Escolar Documentos
Profissional Documentos
Cultura Documentos
RESOLUTION MECHANISM
By Narendra Saigal
Director (Contract)
Military Engineer Services
CE (AF) Ahmedabad
Introduction
1.
The scope of Mega projects for any Govt establishment is large. It
includes large variety of work such as residential and technical buildings, dams,
roads, airfield docks, jetties, power station, water supply and drainage scheme
etc. In order to execute these types of projects a contract is required to be
entered between a Govt agency or another agency with contractor.
2.
A contract contains reciprocal promises. If one contracting party feels that
other party has failed to perform its obligation, the dispute arises between the
parties. Disputes are inevitable in construction contract. A construction contract
has, in it-self inherent seeds of difference or disputes, which can be easily and
speedily sprout and call for decision to smoothen out the process.
Factors Responsible for Disputes.
3.
There are number of factors, which cause disputes between department
and contractor in execution of Mega Projects. Some of the reasons are discussed
in succeeding paragraphs.
Ineffective Management.
4.
The success of mega project generally is guided by the efficiency and
practical effectiveness of the procedure adopted to execute basic project
management. Ineffective management only creates disputes. It is essential to
develop total project management approach plan to obviate disputes.
5.
The vastness and complexities of project will guide the breakdown
structure of project management. However, vital activities are Planning,
Organising, Monitoring and Contracting. Failure in any one of the activities will
result in delay in completion of project, which will cause disputes.
6.
For efficient project planning it is essential to identify a work breakdown
structure with their interface and define schedule for the same. In order to
succeed, the planning should be logical, thorough and should be made with
honest approach.
-2Selection of Contractors.
7.
Selection of Contractors is one of the major factors causing the disputes.
In any department, if list of contractors working with the department is analysed
for contract of value more than 1 Crore, it will be noticed that there may be 10%
to 15% of contractors who create disputes in all contracts, 20% to 30% of
contractors who create disputes occasionally and 55% to 70% do not create
disputes. Thus, it is necessary that past record of contractors should be analysed
before issue of tender.
8.
It may not be legally correct to deny tenders to the firms who are habitual
in creating disputes. But introducing pre-qualification criteria in which negative
marks are included for invoking arbitration cases in completed contracts in last
five years can discourage these types of firms.
Selection of Consultant.
9.
Selection of consultant plays very important role in completion of any
Mega Project. Technical proficiency in planning, designing, preparation of
drawings and preparation of contract in Mega Project is of prime importance.
Failure by consultant in any one of the activities will ultimately result in
dispute.
10. Most of consultants employed in mega projects have shown inherent
weakness in preparation of Bill of quantities. Number of Mega Projects faced
disputes after completion due to increase in quantities beyond the permissible
limit as specified in the contract. This is due to incorrect preparation of bill of
quantities.
Quality of contract documents.
11. Quality of contract documents plays very important role in smooth
completion of project. It reflects the quality of planning, design, specification
and drawings. Failure in any of these aspects will ultimately create disputes.
12. Selection of type of contract also plays an important role in smooth
completion of project. Most of the Govt departments except MES use item rate
tender for Mega projects. It has been noticed that there is abnormal
increase/decrease in quantities catered in bill of quantities, which normally
result in disputes.
-4Causes of Disputes
18. In civil engineering construction, the dispute can be due to legal as well
as contractual aspect. The legal disputes are rare in comparison to contractual
disputes.
Legal Dispute.
19. The legal disputes are normally disputes, which have been created due to
certain court order on which both the contracting parties have no control or one
of contracting party has no control. Some of such disputes are listed below: (a) Honble Supreme Court banned all the crusher in and around
Delhi. The Supply of aggregate became difficult and the rates also
increased. The contractor requested reimbursement of increased rates
from department. The department refused of the reimbursement. Thus,
there was a dispute.
(b) As per the contract, the quarry of stone was permitted in defence
land. The court issued order banning the quarry. The contractor asked
payment due to refusal of quarry from the department.
(c) There was a contract for building a dam up to particular height.
The people whose land was coming in the submersible area approached
court for reduction in height of dam. The court stayed the construction
activity. This may ultimately result in dispute.
Contractual Dispute.
20. Contractual disputes are those disputes, which emerge from the
conditions of contracts. The contractual dispute between owner (department)
and contractor are due to default by owner or contractor.
21. The most common disputes which are raised by contractor with (due to
owner default) department are: (a)
(b)
(c)
(j)
Delay in finalisation of approval in principal for extra items, rates
for payment (star rate) etc.
(k)
(l)
(m)
(n)
22. The disputes (claims), which are raised by department against contractor,
are claim for extra cost in completion of work due to: (a) Extra cost of completion at the risk and cost of contractor due to
failure of contractor in completion of contract.
(b)
Delay in completion.
(c)
(d)
(e)
(f)
-6Resolution of Dispute.
23.
The resolution of disputers as per Arbitration and conciliation Act, 1996
can be made by conciliation in addition to Arbitration.
24. Arbitration is considered to be quicker and more efficient than litigation.
However, experience of the last three decades has shown that arbitration
proceeding have become time consuming, expensive and complex like court
proceeding. Even after publication of award, the parties move to the court for
setting aside award due to various reasons. In such a situation Alternate Dispute
Resolution (ADR) has become popular in developed countries.
Alternate Dispute Resolution Mechanism.
25.
Negotiated settlement.
(b)
(c)
Adjudication.
(d)
Executive tribunal.
(e)
Conciliation.
(f)
Negotiated settlement.
26. Construction claims are complex in nature and are combination of law
and construction practice. Negotiated settlements are always possible when both
the parties adopt flexible, judicious and fair approach towards disputes. It is
necessary that both parties understand basis and principal of contract so that
they are aware of their rights and obligation. In such settlement both the parties
sit together and negotiate on each claim and decide the admissibility and
amount payable against each claim. The settlement is recorded in writing duly
signed by both parties. However even after reaching settlement sometime the
contractors do raises balance claims in Arbitration.