Interim Revised Program

07.02.2016

Phase-I
CDC Work:
Total No of CDC (Bottom Layer): 3422
Done upto 31.01.2016:
3068
Balance:
354-100(Infront of 3storied building) =254
Planning:
One(01) crane upto 03 February 2016:
Nos
One(01) crane from 15.03 to 25.03.2016:
Nos
CDC completion date for Phase-I:

18 Nos CDC per day X 3 days

= 54

18 Nos CDC per day X 11 days = 198

28.03.2016

Recovery Plan: furthermore if we miss this daily/weekly target we will go for extra
working hour
to cover the backlogs.
Sand filling:
Total sand quantity=87000m3(compacted volume)
Required Sand Volume=87000X1.3=113100m3= 39,94,127 cft
Received upto 31.01.2016:
1895253 cft.
Balance : 2099000 cft.
To be finished by: 31.03.2016
Supply per day: 40,000 cft per day.

Top Layer CDC


No of CDC yet to be confirmed. Approximate Nos: 3000.
One trial area will be done for CDC and Plate Load test to be done to fix the
compaction requirement.
Start Date: 10.03.2016
End Date:
30.04.2016
Total 50 days.
CDC per day: 60 Nos with 3 cranes.

Sheet Pile:
As the final sheet pile status,
Start Date: 20.02.2016
End Date:
25.03.2016
Total 35 days.
th
6 crane (50 ton) will be dedicated to work for sheet piling.
Capping and Boundary wall construction:
Start Date: 01.03.2016
End Date:
30.04.2016
Total 60 days

Phase-II
CDC Work:
Total No of CDC (Bottom Layer): 2741
Done upto 21.12.2015:
1872
Balance:
869+150(rework)=1019 Nos
Planning:
One(01) crane from 01.02 to 05.02 .2016:
75 Nos
Two(02) cranes from 06.02 to 08.03 .2016:
960 Nos
Maximum completion date:

15 Nos CDC per day X 5 days

30 Nos CDC per day X 32 days =

CDC completion date (considering 80% efficiency) for Phase-II: 12.03.2016

Sand filling:
Total sand quantity=172000m3(compacted volume)
Required Sand Volume=172000X1.3=223600m3= 7225634cft
40% sandfilling will be done before rainy season.
To reach the existing ground level= 2890253cft.
Completed upto 31.01.2016
= 1343306cft
Balance
=1546947cft
st
To be finished by 31 March 2015.
Supply per day: 30000cft.
Balance after 31st March: 4335381cft
Daily supply after March: 35000cft

To be finished by 15.08.2016
Intermediate Layer CDC
Final no of CDC for Intermediate level is yet to be confirmed
Start Date: 15.03.2016
One(01) Crane with 25 points per day: 25X15=375
Two(02) Cranes with 50 points per day: 50X30=1500
Top Layer CDC
Start Date: 19.08.2016
End Date:
30.09.2016
Total 42 days, its comfortable.

Sheet Pile:
LC opening/shipment/carrying to site:
Start Date: 01.02.2016
End Date:
15.04.2016
Total 60 days.
Sheet Pile driving:
Start Date: 21.04.2016
End Date:
05.07.2016
Total 75 days.
Filling and anchorage:

Start Date: 03.07.2016


End Date: 18.08.2016
Total 45 Days

Capping and Boundary wall construction:


Start Date: 19.08.2016
End Date:
05.10.2016
Total 47 days

Phase-III
CDC work:
Total No of CDC (Bottom Layer): 1819
Done upto 31.01.2016:
186
Balance:
1633
Planning:

One(01) crane from 01.02 to 03.02.2016:


54 Nos
Two(02) crane from 02.02 to 18.02.2016:
540 Nos
Three(03) crane from 19.02 to 08.03.2016:
= 1080 Nos

18 Nos CDC per day X 03 days =


36 Nos CDC per day X 15 days =
54 Nos CDC per day X 20 days

Maximum completion date:


CDC completion date for Phase-III : 14.03.2016
Sand filling:
Total sand quantity=80000m3(compacted volume)
Required Sand Volume=80000X1.3=104000m3= 36,72,760cft
Start Date: 20.02.2016
End Date:
31.03.2016
75 days (filling upto existing ground level), 50% =1836380cft
Per day supply upto 31.03.2016= 50000cft.
End Date:
27.06.2016
Per day supply after 31.03= 21000cft
Top Layer CDC
Start Date:
End Date:
75 days

15.05.2016
31.07.2016

Sheet Pile:
Start Date: 01.04.2016
End Date:
20.05.2016
Total 45 days.
Capping and Boundary wall construction:
Start Date: 05.04.2016
End Date:
25.05.2016
Total 50 days

Hand Over Dates


Phase-I
Phase-II
Phase-III

Hand Over Date: 23.05.2016


Hand Over Date: 10.11.2016
Hand Over Date: 18.08.2016