Escolar Documentos
Profissional Documentos
Cultura Documentos
WORKMANSHIP
3.1. Reinforcement
NO
3.1.1.
3.1.2.
3.1.3.
3.1.4.
Contract
Reinforcement shall be bent
accurately in accordance
with ACI 318 to the shapes and
dimensions shown on
the drawings or in the schedules
where applicable.
Cold worked or high yield bars shall
not be
straightened or bent again once
having been bent.
When it is necessary to bend mild
steel
reinforcement already cast in the
concrete the
internal radius of such bends shall
be not less
than twice the diameter of the bar.
No welding of reinforcement shall
be carried out
without the endorsement of the
Architect.
The use of mechanical splices shall
be of the Building Authority
approved types and shall be used
with the acceptance of the Architect.
Where the use of mechanical splices
is accepted by
the Architect, its use shall comply
with the following :
a. The splicing shall be carried out
directly by certified persons
who have been fully trained by
the supplier in the correct
operation and procedures for
fitting splices with equipment as
per supplier's specification.
b. The splices shall be used only
for high yield deformed bars in
compliance with SII.0136- 84
(UDC.669.14) or ASTM A61S.
c. The correct placing of. the bars
on site to be spliced shall be
FIDIC
Perpres/ UU JK
inspected by responsible
member of the supplier to
ensure that the spacing of bars
is sufficient to allow the
splicing to be done properly and
a check list shall be completed
to this effect.
d. The Manufacturer's
recommendations and
specifications or using the
splices shall be strictly
followed.
e. Three samples for every one
hundred splices shall be taken
from the erected work for
tensile test. In case of splices
less than one hundred, at least
three samples shall be taken for
test. The Architect may ask for
additional tests on samples
selected from
site to ensure the quality and
workmanship at all times
comply with the required
standard.
f. The Contractor shall keep
records of all splices, testing
and relevant data and these
records shall be produced if
requested.
g. The splices shall be staggered
so that no more than half of the
bars are spliced at any location
and the distance between
staggered splices shall not be
less than 30 times bar diameter.
3.1.5.
3.1.6.
3.1.7.
3.1.8.
3.1.9.
3.1.10
3.2.2
Contract
The Contractor shall be responsible
for the design stability, supply,
fixing and alignment of all
formwork and supports.
Formwork shall be so designed and
constructed that concrete can be
properly placed and throughly
compacted to the true shape, line
and dimensions
without loss of cement grout or
FIDIC
Perpres/ UU JK
3.2.3.
3.2.4.
3.2.5
3.2.6
3.2.7
3.2.8