JADWAL WAKTU PELAKSANAAN PEKERJAAN

PROGRAM

: PENINGKATAN JALAN USAHA TANI ( BANTUAN KEUANGAN PROVINSI )

KEGIATAN

: PENINGKATAN PRODUKSI PERTANIAN / PERKEBUNAN

LOKASI

: KECAMATAN MOOK MANAAR BULANT

SUMBER DANA

: BANTUAN KEUANGAN PROVINSI

T. ANGGARAN

: 2016

No.

Uraian

JUMLAH HARGA

PELAKSANAAN PEKERJAAN
120 ( Seratus Dua Puluh ) Hari Kalender

Bobot
%

BULAN 1
1

UMUM

Mobilisasi

48,000,000

2.32%

1.16%

24,977,857

1.21%

1.21%

82,662,857

3.99%

1,183,291,739

57.13%

Jembatan Log

III

PEKERJAAN TANAH

Galian Biasa

Timbunan biasa dari galian

Penyiapan badan jalan

Pembersihan dan Pengupasan Lahan

PERKERASAN BERBUTIR DAN BETON SEMEN

Lapis pondasi Aggregat Sirtu


Total Bobot (%)

BULAN 2
4

BULAN 3
8

10

11

BULAN 4
12

13

14

15

KETERANGAN
16
100 %
1.16%

75 %

22,154,592

1.07%

307,947,998

14.87%

402,281,938

19.42%

3.99%
5.71%

5.71%

5.71%

5.71%

5.71%

5.71%

5.71%

5.71%

5.71%

50 %

5.71%
1.07%

4.96%

4.96%

4.96%

25 %

19.42%

0%

100.00%

Rencana Mingguan (%)

2.36%

4.96%

4.96%

8.95%

5.71%

5.71%

5.71%

5.71%

5.71%

5.71%

5.71%

5.71%

5.71%

5.71%

20.49%

1.16%

Komulatif Rencana (%)

2.36%

7.32%

12.28%

21.22%

26.94%

32.65%

38.36%

44.07%

49.79%

55.50%

61.21%

66.92%

72.64%

78.35%

98.84%

100.00%

Samarinda, 03 Agustus 2016


CV. ADI RAYA

Hj. HASANAH
Direktur

Waktu Pelaksanaan
Pekerajan 120 hari
kalender