CLARIFICATION MATRIX
FOR SUPPLY, DELIVERY, INSTALLATION, CONFIGURATION, TESTING AND COMMISSIONING OF AN
ELECTRONIC DOCUMENT MANAGEMENT SYSTEM (TENDER REFERENCE NO.: PRQ2010121)
This clarification matrix forms an integral part of the tender document and therefore, must be carefully
considered by service providers in preparation and submission of bids.
QUERIES AND RESPONSES
This section contains queries requested by bidders and responses provided against each in relation to Terms
Of Reference and Technical Specifications for the SUPPLY, DELIVERY, INSTALLATION, CONFIGURATION,
TESTING AND COMMISSIONING OF AN ELECTRONIC DOCUMENT MANAGEMENT SYSTEM (TENDER
REFERENCE NO.: PRQ20160121).
All communications must be directed to the procuring entity, TradeMark East Africa through
procurement@trademarkea.com as provided for in the tender document ITB 7.1.
S/No. Query
Status (closed/
open/ pending)
Response
Infrastructure Strata
a) H/W :
High End IBM Power-ppc-64 RISC (5)
Intel x86-64 ORACLE ExaData Engineered
Systems (3)
Intel x86-64 Blade (DELL, IBM, HP & Cisco
UCS) and Standalone (total +6)
VMware ESXi Server Virtualisation (+5)
b) Storage:
EMC-2 VNX 7000 Series (FC interface),
auto tiered between SSD and SAS Disks
and Centera File Share Archiver (>30 TB)
DELL EqualLogic PS4000 series (iSCSI
interface) uniform SAS disks (>18 TB)
IBM DS-4000 series FC interface, uniform
SAS Disks (max 15K rpm) (>10 TB)
ORACLE ExaData Storage FC, Uniform
SD/SAS disks (>12 TB)
c) OS:
Oracle Linux 7 x86-64
SuSE Linux Enterprise Server 11.4, 12.1
(x86-64, SuSE for SAP and ppc-64)
RedHat Enterprise Linux 7.1 (x86-64)
Ms Windows 2000, 2003, 2008, 2013 (x86
and x86-64)
2
Closed
S/No. Query
Status (closed/
open/ pending)
Response
d) Application Platform :
Tiered Java EE architecture
Presentation:
o Apache TomCat 6,7,8,9
o RedHat Ent WS (TomCat 7)
o Ms IIS 5, 6, 7, 8
Business Logic Processing / Framework
o Ms VB 6, VB- .DOT-NET 4
o Apache TomCat EJB Containe
o JBoss AS 7, WildFly 8,9
o RedHat JBoss EAP 7
o Oracle Web-Logic (new iCMS)
Enterprise Information
o ORACLE 10g, 11g (Linux x86-64 &
o ppc-64)
o PostgresSQL 9, EDB
o EDB Postgres Plus Adv Server 9.4
o MySQL 5,
o Microsoft SQL Server 2005, 2008
o IBM DB-2
o SAP HANA (Hi-Perf-Analytic Appl)
Yes
Both Server (VMware)
And Workstations CITRIX Xen VDI
Main Applications;
1. SAP ERP
2. iTax (Java EE on RH Ent JBoss Ent App Plf.
3. SAP ERP (on SuSE Ent. Linux for SAP)
3. Customs ACMS Java EE on JBoss AS 6
4. Customs iCMS Java EE on Oracle WebLogic Closed
10
5. Mail on IBM Lotus Domino on IBM AIX 7
Closed
Closed
S/No. Query
Would you need a DR+HA for
the EDMS system as well? If so,
will this DR environment be
accessible from main location
for the project team?
7.
Status (closed/
open/ pending)
Response
Only major systems (core business applications)
have installed.
S/No. Query
Status (closed/
open/ pending)
Response
REST and so on. If there are any limitations,
please indicate this in your proposal.
Closed
S/No. Query
Status (closed/
open/ pending)
Response
Closed
Yes
Closed
Yes. The details will be discussed during
implementation.
Closed
S/No. Query
Status (closed/
open/ pending)
Response
18.
OR
Digitization of this existing
documents will be done by
Trademark, only configuration
and scan setup will be done by
vendor.
Please clarify.
As per ITB 4.1.
Is it only the pre-qualified
bidders who are allowed to
19. participate in this bid as stated
in this section in the tender
document or is it open to all
vendors even if they havent
been pre-qualified?
20. How many users?
21. No mention of training?
22.
23.
Closed
Closed
be
discussed
during
Closed
Closed
No
Closed
No
Closed
be
discussed
during
Closed
S/No. Query
Confirm whether all the users
28. are in one site. Nairobi or
within East Africa.
Is the DMS is going to use on
29. cloud instance or in local
environment?
Is the requirement based on
30.
open source technology?
31.
32.
Response
Status (closed/
open/ pending)
Closed
Local environment
Closed
No
Closed
Closed
S/No. Query
considered 36 months or 365
days.
In the terms of reference under
Section VI schedule of
requirement there is no
hardware requirements. So
37. kindly confirm that the scope of
work does not include any
hardware supply, installation,
configuration and
commissioning.
Status (closed/
open/ pending)
Response
Closed