Você está na página 1de 36

PEKERJAA

EX

NO
1
I
A.
B.

II
A.
1
2
3
4
5
6
7
8
9
10

B.
1
2
3
4
5
6
7
8

C.

NO
1
D.

E.

F.
1
2
3
4
5

G.

H.

BILL OF QUANTITY (B
PEKERJAAN SIPIL
PEKERJAAN PEMBANGUNAN PRASARANA, POND
EXTENSION 150 kV GI PLTU II KALBAR

URAIAN KEGIATAN
2
PEKERJAAN PRASARANA
PEKERJAAN PERSIAPAN
PEKERJAAN PEMATANGAN TANAH

PEKERJAAN SWITCH YARD


PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN

PONDASI
PONDASI
PONDASI
PONDASI
PONDASI
PONDASI
PONDASI
PONDASI
PONDASI
PONDASI
PONDASI

SWITCHYARD
C-11 ( 1 UNIT )
C-12 ( 1 UNIT )
C-23 ( 1 UNIT )
LA ( 1 UNIT = 3 PONDASI )
CPD (1 UNIT = 3 PONDASI )
CT /CVT ( 1 UNIT = 3 PONDASI )
CB ( 1 UNIT = 3 PONDASI )
DS / DSE ( 1 UNIT = 3 PONDASI )
MK ( 1 UNIT )
CPD BUS (1 UNIT)

PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN

CABLE DUCT DAN TUTUP CABLE DUCT


CABLE DUCT TYPE. I ( 1 m' )
CABLE DUCT TYPE. II ( 1 m' )
CABLE DUCT TYPE. III ( 1 m' )
CABLE DUCT TYPE. IV ( 1 m' )
CABLE DUCT TYPE. V ( 1 m' )
PIPA CONDUIT TYPE I ( K1 / DS)
PIPA CONDUIT TYPE II ( K2 / CB )
PIPA CONDUIT TYPE III( K3/ CT, CPD)

PEKERJAAN PENYANGGA KABEL/ CABLE TRAY

URAIAN KEGIATAN
2
PEKERJAAN DRAINASE (BAK KONTROL)

PEKERJAAN HAMPARAN KORAL & KANSTEEN

PENGADAAN DAN PEMASANGAN KONSTRUKSI BAJA U/ GANTRY


STEEL STRUCTURE U/KOLOM C-11 + MURBOUT LENGKAP
STEEL STRUCTURE U/KOLOM C-12 + MURBOUT LENGKAP
STEEL STRUCTURE U/KOLOM C-23 + MURBOUT LENGKAP
STEEL STRUCTURE U/ BEAM P-12 + MURBOUT LENGKAP
STEEL STRUCTURE U/ BEAM P-23 + MURBOUT LENGKAP

PEKERJAAN PAGAR SWITCHYARD

PEKERJAAN SALURAN SWITCHYARD

ANTITY (BOQ)
AAN SIPIL
ANA, PONDASI SWITCHYARD 2 LINE BAY
II KALBAR, KALIMANTAN BARAT

SATUAN

VOLUME

Unit
Unit

HARGA
SATUAN
(Rp)
5

1.00
1.00

JUMLAH
HARGA
(Rp)
6

JUMLAH I

Unit
Unit
Unit
Unit
Unit
Unit
Unit
Unit
Unit
Unit

2.00
2.00
1.00
2.00
4.00
2.00
6.00
2.00
-

M'
M'
M'
M'
M'
Set
Set
Set

Ls

21,881,810.00
21,881,810.00
28,291,210.00
34,066,980.00
6,848,900.00
JUMLAH A

43,763,620.00
87,527,240.00
56,582,420.00
204,401,880.00
13,697,800.00
405,972,960.00

50.00
30.00
60.00
6.00
2.00
4.00

2,416,710.00
2,050,010.00
1,636,120.00
342,050.00
1,290,000.00
2,096,250.00
JUMLAH B

120,835,500.00
61,500,300.00
98,167,200.00
2,052,300.00
2,580,000.00
8,385,000.00
293,520,300.00

1.00

42,000,000
JUMLAH C

42,000,000.00
42,000,000.00

SATUAN

VOLUME

HARGA
SATUAN
(Rp)
5

JUMLAH
HARGA
(Rp)
6

set

2.00

7,865,329
JUMLAH D

15,730,658.78
15,730,658.78

Ls

1.00

129,031,597
JUMLAH E

129,031,597.47
129,031,597.47

Set
Set
Set
Set
Set

2.00
2.00
1.00
4.00
2.00

JUMLAH F

Ls

1.00

64,110,480.00
JUMLAH G

64,110,480.00
64,110,480.00

Ls

1.00

45,328,197.74
JUMLAH H
JUMLAH II

45,328,197.74
45,328,197.74
995,694,193.99

PEKERJA

NO
1
I.
A.
1
2
3
4
5
6
7

B.
1
2

II.
A.
1.
1
2
3
4
5
6
7
8
9
10
11

NO
1
2.
1
2
3
4
5
6
7
8
9
10
11

3.
1
2
3
4
5
6
7
8
9
10
11

NO
1
4.
1
2
3
4
5
6
7
8
9
10
11

5.
1
2
3
4
5
6
7
8
9
10
11

6.
1
2
3
4
5
6
7
8
9
10

NO
1
11

7.
1
2
3
4
5
6
7
8
9
10
11

NO
1
8.
1
2
3
4
5
6
7
8
9
10
11

9.
1
2
3
4
5
6
7
8
9
10

10.
1
2
3
4
5
6
7
8
9
10
11

NO
1
B.
1.
1
2
3
4
5
6
7
8

NO
1
2.
1
2
3
4
5
6
7
8

3.
1
2
3
4
5
6
7
8

4.
1
2
3
4
5
6
7
8

5.
1
2
3
4
5

NO
1
6
7
8

6.
1
2
3
4
5
6

7.
1
2
3
4
5
6

NO
1
8.
1
2
3
4
5
6

C.
1
2
3
4
5

D.
1
2
3
4
5
6
7
8
9

E.
1
2
3
4
5

F.
1

NO
1
2
3
4
5

G.
1
2
3
4
5
6
7
8
9
10

H.
1
2
3

HARGA PERKIRAAN ENJIN


PEKERJAAN SIPI
PEKERJAAN PEMBANGUNAN PRASARANA, PO
EXTENSION 150 kV GI PLTU II KALBA

URAIAN PEKERJAAN
2
PEKERJAAN PRASARANA :
PEKERJAAN PERSIAPAN
Pembersihan lokasi
Penyediaan Direksi Keet, Gudang dan Barak Kerja
Mobilisasi dan Demobilisasi
Mobilisasi dan Demobilisasi alat borepile
Membuat papan nama ( Nama proyek, jadwal pelaksanaan dan lay out )
Pengukuran dan Pemasangan Bouwplank
Sondir

PEKERJAAN PEMATANGAN TANAH


Pekerjaan Stripping Tanah
Pekerjaan Urugan Tanah dari luar

PEKERJAAN SWITCH YARD


PEKERJAAN PONDASI SWITCHYARD
PEKERJAAN PONDASI GANTRY C-11 ( 1 UNIT )
Galian tanah untuk podasi
Urugan pasir
Urugan tanah kembali
Buangan tanah sisa galian
Borepile beton K-225 dia. 40 cm, L = 4 meter, (8 titik)
Beton Beton Lantai kerja B-0
Beton K - 225
Beton Grouting camp. 1PC : 1.5 Psr : 2.5 Krl
Besi Beton U-24
Anchor lengkap
Bekisting

URAIAN PEKERJAAN
2
PEKERJAAN PONDASI GANTRY C-12 ( 1 UNIT )
Galian tanah untuk podasi
Urugan pasir
Urugan tanah kembali
Buangan tanah sisa galian
Borepile beton K-225 dia. 40 cm, L = 4 meter, (8 titik)
Beton Beton Lantai kerja B-0
Beton K - 225
Beton Grouting camp. 1PC : 1.5 Psr : 2.5 Krl
Besi Beton U-24
Anchor lengkap
Bekisting

PEKERJAAN PONDASI GANTRY C-23 ( 1 UNIT )


Galian tanah untuk podasi
Urugan pasir
Urugan tanah kembali
Buangan tanah sisa galian
Borepile beton K-225 dia. 40 cm, L = 4 meter, (8 titik)
Beton Beton Lantai kerja B-0
Beton K - 225
Beton Grouting camp. 1PC : 1.5 Psr : 2.5 Krl
Besi Beton U-24
Anchor lengkap
Bekisting

URAIAN PEKERJAAN
2
PEKERJAAN PONDASI LA ( 1 UNIT = 3 PONDASI )
Galian tanah untuk podasi
Urugan pasir
Urugan tanah kembali
Buangan tanah sisa galian
Borepile beton K-225 dia. 40 cm, L = 4 meter, (1x3 titik)
Beton Beton Lantai kerja B-0
Beton K - 225
Beton Grouting camp. 1PC : 1.5 Psr : 2.5 Krl
Besi Beton U-24
Anchor lengkap
Bekisting

PEKERJAAN PONDASI CPD (1 UNIT = 3 PONDASI )


Galian tanah untuk podasi
Urugan pasir
Urugan tanah kembali
Buangan tanah sisa galian
Borepile beton K-225 dia. 40 cm, L = 4 meter, (1x3 titik)
Beton Beton Lantai kerja B-0
Beton K - 225
Beton Grouting camp. 1PC : 1.5 Psr : 2.5 Krl
Besi Beton U-24
Anchor lengkap
Bekisting

PEKERJAAN PONDASI CT ( 1 UNIT = 3 PONDASI )


Galian tanah untuk podasi
Urugan pasir
Urugan tanah kembali
Buangan tanah sisa galian
Borepile beton K-225 dia. 40 cm, L = 4 meter, (1x3 titik)
Beton Beton Lantai kerja B-0
Beton K - 225
Beton Grouting camp. 1PC : 1.5 Psr : 2.5 Krl
Besi Beton U-24
Anchor lengkap

URAIAN PEKERJAAN
2
Bekisting

PEKERJAAN PONDASI CB ( 1 UNIT = 3 PONDASI )


Galian tanah untuk podasi
Urugan pasir
Urugan tanah kembali
Buangan tanah sisa galian
Borepile beton K-225 dia. 40 cm, L = 4 meter, (1x3 titik)
Beton Beton Lantai kerja B-0
Beton K - 225
Beton Grouting camp. 1PC : 1.5 Psr : 2.5 Krl
Besi Beton U-24
Anchor lengkap
Bekisting

URAIAN PEKERJAAN
2
PEKERJAAN PONDASI DS/ DSE ( 1 UNIT = 3 PONDASI )
Galian tanah untuk podasi
Urugan pasir
Urugan tanah kembali
Buangan tanah sisa galian
Borepile beton K-225 dia. 40 cm, L = 4 meter, (2x3 titik)
Beton Beton Lantai kerja B-0
Beton K - 225
Beton Grouting camp. 1PC : 1.5 Psr : 2.5 Krl
Besi Beton U-24
Anchor lengkap
Bekisting

PEKERJAAN PONDASI MK ( 1 UNIT )


Galian tanah untuk podasi
Urugan pasir
Urugan tanah kembali
Buangan tanah sisa galian
Borepile beton K-225 dia. 40 cm, L = 4 meter, (1 titik)
Beton Beton Lantai kerja B-0
Beton K - 225
Besi Beton U-24
Bolt fatener M-12
Bekisting

PEKERJAAN PONDASI CPD BUS (1 UNIT)


Galian tanah untuk podasi
Urugan pasir
Urugan tanah kembali
Buangan tanah sisa galian
Borepile beton K-225 dia. 40 cm, L = 4 meter, (1 titik)
Beton Beton Lantai kerja B-0
Beton K - 225
Beton Grouting camp. 1PC : 1.5 Psr : 2.5 Krl
Besi Beton U-24
Anchor lengkap
Bekisting

URAIAN PEKERJAAN
2
PEKERJAAN CABLE DUCT DAN TUTUP CABLE DUCT
PEKERJAAN CABLE DUCT TYPE. I ( 1 m' )
Galian tanah
Urugan pasir
Urugan tanah kembali
Buangan tanah sisa galian
Beton Lantai kerja B-0
Beton K.175
Besi Beton U-24
Bekisting

URAIAN PEKERJAAN
2
PEKERJAAN CABLE DUCT TYPE. II ( 1 m' )
Galian tanah
Urugan pasir
Urugan tanah kembali
Buangan tanah sisa galian
Beton Lantai kerja B-0
Beton K.175
Besi Beton U-24
Bekisting

PEKERJAAN CABLE DUCT TYPE. III ( 1 m' )


Galian tanah
Urugan pasir
Urugan tanah kembali
Buangan tanah sisa galian
Beton Lantai kerja B-0
Beton K.175
Besi Beton U-24
Bekisting

PEKERJAAN CABLE DUCT TYPE. IV ( 1 m' )


Galian tanah
Urugan pasir
Urugan tanah kembali
Buangan tanah sisa galian
Beton Lantai kerja B-0
Beton K.175
Besi Beton U-24
Bekisting

PEKERJAAN CABLE DUCT TYPE. V ( 1 m' )


Galian tanah
Urugan pasir
Urugan tanah kembali
Buangan tanah sisa galian
Beton Lantai kerja B-0

URAIAN PEKERJAAN
2
Beton K.175
Besi Beton U-24
Bekisting

PEKERJAAN PIPA CONDUIT TYPE I ( K1 / DS)


Galian tanah
Urugan tanah kembali
Buangan tanah sisa galian
Beton B-0
Bekisting
Pipa conduit PVC dia 4" AW

PEKERJAAN PIPA CONDUIT TYPE II ( K2 / CB )


Galian tanah
Urugan tanah kembali
Buangan tanah sisa galian
Beton B-0
Bekisting
Pipa conduit PVC dia 4 " AW

URAIAN PEKERJAAN
2
PEKERJAAN PIPA CONDUIT TYPE III( K3/ CT, CPD)
Galian tanah
Urugan tanah kembali
Buangan tanah sisa galian
Beton B-0
Bekisting
Pipa conduit PVC dia 4 " AW

PEKERJAAN PENYANGGA KABEL/CABLE TRAY


TYPE I (6 shaf)
TYPE II (4 shaf)
TYPE III (4 shaf)
TYPE IV (2 shaf)
TYPE V (3 shaf)

PEKERJAAN DRAINASE ( BAK KONTROL )


Galian tanah
Urugan pasir
Urugan tanah kembali
Buangan tanah sisa galian
Beton Beton Lantai kerja B-0
Beton K.175
Besi Beton U-24
Bekisting
Pipa PVC dia. 4"

PEKERJAAN HAMPARAN KORAL & KANSTEEN


Galian tanah
Urugan pasir
Buangan tanah sisa galian
Beton camp. K - 175 u/ kansteen
Hamparan koral

PENGADAAN DAN PEMASANGAN KONSTRUKSI BAJA U/ GANTRY


Steel structure U/ kolom C-11 + murbout lengkap (1 unit )

URAIAN PEKERJAAN

Steel
Steel
Steel
Steel

structure
structure
structure
structure

U/
U/
U/
U/

kolom C-12 + murbout


kolom C-23 + murbout
beam P-12 + murbout
beam P-23 + murbout

2
lengkap (1 unit )
lengkap (1 unit )
lengkap (1 unit )
lengkap (1 unit )

PEKERJAAN PAGAR SWITCHYARD


Galian tanah untuk pondasi
Urugan pasir padat
Urugan tanah kembali
Beton K - 175
Besi Beton U-24
Bekisting
Pancang Cerucuk Dia. 10 cm L = 4 M
Tiang dia.2"tinggi 190 cm galvanize lengkap dg. tutup
Panel BRC tinggi 190cm dia.7mm galvanize lengkap clamp dan baut
Pintu pagar galvanized type T 190, lebar = 2.5 m lengkap

PEKERJAAN SALURAN SWITCHYARD


Galian tanah
Pasangan batu batu belah campuran 1pc :4ps
Plesteran camp. 1 Pc : 4 Ps

N ENJINIRING (HPE)
AAN SIPIL
ANA, PONDASI SWITCHYARD 2 LINE BAY
I KALBAR, KALIMANTAN BARAT

SATUAN

VOLUME

Unit
Unit
Unit
Unit
Unit
Unit
ttk

HARGA
SATUAN
Rp.
5

1.00
1.00
1.00
3.00
JUMLAH A

JUMLAH
HARGA
Rp.
6

#
#

m2
m3

2,500.00
2,500.00
JUMLAH B

m3
m3
m3
m3
m'
m3
m3
m3
kg
set
m2

10.75
1.02
3.50
7.25
32.00
0.51
7.25
0.51
498.75
16.00
7.68

75,000.00
175,000.00
40,000.00
25,000.00
550,000.00
750,000.00
1,300,000.00
900,000.00
15,500.00
250,000.00
225,000.00
JUMLAH 1

#
#
#
#
#
#
806,250.00
178,500.00
140,000.00
181,250.00
17,600,000.00
382,500.00
9,425,000.00
459,000.00
7,730,625.00
4,000,000.00
1,728,000.00
42,631,125.00

SATUAN

VOLUME

HARGA
SATUAN
Rp.
5

m3
m3
m3
m3
m'
m3
m3
m3
kg
set
m2

12.60
1.20
5.00
7.60
32.00
0.60
7.60
0.85
602.61
16.00
9.20

75,000.00
175,000.00
40,000.00
25,000.00
550,000.00
750,000.00
1,300,000.00
900,000.00
15,500.00
250,000.00
225,000.00
JUMLAH 2

m3
m3
m3
m3
m'
m3
m3
m3
kg
set
m2

9.45
0.90
2.45
7.00
32.00
0.45
7.00
0.85
451.82
16.00
6.60

75,000.00
175,000.00
40,000.00
25,000.00
550,000.00
750,000.00
1,300,000.00
900,000.00
15,500.00
250,000.00
225,000.00
JUMLAH 3

JUMLAH
HARGA
Rp.
6
#
#
945,000.00
210,000.00
200,000.00
190,000.00
17,600,000.00
450,000.00
9,880,000.00
765,000.00
9,340,455.00
4,000,000.00
2,070,000.00
69,311,149.18
#
#
708,750.00
157,500.00
98,000.00
175,000.00
17,600,000.00
337,500.00
9,100,000.00
765,000.00
7,003,210.00
4,000,000.00
1,485,000.00
41,429,960.00

SATUAN

VOLUME

m3
m3
m3
m3
m'
m3
m3
m3
kg
set
m2

3.41
0.57
1.66
1.76
12.00
0.29
2.60
0.16
206.22
12.00
21.68

m3
m3
m3
m3
m'
m3
m3
m3
kg
set
m2

3.41
0.57
1.66
1.76
12.00
0.29
2.60
0.16
206.22
12.00
21.68

HARGA
SATUAN
Rp.
5

75,000.00
175,000.00
40,000.00
25,000.00
550,000.00
750,000.00
1,300,000.00
900,000.00
15,500.00
250,000.00
225,000.00
JUMLAH 4

JUMLAH 5

m3
m3
m3
m3
m'
m3
m3
m3
kg
set

3.41
0.57
1.66
1.76
12.00
0.29
2.60
0.16
206.22
12.00

75,000.00
175,000.00
40,000.00
25,000.00
550,000.00
750,000.00
1,300,000.00
900,000.00
15,500.00
250,000.00

JUMLAH
HARGA
Rp.
6
#
#
255,750.00
99,750.00
66,400.00
44,000.00
6,600,000.00
217,500.00
3,380,000.00
144,000.00
3,196,410.00
3,000,000.00
4,878,000.00
21,881,810.00
#
#
#
#
255,750.00
99,750.00
66,400.00
44,000.00
6,600,000.00
217,500.00
3,380,000.00
144,000.00
3,196,410.00
3,000,000.00

SATUAN

VOLUME

3
m2

m3
m3
m3
m3
m'
m3
m3
m3
kg
set
m2

21.68

7.07
0.78
3.79
3.28
12.00
0.39
4.36
0.16
314.12
12.00
30.30

HARGA
SATUAN
Rp.
5
225,000.00
JUMLAH 6

75,000.00
175,000.00
40,000.00
25,000.00
550,000.00
750,000.00
1,300,000.00
900,000.00
15,500.00
250,000.00
225,000.00
JUMLAH 7

JUMLAH
HARGA
Rp.
6
4,878,000.00
21,881,810.00
#
#
530,250.00
136,500.00
151,600.00
82,000.00
6,600,000.00
292,500.00
5,668,000.00
144,000.00
4,868,860.00
3,000,000.00
6,817,500.00
28,291,210.00
#

SATUAN

VOLUME

HARGA
SATUAN
Rp.
5

m3
m3
m3
m3
m'
m3
m3
m3
kg
set
m2

6.08
1.05
2.88
3.21
24.00
0.53
4.97
0.31
408.26
12.00
15.85

75,000.00
175,000.00
40,000.00
25,000.00
550,000.00
750,000.00
1,300,000.00
900,000.00
15,500.00
250,000.00
225,000.00
JUMLAH 8

m3
m3
m3
m3
m'
m3
m3
kg
unit
m2

1.02
0.23
0.52
0.50
4.00
0.11
0.50
67.70
4.00
8.52

75,000.00
175,000.00
40,000.00
25,000.00
550,000.00
750,000.00
1,300,000.00
15,500.00
200,000.00
225,000.00
JUMLAH 9

m3
m3
m3
m3
m'
m3
m3
m3
kg
set
m2

3.41
0.57
1.66
1.76
4.00
0.29
2.60
0.16
206.22
12.00
21.68
JUMLAH 10

JUMLAH
HARGA
Rp.
6
#
456,000.00
183,750.00
115,200.00
80,250.00
13,200,000.00
397,500.00
6,461,000.00
279,000.00
6,328,030.00
3,000,000.00
3,566,250.00
34,066,980.00
#
#
76,500.00
40,250.00
20,800.00
12,500.00
2,200,000.00
82,500.00
650,000.00
1,049,350.00
800,000.00
1,917,000.00
6,848,900.00
#
#
-

SATUAN

VOLUME

m3
m3
m3
m3
m3
m3
kg
m2

1.30
0.14
0.27
1.03
0.07
0.40
42.72
5.26

HARGA
SATUAN
Rp.
5

75,000.00
175,000.00
40,000.00
25,000.00
750,000.00
900,000.00
15,500.00
225,000.00
JUMLAH 1

JUMLAH
HARGA
Rp.
6
#
#
#
#
97,500.00
24,500.00
10,800.00
25,750.00
52,500.00
360,000.00
662,160.00
1,183,500.00
2,416,710.00

SATUAN

VOLUME

HARGA
SATUAN
Rp.
5

m3
m3
m3
m3
m3
m3
kg
m2

0.70
0.10
0.08
0.52
0.05
0.32
36.02
4.80

75,000.00
175,000.00
40,000.00
25,000.00
750,000.00
900,000.00
15,500.00
225,000.00
JUMLAH 2

m3
m3
m3
m3
m3
m3
kg
m2

0.38
0.06
0.05
0.36
0.03
0.27
30.04
3.80

75,000.00
175,000.00
40,000.00
25,000.00
750,000.00
900,000.00
15,500.00
225,000.00
JUMLAH 3

m3
m3
m3
m3
m3
m3
kg
m2

0.12
0.03
0.05
0.14
0.02
0.18
23.16
2.80

75,000.00
175,000.00
40,000.00
25,000.00
750,000.00
900,000.00
15,500.00
225,000.00
JUMLAH 4

m3
m3
m3
m3
m3

0.90
0.10
0.21
0.70
0.05

75,000.00
175,000.00
40,000.00
25,000.00
750,000.00

JUMLAH
HARGA
Rp.
6
#
#
52,500.00
17,500.00
3,200.00
13,000.00
37,500.00
288,000.00
558,310.00
1,080,000.00
2,050,010.00
#
#
28,500.00
10,500.00
2,000.00
9,000.00
22,500.00
243,000.00
465,620.00
855,000.00
1,636,120.00
#
#
9,000.00
5,250.00
2,000.00
3,500.00
15,000.00
162,000.00
358,980.00
630,000.00
1,185,730.00
#
#
67,500.00
17,500.00
8,400.00
17,500.00
37,500.00

SATUAN

VOLUME

3
m3
kg
m2

4
0.35
45.24
4.26

HARGA
SATUAN
Rp.
5
900,000.00
15,500.00
225,000.00
JUMLAH 5

m3
m3
m3
m3
m2
m'

0.20
0.17
0.03
0.03
0.72
1.80

75,000.00
40,000.00
25,000.00
750,000.00
225,000.00
75,000.00
JUMLAH 6

m3
m3
m3
m3
m2
m'

0.84
0.70
0.14
0.14
3.06
5.36

75,000.00
40,000.00
25,000.00
750,000.00
225,000.00
75,000.00
JUMLAH 7

JUMLAH
HARGA
Rp.
6
315,000.00
701,220.00
958,500.00
2,123,120.00
#
#
15,000.00
6,800.00
750.00
22,500.00
162,000.00
135,000.00
342,050.00
#
#
63,000.00
28,000.00
3,500.00
105,000.00
688,500.00
402,000.00
1,290,000.00

SATUAN

VOLUME

HARGA
SATUAN
Rp.
5

m3
m3
m3
m3
m2
m'

1.32
1.10
0.22
0.22
4.79
9.40

75,000.00
40,000.00
25,000.00
750,000.00
225,000.00
75,000.00
JUMLAH 8

Set
Set
Set
Set
Set

100.00
60.00
120.00
-

150,000.00
150,000.00
150,000.00
JUMLAH C

m3
m3
m3
m3
m3
m3
kg
m2
m'

1.06
0.07
0.77
0.29
0.04
0.52
46.52
7.13
30.00

75,000.00
175,000.00
40,000.00
25,000.00
750,000.00
900,000.00
15,500.00
225,000.00
75,000.00
JUMLAH D

M'
m3
m3
m3
m3
m3

100.00
12.00
3.00
6.00
11.00
180.00

set

1.00

75,000.00
175,000.00
25,000.00
900,000.00
350,000.00
JUMLAH E.

JUMLAH
HARGA
Rp.
6
#
#
99,000.00
44,000.00
5,500.00
165,000.00
1,077,750.00
705,000.00
2,096,250.00
#
#
15,000,000.00
9,000,000.00
18,000,000.00
42,000,000.00
#
#
125,323.80
16,921.80
47,539.80
51,156.00
48,609.43
702,178.65
1,144,252.44
2,134,117.47
3,595,230.00
7,865,329.39
#
#
1,418,760.00
725,220.00
1,058,400.00
14,853,779.22
110,975,438.26
129,031,597.47
#
#
87,620,000.00

SATUAN

VOLUME

3
Set
Set
Set
Set

HARGA
SATUAN
Rp.
5

1.00
1.00
1.00
1.00
JUMLAH F.

M'
m3
m3
m3
m3
kg
m2
btg
btg
panel
unit

M'
m3
m3
m2

70.00
4.38
0.73
2.19
6.66
1,331.46
42.00
59.00
31.00
30.00
-

50.00
24.50
22.50
90.00

75,000.00
175,000.00
40,000.00
900,000.00
15,500.00
225,000.00
40,000.00
375,000.00
450,000.00
JUMLAH G

75,000.00
750,000.00
60,000.00
JUMLAH H

JUMLAH
HARGA
Rp.
6
77,847,000.00
50,550,000.00
100,763,000.00
100,763,000.00
417,543,000.00
#
#
328,500
127,750
87,600
5,994,000
20,637,630
9,450,000
2,360,000
11,625,000
13,500,000
64,110,480
#
#
2,896,635.00
33,445,039.78
8,986,522.96
45,328,197.74

Você também pode gostar