Você está na página 1de 203

UPAH KERJA

DALAM 1 HARI KERJA ( 8 JAM )

NO.
1
2
3
4
5
6
7
8
9

JENIS PEKERJA / KEAHLIAN


Pekerja
Tukang
Kepala Tukang
Mandor
Operator Alat Berat
Pembantu Operator / Mekanik
Sopir Truk
Kenek Truk
Penjaga Malam
Keuntungan Maksimal

UPAH
1 HARI 8 JAM
(Rp)
60,000.00
70,000.00
80,000.00
90,000.00
90,000.00
60,000.00
80,000.00
60,000.00
70,000.00
0%

###
###
###
###
###
###
###
###
###

###
###
###
###
###
###
###
###
###

PEKERJA
TUKANG BATU/GALI
KEPALA TUKANG BATU
TUKANG KAYU
KEPALA TUKANG KAYU
TUKANG CAT / PELITUR
KEPALA TUKANG CAT / PELITUR
TUKANG BESI BETON
KEPALA TUKANG BESI BETON
TUKANG BESI PROFIL
KEPALA TUKANG BESI PROFIL
MANDOR

60,000.00
70,000.00
80,000.00
70,000.00
80,000.00
70,000.00
80,000.00
80,000.00
80,000.00
80,000.00
80,000.00
90,000.00

DAFTAR HARGA STANDAR BAHAN BANGUNAN

NO.

JENIS BAHAN

SAT

A.
1
2
3
4

Data 1
4

HARGA (Rp)
Data 2
5

Rata-Rata
4

KETERANGAN
5

AGREGAT KASAR, BAHAN PEREKAT & BAHAN JADINYA


Tanah Urug
m3
Tanah Merah
m3
Pasir Urug
m3
Pasir Batu ( Sirtu ) tersaring
m3

45,000.00
80,000.00
120,000.00
135,000.00

45,000.00
80,000.00
120,000.00
135,000.00

45,000.00
80,000.00
120,000.00
135,000.00

Sirtu
Pasir Pasang
Pasir Beton
Pasir Aspal
Abu Batu

m3
m3
m3
m3
m3

158,000.00
195,000.00
205,000.00
141,000.00
155,000.00

158,000.00
195,000.00
205,000.00
141,000.00
155,000.00

158,000.00
195,000.00
205,000.00
141,000.00
155,000.00

10
11
12
13
14

Kerikil
Batu Gosok ( Apung )
Batu Pecah 1 - 2
Batu Pecah 2 - 3
Batu Pecah 3 - 5

m3
kg
m3
m3
m3

153,000.00
17,000.00
203,000.00
184,000.00
175,000.00

153,000.00
17,000.00
203,000.00
184,000.00
175,000.00

153,000.00
17,000.00
203,000.00
184,000.00
175,000.00

1,800.00 kg/m3

15
16
17
18
19

Batu
Batu
Batu
Batu
Batu

Pecah 5 - 7
Pecah 7 - 10
Pecah 10 - 15
Belah Pondasi
Bronjong (untuk Bronjong)

m3
m3
m3
m3
m3

145,000.00
135,000.00
130,000.00
140,000.00
127,000.00

145,000.00
135,000.00
130,000.00
140,000.00
127,000.00

145,000.00
135,000.00
130,000.00
140,000.00
127,000.00

1,450.00
1,450.00
1,450.00
1,500.00
1,500.00

20
21
22
23

Batu
Batu
Batu
Batu

Koral Beton Kali


Tempel Hitam
Pinggir Beton 10 x 20 x 35 ( Kerb / Kaanstein )
Pinggir Beton 15 x 35 x 60 ( K - 225 )

m3
m2
bh
bh

122,000.00
105,000.00
15,000.00
48,000.00

122,000.00
105,000.00
15,000.00
48,000.00

122,000.00
105,000.00
15,000.00
48,000.00

24
25
26
27

Batu Telor
Batako Kecil 8 x 10 x 20
Batako Besar 8 x 20 x 30
Con Block 8 x 20 x 40

m3
bh
bh
bh

152,000.00
900.00
1,800.00
3,200.00

152,000.00
900.00
1,800.00
3,200.00

152,000.00
900.00
1,800.00
3,200.00

28
29

Bata Merah Bakar Kelas I


Bata Merah Bakar Kelas II

bh
bh

600.00
500.00

600.00
500.00

600.00
500.00

30
31
32

Bata Merah Oven ( Klingker )


Paving Block Natural 8 cm
Paving Block Warna 8 cm

bh
m2
m2

2,700.00
45,000.00
56,000.00

2,700.00
45,000.00
56,000.00

2,700.00
45,000.00
56,000.00

33
34

Paving Block Natural 6 cm


Paving Block Warna 6 cm

m2
m2

40,000.00
45,000.00

40,000.00
45,000.00

40,000.00
45,000.00

35
36
37

Kaanstein Paving Block


Semen PC Tiga Roda/ 50kg
Semen Putih

m'
kg
kg

21,000.00
62,500.00
70,000.00

21,000.00
62,500.00
70,000.00

21,000.00
62,500.00
70,000.00

38
39

Semen Warna
Kapur Pasang / Kapur Tembok

kg
m3

10,000.00
90,000.00

10,000.00
90,000.00

10,000.00
90,000.00

40
41
42

Batu Pinggir Beton Kerb Type A


Batu Pinggir Beton Kerb Type B
Beton K - 175

m3
m3
m3

90,000.00
120,000.00
875,000.00

90,000.00
120,000.00
875,000.00

90,000.00
120,000.00
875,000.00

43
44

Beton K - 225
Beton K - 250

m3
m3

958,000.00
970,500.00

958,000.00
970,500.00

958,000.00
970,500.00

45
46
47
48

Beton
Beton
Beton
Beton

275
300
350
400

m3
m3
m3
m3

978,500.00
1,015,000.00
1,029,000.00
1,085,000.00

978,500.00
1,015,000.00
1,029,000.00
1,085,000.00

978,500.00
1,015,000.00
1,029,000.00
1,085,000.00

49
50
51
52
53

Beton K - 450
Beton K - 500
Biaya Pompa Ready Mix
Material Agregat Kelas A
Material Agregat Kelas B

m3
m3
m3
m3
m3

1,148,208.00
1,200,000.00
86,000.00
155,000.00
129,000.00

1,148,208.00
1,200,000.00
86,000.00
155,000.00
129,000.00

1,148,208.00
1,200,000.00
86,000.00
155,000.00
129,000.00

54
55
56
57
58
59
60

Urugan Pilihan
Gorong - Gorong
Gorong - Gorong
Gorong - Gorong
Gorong - Gorong
Gorong - Gorong
Air

m3
m'
m'
m'
m'
m'
lt

80,000.00
103,000.00
285,000.00
400,000.00
628,000.00
1,027,000.00
10.00

80,000.00
103,000.00
285,000.00
400,000.00
628,000.00
1,027,000.00
10.00

80,000.00
103,000.00
285,000.00
400,000.00
628,000.00
1,027,000.00
10.00

B.

BAHAN PAKU DAN MUR BAUT


kg
kg
kg
bh
bh

28,600.00
17,000.00
17,000.00
500.00
630.00

28,600.00
17,000.00
17,000.00
500.00
630.00

28,600.00
17,000.00
17,000.00
500.00
630.00

5
6
7
8
9

1
2
3
4
5

Paku
Paku
Paku
Paku
Paku

K
K
K
K

Beton
Beton
Beton
Beton
Beton

Tanpa Tulang dia.dalam


Bertulang dia.dalam 45
Bertulang dia.dalam 45
Bertulang dia.dalam 75
Bertulang dia.dalam 95

1 s/d 3 cm
4 s/d 7 cm
8 s/d 12 cm
Beton 2 s/d 5 cm
Kait Lengkap

20 - 30
cm
- 75 cm
- 95 cm
- 120 c

6
7
8
9
10

Paku Cacing
Besi Begel Kuda - Kuda
Duk Angker
Angker Mur Baut dia. 19 mm panjang 60 cm
Mur Baut HTB dia. 10 mm s/d 16 mm ( 5 cm )

kg
kg
kg
bh
bh

30,000.00
12,000.00
2,800.00
26,000.00
6,500.00

30,000.00
12,000.00
2,800.00
26,000.00
6,500.00

30,000.00
12,000.00
2,800.00
26,000.00
6,500.00

11
12

Mur Baut Biasa dia. 10 mm s/d 16 mm ( 5 cm )


Fisher dia. 12 cm s/d 20 cm

bh
bh

4,000.00
1,500.00

4,000.00
1,500.00

4,000.00
1,500.00

C.
1

BAHAN KAYU BERIKUT BAHAN JADINYA


Bambu dia. 5 - 7 cm

bt

17,100.00

17,100.00

17,100.00

bt
bt
m3

23,500.00
45,900.00
1,500,000.00

23,500.00
45,900.00
1,500,000.00

23,500.00
45,900.00
1,500,000.00

2
3
4

Bambu dia. 7 - 10 cm
Bambu Gombong
Kayu Terentang

Harga Bahan SK Gub Jabar 2012

1,400.00
1,400.00
1,400.00
1,400.00

kg/m3
kg/m3
kg/m3
kg/m3

1,450.00 kg/m3
1,450.00 kg/m3
1,450.00 kg/m3
kg/m3
kg/m3
kg/m3
kg/m3
kg/m3

5
6

Kayu Kamper Singkil / Kapur (K. Samarinda klas II)


Kayu Balok Borneo Super

m3
m3

5,087,000.00
4,250,000.00

5,087,000.00
4,250,000.00

5,087,000.00
4,250,000.00

7
8
9
10
11

Kayu
Kayu
Kayu
Kayu
Kayu

Papan Borneo Super


Balok Kamper Medan (Kruing)
Papan Kamper Medan (Kruing)
Balok Kamper Banjar
Papan Kamper Banjar

m3
m3
m3
m3
m3

4,250,000.00
5,450,000.00
5,950,000.00
5,670,000.00
6,960,000.00

4,250,000.00
5,450,000.00
5,950,000.00
5,670,000.00
6,960,000.00

4,250,000.00
5,450,000.00
5,950,000.00
5,670,000.00
6,960,000.00

12
13
14
15
16

Kayu
Kayu
Kayu
Kayu
Kayu

Balok Kamper Samarinda


Papan Kamper Samarinda
Balok Rasamala
Jati Jateng Tua Lepas Mata dari dia. 80 cm keatas
Jati Jabar Tua Lepas Mata dari dia. 80 cm keatas

m3
m3
m3
m3
m3

9,400,000.00
10,400,000.00
2,400,000.00
17,000,000.00
14,800,000.00

9,400,000.00
10,400,000.00
2,400,000.00
17,000,000.00
14,800,000.00

9,400,000.00
10,400,000.00
2,400,000.00
17,000,000.00
14,800,000.00

17
18
19
20
21

Kayu Jati Jabar dia. 40 cm kebawah


Kayu Albasiah
Dolken 5 - 7
Dolken 7 - 10
List Profil Kamper 1 cm

m3
m3
bt
bt
m'

9,500,000.00
650,000.00
13,000.00
22,000.00
4,200.00

9,500,000.00
650,000.00
13,000.00
22,000.00
4,200.00

9,500,000.00
650,000.00
13,000.00
22,000.00
4,200.00

22
23
24
25
26

List Profil Kamper 2 cm


List Profil Kamper 4 cm
List Profil Kamper 5 cm
List Profil Kamper 10 cm
Pegangan Tangga Profil Jati

m'
m'
m'
m'
m'

5,800.00
11,000.00
15,000.00
25,900.00
83,000.00

5,800.00
11,000.00
15,000.00
25,900.00
83,000.00

5,800.00
11,000.00
15,000.00
25,900.00
83,000.00

27
28
29
30

Pegangan Tangga Profil Kamper


Kayu Reng 2/3 Borneo Super
Kayu Reng 2/3 Kamper Banjar
Kayu Reng 3/4 Kamper Banjar

m'
batang
batang
batang

54,000.00
2,400.00
4,000.00
8,000.00

54,000.00
2,400.00
4,000.00
8,000.00

54,000.00
2,400.00 4,000,000.00
4,000.00 6,666,666.67
8,000.00 6,666,666.67

D.
1
2
3

BAHAN FINISHING LABURAN, PENGISI DAN ALATNYA


Plamir Tembok
kg
Cat Tembok Eksterior
gln
Cat Tembok Interior (Plafond dan Dinding)
gln

13,500.00
223,000.00
147,000.00

13,500.00
223,000.00
147,000.00

13,500.00
223,000.00
147,000.00

4
5
6
7

Cat Tahan Asam


Cat Marka / Spotlight
Water Proofing Emulsion
Water Proofing Membrance

kg
kg
kg
ml

39,000.00
47,000.00
46,975.00
77,000.00

39,000.00
47,000.00
46,975.00
77,000.00

39,000.00
47,000.00
46,975.00
77,000.00

8
9

Rool Cat Tembok


Kape Tembok

bh
bh

27,500.00
7,500.00

27,500.00
7,500.00

27,500.00
7,500.00

10
11
12

Kape Kayu
Soligneum
Plintcoat

bh
lt
kg

5,000.00
8,000.00
32,000.00

5,000.00
8,000.00
32,000.00

5,000.00
8,000.00
32,000.00

13
14

Kwas 3"
Oker

bh
kg

10,000.00
25,000.00

10,000.00
25,000.00

10,000.00
25,000.00

15
16
17

Otem (Pewarna Plitur)


Spritus
Bahan Plitur (Sirlak) India

kg
ltr
kg

27,000.00
15,000.00
80,000.00

27,000.00
15,000.00
80,000.00

27,000.00
15,000.00
80,000.00

18
19

Dempul Halus / Impra ( Wood Filler )


Terpentin

kg
lt

25,000.00
12,000.00

25,000.00
12,000.00

25,000.00
12,000.00

20
21
22

Thiner A
Thiner B
Minyak Tanah

lt
lt
lt

21,500.00
20,000.00
12,500.00

21,500.00
20,000.00
12,500.00

21,500.00
20,000.00
12,500.00

23
24

Ampelas
Dempul Kayu Cap Kucing

lbr
kg

10,600.00
20,500.00

10,600.00
20,500.00

10,600.00
20,500.00

25
26
27
28

Meni Kayu / Besi


Sincromat
Cat Kayu
Cat Besi

kg
kg
kg
kg

22,000.00
30,000.00
40,000.00
40,000.00

22,000.00
30,000.00
40,000.00
40,000.00

22,000.00
30,000.00
40,000.00
40,000.00

29
30
31
32

Cat Besi Duco


Cat Brom
Lem Kuning ( Aibond )
Lem Putih Fox

kg
kg
kg
kg

78,000.00
35,000.00
34,000.00
34,000.00

78,000.00
35,000.00
34,000.00
34,000.00

78,000.00
35,000.00
34,000.00
34,000.00

E.
1
2
3
4
5
6

BAHAN PENUTUP RANGKA PLAFOND


Eternit 4 mm
Hardfleks 5mm 120 x 240 cm
Asbes Semen 5 mm
Gypsum 120 x 240 cm, t = 9 mm ex. DN
Gypsum 120 x 240 cm, t = 9 mm ex. Luar
Acustik Amstrong 60 x 120

m2
lbr
m2
lbr
lbr
lbr

12,000.00
48,000.00
15,000.00
60,000.00
68,000.00
90,000.00

12,000.00
48,000.00
15,000.00
60,000.00
68,000.00
90,000.00

12,000.00
48,000.00
15,000.00
60,000.00
68,000.00
90,000.00

F.

BAHAN KAYU LAPIS

1
2
3
4
5

Triplek 3 mm 120 x 240


Triplek 4 mm 120 x 240
Triplek 4 mm Ukuran Pintu
Triplek 6 mm 120 x 240
Jabar Wood 4 mm

lbr
lbr
lbr
lbr
lbr

53,000.00
62,100.00
40,000.00
78,000.00
75,000.00

53,000.00
62,100.00
40,000.00
78,000.00
75,000.00

53,000.00
62,100.00
40,000.00
78,000.00
75,000.00

6
7
8
9
10

Bilik Bambu ( Tanpa Kulit )


Bilik Bambu ( Dengan Kulit )
Bilik Bambu Hitam Variasi
Wall Paper ( Klas Menengah )
Multiplek 9 mm 120 x 240

m2
m2
m2
m2
lbr

15,000.00
18,000.00
32,000.00
46,000.00
125,000.00

15,000.00
18,000.00
32,000.00
46,000.00
125,000.00

15,000.00
18,000.00
32,000.00
46,000.00
125,000.00

11
12
13
14
15

Multiplek 12 mm 120 x 240


Multiplek 18 mm 120 x 240
Plywood 18 mm 120 x 240
Teak Wood 3 mm 120 x 240
Teak Wood 4 mm 120 x 240

lbr
lbr
lbr
lbr
lbr

150,000.00
205,000.00
239,000.00
88,000.00
107,000.00

150,000.00
205,000.00
239,000.00
88,000.00
107,000.00

150,000.00
205,000.00
239,000.00
88,000.00
107,000.00

16
17
18

Teak Wood 3 mm Ukuran Pintu


Teak Wood 4 mm Ukuran Pintu
Melamin 4 mm 120 x 240

lbr
lbr
lbr

63,000.00
80,000.00
98,000.00

63,000.00
80,000.00
98,000.00

63,000.00
80,000.00
98,000.00

Harga Bahan SK Gub Jabar 2012

40,000.00 /5 liter

30x30

19
20

Melamin TIK 4 mm
Formika 120 x 240

lbr
lbr

110,000.00
132,000.00

110,000.00
132,000.00

110,000.00
132,000.00

21

Formika Ukuran Pintu

lbr

87,000.00

87,000.00

87,000.00

G.
1
2

BAHAN LANTAI DAN PELAPIS DINDING


Tegel PC 20 x 20
Plin Tegel 20 x 20

bh
bh

1,700.00
1,300.00

1,700.00
1,300.00

1,700.00
1,300.00

Tegel PC 30 x 30
Plin Tegel 15 x 30
Tegel Warna 20 x 20
Plin Tegel Warna 10 x 20
Tegel Warna 30 x 30

bh
bh
bh
bh
bh

2,200.00
2,200.00
2,100.00
1,900.00
2,600.00

2,200.00
2,200.00
2,100.00
1,900.00
2,600.00

2,200.00
2,200.00
2,100.00
1,900.00
2,600.00

8
9
10
11
12

Plin Tegel Warna 15 x 30


Tegel Wafel PC 20 x 20
Tegel Wafel Warna 20 x 20
Tegel Badak PC 30 x 30
Porcelin 11 x 11 Warna Standar DN

bh
bh
bh
bh
bh

2,100.00
1,500.00
2,300.00
2,300.00
446.00

2,100.00
1,500.00
2,300.00
2,300.00
446.00

2,100.00
1,500.00
2,300.00
2,300.00
446.00

44,600.00 /dus

13
14
15
16
17

Porcelin 11 x 11 Warna Khusus DN


Keramik 10 x 20 dan 20 x 20 KW I DN Putih / Polos
Keramik 10 x 20 KW I DN Corak / Warna / Anti Slip
Keramik 20 x 20 ( KM ) KW I DN Putih / Polos
Keramik 20 x 20 ( KM ) KW I DN Corak / Warna / Anti Sli

bh
bh
bh
bh
bh

517.00
870.00
970.00
2,144.00
3,360.00

517.00
870.00
970.00
2,144.00
3,360.00

517.00
870.00
970.00
2,144.00
3,360.00

51,700.00
43,500.00
48,500.00
53,600.00
84,000.00

18
19
20
21
22

Keramik 20
Keramik 30
Keramik 30
Stairnosing
Stairnosing

bh
bh
bh
m2
m2

3,700.00
8,400.00
8,000.00
10,000.00
13,300.00

3,700.00
8,400.00
8,000.00
10,000.00
13,300.00

3,700.00
8,400.00
8,000.00
10,000.00
13,300.00

23
24
25
26

Granit
Granit
Granit
Granit

m2
m2
m2
m2

1,867,200.00
1,570,600.00
1,373,200.00
1,273,900.00

1,867,200.00
1,570,600.00
1,373,200.00
1,273,900.00

1,867,200.00
1,570,600.00
1,373,200.00
1,273,900.00

27
28
29
30

Granito
Granito
Granito
Granito

m2
m2
m2
m2

272,000.00
195,000.00
312,600.00
277,400.00

272,000.00
195,000.00
312,600.00
277,400.00

272,000.00
195,000.00
312,600.00
277,400.00

31

Bata Karawang

bh

2,500.00

2,500.00

2,500.00

H.
1
2

BAHAN SALURAN AIR KOTOR / BERSIH


Gravel U 20 cm
Gravel U 30 cm

m'
m'

40,000.00
44,000.00

40,000.00
44,000.00

40,000.00
44,000.00

3
4

Gravel U 40 cm
Buis Beton dia. 20 cm (1 m')

m'
m'

57,600.00
61,750.00

57,600.00
61,750.00

57,600.00
61,750.00

5
6
7

Buis Beton dia. 30 cm (1 m')


Buis Beton dia. 40 cm (1 m')
Buis Beton dia. 50 cm (1 m')

m'
m'
m'

74,750.00
100,000.00
115,000.00

74,750.00
100,000.00
115,000.00

74,750.00
100,000.00
115,000.00

8
9

Buis Beton dia. 60 cm (1 m')


Buis Beton dia. 80 cm (1 m')

m'
m'

150,800.00
186,700.00

150,800.00
186,700.00

150,800.00
186,700.00

10
11
12

Buis Beton dia. 100 cm (1 m')


Buis Tanah dia. 10 cm (0.50 m)
Buis Tanah dia. 15 cm (0.50 m)

m'
stk
stk

240,100.00
7,200.00
9,700.00

240,100.00
7,200.00
9,700.00

240,100.00
7,200.00
9,700.00

13
14

Buis Tanah dia. 20 cm (0.50 m)


Buis Tanah dia. 25 cm (0.50 m)

stk
stk

11,300.00
16,000.00

11,300.00
16,000.00

11,300.00
16,000.00

15

Injuk

kg

10,000.00

10,000.00

10,000.00

I.
1

BAHAN LOGAM DAN BAHAN JADINYA


Baja Tulangan D 32 Ulir

kg

9,000.00

9,000.00

9,000.00

2
3
4
5
6

Baja Tulangan D 39 Ulir


Baja Tulangan D 42 Ulir
Baja Tulangan U 24 Polos
Baja Tulangan U 32 Polos
Pagar BRC Lengkap Tiang ( Tanpa Pondasi )

kg
kg
kg
kg
m2

10,000.00
14,000.00
7,000.00
9,000.00
127,000.00

10,000.00
14,000.00
7,000.00
9,000.00
127,000.00

10,000.00
14,000.00
7,000.00
9,000.00
127,000.00

7
8
9
10
11
12
13
14
15

Bondex
IWF Ex. DN SII
IWF Ex. Jepang
Besi Profil DN SII
Besi Profil Ex. Luar Negeri
Besi C Lip Chanel
Ongkos Galpanis Besi
Kawat Beton
Kawat Duri

m2
kg
kg
kg
kg
kg
kg
kg
m'

107,000.00
12,000.00
12,000.00
10,000.00
11,000.00
10,000.00
3,400.00
25,000.00
3,800.00

107,000.00
12,000.00
12,000.00
10,000.00
11,000.00
10,000.00
3,400.00
25,000.00
3,800.00

107,000.00
12,000.00
12,000.00
10,000.00
11,000.00
10,000.00
3,400.00
25,000.00
3,800.00

16
17
18
19
20

Kawat
Kawat
Kawat
Kawat
Kawat

m'
kg
kg
kg
kg

2,000.00
19,000.00
17,000.00
17,000.00
22,000.00

2,000.00
19,000.00
17,000.00
17,000.00
22,000.00

2,000.00
19,000.00
17,000.00
17,000.00
22,000.00

21
22
23
24
25

Wiremesh M8
Wiremesh M6
Seng Plat BJLS 30 lebar 60 cm ( 180 m )
Seng Plat BJLS 30 lebar 90 cm ( 180 m )
Plat Besi Tipis 1 mm

kg
kg
lbr
lbr
kg

8,300.00
8,300.00
29,000.00
44,000.00
16,000.00

8,300.00
8,300.00
29,000.00
44,000.00
16,000.00

8,300.00
8,300.00
29,000.00
44,000.00
16,000.00

26
27
28
29
30

Plat Besi Tipis


Plat Besi Tipis
Plat Besi Tipis
Plat Besi Tipis
Guard Rill

kg
kg
kg
kg
m

21,000.00
13,000.00
13,000.00
13,000.00

21,000.00
13,000.00
13,000.00
13,000.00

21,000.00
13,000.00
13,000.00
13,000.00

m2

40,000.00

40,000.00

40,000.00

3
4
5
6
7

J.
1

Alam
Alam
Alam
Alam
Tile
Tile
Tile
Tile

x 25 Dinding KM KW I DN Corak / Warna


x 30 KW I DN Corak / Warna / Anti Slip
x 30 KW I DN Putih / Polos
Keramik 10 / 20
Fiber
LN Ukuran Besar
LN Ukuran Kecil
DN Ukuran Besar
DN Ukuran Kecil
Essenza
Essenza
Essenza
Essenza

Ukuran
Ukuran
Ukuran
Ukuran

40
40
60
60

x
x
x
x

40
40
60
60

Polis
Unpolis
Polis
Unpolis

Pengikat
Bronjong 4 mm
Bronjong 3 mm
Tembaga
Las listrik

0,5 mm
2 mm s/d 5 mm
6 mm s/d 10 mm
10 mm ke atas

BAHAN KACA
Kaca Polos 2 mm ( ASAHI )

Harga Bahan SK Gub Jabar 2012

/dus
/dus
/dus
/dus
/dus

74,000.00 /dus
84,000.00 /dus
80,000.00 /dus

2
3

Kaca Polos 3 mm ( ASAHI )


Kaca Polos 5 mm ( ASAHI )

m2
m2

51,000.00
95,000.00

51,000.00
95,000.00

51,000.00
95,000.00

4
5
6
7
8

Kaca
Kaca
Kaca
Kaca
Kaca

m2
m2
m2
m2
m2

120,000.00
131,000.00
144,000.00
537,000.00
3,100,000.00

120,000.00
131,000.00
144,000.00
537,000.00
3,100,000.00

120,000.00
131,000.00
144,000.00
537,000.00
3,100,000.00

Rayband 5 mm ( ASAHI )
Rayband 8 mm ( ASAHI )
Rayband 12 mm ( ASAHI )
Patri Lokal Terpasang ( ASAHI )
Patri Ex.Luar Negeri Terpasang

9
10

Glass Block 20 x 20 cm ( Ex. Luar )


Glass Block DN 20 x 20 cm ( Kedaung )

bh
bh

38,000.00
24,000.00

38,000.00
24,000.00

38,000.00
24,000.00

K.
1

BAHAN PENUTUP ATAP


Atap Plastik Gelombang 80 x 180

lbr

23,000.00

23,000.00

23,000.00

Atap
Atap
Atap
Atap
Atap

lbr
lbr
lbr
lbr
bh

38,000.00
72,000.00
38,000.00
49,000.00
960.00

38,000.00
72,000.00
38,000.00
49,000.00
960.00

38,000.00
72,000.00
38,000.00
49,000.00
960.00

2
3
4
5
6

Fiber Glass Tipis 80 x 180 (Gelombang)


Fiber Glass Tebal 80 x 180 (Gelombang)
Asbes Gel. Kecil 4 mm 80 x 180
Asbes Gel. Kecil 5 mm 80 x 180
Genteng Plentong Pres Bakar KW I

7
8
9
10
11

Atap Genteng Plentong Pres Molen Oven KW I


Atap Genteng Flam Pres Molen Oven Jatiwangi
Bubung Genteng Pres Bulat ex. Jatiwangi
Bubung Genteng Segi Tiga ex. Jatiwangi
Bubung Genteng Beton

bh
bh
bh
bh
bh

1,100.00
1,300.00
4,000.00
4,200.00
6,000.00

1,100.00
1,300.00
4,000.00
4,200.00
6,000.00

1,100.00
1,300.00
4,000.00
4,200.00
6,000.00

12
13
14
15
16

Atap Genteng Beton Warna 14,4/m2


Atap Genteng Beton Natural 14,4/m2
Sirap Kelas I ( 80/m2 )
Atap Morando Glazur ( 18 bh/m2 )
Atap Morando Natural ( 18 bh/m2 )

m2
m2
bh
bh
bh

62,000.00
53,000.00
1,100.00
2,700.00
2,200.00

62,000.00
53,000.00
1,100.00
2,700.00
2,200.00

62,000.00
53,000.00
1,100.00
2,700.00
2,200.00

17
18
19
20

Bubung Murando Glazur


Seng Gelombang BJLS 30 80 x 180
Seng Gelombang BJLS 28 80 x 180
Atap Metal Rainbow Warna

bh
lbr
lbr
bh

4000
60,000.00
50,000.00

4000
60,000.00
50,000.00

4,000.00
60,000.00
50,000.00
0.00

L.
1
2

BAHAN
Lempengan Besi Baja Profil Desain Galvanis
Tiang Penyangga Besi st. 32 Galvanis

m
bh

133,333.33
400,000.00

133,333.33
400,000.00

133,333.33
400,000.00

3
4

Baja Struktur (15)


Pipa Baja (Tiang Panjang)

kg
kg

23,500.00
9,500,000.00

23,500.00
9,500,000.00

23,500.00
9,500,000.00

5
6
7

Besi Pengikat Baja Profil Desain (Blocking)


Mur Baut Blocking 12 x 25 mm
Mur Baut Post 16 x 48 mm

bh
bh
bh

57,500.00
2,600.00
2,600.00

57,500.00
2,600.00
2,600.00

57,500.00
2,600.00
2,600.00

M.

N.

800,000.00 /batang

BAHAN PENAMPUNG AIR


Tangki Air Fiber Glass 0.5 m3
Tangki Air Fiber Glass 1.0 m3
Tangki Air Fiber Glass 2.0 m3

bh
bh
bh

n/a
n/a
n/a

n/a
n/a
n/a

#VALUE!
#VALUE!
#VALUE!

Bak KM Fiber 60 x 60
Bak Teraso WC 30 x 40

bh
bh

n/a
n/a

n/a
n/a

#VALUE!
#VALUE!

Bak KM Teraso 60 x 60

bh

n/a

n/a

#VALUE!

ALAT TUKANG

1
2

Palu 0.5 kg
Cangkul

bh
bh

50,000.00
45,000.00

50,000.00
45,000.00

50,000.00
45,000.00

3
4
5
6

Singkup
Sekrop
Pengki
Linggis

bh
bh
bh
bh

55,100.00
55,100.00
11,000.00
48,000.00

55,100.00
55,100.00
11,000.00
48,000.00

55,100.00
55,100.00
11,000.00
48,000.00

7
8
9
10

Rool Meter 50 meter (Bahan Plastik)


Rool Meter 5 meter (Bahan Besi)
Selang Plastik untuk Waterpass dia. 0.5 cm
Waterpass Alumunium 60 cn

bh
bh
m
bh

80,000.00
25,000.00
1,700.00
70,000.00

80,000.00
25,000.00
1,700.00
70,000.00

80,000.00
25,000.00
1,700.00
70,000.00

O.
1
2
3
4
5
6
7
8

BAHAN PERPIPAAN
Besi Pipa Untuk Hydrant
Besi Pipa Untuk Hydrant
Besi Pipa Untuk Hydrant
Besi Pipa Untuk Hydrant
Shower Dengan Tiang
Shower Tanpa Tiang
Kran Tembok dia 0,5"
Kran Tembok dia 1"

bt
bt
bt
bt
bh
bh
bh
bh

230,000.00
268,000.00
367,000.00
411,000.00
200,000.00
150,000.00
25,000.00
50,000.00

230,000.00
268,000.00
367,000.00
411,000.00
200,000.00
150,000.00
25,000.00
50,000.00

230,000.00
268,000.00
367,000.00
411,000.00
200,000.00
150,000.00
25,000.00
50,000.00

9
10
11
12
13

Kran Panas Dingin San Ei Standar


Tempat Sabun Porselin
Wastafel Lengkap TOTO LW 230
Wastafel Lengkap INA
Closet Jongkok Porselin Warna TOTO

bh
bh
unit
unit
unit

240,000.00
25,000.00
900,000.00
650,000.00
115,000.00

240,000.00
25,000.00
900,000.00
650,000.00
115,000.00

240,000.00
25,000.00
900,000.00
650,000.00
115,000.00

14
15
16
17
18

Closet Jongkok Standar Putih Porselin TOTO


Wastafel Bulat Warna Standar Lengkap
Closet Duduk Warna Standar Lengkap INA
Urinoar Lengkap TOTO Warna Standar Lengkap
Penyekat Porselin Urinoir TOTO

unit
unit
bh
unit
lbr

95,000.00
700,000.00
950,000.00
650,000.00
350,000.00

95,000.00
700,000.00
950,000.00
650,000.00
350,000.00

95,000.00
700,000.00
950,000.00
650,000.00
350,000.00

19
20
21

Kitchen Zink Stainless Standar Lokal ( 1 Lobang )


Kitchen Zink Stainless Non Standar Franke ( 1 Lobang )
Kitchen Zink Stainless Non Standar Franke ( 2 Lobang )

bh
bh
bh

250,000.00
400,000.00
950,000.00

250,000.00
400,000.00
950,000.00

250,000.00
400,000.00
950,000.00

ltr
m3
ltr

15,000.00
600,000.00
12,000.00

15,000.00
600,000.00
12,000.00

15,000.00
600,000.00
12,000.00

BSP
BSP
BSP
BSP

dia.
dia.
dia.
dia.

P.

BAHAN BAKAR DAN PELUMAS

1
2
3

Minyak Tanah
Kayu bakar dari kayu-kayu karet
Minyak Solar

1"
1,25"
1,5"
2"

Harga Bahan SK Gub Jabar 2012

4
5

Bensin Premium
Plus Oil

6
7

Oli Mesran 40 SAE


Elpiji / Botol

Q.
1

ltr
ltr
ltr
15 Kg

12,000.00
20,000.00

12,000.00
20,000.00

12,000.00
20,000.00

25,000.00
150,000.00

25,000.00
150,000.00

25,000.00
150,000.00

PIPA POLY VINYL CHLORID (PVC)


Pipa PVC dia. 20 mm ( 3/4")

m'

1,687.50

1,687.50

1,687.50

2
3
4
5
6

Pipa
Pipa
Pipa
Pipa
Pipa

PVC
PVC
PVC
PVC
PVC

dia.
dia.
dia.
dia.
dia.

25
32
40
50
63

m'
m'
m'
m'
m'

2,312.50
3,125.00
4,062.50
6,325.00
8,000.00

2,312.50
3,125.00
4,062.50
6,325.00
8,000.00

2,312.50
3,125.00
4,062.50
6,325.00
8,000.00

9,250.00
12,500.00
16,250.00
25,300.00
32,000.00

/batang
/batang
/batang
/batang
/batang

7
8
9
10
11

Pipa
Pipa
Pipa
Pipa
Pipa

PVC
PVC
PVC
PVC
PVC

dia.
dia.
dia.
dia.
dia.

75 mm ( 3")
90 mm ( 4")
110 mm ( 5")
140 mm ( 6")
160 mm (8")

m'
m'
m'
m'
m'

8,775.00
11,725.00
17,500.00
28,400.00
30,000.00

8,775.00
11,725.00
17,500.00
28,400.00
30,000.00

8,775.00
11,725.00
17,500.00
28,400.00
30,000.00

35,100.00
46,900.00
70,000.00
113,600.00
120,000.00

/batang
/batang
/batang
/batang
/batang

12
13
14
15
16

Pipa
Pipa
Pipa
Pipa
Pipa

PVC
PVC
PVC
PVC
PVC

dia.
dia.
dia.
dia.
dia.

200
225
250
315
355

m'
m'
m'
m'
m'

57,700.00
72,575.00
83,750.00
130,000.00
196,825.00

57,700.00
72,575.00
83,750.00
130,000.00
196,825.00

57,700.00
72,575.00
83,750.00
130,000.00
196,825.00

230,800.00
290,300.00
335,000.00
520,000.00
787,300.00

/batang
/batang
/batang
/batang
/batang

17
18
19
20
21

Pipa PVC dia. 400 mm


Pipa PVC dia. 500 mm
Pipa PVC dia. 630 mm
Ground Reservoir 50 m3
Ground Reservoir 100 m3

m'
m'
m'
unit
unit

239,625.00
239,625.00
239,625.00
958,500.00 /batang
408,325.00
408,325.00
408,325.00 1,633,300.00 /batang
650,450.00
650,450.00
650,450.00 2,601,800.00 /batang
179,853,300.00 179,853,300.00 179,853,300.00
335,170,000.00 335,170,000.00 335,170,000.00

22
23
24
25

Ground
Ground
Ground
Ground

unit
unit
unit
unit

665,500,000.00 665,500,000.00 665,500,000.00


937,750,000.00 937,750,000.00 937,750,000.00
###
###
###
###
###
###

26
27
28
29

Bend
Bend
Bend
Bend

63 mm
75 mm
90 mm
110 mm

bh
bh
bh
bh

63,200.00
113,100.00
119,200.00
176,900.00

63,200.00
113,100.00
119,200.00
176,900.00

63,200.00
113,100.00
119,200.00
176,900.00

30
31

Bend 90 0 all socket dia. 160 mm


Bend 90 0 all socket dia. 200 mm

bh
bh

412,100.00
759,900.00

412,100.00
759,900.00

412,100.00
759,900.00

32
33
34

Bend 90 0 all socket dia. 225 mm


Bend 90 0 all socket dia. 250 mm
Bend 90 0 all socket dia. 285 mm

bh
bh
bh

948,900.00
1,361,000.00
1,640,100.00

948,900.00
1,361,000.00
1,640,100.00

948,900.00
1,361,000.00
1,640,100.00

35
36

Bend 90 0 all socket dia. 315 mm


Knee PVC 1"

bh
bh

2,409,900.00
4,000.00

2,409,900.00
4,000.00

2,409,900.00
4,000.00

37
38
39

Bend 45 0 all socket dia. 63 mm


Bend 45 0 all socket dia. 75 mm
Bend 45 0 all socket dia. 90 mm

bh
bh
bh

57,100.00
95,000.00
106,600.00

57,100.00
95,000.00
106,600.00

57,100.00
95,000.00
106,600.00

40
41

Bend 45 0 all socket dia. 110 mm


Bend 45 0 all socket dia. 160 mm

bh
bh

146,100.00
347,700.00

146,100.00
347,700.00

146,100.00
347,700.00

42
43
44

Bend 45 0 all socket dia. 200 mm


Bend 45 0 all socket dia. 225 mm
Bend 45 0 all socket dia. 250 mm

bh
bh
bh

595,600.00
865,900.00
1,096,200.00

595,600.00
865,900.00
1,096,200.00

595,600.00
865,900.00
1,096,200.00

45
46

Bend 45 0 all socket dia. 285 mm


Bend 45 0 all socket dia. 315 mm

bh
bh

1,492,900.00
1,848,900.00

1,492,900.00
1,848,900.00

1,492,900.00
1,848,900.00

47
48
49
50

Bend
Bend
Bend
Bend

22,5
22,5
22,5
22,5

0
0
0
0

all
all
all
all

socket
socket
socket
socket

dia.
dia.
dia.
dia.

63 mm
75 mm
90 mm
110 mm

bh
bh
bh
bh

52,200.00
87,300.00
100,000.00
130,200.00

52,200.00
87,300.00
100,000.00
130,200.00

52,200.00
87,300.00
100,000.00
130,200.00

51
52
53
54
55

Bend
Bend
Bend
Bend
Bend

22,5
22,5
22,5
22,5
22,5

0
0
0
0
0

all
all
all
all
all

socket
socket
socket
socket
socket

dia.
dia.
dia.
dia.
dia.

160
200
225
250
285

mm
mm
mm
mm
mm

bh
bh
bh
bh
bh

299,900.00
499,400.00
747,300.00
923,100.00
1,247,800.00

299,900.00
499,400.00
747,300.00
923,100.00
1,247,800.00

299,900.00
499,400.00
747,300.00
923,100.00
1,247,800.00

56
57
58
59
60
61
62
63
64

Bend 22,5 0 all socket dia. 315 mm


Tee all Socket dia. 32 x 32
Tee all Socket dia. 50 x 32
Tee all Socket dia. 50 x 50
Tee all Socket dia. 63 x 32
Tee all Socket dia. 63 x 50
Tee all Socket dia. 63 x 63
Tee all Socket dia. 75 x 32
Tee all Socket dia. 75 x 50

bh
bh
bh
bh
bh
bh
bh
bh
bh

1,519,800.00
4,400.00
12,100.00
13,700.00
63,700.00
68,100.00
167,000.00
178,500.00
178,500.00

1,519,800.00
4,400.00
12,100.00
13,700.00
63,700.00
68,100.00
167,000.00
178,500.00
178,500.00

1,519,800.00
4,400.00
12,100.00
13,700.00
63,700.00
68,100.00
167,000.00
178,500.00
178,500.00

65
66
67
68
69

Tee
Tee
Tee
Tee
Tee

all
all
all
all
all

Socket
Socket
Socket
Socket
Socket

dia.
dia.
dia.
dia.
dia.

75
75
90
90
90

bh
bh
bh
bh
bh

129,100.00
167,500.00
189,500.00
165,900.00
204,300.00

129,100.00
167,500.00
189,500.00
165,900.00
204,300.00

129,100.00
167,500.00
189,500.00
165,900.00
204,300.00

70
71
72
73
74

Tee
Tee
Tee
Tee
Tee

all
all
all
all
all

Socket
Socket
Socket
Socket
Socket

dia.
dia.
dia.
dia.
dia.

90 x 75
90 x 90
110 x 63
110 x 75
110 x 90

bh
bh
bh
bh
bh

232,900.00
232,900.00
266,400.00
280,700.00
329,700.00

232,900.00
232,900.00
266,400.00
280,700.00
329,700.00

232,900.00
232,900.00
266,400.00
280,700.00
329,700.00

75
76
77
78
79

Tee
Tee
Tee
Tee
Tee

all
all
all
all
all

Socket
Socket
Socket
Socket
Socket

dia.
dia.
dia.
dia.
dia.

110
160
160
160
160

110
63
75
90
110

bh
bh
bh
bh
bh

309,300.00
471,400.00
483,500.00
547,800.00
568,700.00

309,300.00
471,400.00
483,500.00
547,800.00
568,700.00

309,300.00
471,400.00
483,500.00
547,800.00
568,700.00

80
81
82

Tee all Socket dia. 160 x 160


Tee all Socket dia. 200 x 90
Tee all Socket dia. 200 x 110

bh
bh
bh

643,900.00
951,600.00
987,400.00

643,900.00
951,600.00
987,400.00

643,900.00
951,600.00
987,400.00

mm
mm
mm
mm
mm

Reservoir
Reservoir
Reservoir
Reservoir

90
90
90
90

0
0
0
0

all
all
all
all

(
(
(
(
(

1")
1,1/4")
1,1/2")
2")
2,5")

mm (10")
mm (12")
mm
mm
mm

200 m3
300 m3
500 m3
1000 m3

socket
socket
socket
socket

dia.
dia.
dia.
dia.

x
x
x
x
x

63
75
32
50
63

x
x
x
x
x

Harga Bahan SK Gub Jabar 2012

6,750.00 /batang

83
84

Tee all Socket dia. 200 x 160


Tee all Socket dia. 200 x 200

bh
bh

1,148,400.00
1,309,900.00

1,148,400.00
1,309,900.00

1,148,400.00
1,309,900.00

85
86
87
88
89

Tee all Socket dia. 250 x 160


Tee all Socket dia. 250 x 200
Tee all Socket dia. 250 x 250
Tee all Socket dia. 250 x 315
Reducer all Socket dia. 50 x 32

bh
bh
bh
bh
bh

2,681,500.00
3,207,200.00
3,752,800.00
5,362,300.00
6,000.00

2,681,500.00
3,207,200.00
3,752,800.00
5,362,300.00
6,000.00

2,681,500.00
3,207,200.00
3,752,800.00
5,362,300.00
6,000.00

90
91
92
93
94

Reducer
Reducer
Reducer
Reducer
Reducer

all
all
all
all
all

Socket
Socket
Socket
Socket
Socket

dia.
dia.
dia.
dia.
dia.

63 x 32
63 x 50
90 x 50
90 x 63
110 x 63

bh
bh
bh
bh
bh

18,700.00
13,700.00
44,000.00
63,700.00
92,300.00

18,700.00
13,700.00
44,000.00
63,700.00
92,300.00

18,700.00
13,700.00
44,000.00
63,700.00
92,300.00

95
96
97
98
99

Reducer
Reducer
Reducer
Reducer
Reducer

all
all
all
all
all

Socket
Socket
Socket
Socket
Socket

dia.
dia.
dia.
dia.
dia.

110
160
200
250
315

bh
bh
bh
bh
bh

107,700.00
180,200.00
322,500.00
587,900.00
755,500.00

107,700.00
180,200.00
322,500.00
587,900.00
755,500.00

107,700.00
180,200.00
322,500.00
587,900.00
755,500.00

bh
bh
bh
bh
bh

143,400.00
183,500.00
325,200.00
533,500.00
924,700.00

143,400.00
183,500.00
325,200.00
533,500.00
924,700.00

143,400.00
183,500.00
325,200.00
533,500.00
924,700.00

Flange
Flange
Flange
Flange
Flange

105
106
107
108
109

Flange Socket dia. 250


Flange Socket dia. 315
Clamp Saddle dia. 90 x 63
Clamp Saddle dia. 110 x 63
Clamp Saddle dia. 160 x 63

bh
bh
bh
bh
bh

1,057,100.00
1,826,900.00
45,600.00
52,200.00
136,800.00

1,057,100.00
1,826,900.00
45,600.00
52,200.00
136,800.00

1,057,100.00
1,826,900.00
45,600.00
52,200.00
136,800.00

110
111
112
113

Clamp Saddle dia. 200 x 63


Dop / Cap dia. 32
Dop / Cap dia. 50
Dop / Cap dia. 63

bh
bh
bh
bh

277,400.00
2,700.00
4,400.00
22,000.00

277,400.00
2,700.00
4,400.00
22,000.00

277,400.00
2,700.00
4,400.00
22,000.00

114
115
116
117

Dop / Cap dia. 90


Drat Socket dia. 32
Drat Socket dia. 50
Drat Socket dia. 63

bh
bh
bh
bh

39,500.00
5,400.00
14,800.00
24,100.00

39,500.00
5,400.00
14,800.00
24,100.00

39,500.00
5,400.00
14,800.00
24,100.00

118
119

Pipa GI Medium Class dia 1/2"


Pipa GI Medium Class dia 3/4"

m'
m'

18,700.00
27,200.00

18,700.00
27,200.00

18,700.00
27,200.00

108,800.00 /batang

120
121
122

Pipa GI Medium Class dia 1 1/4"


Pipa GI Medium Class dia 1 1/2"
Pipa GI Medium Class dia 2"

m'
m'
m'

38,400.00
78,425.00
96,025.00

38,400.00
78,425.00
96,025.00

38,400.00
78,425.00
96,025.00

153,600.00 /batang
313,700.00 /batang
384,100.00 /batang

123
124

Pipa GI Medium Class dia 2 1/2"


Pipa GI Medium Class dia 3"

m'
m'

122,700.00
160,050.00

122,700.00
160,050.00

122,700.00
160,050.00

490,800.00 /batang
640,200.00 /batang

125
126
127

Pipa GI Medium Class dia 4"


Accessories GI Bend 90 0 all flange dia. 8
Accessories GI Bend 90 0 all flange dia. 12

m'
bh
bh

233,400.00
473,100.00
987,400.00

233,400.00
473,100.00
987,400.00

233,400.00
473,100.00
987,400.00

933,600.00 /batang

128
129

Accessories GI Tee all flange dia. 8" x 8"


Accessories GI Tee all flange dia. 12" x 12"

bh
bh

685,200.00
1,370,900.00

685,200.00
1,370,900.00

685,200.00
1,370,900.00

130
131
132

Accessories GI Tee Flange dia. 8"


Accessories GI Tee Flange dia. 12"
Accessories GI Gate Valve dia. 2" ( all screw )

bh
bh
bh

188,400.00
342,800.00
864,200.00

188,400.00
342,800.00
864,200.00

188,400.00
342,800.00
864,200.00

133
134

Accessories GI Gate Valve dia. 3" ( all screw )


Accessories GI Gate Valve dia. 4" ( all screw )

bh
bh

1,217,600.00
1,452,800.00

1,217,600.00
1,452,800.00

1,217,600.00
1,452,800.00

135
136
137
138

Accessories
Accessories
Accessories
Accessories

bh
bh
bh
bh

2,433,600.00
5,258,500.00
8,752,600.00
11,380,100.00

2,433,600.00
5,258,500.00
8,752,600.00
11,380,100.00

2,433,600.00
5,258,500.00
8,752,600.00
11,380,100.00

139
140
141

Waterstop PVC lebar 15 cm (25m/rol)


Waterstop PVC lebar 20 cm (25m/rol)
Check/ Ball Valve dia 1"

m'
m'
bh

64,000.00
80,000.00
25,000.00

64,000.00
80,000.00
25,000.00

Karet Penyekat Air / Rubber Water Stop lebar 150 cm


Karet Penyekat Air / Rubber Water Stop lebar 225 cm
Plat Karet Untuk Perletakan Jembatan Type 4 Kx
Penutup Sambungan / Joint Sealer tebal 25 mm
Pengisi Sambungan / Joint Sealer tebal 10 mm
Pengisi Sambungan / Joint Sealer tebal 20 mm
Mistar Ukur Panjang 0,50 - 1,00 m
Mistar Ukur Panjang 1,00 - 1,50 m
Mistar Ukur Panjang 1,50 - 2,00 m

m
m
m
m
m2
m2
bh
bh
bh

200,000.00
275,000.00
110,000.00
225,000.00
200,000.00
210,000.00
175,000.00
225,000.00
325,000.00

200,000.00
275,000.00
110,000.00
225,000.00
200,000.00
210,000.00
175,000.00
225,000.00
325,000.00

200,000.00
275,000.00
110,000.00
225,000.00
200,000.00
210,000.00
175,000.00
225,000.00
325,000.00

10
11
12
13
14

Mistar
Mistar
Papan
Papan
Papan

bh
bh
bh
bh
bh

450,000.00
650,000.00
1,000,000.00
300,000.00
750,000.00

450,000.00
650,000.00
1,000,000.00
300,000.00
750,000.00

450,000.00
650,000.00
1,000,000.00
300,000.00
750,000.00

15
16
17
18
19

Papan Operasi Bendung


Kotak Baja Untuk Menyimpan Data
Pintu Angkat Type I.B = 0,30 m
Pintu Angkat Type I.B = 0,40 m
Pintu Angkat Type I.B = 0,50 m

bh
bh
bh
bh
bh

750,000.00
200,000.00
1,425,000.00
1,700,000.00
2,550,000.00

750,000.00
200,000.00
1,425,000.00
1,700,000.00
2,550,000.00

750,000.00
200,000.00
1,425,000.00
1,700,000.00
2,550,000.00

20
21
22

Pintu Angkat Type II.B = 0,30 m


Pintu Angkat Type II.B = 0,40 m
Pintu Angkat Type II.B = 0,50 m

bh
bh
bh

2,000,000.00
2,550,000.00
3,100,000.00

2,000,000.00
2,550,000.00
3,100,000.00

2,000,000.00
2,550,000.00
3,100,000.00

S.

BAHAN MEKANIKAL

1
2
3
4
5
6
7
8
9

1
2
3

GI
GI
GI
GI

dia.
dia.
dia.
dia.
dia.

90
110
160
200
250

100
101
102
103
104

R.

Socket
Socket
Socket
Socket
Socket

x
x
x
x
x

90
110
160
200
225

Gate
Gate
Gate
Gate

Valve
Valve
Valve
Valve

dia.
dia.
dia.
dia.

6" ( all screw )


8" ( all screw )
10" ( all screw )
12" ( all screw )

64,000.00 Harga Bekasi/ Bogor 7-1- 2012


80,000.00 Harga Bekasi/ Bogor 7-1- 2012
25,000.00 Harga Bekasi/ Bogor 7-1- 2012

BAHAN FASILITAS PENGAIRAN

Ukur Panjang 2,00 - 3,00 m


Ukur Panjang 3,50 - 4,00 m
Nama Bendung
Nama Bangunan / Nomenklatur
Eksploitasi

Kabel NYA 1 x 1.5 Prima


Kabel NYA 1 x 2.5 Prima
Kabel NYM 2 x 1.5 Prima

n/a
n/a
n/a

n/a
n/a
n/a

Harga Bahan SK Gub Jabar 2012

#VALUE!
#VALUE!
#VALUE!

4
5

Kabel NYM 3 x 1.5 Prima


Kabel NYM 2 x 2.5 Prima

n/a
n/a

n/a
n/a

#VALUE!
#VALUE!

6
7
8
9
10

Kabel
Kabel
Kabel
Kabel
Kabel

NYM
NYM
NYM
NYM
NYM

3
4
2
3
4

x
x
x
x
x

2.5 Prima
2.5 Prima
4 Prima
4 Prima
4 Prima

n/a
n/a
n/a
n/a
n/a

n/a
n/a
n/a
n/a
n/a

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

11
12
13
14
15

Kabel
Kabel
Kabel
Kabel
Kabel

NYM
NYM
NYM
NYM
NYM

2
3
4
2
3

x
x
x
x
x

6 Prima
6 Prima
6 Prima
10 Prima
10 Prima

n/a
n/a
n/a
n/a
n/a

n/a
n/a
n/a
n/a
n/a

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

16
17
18
19
20

Kabel
Kabel
Kabel
Kabel
Kabel

NYM 4 x 10 Prima
NYM 4 x 16 Prima
NYY 2 x 4 Prima
NYY 3 x 4 Prima
NYY 4 x 4 Prima

n/a
n/a
n/a
n/a
n/a

n/a
n/a
n/a
n/a
n/a

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

21
22
23
24
25

Kabel
Kabel
Kabel
Kabel
Kabel

NYY
NYY
NYY
NYY
NYY

n/a
n/a
n/a
n/a
n/a

n/a
n/a
n/a
n/a
n/a

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

26
27
28
29
30

Kabel NYY 4 x 10 Prima


Kabel NYY 4 x 16 Prima
NSFB FUJI EA - 100A
NSFB FUJI EA - 150A
Rumah Panel 30 x 60 cm (Kosong)

n/a
n/a
n/a
n/a
n/a

n/a
n/a
n/a
n/a
n/a

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

31
32
33
34

Skring
Skring
Skring
MCB 1

n/a
n/a
n/a
n/a

n/a
n/a
n/a
n/a

#VALUE!
#VALUE!
#VALUE!
#VALUE!

35
36
37
38

MCB 3 PAS
Tahanan 50 A Merk FUJI
Tahanan 100 A Merk FUJI
Saklar Broco Tunggal Standard

n/a
n/a
n/a
n/a

n/a
n/a
n/a
n/a

#VALUE!
#VALUE!
#VALUE!
#VALUE!

39
40

Saklar Broco Seri Standard


Stop Kontak Broco Standard

n/a
n/a

n/a
n/a

#VALUE!
#VALUE!

41
42
43

Instalasi Titik Lampu/Stop Kontak


Lampu Pijar 25 watt s/d 100 watt
Lampu Neon TL Philip 20 watt

bh
bh

15,000.00
30,000.00

15,000.00
30,000.00

#VALUE!
15,000.00
30,000.00

44
45

Lampu Neon TL Philip 40 watt


Down Light + SL 25 watt

bh
bh

34,000.00
75,000.00

34,000.00
75,000.00

34,000.00
75,000.00

46
47
48

Lampu Sirkel TL 20 watt Lengkap


Lampu Merkuri 80 watt
Lampu Taman + Tiang + Lampu 1 Buah

bh
bh
bh

54,000.00
150,000.00
200,000.00

54,000.00
150,000.00
200,000.00

54,000.00
150,000.00
200,000.00

49
50

Lampu Baret 30 cm + Neon


Lampu Neon Arcrilik 2 x 40 watt

bh
bh

160,000.00
325,000.00

160,000.00
325,000.00

160,000.00
325,000.00

51
52
53

Jarum Penangkal Petir 16


Kawat BC ( Tembaga )
Pentanahan Penangkal Petir

bh
kg
ttk

27,000.00
40,000.00
225,000.00

27,000.00
40,000.00
225,000.00

27,000.00
40,000.00
225,000.00

54

Pentanahan Panel

ttk

100,000.00

100,000.00

100,000.00

T.
1
2
3

BAHAN ALAT PENGGANTUNG / KUNCI


Kunci Silinder ALFA Untuk Pintu Alumunium
Tarikan Pintu Alumunium
Kunci 2 Slaag ROYAL

bh
bh
bh

137,500.00
113,500.00
125,000.00

137,500.00
113,500.00
125,000.00

137,500.00
113,500.00
125,000.00

4
5
6
7
8

Rel Henderson Lengkap


Rel Marathon 1 Pintu
Kunci Slaag Silinder SEIS Asli Type 210 s/d 226
Kunci Slaag Anchor Asli
Kunci Slaag ISO

unit
unit
bh
bh
bh

225,000.00
200,000.00
275,000.00
200,000.00
150,000.00

225,000.00
200,000.00
275,000.00
200,000.00
150,000.00

225,000.00
200,000.00
275,000.00
200,000.00
150,000.00

2
3
4
2
3

x
x
x
x
x

6 Prima
6 Prima
6 Prima
10 Prima
10 Prima

Kas 2 Group Biasa


Kas 3 Group Biasa
Kas 5 Group Biasa
PAS

n/a

n/a

9
10
11
12
13
14
15
16
17

Kunci KM Bulat Kualitas Biasa


Kunci KM Bulat ALFA
Kunci 2 Slaag Silinder Utama Standard
Kunci Gembok Besar
Kunci 2 Slaag Kuda Terbang
Espagnolet
Grendel 15 cm
Grendel 5 cm
Hak Angin Kait Jendela Biasa

bh
bh
bh
bh
bh
ps
bh
bh
ps

70,000.00
75,000.00
200,000.00
40,000.00
45,000.00
27,000.00
12,000.00
7,000.00
15,000.00

70,000.00
75,000.00
200,000.00
40,000.00
45,000.00
27,000.00
12,000.00
7,000.00
15,000.00

70,000.00
75,000.00
200,000.00
40,000.00
45,000.00
27,000.00
12,000.00
7,000.00
15,000.00

18
19
20
21
22

Hak Angin Jendela Antik


Hak Angin Sendok Stainless / Kuningan
Nako Lengkap Tralis 1 Daun
Sloot Pintu Berikut Rantai
Sloot Jendela Tunggal

ps
bh
bh
bh
bh

25,000.00
27,000.00
25,000.00
27,000.00
12,000.00

25,000.00
27,000.00
25,000.00
27,000.00
12,000.00

25,000.00
27,000.00
25,000.00
27,000.00
12,000.00

23
24
25

Engsel Pintu Unilon Standard


Engsel Jendela Unilon Standard
Tarikan Almari Rata - Rata

ps
ps
bh

30,000.00
25,000.00
10,000.00

30,000.00
25,000.00
10,000.00

30,000.00
25,000.00
10,000.00

U.

BAHAN PENGIKAT UNTUK KONSTRUKSI JALAN


Hotmix
Aspal ( ESO ) 1 Drum 150 kg
Aspal Curah
Aspal Minyak

ton
kg
kg
kg

1,284,000.00
10,322.58
9,000.00
10,000.00

1,284,000.00
10,322.58
9,000.00
10,000.00

BAHAN PENGISAP AIR SUMUR DALAM


Pompa Kodok
Pompa Dragon Tegal

unit
unit

135,000.00
210,000.00

135,000.00
210,000.00

1
2
3
4
V.
1
2

Harga Bahan SK Gub Jabar 2012

1,284,000.00
10,322.58 1,600,000.00 /drum
9,000.00
10,000.00

135,000.00
210,000.00

3
4

Pompa Dragon Asli


Mesin Pompa Air 100 watt - Sanyo

unit
unit

280,000.00
600,000.00

280,000.00
600,000.00

280,000.00
600,000.00

5
6
7
8
9

Mesin Pompa Air 150 watt - Sanyo


Pompa Zet Pump 250 watt - Sanyo
Pompa Zet Pump 450 watt - Sanyo
Pompa Submersible Kap. 150 Liter / menit 3 KW
Gear Pump Kap. 60 Liter / menit

unit
unit
unit
unit
unit

825,000.00
3,600,000.00
5,200,000.00
19,000,000.00
11,000,000.00

825,000.00
3,600,000.00
5,200,000.00
19,000,000.00
11,000,000.00

825,000.00
3,600,000.00
5,200,000.00
19,000,000.00
11,000,000.00

10
11

Deep Weil Dengan Kelengkapannya Kap. 150 Liter / men unit


Hand Oil Pump
unit

###
3,200,000.00

###
3,200,000.00

###
3,200,000.00

W
1

STANDARD RATA - RATA SEWA ALAT BERAT, KENDARAAN, TRUCK DAN LAINNYA
Asphal Finisher
jam
122,400.00
122,400.00

122,400.00

2
3
4
5
6

Asphal Melting Kalte


Asphal Mixing Plant
Asphal Sprayer
Bulldozer 100 - 150 HP
Compressor 4000 - 6500 L/M

jam
jam
jam
jam
jam

n/a
n/a
3,391,400.00
3,391,400.00
50,000.00
50,000.00
220,000.00
220,000.00
52,800.00
52,800.00

7
8
9
10
11

Concrete Mixer 0,125 m3


Concrete Mixer 0,3 - 0,60 m3
Concrete Vibrator
Crane 10 - 15 Ton
Crusher / SCB

jam
jam
jam
jam
jam

n/a

12
13
14
15
16

Draklint
Dump Truck 3 - 4 m3
Dump Truck 5 Ton 125 HP
Excavator 80 - 100 HP
Excavator Backhoe ( Long )

jam
jam
jam
jam
jam

n/a

17
18
19
20

Excavator Backhoe ( Short )


Flatbed Truck 3,5 Ton
Generator set
Jack Hammer

jam
jam
jam
jam

n/a

21
22
23
24

Mesin Las Listrik 18 PK


Mesin Pompa Air 3"
Motor Grader 100 HP
Pedestrian Roller

jam
jam
jam
jam

25
26

Pick UP
Pneumatic Drill Hammer

jam
jam

n/a
n/a

27
28
29

Roller Pneumatic 8 - 15 Ton


Roller Vibrator 5 - 8 Ton
Screening Plant

jam
jam
jam

n/a
n/a

n/a

#VALUE!
192,000.00
#VALUE!

30
31

Sheep Foot Roller


Sprayer, Self - Prop 10001

jam
jam

n/a
n/a

n/a
n/a

#VALUE!
#VALUE!

32
33
34

Stone Crusher
Tamper, Viberator Plate
Tandem Roller 6 - 8 Ton

jam
jam
jam

396,000.00
26,400.00
191,600.00

396,000.00
26,400.00
191,600.00

396,000.00
26,400.00
191,600.00

35
36

Three Wheel Roller


Tire Roller 8 - 10 Ton

jam
jam

94,400.00
81,600.00

94,400.00
81,600.00

94,400.00
81,600.00

37
38
39

Track Loader 75 - 100 HP


Tractor Equitment
Trailler, Towed 1 Ton

jam
jam
jam

n/a
n/a
n/a

n/a
n/a
n/a

#VALUE!
#VALUE!
#VALUE!

40
41

Truck 3/4
Truck Fuso

jam
jam

n/a
n/a

n/a
n/a

#VALUE!
#VALUE!

42
43
44

Water Pump 70 - 100 mm


Water Tank 3000 - 4500 Liter
Wheel Loader 1 - 1,6 m3

jam
jam
jam

n/a
46,200.00
18,600.00
300,600.00

n/a

46,200.00
18,600.00
300,600.00

#VALUE!
46,200.00
18,600.00
300,600.00
#VALUE!

122,200.00
135,500.00
250,000.00

#VALUE!
122,200.00
135,500.00
250,000.00
#VALUE!

n/a
n/a
122,200.00
135,500.00
250,000.00

n/a

n/a
n/a
250,000.00
218,100.00
28,000.00

250,000.00
218,100.00
28,000.00

48,700.00
n/a

48,700.00
n/a

208,000.00
38,300.00

208,000.00
38,300.00
n/a
n/a

20,700.00
81,600.00
220,000.00

#VALUE!
250,000.00
218,100.00
28,000.00
48,700.00
#VALUE!
208,000.00
38,300.00
#VALUE!
#VALUE!

n/a
192,000.00

#VALUE!
3,391,400.00
50,000.00
220,000.00
52,800.00

192,000.00

20,700.00
81,600.00
220,000.00

Harga Bahan SK Gub Jabar 2012

20,700.00
81,600.00
220,000.00

10

HARGA SATUAN PEKERJAAN


NO

JENIS PEKERJAAN

HARGA SATUAN

PEKERJAAN PERSIAPAN
1 m' Pagar sementara dari kayu tinggi 2 m

128,290.00

2
3

1 m' Pagar sementara dari seng gelombang tinggi 2 m


1 m' Pagar sementara dari kawat berduri tinggi 1,8 m

193,860.00
159,040.00

4
5

1 m' Pengukuran dan pemasangan bouwplank


1 m Pembuatan kantor sementara dengan lantai plesteran

97,140.00
994,010.00

6
7

1 m Pembuatan gudang semen dan alat - alat


1 m Membersihkan lapangan dan peralatan

510,870.00
10,500.00

8
9

1 m Pembuatan bak adukan ukuran 40 cm x 50 cm x 20 cm


1 m Pembuatan bedeng buruh

48,460.00
567,580.00

10
11
12

1 m Pembuatan steger bambu


1 m Pembuatan jalan sementara (dengan tenaga)
1 m Pembuatan jalan sementara, tebal 25 cm (dengan tenaga)

243,730.00
95,670.00
115,340.00

13
14

1 m Bongkaran beton bertulang


1 m Bongkaran dinding tembok bata merah

859,980.00
429,990.00

15
16

1 m Bongkaran lantai
1 m Menurunkan atap genteng/sirap

240,900.00
3,300.00

17
18

1 m Menurunkan atap seng


1 m Membongkar rangka atap

19
20

1 m Membongkar rangka kuda-kuda kayu


1 m Membongkar langit-langit + rangka

PEKERJAAN TANAH
Menggali 1 m3 tanah biasa sedalam 1 meter

3,300.00
64,650.00
3,512,400.00
244,650.00
47,250.00

2
3

Menggali 1 m3 tanah biasa sedalam 2 meter


Menggali 1 m3 tanah biasa sedalam 3 meter

58,050.00
69,030.00

4
5
6

Menggali 1 m3 tanah keras sedalam 1 meter


Menggali 1 m3 tanah cadas sedalam 1 meter
Menggali 1 m3 tanah lumpur sedalam 1 meter

62,880.00
95,400.00
76,050.00

7
8

Mengerjakan 1 m2 stripping tebing setinggi 1 meter


Membuang 1 m3 tanah sejauh 30 meter

3,450.00
20,700.00

9
10

Mengurug kembali 1 m3 galian tanah biasa sedalam 1 meter


Mengurug kembali 1 m3 galian tanah biasa sedalam 2 meter

34,500.00
19,350.00

11
12

Mengurug kembali 1 m3 galian tanah biasa sedalam 3 meter


Mengurug kembali 1 m3 galian tanah keras sedalam 1 meter

23,010.00
20,960.00

13
14

Mengurug kembali 1 m3 galian tanah cadas sedalam 1 meter


Mengurug kembali 1 m3 galian tanah lumpur sedalam 1 meter

31,800.00
25,350.00

15
16

Memadatkan 1 m3 tanah (per 20 cm)


Mengurug 1 m3 pasir urug

34,500.00
162,900.00

17
18

Memasang 1 m3 Lapisan pudel campuran 1 KP : 3 PP : 7 TL untuk stabilisasi tanah.


Memasang 1 m3 Lapisan pudel campuran 1 KP : 5 TL untuk stabilisasi tanah.

252,390.00
207,920.00

19
20

Memasang 1 m2 lapisan ijuktebal 10 cm , untuk bidang resapan.


Mengurug 1 m3 sirtu padat untuk peninggian lantai bangunan
PEKERJAAN PONDASI

70,350.00
206,850.00

1
2

Memasang 1 m3 pondasi batu belah, campuran 1 PC : 3 PP


Memasang 1 m3 pondasi batu belah, campuran 1 PC : 4 PP

670,320.00
628,400.00

3
4

Memasang 1 m3 pondasi batu belah, campuran 1 PC : 5 PP


Memasang 1 m3 pondasi batu belah, campuran 1 PC : 6 PP

599,330.00
578,890.00

5
6

Memasang 1 m3 pondasi batu belah, campuran 1 PC : 8 PP


Memasang 1 m3 pondasi batu belah, campuran 1 KP : 1 SM : 2 PP

550,880.00
405,060.00

7
8

Memasang 1 m3 pondasi batu belah, campuran 1 PC : 3 KP : 10 PP


Memasang 1 m3 pondasi batu belah, campuran 1/4 PC : 1 KP : 4 PP

508,670.00
488,270.00

9
10
11
1

Memasang 1 m3 batu kosong (anstamping)


Memasang 1 m3 pondasi siklop, 60% beton campuran 1 PC : 2 PB : 3 KR dan 40% batu belah
Memasang 1 m3 pondasi sumuran, diameter 100 cm
PEKERJAAN BETON
Membuat 1 m3 beton mutu f'c = 7,4 MPa (K 100), slump (12 2) cm, w/c = 0,87

300,570.00
1,657,860.00
658,170.00
692,870.00

2
3

Membuat 1 m3 beton mutu f'c = 9,8 MPa (K 125), slump (12 2) cm, w/c = 0,78
Membuat 1 m3 beton mutu f'c = 12,2 MPa (K 150), slump (12 2) cm, w/c = 0,72

724,770.00
749,910.00

4
5

Membuat 1 m3 lantai kerja beton mutu f'c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
Membuat 1 m3 beton mutu f'c = 14,5 MPa (K 175), slump (12 2) cm, w/c = 0,66

643,580.00
779,470.00

6
7

Membuat 1 m3 beton mutu f'c = 16,9 MPa (K 200), slump (12 2) cm, w/c = 0,61
Membuat 1 m3 beton mutu f'c = 19,3 MPa (K 225), slump (12 2) cm, w/c = 0,58

807,970.00
828,920.00

NO

JENIS PEKERJAAN

HARGA SATUAN
3

8
9

Membuat 1 m3 beton mutu f'c = 21,7 MPa (K 250), slump (12 2) cm, w/c = 0,56
Membuat 1 m3 beton mutu f'c = 24,0 MPa (K 275), slump (12 2) cm, w/c = 0,53

843,280.00
995,920.00

10
11

Membuat 1 m3 beton mutu f'c = 26,4 MPa (K 300), slump (12 2) cm, w/c = 0,52
Membuat 1 m3 beton mutu f'c = 28,8 MPa (K 325), slump (12 2) cm, w/c = 0,49

875,630.00
1,102,160.00

12
13

Membuat 1 m3 beton mutu f'c = 31,2 MPa (K 350), slump (12 2) cm, w/c = 0,48
Membuat 1 m3 beton kedap air dengan strorox - 100

949,460.00
665,020.00

14
15

Memasang 1 m PVC Waterstop lebar 150 mm


Memasang 1 m PVC Waterstop lebar 200 mm

73,410.00
91,330.00

16
17

Membuat 1 m PVC Waterstop lebar 230 mm - 320 mm


Pembesian 10 kg dengan besi polos atau besi ulir

#VALUE!
87,270.00

18
19

Memasang 10 kg kabel presstressed polos/strands


Memasang 10 Kg jaring kawat baja/wire mesh

83,170.00
91,250.00

20
21
22

Memasang 1 m2 bekisting untuk pondasi


Memasang 1 m2 bekisting untuk sloof
Memasang 1 m2 bekisting untuk kolom

85,720.00
88,970.00
212,960.00

23
24

Memasang 1 m2 bekisting untuk balok


Memasang 1 m2 bekisting untuk plat lantai

217,460.00
300,960.00

25
26

Memasang 1 m2 bekisting untuk dinding


Memasang 1 m2 bekisting untuk tangga

#VALUE!
206,060.00

27
28

Memasang 1 m2 jembatan untuk pengecoran beton


Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting)

51,980.00
2,543,750.00

29
30

Membuat 1 m3 sloof beton bertulang (200 kg besi + bekisting)


Membuat 1 m3 kolom beton bertulang (300 kg besi + bekisting)

3,055,800.00
5,212,500.00

31
32

Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting)


Membuat 1 m3 plat beton bertulang (150 kg besi + bekisting)

4,080,950.00
3,894,490.00

33
34

Membuat 1 m3dinding beton bertulang (150 kg besi + bekisting)


Membuat 1 m3dinding beton bertulang (200 kg besi + bekisting)

3,726,250.00
3,842,600.00

35
36

Membuat 1 m kolom praktis beton bertulang (11 x 11) cm


Membuat 1 m ring balok beton bertulang (10 x 15) cm
PEKERJAAN BESI

47,770.00
67,120.00

1
2

Memasang 1 kg besi profil


Memasang 1 kg rangka kuda-kuda baja IWF

20,050.00
22,350.00

3
4

Mengerjakan 100 kg pekerjaan perakitan


Membuat 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku

5
6

Mengerjakan 10 cm pengelasan dengan las listrik


Membuat 1 m2 rangka jendela besi scuare tube (25 x 5) cm

7
8

Memasang 1 m2 pintu rolling door besi


Memasang 1 m2 pintu lipat (Folding door) bahan plastik/PVC

#VALUE!
#VALUE!

9
10

Memasang 1 m2 sunscreen alluminium


Memasang 1 m2 rolling door alluminium

#VALUE!
#VALUE!

11
12

Memasang 1 m kusen pintu alluminium


Memasang 1 m2 pintu alluminium strip lebar 8 cm

#VALUE!
#VALUE!

13
14
15

Memasang 1 m2 pintu kaca rangka alluminium


Memasang 1 m2 venetions blinds dan Vertical blinds
Memasang 1 m2 terali besi strip (2 x 3) mm

16
17

Memasang 1 m2 kawat nyamuk


Memasang 1 m2 jendela nako & tralis

14,250.00
27,690.00

18
19

Memasang 1 m' talang datar/ jurai seng bjls 28 lebar 90 cm


Memasang 1 m' talang 1/2 lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm

28,500.00
33,120.00

20
21

Memasang 1 m' rangka besi hollow 1 x 40.40.2 mm, modul 60 x 120, dinding partisi
Memasang 1 m' rangka besi hollow 1 x 40.40.2 mm, modul 60 x 60, plafon

35,670.00
49,920.00

28,030.00
727,080.00
22,680.00
#VALUE!

12,220.00
49,920.00
237,930.00

PEKERJAAN DINDING
Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 2 PP

208,270.00

2
3

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 3 PP
Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 4 PP

197,230.00
189,620.00

4
5
6

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 5 PP
Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 6 PP
Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 3 KP :

185,940.00
185,210.00
171,410.00

7
8

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 2 PP
Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 3 PP

100,240.00
94,910.00

9
10

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 4 PP
Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 5 PP

91,910.00
48,020.00

11
12

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 6 PP
Memasang 1 m2 dinding bata merah ukuran (5 x11 x 22) tebal 1/2 bata, campuran spesi 1 PC : 8 PP

89,100.00
87,020.00

NO

JENIS PEKERJAAN

HARGA SATUAN

13
14

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 3 KP
Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 KP : 1 SM

85,870.00
#VALUE!

15
16

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal V2 bata, campuran spesi 1 KP : 1 SM
Memasang 1 m2 dinding HB/CB 20 , campuran spesi 1 PC : 3 PP

#VALUE!
256,620.00

17
18

Memasang 1 m2 dinding HB/CB 20, campuran spesi 1 PC : 4 PP


Memasang 1 m2 dinding HB/CB 15, campuran spesi 1 PC : 3 PP

257,620.00
#VALUE!

19
20

Memasang 1 m2 dinding HB/CB 15, campuran spesi 1 PC : 4 PP


Memasang 1 m2 dinding HB/CB 10, campuran spesi 1 PC : 3 PP

#VALUE!
#VALUE!

21
22

Memasang 1 m2 dinding HB/CB 10, campuran spesi 1 PC : 4 PP


Memasang 1 m2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 PC : 3 PP

#VALUE!
#VALUE!

23
24

Memasang 1 m2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 PC : 4 PP
Memasang 1 m2 dinding bata berongga ekspose ukuran (5x11x24) cm, campuran spesi 1 PC : 3 PP

#VALUE!
#VALUE!

1
2

PEKERJAAN PLESTERAN
Membuat 1 m2 plesteran 1 PC : 1 PP, tebal 15 mm
Membuat 1 m2 plesteran 1 PC : 2 PP, tebal 15 mm

53,550.00
47,730.00

3
4

Membuat 1 m2 plesteran 1 PC : 3 PP, tebal 15 mm


Membuat 1 m2 plesteran 1 PC : 4 PP, tebal 15 mm

45,250.00
43,530.00

5
6

Membuat 1 m2 plesteran 1 PC : 5 PP, tebal 15 mm


Membuat 1 m2 plesteran 1 PC : 6 PP, tebal 15 mm

42,600.00
41,830.00

7
8

Membuat 1 m2 plesteran 1 PC : 7 PP, tebal 15 mm


Membuat 1 m2 plesteran 1 PC : 8 PP, tebal 15 mm

41,430.00
41,020.00

9
10

Membuat 1 m2 plesteran 1 PC : 1/2 KP : 3 PP, tebal 15 mm


Membuat 1 m2 plesteran 1 PC : 2 KP : 8 PP, tebal 15 mm

42,580.00
40,680.00

11
12

Membuat 1 m2 plesteran 1 SM : 1 KP : 1 PP, tebal 15 mm


Membuat 1 m2 plesteran 1 SM : 1 KP : 2 PP, tebal 15 mm

13
14

Membuat 1 m2 plesteran 1 PC : 2 PP, tebal 20 mm


Membuat 1 m2 plesteran 1 PC : 3 PP, tebal 20 mm

63,880.00
51,370.00

15
16
17

Membuat 1 m2 plesteran 1 PC : 4 PP, tebal 20 mm


Membuat 1 m2 plesteran 1 PC : 5 PP, tebal 20 mm
Membuat 1 m2 plesteran 1 PC : 6 PP, tebal 20 mm

58,220.00
57,040.00
55,960.00

18
19

Membuat 1 m2 plesteran 1 SM : 1 KP : 2 PP, tebal 20 mm


Membuat 1 m2 Berapen 1 PC : 5 PP, tebal 15 mm

#VALUE!
27,160.00

20
21

Membuat 1 m' Plesteran Skoning lebar 10 mm 1 PC : 2 PP.


Membuat 1 m2 Plesteran Granit, 1 PC : 2 Granit, tebal 10 mm

39,520.00
#VALUE!

22
23

Membuat 1 m2 Plesteran Teraso , 1 PC : 2 Batu Teraso, tebal 10 mm


Membuat 1 m2 Plesteran Ciprat / Kamprotan 1 PC : 2 PP

#VALUE!
33,720.00

24
25

Membuat 1 m2 finishing siar pasangan dinding bata merah (=20 m')


Membuat 1 m2 finishing siar pasangan dinding conblock ekspose (=8 m')

19,490.00
9,330.00

26
27

Membuat 1 m2 finishing siar pasangan batu kali adukan 1 PC : 2 PP


Membuat 1 m2 acian

41,310.00
24,760.00

#VALUE!
#VALUE!

PEKERJAAN LANTAI
Memasang 1 m2 lantai ubin PC abu-abu ukuran (40 x 40) cm

#VALUE!

2
3
4

Memasang 1 m2 lantai ubin PC abu-abu ukuran (30 x 30) cm


Memasang 1 m2 lantai ubin PC abu-abu ukuran (20 x 20) cm
Memasang 1 m2 lantai ubin warna ukuran (40 x 40) cm

#VALUE!
#VALUE!
#VALUE!

5
6

Memasang 1 m2 lantai ubin warna ukuran (30 x 30) cm


Memasang 1 m2 lantai ubin warna ukuran (20 x 20) cm

#VALUE!
#VALUE!

7
8

Memasang 1 m2 lantai ubin teraso ukuran (40 x 40) cm


Memasang 1 m2 lantai ubin teraso ukuran (30 x 30) cm

#VALUE!
89,290.00

9
10

Memasang 1 m2 lantai ubin granit ukuran (40 x 40) cm


Memasang 1 m2 lantai ubin granit ukuran (30 x 30) cm

#VALUE!
#VALUE!

11
12

Memasang 1 m2 lantai ubin teralux ukuran (40 x 40) cm


Memasang 1 m2 lantai ubin teralux ukuran (30 x 30) cm

#VALUE!
#VALUE!

13
14

Memasang 1 m2 lantai ubin teralux marmer ukuran (60 x 60) cm


Memasang 1 m2 lantai ubin teralux marmer ukuran (40 x 40) cm

#VALUE!
#VALUE!

15
16
17

Memasang 1 m2 lantai ubin teralux marmer ukuran (30 x 30) cm


Memasang 1 m plint ubin PC abu-abu ukuran (15 x 20) cm
Memasang 1 m plint ubin PC abu-abu ukuran (10 x 30) cm

#VALUE!
#VALUE!
#VALUE!

18
19

Memasang 1 m plint ubin PC abu-abu ukuran (10 x 40) cm


Memasang 1 m plint ubin PC warna ukuran (10 x20) cm

#VALUE!
#VALUE!

20
21

Memasang 1 m plint ubin PC warna ukuran (10x 30) cm


Memasang 1 m plint ubin PC warna ukuran (10x 40) cm

#VALUE!
#VALUE!

22
23

Memasang 1 m plint ubin teraso ukuran (15 x 30) cm


Memasang 1 m plint ubin teraso ukuran (10 x 40) cm

23,640.00
#VALUE!

NO

JENIS PEKERJAAN

HARGA SATUAN

24
25

Memasang 1 m plint ubin granit ukuran (10 x 40) cm


Memasang 1 m plint ubin granit ukuran (10 x 30) cm

#VALUE!
#VALUE!

26
27

Memasang 1 m plint ubin teralux kerang ukuran (10 x 40) cm


Memasang 1 m plint ubin teralux kerang ukuran (10 x 30) cm

#VALUE!
#VALUE!

28
29

Memasang 1 m plint ubin teralux marmer ukuran (10 x 60) cm


Memasang 1 m plint ubin teralux marmer ukuran (10 x 40) cm

#VALUE!
#VALUE!

30
31

Memasang 1 m plint ubin teralux marmer ukuran (10 x 30) cm


Memasang 1 m2 lantai teraso cor ditempat, tebal 3 cm

#VALUE!
#VALUE!

32
33

Memasang 1 m2 lantai keramik artistik ukuran (10 x 20) cm


Memasang 1 m2 lantai keramik artistik ukuran (10 x 10) cm atau (5 x 20) cm

170,370.00
178,260.00

34
35

Memasang 1 m2 lantai keramik ukuran (33 x 33) cm


Memasang 1 m2 lantai keramik warna ukuran (30 x 30) cm

#VALUE!
208,430.00

36
37
38

Memasang 1 m2 lantai keramik warna ukuran (20 x 20) cm


Memasang 1 m2 lantai keramik ukuran (10 x 33) cm, variasi/border
Memasang 1 m2 lantai mosaik ukuran (30 x 30) cm, campuran spesi 1 PC : 3 PP

199,460.00
#VALUE!
#VALUE!

39
40

Memasang 1 m plint keramik warna ukuran (10 x 20) cm


Memasang 1 m' plint keramik warna ukuran (10 x 10) cm

41
42

Memasang 1 m plint keramik ukuran (5 x 20) cm


Memasang 1 m plint internal cove artistik ukuran (5 x 5 x 20) cm

43
44

Memasang 1 m2 lantai granit DN ukuran (100 x 100) cm


Memasang 1 m2 lantai karpet

45
46

Memasang 1 m2 underlayer/ Pelapis bawah karpet


Memasang 1 m2 lantai parquet kayu

47
48

Memasang 1 m2 lantai kayu (gymfloor)


Memasang 1 m2 dinding porselen ukuran (11 x 11) cm

49
50

Memasang 1 m2 dinding porselin ukuran (10 x 20) cm


Memasang 1 m2 dinding porselin ukuran (20 x 20) cm

51
52
53

Memasang 1 m2 dinding keramik artistik ukuran (10 x20) cm


Memasang 1 m2 dinding keramik artistik ukuran (5 x 20) cm
Memasang 1 m2 dinding keramik ukuran (10x20) cm

187,190.00
#VALUE!
181,890.00

54
55

Memasang 1 m2 dinding keramik warna ukuran (20 x 20) cm


Memasang 1 m2 dinding granit DN ukuran (100 x 100) cm

#VALUE!
#VALUE!

56
57

Memasang 1 m2 dinding bata pelapis ukuran (3 x 7 x 24) cm


Memasang 1 m2 dinding batu paras

#VALUE!
#VALUE!

58
59

Memasang 1 m2 dinding batu tempel hitam


Memasang 1 m2 lantai Vinyl ukuran (30 x 30) cm

60
61

Memasang 1 m2 wall paper, lebar 50 cm


Memasang 1 m2 floor hardener

62
63

Memasang 1 m' plint Vinyl karet ukuran (15 x 30) cm dengan perekat
Memasang 1 m' plint kayu kelas II tebal 2Cm, Lebar 10 Cm

22,350.00
22,940.00
#VALUE!
#VALUE!
1,553,550.00
#VALUE!
#VALUE!
#VALUE!

KL. I

PEKERJAAN LANGIT-LANGIT
Memasang 1 m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm

#VALUE!
178,090.00
#VALUE!
#VALUE!

209,460.00
#VALUE!
#VALUE!
#VALUE!
#VALUE!
35,800.00
24,400.00

2
3
4

Memasang 1 m2 langit-langit akustik ukuran (30 x 30) cm


Memasang 1 m2 langit-langit akustik ukuran (30 x 60) cm
Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm

5
6

Memasang 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 4 mm


Memasang 1 m2 langit-langit lambriziring kayu, tebal 9 mm

38,390.00
#VALUE!

7
8

Memasang 1 m2 langit-langit gypsum board DN ukuran (1200x2400x9) mm,


Memasang 1 m' list plafond gysum profil

35,490.00
#VALUE!

Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm + rangka alluminium


Memasang 1 m' list langit-langit kayu kamper 5 cm

#VALUE!
23,200.00

9
10
1

PEKERJAAN KAYU
Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu kelas I

#VALUE!
#VALUE!
150,680.00

12,484,750.00

2
3

Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III
Membuat dan memasang 1 m2 pintu klamp standar, kayu kelas II

8,650,250.00
9,034,020.00

4
5
6

Membuat dan memasang 1 m2 pintu klamp sederhana, kayu kelas gudang sementara.
Membuat dan memasang 1 m2 daun pintu panel, kayu kelas I
Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu kelas I atau II

275,370.00
731,500.00
416,040.00

7
8

Membuat dan memasang 1 m2 pintu dan jendela jalusi kayu kelas I atau II
Membuat 1 m2 daun pintu kayu lapis (teakwood) rangkap, rangka tertutup kayu kelas II (lebar sampai

760,940.00
480,800.00

9
10

Membuat 1 m2 pintu Teakwood rangkap, rangka expose kayu kelas I atau II


Memasang 1 m2jalusi kusen, kayu kelas I atau II

602,890.00
854,640.00

11
12

Memasang 1 m2teakwood rangkap, rangka expose kayu kelas I


Memasang 1 m2 teakwood rangkap lapis formika, rangka expose kayu kelas I

589,850.00
687,820.00

NO

JENIS PEKERJAAN

HARGA SATUAN
3

13
14

Memasang 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan bentang 6 meter


Memasang 1 m3 konstruksi kuda-kuda expose, kayu kelas I

15
16

Memasang 1 m3 konstruksi gordeng, kayu kelas II


Memasang 1 m2 rangka atap genteng keramik, kayu kelas II

17
18

Memasang 1 m2 rangka atap genteng beton, kayu kelas II


Memasang 1 m2 rangka atap sirap, kayu kelas II

474,800.00
94,360.00

19
20

Memasang 1 m2 rangka langit-langit (50x100) cm, kayu kelas II atau III


Memasang 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III

108,000.00
109,820.00

21
22

Memasang 1 m1 lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II


Memasang 1 m1 lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II

23
24

Memasang 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas II atau


Memasang 1 m2 dinding pemisah teakwood rangkap, rangka kayu kelas II

199,970.00
311,030.00

25
26
27

Memasang 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II


Memasang 1 m2 dinding lambriziring dari papan kayu kelas I
Memasang 1 m2 dinding lambriziring dari teakwood ukuran (120 x 240) cm

#VALUE!
258,100.00
51,710.00

28

Memasang 1 m2 dinding bilik, rangka kayu kelas III atau IV


PEKERJAAN PENUTUP ATAP

7,706,200.00
13,555,150.00
8,467,950.00
334,800.00

98,910.00
99,460.00

65,750.00

1
2

1 m Pasang atap genteng palentong kecil


1 m Pasang atap genteng kodok / glazzur

39,610.00
#VALUE!

3
4

1 m Pasang atap genteng palentong besar/ super


1 m' Pasang bubung genteng palentong kecil

28,810.00
76,020.00

5
6

1 m' Pasang bubung genteng kodok glazuur


1 m' Pasang bubung genteng palentong besar

#VALUE!
72,820.00

7
8

1 m Pasang roof light fibreglass uk. 180 cm x 90 cm


1 m Pasang atap asbes gelombang uk. 2.500 mm x 920 mm, tebal 5 mm

#VALUE!
#VALUE!

9
10

1 m Pasang atap asbes gelombang uk. 2.250 mm x 920 mm, tebal 5 mm


1 m Pasang atap asbes gelombang uk. 2.000 mm x 920 mm, tebal 5 mm

#VALUE!
#VALUE!

11
12
13

1 m Pasang atap asbes gelombang uk. 1.800 mm x 920 mm, tebal 5 mm


1 m Pasang atap asbes gelombang uk. 3.000 mm x 1.050 mm, tebal 4 mm
1 m Pasang atap asbes gelombang uk. 2.700 mm x 1.050 mm, tebal 4 mm

54,840.00
#VALUE!
#VALUE!

14
15

1 m Pasang atap asbes gelombang uk. 2.400 mm x 1.050 mm, tebal 4 mm


1 m Pasang atap asbes gelombang uk. 2.100 mm x 1.050 mm, tebal 4 mm

#VALUE!
#VALUE!

16
17

1 m Pasang atap asbes gelombang uk. 1.500 mm x 1.050 mm, tebal 4 mm


1 m Pasang atap asbes gelombang uk. 3.000 mm x 1.080 mm, tebal 6 mm

#VALUE!
#VALUE!

18
19

1 m Pasang atap asbes gelombang uk. 2.700 mm x 1.080 mm, tebal 6 mm


1 m Pasang atap asbes gelombang uk. 2.400 mm x 1.080 mm, tebal 6 mm

#VALUE!
#VALUE!

20
21

1 m Pasang atap asbes gelombang uk. 2.100 mm x 1.080 mm, tebal 6 mm


1 m Pasang atap asbes gelombang uk. 1.800 mm x 1.080 mm, tebal 6 mm

#VALUE!
#VALUE!

22
23

1 m' Bubung stel gelombang 0,92 m


1 m' Bubung stel gelombang 1,05 m

#VALUE!
#VALUE!

24
25

1 m' Bubung stel gelombang 1,08 m


1 m' Bubung nok paten 0,92 m

#VALUE!
#VALUE!

26
27
28

1 m' Bubung nok paten 1,05 m


1 m' Bubung nok paten 1,08 m
1 m' Nok stel rata 0,92 m

#VALUE!
#VALUE!
#VALUE!

29
30

1 m' Nok stel rata 1,05 m


1 m Pasang genteng beton

#VALUE!
703,210.00

31
32

1 m Pasang genteng aspal


1 m Pasang genteng metal

#VALUE!
#VALUE!

33
34

1 m Pasang atap sirap kayu


1 m' Pasang nok genteng beton

35
36

1 m' Pasang nok genteng aspal


1 m' Pasang nok genteng metal

37
38

1 m' Pasang nok sirap


1 m Pasang atap seng gelombang

41,020.00
33,060.00

39
40
41

1 m' Pasang nok atap seng


1 m Pasang atap aluminium
1 m' Pasang nok aluminium

24,040.00
#VALUE!
#VALUE!

42

1 m Pasang aluminium foil/ sisalation

66,580.00
81,770.00
#VALUE!
#VALUE!

#VALUE!

NO.
1

INDEKS

HARGA

SATUAN

KEBUTUHAN

HARGA,
SATUAN
(Rp)

BAHAN
(Rp)

UPAH (Rp)

JUMLAH HARGA
(Rp)

2.000

PEKERJAAN PERSIAPAN
1

1 m' Pagar sementara dari kayu tinggi 2 m


Kayu dolken 8 - 10 (cm) panjang 4 m /
1.250 btg
kiau
5.000 kg
Semen PC @ 50 kg

22,000.00

27,500.00

27,500.00

1,250.00

6,250.00

6,250.00
1,025.00

0.005 m

Pasir ayak untuk beton

205,000.00

1,025.00

0.009 m

Koral Beton

122,000.00

1,098.00

1,098.00

0.072 m

Kayu 5/7

650,000.00

46,800.00

46,800.00

0.060 kg

Paku berbagai ukuran (2" - 5")

17,000.00

1,020.00

1,020.00

0.400 ltr

Residu

8,000.00

3,200.00

0.400 Oh

Pekerja tak terlatih

60,000.00

0.200 Oh

Tukang kayu

70,000.00

0.020 Oh

Kepala tukang

80,000.00

0.020 Oh

Mandor

90,000.00

3,200.00

24,000.00
14,000.00

24,000.00

1,600.00
1,800.00

1,600.00

Jumlah
0%

Jumlah

128,290.00

1 m' Pagar sementara dari seng gelombang tinggi 2 m


Kayu dolken 8 - 10 (cm) panjang 4 m /
1.250 btg
kiau
2.500 kg
Semen PC @ 50 kg
Seng gelombang bjls 20 uk. 0,914 x 1,829
1.200 lbr
(m)
0.005 m
Pasir ayak untuk beton

22,000.00

27,500.00

1,250.00

3,125.00

27,500.00
3,125.00

50,000.00

60,000.00

60,000.00
1,025.00

205,000.00

1,025.00

0.009 m

Koral Beton

122,000.00

1,098.00

1,098.00

0.072 m

Kayu 5/7

650,000.00

46,800.00

46,800.00

0.060 kg

Paku berbagai ukuran (2" - 5")

17,000.00

1,020.00

1,020.00

0.450 ltr

Cat menie

22,000.00

9,900.00

0.200 Oh

Pekerja tak terlatih

60,000.00

0.400 Oh

Tukang kayu

70,000.00

0.020 Oh

Kepala tukang

80,000.00

0.020 Oh

Mandor

90,000.00

9,900.00

12,000.00
28,000.00

12,000.00

1,600.00
1,800.00

1,600.00

Jumlah
0%

Jumlah

1,800.00
193,868.00

Dibulatkan

193,860.00

1 m' Pagar sementara dari kawat berduri tinggi 1,8 m


Kayu dolken 8 - 10 (cm) panjang 4 m /
1.000 btg
kiau
2.000 kg
Semen PC @ 50 kg
25.000 kg

28,000.00

193,868.00

Keuntungan Maksimal

Kawat berduri

22,000.00

22,000.00

1,250.00

2,500.00

22,000.00
2,500.00

3,800.00

95,000.00

95,000.00

0.005 m

Pasir ayak untuk beton

205,000.00

1,025.00

1,025.00

0.009 m

Koral Beton

122,000.00

1,098.00

1,098.00

0.060 kg

Paku berbagai ukuran (2" - 5")

17,000.00

1,020.00

0.200 Oh

Pekerja tak terlatih

60,000.00

0.300 Oh

Tukang kayu

70,000.00

0.020 Oh

Kepala tukang

80,000.00

0.020 Oh

Mandor

90,000.00

1,020.00

12,000.00
21,000.00

12,000.00

1,600.00
1,800.00

1,600.00

Jumlah

21,000.00
1,800.00
159,043.00

Keuntungan Maksimal

0%

Jumlah

159,043.00

Dibulatkan
4

128,293.00

Dibulatkan

1,800.00
128,293.00

Keuntungan Maksimal

14,000.00

159,040.00

1 m' Pengukuran dan pemasangan bouwplank


0.007 m

Kayu papan 3/20

650,000.00

4,550.00

4,550.00

0.120 m

Kayu balok 5/7

650,000.00

78,000.00

78,000.00

0.020 kg

Paku berbagai ukuran (2" - 5")

17,000.00

340.00

0.100 Oh

Pekerja tak terlatih

60,000.00

340.00

6,000.00

6,000.00

NO.
1

INDEKS

SATUAN

2.000

KEBUTUHAN

HARGA

HARGA,
SATUAN
(Rp)

BAHAN
(Rp)

UPAH (Rp)

JUMLAH HARGA
(Rp)

0.100 Oh

Tukang kayu

70,000.00

0.010 Oh

Kepala tukang

80,000.00

7,000.00
800.00

0.005 Oh

Mandor

90,000.00

450.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

7,000.00
800.00
450.00
97,140.00

0%

97,140.00
97,140.00

NO.
1
5

INDEKS

HARGA

SATUAN

KEBUTUHAN

HARGA,
SATUAN
(Rp)

BAHAN
(Rp)

UPAH (Rp)

JUMLAH HARGA
(Rp)

2.000

1 m Pembuatan kantor sementara dengan lantai plesteran


Kayu dolken 8 - 10 (cm) panjang 4 m /
1.250 btg
kiau
0.180 m
Kayu Kelas II

22,000.00

27,500.00

27,500.00

### 432,000.00

432,000.00

0.080 kg

Paku berbagai ukuran (2" - 5")

17,000.00

1,360.00

1,360.00

1.100 kg

Besi strip

13,000.00

14,300.00

14,300.00

35.000 kg

1,250.00

43,750.00

43,750.00

0.150 m

Pasir pasang

195,000.00

29,250.00

29,250.00

0.100 m

Pasir ayak untuk beton

205,000.00

20,500.00

20,500.00

0.150 m

Koral Beton

122,000.00

18,300.00

18,300.00

600.00

18,000.00

18,000.00

30.000 bh

Semen PC @ 50 kg

Batu bata merah (lokal)

0.250 lbr

Seng plat BJLS 27 uk. 0.9 x 1.83 (m)

44,000.00

11,000.00

11,000.00

0.200 bh

Jendela nako (kerangka + kaca 5 mm)

25,000.00

5,000.00

5,000.00

0.080 m

Kaca bening tebal 3 mm

51,000.00

4,080.00

4,080.00

0.150 bh

Kunci tanam

45,000.00

6,750.00

6,750.00

0.060 lbr

Tripleks uk. 1,22 x 2,44 (m), tebal 4 mm

62,100.00

3,726.00

2.000 Oh

Pekerja tak terlatih

60,000.00

1.000 Oh

Tukang batu

70,000.00

2.000 Oh

Tukang kayu

70,000.00

0.300 Oh

Kepala tukang

0.050 Oh

Mandor

3,726.00

###
70,000.00

120,000.00
140,000.00

80,000.00

###
24,000.00

90,000.00

4,500.00

Jumlah
0%

Jumlah

994,010.00

1 m Pembuatan gudang semen dan alat - alat


Kayu dolken 8 - 10 (cm) panjang 4 m /
1.700 btg
kiau
0.210 m
Kayu
0.300 kg
10.500 kg

Paku berbagai ukuran (2" - 5")


Semen PC @ 50 kg

37,400.00

37,400.00

650,000.00 136,500.00

22,000.00

136,500.00

17,000.00

5,100.00

5,100.00

1,250.00

13,125.00

13,125.00
6,150.00

0.030 m

Pasir ayak untuk beton

205,000.00

6,150.00

0.050 m

122,000.00

6,100.00

6,100.00

50,000.00

75,000.00

75,000.00

0.250 lbr

Koral Beton
Atap seng gelombang bjls 20 uk. 0,914 x
1,829 (m)
Seng plat BJLS 27 uk. 0.9 x 1.83 (m)

44,000.00

11,000.00

1.000 Oh

Pekerja tak terlatih

60,000.00

2.000 Oh

Tukang kayu

70,000.00

0.200 Oh

Kepala tukang

80,000.00

0.050 Oh

Mandor

90,000.00

1.500 lbr

11,000.00

60,000.00
###
16,000.00
4,500.00

Jumlah

60,000.00
140,000.00
16,000.00
4,500.00
510,875.00

Keuntungan Maksimal

0%

Jumlah

510,875.00

Dibulatkan

510,870.00

1 m Membersihkan lapangan dan peralatan


0.100 Oh

Pekerja tak terlatih

60,000.00

6,000.00

0.050 Oh

Mandor

90,000.00

4,500.00

Jumlah

6,000.00
4,500.00
10,500.00

Keuntungan Maksimal

0%

Jumlah

10,500.00

Dibulatkan
8

4,500.00

994,016.00

Dibulatkan

24,000.00
994,016.00

Keuntungan Maksimal

70,000.00

10,500.00

1 m Pembuatan bak adukan ukuran 40 cm x 50 cm x 20 cm


0.036 m

Kayu gergajian kelas IV, papan

650,000.00

23,400.00

23,400.00

0.080 kg

Paku berbagai ukuran (2" - 5")

17,000.00

1,360.00

1,360.00

Kayu gergajian kelas IV, balok

650,000.00

0.00

0.300 Oh

Tukang kayu

70,000.00

0.030 Oh

Mandor

90,000.00

0.00

21,000.00
2,700.00

21,000.00
2,700.00

NO.
1

INDEKS
2.000

HARGA

SATUAN

KEBUTUHAN

HARGA,
SATUAN
(Rp)

BAHAN
(Rp)

UPAH (Rp)

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

JUMLAH HARGA
(Rp)

48,460.00
0%

48,460.00
48,460.00

NO.
1
9

INDEKS

HARGA

SATUAN

KEBUTUHAN

HARGA,
SATUAN
(Rp)

BAHAN
(Rp)

UPAH (Rp)

JUMLAH HARGA
(Rp)

2.000

1 m Pembuatan bedeng buruh


Kayu dolken 8 - 10 (cm) panjang 4 m /
1.250 btg
kiau
0.186 m
Kayu
0.300 kg
18.000 kg

Paku berbagai ukuran (2" - 5")


Semen PC @ 50 kg

27,500.00

27,500.00

650,000.00 120,900.00

22,000.00

120,900.00

17,000.00

5,100.00

5,100.00

1,250.00

22,500.00

22,500.00
6,150.00

0.030 m

Pasir ayak untuk beton

205,000.00

6,150.00

0.050 m

122,000.00

6,100.00

6,100.00

50,000.00

75,000.00

75,000.00

1.350 lbr

Koral Beton
Atap seng gelombang bjls 20 uk. 0,914 x
1,829 (m)
Tripleks uk. 1,22 x 2,44 (m), tebal 4 mm

62,100.00

83,835.00

1.000 Oh

Pekerja tak terlatih

60,000.00

2.000 Oh

Tukang kayu

70,000.00

0.200 Oh

Kepala tukang

80,000.00

0.050 Oh

Mandor

90,000.00

1.500 lbr

83,835.00

60,000.00
###
16,000.00
4,500.00

Jumlah
0%

Jumlah

567,580.00

1.250 btg

Bambu diameter 6-8/600cm

17,100.00

21,375.00

0.186 m

Tali ijuk

10,000.00

1,860.00

1.000 Oh

Pekerja tak terlatih

60,000.00

2.000 Oh

Tukang kayu

70,000.00

0.200 Oh

Kepala tukang

80,000.00

0.050 Oh

Mandor

90,000.00

21,375.00
1,860.00

60,000.00
###
16,000.00
4,500.00

60,000.00
140,000.00
16,000.00
4,500.00
243,735.00

Keuntungan Maksimal

0%

Jumlah

243,735.00

Dibulatkan

243,730.00

1 m Pembuatan jalan sementara (dengan tenaga)


0.150 m

Batu belah 10 - 15 (cm)

130,000.00

19,500.00

19,500.00

0.090 m

Batu kerikil dari galian bukit

153,000.00

13,770.00

13,770.00

0.010 m

Pasir pasang

195,000.00

1,950.00

1.000 Oh

Pekerja tak terlatih

60,000.00

0.005 Oh

Mandor

90,000.00

1,950.00

60,000.00
450.00

Jumlah

60,000.00
450.00
95,670.00

Keuntungan Maksimal

0%

Jumlah

95,670.00

Dibulatkan

95,670.00

1 m Pembuatan jalan sementara, tebal 25 cm (dengan tenaga)


0.275 m

Batu belah 10 - 15 (cm)

130,000.00

35,750.00

35,750.00

0.030 m

Batu kerikil dari galian bukit

153,000.00

4,590.00

4,590.00

0.050 m

Pasir urug / timbun

120,000.00

6,000.00

1.000 Oh

Pekerja tak terlatih

60,000.00

60,000.00

0.100 Oh

Mandor

90,000.00

9,000.00

6,000.00

Jumlah

60,000.00
9,000.00
115,340.00

Keuntungan Maksimal

0%

Jumlah

115,340.00

Dibulatkan
13

1 m Pembuatan steger bambu

Jumlah

12

4,500.00

567,585.00

Dibulatkan

11

16,000.00
567,585.00

Keuntungan Maksimal

10

60,000.00
140,000.00

115,340.00

1 m Bongkaran beton bertulang


13.334 Oh
0.666 Oh

Pekerja tak terlatih

60,000.00

###

Mandor

90,000.00

59,940.00

Jumlah
Keuntungan Maksimal
Jumlah

800,040.00
59,940.00
859,980.00

0%

859,980.00

NO.
1

INDEKS
2.000
Dibulatkan

HARGA

SATUAN

KEBUTUHAN

HARGA,
SATUAN
(Rp)

BAHAN
(Rp)

UPAH (Rp)

JUMLAH HARGA
(Rp)
8
859,980.00

NO.
1
14

INDEKS

HARGA

SATUAN

KEBUTUHAN

HARGA,
SATUAN
(Rp)

BAHAN
(Rp)

UPAH (Rp)

JUMLAH HARGA
(Rp)

2.000

1 m Bongkaran dinding tembok bata merah


6.667 Oh

Pekerja tak terlatih

60,000.00

###

0.333 Oh

Mandor

90,000.00

29,970.00

Jumlah
0%

Jumlah

429,990.00

1 m Bongkaran lantai
2.000 Oh

Pekerja tak terlatih

60,000.00

###

0.100 Oh

Mandor

90,000.00

9,000.00

Jumlah
0%

Jumlah

240,900.00

0.200 Oh

Pekerja tak terlatih

60,000.00

0.100 Oh

Mandor

90,000.00

12,000.00
9,000.00

2,400.00
900.00
3,300.00

Keuntungan Maksimal

0%

Jumlah

3,300.00

Dibulatkan

3,300.00

1 m Menurunkan atap seng


0.200 Oh

Pekerja tak terlatih

60,000.00

0.100 Oh

Mandor

90,000.00

12,000.00
9,000.00

Jumlah

2,400.00
900.00
3,300.00

Keuntungan Maksimal

0%

Jumlah

3,300.00

Dibulatkan

3,300.00

1 m Membongkar rangka atap


0.250 Oh

Tukang kayu

70,000.00

17,500.00

4,375.00

0.025 Oh

Kepala tukang

80,000.00

1.000 Oh

Pekerja tak terlatih

60,000.00

2,000.00
60,000.00

60,000.00

0.050 Oh

Mandor

90,000.00

4,500.00

Jumlah

50.00
225.00
64,650.00

Keuntungan Maksimal

0%

Jumlah

64,650.00

Dibulatkan

64,650.00

1 m Membongkar rangka kuda-kuda kayu


6.000 Oh

Tukang kayu

70,000.00

###

2,520,000.00

0.600 Oh

Kepala tukang

80,000.00

4.000 Oh

Pekerja tak terlatih

60,000.00

48,000.00
###

960,000.00

0.200 Oh

Mandor

90,000.00

18,000.00

Jumlah

28,800.00
3,600.00
3,512,400.00

Keuntungan Maksimal

0%

Jumlah

3,512,400.00

Dibulatkan
20

1 m Menurunkan atap genteng/sirap

Jumlah

19

900.00

240,900.00

Dibulatkan

18

240,000.00
240,900.00

Keuntungan Maksimal

17

429,990.00

Dibulatkan

16

29,970.00
429,990.00

Keuntungan Maksimal

15

400,020.00

3,512,400.00

1 m Membongkar langit-langit + rangka


0.250 Oh

Tukang kayu

70,000.00

0.025 Oh

Kepala tukang

80,000.00

2.000 Oh

Pekerja tak terlatih

60,000.00

17,500.00
2,000.00
###

0.050 Oh

Mandor

90,000.00

4,500.00

Jumlah
Keuntungan Maksimal
Jumlah

4,375.00
50.00
240,000.00
225.00
244,650.00

0%

244,650.00

NO.
1

INDEKS
2.000
Dibulatkan

HARGA

SATUAN

KEBUTUHAN

HARGA,
SATUAN
(Rp)

BAHAN
(Rp)

UPAH (Rp)

JUMLAH HARGA
(Rp)
8
244,650.00

HARGA

NO.

INDEKS

SATUAN

KEBUTUHAN

HARGA,
SATUAN
(Rp)

BAHAN
(Rp)

PEKERJAAN TANAH
1

Menggali 1 m3 tanah biasa sedalam 1 meter


0.750

OH

Pekerja

60,000.00

0.025

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
2

Menggali 1 m3 tanah biasa sedalam 2 meter


0.900

OH

Pekerja

60,000.00

0.045

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
3

Menggali 1 m3 tanah biasa sedalam 3 meter


1.050

OH

Pekerja

60,000.00

0.067

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
4

Menggali 1 m3 tanah keras sedalam 1 meter


1.000

OH

Pekerja

60,000.00

0.032

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
5

Menggali 1 m3 tanah cadas sedalam 1 meter


1.500

OH

Pekerja

60,000.00

0.060

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
6

Menggali 1 m3 tanah lumpur sedalam 1 meter


1.200

OH

Pekerja

60,000.00

0.045

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
7

Mengerjakan 1 m2 stripping tebing setinggi 1 meter

0%

0.050

OH

Pekerja

60,000.00

0.005

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
8

Membuang 1 m3 tanah sejauh 30 meter


0.330

OH

Pekerja

60,000.00

0.010

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
9

Mengurug kembali 1 m3 galian tanah biasa sedalam 1 meter


0.500

OH

Pekerja

60,000.00

0.050

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
10

Mengurug kembali 1 m3 galian tanah biasa sedalam 2 meter


0.300

OH

Pekerja

60,000.00

0.015

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
11

Mengurug kembali 1 m3 galian tanah biasa sedalam 3 meter


0.350

OH

Pekerja

60,000.00

0.022

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
12

Mengurug kembali 1 m3 galian tanah keras sedalam 1 meter


0.333

OH

Pekerja

60,000.00

0.011

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
13

Mengurug kembali 1 m3 galian tanah cadas sedalam 1 meter


0.500

OH

Pekerja

60,000.00

0.020

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

0%

14

Mengurug kembali 1 m3 galian tanah lumpur sedalam 1 meter


0.400

OH

Pekerja

60,000.00

0.015

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
15

Memadatkan 1 m3 tanah (per 20 cm)


0.500

OH

Pekerja

60,000.00

0.050

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
16

Mengurug 1 m3 pasir urug


1.200

m3

Pasir urug

120,000.00 144,000.00

0.300

OH

Pekerja

60,000.00

0.010

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
17

Memasang 1 m3 Lapisan pudel campuran 1 KP : 3 PP : 7 TL untuk stabilisasi tanah.


0.135

m3

Kapur padam

0.400

Pasir pasang

0.948

m3

Tanah liat

0.800

OH

Pekerja

60,000.00

0.400

OH

Tukang batu

70,000.00

0.040

OH

Kepala tukang

80,000.00

0.080

OH

Mandor

90,000.00

90,000.00

12,150.00

195,000.00

78,000.00

80,000.00

75,840.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
18

Memasang 1 m3 Lapisan pudel campuran 1 KP : 5 TL untuk stabilisasi tanah.


0.248

m3

Kapur padam

90,000.00

22,320.00

1.240

Tanah liat

80,000.00

99,200.00

0.800

OH

Pekerja

60,000.00

0.400

OH

Tukang batu

70,000.00

0.040

OH

Kepala tukang

80,000.00

0.080

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
19

Memasang 1 m2 lapisan ijuktebal 10 cm , untuk bidang resapan.


6.000

kg

Ijuk

10,000.00

0.150

OH

Pekerja

60,000.00

60,000.00

0.015

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
20

Mengurug 1 m3 sirtu padat untuk peninggian lantai bangunan


1.200

m3

Sirtu

158,000.00 189,600.00

0.250

OH

Pekerja

60,000.00

0.025

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

0%

HARGA
UPAH (Rp)

JUMLAH HARGA
(Rp)

45,000.00

45,000.00

2,250.00

2,250.00
47,250.00

0%

0.00
47,250.00
47,250.00

54,000.00

54,000.00

4,050.00

4,050.00
58,050.00

0%

0.00
58,050.00
58,050.00

63,000.00

63,000.00

6,030.00

6,030.00
69,030.00

0%

0.00
69,030.00
69,030.00

60,000.00
2,880.00

60,000.00
2,880.00
62,880.00

0%

0.00
62,880.00
62,880.00

90,000.00

90,000.00

5,400.00

5,400.00
95,400.00

0%

0.00
95,400.00
95,400.00

72,000.00

72,000.00

4,050.00

4,050.00
76,050.00

0%

0.00
76,050.00
76,050.00

3,000.00

3,000.00

450.00

450.00
3,450.00

0%

0.00
3,450.00
3,450.00

19,800.00
900.00

19,800.00
900.00
20,700.00

0%

0.00
20,700.00
20,700.00

30,000.00

30,000.00

4,500.00

4,500.00
34,500.00

0%

0.00
34,500.00
34,500.00

18,000.00

18,000.00

1,350.00

1,350.00
19,350.00

0%

0.00
19,350.00
19,350.00

21,000.00

21,000.00

2,010.00

2,010.00
23,010.00

0%

0.00
23,010.00
23,010.00

20,000.00
960.00

20,000.00
960.00
20,960.00

0%

0.00
20,960.00
20,960.00

30,000.00

30,000.00

1,800.00

1,800.00
31,800.00

0%

0.00
31,800.00
31,800.00

24,000.00

24,000.00

1,350.00

1,350.00
25,350.00

0%

0.00
25,350.00
25,350.00

30,000.00

30,000.00

4,500.00

4,500.00
34,500.00

0%

0.00
34,500.00
34,500.00
144,000.00

18,000.00

18,000.00

900.00

900.00
162,900.00

0%

0.00
162,900.00
162,900.00

sasi tanah.
12,150.00
78,000.00
75,840.00
48,000.00

48,000.00

28,000.00

28,000.00

3,200.00

3,200.00

7,200.00

7,200.00
252,390.00

0%

0.00
252,390.00
252,390.00
22,320.00
99,200.00

48,000.00

48,000.00

28,000.00

28,000.00

3,200.00

3,200.00

7,200.00

7,200.00
207,920.00

0%

0.00
207,920.00
207,920.00
60,000.00

9,000.00

9,000.00

1,350.00

1,350.00
70,350.00

0%

0.00
70,350.00
70,350.00
189,600.00

15,000.00
2,250.00

15,000.00
2,250.00
206,850.00

0%

0.00
206,850.00
206,850.00

HARGA

NO.

INDEKS

SATUAN

KEBUTUHAN

HARGA,
SATUAN
(Rp)

BAHAN (Rp)

PEKERJAAN PONDASI
1

Memasang 1 m3 pondasi batu belah, campuran 1 PC : 3 PP


1.200

M3

Batu belah 15 cm/20 cm

202.000

Kg

Portland Cement

0.485

Pasir Pasang

1.500

OH

Pekerja

60,000.00

0.750

OH

Tukang batu

70,000.00

0.075

OH

Kepala tukang

80,000.00

0.075

OH

Mandor

90,000.00

###
1,250.00
###

168,000.00
252,500.00
94,575.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
2

Memasang 1 m3 pondasi batu belah, campuran 1 PC : 4 PP


1.200

M3

Batu belah 15 cm/20 cm

163.000

Kg

Portland Cement

0.520

Pasir Pasang

1.500

OH

Pekerja

60,000.00

0.750

OH

Tukang batu

70,000.00

0.075

OH

Kepala tukang

80,000.00

0.075

OH

Mandor

90,000.00

###
1,250.00
###

168,000.00
203,750.00
101,400.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
3

Memasang 1 m3 pondasi batu belah, campuran 1 PC : 5 PP


1.200

M3

Batu belah 15 cm/20 cm

136.000

Kg

Portland Cement

0.544

Pasir Pasang

1.500

OH

Pekerja

60,000.00

0.750

OH

Tukang batu

70,000.00

0.075

OH

Kepala tukang

80,000.00

0.075

OH

Mandor

90,000.00

###
1,250.00
###

168,000.00
170,000.00
106,080.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
4

Memasang 1 m3 pondasi batu belah, campuran 1 PC : 6 PP


1.200

m3

Batu belah 15 cm/20 cm

117.000

kg

Portland Cement

Pasir Pasang

0.561

###
1,250.00
###

168,000.00
146,250.00
109,395.00

1.500

OH

Pekerja

60,000.00

0.750

OH

Tukang batu

70,000.00

0.075

OH

Kepala tukang

80,000.00

0.075

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
5

Memasang 1 m3 pondasi batu belah, campuran 1 PC : 8 PP


1.200

m3

Batu belah 15 cm/20 cm

91.000

kg

Portland Cement

0.584

Pasir Pasang

1.500

OH

Pekerja

60,000.00

0.750

OH

Tukang batu

70,000.00

0.075

OH

Kepala tukang

80,000.00

0.075

OH

Mandor

90,000.00

###
1,250.00
###

168,000.00
113,750.00
113,880.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
6

Memasang 1 m3 pondasi batu belah, campuran 1 KP : 1 SM : 2 PP


1.200

m3

Batu belah 15 cm/20 cm

0.170

###

Kapur

0.170

Portland Cement

0.340

Pasir Pasang

1.500

OH

Pekerja

60,000.00

0.750

OH

Tukang batu

70,000.00

0.075

OH

Kepala tukang

80,000.00

0.075

OH

Mandor

90,000.00

168,000.00

90,000.00

15,300.00

1,250.00

212.50

###

66,300.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
7

Memasang 1 m3 pondasi batu belah, campuran 1 PC : 3 KP : 10 PP


1.200

m3

Batu belah 15 cm/20 cm

61.000

kg

Portland Cement

0.147

Kapur padam

0.492

m3

Pasir Pasang

1.500

OH

Pekerja

60,000.00

0.750

OH

Tukang batu

70,000.00

0.075

OH

Kepala tukang

80,000.00

0.075

OH

Mandor

90,000.00

###

168,000.00

1,250.00

76,250.00

90,000.00

13,230.00

###

95,940.00

Jumlah
Keuntungan Maksimal
Jumlah

Dibulatkan
8

Memasang 1 m3 pondasi batu belah, campuran 1/4 PC : 1 KP : 4 PP


1.200

m3

Batu belah 15 cm/20 cm

41.000

kg

Portland Cement

0.131

Kapur padam

0.523

m3

Pasir Pasang

1.500

OH

Pekerja

60,000.00

0.750

OH

Tukang batu

70,000.00

0.075

OH

Kepala tukang

80,000.00

0.075

OH

Mandor

90,000.00

###
1,250.00
90,000.00
###

168,000.00
51,250.00
11,790.00
101,985.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
9

Memasang 1 m3 batu kosong (anstamping)


1.200

m3

Batu belah 15 cm/20 cm


Pasir urug

###

168,000.00

###

51,840.00

0.432

0.780

OH

Pekerja

60,000.00

0.390

OH

Tukang batu

70,000.00

0.039

OH

Kepala tukang

80,000.00

0.039

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
10

Memasang 1 m3 pondasi siklop, 60% beton campuran 1 PC : 2 PB : 3 KR dan 40% batu belah
0.480

m3

Batu belah 15 cm/20 cm

194.000

kg

Portland Cement

0.312

Pasir beton

###

63,960.00

0.468

m3

Kerikil

###

71,604.00

126.000

kg

Besi beton

1.800

kg

3.400
0.850

###
1,250.00

67,200.00
242,500.00

7,000.00

882,000.00

Kawat beton

25,000.00

45,000.00

OH

Pekerja

60,000.00

OH

Tukang batu

70,000.00

0.085

OH

Kepala tukang

80,000.00

0.170

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
11

Memasang 1 m3 pondasi sumuran, diameter 100 cm


0.450

m3

Batu belah 15 cm/20 cm

###

194.000

kg

Portland Cement

0.312

Pasir beton

###

63,960.00

0.468

Kerikil

###

71,604.00

1,250.00

63,000.00
242,500.00

2.400

OH

Pekerja

60,000.00

0.800

OH

Tukang batu

70,000.00

0.080

OH

Kepala tukang

80,000.00

0.119

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

HARGA
UPAH (Rp)

JUMLAH HARGA
(Rp)

168,000.00
252,500.00
94,575.00
90,000.00

90,000.00

52,500.00

52,500.00

6,000.00

6,000.00

6,750.00

6,750.00
670,325.00

670,325.00
670,320.00
168,000.00
203,750.00
101,400.00

90,000.00

90,000.00

52,500.00

52,500.00

6,000.00

6,000.00

6,750.00

6,750.00
628,400.00

628,400.00
628,400.00
168,000.00
170,000.00
106,080.00

90,000.00

90,000.00

52,500.00

52,500.00

6,000.00

6,000.00

6,750.00

6,750.00
599,330.00

599,330.00
599,330.00
168,000.00
146,250.00
109,395.00

3.26

90,000.00

90,000.00

52,500.00

52,500.00

6,000.00

6,000.00

6,750.00

6,750.00
578,895.00

578,895.00
578,890.00
168,000.00
113,750.00
113,880.00

90,000.00

90,000.00

52,500.00

52,500.00

6,000.00

6,000.00

6,750.00

6,750.00
550,880.00

550,880.00
550,880.00
168,000.00
15,300.00
212.50
66,300.00

90,000.00

90,000.00

52,500.00

52,500.00

6,000.00

6,000.00

6,750.00

6,750.00
405,062.50

405,062.50
405,060.00
168,000.00
76,250.00
13,230.00
95,940.00

90,000.00

90,000.00

52,500.00

52,500.00

6,000.00

6,000.00

6,750.00

6,750.00
508,670.00

508,670.00

508,670.00
168,000.00
51,250.00
11,790.00
101,985.00
90,000.00

90,000.00

52,500.00

52,500.00

6,000.00

6,000.00

6,750.00

6,750.00
488,275.00

488,275.00
488,270.00
168,000.00
51,840.00

46,800.00

46,800.00

27,300.00

27,300.00

3,120.00

3,120.00

3,510.00

3,510.00
300,570.00

300,570.00
300,570.00

n 40% batu belah


67,200.00
242,500.00
63,960.00
71,604.00
882,000.00
45,000.00
204,000.00

204,000.00

59,500.00

59,500.00

6,800.00

6,800.00

15,300.00

15,300.00
1,657,864.00

1,657,864.00
1,657,860.00
63,000.00
242,500.00
63,960.00
71,604.00

144,000.00

144,000.00

56,000.00

56,000.00

6,400.00

6,400.00

10,710.00

10,710.00
658,174.00

658,174.00
658,170.00

NO.

INDEKS

SATUAN

KEBUTUHAN

HARGA,
SATUAN (Rp)

PEKERJAAN BETON
1

Membuat 1 m3 beton mutu f'c = 7,4 MPa (K 100), slump (12 2) cm, w/c = 0,87
247.000

kg

Portland Cement

869.000

kg

Pasir Beton

146.43

999.000

kg

Kerikil (maksimum 30 mm)

126.90

215.000

Liter

Air

1,250.00

10.00

1.650

OH

Pekerja

60,000.00

0.275

OH

Tukang batu

70,000.00

0.028

OH

Kepala tukang

80,000.00

0.083

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
2

Membuat 1 m3 beton mutu f'c = 9,8 MPa (K 125), slump (12 2) cm, w/c = 0,78
276.000

kg

Portland Cement

828.000

kg

Pasir Beton

146.43

1,012.000

kg

Kerikil (maksimum 30 mm)

126.90

215.000

Liter

Air

1,250.00

10.00

1.650

OH

Pekerja

60,000.00

0.275

OH

Tukang batu

70,000.00

0.028

OH

Kepala tukang

80,000.00

0.083

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
3

Membuat 1 m3 beton mutu f'c = 12,2 MPa (K 150), slump (12 2) cm, w/c = 0,72
299.000

kg

Portland Cement

799.000

kg

Pasir Beton

146.43

1,017.000

kg

Kerikil (maksimum 30 mm)

126.90

215.000

Liter

Air

1,250.00

10.00

1.650

OH

Pekerja

60,000.00

0.275

OH

Tukang batu

70,000.00

0.028

OH

Kepala tukang

80,000.00

0.083

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
4

Membuat 1 m3 lantai kerja beton mutu f'c = 7,4 MPa (K 100), slump (3-6) cm,
230.000

kg

Portland Cement

1,250.00

893.000

kg

Pasir Beton

146.43

1,027.000

kg

Kerikil (maksimum 30 mm)

126.90

w/c = 0,87

200.000

Liter

Air

10.00

1.200

OH

Pekerja

60,000.00

0.200

OH

Tukang batu

70,000.00

0.020

OH

Kepala tukang

80,000.00

0.060

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
5

Membuat 1 m3 beton mutu f'c = 14,5 MPa (K 175), slump (12 2) cm, w/c = 0,66
326.000

kg

Portland Cement

760.000

kg

Pasir Beton

146.43

kg

Kerikil (maksimum 30 mm)

126.90

1,029.000
215.000

Liter

Air

1,250.00

10.00

1.650

OH

Pekerja

60,000.00

0.275

OH

Tukang batu

70,000.00

0.028

OH

Kepala tukang

80,000.00

0.083

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
6

Membuat 1 m3 beton mutu f'c = 16,9 MPa (K 200), slump (12 2) cm, w/c = 0,61
352.000

kg

Portland Cement

731.000

kg

Pasir Beton

146.43

1,031.000

kg

Kerikil (maksimum 30 mm)

126.90

215.000

Liter

Air

1,250.00

10.00

1.650

OH

Pekerja

60,000.00

0.275

OH

Tukang batu

70,000.00

0.028

OH

Kepala tukang

80,000.00

0.083

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
7

Membuat 1 m3 beton mutu f'c = 19,3 MPa (K 225), slump (12 2) cm, w/c = 0,58
371.000

kg

Portland Cement

698.000

kg

Pasir Beton

146.43

1,047.000

kg

Kerikil (maksimum 30 mm)

126.90

215.000

Liter

Air

1,250.00

10.00

1.650

OH

Pekerja

60,000.00

0.275

OH

Tukang batu

70,000.00

0.028

OH

Kepala tukang

80,000.00

0.083

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

Membuat 1 m3 beton mutu f'c = 21,7 MPa (K 250), slump (12 2) cm, w/c = 0,56
384.000

kg

Portland Cement

692.000

kg

Pasir Beton

146.43

1,039.000

kg

Kerikil (maksimum 30 mm)

126.90

215.000

Liter

Air

1,250.00

10.00

1.650

OH

Pekerja

60,000.00

0.275

OH

Tukang batu

70,000.00

0.028

OH

Kepala tukang

80,000.00

0.083

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
9

Membuat 1 m3 beton mutu f'c = 24,0 MPa (K 275), slump (12 2) cm, w/c = 0,53
406.000

kg

Portland Cement

684.000

kg

Pasir Beton

146.43

kg

Kerikil (maksimum 30 mm)

126.90

1,026.000
215.000

Liter

Air

1,250.00

10.00

1.650

OH

Pekerja

60,000.00

0.275

OH

Tukang batu

70,000.00

0.028

OH

Kepala tukang

80,000.00

0.083

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
10

Membuat 1 m3 beton mutu f'c = 26,4 MPa (K 300), slump (12 2) cm, w/c = 0,52
413.000

kg

Portland Cement

681.000

Pasir Beton

146.43

Kerikil (maksimum 30 mm)

126.90

1,021.000
215.000

m3
Liter

Air

1,250.00

10.00

1.650

OH

Pekerja

60,000.00

0.275

OH

Tukang batu

70,000.00

0.028

OH

Kepala tukang

80,000.00

0.083

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
11

Membuat 1 m3 beton mutu f'c = 28,8 MPa (K 325), slump (12 2) cm, w/c = 0,49
439.000

kg

Portland Cement

670.000

kg

Pasir Beton

146.43

1,006.000

kg

Kerikil (maksimum 30 mm)

126.90

215.000

Liter

Air

1,250.00

10.00

2.100

OH

Pekerja

60,000.00

0.350

OH

Tukang batu

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.105

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
12

Membuat 1 m3 beton mutu f'c = 31,2 MPa (K 350), slump (12 2) cm, w/c = 0,48
448.000

kg

Portland Cement

667.000

kg

Pasir Beton

146.43

1,000.000

kg

Kerikil (maksimum 30 mm)

126.90

215.000

Liter

Air

1,250.00

10.00

2.100

OH

Pekerja

60,000.00

0.350

OH

Tukang batu

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.105

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
13

Membuat 1 m3 beton kedap air dengan strorox - 100


400.000

kg

Portland Cement

0.480

Pasir Beton

146.43

0.800

m/

KR (Kerikil 2cm/3cm)

126.90

1.200

kg

Strorox-100

210.000

3
3

Liter

Air

1,250.00

10.00

2.100

OH

Pekerja

60,000.00

0.350

OH

Tukang batu

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.105

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
14

Memasang 1 m PVC Waterstop lebar 150 mm


1.050

Waterstop lebar 150 mm

64,000.00

0.060

OH

Pekerja

60,000.00

0.030

OH

Tukang batu

70,000.00

0.003

OH

Kepala tukang

80,000.00

0.003

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
15

Memasang 1 m PVC Waterstop lebar 200 mm


1.050

Waterstop lebar 200 mm

80,000.00

0.070

OH

Pekerja

60,000.00

0.035

OH

Tukang batu

70,000.00

0.004

OH

Kepala tukang

80,000.00

0.004

OH

Mandor

90,000.00

Jumlah

Keuntungan Maksimal
Jumlah
Dibulatkan
16

Membuat 1 m PVC Waterstop lebar 230 mm - 320 mm


1.050

Waterstop lebar 230 mm - 320 mm

0.080

OH

Pekerja

n.a
60,000.00

0.040

OH

Tukang batu

70,000.00

0.004

OH

Kepala tukang

80,000.00

0.004

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
17

Pembesian 10 kg dengan besi polos atau besi ulir


10.500

kg

Besi beton (polos/ulir)

7,000.00

0.150

kg

Kawat beton

25,000.00

0.070

OH

Pekerja

60,000.00

0.070

OH

Tukang besi

70,000.00

0.007

OH

Kepala tukang

80,000.00

0.004

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
18

Memasang 10 kg kabel presstressed polos/strands


10.500

kg

Besi beton (polos/ulir)

7,000.00

0.100

kg

Kawat beton

25,000.00

0.050

OH

Pekerja

60,000.00

0.050

OH

Tukang besi

70,000.00

0.005

OH

Kepala tukang

80,000.00

0.003

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
19

Memasang 10 Kg jaring kawat baja/wire mesh


10.200

kg

Jaring kawat baja dilas

0.050

kg

Kawat beton

25,000.00

8,300.00

0.025

OH

Pekerja

60,000.00

0.025

OH

Tukang besi

70,000.00

0.025

OH

Kepala tukang

80,000.00

0.001

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
20

Memasang 1 m2 bekisting untuk pondasi


0.040

m3

Kayu kelas III

650,000.00

0.300

kg

0.100

Liter

Paku 5 cm - 10 cm

0.520

OH

Pekerja

60,000.00

0.260

OH

Tukang kayu

70,000.00

0.026

OH

Kepala tukang

80,000.00

0.026

OH

Mandor

90,000.00

Minyak bekisting

17,000.00
8,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
21

Memasang 1 m2 bekisting untuk sloof


0.045

m3

Kayu kelas III

0.300

kg

Paku 5 cm - 10 cm

0.100

Liter

0.520

OH

Pekerja

60,000.00

0.260

OH

Tukang kayu

70,000.00

0.026

OH

Kepala tukang

80,000.00

0.026

OH

Mandor

90,000.00

Minyak bekisting

650,000.00
17,000.00
8,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
22

Memasang 1 m2 bekisting untuk kolom


0.040

m3

Kayu kelas III

0.400

kg

Paku 5 cm-12 cm

17,000.00

0.200

Liter

Minyak bekisting

8,000.00

0.015

0.350

Lbr

2.000

Batang

Dolken kayu galam, <j) (8-10) cm, pjg 4 m

22,000.00

0.660

OH

Pekerja

60,000.00

0.330

OH

Tukang kayu

70,000.00

0.033

OH

Kepala tukang

80,000.00

0.033

OH

Mandor

90,000.00

Balok kayu kelas II


Multipleks tebal 9 mm

650,000.00

1,500,000.00
125,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
23

Memasang 1 m2 bekisting untuk balok


0.040 m3

Kayu kelas III

0.400

kg

Paku 5 cm-12 cm

0.200

Liter

Minyak bekisting

0.018

m3

Balok kayu kelas II

0.350

Lbr

Multipleks tebal 9 mm

2.000

Batang

0.660
0.330

650,000.00
17,000.00
8,000.00
1,500,000.00
125,000.00

Dolken kayu galam, <f> (8-10) cm, pjg 4 m

22,000.00

OH

Pekerja

60,000.00

OH

Tukang kayu

70,000.00

0.033

OH

Kepala tukang

80,000.00

0.033

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
24

Memasang 1 m2 bekisting untuk plat lantai


0.040

m3

Kayu kelas III

0.400

kg

Paku 5 cm-12 cm

17,000.00

0.200

Liter

Minyak bekisting

8,000.00

0.015

0.350

Lbr

6.000

Batang

0.660

OH

Multipleks tebal 9 mm
Dolken kayu galam, (8-10) cm, panjang 4
m
Pekerja

0.330

OH

Tukang kayu

70,000.00

0.033

OH

Kepala tukang

80,000.00

0.033

OH

Mandor

90,000.00

Balok kayu kelas II

650,000.00

1,500,000.00
125,000.00
22,000.00
60,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
25

Memasang 1 m2 bekisting untuk dinding


0.030

m3

Kayu kelas III

0.400

kg

Paku 5 cm -12 cm

0.200

Liter

Minyak bekisting

0.020

Balok kayu kelas II


Multipleks tebal 9 mm
Dolken kayu galam, (8-10) cm, panjang 4
m
Formite /penjaga jarak bekisting/ spacer

650,000.00
17,000.00
8,000.00
1,500,000.00

0.350

Lbr

3.000

Batang

125,000.00

4.000

Buah

0.660

OH

Pekerja

60,000.00

0.330

OH

Tukang kayu

70,000.00

0.033

OH

Kepala tukang

80,000.00

0.033

OH

Mandor

90,000.00

22,000.00
n.a

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
26

Memasang 1 m2 bekisting untuk tangga


0.030

m3

Kayu kelas III

0.400

kg

Paku 5 cm-12 cm

17,000.00

0.150

Liter

Minyak bekisting

8,000.00

0.015

Balok kayu kelas II

650,000.00

1,500,000.00

0.350

Lbr

2.000

Batang

0.660

OH

Plywood tebal 9 mm
Dolken kayu galam, (8-10) cm, panjang 4
m
Pekerja

0.330

OH

Tukang kayu

70,000.00

0.033

OH

Kepala tukang

80,000.00

0.033

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

125,000.00
22,000.00
60,000.00

Jumlah
Dibulatkan
27

Memasang 1 m2 jembatan untuk pengecoran beton


0.026

m3

Kayu kelas III (papan)

650,000.00

0.600

kg
Batang

0.150

OH

Paku 5 cm-12 cm
Dolken kayu galam (kaso), (8-10) cm, p 4
m
Pekerja

17,000.00

0.500
0.050

OH

Tukang kayu

70,000.00

0.005

OH

Kepala tukang

80,000.00

0.008

OH

Mandor

90,000.00

22,000.00
60,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
28

Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting)


0.200

m3

Kayu kelas III

650,000.00

1.500

kg

Paku 5 cm-12 cm

17,000.00

0.400

Liter

Minyak bekisting

8,000.00

157.500

kg

Besi beton polos

7,000.00

2.250

kg

Kawat beton

336.000

kg

Portland Cement

0.540

m3

Pasir Beton

205,000.00

0.810

m3

Kerikil 2/3

184,000.00

5.300

OH

Pekerja

60,000.00

0.275

OH

Tukang batu

70,000.00

1.300

OH

Tukang kayu

70,000.00

1.050

OH

Tukang besi

70,000.00

0.262

OH

Kepala tukang

80,000.00

0.265

OH

Mandor

90,000.00

25,000.00
1,250.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
29

Membuat 1 m3 sloof beton bertulang (200 kg besi + bekisting)


0.270

m3

Kayu kelas III

650,000.00

2.000

kg

Paku 5 cm-12cm

17,000.00

0.600

Liter

Minyak bekisting

8,000.00

210.000

kg

Besi beton polos

7,000.00

3.000

kg

Kawat beton

336.000

kg

Portland Cement

0.540

Pasir Beton

205,000.00

0.810

m3

Kerikil 2/3

184,000.00

5.650

OH

Pekerja

60,000.00

0.275

OH

Tukang batu

70,000.00

1.560

OH

Tukang kayu

70,000.00

1.400

OH

Tukang besi

70,000.00

0.323

OH

Kepala tukang

80,000.00

0.283

OH

Mandor

90,000.00

25,000.00
1,250.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
30

Membuat 1 m3 kolom beton bertulang (300 kg besi + bekisting)


0.400

m3

Kayu kelas III

4.000

kg

Paku 5 cm - 12 cm

2.000

Liter

Minyak bekisting

315.000

kg

Besi beton polos

4.500

kg

Kawat beton

336.000

kg

Portland Cement

0.540

Pasir Beton

0.810

Kerikil 2/3

0.150

m3

3.500

Lembar

20.000

Batang

Kayu kelas II balok

650,000.00
17,000.00
8,000.00
7,000.00
25,000.00
1,250.00
205,000.00
184,000.00
1,500,000.00

7.050

OH

Multipleks 9 mm
Dolken kayu galam, (8-10) cm, panjang 4
m
Pekerja

125,000.00

0.275

OH

Tukang batu

70,000.00

1.650

OH

Tukang kayu

70,000.00

2.100

OH

Tukang besi

70,000.00

0.403

OH

Kepala tukang

80,000.00

0.353

OH

Mandor

90,000.00

22,000.00
60,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
31

Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting)


0.320

m3

Kayu kelas III

3.200

kg

Paku 5 cm-12 cm

17,000.00

1.600

Liter

Minyak bekisting

8,000.00

210.000

kg

Besi beton polos

7,000.00

3.000

kg

Kawat beton

336.000

kg

Portland Cement

0.540

m3

Pasir Beton

205,000.00

0.810

m3

Kerikil 2/3

184,000.00

0.140

Kayu kelas II balok

2.800

Lembar

16.000

Batang

650,000.00

25,000.00
1,250.00

1,500,000.00

6.350

OH

Multipleks 9 mm
Dolken kayu galam, (8-10) cm, panjang 4
m
Pekerja

0.275

OH

Tukang batu

70,000.00

1.650

OH

Tukang kayu

70,000.00

1.400

OH

Tukang besi

70,000.00

0.333

OH

Kepala tukang

80,000.00

0.318

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

125,000.00
22,000.00
60,000.00

32

Membuat 1 m3 plat beton bertulang (150 kg besi + bekisting)


0.320

m3

Kayu kelas III

3.200

kg

Paku 5 cm-12 cm

17,000.00

1.600

Liter

Minyak bekisting

8,000.00

157.500

kg

Besi beton polos

2.250

kg

Kawat beton

336.000

kg

Portland Cement

0.540

Pasir Beton

0.810

Kerikil 2/3

0.120

m3

2.800

Lembar

32.000

Batang

Kayu kelas II balok

650,000.00

7,000.00
25,000.00
1,250.00
205,000.00
184,000.00
1,500,000.00

5.300

OH

Plywood 9 mm
Dolken kayu galam, (8-10) cm, panjang 4
m
Pekerja

125,000.00

0.275

OH

Tukang batu

70,000.00

1.300

OH

Tukang kayu

70,000.00

1.050

OH

Tukang besi

70,000.00

0.265

OH

Kepala tukang

80,000.00

0.265

OH

Mandor

90,000.00

22,000.00
60,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
33

Membuat 1 m3dinding beton bertulang (150 kg besi + bekisting)


0.240

m3

Kayu kelas III

3.200

kg

Paku 5 cm-12 cm

17,000.00

1.600

Liter

Minyak bekisting

8,000.00

157.500

kg

Besi beton polos

7,000.00

2.250

kg

Kawat beton

336.000

kg

Portland Cement

0.540

m3

Pasir Beton

205,000.00

0.810

m3

Kerikil 2/3

184,000.00

0.160

Kayu kelas II balok

2.800

Lembar

24.000

Batang

650,000.00

25,000.00
1,250.00

1,500,000.00

5.300

OH

Plywood 9 mm
Dolken kayu galam, (8-10) cm, panjang 4
m
Pekerja

125,000.00

0.275

OH

Tukang batu

70,000.00

1.300

OH

Tukang kayu

70,000.00

1.050

OH

Tukang besi

70,000.00

0.262

OH

Kepala tukang

80,000.00

0.265

OH

Mandor

90,000.00

22,000.00
60,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
34

Membuat 1 m3dinding beton bertulang (200 kg besi + bekisting)


0.250

m3

Kayu kelas III

3.000

kg

Paku 5 cm - 12 cm

1.200

Liter

Minyak bekisting

650,000.00
17,000.00
8,000.00

210.000

kg

Besi beton polos

3.000

kg

Kawat beton

336.000

kg

Portland Cement

0.540

Pasir Beton

0.810

Kerikil 2/3

0.105

m3

2.500

Lembar

14.000

Batang

Kayu kelas II balok

7,000.00
25,000.00
1,250.00
205,000.00
184,000.00
1,500,000.00

5.650

OH

Plywood 9 mm
Dolken kayu galam, (8-10) cm, panjang 4
m
Pekerja

0.275

OH

Tukang batu

70,000.00

1.560

OH

Tukang kayu

70,000.00

1.400

OH

Tukang besi

70,000.00

Kepala tukang

80,000.00

Mandor

90,000.00

0.323 OH
0.283

OH

125,000.00
22,000.00
60,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
35

Membuat 1 m kolom praktis beton bertulang (11 x 11) cm


0.002

m3

Kayu kelas III

0.010

kg

Paku 5 cm-12 cm

3.000

kg

Besi beton polos

0.045

kg

Kawat beton

4.000

kg

Portland Cement

0.006

Pasir Beton

205,000.00

0.009

m3

Kerikil 2/3

184,000.00

0.180

OH

Pekerja

60,000.00

0.020

OH

Tukang batu

70,000.00

0.020

OH

Tukang kayu

70,000.00

0.020

OH

Tukang besi

70,000.00

0.006

OH

Kepala tukang

80,000.00

0.009

OH

Mandor

90,000.00

650,000.00
17,000.00
7,000.00
25,000.00
1,250.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
36

Membuat 1 m ring balok beton bertulang (10 x 15) cm


0.003

m3

Kayu kelas III

650,000.00

0.020

kg

Paku 5 cm-12 cm

3.600

kg

Besi beton polos

0.050

kg

Kawat beton

5.500

kg

Portland Cement

0.009

Pasir Beton

205,000.00

0.015

Kerikil 2/3

184,000.00

0.297

OH

Pekerja

60,000.00

0.033

OH

Tukang batu

70,000.00

0.033

OH

Tukang kayu

70,000.00

0.033

OH

Tukang besi

70,000.00

17,000.00
7,000.00
25,000.00
1,250.00

0.010

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

HARGA
BAHAN (Rp)

UPAH (Rp)

JUMLAH HARGA
(Rp)

cm, w/c = 0,87


308,750.00

308,750.00

127,246.43

127,246.43

126,769.66

126,769.66

2,150.00

2,150.00
99,000.00

99,000.00

19,250.00

19,250.00

2,240.00

2,240.00

7,470.00

7,470.00
692,876.08

692,876.08
692,870.00

cm, w/c = 0,78


345,000.00

345,000.00

121,242.86

121,242.86

128,419.31

128,419.31

2,150.00

2,150.00
99,000.00

99,000.00

19,250.00

19,250.00

2,240.00

2,240.00

7,470.00

7,470.00
724,772.17

724,772.17
724,770.00

) cm, w/c = 0,72

mp (3-6) cm,

373,750.00

373,750.00

116,996.43

116,996.43

129,053.79

129,053.79

2,150.00

2,150.00
99,000.00

99,000.00

19,250.00

19,250.00

2,240.00

2,240.00

7,470.00

7,470.00
749,910.22

749,910.22
749,910.00

w/c = 0,87
287,500.00

287,500.00

130,760.71

130,760.71

130,322.76

130,322.76

2,000.00

2,000.00
72,000.00

72,000.00

14,000.00

14,000.00

1,600.00

1,600.00

5,400.00

5,400.00
643,583.47

643,583.47
643,580.00

) cm, w/c = 0,66


407,500.00

407,500.00

111,285.71

111,285.71

130,576.55

130,576.55

2,150.00

2,150.00
99,000.00

99,000.00

19,250.00

19,250.00

2,240.00

2,240.00

7,470.00

7,470.00
779,472.27

779,472.27
779,470.00

) cm, w/c = 0,61


440,000.00

440,000.00

107,039.29

107,039.29

130,830.34

130,830.34

2,150.00

2,150.00
99,000.00

99,000.00

19,250.00

19,250.00

2,240.00

2,240.00

7,470.00

7,470.00
807,979.63

807,979.63
807,970.00

) cm, w/c = 0,58


463,750.00

463,750.00

102,207.14

102,207.14

132,860.69

132,860.69

2,150.00

2,150.00
99,000.00

99,000.00

19,250.00

19,250.00

2,240.00

2,240.00

7,470.00

7,470.00
828,927.83

828,927.83
828,920.00

) cm, w/c = 0,56


480,000.00

480,000.00

101,328.57

101,328.57

131,845.52

131,845.52

2,150.00

2,150.00
99,000.00

99,000.00

19,250.00

19,250.00

2,240.00

2,240.00

7,470.00

7,470.00
843,284.09

843,284.09
843,280.00

) cm, w/c = 0,53


507,500.00

507,500.00

100,157.14

100,157.14

130,195.86

130,195.86

2,150.00

2,150.00

99,000.00

99,000.00

198,000.00

19,250.00

19,250.00

38,500.00

2,240.00

2,240.00

4,480.00

7,470.00

7,470.00

14,940.00
995,923.00

995,923.00
995,920.00

) cm, w/c = 0,52


516,250.00

516,250.00

99,717.86

99,717.86

129,561.38

129,561.38

2,150.00

2,150.00
99,000.00

99,000.00

19,250.00

19,250.00

2,240.00

2,240.00

7,470.00

7,470.00
875,639.24

875,639.24
875,630.00

) cm, w/c = 0,49


548,750.00

548,750.00

98,107.14

98,107.14

127,657.93

127,657.93

2,150.00

2,150.00

126,000.00

126,000.00

252,000.00

24,500.00

24,500.00

49,000.00

2,800.00

2,800.00

5,600.00

9,450.00

9,450.00

18,900.00

1,102,165.07
-

1,102,165.07
1,102,160.00

) cm, w/c = 0,48


560,000.00

560,000.00

97,667.86

97,667.86

126,896.55

126,896.55

2,150.00

2,150.00
126,000.00

126,000.00

24,500.00

24,500.00

2,800.00

2,800.00

9,450.00

9,450.00
949,464.41

949,464.41
949,460.00

500,000.00

500,000.00

70.29

70.29

101.52

101.52

2,100.00

2,100.00
126,000.00

126,000.00

24,500.00

24,500.00

2,800.00

2,800.00

9,450.00

9,450.00
665,021.80

665,021.80
665,020.00

67,200.00

67,200.00
3,600.00

3,600.00

2,100.00

2,100.00

240.00

240.00

270.00

270.00
73,410.00

73,410.00
73,410.00

84,000.00

84,000.00
4,200.00

4,200.00

2,450.00

2,450.00

320.00

320.00

360.00

360.00
91,330.00

91,330.00
91,330.00

#VALUE!

#VALUE!
4,800.00

4,800.00

2,800.00

2,800.00

320.00

320.00

360.00

360.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!

73,500.00

73,500.00

3,750.00

3,750.00
4,200.00

4,200.00

4,900.00

4,900.00

560.00

560.00

360.00

360.00
87,270.00

87,270.00
87,270.00

73,500.00

73,500.00

2,500.00

2,500.00
3,000.00

3,000.00

3,500.00

3,500.00

400.00

400.00

270.00

270.00
83,170.00

83,170.00
83,170.00

84,660.00

84,660.00

1,250.00

1,250.00
1,500.00

1,500.00

1,750.00

1,750.00

2,000.00

2,000.00

90.00

90.00
91,250.00

91,250.00
91,250.00

26,000.00

26,000.00

5,100.00

5,100.00

800.00

800.00
31,200.00

31,200.00

18,200.00

18,200.00

2,080.00

2,080.00

2,340.00

2,340.00
85,720.00

85,720.00
85,720.00

29,250.00

29,250.00

5,100.00

5,100.00

800.00

800.00
31,200.00

31,200.00

18,200.00

18,200.00

2,080.00

2,080.00

2,340.00

2,340.00
88,970.00

88,970.00
88,970.00

26,000.00

26,000.00

6,800.00

6,800.00

1,600.00

1,600.00

22,500.00

22,500.00

43,750.00

43,750.00

44,000.00

44,000.00
39,600.00

39,600.00

23,100.00

23,100.00

2,640.00

2,640.00

2,970.00

2,970.00
212,960.00

212,960.00
212,960.00

26,000.00

26,000.00

6,800.00

6,800.00

1,600.00

1,600.00

27,000.00

27,000.00

43,750.00

43,750.00

44,000.00

44,000.00
39,600.00

39,600.00

23,100.00

23,100.00

2,640.00

2,640.00

2,970.00

2,970.00

217,460.00
-

217,460.00
217,460.00

26,000.00

26,000.00

6,800.00

6,800.00

1,600.00

1,600.00

22,500.00

22,500.00

43,750.00

43,750.00

132,000.00

132,000.00
39,600.00

39,600.00

23,100.00

23,100.00

2,640.00

2,640.00

2,970.00

2,970.00
300,960.00

300,960.00
300,960.00

19,500.00

19,500.00

6,800.00

6,800.00

1,600.00

1,600.00

30,000.00

30,000.00

43,750.00

43,750.00

66,000.00

66,000.00

#VALUE!

#VALUE!
39,600.00

39,600.00

23,100.00

23,100.00

2,640.00

2,640.00

2,970.00

2,970.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!

19,500.00

19,500.00

6,800.00

6,800.00

1,200.00

1,200.00

22,500.00

22,500.00

43,750.00

43,750.00

44,000.00

44,000.00
39,600.00

39,600.00

23,100.00

23,100.00

2,640.00

2,640.00

2,970.00

2,970.00
206,060.00

206,060.00
206,060.00
17,160.00

17,160.00

10,200.00

10,200.00

11,000.00

11,000.00
9,000.00

9,000.00

3,500.00

3,500.00

400.00

400.00

720.00

720.00
51,980.00

51,980.00
51,980.00

130,000.00

130,000.00

25,500.00

25,500.00

3,200.00

3,200.00

1,102,500.00

1,102,500.00

56,250.00

56,250.00

420,000.00

420,000.00

110,700.00

110,700.00

149,040.00

149,040.00
318,000.00

318,000.00

19,250.00

19,250.00

91,000.00

91,000.00

73,500.00

73,500.00

20,960.00

20,960.00

23,850.00

23,850.00
2,543,750.00

2,543,750.00
2,543,750.00

175,500.00

175,500.00

34,000.00

34,000.00

4,800.00

4,800.00

1,470,000.00

1,470,000.00

75,000.00

75,000.00

420,000.00

420,000.00

110,700.00

110,700.00

149,040.00

149,040.00
339,000.00

339,000.00

19,250.00

19,250.00

109,200.00

109,200.00

98,000.00

98,000.00

25,840.00

25,840.00

25,470.00

25,470.00

3,055,800.00
-

3,055,800.00
3,055,800.00

260,000.00

260,000.00

68,000.00

68,000.00

16,000.00

16,000.00

2,205,000.00

2,205,000.00

112,500.00

112,500.00

420,000.00

420,000.00

110,700.00

110,700.00

149,040.00

149,040.00

225,000.00

225,000.00

437,500.00

437,500.00

440,000.00

440,000.00
423,000.00

423,000.00

19,250.00

19,250.00

115,500.00

115,500.00

147,000.00

147,000.00

32,240.00

32,240.00

31,770.00

31,770.00
5,212,500.00

5,212,500.00
5,212,500.00

208,000.00

208,000.00

54,400.00

54,400.00

12,800.00

12,800.00

1,470,000.00

1,470,000.00

75,000.00

75,000.00

420,000.00

420,000.00

110,700.00

110,700.00

149,040.00

149,040.00

210,000.00

210,000.00

350,000.00

350,000.00

352,000.00

352,000.00
381,000.00

381,000.00

19,250.00

19,250.00

115,500.00

115,500.00

98,000.00

98,000.00

26,640.00

26,640.00

28,620.00

28,620.00
4,080,950.00

4,080,950.00
4,080,950.00

208,000.00

208,000.00

54,400.00

54,400.00

12,800.00

12,800.00

1,102,500.00

1,102,500.00

56,250.00

56,250.00

420,000.00

420,000.00

110,700.00

110,700.00

149,040.00

149,040.00

180,000.00

180,000.00

350,000.00

350,000.00

704,000.00

704,000.00
318,000.00

318,000.00

19,250.00

19,250.00

91,000.00

91,000.00

73,500.00

73,500.00

21,200.00

21,200.00

23,850.00

23,850.00
3,894,490.00

3,894,490.00
3,894,490.00

156,000.00

156,000.00

54,400.00

54,400.00

12,800.00

12,800.00

1,102,500.00

1,102,500.00

56,250.00

56,250.00

420,000.00

420,000.00

110,700.00

110,700.00

149,040.00

149,040.00

240,000.00

240,000.00

350,000.00

350,000.00

528,000.00

528,000.00
318,000.00

318,000.00

19,250.00

19,250.00

91,000.00

91,000.00

73,500.00

73,500.00

20,960.00

20,960.00

23,850.00

23,850.00
3,726,250.00

3,726,250.00
3,726,250.00

162,500.00

162,500.00

51,000.00

51,000.00

9,600.00

9,600.00

1,470,000.00

1,470,000.00

75,000.00

75,000.00

420,000.00

420,000.00

110,700.00

110,700.00

149,040.00

149,040.00

157,500.00

157,500.00

312,500.00

312,500.00

308,000.00

308,000.00
339,000.00

339,000.00

19,250.00

19,250.00

109,200.00

109,200.00

98,000.00

98,000.00

25,840.00

25,840.00

25,470.00

25,470.00
3,842,600.00

3,842,600.00
3,842,600.00

1,300.00

1,300.00

170.00

170.00

21,000.00

21,000.00

1,125.00

1,125.00

5,000.00

5,000.00

1,230.00

1,230.00

1,656.00

1,656.00
10,800.00

10,800.00

1,400.00

1,400.00

1,400.00

1,400.00

1,400.00

1,400.00

480.00

480.00

810.00

810.00
47,771.00

47,771.00
47,770.00

1,950.00

1,950.00

340.00

340.00

25,200.00

25,200.00

1,250.00

1,250.00

6,875.00

6,875.00

1,845.00

1,845.00

2,760.00

2,760.00
17,820.00

17,820.00

2,310.00

2,310.00

2,310.00

2,310.00

2,310.00

2,310.00

800.00

800.00

1,350.00

1,350.00
67,120.00

67,120.00
67,120.00

HARGA

NO.

INDEKS

SATUAN

KEBUTUHAN

HARGA,
SATUAN
(Rp)

BAHAN (Rp)

PEKERJAAN BESI
1

Memasang 1 kg besi profil


1.150

Kg

Besi profil

10,000.00

0.060

OH

Pekerja

60,000.00

0.060

OH

Tukang las Konstruksi

70,000.00

0.006

OH

Kepala tukang

80,000.00

0.003

OH

Mandor

90,000.00

11,500.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
2

Memasang 1 kg rangka kuda-kuda baja IWF


1.150

Kg

Besi baja IWF

12,000.00

0.060

OH

Pekerja

60,000.00

0.060

OH

Tukang las Konstruksi

70,000.00

0.006

OH

Kepala tukang

80,000.00

0.003

OH

Mandor

90,000.00

13,800.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
3

Mengerjakan 100 kg pekerjaan perakitan


1.000

Liter

Solar

12,000.00

12,000.00

0.100

Liter

Minyak pelumas

25,000.00

2,500.00

0.100

OH

Pekerja

60,000.00

0.100

OH

Tukang besi Konstruksi

70,000.00

0.001

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

0.800

Jam

Sewa alat

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
4

Membuat 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
15.000

Kg

Besi siku L 30.30.3

10,000.00

150,000.00

32.800

Kg

Besi plat baja

13,000.00

426,400.00

0.050

Kg

kawat las

22,000.00

1,100.00

1.050

OH

Pekerja

60,000.00

1.050

OH

Tukang Las Biasa

70,000.00

0.105

OH

Kepala tukang

80,000.00

0.052

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
5

Mengerjakan 10 cm pengelasan dengan las listrik


0.400

Kg

Kawat las listrik

22,000.00

8,800.00

0.300

Liter

Solar

12,000.00

3,600.00

0.040

Liter

Minyak pelumas

25,000.00

1,000.00

0.040

OH

Pekerja

60,000.00

0.020

OH

Tukang besi Konstruksi

70,000.00

0.002

OH

Kepala tukang

80,000.00

0.002

OH

Mandor

90,000.00

0.170

Jam

Sewa alat

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
6

Membuat 1 m2 rangka jendela besi scuare tube (25 x 5) cm


4.760

Besi scuare tube

n/a

#VALUE!

4.522

Besi lis kaca (1 x 1) cm

n/a

#VALUE!

n/a

#VALUE!

20.000

Cm

Pengelasan

0.650

OH

Pekerja

60,000.00

0.650

OH

Tukang Las Biasa

70,000.00

0.065

OH

Kepala tukang

80,000.00

0.032

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
7

Memasang 1 m2 pintu rolling door besi


1.000

M2

Pintu gulung besi

n/a

1.200

OH

Pekerja

60,000.00

1.200

OH

Tukang Las biasa

70,000.00

0.120

OH

Kepala tukang

80,000.00

0.006

OH

Mandor

90,000.00

#VALUE!

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
8

Memasang 1 m2 pintu lipat (Folding door) bahan plastik/PVC


1.000

M2

Pintu lipat

0.440

OH

Pekerja

n/a
60,000.00

0.440

OH

Tukang

70,000.00

0.044

OH

Kepala tukang

80,000.00

0.022

OH

Mandor

90,000.00

#VALUE!

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
9

Memasang 1 m2 sunscreen alluminium


1.000

M2

Sunscreen alluminium

n/a

0.080

OH

Pekerja

60,000.00

0.800

OH

Tukang

70,000.00

0.080

OH

Kepala tukang

80,000.00

0.004

OH

Mandor

90,000.00

#VALUE!

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
10

Memasang 1 m2 rolling door alluminium


1.000

m2

Rolling door alluminium

n/a

1.000

OH

Pekerja

60,000.00

1.000

OH

Tukang Khusus alluminium

70,000.00

0.100

OH

Kepala tukang

80,000.00

0.050

OH

Mandor

90,000.00

#VALUE!

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
11

Memasang 1 m kusen pintu alluminium


1.100

Profil alluminium

n/a

#VALUE!

2.000

Buah

Skrup fixer

n/a

#VALUE!

0.060

Tube

Sealant

n/a

#VALUE!

0.043

OH

Pekerja

60,000.00

0.043

OH

Tukang Khusus alluminium

70,000.00

0.004

OH

Kepala tukang

80,000.00

0.002

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
12

Memasang 1 m2 pintu alluminium strip lebar 8 cm


4.400

m'

Profil alluminium

n/a

#VALUE!

14.600

m'

Alluminium strip

n/a

#VALUE!

0.085

OH

Pekerja

60,000.00

0.085

OH

Tukang Khusus alluminium

70,000.00

0.009

OH

Kepala tukang

80,000.00

0.004

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
13

Memasang 1 m2 pintu kaca rangka alluminium


4.400

Pintu alluminium

4.500

Profil kaca

0.270

Tube

Sealant

0.085

OH

Pekerja

60,000.00

0.085

OH

Tukang Khusus alluminium

70,000.00

0.009

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
14

Memasang 1 m2 venetions blinds dan Vertical blinds


1.000

m2

Venetions blinds dan vertical blinds (tirai)

0.350

OH

Pe kerja

60,000.00

0.350

OH

Tukang

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.018

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
15

Memasang 1 m2 terali besi strip (2 x 3) mm


6.177

kg

Besi strip

27.080

cm

Pengelasan

1.670

OH

Pekerja

60,000.00

1.670

OH

Tukang Las

70,000.00

0.167

OH

Kepala tukang

80,000.00

0.083

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
16

Memasang 1 m2 kawat nyamuk


1.100

m2

Kawat nyamuk

11.110

cm

Pengelasan

1.716

kg

Baja strip (0,2 x 2) cm

0.100

OH

Pe kerja

60,000.00

0.100

OH

Tukang

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
17

Memasang 1 m2 jendela nako & tralis


1.100
10.000

m2
Buah

Jendela nako (rangka + kaca 5 mm)

Paku skrup 1 cm - 2,5 cm

7.000

Besi strip

0.200

OH

Pekerja

60,000.00

0.200

OH

Tukang

70,000.00

0.020

OH

Kepala tukang

80,000.00

0.001

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
18

Memasang 1 m' talang datar/ jurai seng bjls 28 lebar 90 cm


1.050

m'

Seng plat

0.015

kg

Paku 1 cm - 2,5 cm

0.019

m3

Papan kayu kelas II atau III

0.200

OH

Pekerja

60,000.00

0.200

OH

Tukang

70,000.00

0.020

OH

Kepala tukang

80,000.00

0.010

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
19

Memasang 1 m' talang 1/2 lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm
1.050

Seng plat

0.010

kg

Paku 1 cm -2,5 cm

0.500

kg

Besi strip

0.150

OH

Pekerja

60,000.00

0.300

OH

Tukang

70,000.00

0.030

OH

Kepala tukang

80,000.00

0.008

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
20

Memasang 1 m' rangka besi hollow 1 x 40.40.2 mm, modul 60 x 120, dinding partisi
3.500
1 x rangka

Rangka metal hollow 40.40.2

ls

Assesoris (perkuatan, las, dll)

0.250

OH

Pekerja

60,000.00

0.250

OH

Tukang

70,000.00

0.025

OH

Kepala tukang

80,000.00

0.013

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
21

Memasang 1 m' rangka besi hollow 1 x 40.40.2 mm, modul 60 x 60, plafon
4.000

Rangka metal hollow 40.40.2

1 x rangka

ls

Assesoris (perkuatan, las, dll)

0.350

OH

Pekerja

60,000.00

0.350

OH

Tukang

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.018

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

HARGA
UPAH (Rp)

JUMLAH HARGA
(Rp)

11,500.00
3,600.00

3,600.00

4,200.00

4,200.00

480.00

480.00

270.00

270.00
20,050.00

20,050.00
20,050.00
13,800.00

3,600.00

3,600.00

4,200.00

4,200.00

480.00

480.00

270.00

270.00
22,350.00

22,350.00
22,350.00
12,000.00
2,500.00

6,000.00

6,000.00

7,000.00

7,000.00

80.00

80.00

450.00

450.00
28,030.00

28,030.00
28,030.00
150,000.00
426,400.00
1,100.00

63,000.00

63,000.00

73,500.00

73,500.00

8,400.00

8,400.00

4,680.00

4,680.00

727,080.00
-

727,080.00
727,080.00
8,800.00
3,600.00
1,000.00

2,400.00

2,400.00

1,400.00

1,400.00

160.00

160.00

180.00

180.00
5,140.00
22,680.00

22,680.00
22,680.00
#VALUE!
#VALUE!
#VALUE!

39,000.00

39,000.00

45,500.00

45,500.00

5,200.00

5,200.00

2,880.00

2,880.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!

72,000.00

72,000.00

84,000.00

84,000.00

9,600.00

9,600.00

540.00

540.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!

26,400.00

26,400.00

30,800.00

30,800.00

3,520.00

3,520.00

1,980.00

1,980.00

#VALUE!
-

#VALUE!
#VALUE!
#VALUE!
#VALUE!

4,800.00

4,800.00

56,000.00

56,000.00

6,400.00

6,400.00

360.00

360.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!

60,000.00

60,000.00

70,000.00

70,000.00

8,000.00

8,000.00

4,500.00

4,500.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

2,580.00

2,580.00

3,010.00

3,010.00

344.00

344.00

189.00

189.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

5,100.00

5,100.00

5,950.00

5,950.00

680.00

680.00

378.00

378.00
#VALUE!

#VALUE!

#VALUE!
#VALUE!
5,100.00

5,100.00

5,950.00

5,950.00

720.00

720.00

450.00

450.00
12,220.00

12,220.00
12,220.00
-

21,000.00

21,000.00

24,500.00

24,500.00

2,800.00

2,800.00

1,620.00

1,620.00
49,920.00

49,920.00
49,920.00
-

100,200.00

100,200.00

116,900.00

116,900.00

13,360.00

13,360.00

7,470.00

7,470.00
237,930.00

237,930.00
237,930.00
-

6,000.00

6,000.00

7,000.00

7,000.00

800.00

800.00

450.00

450.00
14,250.00

14,250.00
14,250.00
12,000.00

12,000.00

14,000.00

14,000.00

1,600.00

1,600.00

90.00

90.00
27,690.00

27,690.00
27,690.00
-

12,000.00

12,000.00

14,000.00

14,000.00

1,600.00

1,600.00

900.00

900.00
28,500.00

28,500.00
28,500.00
-

9,000.00

9,000.00

21,000.00

21,000.00

2,400.00

2,400.00

720.00

720.00
33,120.00

33,120.00
33,120.00
-

15,000.00

15,000.00

17,500.00

17,500.00

2,000.00

2,000.00

1,170.00

1,170.00

35,670.00
-

35,670.00
35,670.00
-

21,000.00

21,000.00

24,500.00

24,500.00

2,800.00

2,800.00

1,620.00

1,620.00
49,920.00

49,920.00
49,920.00

HARGA

NO.

INDEKS

SATUAN

KEBUTUHAN

HARGA,
SATUAN
(Rp)

BAHAN
(Rp)

PEKERJAAN DINDING
1

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 2 PP
140.000
43.500

Buah

Bata merah

600.00

84,000.00

1,250.00

54,375.00

195,000.00

15,600.00

kg

Portland Cement

0.080

Pasir pasang

0.600

OH

Pekerja

60,000.00

0.200

OH

Tukang batu

70,000.00

0.020

OH

Kepala tukang

80,000.00

0.030

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
2

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 3 PP
140.000
32.950

Buah

Bata merah

600.00

84,000.00

1,250.00

41,187.50

195,000.00

17,745.00

kg

Portland Cement

0.091

Pasir pasang

0.600

OH

Pekerja

60,000.00

0.200

OH

Tukang batu

70,000.00

0.020

OH

Kepala tukang

80,000.00

0.030

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
3

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 4 PP
140.000
26.550

Buah

Bata merah

600.00

84,000.00

1,250.00

33,187.50

195,000.00

18,135.00

kg

Portland Cement

0.093

Pasir pasang

0.600

OH

Pekerja

60,000.00

0.200

OH

Tukang batu

70,000.00

0.020

OH

Kepala tukang

80,000.00

0.030

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
4

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 5 PP
140.000
22.200
0.102

Buah

Bata merah

kg

Portland Cement

Pasir pasang

600.00

84,000.00

1,250.00

27,750.00

195,000.00

19,890.00

0.600

OH

Pekerja

60,000.00

0.200

OH

Tukang batu

70,000.00

0.020

OH

Kepala tukang

80,000.00

0.030

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
5

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 6 PP
140.000
18.500

Buah

Bata merah

600.00

84,000.00

1,250.00

23,125.00

195,000.00

23,790.00

kg

Portland Cement

0.122

Pasir pasang

0.600

OH

Pekerja

60,000.00

0.200

OH

Tukang batu

70,000.00

0.020

OH

Kepala tukang

80,000.00

0.030

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
6

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1 bata, campuran spesi 1 PC : 3 KP :
140.000
10.080

Buah

Bata merah

600.00

84,000.00

1,250.00

12,600.00

195,000.00

18,037.50
2,475.00

kg

Portland Cement

0.093

Pasir pasang

0.028

Kapur padam

90,000.00

0.600

OH

Pekerja

60,000.00

0.200

OH

Tukang batu

70,000.00

0.020

OH

Kepala tukang

80,000.00

0.030

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
7

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 2 PP
70.000

Buah

18.950

kg

Portland Cement

0.038

Pasir pasang

0.300

OH

Pekerja

60,000.00

0.100

OH

Tukang batu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

Bata merah

600.00

42,000.00

1,250.00

23,687.50

195,000.00

7,410.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

0%

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 3 PP
70.000

Buah

14.370

kg

Portland Cement

0.040

Pasir pasang

0.300

OH

Pekerja

60,000.00

0.100

OH

Tukang batu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

Bata merah

600.00

42,000.00

1,250.00

17,962.50

195,000.00

7,800.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
9

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 4 PP
70.000

Buah

11.500

kg

Portland Cement

0.043

Pasir pasang

0.300

OH

Pekerja

60,000.00

0.100

OH

Tukang batu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

Bata merah

600.00

42,000.00

1,250.00

14,375.00

195,000.00

8,385.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
10

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 5 PP
70.000

Buah

Bata merah

600.00

42,000.00

1,250.00

12,100.00

195,000.00

8,775.00

9.680

kg

Portland Cement

0.045

Pasir pasang

0.300

OH

Pekerja

60,000.00

0.100

OH

Tukang batu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
11

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 6 PP
70.000

Buah

Bata merah

600.00

42,000.00

1,250.00

10,400.00

195,000.00

9,555.00

8.320

kg

Portland Cement

0.049

Pasir pasang

0.300

OH

Pekerja

60,000.00

0.100

OH

Tukang batu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

Jumlah

Keuntungan Maksimal

0%

Jumlah
Dibulatkan
12

Memasang 1 m2 dinding bata merah ukuran (5 x11 x 22) tebal 1/2 bata, campuran spesi 1 PC : 8 PP
70.000

Buah

Bata merah

600.00

42,000.00

1,250.00

8,125.00

195,000.00

9,750.00

6.500

kg

Portland Cement

0.050

Pasir pasang

0.300

OH

Pekerja

60,000.00

0.100

OH

Tukang batu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
13

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 3 KP :
70.000

Buah

Bata merah

600.00

42,000.00

1,250.00

5,625.00

195,000.00

9,750.00

Kapur padam

90,000.00

1,350.00

OH

Pekerja

60,000.00

OH

Tukang batu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

4.500

kg

Portland Cement

0.050

Pasir pasang

0.015

0.300
0.100

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
14

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 KP : 1 SM :
70.000

Buah

Bata merah

0.018

0.018

Semen merah
Pasir pasang

0.018

0.300

OH

0.100

600.00
n.a

42,000.00
#VALUE!

195,000.00

3,510.00

Kapur padam

90,000.00

1,620.00

Pekerja

60,000.00

OH

Tukang batu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
15

Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal V2 bata, campuran spesi 1 KP : 1 SM
70.000

Buah

0.014

0.028

Bata merah
Semen merah
Pasir pasang

600.00
n.a
195,000.00

42,000.00
#VALUE!
5,460.00

0.014

m3

Kapur padam

90,000.00

0.300

OH

Pekerja

60,000.00

0.100

OH

Tukang batu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

1,260.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
16

Memasang 1 m2 dinding HB/CB 20 , campuran spesi 1 PC : 3 PP


12.500

Buah

HB/CB 20

3,200.00

40,000.00

30.320

kg

Portland Cement

1,250.00

37,900.00

0.728

Pasir pasang

0.280

kg

Besi angkur =8 mm

0.350

OH

Pekerja

60,000.00

0.150

OH

Tukang batu

70,000.00

0.015

OH

Kepala tukang

80,000.00

0.018

OH

Mandor

90,000.00

195,000.00 141,960.00
8,727.00

2,443.56

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
17

Memasang 1 m2 dinding HB/CB 20, campuran spesi 1 PC : 4 PP


12.500

Buah

HB20

3,200.00

40,000.00

1,250.00

30,325.00

24.260

kg

Portland Cement

0.772

m3

Pasir pasang

0.280

kg

Besi angkur =8 mm

0.350

OH

Pekerja

60,000.00

0.150

OH

Tukang batu

70,000.00

0.015

OH

Kepala tukang

80,000.00

0.018

OH

Mandor

90,000.00

195,000.00 150,540.00
8,727.00

2,443.56

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
18

Memasang 1 m2 dinding HB/CB 15, campuran spesi 1 PC : 3 PP


12.500

Buah

22.740

kg

Portland Cement

0.550

m3

Pasir pasang

0.280

kg

Besi angkur =8 mm

0.320

OH

Pekerja

60,000.00

0.120

OH

Tukang batu

70,000.00

0.012

OH

Kepala tukang

80,000.00

0.016

OH

Mandor

90,000.00

Jumlah

HB15

n.a

#VALUE!
1,250.00

28,425.00

195,000.00 107,250.00
8,727.00

2,443.56

Keuntungan Maksimal

0%

Jumlah
Dibulatkan
19

Memasang 1 m2 dinding HB/CB 15, campuran spesi 1 PC : 4 PP


12.500

Buah

18.200

kg

HB 15
Portland Cement

n.a

#VALUE!

0.582

m3

Pasir pasang

0.280

kg

Besi angkur =8 mm

0.320

OH

Pekerja

60,000.00

0.120

OH

Tukang batu

70,000.00

0.012

OH

Kepala tukang

80,000.00

0.016

OH

Mandor

90,000.00

1,250.00

22,750.00

195,000.00 113,490.00
8,727.00

2,443.56

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
20

Memasang 1 m2 dinding HB/CB 10, campuran spesi 1 PC : 3 PP


12.500

Buah

15.160

kg

Portland Cement

Pasir pasang

0.364

HB 10

n.a

#VALUE!
1,250.00

18,950.00

195,000.00

70,980.00

8,727.00

2,443.56

0.280

kg

Besi angkur =8 mm

0.300

OH

Pekerja

60,000.00

0.100

OH

Tukang batu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
21

Memasang 1 m2 dinding HB/CB 10, campuran spesi 1 PC : 4 PP


12.500

Buah

12.130

kg

Portland Cement

0.388

Pasir pasang

0.280

kg

Besi angkur =8 mm

0.300

OH

Pekerja

60,000.00

0.100

OH

Tukang batu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

HB 10

n.a

#VALUE!
1,250.00

15,162.50

195,000.00

75,660.00

8,727.00

2,443.56

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
22

Memasang 1 m2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 PC : 3 PP
30.000

Buah

Terawang (roster)

14.000

kg

Portland Cement

n.a

#VALUE!
1,250.00

17,500.00

0.032

m3

Pasir pasang

0.300

OH

Pekerja

195,000.00
60,000.00

0.100

OH

Tukang batu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

6,240.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
23

Memasang 1 m2 dinding terawang (roster) ukuran (12 x 11 x 24) cm, campuran spesi 1 PC : 4 PP
30.000

Buah

Terawang (roster)

11.000

kg

Portland Cement

0.035

Pasir pasang

0.300

OH

Pekerja

60,000.00

0.100

OH

Tukang batu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

n.a

#VALUE!
1,250.00

13,750.00

195,000.00

6,825.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
24

Memasang 1 m2 dinding bata berongga ekspose ukuran (5x11x24) cm, campuran spesi 1 PC : 3 PP
70.000

Buah

14.000

kg

Portland Cement

0.032

Pasir pasang

0.300

OH

Pekerja

60,000.00

0.150

OH

Tukang batu

70,000.00

0.015

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

Bata berongga ekspose

n.a

#VALUE!
1,250.00

17,500.00

195,000.00

6,240.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

0%

HARGA
UPAH (Rp)

JUMLAH HARGA
(Rp)

, campuran spesi 1 PC : 2 PP
84,000.00
54,375.00
15,600.00
36,000.00

36,000.00

14,000.00

14,000.00

1,600.00

1,600.00

2,700.00

2,700.00
208,275.00

0%

208,275.00
208,270.00

, campuran spesi 1 PC : 3 PP
84,000.00
41,187.50
17,745.00
36,000.00

36,000.00

14,000.00

14,000.00

1,600.00

1,600.00

2,700.00

2,700.00
197,232.50

0%

197,232.50
197,230.00

, campuran spesi 1 PC : 4 PP
84,000.00
33,187.50
18,135.00
36,000.00

36,000.00

14,000.00

14,000.00

1,600.00

1,600.00

2,700.00

2,700.00
189,622.50

0%

189,622.50
189,620.00

, campuran spesi 1 PC : 5 PP
84,000.00
27,750.00
19,890.00

36,000.00

36,000.00

14,000.00

14,000.00

1,600.00

1,600.00

2,700.00

2,700.00
185,940.00

0%

185,940.00
185,940.00

, campuran spesi 1 PC : 6 PP
84,000.00
23,125.00
23,790.00
36,000.00

36,000.00

14,000.00

14,000.00

1,600.00

1,600.00

2,700.00

2,700.00
185,215.00

0%

185,215.00
185,210.00

a, campuran spesi 1 PC : 3 KP : 10 PP
84,000.00
12,600.00
18,037.50
2,475.00
36,000.00

36,000.00

14,000.00

14,000.00

1,600.00

1,600.00

2,700.00

2,700.00
171,412.50

0%

171,412.50
171,410.00

a, campuran spesi 1 PC : 2 PP
42,000.00
23,687.50
7,410.00
18,000.00

18,000.00

7,000.00

7,000.00

800.00

800.00

1,350.00

1,350.00
100,247.50

0%

100,247.50
100,240.00

a, campuran spesi 1 PC : 3 PP
42,000.00
17,962.50
7,800.00
18,000.00

18,000.00

7,000.00

7,000.00

800.00

800.00

1,350.00

1,350.00
94,912.50

0%

94,912.50
94,910.00

a, campuran spesi 1 PC : 4 PP
42,000.00
14,375.00
8,385.00
18,000.00

18,000.00

7,000.00

7,000.00

800.00

800.00

1,350.00

1,350.00
91,910.00

0%

91,910.00
91,910.00

a, campuran spesi 1 PC : 5 PP
42,000.00
12,100.00
8,775.00
18,000.00

18,000.00

7,000.00

7,000.00

800.00

800.00

1,350.00

1,350.00
48,025.00

0%

48,025.00
48,020.00

a, campuran spesi 1 PC : 6 PP
42,000.00
10,400.00
9,555.00
18,000.00

18,000.00

7,000.00

7,000.00

800.00

800.00

1,350.00

1,350.00
89,105.00

0%

89,105.00
89,100.00

ampuran spesi 1 PC : 8 PP
42,000.00
8,125.00
9,750.00
18,000.00

18,000.00

7,000.00

7,000.00

800.00

800.00

1,350.00

1,350.00
87,025.00

0%

87,025.00
87,020.00

a, campuran spesi 1 PC : 3 KP : 10 PP
42,000.00
5,625.00
9,750.00
1,350.00
18,000.00

18,000.00

7,000.00

7,000.00

800.00

800.00

1,350.00

1,350.00
85,875.00

0%

85,875.00
85,870.00

a, campuran spesi 1 KP : 1 SM : 1 PP
42,000.00
#VALUE!
3,510.00
1,620.00
18,000.00

18,000.00

7,000.00

7,000.00

800.00

800.00

1,350.00

1,350.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!

a, campuran spesi 1 KP : 1 SM : 2 PP
42,000.00
#VALUE!
5,460.00

1,260.00
18,000.00

18,000.00

7,000.00

7,000.00

800.00

800.00

1,350.00

1,350.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
40,000.00
37,900.00
141,960.00
2,443.56

21,000.00

21,000.00

10,500.00

10,500.00

1,200.00

1,200.00

1,620.00

1,620.00
256,623.56

0%

256,623.56
256,620.00
40,000.00
30,325.00
150,540.00
2,443.56

21,000.00

21,000.00

10,500.00

10,500.00

1,200.00

1,200.00

1,620.00

1,620.00
257,628.56

0%

257,628.56
257,620.00
#VALUE!
28,425.00
107,250.00
2,443.56

19,200.00

19,200.00

8,400.00

8,400.00

960.00

960.00

1,440.00

1,440.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
22,750.00
113,490.00
2,443.56

19,200.00

19,200.00

8,400.00

8,400.00

960.00

960.00

1,440.00

1,440.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
18,950.00
70,980.00
2,443.56

18,000.00

18,000.00

7,000.00

7,000.00

800.00

800.00

1,350.00

1,350.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
15,162.50
75,660.00
2,443.56

18,000.00

18,000.00

7,000.00

7,000.00

800.00

800.00

1,350.00

1,350.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!

puran spesi 1 PC : 3 PP
#VALUE!
17,500.00

6,240.00
18,000.00

18,000.00

7,000.00

7,000.00

800.00

800.00

1,350.00

1,350.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!

puran spesi 1 PC : 4 PP
#VALUE!
13,750.00
6,825.00
18,000.00

18,000.00

7,000.00

7,000.00

800.00

800.00

1,350.00

1,350.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!

ampuran spesi 1 PC : 3 PP
#VALUE!
17,500.00
6,240.00
18,000.00

18,000.00

10,500.00

10,500.00

1,200.00

1,200.00

1,350.00

1,350.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!

HARGA

NO.

INDEKS

SATUAN

KEBUTUHAN

HARGA,
SATUAN
(Rp)

BAHAN
(Rp)

PEKERJAAN PLESTERAN
1

Membuat 1 m2 plesteran 1 PC : 1 PP, tebal 15 mm


15.504

Kg

Portland Cement

0.016

Pasir Pasang

0.300

OH

Pekerja

60,000.00

0.150

OH

Tukang batu

70,000.00

0.015

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

1,250.00

19,380.00

195,000.00

3,120.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
2

Membuat 1 m2 plesteran 1 PC : 2 PP, tebal 15 mm


10.224

Kg

Portland Cement

0.020

Pasir Pasang

0.300

OH

Pekerja

60,000.00

0.150

OH

Tukang batu

70,000.00

0.015

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

1,250.00

12,780.00

195,000.00

3,900.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
3

Membuat 1 m2 plesteran 1 PC : 3 PP, tebal 15 mm


7.776

Kg

Portland Cement

0.023

M3

Pasir Pasang

1,250.00

9,720.00

195,000.00

4,485.00

0.300

OH

Pekerja

60,000.00

0.150

OH

Tukang batu

70,000.00

0.015

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
4

Membuat 1 m2 plesteran 1 PC : 4 PP, tebal 15 mm


6.240

Kg

Portland Cement

0.024

Pasir Pasang

0.300

OH

Pekerja

60,000.00

0.150

OH

Tukang batu

70,000.00

0.015

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

1,250.00

7,800.00

195,000.00

4,680.00

Jumlah
Keuntungan Maksimal
Jumlah

0%

Dibulatkan
5

Membuat 1 m2 plesteran 1 PC : 5 PP, tebal 15 mm


5.184

Kg

Portland Cement

0.026

Pasir Pasang

0.300

OH

Pekerja

60,000.00

0.150

OH

Tukang batu

70,000.00

0.015

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

1,250.00

6,480.00

195,000.00

5,070.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
6

Membuat 1 m2 plesteran 1 PC : 6 PP, tebal 15 mm


4.416

kg

Portland Cement

0.027

Pasir Pasang

0.300

OH

Pekerja

60,000.00

0.150

OH

Tukang batu

70,000.00

0.015

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

1,250.00

5,520.00

195,000.00

5,265.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
7

Membuat 1 m2 plesteran 1 PC : 7 PP, tebal 15 mm


3.936

kg

Portland Cement

0.028

m3

Pasir Pasang

1,250.00

4,920.00

195,000.00

5,460.00

0.300

OH

Pekerja

60,000.00

0.150

OH

Tukang batu

70,000.00

0.015

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
8

Membuat 1 m2 plesteran 1 PC : 8 PP, tebal 15 mm


3.456

kg

Portland Cement

0.029

Pasir Pasang

0.300

OH

Pekerja

60,000.00

0.150

OH

Tukang batu

70,000.00

0.015

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

1,250.00

4,320.00

195,000.00

5,655.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
9

Membuat 1 m2 plesteran 1 PC : 1/2 KP : 3 PP, tebal 15 mm


5.760

kg

Portland Cement

0.003

Kapur Padam

1,250.00

7,200.00

90,000.00

270.00

0.013

m3

Pasir Pasang

0.360

OH

Pekerja

195,000.00
60,000.00

0.120

OH

Tukang batu

70,000.00

0.012

OH

Kepala tukang

80,000.00

0.018

OH

Mandor

90,000.00

2,535.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
10

Membuat 1 m2 plesteran 1 PC : 2 KP : 8 PP, tebal 15 mm


3.000

kg

Portland Cement

0.005

1,250.00

3,750.00

Kapur Padam

0.020

90,000.00

450.00

Pasir Pasang

0.360

OH

Pekerja

195,000.00
60,000.00

3,900.00

0.120

OH

Tukang batu

70,000.00

0.012

OH

Kepala tukang

80,000.00

0.018

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
11

Membuat 1 m2 plesteran 1 SM : 1 KP : 1 PP, tebal 15 mm


0.009

m3

Semen Merah

0.009

n.a

#VALUE!

Kapur Padam

0.009

Pasir Pasang

0.360

OH

Pekerja

60,000.00

0.120

OH

Tukang batu

70,000.00

0.012

OH

Kepala tukang

80,000.00

0.018

OH

Mandor

90,000.00

90,000.00

810.00

195,000.00

1,755.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
12

Membuat 1 m2 plesteran 1 SM : 1 KP : 2 PP, tebal 15 mm


0.007

m3

Semen Merah

0.007

n.a

#VALUE!

Kapur Padam

0.015

Pasir Pasang

0.360

OH

Pekerja

60,000.00

0.120

OH

Tukang batu

70,000.00

0.012

OH

Kepala tukang

80,000.00

0.018

OH

Mandor

90,000.00

90,000.00

630.00

195,000.00

2,925.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
13

Membuat 1 m2 plesteran 1 PC : 2 PP, tebal 20 mm


13.632
0.027

kg

Portland Cement

Pasir Pasang

1,250.00

17,040.00

195,000.00

5,265.00

0.400

OH

Pekerja

60,000.00

0.200

OH

Tukang batu

70,000.00

0.020

OH

Kepala tukang

80,000.00

0.022

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
14

Membuat 1 m2 plesteran 1 PC : 3 PP, tebal 20 mm


10.368

kg

Portland Cement

0.031

Pasir Pasang

0.260

OH

Pekerja

60,000.00

0.200

OH

Tukang batu

70,000.00

0.020

OH

Kepala tukang

80,000.00

0.013

OH

Mandor

90,000.00

1,250.00

12,960.00

195,000.00

6,045.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
15

Membuat 1 m2 plesteran 1 PC : 4 PP, tebal 20 mm


8.320

kg

Portland Cement

0.032

m3

Pasir Pasang

1,250.00

10,400.00

195,000.00

6,240.00

0.400

OH

Pekerja

60,000.00

0.200

OH

Tukang batu

70,000.00

0.020

OH

Kepala tukang

80,000.00

0.022

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
16

Membuat 1 m2 plesteran 1 PC : 5 PP, tebal 20 mm


6.912

kg

Portland Cement

0.035

Pasir Pasang

0.400

OH

Pekerja

60,000.00

0.200

OH

Tukang batu

70,000.00

0.020

OH

Kepala tukang

80,000.00

0.022

OH

Mandor

90,000.00

1,250.00

8,640.00

195,000.00

6,825.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
17

Membuat 1 m2 plesteran 1 PC : 6 PP, tebal 20 mm


5.888

kg

Portland Cement

0.036

Pasir Pasang

0.400

OH

Pekerja

60,000.00

0.200

OH

Tukang batu

70,000.00

0.020

OH

Kepala tukang

80,000.00

0.022

OH

Mandor

90,000.00

1,250.00

7,360.00

195,000.00

7,020.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
18

Membuat 1 m2 plesteran 1 SM : 1 KP : 2 PP, tebal 20 mm


0.009

m3

Semen Merah

0.009

n.a

#VALUE!

Kapur Padam

0.018

Pasir Pasang

0.440

OH

Pekerja

60,000.00

0.220

OH

Tukang batu

70,000.00

0.022

OH

Kepala tukang

80,000.00

0.022

OH

Mandor

90,000.00

90,000.00

810.00

195,000.00

3,510.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
19

Membuat 1 m2 Berapen 1 PC : 5 PP, tebal 15 mm


5.184

kg

Portland Cement

0.026

Pasir Pasang

0.150

OH

Pekerja

60,000.00

0.075

OH

Tukang batu

70,000.00

0.008

OH

Kepala tukang

80,000.00

0.008

OH

Mandor

90,000.00

1,250.00

6,480.00

195,000.00

5,070.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
20

Membuat 1 m' Plesteran Skoning lebar 10 mm 1 PC : 2 PP.


0.500

kg

Portland Cement

0.013

m3

Pasir Pasang

1,250.00

625.00

195,000.00

2,535.00

0.080

OH

Pekerja

60,000.00

0.400

OH

Tukang batu

70,000.00

0.040

OH

Kepala tukang

80,000.00

0.004

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
21

Membuat 1 m2 Plesteran Granit, 1 PC : 2 Granit, tebal 10 mm


10.000

kg

Portland Cement

1,250.00

15.000

kg

Batu granit

0.450

OH

Pekerja

60,000.00

0.225

OH

Tukang batu

70,000.00

0.023

OH

Kepala tukang

80,000.00

0.023

OH

Mandor

90,000.00

n.a

12,500.00
#VALUE!

Jumlah
Keuntungan Maksimal
Jumlah

0%

Dibulatkan
22

Membuat 1 m2 Plesteran Teraso , 1 PC : 2 Batu Teraso, tebal 10 mm


10.000

kg

Portland Cement

1,250.00

15.000

kg

Batu teraso

0.450

OH

Pekerja

60,000.00

0.225

OH

Tukang batu

70,000.00

0.023

OH

Kepala tukang

80,000.00

0.023

OH

Mandor

90,000.00

n.a

12,500.00
#VALUE!

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
23

Membuat 1 m2 Plesteran Ciprat / Kamprotan 1 PC : 2 PP


4.320

kg

Portland Cement

0.006

Pasir Pasang

0.300

OH

Pekerja

60,000.00

0.100

OH

Tukang batu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

1,250.00

5,400.00

195,000.00

1,170.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
24

Membuat 1 m2 finishing siar pasangan dinding bata merah (=20 m')


3.108

kg

Portland Cement

0.150

OH

Pekerja

60,000.00

1,250.00

0.075

OH

Tukang batu

70,000.00

0.008

OH

Kepala tukang

80,000.00

0.008

OH

Mandor

90,000.00

3,885.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
25

Membuat 1 m2 finishing siar pasangan dinding conblock ekspose (=8 m')


1.600

kg

Portland Cement

1,250.00

0.070

OH

Pekerja

60,000.00

0.035

OH

Tukang batu

70,000.00

0.004

OH

Kepala tukang

80,000.00

0.004

OH

Mandor

90,000.00

2,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
26

Membuat 1 m2 finishing siar pasangan batu kali adukan 1 PC : 2 PP


6.340

kg

Portland Cement

0.012

m3

Pasir Pasang

1,250.00

7,925.00

195,000.00

2,340.00

0.300

OH

Pekerja

60,000.00

0.150

OH

Tukang batu

70,000.00

0.015

OH

Kepala tukang

80,000.00

0.015

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
27

Membuat 1 m2 acian
3.250

kg

Portland Cement

1,250.00

0.200

OH

Pekerja

60,000.00

0.100

OH

Tukang batu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.010

OH

Mandor

90,000.00

4,062.50

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

0%

HARGA
UPAH (Rp)

JUMLAH HARGA
(Rp)

19,380.00
3,120.00
18,000.00

18,000.00

10,500.00

10,500.00

1,200.00

1,200.00

1,350.00

1,350.00
53,550.00

0%

53,550.00
53,550.00
12,780.00
3,900.00

18,000.00

18,000.00

10,500.00

10,500.00

1,200.00

1,200.00

1,350.00

1,350.00
47,730.00

0%

47,730.00
47,730.00
9,720.00
4,485.00

18,000.00

18,000.00

10,500.00

10,500.00

1,200.00

1,200.00

1,350.00

1,350.00
45,255.00

0%

45,255.00
45,250.00
7,800.00
4,680.00

18,000.00

18,000.00

10,500.00

10,500.00

1,200.00

1,200.00

1,350.00

1,350.00
43,530.00

0%

43,530.00

43,530.00
6,480.00
5,070.00
18,000.00

18,000.00

10,500.00

10,500.00

1,200.00

1,200.00

1,350.00

1,350.00
42,600.00

0%

42,600.00
42,600.00
5,520.00
5,265.00

18,000.00

18,000.00

10,500.00

10,500.00

1,200.00

1,200.00

1,350.00

1,350.00
41,835.00

0%

41,835.00
41,830.00
4,920.00
5,460.00

18,000.00

18,000.00

10,500.00

10,500.00

1,200.00

1,200.00

1,350.00

1,350.00
41,430.00

0%

41,430.00
41,430.00
4,320.00
5,655.00

18,000.00

18,000.00

10,500.00

10,500.00

1,200.00

1,200.00

1,350.00

1,350.00
41,025.00

0%

41,025.00
41,020.00
7,200.00
270.00

2,535.00
21,600.00

21,600.00

8,400.00

8,400.00

960.00

960.00

1,620.00

1,620.00
42,585.00

0%

42,585.00
42,580.00
3,750.00
450.00
3,900.00

21,600.00

21,600.00

8,400.00

8,400.00

960.00

960.00

1,620.00

1,620.00
40,680.00

0%

40,680.00
40,680.00
#VALUE!
810.00
1,755.00

21,600.00

21,600.00

8,400.00

8,400.00

960.00

960.00

1,620.00

1,620.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
630.00
2,925.00

21,600.00

21,600.00

8,400.00

8,400.00

960.00

960.00

1,620.00

1,620.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
17,040.00
5,265.00

24,000.00

24,000.00

14,000.00

14,000.00

1,600.00

1,600.00

1,980.00

1,980.00
63,885.00

0%

63,885.00
63,880.00
12,960.00
6,045.00

15,600.00

15,600.00

14,000.00

14,000.00

1,600.00

1,600.00

1,170.00

1,170.00
51,375.00

0%

51,375.00
51,370.00
10,400.00
6,240.00

24,000.00

24,000.00

14,000.00

14,000.00

1,600.00

1,600.00

1,980.00

1,980.00
58,220.00

0%

58,220.00
58,220.00
8,640.00
6,825.00

24,000.00

24,000.00

14,000.00

14,000.00

1,600.00

1,600.00

1,980.00

1,980.00
57,045.00

0%

57,045.00
57,040.00
7,360.00
7,020.00

24,000.00

24,000.00

14,000.00

14,000.00

1,600.00

1,600.00

1,980.00

1,980.00

55,960.00
0%

55,960.00
55,960.00
#VALUE!
810.00
3,510.00

26,400.00

26,400.00

15,400.00

15,400.00

1,760.00

1,760.00

1,980.00

1,980.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
6,480.00
5,070.00

9,000.00

9,000.00

5,250.00

5,250.00

640.00

640.00

720.00

720.00
27,160.00

0%

27,160.00
27,160.00
625.00
2,535.00

4,800.00

4,800.00

28,000.00

28,000.00

3,200.00

3,200.00

360.00

360.00
39,520.00

0%

39,520.00
39,520.00
12,500.00
#VALUE!

27,000.00

27,000.00

15,750.00

15,750.00

1,840.00

1,840.00

2,070.00

2,070.00
#VALUE!

0%

#VALUE!
#VALUE!

#VALUE!
12,500.00
#VALUE!
27,000.00

27,000.00

15,750.00

15,750.00

1,840.00

1,840.00

2,070.00

2,070.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
5,400.00
1,170.00

18,000.00

18,000.00

7,000.00

7,000.00

800.00

800.00

1,350.00

1,350.00
33,720.00

0%

33,720.00
33,720.00
3,885.00

9,000.00

9,000.00

5,250.00

5,250.00

640.00

640.00

720.00

720.00
19,495.00

0%

19,495.00
19,490.00
2,000.00

4,200.00

4,200.00

2,450.00

2,450.00

320.00

320.00

360.00

360.00
9,330.00

0%

9,330.00
9,330.00
7,925.00
2,340.00

18,000.00

18,000.00

10,500.00

10,500.00

1,200.00

1,200.00

1,350.00

1,350.00
41,315.00

0%

41,315.00
41,310.00
4,062.50

12,000.00

12,000.00

7,000.00

7,000.00

800.00

800.00

900.00

900.00
24,762.50

0%

24,762.50
24,760.00

HARGA

NO.

INDEKS

SATUAN

KEBUTUHAN

HARGA,
SATUAN (Rp)

BAHAN (Rp)

PEKERJAAN LANTAI
1

Memasang 1 m2 lantai ubin PC abu-abu ukuran (40 x 40) cm


6.630

Buah

9.800

kg

Portland Cement

0.045

Pasir pasang

0.250

OH

Pekerja

60,000.00

0.125

OH

Tukang batu

70,000.00

0.013

OH

Kepala tukang

80,000.00

0.013

OH

Mandor

90,000.00

Ubin abu-abu

n/a

#VALUE!
1,250.00

12,250.00

195,000.00

8,775.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
2

Memasang 1 m2 lantai ubin PC abu-abu ukuran (30 x 30) cm


11.870

Buah

10.000

kg

Portland Cement

0.045

Pasir pasang

0.250

OH

Pekerja

60,000.00

0.125

OH

Tukang batu

70,000.00

0.013

OH

Kepala tukang

80,000.00

0.013

OH

Mandor

90,000.00

Ubin abu-abu

n/a

#VALUE!
1,250.00

12,500.00

195,000.00

8,775.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
3

Memasang 1 m2 lantai ubin PC abu-abu ukuran (20 x 20) cm


26.500

Buah

10.400

kg

Portland Cement

0.045

Pasir pasang

0.270

OH

Pekerja

60,000.00

0.135

OH

Tukang batu

70,000.00

0.014

OH

Kepala tukang

80,000.00

0.014

OH

Mandor

90,000.00

Ubin abu-abu

n/a

#VALUE!
1,250.00

13,000.00

195,000.00

8,775.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
4

Memasang 1 m2 lantai ubin warna ukuran (40 x 40) cm


6.630

Buah

9.800

kg

Portland Cement

0.045

Pasir pasang

Ubin warna

n/a

#VALUE!
1,250.00

12,250.00

195,000.00

8,775.00

1.300

kg

Semen warna

10,000.00

0.250

OH

Pekerja

60,000.00

0.125

OH

Tukang batu

70,000.00

0.013

OH

Kepala tukang

80,000.00

0.013

OH

Mandor

90,000.00

13,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
5

Memasang 1 m2 lantai ubin warna ukuran (30 x 30) cm


11.870

Buah

10.000

kg

Portland Cement

0.045

Pasir pasang

195,000.00

8,775.00

1.500

kg

Semen warna

10,000.00

15,000.00

0.260

OH

Pekerja

60,000.00

0.130

OH

Tukang batu

70,000.00

0.013

OH

Kepala tukang

80,000.00

0.013

OH

Mandor

90,000.00

Ubin warna

n/a

#VALUE!
1,250.00

12,500.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
6

Memasang 1 m2 lantai ubin warna ukuran (20 x 20) cm


26.500

Buah

Ubin warna

10.400

kg

Portland Cement

0.045

m3

Pasir pasang

1.620

kg

0.270

n/a

#VALUE!
1,250.00

13,000.00

195,000.00

8,775.00

Semen warna

10,000.00

16,200.00

OH

Pekerja

60,000.00

0.135

OH

Tukang batu

70,000.00

0.014

OH

Kepala tukang

80,000.00

0.014

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
7

Memasang 1 m2 lantai ubin teraso ukuran (40 x 40) cm


6.630

Buah

9.800

kg

Ubin teraso
Portland Cement

0.045

m3

Pasir pasang

1.300

kg

0.250
0.125

n/a

#VALUE!
1,250.00

12,250.00

195,000.00

8,775.00

Semen warna

10,000.00

13,000.00

OH

Pekerja

60,000.00

OH

Tukang batu

70,000.00

0.013

OH

Kepala tukang

80,000.00

0.013

OH

Mandor

90,000.00

Jumlah

Keuntungan Maksimal

Jumlah
Dibulatkan
8

Memasang 1 m2 lantai ubin teraso ukuran (30 x 30) cm


11.870

Buah

Ubin teraso

2,200.00

26,114.00

10.000

kg

Portland Cement

1,250.00

12,500.00

0.045

Pasir pasang

195,000.00

8,775.00

1.500

kg

Semen warna

10,000.00

15,000.00

0.260

OH

Pekerja

60,000.00

0.130

OH

Tukang batu

70,000.00

0.013

OH

Kepala tukang

80,000.00

0.013

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
9

Memasang 1 m2 lantai ubin granit ukuran (40 x 40) cm


6.630

Buah

9.800

kg

Portland Cement

0.045

Pasir pasang

Ubin granit

n/a

#VALUE!
1,250.00

12,250.00

195,000.00

8,775.00
13,000.00

1.300

kg

Semen warna

10,000.00

0.250

OH

Pekerja

60,000.00

0.125

OH

Tukang batu

70,000.00

0.013

OH

Kepala tukang

80,000.00

0.013

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
10

Memasang 1 m2 lantai ubin granit ukuran (30 x 30) cm


11.870

Buah

10.000

kg

Portland Cement

0.045

Pasir pasang

195,000.00

8,775.00

1.500

kg

Semen warna

10,000.00

15,000.00

0.260

OH

Pekerja

60,000.00

0.130

OH

Tukang batu

70,000.00

0.013

OH

Kepala tukang

80,000.00

0.013

OH

Mandor

90,000.00

Ubin granit

n/a

#VALUE!
1,250.00

12,500.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
11

Memasang 1 m2 lantai ubin teralux ukuran (40 x 40) cm


6.630

Buah

9.800

kg

Ubin teralux kerang


Portland Cement

n/a

#VALUE!
1,250.00

12,250.00

0.045

m3

Pasir pasang

195,000.00

8,775.00

1.300

kg

Semen warna

10,000.00

13,000.00

0.250

OH

Pekerja

60,000.00

0.125

OH

Tukang batu

70,000.00

0.013

OH

Kepala tukang

80,000.00

0.013

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
12

Memasang 1 m2 lantai ubin teralux ukuran (30 x 30) cm


11.870

Buah

Ubin teralux kerang

10.000

kg

Portland Cement

0.045

m3

Pasir pasang

1.500

kg

0.260

n/a

#VALUE!
1,250.00

12,500.00

195,000.00

8,775.00

Semen warna

10,000.00

15,000.00

OH

Pekerja

60,000.00

0.130

OH

Tukang batu

70,000.00

0.013

OH

Kepala tukang

80,000.00

0.013

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
13

Memasang 1 m2 lantai ubin teralux marmer ukuran (60 x 60) cm


3.100

Buah

9.600

kg

Ubin teralux marmer


Portland Cement

0.045

m3

Pasir pasang

1.500

kg

0.240
0.120

n/a

#VALUE!
1,250.00

12,000.00

195,000.00

8,775.00

Semen warna

10,000.00

15,000.00

OH

Pekerja

60,000.00

OH

Tukang batu

70,000.00

0.012

OH

Kepala tukang

80,000.00

0.012

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
14

Memasang 1 m2 lantai ubin teralux marmer ukuran (40 x 40) cm


6.630

Buah

9.800

kg

Portland Cement

0.045

Pasir pasang

Ubin teralux marmer

n/a

#VALUE!
1,250.00

12,250.00

195,000.00

8,775.00
13,000.00

1.300

kg

Semen warna

10,000.00

0.250

OH

Pekerja

60,000.00

0.125

OH

Tukang batu

70,000.00

0.013

OH

Kepala tukang

80,000.00

0.013

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
15

Memasang 1 m2 lantai ubin teralux marmer ukuran (30 x 30) cm


11.870

Buah

10.000

kg

Portland Cement

Pasir pasang

0.045

Ubin teralux marmer

n/a

#VALUE!
1,250.00

12,500.00

195,000.00

8,775.00
15,000.00

1.500

kg

Semen warna

10,000.00

0.260

OH

Pekerja

60,000.00

0.130

OH

Tukang batu

70,000.00

0.013

OH

Kepala tukang

80,000.00

0.013

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
16

Memasang 1 m plint ubin PC abu-abu ukuran (15 x 20) cm


5.300

Buah

1.650

kg

Portland Cement

0.004

Pasir pasang

0.090

OH

Pekerja

60,000.00

0.090

OH

Tukang batu

70,000.00

0.009

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Plint Ubin

n/a

#VALUE!
1,250.00

2,062.50

195,000.00

780.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
17

Memasang 1 m plint ubin PC abu-abu ukuran (10 x 30) cm


3.530

Buah

1.240

kg

Portland Cement

0.003

Pasir pasang

0.090

OH

Pekerja

60,000.00

0.090

OH

Tukang batu

70,000.00

0.009

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Plint Ubin

n/a

#VALUE!
1,250.00

1,550.00

195,000.00

585.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
18

Memasang 1 m plint ubin PC abu-abu ukuran (10 x 40) cm


2.650 Buah

Plint Ubin

1.240 kg

Portland Cement

0.003 m

Pasir pasang

n/a

#VALUE!
1,250.00

1,550.00

195,000.00

585.00

0.090 OH

Pekerja

60,000.00

0.090 OH

Tukang batu

70,000.00

0.009 OH

Kepala tukang

80,000.00

0.005 OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
19

Memasang 1 m plint ubin PC warna ukuran (10 x20) cm


5.300 Buah

Plint ubin PC warna

1.140 kg

Portland Cement

0.003 m

Pasir pasang

n/a

#VALUE!
1,250.00

1,425.00

195,000.00

585.00
1,000.00

0.100 kg

Semen warna

10,000.00

0.090 OH

Pekerja

60,000.00

0.090 OH

Tukang batu

70,000.00

0.009 OH

Kepala tukang

80,000.00

0.005 OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
20

Memasang 1 m plint ubin PC warna ukuran (10x 30) cm


3.530 Buah

Plint ubin PC warna

1.140 kg

Portland Cement

0.003 m

Pasir pasang

n/a

#VALUE!
1,250.00

1,425.00

195,000.00

585.00

0.100 kg

Semen warna

10,000.00

1,000.00

0.090 OH

Pekerja

60,000.00

0.090 OH

Tukang batu

70,000.00

0.009 OH

Kepala tukang

80,000.00

0.005 OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
21

Memasang 1 m plint ubin PC warna ukuran (10x 40) cm


2.650 Buah

Plint ubin PC warna

1.140 kg

Portland Cement

0.003 m3

Pasir pasang

0.100 kg

n/a

#VALUE!
1,250.00

1,425.00

195,000.00

585.00

Semen warna

10,000.00

1,000.00

0.090 OH

Pekerja

60,000.00

0.090 OH

Tukang batu

70,000.00

0.009 OH

Kepala tukang

80,000.00

0.005 OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
22

Memasang 1 m plint ubin teraso ukuran (15 x 30) cm


3.530

Buah

Plint ubin teraso

1.140

kg

Portland Cement

0.003

m3

Pasir pasang

0.100

kg

0.090

2,200.00

7,766.00

1,250.00

1,425.00

195,000.00

585.00

Semen warna

10,000.00

1,000.00

OH

Pekerja

60,000.00

0.090

OH

Tukang batu

70,000.00

0.009

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
23

Memasang 1 m plint ubin teraso ukuran (10 x 40) cm


2.650

Buah

Plint ubin teraso

1.140

kg

Portland Cement

0.003

m3

Pasir pasang

0.100

Kg

0.090
0.090

n/a

#VALUE!
1,250.00

1,425.00

195,000.00

585.00

Semen warna

10,000.00

1,000.00

OH

Pekerja

60,000.00

OH

Tukang batu

70,000.00

0.009

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
24

Memasang 1 m plint ubin granit ukuran (10 x 40) cm


2.650

Buah

Plint ubin granit

1.140

kg

Portland Cement

0.003

Pasir pasang

n/a

#VALUE!
1,250.00

1,425.00

195,000.00

585.00
1,000.00

0.100

kg

Semen warna

10,000.00

0.090

OH

Pekerja

60,000.00

0.090

OH

Tukang batu

70,000.00

0.009

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
25

Memasang 1 m plint ubin granit ukuran (10 x 30) cm


3.530

Buah

Plint ubin granit

1.140

kg

Portland Cement

0.003

Pasir pasang

n/a

#VALUE!
1,250.00

1,425.00

195,000.00

585.00

0.100

kg

Semen warna

10,000.00

0.090

OH

Pekerja

60,000.00

0.090

OH

Tukang batu

70,000.00

0.009

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

1,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
26

Memasang 1 m plint ubin teralux kerang ukuran (10 x 40) cm


2.650

Buah

Plint ubin granit

1.140

kg

Portland Cement

0.003

Pasir pasang

195,000.00

585.00

0.100

kg

Semen warna

10,000.00

1,000.00

0.090

OH

Pekerja

60,000.00

0.090

OH

Tukang batu

70,000.00

0.009

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

n/a

#VALUE!
1,250.00

1,425.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
27

Memasang 1 m plint ubin teralux kerang ukuran (10 x 30) cm


3.530

Buah

Plint ubin teralux kerang

1.140

kg

Portland Cement

0.003

m3

Pasir pasang

0.100

Kg

0.090

n/a

#VALUE!
1,250.00

1,425.00

195,000.00

585.00

Semen warna

10,000.00

1,000.00

OH

Pekerja

60,000.00

0.090

OH

Tukang batu

70,000.00

0.009

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
28

Memasang 1 m plint ubin teralux marmer ukuran (10 x 60) cm


1.700

Buah

1.140

kg

Plint ubin teralux marmer


Portland Cement

0.003

m3

Pasir pasang

0.100

kg

0.090
0.090

n/a

#VALUE!
1,250.00

1,425.00

195,000.00

585.00

Semen warna

10,000.00

1,000.00

OH

Pekerja

60,000.00

OH

Tukang batu

70,000.00

0.009

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Jumlah

Keuntungan Maksimal

Jumlah
Dibulatkan
29

Memasang 1 m plint ubin teralux marmer ukuran (10 x 40) cm


2.650

Buah

1.140

kg

Plint ubin teralux marmer


Portland Cement

0.003

m3

Pasir pasang

0.100

kg

0.090
0.090

n/a

#VALUE!
1,250.00

1,425.00

195,000.00

585.00

Semen warna

10,000.00

1,000.00

OH

Pekerja

60,000.00

OH

Tukang batu

70,000.00

0.009

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
30

Memasang 1 m plint ubin teralux marmer ukuran (10 x 30) cm


3.530

Buah

1.140

kg

Portland Cement

0.003

Pasir pasang

Plint ubin teralux marmer

n/a

#VALUE!
1,250.00

1,425.00

195,000.00

585.00
1,000.00

0.100

kg

Semen warna

10,000.00

0.090

OH

Pekerja

60,000.00

0.090

OH

Tukang batu

70,000.00

0.009

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
31

Memasang 1 m2 lantai teraso cor ditempat, tebal 3 cm


0.036

m3

Bahan teraso cor

n/a

#VALUE!

0.100

kg

Semen warna

10,000.00

0.360

OH

Pekerja

60,000.00

0.180

OH

Tukang batu

70,000.00

0.018

OH

Kepala tukang

80,000.00

0.018

OH

Mandor

90,000.00

1,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
32

Memasang 1 m2 lantai keramik artistik ukuran (10 x 20) cm


53.000

Buah

Ubin keramik artistik

8.190

kg

Portland Cement

0.045

Pasir pasang

2.750

kg

Semen warna

970.00

51,410.00

1,250.00

10,237.50

195,000.00

8,775.00

10,000.00

27,500.00

0.700

OH

Pekerja

60,000.00

0.350

OH

Tukang batu

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.035

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
33

Memasang 1 m2 lantai keramik artistik ukuran (10 x 10) cm atau (5 x 20) cm


106.000

Buah

Ubin keramik artistik

8.190

kg

Portland Cement

0.045

Pasir pasang

517.00

54,802.00

1,250.00

10,237.50

195,000.00

8,775.00
32,000.00

3.200

kg

Semen warna

10,000.00

0.700

OH

Pekerja

60,000.00

0.350

OH

Tukang batu

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.035

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
34

Memasang 1 m2 lantai keramik ukuran (33 x 33) cm


10.000

Buah

Ubin keramik

n/a

#VALUE!

8.190

kg

Portland Cement

0.045

Pasir pasang

195,000.00

8,775.00

1.620

kg

Semen warna

10,000.00

16,200.00

0.700

OH

Pekerja

60,000.00

0.350

OH

Tukang batu

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.035

OH

Mandor

90,000.00

1,250.00

10,237.50

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
35

Memasang 1 m2 lantai keramik warna ukuran (30 x 30) cm


11.870

Buah

Ubin keramik

10.000

kg

Portland Cement

0.045

m3

Pasir pasang

1.500

kg

0.700

8,400.00

99,708.00

1,250.00

12,500.00

195,000.00

8,775.00

Semen warna

10,000.00

15,000.00

OH

Pekerja

60,000.00

0.350

OH

Tukang batu

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.035

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
36

Memasang 1 m2 lantai keramik warna ukuran (20 x 20) cm


26.500

Buah

Ubin keramik

10.400

kg

Portland Cement

0.045

m3

Pasir pasang

1.620

kg

0.700

3,360.00

89,040.00

1,250.00

13,000.00

195,000.00

8,775.00

Semen warna

10,000.00

16,200.00

OH

Pekerja

60,000.00

0.350

OH

Tukang batu

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.035

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
37

Memasang 1 m2 lantai keramik ukuran (10 x 33) cm, variasi/border


33.000

Buah

Ubin keramik

9.800

kg

Portland Cement

0.045

m3

Pasir pasang

4.370

kg

1.050
0.525

n/a

#VALUE!
1,250.00

12,250.00

195,000.00

8,775.00

Semen warna

10,000.00

43,700.00

OH

Pekerja

60,000.00

OH

Tukang batu

70,000.00

0.053

OH

Kepala tukang

80,000.00

0.053

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
38

Memasang 1 m2 lantai mosaik ukuran (30 x 30) cm, campuran spesi 1 PC : 3 PP


11.870

Buah

14.150

kg

Portland Cement

Pasir pasang

0.039

Mosaik

n/a

#VALUE!
1,250.00

17,687.50

195,000.00

7,605.00
20,000.00

2.000

kg

Semen warna

10,000.00

0.700

OH

Pekerja

60,000.00

0.350

OH

Tukang batu

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.035

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
39

Memasang 1 m plint keramik warna ukuran (10 x 20) cm


5.300

Buah

1.140

kg

Portland Cement

0.003

Pasir pasang

Plint keramik artistik

970.00

5,141.00

1,250.00

1,425.00

195,000.00

585.00

0.025

kg

Semen warna

10,000.00

0.090

OH

Pekerja

60,000.00

0.090

OH

Tukang batu

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

250.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
40

Memasang 1 m' plint keramik warna ukuran (10 x 10) cm


10.600

Buah

Plint keramik artistik

517.00

5,480.20

1,250.00

1,425.00

1.140

kg

Portland Cement

0.003

Pasir pasang

195,000.00

585.00

0.050

kg

Semen warna

10,000.00

500.00

0.090

OH

Pekerja

60,000.00

0.090

OH

Tukang batu

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
41

Memasang 1 m plint keramik ukuran (5 x 20) cm


5.300

Buah

Plint keramik artistik

0.570

kg

Portland Cement

0.002

m3

Pasir pasang

0.013

kg

0.090

n/a

#VALUE!
1,250.00

712.50

195,000.00

292.50

Semen warna

10,000.00

130.00

OH

Pekerja

60,000.00

0.090

OH

Tukang batu

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
42

Memasang 1 m plint internal cove artistik ukuran (5 x 5 x 20) cm


5.300

Buah

1.140

kg

Internal cove
Portland Cement

0.003

m3

Pasir pasang

0.100

kg

0.750
0.750

n/a

#VALUE!
1,250.00

1,425.00

195,000.00

585.00

Semen warna

10,000.00

1,000.00

OH

Pekerja

60,000.00

OH

Tukang batu

70,000.00

0.075

OH

Kepala tukang

80,000.00

0.038

OH

Mandor

90,000.00

Jumlah

Keuntungan Maksimal

Jumlah
Dibulatkan
43

Memasang 1 m2 lantai granit DN ukuran (100 x 100) cm


1.060

Buah

8.190

kg

Portland Cement

1,373,200.00

1,455,592.00

1,250.00

10,237.50

0.045

Pasir pasang

195,000.00

8,775.00

0.650

kg

Semen warna

10,000.00

6,500.00

0.700
0.350

OH

Pekerja

60,000.00

OH

Tukang batu

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.035

OH

Mandor

90,000.00

Marmer

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
44

Memasang 1 m2 lantai karpet


1.050

m2

Karpet

n/a

#VALUE!

0.350

kg

Lem

34,000.00

0.170

OH

Pekerja

60,000.00

0.170

OH

Tukang kayu

70,000.00

0.017

OH

Kepala tukang

80,000.00

0.009

OH

Mandor

90,000.00

11,900.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
45

Memasang 1 m2 underlayer/ Pelapis bawah karpet


1.050

m2

Underlayer/rubber corrugated

0.350

kg

Lem

n/a
34,000.00

#VALUE!

0.120

OH

Pekerja

60,000.00

0.120

OH

Tukang kayu

70,000.00

0.012

OH

Kepala tukang

80,000.00

0.006

OH

Mandor

90,000.00

11,900.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
46

Memasang 1 m2 lantai parquet kayu


1.050

m2

Parquet

n/a

#VALUE!

0.600

kg

Lem

34,000.00

0.700

OH

Pekerja

60,000.00

0.350

OH

Tukang kayu

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.035

OH

Mandor

90,000.00

20,400.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
47

Memasang 1 m2 lantai kayu (gymfloor)


1.050

m2

Gymfloor

n/a

#VALUE!

0.600

kg

Lem

34,000.00

0.700

OH

Pekerja

60,000.00

0.350

OH

Tukang kayu

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.035

OH

Mandor

90,000.00

20,400.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
48

Memasang 1 m2 dinding porselen ukuran (11 x 11) cm


86.000

Buah

Porselen

517.00

44,462.00

1,250.00

11,625.00

195,000.00

3,510.00

Semen warna

10,000.00

15,000.00

OH

Pekerja

60,000.00

OH

Tukang batu

70,000.00

0.050

OH

Kepala tukang

80,000.00

0.050

OH

Mandor

90,000.00

9.300

kg

Portland Cement

0.018

Pasir pasang

1.500

kg

1.000
0.500

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
49

Memasang 1 m2 dinding porselin ukuran (10 x 20) cm


53.000

Buah

Porselin

9.300

kg

Portland Cement

0.018

Pasir pasang

n/a

#VALUE!
1,250.00

11,625.00

195,000.00

3,510.00
27,500.00

2.750

kg

Semen warna

10,000.00

0.900

OH

Pekerja

60,000.00

0.450

OH

Tukang batu

70,000.00

0.045

OH

Kepala tukang

80,000.00

0.045

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
50

Memasang 1 m2 dinding porselin ukuran (20 x 20) cm


26.500

Buah

Porselin

9.300

kg

Portland Cement

0.018

Pasir pasang

n/a

#VALUE!
1,250.00

11,625.00

195,000.00

3,510.00

1.940

kg

Semen warna

10,000.00

0.900

OH

Pekerja

60,000.00

0.450

OH

Tukang batu

70,000.00

0.045

OH

Kepala tukang

80,000.00

0.045

OH

Mandor

90,000.00

19,400.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
51

Memasang 1 m2 dinding keramik artistik ukuran (10 x20) cm


53.000

Buah

Keramik artistik

9.300

kg

Portland Cement

0.018

Pasir pasang

195,000.00

3,510.00

2.750

kg

Semen warna

10,000.00

27,500.00

0.900

OH

Pekerja

60,000.00

0.450

OH

Tukang batu

70,000.00

0.045

OH

Kepala tukang

80,000.00

0.045

OH

Mandor

90,000.00

970.00

51,410.00

1,250.00

11,625.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
52

Memasang 1 m2 dinding keramik artistik ukuran (5 x 20) cm


106.000

Buah

Keramik artistik

9.300

kg

Portland Cement

0.018

m3

Pasir pasang

2.900

kg

0.900

n/a

#VALUE!
1,250.00

11,625.00

195,000.00

3,510.00

Semen warna

10,000.00

29,000.00

OH

Pekerja

60,000.00

0.450

OH

Tukang batu

70,000.00

0.045

OH

Kepala tukang

80,000.00

0.045

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
53

Memasang 1 m2 dinding keramik ukuran (10x20) cm


53.000

Buah

Keramik

870.00

46,110.00

1,250.00

11,625.00

195,000.00

3,510.00

Semen warna

10,000.00

27,500.00

OH

Pekerja

60,000.00

OH

Tukang batu

70,000.00

0.045

OH

Kepala tukang

80,000.00

0.045

OH

Mandor

90,000.00

9.300

kg

Portland Cement

0.018

Pasir pasang

2.750

kg

0.900
0.450

Jumlah

Keuntungan Maksimal

Jumlah
Dibulatkan
54

Memasang 1 m2 dinding keramik warna ukuran (20 x 20) cm


26.500

Keramik

3,360.00

89,040.00

9.300

Buah
kg

Portland Cement

1,250.00

11,625.00

0.018

PS

195,000.00

3,510.00

1.940

kg

Semen warna

10,000.00

19,400.00

0.900

OH

Pekerja

60,000.00

0.450

OH

Tukang batu

70,000.00

0.045

OH

Kepala tukang

80,000.00

0.045

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
55

Memasang 1 m2 dinding granit DN ukuran (100 x 100) cm


1.060

m2

3.003

Buah

12.440

Marmer

1,373,200.00

Paku 12 cm

n/a

#VALUE!

kg

Portland Cement

0.025

Pasir pasang

0.650

kg

Semen warna

1.300

OH

Pekerja

60,000.00

0.650

OH

Tukang batu

70,000.00

0.065

OH

Kepala tukang

80,000.00

0.065

OH

Mandor

90,000.00

1,455,592.00

1,250.00

15,550.00

195,000.00

4,875.00

10,000.00

6,500.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
56

Memasang 1 m2 dinding bata pelapis ukuran (3 x 7 x 24) cm


63.000

Buah

Bata pelapis dinding

12.440

kg

Portland Cement

0.025

m3

Pasir pasang

2.750

kg

1.000

n/a

#VALUE!
1,250.00

15,550.00

195,000.00

4,875.00

Semen warna

10,000.00

27,500.00

OH

Pekerja

60,000.00

0.500

OH

Tukang batu

70,000.00

0.050

OH

Kepala tukang

80,000.00

0.050

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
57

Memasang 1 m2 dinding batu paras


1.100

m2

Batu paras

n/a

#VALUE!

11.750

kg

Portland Cement

0.035

m3

Pasir pasang

1,250.00

14,687.50

195,000.00

6,825.00

0.700

OH

Pekerja

60,000.00

0.350

OH

Tukang batu

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.035

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
58

Memasang 1 m2 dinding batu tempel hitam


1.100

m2

Batu tempel hitam

105,000.00

115,500.00

11.750

kg

Portland Cement

0.035

m3

Pasir pasang

1,250.00

14,687.50

195,000.00

6,825.00

0.700

OH

Pekerja

60,000.00

0.350

OH

Tukang batu

70,000.00

0.035

OH

Kepala tukang

80,000.00

0.035

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
59

Memasang 1 m2 lantai Vinyl ukuran (30 x 30) cm


11.870

Buah

KL. I

Vinyl

n/a
n/a

#VALUE!

0.350

kg

Lem vinyl

0.150

OH

Pekerja

60,000.00

#VALUE!

0.150

OH

Tukang

70,000.00

0.015

OH

Kepala tukang

80,000.00

0.008

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
60

Memasang 1 m2 wall paper, lebar 50 cm


2.200

Wall paper

n/a

#VALUE!

0.250

kg

Lem

n/a

#VALUE!

0.350

OH

Pekerja

60,000.00

0.175

OH

Tukang

70,000.00

0.017

OH

Kepala tukang

80,000.00

0.002

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
61

Memasang 1 m2 floor hardener

5.000

kg

Floor hardener

0.120

OH

Pekerja

n/a
60,000.00

#VALUE!

0.120

OH

Tukang

70,000.00

0.012

OH

Kepala tukang

80,000.00

0.006

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
62

Memasang 1 m' plint Vinyl karet ukuran (15 x 30) cm dengan perekat
1.760

Buah

Vinyl karet

n/a

#VALUE!

0.080

kg

Lem vinyl

n/a

#VALUE!

0.080

OH

Pekerja

60,000.00

0.080

OH

Tukang

70,000.00

0.008

OH

Kepala tukang

80,000.00

0.004

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
63

Memasang 1 m' plint kayu kelas II tebal 2Cm, Lebar 10 Cm


0.003

m3

Papan kayu kelas II

5,950,000.00

17,850.00

0.050

kg

Paku /skrup 5 cm

17,000.00

850.00

0.120

OH

Pekerja

60,000.00

0.120

OH

Tukang kayu

70,000.00

0.012

OH

Kepala tukang

80,000.00

0.006

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

HARGA
UPAH (Rp)

JUMLAH HARGA
(Rp)

#VALUE!
12,250.00
8,775.00
15,000.00

15,000.00

8,750.00

8,750.00

1,040.00

1,040.00

1,170.00

1,170.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
12,500.00
8,775.00

15,000.00

15,000.00

8,750.00

8,750.00

1,040.00

1,040.00

1,170.00

1,170.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
13,000.00
8,775.00

16,200.00

16,200.00

9,450.00

9,450.00

1,120.00

1,120.00

1,260.00

1,260.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
12,250.00
8,775.00

13,000.00
15,000.00

15,000.00

8,750.00

8,750.00

1,040.00

1,040.00

1,170.00

1,170.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
12,500.00
8,775.00
15,000.00

15,600.00

15,600.00

9,100.00

9,100.00

1,040.00

1,040.00

1,170.00

1,170.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
13,000.00
8,775.00
16,200.00

16,200.00

16,200.00

9,450.00

9,450.00

1,120.00

1,120.00

1,260.00

1,260.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
12,250.00
8,775.00
13,000.00

15,000.00

15,000.00

8,750.00

8,750.00

1,040.00

1,040.00

1,170.00

1,170.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
26,114.00
12,500.00
8,775.00
15,000.00

15,600.00

15,600.00

9,100.00

9,100.00

1,040.00

1,040.00

1,170.00

1,170.00
89,299.00

89,299.00
89,290.00
#VALUE!
12,250.00
8,775.00
13,000.00

15,000.00

15,000.00

8,750.00

8,750.00

1,040.00

1,040.00

1,170.00

1,170.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
12,500.00
8,775.00
15,000.00

15,600.00

15,600.00

9,100.00

9,100.00

1,040.00

1,040.00

1,170.00

1,170.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
12,250.00

8,775.00
13,000.00
15,000.00

15,000.00

8,750.00

8,750.00

1,040.00

1,040.00

1,170.00

1,170.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
12,500.00
8,775.00
15,000.00

15,600.00

15,600.00

9,100.00

9,100.00

1,040.00

1,040.00

1,170.00

1,170.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
12,000.00
8,775.00
15,000.00

14,400.00

14,400.00

8,400.00

8,400.00

960.00

960.00

1,080.00

1,080.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
12,250.00
8,775.00
13,000.00

15,000.00

15,000.00

8,750.00

8,750.00

1,040.00

1,040.00

1,170.00

1,170.00

#VALUE!
-

#VALUE!
#VALUE!
#VALUE!
#VALUE!
12,500.00
8,775.00
15,000.00

15,600.00

15,600.00

9,100.00

9,100.00

1,040.00

1,040.00

1,170.00

1,170.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
2,062.50
780.00

5,400.00

5,400.00

6,300.00

6,300.00

720.00

720.00

450.00

450.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
1,550.00
585.00

5,400.00

5,400.00

6,300.00

6,300.00

720.00

720.00

450.00

450.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
1,550.00
585.00

5,400.00

5,400.00

6,300.00

6,300.00

720.00

720.00

450.00

450.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
1,425.00
585.00
1,000.00

5,400.00

5,400.00

6,300.00

6,300.00

720.00

720.00

450.00

450.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
1,425.00
585.00
1,000.00

5,400.00

5,400.00

6,300.00

6,300.00

720.00

720.00

450.00

450.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
1,425.00
585.00
1,000.00

5,400.00

5,400.00

6,300.00

6,300.00

720.00

720.00

450.00

450.00
#VALUE!

#VALUE!

#VALUE!
#VALUE!
7,766.00
1,425.00
585.00
1,000.00
5,400.00

5,400.00

6,300.00

6,300.00

720.00

720.00

450.00

450.00
23,646.00

23,646.00
23,640.00
#VALUE!
1,425.00
585.00
1,000.00

5,400.00

5,400.00

6,300.00

6,300.00

720.00

720.00

450.00

450.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
1,425.00
585.00
1,000.00

5,400.00

5,400.00

6,300.00

6,300.00

720.00

720.00

450.00

450.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
1,425.00
585.00

1,000.00
5,400.00

5,400.00

6,300.00

6,300.00

720.00

720.00

450.00

450.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
1,425.00
585.00
1,000.00

5,400.00

5,400.00

6,300.00

6,300.00

720.00

720.00

450.00

450.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
1,425.00
585.00
1,000.00

5,400.00

5,400.00

6,300.00

6,300.00

720.00

720.00

450.00

450.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
1,425.00
585.00
1,000.00

5,400.00

5,400.00

6,300.00

6,300.00

720.00

720.00

450.00

450.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
1,425.00
585.00
1,000.00

5,400.00

5,400.00

6,300.00

6,300.00

720.00

720.00

450.00

450.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
1,425.00
585.00
1,000.00

5,400.00

5,400.00

6,300.00

6,300.00

720.00

720.00

450.00

450.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
1,000.00

21,600.00

21,600.00

12,600.00

12,600.00

1,440.00

1,440.00

1,620.00

1,620.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
51,410.00
10,237.50
8,775.00
27,500.00

42,000.00

42,000.00

24,500.00

24,500.00

2,800.00

2,800.00

3,150.00

3,150.00
170,372.50

170,372.50
170,370.00
54,802.00
10,237.50
8,775.00
32,000.00

42,000.00

42,000.00

24,500.00

24,500.00

2,800.00

2,800.00

3,150.00

3,150.00
178,264.50

178,264.50
178,260.00
#VALUE!
10,237.50
8,775.00
16,200.00

42,000.00

42,000.00

24,500.00

24,500.00

2,800.00

2,800.00

3,150.00

3,150.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
99,708.00
12,500.00
8,775.00
15,000.00

42,000.00

42,000.00

24,500.00

24,500.00

2,800.00

2,800.00

3,150.00

3,150.00
208,433.00

208,433.00
208,430.00
89,040.00
13,000.00
8,775.00
16,200.00
42,000.00

42,000.00

24,500.00

24,500.00

2,800.00

2,800.00

3,150.00

3,150.00
199,465.00

199,465.00
199,460.00
#VALUE!
12,250.00
8,775.00
43,700.00

63,000.00

63,000.00

36,750.00

36,750.00

4,240.00

4,240.00

4,770.00

4,770.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
17,687.50
7,605.00
20,000.00

42,000.00

42,000.00

24,500.00

24,500.00

2,800.00

2,800.00

3,150.00

3,150.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
5,141.00
1,425.00
585.00

250.00
5,400.00

5,400.00

6,300.00

6,300.00

2,800.00

2,800.00

450.00

450.00
22,351.00

22,351.00
22,350.00
5,480.20
1,425.00
585.00
500.00

5,400.00

5,400.00

6,300.00

6,300.00

2,800.00

2,800.00

450.00

450.00
22,940.20

22,940.20
22,940.00
#VALUE!
712.50
292.50
130.00

5,400.00

5,400.00

6,300.00

6,300.00

2,800.00

2,800.00

450.00

450.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
1,425.00
585.00
1,000.00

45,000.00

45,000.00

52,500.00

52,500.00

6,000.00

6,000.00

3,420.00

3,420.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
1,455,592.00
10,237.50
8,775.00
6,500.00

42,000.00

42,000.00

24,500.00

24,500.00

2,800.00

2,800.00

3,150.00

3,150.00
1,553,554.50

1,553,554.50
1,553,550.00
#VALUE!
11,900.00

10,200.00

10,200.00

11,900.00

11,900.00

1,360.00

1,360.00

810.00

810.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
11,900.00

7,200.00

7,200.00

8,400.00

8,400.00

960.00

960.00

540.00

540.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
20,400.00

42,000.00

42,000.00

24,500.00

24,500.00

2,800.00

2,800.00

3,150.00

3,150.00

#VALUE!
-

#VALUE!
#VALUE!
#VALUE!
#VALUE!
20,400.00

42,000.00

42,000.00

24,500.00

24,500.00

2,800.00

2,800.00

3,150.00

3,150.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
44,462.00
11,625.00
3,510.00
15,000.00

60,000.00

60,000.00

35,000.00

35,000.00

4,000.00

4,000.00

4,500.00

4,500.00
178,097.00

178,097.00
178,090.00
#VALUE!
11,625.00
3,510.00
27,500.00

54,000.00

54,000.00

31,500.00

31,500.00

3,600.00

3,600.00

4,050.00

4,050.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
11,625.00
3,510.00

19,400.00
54,000.00

54,000.00

31,500.00

31,500.00

3,600.00

3,600.00

4,050.00

4,050.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
51,410.00
11,625.00
3,510.00
27,500.00

54,000.00

54,000.00

31,500.00

31,500.00

3,600.00

3,600.00

4,050.00

4,050.00
187,195.00

187,195.00
187,190.00
#VALUE!
11,625.00
3,510.00
29,000.00

54,000.00

54,000.00

31,500.00

31,500.00

3,600.00

3,600.00

4,050.00

4,050.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
46,110.00
11,625.00
3,510.00
27,500.00

54,000.00

54,000.00

31,500.00

31,500.00

3,600.00

3,600.00

4,050.00

4,050.00
181,895.00

181,895.00
181,890.00
89,040.00
11,625.00
3,510.00
19,400.00

54,000.00

54,000.00

31,500.00

31,500.00

3,600.00

3,600.00

4,050.00

4,050.00
216,725.00

216,725.00
216,720.00
1,455,592.00
#VALUE!
15,550.00
4,875.00
6,500.00

78,000.00

78,000.00

45,500.00

45,500.00

5,200.00

5,200.00

5,850.00

5,850.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
15,550.00
4,875.00
27,500.00

60,000.00

60,000.00

35,000.00

35,000.00

4,000.00

4,000.00

4,500.00

4,500.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!

14,687.50
6,825.00
42,000.00

42,000.00

24,500.00

24,500.00

2,800.00

2,800.00

3,150.00

3,150.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
115,500.00
14,687.50
6,825.00

42,000.00

42,000.00

24,500.00

24,500.00

2,800.00

2,800.00

3,150.00

3,150.00
209,462.50

209,462.50
209,460.00
#VALUE!
#VALUE!

9,000.00

9,000.00

10,500.00

10,500.00

1,200.00

1,200.00

720.00

720.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

21,000.00

21,000.00

12,250.00

12,250.00

1,360.00

1,360.00

180.00

180.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!
7,200.00

7,200.00

8,400.00

8,400.00

960.00

960.00

540.00

540.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

4,800.00

4,800.00

5,600.00

5,600.00

640.00

640.00

360.00

360.00
#VALUE!

#VALUE!
#VALUE!
#VALUE!
17,850.00
850.00

7,200.00

7,200.00

8,400.00

8,400.00

960.00

960.00

540.00

540.00
35,800.00

35,800.00
35,800.00

NO.

INDEKS

SATUAN

KEBUTUHAN

HARGA
HARGA,
SATUAN (Rp) BAHAN (Rp)
5

PEKERJAAN LANGIT-LANGIT
1

Memasang 1 m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm


1.100

m2

Asbes semen

15,000.00

16,500.000

0.010

kg

Paku tripleks

28,600.00

286.000

0.030

OH

Pekerja

60,000.00

0.070

OH

Tukang kayu

70,000.00

0.007

OH

Kepala tukang

80,000.00

0.004

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
2

Memasang 1 m2 langit-langit akustik ukuran (30 x 30) cm


12.000

Lembar

Akustik

n/a

#VALUE!

0.050

kg

Paku tripleks

28,600.00

0.120

OH

Pekerja

60,000.00

0.120

OH

Tukang kayu

70,000.00

0.012

OH

Kepala tukang

80,000.00

0.006

OH

Mandor

90,000.00

1,430.000

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
3

Memasang 1 m2 langit-langit akustik ukuran (30 x 60) cm


5.800

Lembar

0.050

kg

Akustik
Paku tripleks

n/a
28,600.00

#VALUE!

0.120

OH

Pekerja

60,000.00

0.120

OH

Tukang kayu

70,000.00

0.012

OH

Kepala tukang

80,000.00

0.006

OH

Mandor

90,000.00

1,430.000

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
4

Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm


1.500

Lembar

Akustik

90,000.00

135,000.000
1,430.000

0.050

kg

Paku tripleks

28,600.00

0.100

OH

Pekerja

60,000.00

0.100

OH

Tukang kayu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
5

Memasang 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 4 mm


0.375

Lembar

Tripleks

62,100.00

23,287.500

0.030

kg

Paku tripleks

28,600.00

858.000

0.100

OH

Pekerja

60,000.00

0.100

OH

Tukang kayu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
6

Memasang 1 m2 langit-langit lambriziring kayu, tebal 9 mm


0.015

Kayu papan

n/a

#VALUE!

0.010

kg

Paku tripleks

28,600.00

0.800

OH

Pekerja

60,000.00

0.800

OH

Tukang kayu

70,000.00

0.080

OH

Kepala tukang

80,000.00

0.040

OH

Mandor

90,000.00

286.000

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
7

Memasang 1 m2 langit-langit gypsum board DN ukuran (1200x2400x9) mm,


0.364

Lembar

Gypsum board

60,000.00

21,840.000
3,300.000

0.110

kg

Paku skrup

30,000.00

0.100

OH

Pekerja

60,000.00

0.050

OH

Tukang kayu

70,000.00

0.005

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
8

Memasang 1 m' list plafond gysum profil


1.050

m'

List gypsum profil

n/a

#VALUE!

0.150

kg

Tepung gypsum

n/a

#VALUE!

0.060

OH

Pekerja

60,000.00

0.060

OH

Tukang kayu

70,000.00

0.006

OH

Kepala tukang

80,000.00

0.003

OH

Mandor

90,000.00

Jumlah

Keuntungan Maksimal

0%

Jumlah
Dibulatkan
9

Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm + rangka alluminium


3.600

m'

Profil Alluminium "T"

n/a

#VALUE!

0.150

kg

Kawat diameter 4 mm

n/a

#VALUE!

1.050

Buah

Ramset

n/a

#VALUE!

1.500

Lembar

0.500
0.500

Akustik 60 cm x 120 cm

60,000.00

OH

Pekerja

60,000.00

OH

Tukang besi

70,000.00

0.050

OH

Kepala tukang

80,000.00

0.025

OH

Mandor

90,000.00

90,000.000

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
10

Memasang 1 m' list langit-langit kayu kamper 5 cm


1.050

m'

List kayu profil

15,000.00

15,750.000

0.010

kg

Paku

28,600.00

286.000

0.050

OH

Pekerja

60,000.00

0.050

OH

Tukang kayu

70,000.00

0.005

OH

Kepala tukang

80,000.00

0.003

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

0%

HARGA
UPAH (Rp)

JUMLAH HARGA
(Rp)

16,500.00
286.00
1,800.00

1,800.00

4,900.00

4,900.00

560.00

560.00

360.00

360.00
24,406.00

0%

24,406.00
24,400.00
#VALUE!
1,430.00

7,200.00

7,200.00

8,400.00

8,400.00

960.00

960.00

540.00

540.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
1,430.00

7,200.00

7,200.00

8,400.00

8,400.00

960.00

960.00

540.00

540.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
135,000.00
1,430.00

6,000.00

6,000.00

7,000.00

7,000.00

800.00

800.00

450.00

450.00

150,680.00
0%

150,680.00
150,680.00
23,287.50
858.00

6,000.00

6,000.00

7,000.00

7,000.00

800.00

800.00

450.00

450.00
38,395.50

0%

38,395.50
38,390.00
#VALUE!
286.00

48,000.00

48,000.00

56,000.00

56,000.00

6,400.00

6,400.00

3,600.00

3,600.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
21,840.00
3,300.00

6,000.00

6,000.00

3,500.00

3,500.00

400.00

400.00

450.00

450.00
35,490.00

0%

35,490.00
35,490.00
#VALUE!
#VALUE!

3,600.00

3,600.00

4,200.00

4,200.00

480.00

480.00

270.00

270.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
90,000.00

30,000.00

30,000.00

35,000.00

35,000.00

4,000.00

4,000.00

2,250.00

2,250.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
15,750.00
286.00

3,000.00

3,000.00

3,500.00

3,500.00

400.00

400.00

270.00

270.00
23,206.00

0%

23,206.00
23,200.00

NO.

INDEKS

SATUAN

KEBUTUHAN

HARGA
HARGA,
SATUAN (Rp) BAHAN (Rp)
5

PEKERJAAN KAYU
1

Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu kelas I
1.100

M3

Balok kayu

9,400,000.00 10,340,000.00

1.250

Kg

Paku 10 cm

17,000.00

21,250.00

1.000

Kg

Lem kayu

34,000.00

34,000.00

7.000

OH

Pekerja

60,000.00

21.000

OH

Tukang kayu

70,000.00

2.100

OH

Kepala tukang

80,000.00

0.350

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
2

Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III
1.200

M3

Balok kayu

5,670,000.00

6,804,000.00

1.250

Kg

Paku 10 cm

17,000.00

21,250.00

1.000

Kg

Lem kayu

34,000.00

34,000.00

6.000

OH

Pekerja

60,000.00

18.000

OH

Tukang kayu

70,000.00

1.800

OH

Kepala tukang

80,000.00

0.300

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
3

Membuat dan memasang 1 m2 pintu klamp standar, kayu kelas II


0.040

M3

Papan kayu

6,960,000.00

278,400.00

0.050

Kg

Paku 5 cm - 7 cm

17,000.00

850.00

0.350
1.050

OH

Pekerja

60,000.00

OH

Tukang kayu

70,000.00

0.105

OH

Kepala tukang

80,000.00

0.018

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
4

Membuat dan memasang 1 m2 pintu klamp sederhana, kayu kelas gudang sementara.
0.040

M3

Papan kayu

4,250,000.00

170,000.00

0.050

Kg

Paku 5 cm - 7 cm

17,000.00

850.00

0.350

OH

Pekerja

60,000.00

1.050

OH

Tukang kayu

70,000.00

0.105

OH

Kepala tukang

80,000.00

0.018

OH

Mandor

90,000.00

Jumlah

Keuntungan Maksimal

0%

Jumlah
Dibulatkan
5

Membuat dan memasang 1 m2 daun pintu panel, kayu kelas I


0.040

m3

Papan kayu

10,400,000.00

416,000.00

0.500

kg

Lem kayu

34,000.00

17,000.00

1.000

OH

Pekerja

60,000.00

3.000

OH

Tukang kayu

70,000.00

0.300

OH

Kepala tukang

80,000.00

0.050

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
6

Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu kelas I atau II
0.024

m3

Papan kayu

6,960,000.00

167,040.00

0.300

kg

0.800

OH

Lem kayu

34,000.00

10,200.00

Pekerja

60,000.00

2.400

OH

Tukang kayu

70,000.00

0.240

OH

Kepala tukang

80,000.00

0.040

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
7

Membuat dan memasang 1 m2 pintu dan jendela jalusi kayu kelas I atau II
0.064

m3

Papan kayu

6,960,000.00

445,440.00

0.500

kg

Lem kayu

34,000.00

17,000.00

1.000
3.000

OH

Pekerja

60,000.00

OH

Tukang kayu

70,000.00

0.300

OH

Kepala tukang

80,000.00

0.050

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
8

Membuat 1 m2 daun pintu kayu lapis (teakwood) rangkap, rangka tertutup kayu kelas II (lebar samp
0.025

m3

Papan kayu

6,960,000.00

174,000.00

0.030

kg

Paku 1 cm - 2,5 cm

28,600.00

858.00

0.500

kg

34,000.00

17,000.00

80,000.00

80,000.00

OH

Lem kayu
Teakwood tebal 4 mm Ukuran (90 x 220)
cm
Pekerja

1.000

Lembar

0.700
2.100

OH

Tukang kayu

70,000.00

0.210

OH

Kepala tukang

80,000.00

0.035

OH

Mandor

90,000.00

60,000.00

Jumlah
Keuntungan Maksimal
Jumlah

0%

Dibulatkan
9

Membuat 1 m2 pintu Teakwood rangkap, rangka expose kayu kelas I atau II


0.026

m3

Papan kayu

10,400,000.00

266,240.00

0.030

kg

Paku 1 cm - 2,5 cm

28,600.00

858.00

0.500

kg

1.000

Lembar

34,000.00

17,000.00

80,000.00

80,000.00

OH

Lem kayu
Teakwood tebal 4 mm Ukuran (90 x 220)
cm
Pekerja

0.800
2.400

OH

Tukang kayu

70,000.00

0.240

OH

Kepala tukang

80,000.00

0.040

OH

Mandor

90,000.00

60,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
10

Memasang 1 m2jalusi kusen, kayu kelas I atau II


0.060

m3

Papan kayu

10,400,000.00

624,000.00

0.150

kg

0.670

OH

Paku 1 cm - 2,5 cm

28,600.00

4,290.00

Pekerja

60,000.00

2.000

OH

Tukang kayu

70,000.00

0.200

OH

Kepala tukang

80,000.00

0.335

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
11

Memasang 1 m2teakwood rangkap, rangka expose kayu kelas I


0.025

m3

Papan kayu

10,400,000.00

260,000.00

0.030

kg

Paku 1 cm - 2,5 cm

28,600.00

858.00

0.300

kg

1.000

Lembar

34,000.00

10,200.00

80,000.00

80,000.00

OH

Lem kayu
Teakwood tebal 4 mm ukuran (90 x 220)
cm
Pekerja

0.800
2.400

OH

Tukang kayu

70,000.00

0.240

OH

Kepala tukang

80,000.00

0.040

OH

Mandor

90,000.00

60,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
12

Memasang 1 m2 teakwood rangkap lapis formika, rangka expose kayu kelas I


0.025

m3

Papan kayu

10,400,000.00

260,000.00

0.030

kg

Paku 1 cm - 2,5 cm

28,600.00

858.00

0.800

kg

34,000.00

27,200.00

1.000

Lembar

80,000.00

80,000.00

0.500

Lembar

Lem kayu
Teakwood tebal 4 mm ukuran (90 x 220)
cm
Formika

132,000.00

66,000.00

0.850

OH

Pekerja

60,000.00

2.550

OH

Tukang kayu

70,000.00

0.255

OH

Kepala tukang

80,000.00

0.043

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
13

Memasang 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan bentang 6 meter


1.100

m3

Balok kayu (kamper banjar)

5,670,000.00

6,237,000.00

15.000

kg

Besi strip tebal 5 mm

12,000.00

180,000.00

5.600

kg

Paku 12 cm

17,000.00

95,200.00

4.000

OH

Pekerja

60,000.00

12.000

OH

Tukang kayu

70,000.00

1.200

OH

Kepala tukang

80,000.00

0.200

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
14

Memasang 1 m3 konstruksi kuda-kuda expose, kayu kelas I


1.200

m3

Balok kayu (kamper samarinda)

9,400,000.00 11,280,000.00

15.000

kg

Besi strip tebal 5 mm

12,000.00

180,000.00

5.600

kg

Paku 12 cm

17,000.00

95,200.00

6.700

OH

Pekerja

60,000.00

20.100

OH

Tukang kayu

70,000.00

2.010

OH

Kepala tukang

80,000.00

0.335

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
15

Memasang 1 m3 konstruksi gordeng, kayu kelas II


1.100

m3

Balok kayu (kamper banjar)

5,670,000.00

6,237,000.00

15.000

kg

Besi strip tebal 5 mm

12,000.00

180,000.00

3.000

kg

Paku 12 cm

17,000.00

51,000.00

6.700

OH

Pekerja

60,000.00

20.100

OH

Tukang kayu

70,000.00

2.010

OH

Kepala tukang

80,000.00

0.335

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
16

Memasang 1 m2 rangka atap genteng keramik, kayu kelas II


0.014

m3

Kaso-kaso (5 x 7) cm

5,450,000.00

76,300.00

0.036

Reng (2 x 3) cm

6,666,666.67

240,000.00

0.250

kg

Paku 5 cm dan 10 cm

17,000.00

4,250.00

0.100

OH

Pekerja

60,000.00

0.100

OH

Tukang kayu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
17

Memasang 1 m2 rangka atap genteng beton, kayu kelas II


0.014

m3

Kaso-kaso (5 x 7) cm

5,450,000.00

76,300.00

0.057

Reng (3 x 4) cm

6,666,666.67

380,000.00

0.250

kg

Paku 5 cm dan 10 cm

17,000.00

4,250.00

0.100

OH

Pekerja

60,000.00

0.100

OH

Tukang kayu

70,000.00

0.010

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
18

Memasang 1 m2 rangka atap sirap, kayu kelas II


0.014

m3

Kayu kelas II

5,450,000.00

76,300.00

0.057

kg

Paku 5 cm sampai 10 cm

17,000.00

969.00

0.120

OH

Pekerja

60,000.00

0.120

OH

Tukang kayu

70,000.00

0.012

OH

Kepala tukang

80,000.00

0.006

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
19

Memasang 1 m2 rangka langit-langit

(50x100) cm, kayu kelas II atau III

0.015

4,250,000.00

65,450.00

0.200

kg

Paku 7 cm - 10 cm

17,000.00

3,400.00

0.150

OH

Pekerja

60,000.00

0.300

OH

Tukang kayu

70,000.00

0.030

OH

Kepala tukang

80,000.00

0.075

OH

Mandor

90,000.00

Kaso-kaso (5 x 7) cm

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
20

Memasang 1 m2 rangka langit-langit


0.016

(60 x 60) cm, kayu kelas II atau III

Kaso-kaso (5 x 7) cm

4,250,000.00

69,275.00
4,250.00

0.250

kg

Paku 7 cm- 10 cm

17,000.00

0.200

OH

Pekerja

60,000.00

0.300

OH

Tukang kayu

70,000.00

0.030

OH

Kepala tukang

80,000.00

0.010

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah

0%

Dibulatkan
21

Memasang 1 m1

lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II

0.011

0.100

kg

0.100
0.200

Papan kayu

6,960,000.00

75,168.00

Paku 5 cm dan 7 cm

17,000.00

1,700.00

OH

Pekerja

60,000.00

OH

Tukang kayu

70,000.00

0.020

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
22

Memasang 1 m1

lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II

0.011

m3

Papan kayu

6,960,000.00

76,560.00

0.050

kg

Paku 5 cm dan 7 cm

17,000.00

850.00

0.100

OH

Pekerja

60,000.00

0.200

OH

Tukang kayu

70,000.00

0.020

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
23

Memasang 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas II atau


0.028

m3

Balok kayu

5,450,000.00

152,600.00

0.150

kg

Paku 5 cm dan 7 cm

17,000.00

2,550.00

0.150

OH

Pekerja

60,000.00

0.450

OH

Tukang kayu

70,000.00

0.045

OH

Kepala tukang

80,000.00

0.008

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
24

Memasang 1 m2 dinding pemisah teakwood rangkap, rangka kayu kelas II


0.028

m3

Balok kayu, Ukuran (6x 12) cm

5,450,000.00

0.150

kg

0.860

Lembar

0.560

kg

Paku 5 cm dan 10 cm
Teakwood t= 4 mm, Ukuran 120 cm x 240
cm
Lem kayu

0.150

OH

Pekerja

60,000.00

0.450

OH

Tukang kayu

70,000.00

0.045

OH

Kepala tukang

80,000.00

0.008

OH

Mandor

90,000.00

152,600.00

17,000.00

2,550.00

107,000.00

92,020.00

34,000.00

19,040.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
25

Memasang 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II

0%

0.028

m3

Balok kayu, ukuran (6x12) cm

0.150

kg

Paku 5 cm dan 10 cm

5,450,000.00

152,600.00

17,000.00

2,550.00

0.860

Lembar

0.560

kg

Lem kayu

34,000.00

0.200

OH

Pekerja

60,000.00

0.600

OH

Tukang kayu

70,000.00

0.060

OH

Kepala tukang

80,000.00

0.010

OH

Mandor

90,000.00

Plywood t=4 mm, ukuran 120 cm x 240 cm n/a

#VALUE!
19,040.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
26

Memasang 1 m2 dinding lambriziring dari papan kayu kelas I


0.007

m3

Papan kayu

10,400,000.00

72,800.00

0.100

kg

Paku 5 cm dan 10 cm

17,000.00

1,700.00

0.150

kg

Paku skrup 10 cm

30,000.00

4,500.00

0.600

OH

Pekerja

60,000.00

1.800

OH

Tukang kayu

70,000.00

0.180

OH

Kepala tukang

80,000.00

0.030

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
27

Memasang 1 m2 dinding lambriziring dari teakwood ukuran (120 x 240) cm


0.400

Lembar

Teakwood tebal 4 mm

107,000.00

42,800.00

0.050

kg

Paku 1 cm dan 2,5 cm

28,600.00

1,430.00

0.025

OH

Pekerja

60,000.00

0.075

OH

Tukang kayu

70,000.00

0.008

OH

Kepala tukang

80,000.00

0.001

OH

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
28

Memasang 1 m2 dinding bilik, rangka kayu kelas III atau IV


1.500

m2

Bilik bambu

0.014

m3

Kaso-kaso (5 x 7) cm

0.012

kg

Paku

0.003

List kayu 2/4

0.100

OH

Pekerja

60,000.00

0.050

OH

Tukang kayu

70,000.00

0.005

OH

Kepala tukang

80,000.00

0.005

OH

Mandor

90,000.00

18,000.00

27,000.00

1,500,000.00

21,000.00

17,000.00

204.00

2,400,000.00

7,200.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

0%

HARGA
UPAH (Rp)

JUMLAH HARGA
(Rp)

10,340,000.00
21,250.00
34,000.00
420,000.00

420,000.00

1,470,000.00

1,470,000.00

168,000.00

168,000.00

31,500.00

31,500.00
12,484,750.00

0%

0.00
12,484,750.00
12,484,750.00
6,804,000.00
21,250.00
34,000.00

360,000.00

360,000.00

1,260,000.00

1,260,000.00

144,000.00

144,000.00

27,000.00

27,000.00
8,650,250.00

0%

8,650,250.00
8,650,250.00
278,400.00
850.00

21,000.00

21,000.00

73,500.00

73,500.00

8,400.00

8,400.00

1,620.00

1,620.00
9,034,020.00

0%

9,034,020.00
9,034,020.00
170,000.00
850.00

21,000.00

21,000.00

73,500.00

73,500.00

8,400.00

8,400.00

1,620.00

1,620.00
275,370.00

0%

275,370.00
275,370.00
416,000.00
17,000.00

60,000.00

60,000.00

210,000.00

210,000.00

24,000.00

24,000.00

4,500.00

4,500.00
731,500.00

0%

731,500.00
731,500.00
167,040.00
10,200.00

48,000.00

48,000.00

168,000.00

168,000.00

19,200.00

19,200.00

3,600.00

3,600.00
416,040.00

0%

416,040.00
416,040.00
445,440.00
17,000.00

60,000.00

60,000.00

210,000.00

210,000.00

24,000.00

24,000.00

4,500.00

4,500.00
760,940.00

0%

760,940.00
760,940.00

yu kelas II (lebar sampai 90 cm)


174,000.00
858.00
17,000.00
80,000.00
42,000.00

42,000.00

147,000.00

147,000.00

16,800.00

16,800.00

3,150.00

3,150.00
480,808.00

0%

480,808.00

480,800.00
266,240.00
858.00
17,000.00
80,000.00
48,000.00

48,000.00

168,000.00

168,000.00

19,200.00

19,200.00

3,600.00

3,600.00
602,898.00

0%

602,898.00
602,890.00
624,000.00
4,290.00

40,200.00

40,200.00

140,000.00

140,000.00

16,000.00

16,000.00

30,150.00

30,150.00
854,640.00

0%

854,640.00
854,640.00
260,000.00
858.00
10,200.00
80,000.00

48,000.00

48,000.00

168,000.00

168,000.00

19,200.00

19,200.00

3,600.00

3,600.00
589,858.00

0%

589,858.00
589,850.00
260,000.00
858.00
27,200.00
80,000.00
66,000.00

51,000.00

51,000.00

178,500.00

178,500.00

20,400.00

20,400.00

3,870.00

3,870.00

687,828.00
0%

687,828.00
687,820.00

ng 6 meter
6,237,000.00
180,000.00
95,200.00
240,000.00

240,000.00

840,000.00

840,000.00

96,000.00

96,000.00

18,000.00

18,000.00
7,706,200.00

0%

7,706,200.00
7,706,200.00
11,280,000.00
180,000.00
95,200.00

402,000.00

402,000.00

1,407,000.00

1,407,000.00

160,800.00

160,800.00

30,150.00

30,150.00
13,555,150.00

0%

13,555,150.00
13,555,150.00
6,237,000.00
180,000.00
51,000.00

402,000.00

402,000.00

1,407,000.00

1,407,000.00

160,800.00

160,800.00

30,150.00

30,150.00
8,467,950.00

0%

8,467,950.00
8,467,950.00
76,300.00
240,000.00
4,250.00

6,000.00

6,000.00

7,000.00

7,000.00

800.00

800.00

450.00

450.00

334,800.00
0%

334,800.00
334,800.00
76,300.00
380,000.00
4,250.00

6,000.00

6,000.00

7,000.00

7,000.00

800.00

800.00

450.00

450.00
474,800.00

0%

474,800.00
474,800.00
76,300.00
969.00

7,200.00

7,200.00

8,400.00

8,400.00

960.00

960.00

540.00

540.00
94,369.00

0%

94,369.00
94,360.00
65,450.00
3,400.00

9,000.00

9,000.00

21,000.00

21,000.00

2,400.00

2,400.00

6,750.00

6,750.00
108,000.00

0%

108,000.00
108,000.00
69,275.00
4,250.00

12,000.00

12,000.00

21,000.00

21,000.00

2,400.00

2,400.00

900.00

900.00
109,825.00

0%

109,825.00

109,820.00
75,168.00
1,700.00
6,000.00

6,000.00

14,000.00

14,000.00

1,600.00

1,600.00

450.00

450.00
98,918.00

0%

98,918.00
98,910.00
76,560.00
850.00

6,000.00

6,000.00

14,000.00

14,000.00

1,600.00

1,600.00

450.00

450.00
99,460.00

0%

99,460.00
99,460.00
152,600.00
2,550.00

9,000.00

9,000.00

31,500.00

31,500.00

3,600.00

3,600.00

720.00

720.00
199,970.00

0%

199,970.00
199,970.00
152,600.00
2,550.00
92,020.00
19,040.00

9,000.00

9,000.00

31,500.00

31,500.00

3,600.00

3,600.00

720.00

720.00
311,030.00

0%

311,030.00
311,030.00

152,600.00
2,550.00
#VALUE!
19,040.00
12,000.00

12,000.00

42,000.00

42,000.00

4,800.00

4,800.00

900.00

900.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
72,800.00
1,700.00
4,500.00

36,000.00

36,000.00

126,000.00

126,000.00

14,400.00

14,400.00

2,700.00

2,700.00
258,100.00

0%

258,100.00
258,100.00
42,800.00
1,430.00

1,500.00

1,500.00

5,250.00

5,250.00

640.00

640.00

90.00

90.00
51,710.00

0%

51,710.00
51,710.00
27,000.00
21,000.00
204.00
7,200.00

6,000.00

6,000.00

3,500.00

3,500.00

400.00

400.00

450.00

450.00
65,754.00

0%

65,754.00
65,750.00

NO

INDEKS

SATUAN

KEBUTUHAN

HARGA
HARGA,
SATUAN (Rp) BAHAN (Rp)
5

PEKERJAAN PENUTUP ATAP


1

1 m Pasang atap genteng palentong kecil


25.000

bh

Genteng palentong kecil

960.00

0.150

Oh

Pekerja

60,000.00

0.075

Oh

Tukang kayu

70,000.00

0.008

Oh

Kepala tukang

80,000.00

0.008

Oh

Mandor

90,000.00

24,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
2

1 m Pasang atap genteng kodok / glazzur


25.000

bh

Atap genteng kodok

0.150

Oh

Pekerja

n/a
60,000.00

#VALUE!

0.075

Oh

Tukang kayu

70,000.00

0.008

Oh

Kepala tukang

80,000.00

0.008

Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
3

1 m Pasang atap genteng palentong besar/ super


12.000

bh

Genteng palentong kecil

1,100.00

0.150

Oh

Pekerja

60,000.00

0.075

Oh

Tukang kayu

70,000.00

0.008

Oh

Kepala tukang

80,000.00

0.008

Oh

Mandor

90,000.00

13,200.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
4

1 m' Pasang bubung genteng palentong kecil


5.000

bh

Genteng bubung

4,000.00

20,000.00

8.000

kg

Semen portland

1,250.00

10,000.00

0.032

kg

Pasir pasang

195,000.00

6,240.00

0.400

Oh

Pekerja

60,000.00

0.200

Oh

Tukang kayu

70,000.00

0.020

Oh

Kepala tukang

80,000.00

0.002

Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
5

1 m' Pasang bubung genteng kodok glazuur


5.000

bh

Genteng bubung

n/a

#VALUE!

8.000

kg

Semen portland

0.032

kg

Pasir pasang

0.400

Oh

Pekerja

60,000.00

0.200

Oh

Tukang kayu

70,000.00

0.020

Oh

Kepala tukang

80,000.00

0.002

Oh

Mandor

90,000.00

1,250.00

10,000.00

195,000.00

6,240.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
6

1 m' Pasang bubung genteng palentong besar


4.000

bh

Genteng bubung

4,200.00

16,800.00

8.000

kg

Semen portland

0.032

kg

Pasir pasang

1,250.00

10,000.00

195,000.00

6,240.00

0.400

Oh

Pekerja

60,000.00

0.200

Oh

Tukang kayu

70,000.00

0.020

Oh

Kepala tukang

80,000.00

0.002

Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
7

1 m Pasang roof light fibreglass uk. 180 cm x 90 cm


0.600

lbr

Rooflight fibreglass uk. 1,8 x 0,9 (m)

n/a

#VALUE!

0.050

kg

Paku berbagai ukuran (1/2" - 1")

17,000.00

0.140

Oh

Pekerja

60,000.00

0.067

Oh

Tukang kayu

70,000.00

0.007

Oh

Kepala tukang

80,000.00

0.007

Oh

Mandor

90,000.00

850.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
8

1 m Pasang atap asbes gelombang uk. 2.500 mm x 920 mm, tebal 5 mm


0.500

lbr

Atap asbes gelombang uk. 2,50 x 0,92 (m) t=5

0.120

kg

Paku asbes

30,000.00

0.140

Oh

Pekerja

60,000.00

0.075

Oh

Tukang kayu

70,000.00

0.008

Oh

Kepala tukang

80,000.00

0.008

Oh

Mandor

90,000.00

Jumlah

n/a

#VALUE!
3,600.00

Keuntungan Maksimal

Jumlah
Dibulatkan
9

1 m Pasang atap asbes gelombang uk. 2.250 mm x 920 mm, tebal 5 mm


0.600

lbr

Atap asbes gelombang uk. 2,25 x 0,92 (m) t=5

0.120

kg

Paku asbes

n/a
30,000.00

#VALUE!

0.140

Oh

Pekerja

60,000.00

0.075

Oh

Tukang kayu

70,000.00

0.008

Oh

Kepala tukang

80,000.00

0.008

Oh

Mandor

90,000.00

3,600.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
10

1 m Pasang atap asbes gelombang uk. 2.000 mm x 920 mm, tebal 5 mm


0.600

lbr

Atap asbes gelombang uk. 2,00 x 0,92 (m) tebal

n/a

#VALUE!

0.120

kg

Paku asbes

30,000.00

0.140

Oh

Pekerja

60,000.00

0.075

Oh

Tukang kayu

70,000.00

0.008

Oh

Kepala tukang

80,000.00

0.008

Oh

Mandor

90,000.00

3,600.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
11

1 m Pasang atap asbes gelombang uk. 1.800 mm x 920 mm, tebal 5 mm


0.750

lbr

Atap asbes gelombang uk. 1,80 x 0,92 (m) tebal

49,000.00

36,750.00

0.120

kg

Paku asbes

30,000.00

3,600.00

0.140

Oh

Pekerja

60,000.00

0.070

Oh

Tukang kayu

70,000.00

0.007

Oh

Kepala tukang

80,000.00

0.007

Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
12

1 m Pasang atap asbes gelombang uk. 3.000 mm x 1.050 mm, tebal 4 mm


0.350

lbr

Atap asbes gelombang uk. 3,00 x 1,05 (m) tebal

n/a

#VALUE!

0.120

kg

Paku asbes

30,000.00

0.140

Oh

Pekerja

60,000.00

0.070

Oh

Tukang kayu

70,000.00

0.007

Oh

Kepala tukang

80,000.00

0.007

Oh

Mandor

90,000.00

3,600.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
13

1 m Pasang atap asbes gelombang uk. 2.700 mm x 1.050 mm, tebal 4 mm


0.420

lbr

Atap asbes gelombang uk. 2,70 x 1,05 (m) tebal

n/a

#VALUE!

0.120

kg

Paku asbes

30,000.00

0.140

Oh

Pekerja

60,000.00

0.070

Oh

Tukang kayu

70,000.00

0.007

Oh

Kepala tukang

80,000.00

0.007

Oh

Mandor

90,000.00

3,600.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
14

1 m Pasang atap asbes gelombang uk. 2.400 mm x 1.050 mm, tebal 4 mm


0.440

lbr

Atap asbes gelombang uk. 2,40 x 1,05 (m) tebal

n/a

#VALUE!

0.120

kg

Paku asbes

30,000.00

0.140

Oh

Pekerja

60,000.00

0.070

Oh

Tukang kayu

70,000.00

0.007

Oh

Kepala tukang

80,000.00

0.007

Oh

Mandor

90,000.00

3,600.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
15

1 m Pasang atap asbes gelombang uk. 2.100 mm x 1.050 mm, tebal 4 mm


0.510

lbr

Atap asbes gelombang uk. 2,10 x 1,05 (m) tebal

n/a

#VALUE!

0.120

kg

Paku asbes

30,000.00

0.140

Oh

Pekerja

60,000.00

0.070

Oh

Tukang kayu

70,000.00

0.007

Oh

Kepala tukang

80,000.00

0.007

Oh

Mandor

90,000.00

3,600.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
16

1 m Pasang atap asbes gelombang uk. 1.500 mm x 1.050 mm, tebal 4 mm


0.800

lbr

Atap asbes gelombang uk. 1,50 x 1,05 (m) tebal

0.120

kg

Paku asbes

n/a
30,000.00

#VALUE!

0.140

Oh

Pekerja

60,000.00

0.070

Oh

Tukang kayu

70,000.00

0.007

Oh

Kepala tukang

80,000.00

0.007

Oh

Mandor

90,000.00

3,600.00

Jumlah
Keuntungan Maksimal
Jumlah

Dibulatkan
17

1 m Pasang atap asbes gelombang uk. 3.000 mm x 1.080 mm, tebal 6 mm


0.370

lbr

Atap asbes gelombang uk. 3,00 x 1,08 (m) tebal

n/a

#VALUE!

0.120

kg

Paku asbes

30,000.00

0.140

Oh

Pekerja

60,000.00

0.070

Oh

Tukang kayu

70,000.00

0.007

Oh

Kepala tukang

80,000.00

0.007

Oh

Mandor

90,000.00

3,600.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
18

1 m Pasang atap asbes gelombang uk. 2.700 mm x 1.080 mm, tebal 6 mm


0.380

lbr

Atap asbes gelombang uk. 2,70 x 1,08 (m) tebal

n/a

#VALUE!

0.120

kg

Paku asbes

30,000.00

0.140

Oh

Pekerja

60,000.00

0.070

Oh

Tukang kayu

70,000.00

0.007

Oh

Kepala tukang

80,000.00

0.007

Oh

Mandor

90,000.00

3,600.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
19

1 m Pasang atap asbes gelombang uk. 2.400 mm x 1.080 mm, tebal 6 mm


0.460

lbr

Atap asbes gelombang uk. 2,40 x 1,08 (m) tebal

0.120

kg

Paku asbes

n/a
30,000.00

#VALUE!

0.140

Oh

Pekerja

60,000.00

0.070

Oh

Tukang kayu

70,000.00

0.007

Oh

Kepala tukang

80,000.00

0.007

Oh

Mandor

90,000.00

3,600.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
20

1 m Pasang atap asbes gelombang uk. 2.100 mm x 1.080 mm, tebal 6 mm


0.490

lbr

Atap asbes gelombang uk. 2,10 x 1,08 (m) tebal

n/a

#VALUE!

0.120

kg

Paku asbes

30,000.00

0.140

Oh

Pekerja

60,000.00

0.070

Oh

Tukang kayu

70,000.00

0.007

Oh

Kepala tukang

80,000.00

0.007

Oh

Mandor

90,000.00

3,600.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

21

1 m Pasang atap asbes gelombang uk. 1.800 mm x 1.080 mm, tebal 6 mm


0.570

lbr

Atap asbes gelombang uk. 1,80 x 1,08 (m) tebal

n/a

#VALUE!

0.120

kg

Paku asbes

30,000.00

0.140

Oh

Pekerja

60,000.00

0.070

Oh

Tukang kayu

70,000.00

0.007

Oh

Kepala tukang

80,000.00

0.007

Oh

Mandor

90,000.00

3,600.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
22

1 m' Bubung stel gelombang 0,92 m


2.400

lbr

Bubung stel gelombang 92 cm

n/a

#VALUE!

6.000

bh

Paku skrup 3,5"

n/a

#VALUE!

0.084

Oh

Pekerja

60,000.00

0.125

Oh

Tukang kayu

70,000.00

0.013

Oh

Kepala tukang

80,000.00

0.004

Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
23

1 m' Bubung stel gelombang 1,05 m


2.100

lbr

Bubung stel gelombang 105 cm

n/a

#VALUE!

6.000

bh

Paku skrup 3,5"

n/a

0.084

Oh

Pekerja

60,000.00

0.125

Oh

Tukang kayu

70,000.00

0.013

Oh

Kepala tukang

80,000.00

0.004

Oh

Mandor

90,000.00

#VALUE!

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
24

1 m' Bubung stel gelombang 1,08 m


2.050

lbr

Bubung stel gelombang 108 cm

n/a

#VALUE!

6.000

bh

Paku skrup 3,5"

n/a

#VALUE!

0.084

Oh

Pekerja

60,000.00

0.125

Oh

Tukang kayu

70,000.00

0.013

Oh

Kepala tukang

80,000.00

0.004

Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
25

1 m' Bubung nok paten 0,92 m

1.200

lbr

Nok paten 92 cm

n/a

#VALUE!

6.000

bh

Paku skrup 3,5"

n/a

#VALUE!

0.084

Oh

Pekerja

60,000.00

0.125

Oh

Tukang kayu

70,000.00

0.013

Oh

Kepala tukang

80,000.00

0.004

Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
26

1 m' Bubung nok paten 1,05 m


1.200

lbr

Nok paten 105 cm

n/a

#VALUE!

6.000

bh

Paku skrup 3,5"

n/a

0.084

Oh

Pekerja

60,000.00

0.125

Oh

Tukang kayu

70,000.00

0.013

Oh

Kepala tukang

80,000.00

0.004

Oh

Mandor

90,000.00

#VALUE!

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
27

1 m' Bubung nok paten 1,08 m


1.200

lbr

Nok paten 108 cm

n/a

#VALUE!

6.000

bh

Paku skrup 3,5"

n/a

#VALUE!

0.084

Oh

Pekerja

60,000.00

0.125

Oh

Tukang kayu

70,000.00

0.013

Oh

Kepala tukang

80,000.00

0.004

Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
28

1 m' Nok stel rata 0,92 m


1.100

lbr

Nok paten 92 cm

n/a

#VALUE!

6.000

bh

Paku skrup 3,5"

n/a

#VALUE!

0.100

Oh

Pekerja

60,000.00

0.150

Oh

Tukang kayu

70,000.00

0.013

Oh

Kepala tukang

80,000.00

0.004

Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
29

1 m' Nok stel rata 1,05 m


1.100

lbr

Nok paten 105 cm

n/a

#VALUE!

6.000

bh

Paku skrup 3,5"

0.100

Oh

Pekerja

n/a
60,000.00

#VALUE!

0.150

Oh

Tukang kayu

70,000.00

0.013

Oh

Kepala tukang

80,000.00

0.004

Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
30

1 m Pasang genteng beton


11.000

bh

Genteng beton

62,000.00

682,000.00

0.030

kg

Paku biasa

17,000.00

510.00

0.200

Oh

Pekerja

60,000.00

0.100

Oh

Tukang kayu

70,000.00

0.010

Oh

Kepala tukang

80,000.00

0.010

Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
31

1 m Pasang genteng aspal


6.900

bh

Genteng aspal

n/a

#VALUE!

0.350

lbr

Plywood 6 mm

0.030

kg

Paku biasa - 1"

0.500

bh

Plastic Aerator

0.200

Oh

Pekerja

60,000.00

0.300

Oh

Tukang kayu

70,000.00

0.030

Oh

Kepala tukang

80,000.00

0.500

Oh

Mandor

90,000.00

17,000.00
n/a

510.00
#VALUE!

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
32

1 m Pasang genteng metal


1.020

bh

Genteng metal

n/a

#VALUE!

0.200

kg

Paku biasa - 1"

17,000.00

0.200

Oh

Pekerja

60,000.00

0.100

Oh

Tukang kayu

70,000.00

0.010

Oh

Kepala tukang

80,000.00

0.010

Oh

Mandor

90,000.00

3,400.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan
33

1 m Pasang atap sirap kayu

30.000

bh

Sirap kayu

1,100.00

33,000.00

0.200

kg

Paku biasa - 1"

17,000.00

3,400.00

0.166

Oh

Pekerja

60,000.00

0.250

Oh

Tukang kayu

70,000.00

0.025

Oh

Kepala tukang

80,000.00

0.008

Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
34

1 m' Pasang nok genteng beton


3.500

bh

Nok genteng beton

0.050

kg

Paku biasa - 1"

10.800

kg

Semen portland

0.032

m3

Pasir pasang

1.000

kg

0.166
0.250

6,000.00

21,000.00

17,000.00

850.00

1,250.00

13,500.00

195,000.00

6,240.00

Semen warna

10,000.00

10,000.00

Oh

Pekerja

60,000.00

Oh

Tukang kayu

70,000.00

0.025

Oh

Kepala tukang

80,000.00

0.008

Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
35

1 m' Pasang nok genteng aspal


2.000

bh

Nok genteng aspal

n/a

#VALUE!

0.050

kg

Paku biasa - 1"

0.004

m3

Kayu balok borneo

0.125

Oh

Pekerja

60,000.00

0.250

Oh

Tukang kayu

70,000.00

0.025

Oh

Kepala tukang

80,000.00

0.008

Oh

Mandor

90,000.00

17,000.00

850.00

4,250,000.00

14,875.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
36

1 m' Pasang nok genteng metal


1.100

bh

Nok genteng metal

n/a

#VALUE!

0.050

kg

Paku biasa - 1"

17,000.00

0.250

Oh

Pekerja

60,000.00

0.150

Oh

Tukang kayu

70,000.00

0.015

Oh

Kepala tukang

80,000.00

0.013

Oh

Mandor

90,000.00

850.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
37

1 m' Pasang nok sirap


0.400

lbr

Seng plat 3 x 6"

29,000.00

11,600.00

0.050

kg

Paku biasa - 1"

17,000.00

850.00

0.050

kg

Paku biasa 2 - 5"

17,000.00

850.00

0.125

Oh

Pekerja

60,000.00

0.250

Oh

Tukang kayu

70,000.00

0.025

Oh

Kepala tukang

80,000.00

0.008

Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
38

1 m Pasang atap seng gelombang


0.700

lbr

Seng gelombang 3" x 6"

29,000.00

20,300.00

0.020

kg

Paku biasa - 1"

17,000.00

340.00

0.120

Oh

Pekerja

60,000.00

0.060

Oh

Tukang kayu

70,000.00

0.006

Oh

Kepala tukang

80,000.00

0.006

Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
39

1 m' Pasang nok atap seng


0.300

lbr

Seng plat 3" x 6" BJLS

29,000.00

8,700.00

0.020

kg

Paku biasa - 1"

17,000.00

340.00

0.150

Oh

Pekerja

60,000.00

0.070

Oh

Tukang kayu

70,000.00

0.007

Oh

Kepala tukang

80,000.00

0.006

Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
40

1 m Pasang atap aluminium


1.050

lbr

Aluminium gelombang t=0,55

n/a

#VALUE!

0.020

kg

Paku hak panjang 15 cm

n/a

#VALUE!

0.150

Oh

Pekerja

60,000.00

0.750

Oh

Tukang kayu

70,000.00

0.080

Oh

Kepala tukang

80,000.00

0.006

Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
41

1 m' Pasang nok aluminium


1.200

bh

Nok standar 40 x 18

n/a

#VALUE!

0.040

kg

Paku hak panjang 15 cm

n/a

0.100

Oh

Pekerja

60,000.00

1.000

Oh

Tukang kayu

70,000.00

0.100

Oh

Kepala tukang

80,000.00

0.050

Oh

Mandor

90,000.00

#VALUE!

Jumlah
Keuntungan Maksimal

Jumlah
Dibulatkan
42

1 m Pasang aluminium foil/ sisalation


1.050

m2

Aluminium foil

n/a

#VALUE!

0.150

Oh

Pekerja

60,000.00

0.050

Oh

Tukang kayu

70,000.00

0.005

Oh

Kepala tukang

80,000.00

0.008

Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

HARGA
UPAH (Rp)

JUMLAH HARGA
(Rp)

24,000.00
9,000.00

9,000.00

5,250.00

5,250.00

640.00

640.00

720.00

720.00
39,610.00

0%

0.00
39,610.00
39,610.00
#VALUE!

9,000.00

9,000.00

5,250.00

5,250.00

640.00

640.00

720.00

720.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
13,200.00

9,000.00

9,000.00

5,250.00

5,250.00

640.00

640.00

720.00

720.00
28,810.00

0%

0.00
28,810.00
28,810.00
20,000.00
10,000.00
6,240.00

24,000.00

24,000.00

14,000.00

14,000.00

1,600.00

1,600.00

180.00

180.00
76,020.00

0%

0.00

76,020.00
76,020.00
#VALUE!
10,000.00
6,240.00
24,000.00

24,000.00

14,000.00

14,000.00

1,600.00

1,600.00

180.00

180.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
16,800.00
10,000.00
6,240.00

24,000.00

24,000.00

14,000.00

14,000.00

1,600.00

1,600.00

180.00

180.00
72,820.00

0%

0.00
72,820.00
72,820.00
#VALUE!
850.00

8,400.00

8,400.00

4,690.00

4,690.00

560.00

560.00

630.00

630.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
3,600.00

8,400.00

8,400.00

5,250.00

5,250.00

640.00

640.00

720.00

720.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
3,600.00

8,400.00

8,400.00

5,250.00

5,250.00

640.00

640.00

720.00

720.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
3,600.00

8,400.00

8,400.00

5,250.00

5,250.00

640.00

640.00

720.00

720.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
36,750.00
3,600.00

8,400.00

8,400.00

4,900.00

4,900.00

560.00

560.00

630.00

630.00
54,840.00

0%

0.00
54,840.00
54,840.00
#VALUE!
3,600.00

8,400.00

8,400.00

4,900.00

4,900.00

560.00

560.00

630.00

630.00
#VALUE!

0%

#VALUE!

#VALUE!
#VALUE!
#VALUE!
3,600.00
8,400.00

8,400.00

4,900.00

4,900.00

560.00

560.00

630.00

630.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
3,600.00

8,400.00

8,400.00

4,900.00

4,900.00

560.00

560.00

630.00

630.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
3,600.00

8,400.00

8,400.00

4,900.00

4,900.00

560.00

560.00

630.00

630.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
3,600.00

8,400.00

8,400.00

4,900.00

4,900.00

560.00

560.00

630.00

630.00
#VALUE!

0%

#VALUE!
#VALUE!

#VALUE!
#VALUE!
3,600.00
8,400.00

8,400.00

4,900.00

4,900.00

560.00

560.00

630.00

630.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
3,600.00

8,400.00

8,400.00

4,900.00

4,900.00

560.00

560.00

630.00

630.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
3,600.00

8,400.00

8,400.00

4,900.00

4,900.00

560.00

560.00

630.00

630.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
3,600.00

8,400.00

8,400.00

4,900.00

4,900.00

560.00

560.00

630.00

630.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!

#VALUE!
3,600.00
8,400.00

8,400.00

4,900.00

4,900.00

560.00

560.00

630.00

630.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

5,040.00

5,040.00

8,750.00

8,750.00

1,040.00

1,040.00

360.00

360.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

5,040.00

5,040.00

8,750.00

8,750.00

1,040.00

1,040.00

360.00

360.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

5,040.00

5,040.00

8,750.00

8,750.00

1,040.00

1,040.00

360.00

360.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
5,040.00

5,040.00

8,750.00

8,750.00

1,040.00

1,040.00

360.00

360.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

5,040.00

5,040.00

8,750.00

8,750.00

1,040.00

1,040.00

360.00

360.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

5,040.00

5,040.00

8,750.00

8,750.00

1,040.00

1,040.00

360.00

360.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

6,000.00

6,000.00

10,500.00

10,500.00

1,040.00

1,040.00

360.00

360.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
6,000.00

6,000.00

10,500.00

10,500.00

1,040.00

1,040.00

360.00

360.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
682,000.00
510.00

12,000.00

12,000.00

7,000.00

7,000.00

800.00

800.00

900.00

900.00
703,210.00

0%

0.00
703,210.00
703,210.00
#VALUE!
510.00
#VALUE!

12,000.00

12,000.00

21,000.00

21,000.00

2,400.00

2,400.00

45,000.00

45,000.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
3,400.00

12,000.00

12,000.00

7,000.00

7,000.00

800.00

800.00

900.00

900.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!

33,000.00
3,400.00
9,960.00

9,960.00

17,500.00

17,500.00

2,000.00

2,000.00

720.00

720.00
66,580.00

0%

0.00
66,580.00
66,580.00
21,000.00
850.00
13,500.00
6,240.00
10,000.00

9,960.00

9,960.00

17,500.00

17,500.00

2,000.00

2,000.00

720.00

720.00
81,770.00

0%

0.00
81,770.00
81,770.00
#VALUE!
850.00
14,875.00

7,500.00

7,500.00

17,500.00

17,500.00

2,000.00

2,000.00

720.00

720.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!
850.00

15,000.00

15,000.00

10,500.00

10,500.00

1,200.00

1,200.00

1,170.00

1,170.00
#VALUE!

0%

#VALUE!

#VALUE!
#VALUE!
11,600.00
850.00
850.00
7,500.00

7,500.00

17,500.00

17,500.00

2,000.00

2,000.00

720.00

720.00
41,020.00

0%

0.00
41,020.00
41,020.00
20,300.00
340.00

7,200.00

7,200.00

4,200.00

4,200.00

480.00

480.00

540.00

540.00
33,060.00

0%

0.00
33,060.00
33,060.00
8,700.00
340.00

9,000.00

9,000.00

4,900.00

4,900.00

560.00

560.00

540.00

540.00
24,040.00

0%

0.00
24,040.00
24,040.00
#VALUE!
#VALUE!

9,000.00

9,000.00

52,500.00

52,500.00

6,400.00

6,400.00

540.00

540.00
#VALUE!

0%

#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
6,000.00

6,000.00

70,000.00

70,000.00

8,000.00

8,000.00

4,500.00

4,500.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!
#VALUE!

9,000.00

9,000.00

3,500.00

3,500.00

400.00

400.00

720.00

720.00
#VALUE!

0%

#VALUE!
#VALUE!
#VALUE!

HARGA

NO.

INDEKS

SATUAN

KEBUTUHAN

HARGA,
SATUAN
(Rp)

BAHAN (Rp)

PEKERJAAN PIPA DAN SANITASI (RSNI T15-2002)


1

Memasang 1 buah klosed duduk / monoblock


1.000 bh

Closed duduk (lokal)

6.000 %

Perlengkapan (dari harga closed)

3.300 Oh

Pekerja tak terlatih

60,000.00

1.100 Oh

Tukang batu

70,000.00

0.001 Oh

Kepala tukang

80,000.00

0.160 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
2

Memasang 1 buah klosed jongkok porselin


1.000 bh

Closed jongkok porcelaint (lokal)

6.000 kg

Semen PC @ 50 kg

0.010 m

Pasir pasang

1.000 Oh

Pekerja tak terlatih

60,000.00

1.500 Oh

Tukang batu

70,000.00

1.500 Oh

Kepala tukang

80,000.00

0.160 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
3

Memasang 1 buah klosed jongkok keramik


1.000 bh

Closed jongkok keramik

7.000 bh

Batu bata merah (lokal)

6.000 kg

Semen PC @ 50 kg

0.010 m

Pasir pasang

1.000 Oh

Pekerja tak terlatih

60,000.00

1.500 Oh

Tukang batu

70,000.00

0.300 Oh

Kepala tukang

80,000.00

0.110 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
4

Memasang 1 buah urinoir


1.000 bh
30.000 %

Urinoir terasso

Perlengkapan (dari harga urinoir)

6.000 kg

Semen PC @ 50 kg

0.010 m

Pasir pasang

1.000 Oh

Pekerja tak terlatih

60,000.00

1.000 Oh

Tukang batu

70,000.00

0.100 Oh

Kepala tukang

80,000.00

0.100 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
5

Memasang 1 buah wastafel


1.000 bh
12.000 %

Wastafel

Perlengkapan (dari harga wastafel)

6.000 kg

Semen PC @ 50 kg

0.010 m

Pasir pasang

1.200 Oh

Pekerja tak terlatih

60,000.00

1.450 Oh

Tukang batu

70,000.00

0.150 Oh

Kepala tukang

80,000.00

0.100 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
6

Memasang 1 buah bak mandi fibreglass vol. 0,3 m


1.000 bh
18.000 %

Bak mandi fibreglass volume 0,30 m


Perlengkapan (dari harga bak)

1.800 Oh

Pekerja tak terlatih

60,000.00

2.700 Oh

Tukang batu

70,000.00

0.540 Oh

Kepala tukang

80,000.00

0.110 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
7

Memasang 1 buah bak mandi fibreglass vol. 1 m


1.000 bh
12.000 %

Bak mandi fibreglass volume 1,00 m


Perlengkapan (dari harga bak)

3.000 Oh

Pekerja tak terlatih

60,000.00

4.500 Oh

Tukang batu

70,000.00

0.900 Oh

Kepala tukang

80,000.00

0.900 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

0%

Memasang 1 buah bak mandi batu bata vol. 0,3 m + porselin 11 cm x 11 cm


180.000 bh

Batu bata merah (lokal)

120.000 kg

Semen PC @ 50 kg

Pasir pasang

0.300 m
360.000 bh

Porcelaint uk. 11 cm x 11 cm

6.000 kg

Semen putih

6.000 Oh

Pekerja tak terlatih

60,000.00

3.000 Oh

Tukang batu

70,000.00

0.300 Oh

Kepala tukang

80,000.00

0.300 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
9

Memasang 1 buah bak mandi batu bata vol. 0,3 m + keramik 10 cm x 20 cm


180.000 bh

Batu bata merah (lokal)

120.000 kg

Semen PC @ 50 kg

0.300 m

Pasir pasang

4.400 m

Keramik 10 x 20 (cm) terang

6.000 kg

Semen putih

60,000.00

6.000 Oh

Pekerja tak terlatih

70,000.00

3.000 Oh

Tukang batu

80,000.00

0.300 Oh

Kepala tukang

90,000.00

0.300 Oh

Mandor

Jumlah

0%

Keuntungan Maksimal

10%

Jumlah
Dibulatkan
10

Memasang 1 buah bak beton vol. 1 m air dengan keramik 10 cm x 20 cm


0.900 m
180.000 kg
0.800 m

Beton adukan 1 pc : 1 ps : 2 krk

Besi beton

Kayu gergajian kelas IV, papan

10.760 m

Keramik 10 x 20 (cm) terang

10.000 %

Perlengkapan (dari harga total bahan)

2.300 Oh

Pekerja tak terlatih

60,000.00

3.200 Oh

Tukang batu

70,000.00

0.700 Oh

Kepala tukang

80,000.00

0.700 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
11

Memasang 1 buah bak beton vol. 1 m air dengan porselin 11 cm x 11 cm


0.900 m
180.000 kg

Beton adukan 1 pc : 1 ps : 2 krk

Besi beton

0.800 m
1,115.000 bh
10.000 %

Kayu gergajian kelas IV, papan

Porcelaint uk. 11 cm x 11 cm

Perlengkapan (dari harga total bahan)

3.500 Oh

Pekerja tak terlatih

60,000.00

4.500 Oh

Tukang batu

70,000.00

0.900 Oh

Kepala tukang

80,000.00

0.900 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
12

Memasang 1 buah bathtub (non SNI)


1.000 bh
20.000 %

Bak mandi jenis bathtub

Perlengkapan (dari harga bathtub)

0.075 Oh

Tukang batu

0.075 Oh

Kepala tukang

0.250 Oh

Mandor

Jumlah
Keuntungan Maksimal

10%

Jumlah
Dibulatkan
13

Memasang 1 m' pipa beton 15 cm - 20 cm


1.100 bh

Pipa beton 20 cm, panjang 1 m'

Batu bata merah (lokal)

3.920 kg

Semen PC @ 50 kg

0.056 m

Pasir pasang

0.024 m

Pasir urug / timbun

0.140 Oh

Pekerja tak terlatih

60,000.00

0.070 Oh

Tukang batu

70,000.00

0.007 Oh

Kepala tukang

80,000.00

0.007 Oh

Mandor

90,000.00

13.000 bh

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
14

Memasang 1 m' pipa beton 30 cm - 100 cm


Pipa beton 60 cm, panjang 1 m'

25.000 bh

1.100 bh

Batu bata merah (lokal)

10.300 kg

Semen PC @ 50 kg

0.061 m

Pasir pasang

0.069 m

Pasir urug / timbun

0.380 Oh

Pekerja tak terlatih

60,000.00

0.190 Oh

Tukang batu

70,000.00

0.019 Oh

Kepala tukang

80,000.00

0.019 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
15

Memasang 1 bh bak kontrol pas. batu bata uk. 30 cm x 30 cm, tinggi 35 cm


66.000 bh

Batu bata merah (lokal)

44.000 kg

Semen PC @ 50 kg

0.070 m

Pasir pasang

0.070 m

Batu kerikil ayak / batu saring / kerai

1.600 kg

Besi beton

0.060 m

Pasir ayak untuk beton

3.200 Oh

Pekerja tak terlatih

60,000.00

1.105 Oh

Tukang batu

70,000.00

0.002 Oh

Kepala tukang

80,000.00

0.016 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
16

Memasang 1 bh bak kontrol pas. batu bata uk. 45 cm x 45 cm, tinggi 50 cm


113.000 bh

Batu bata merah (lokal)

Semen PC @ 50 kg

0.130 m

Pasir pasang

0.020 m

Batu kerikil ayak / batu saring / kerai

2.600 kg

Besi beton

0.090 m

Pasir ayak untuk beton

1.420 Oh

Pekerja tak terlatih

60,000.00

0.473 Oh

Tukang batu

70,000.00

0.047 Oh

Kepala tukang

80,000.00

0.071 Oh

Mandor

90,000.00

77.000 kg

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
17

Memasang 1 bh bak kontrol pas. batu bata uk. 60 cm x 60 cm, tinggi 65 cm


167.000 bh

Batu bata merah (lokal)

114.000 kg

Semen PC @ 50 kg

0.184 m

Pasir pasang

0.033 m

Batu kerikil ayak / batu saring / kerai

4.850 kg

Besi beton

0.120 m

Pasir ayak untuk beton

2.160 Oh

Pekerja tak terlatih

60,000.00

0.720 Oh

Tukang batu

70,000.00

0.072 Oh

Kepala tukang

80,000.00

0.108 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
18

Memasang 1 m' pipa galvanis 1/2"


1.200 m'
35.000 %

Pipa besi galvanis 0,5 (inch)


Perlengkapan (dari harga pipa)

0.054 Oh

Pekerja tak terlatih

60,000.00

0.090 Oh

Tukang batu

70,000.00

0.009 Oh

Kepala tukang

80,000.00

0.027 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
19

Memasang 1 m' pipa galvanis 3/4"


1.200 m'

Pipa besi galvanis 0,75 (inch)

35.000 %

Perlengkapan (dari harga pipa)

0.054 Oh

Pekerja tak terlatih

60,000.00

0.090 Oh

Tukang batu

70,000.00

0.009 Oh

Kepala tukang

80,000.00

0.027 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
20

Memasang 1 m' pipa galvanis 1"


1.200 m'
35.000 %

Pipa besi galvanis 1 (inch)


Perlengkapan (dari harga pipa)

0.054 Oh

Pekerja tak terlatih

60,000.00

0.090 Oh

Tukang batu

70,000.00

0.009 Oh

Kepala tukang

80,000.00

0.027 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
21

Memasang 1 m' pipa galvanis 1,5"


1.200 m'
35.000 %

Jumlah

Pipa besi galvanis 1,5 (inch)


Perlengkapan (dari harga pipa)

0.108 Oh

Pekerja tak terlatih

60,000.00

0.180 Oh

Tukang batu

70,000.00

0.018 Oh

Kepala tukang

80,000.00

0.005 Oh

Mandor

90,000.00

Keuntungan Maksimal

0%

Jumlah
Dibulatkan
22

Memasang 1 m' pipa galvanis 2"


1.200 m'
35.000 %

Pipa besi galvanis 2 (inch)


Perlengkapan (dari harga pipa)

0.108 Oh

Pekerja tak terlatih

60,000.00

0.180 Oh

Tukang batu

70,000.00

0.018 Oh

Kepala tukang

80,000.00

0.005 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
23

Memasang 1 m' pipa galvanis 4"


1.200 m'
35.000 %

Pipa besi galvanis 4 (inch)


Perlengkapan (dari harga pipa)

0.135 Oh

Pekerja tak terlatih

60,000.00

0.225 Oh

Tukang batu

70,000.00

0.023 Oh

Kepala tukang

80,000.00

0.007 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
24

Memasang 1 m' pipa PVC tipe AW 1/2"


1.200 m'
35.000 %

Pipa PVC 1/2 (inch) AW, panjang 4 m


Perlengkapan (dari harga pipa)

0.036 Oh

Pekerja tak terlatih

60,000.00

0.060 Oh

Tukang batu

70,000.00

0.006 Oh

Kepala tukang

80,000.00

0.002 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
25

Memasang 1 m' pipa PVC tipe AW 3/4"


1.200 m'
35.000 %

Pipa PVC 3/4 (inch) AW, panjang 4 m


Perlengkapan (dari harga pipa)

0.036 Oh

Pekerja tak terlatih

60,000.00

0.060 Oh

Tukang batu

70,000.00

0.006 Oh

Kepala tukang

80,000.00

0.002 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
26

Memasang 1 m' pipa PVC tipe AW 1"


1.200 m'
35.000 %

Pipa PVC 1(inch) AW, panjang 4 m


Perlengkapan (dari harga pipa)

0.036 Oh

Pekerja tak terlatih

60,000.00

0.060 Oh

Tukang batu

70,000.00

0.006 Oh

Kepala tukang

80,000.00

0.002 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
27

Memasang 1 m' pipa PVC tipe AW 1,5"


1.200 m'
35.000 %

Pipa PVC 1,5 (inch) AW, panjang 4 m


Perlengkapan (dari harga pipa)

0.036 Oh

Pekerja tak terlatih

60,000.00

0.060 Oh

Tukang batu

70,000.00

0.006 Oh

Kepala tukang

80,000.00

0.002 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
28

Memasang 1 m' pipa PVC type AW 3"


1.200 m'
35.000 %

Pipa PVC 3 (inch) AW, panjang 4 m


Perlengkapan (dari harga pipa)

0.081 Oh

Pekerja tak terlatih

60,000.00

0.135 Oh

Tukang batu

70,000.00

0.135 Oh

Kepala tukang

80,000.00

0.004 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
29

Memasang 1 m' pipa PVC type AW 4"


1.200 m'
35.000 %

Pipa PVC 3 (inch) AW, panjang 4 m


Perlengkapan (dari harga pipa)

0.081 Oh

Pekerja tak terlatih

60,000.00

0.135 Oh

Tukang batu

70,000.00

0.135 Oh

Kepala tukang

80,000.00

0.004 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal
Jumlah

0%

Dibulatkan
30

Memasang 1 m' pipa PVC type AW 8"


1.200 m'
35.000 %

Pipa PVC 8 (inch) AW, panjang 4 m


Perlengkapan (dari harga pipa)

0.081 Oh

Pekerja tak terlatih

60,000.00

0.135 Oh

Tukang batu

70,000.00

0.135 Oh

Kepala tukang

80,000.00

0.004 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
30

Memasang 1 bh kran air 3/4" atau 1/2"


1.000 bh

Kran air 0,75 (inch)

0.025 bh

seal tape

0.010 Oh

Pekerja tak terlatih

60,000.00

0.100 Oh

Tukang batu

70,000.00

0.010 Oh

Kepala tukang

80,000.00

0.005 Oh

mandor

90,000.00

Jumlah
Keuntungan Maksimal

0%

Jumlah
Dibulatkan
31

Memasang 1 bh floor drain


1.000 bh

Floor drain

0.010 Oh

Pekerja tak terlatih

60,000.00

0.100 Oh

Tukang batu

70,000.00

0.010 Oh

Kepala tukang

80,000.00

0.005 Oh

Mandor

90,000.00

Jumlah
Keuntungan Maksimal

10%

Jumlah
Dibulatkan
32

Memasang 1 bh tempat sabun keramik (non SNI)


1.000 bh

Tempat sabun keramik

0.002 kg

Semen putih

0.100 Oh

Tukang batu

70,000.00

0.010 Oh

Kepala tukang

80,000.00

Jumlah
Keuntungan Maksimal

10%

Jumlah
Dibulatkan
33

Memasang 1 bh septic tank, volume air 1 m (non SNI)


3.717 m

Galian tanah

2.038 m

Urugan kembali

0.360 m

Pas. dinding bata merah tebal 1/2 bata ad. 1 : 4

3.567 m

Pas. plesteran dinding dalam bak ad. 1 : 2, tebal 15 mm

0.056 m

Pas. kolom beton bertulang ad. 1 : 2 : 3

0.130 m

Pas. sloof beton bertulang ad. 1 : 2 : 3

0.020 m

Pas. ringbalk beton bertulang ad. 1 : 2 : 3

2.600 m

Pas. lantai bak beton tumbuk ad. 1 : 3 : 6

0.600 m'

Pas. pipa galvanis 1,5"

Jumlah
Keuntungan Maksimal

10%

Jumlah
Dibulatkan
34

Memasang 1 bh septic tank, volume air 1,5 m (non SNI)


5.580 m

Galian tanah

3.050 m

Urugan kembali

0.540 m

Pas. dinding bata merah tebal 1/2 bata ad. 1 : 4

5.351 m

Pas. plesteran dinding dalam bak ad. 1 : 2, tebal 15 mm

0.084 m

Pas. kolom beton bertulang ad. 1 : 2 : 3

0.200 m

Pas. sloof beton bertulang ad. 1 : 2 : 3

0.030 m

Pas. ringbalk beton bertulang ad. 1 : 2 : 3

3.900 m

Pas. lantai bak beton tumbuk ad. 1 : 3 : 6

0.600 m'

Pas. pipa galvanis 1,5"

Jumlah
Keuntungan Maksimal

10%

Jumlah
Dibulatkan
35

Memasang 1 bh septic tank, volume air 2 m (non SNI)


7.434 m

Galian tanah

4.076 m

Urugan kembali

0.720 m

Pas. dinding bata merah tebal 1/2 bata ad. 1 : 4

7.134 m

Pas. plesteran dinding dalam bak ad. 1 : 2, tebal 15 mm

0.112 m

Pas. kolom beton bertulang ad. 1 : 2 : 3

0.260 m

Pas. sloof beton bertulang ad. 1 : 2 : 3

0.040 m

Pas. ringbalk beton bertulang ad. 1 : 2 : 3

5.200 m

Pas. lantai bak beton tumbuk ad. 1 : 3 : 6

0.600 m'

Pas. pipa galvanis 1,5"

Jumlah
Keuntungan Maksimal

10%

Jumlah
Dibulatkan
36

Memasang 1 bh Peresapan, dalam 5 m'


5.000 m

Galian Tanah

2.488 m

Urugan Kembali

2.512 m

Pas.Buis Beton tak bertulang 80 cm

0.384 m

Pas. Plesteran dinding(dalam) pd pertemuan buis , ad. 1 : 2, te

0.600 m'

Pas. Pipa galvanis 1,5"

Jumlah
Keuntungan Maksimal
Jumlah
Dibulatkan

10%

HARGA
UPAH (Rp)

JUMLAH HARGA
(Rp)

7.00

198,000.00

198,000.00

77,000.00

77,000.00

80.00

80.00

14,400.00

14,400.00
289,480.00

0%

289,480.00
289,480.00
-

60,000.00

60,000.00

105,000.00

105,000.00

120,000.00

120,000.00

14,400.00

14,400.00
299,400.00

0%

299,400.00
299,400.00
-

60,000.00

60,000.00

105,000.00

105,000.00

24,000.00

24,000.00

9,900.00

9,900.00
198,900.00

0%

198,900.00
198,900.00
-

60,000.00

60,000.00

70,000.00

70,000.00

8,000.00

8,000.00

9,000.00

9,000.00
147,000.00

0%

147,000.00
147,000.00
-

72,000.00

72,000.00

101,500.00

101,500.00

12,000.00

12,000.00

9,000.00

9,000.00
194,500.00

0%

194,500.00
194,500.00
-

108,000.00

108,000.00

189,000.00

189,000.00

43,200.00

43,200.00

9,900.00

9,900.00
350,100.00

0%

350,100.00
350,100.00
-

180,000.00

180,000.00

315,000.00

315,000.00

72,000.00

72,000.00

81,000.00

81,000.00
648,000.00

0%

648,000.00
648,000.00

360,000.00

360,000.00

210,000.00

210,000.00

24,000.00

24,000.00

27,000.00

27,000.00
621,000.00

0%

621,000.00
621,000.00
-

360,000.00

360,000.00

420,000.00

420,000.00

240,000.00

240,000.00

27,000.00

27,000.00
1,047,000.00

0%

10%

138,000.00

138,000.00

224,000.00

224,000.00

56,000.00

56,000.00

63,000.00

63,000.00
481,000.00
481,000.00
481,000.00
-

210,000.00

210,000.00

315,000.00

315,000.00

72,000.00

72,000.00

81,000.00

81,000.00
678,000.00

0%

678,000.00
678,000.00
-

315,000.00

315,000.00

72,000.00

72,000.00

81,000.00

81,000.00
468,000.00

10%

46,800.00
514,800.00
514,800.00
-

8,400.00

8,400.00

4,900.00

4,900.00

560.00

560.00

630.00

630.00
14,490.00

0%

14,490.00
14,490.00
-

22,800.00

22,800.00

13,300.00

13,300.00

1,520.00

1,520.00

1,710.00

1,710.00

39,330.00
0%

39,330.00
39,330.00
-

192,000.00

192,000.00

77,350.00

77,350.00

120.00

120.00

1,440.00

1,440.00
270,910.00

0%

270,910.00
270,910.00
-

85,200.00

85,200.00

33,110.00

33,110.00

3,760.00

3,760.00

6,390.00

6,390.00
128,460.00

0%

128,460.00
128,460.00
-

129,600.00

129,600.00

50,400.00

50,400.00

5,760.00

5,760.00

9,720.00

9,720.00

195,480.00
0%

195,480.00
195,480.00
-

3,240.00

3,240.00

6,300.00

6,300.00

720.00

720.00

2,430.00

2,430.00
12,690.00

0%

12,690.00
12,690.00
-

3,240.00

3,240.00

6,300.00

6,300.00

720.00

720.00

2,430.00

2,430.00
12,690.00

0%

12,690.00
12,690.00
-

3,240.00

3,240.00

6,300.00

6,300.00

720.00

720.00

2,430.00

2,430.00
12,690.00

0%

12,690.00
12,690.00
-

6,480.00

6,480.00

12,600.00

12,600.00

1,440.00

1,440.00

486.00

486.00
21,006.00

0%

21,006.00
21,000.00
-

6,480.00

6,480.00

12,600.00

12,600.00

1,440.00

1,440.00

486.00

486.00
21,006.00

0%

21,006.00
21,000.00
-

8,100.00

8,100.00

15,750.00

15,750.00

1,800.00

1,800.00

612.00

612.00
26,262.00

0%

26,262.00
26,260.00
-

2,160.00

2,160.00

4,200.00

4,200.00

480.00

480.00

162.00

162.00
7,002.00

0%

7,002.00
7,000.00
-

2,160.00

2,160.00

4,200.00

4,200.00

480.00

480.00

162.00

162.00
7,002.00

0%

7,002.00
7,000.00
2,160.00

2,160.00

4,200.00

4,200.00

480.00

480.00

162.00

162.00
7,002.00

0%

7,002.00
7,000.00
-

2,160.00

2,160.00

4,200.00

4,200.00

480.00

480.00

162.00

162.00
7,002.00

0%

7,002.00
7,000.00
-

4,860.00

4,860.00

9,450.00

9,450.00

10,800.00

10,800.00

369.00

369.00
25,479.00

0%

25,479.00
25,470.00
-

4,860.00

4,860.00

9,450.00

9,450.00

10,800.00

10,800.00

369.00

369.00
25,479.00

0%

25,479.00

25,470.00
4,860.00

4,860.00

9,450.00

9,450.00

10,800.00

10,800.00

369.00

369.00
25,479.00

0%

25,479.00
25,470.00
-

600.00

600.00

7,000.00

7,000.00

800.00

800.00

450.00

450.00
8,850.00

0%

8,850.00
8,850.00
-

600.00

600.00

7,000.00

7,000.00

800.00

800.00

450.00

450.00
8,850.00

10%

885.00
9,735.00
9,730.00
-

7,000.00

7,000.00

800.00

800.00
7,800.00

10%

780.00
8,580.00
8,580.00
-

10%

10%

10%

10%