Escolar Documentos
Profissional Documentos
Cultura Documentos
By
Joseph Pikas
NACE CP & Corrosion Specialist
NACE RP0169 states that external corrosion control of steel and cast iron piping may be
achieved if there is a minimum of 100 mV of cathodic polarization between the structure
surface and a stable reference electrode contacting the electrolyte. Measurement of
cathodic polarization with the cathodic protection (CP) system energized or polarization
decay when the CP system is turned off are both acceptable methods of evaluating
conformance to this criterion.
Despite widespread acceptance of this protection criterion by the corrosion control
industry, most CP practitioners prefer to evaluate their CP system effectiveness against
the -850 mV potential criterion. The simplicity of a single potential measurement versus
multiple measurements or continuous observation of cathodic polarization buildup or
decay is the deciding factor for operators concerned with monitoring costs.
However, aging coating systems and increasing use of IR free or instant off polarized
potential measurements have resulted in increased use of the 100 mV polarization
criterion. In a recent industry survey of 75 CP practitioners/users, the number of
companies employing the 100 mV polarization criterion has increased 300% (from 26%
to 76%) in the last ten years. While most of the survey respondents report using the
polarization criterion for only a small percentage of their system (11% on average), the
trend towards more widespread use in locations where it offers advantages of users is
clearly established.
The following discussion assumes familiarity with NACE TM0497-97, Measurement
Techniques Related to Criteria for Cathodic Protection of Underground or Submerged
Metallic Piping Systems. This report is intended to summarize the circumstances where
the 100 mV polarization criterion is most often utilized, as well as identify some of the
sensitivities and problems associated with testing to this criterion.
WHEN TO USE THE CRITERION
The majority of CP practitioners surveyed utilize the polarization criterion only in areas
where it is uneconomical or impractical to achieve the -850 mV CSE potential criterion.
However, there may be circumstances where a polarization criterion is preferred for
technical reasons. These rationale are categorized as follows:
potentials on the well coated parts of the protected structure leading to accelerated
coating damage. Several pipeline operators cite coating preservation as a significant
factor in their decision to use the 100 mV polarization criterion.
The True Criterion:
Because the polarized survey involves an interrupted on/off survey and a second
depolarized survey some time later, the additional cost of the polarization survey must be
balanced against the additional cost of CP to assure one of the first two NACE criteria.
Many will perform an on potential or an off potential survey first and then, when adding
incremental cathodic protection is undesirable, proceed to perform a polarization survey
to determine whether or not 100 mV or more of polarization exists.
IMPLEMENTATION
In addition to the test methods outlined in TM0497-97, the following comments are
provided:
Polarization Growth vs. Decay:
Application of any monitoring procedure should be practical. It is recommended that
new, unprotected structures have a complete native state (static) potential survey
performed prior to initial application of cathodic protection. This will ensure that
unusually high native potentials are considered appropriately, and provide an excellent
baseline for a polarization survey. This survey will necessarily be conservative for two
reasons: a) the rest potential of the protected structure will typically become more
positive as the system ages, and b) if monitoring of the cathodic polarization is
terminated when 100 mV of polarization is achieved a steady state level of polarization
(which would be more cathodic) may not yet be achieved.
For existing facilities, it is most practical to establish the level of polarization through
monitoring of depolarization. This test will also be conservative, because the native
potential may not yet be achieved once 100 mV has been observed and the CP systems
re-energized.
It is important to observe basic guidelines for monitoring either polarization or
depolarization:
Seasonal Variations in Native Potentials:
Seasonal variations in native (free corrosion) potential vary geo-climatically, with
structure age and CP history. These variations can change the native potential by 100
mV or more. It is therefore critical that the native potentials be taken within a short time
of the polarized potential. For these reasons the depolarized potential should be taken
every time the 100 mV criterion is evaluated in order to correctly determine the amount
of polarization and confirm a 100 mV shift.
Because the polarized potential and native potential may fluctuate seasonally, a
conservative approach is to perform the 100 mV criterion evaluation when polarization is
the lowest. Polarization tends to decrease when moisture around the structure increases,
and the structure temperature increases. These cycles are typically seasonal in nature and
may or may not occur at the same time depending upon geo-climatic location and
pipeline operating characteristics.
total current applied, the amount of bare metal, the size of the structure, the environment
and other factors. Polarization times can range from a few seconds to days to weeks.
One means of determining the polarization time is to use a recording voltmeter to
generate a plot of the polarization curve. The time for a structure to polarize after current
is applied may be considerably different form the time for the structure to depolarize after
the current is removed.
Measurement of the polarization on a structure requires the measurement of the instant
off potential. This measurement requires the installation of current interrupters on the
current sources influencing the structure. The instant off potential can be obtained by
interrupting all the current sources simultaneously or by interrupting each current source
one at a time and using superposition to determine the actual instant off potential.
Depending on the location where the interrupter is installed and the resistance, inductance
and capacitance of the circuit, interruption of the DC current can cause spiking in the
instant off potential and thus erroneous data.
Polarization testing can be performed on a system protected by galvanic anodes if the
current from the anodes can be interrupted. Isolated directly connected galvanic anodes
do not have to be disconnected if there are sufficient other current sources to achieve the
required amount of polarization.
The amount of polarization of a structure is proportional to the current applied. The
depolarized potential or native potential of a structure will decrease in magnitude with
time and polarization, with the depolarized potential decreasing approximately in direct
proportion to the amount of polarization. 2
Monitoring Practices
The 100 mV polarization criterion can be met by measuring either the amount of
polarization from native potentials or the depolarization after the cathodic protection
system has been in service time to allow for complete polarization. Polarization testing is
usually performed by measuring the native or static potential of a system before any
current is applied. The cathodic protection system is then energized and the system
allowed to polarize until the on potential stabilizes. On and instant off potentials are then
measured with the polarization being the difference between the instant off and the native
potential. Coupons can also be used to measuring the amount of depolarization.
Depolarization testing is usually performed by measuring the on and instant off
potentials, turning the current sources off, and allowing the system to depolarize. After
the system has depolarized, the potential is again measured. The amount of polarization
is the difference between instant off potential and the depolarized potential.
Depolarization may take from a few minutes to a number of weeks. .
Once the 100 mV criterion has been established at a location, verification is usually
performed on a periodic basis. . One way to accomplish this is by repeating the complete
polarization testing. Another is to use either the on or instant off potential reading
obtained during the initial testing as a measure of the effectiveness of the criterion if there
have been no significant changes in the system being protected.
Retesting time frames for performing a complete polarization test usually vary from one
to five years with some going longer. Retesting is usually driven by changes in the
system that is being protected. These changes can include changes in rectifier current
output, changes in the amount of material being protected, changes in cathodic system
configuration, environmental changes, etc.
Advantages and Disadvantages
Cost of survey
The cost to perform a survey to demonstrate the 100 mV shift criterion is greater than the
850 mV criterion. There is duplicate effort required in that the areas have to be
surveyed twice. In addition, the cost of analysis is more, since the interpretation of the
data is more involved. The areas that meet the 850 mV criterion may not be resurveyed
to demonstrate 100 mV shift criterion in order to reduce the cost. Since the 100 mV
criterion is often applied to older pipe systems, some companies perform close interval
surveys of the on, instant off and depolarized potentials. This also adds additional cost.
Additional cost in some areas is due to the time required to depolarize, in some cases
requiring 30 days or more to fully depolarize.
Conversely, performing a 100 mV polarization survey can reduce costs by reducing the
amount of remediation necessary to demonstrate compliance to criteria, as well as allow
work to go on a more practical schedule, since compliance has been demonstrated, and
prompt remedial action timeframes are not required to be met.
Cathodic protection coupons can reduce the cost of obtaining the polarization shift data.
The 100 mV shift criterion is not be valid for use on systems with the interconnection of
different metals (e.g. steel pipe connected to copper grounding system) In addition, for
galvanic cathodic protection systems, a depolarized survey may not be practical to
perform.
Cost of current
Facilities that meet the 100 mV shift criterion have less current required in most soil
conditions. Applying the criterion is almost always less expensive than recoating or
installing additional cathodic protection current.
Reduction of cathodic protection current should always be performed following complete
depolarization. This may be necessary where the cost of current is extremely high, for
Level of Protection
The 100 mV shift criterion is a more technically correct criterion than potential criteria.
There are concerns about the possibility of high pH SCC. Some regulatory agencies do
not accept the 100 mV shift criterion. Annual demonstration of compliance can be
expensive if the entire survey is required to be performed annually.
The 100 mV shift criterion can reduce the possibility of overprotection, including
cathodic disbondment and hydrogen embitterment, and reduce the risk of stray current.
Effects of Heat and Bacteria
Hotter environments and the present of bacteria tend to increase the amount of
polarization required to obtain protection. In these cases, more than a 100 mV of
polarization may be required.
IR Drop Errors
IR drop errors can be a problem in the interpretation of some of the cathodic protection
criteria. Due to using the instant off potential in the 100 mV polarization criterion, IR
drop errors are not a problem.
Stress Corrosion Cracking (SCC)
SCC can be a problem for some pipelines operating in certain environments. One of the
variables that affect the susceptibility of a pipeline to SCC is the instant off potential.
The instant off potential of pipelines protected using the 100 mV criterion may fall in the
range of potential that are susceptible to SCC. It may be necessary to increase value of
polarization where SCC is suspected such as underneath shielded high dielectric type
coatings.
Note:
For Additional Information see NACE TM0497-97, Measurement Techniques
Related to Criteria for Cathodic Protection of Underground or Submerged Metallic
Piping Systems.