration except CC road (80%)
But the following minor components are not completed within the
E.O.T period for which LD is proposed (Statement Attached Separately).
a. Finishing work of raw water pump house at off-take point.
In View of the above reasons the firm has requested to grant the
Extension of Time up to 30-09-2013 to complete the Tanuku WSIS excluding the
construction of Summer Storage tank and allied components .The firm also submitted the
revised mile stone programme and revised planning schedule and committed to complete
by September 2013.
In these circumstances the reasons explained by the EPC Agency
and the same was recommended by the Deputy Executive Engineer (PH)
Bhimavaram, the EOT proposals upto 30-9-2013 with imposing Liquidated
Damages of Rs. 1,09,872/- for delayed components which are completed after
the E.O.T period i.e. 30-09-2012 are herewith submitted for perusal and taking
further necessary action .
The firm representation in original together with proposals for
extension of time, revised work programme charts is herewith submitted for favor
of perusal and requested to place the proposals in Committee-III for approval.
Yours faithfully,
Encl:- 1. Proposals for Extension of time
2. Revised construction Programme
3. Firm Representation.
4. LD Statement.
ELURU.