Escolar Documentos
Profissional Documentos
Cultura Documentos
Study Report
February 2006
List of Contents
Executive Summary
Chapter 1
s1
1.1
1.2
1.3
Survey summary
2.2
Chapter 3
3.1
3.2
3.2.1
10
3.2.2
11
Chapter 4
4.1
4.1.1
14
4.1.2
17
4.2
4.2.1
21
4.2.2
24
4.2.3
26
4.3
Chapter 5
26
5.1
28
5.2
32
5.3
32
5.4
33
6.1.1
Overall conditions
34
6.1.2
34
6.2
6.2.1
A development schedule
37
6.2.2
Project Participants
38
6.2.3
39
6.2.4
40
6.2.5
6.3
45
6.3.1
Overview
46
6.3.2
Development plan
47
6.3.3
Development structure
47
6.3.4
48
Chapter 7
Conclusion
7.1
49
7.2
49
7.3
50
7.4
Suggestions
51
APPENDIX
Calculation sheet
A location map
Fig.2-1-2
Fig.2-1-3
A fumarole
Fig.2-1-4
Fig.2-1-5
Fig.2-2-1
Fig.2-2-2
Fig.3-1-1
Silica scale of injection pipe in the initial phase of the commercial operation (1)
Fig.3-1-2
Silica scale of injection pipe in the initial phase of the commercial operation(2)
Fig.3-2-1-1
Fig.3-2-2-1
Fig.3-2-2-2
Fig.3-2-2-3
Fig.4-1-1
Fig.4-1-2
Fig.4-1-3
Table 4-1-1 The opening angle of governing valves during water injection
Fig.4-1-4
Fig.4-1-5
Fig.4-1-6
Condenser Vacuum
Fig.4-2-1-1
Fig.4-2-1-2
Fig.4-2-2-2
Coiled Tubing
Fig.4-3-1
Relations between the number of operating cooling fan and condenser vacuum
Fig.4-3-2
Fig.5-2-1
Fig.6-2-1-1
Project Participants
Fig.6-2-3-1
Fig.6-2-4-1
Fig.6-2-4-2
Fig.6-2-4-3
Fig.6-3-1-1
Project Participants
Fig.7-4-1
Project Flow
Abbreviation
ASEAN Association of
Southeast
Asian Nations
BOT
CDM
CER
CRT
Cathode Ray
GDP
IEA
International Energy
IPP
Independent
IRR
JI
Joint Implementation
JV
Joint Venture
LNG
Liquefied
NGO
Non-Governmental
NPV
O&M
Operation
PPA
Power Purchase
wt%
Weight %
Tube
Power
Natural
Agency
Producer
Gas
Organization
& Maintenance
Agreement
This work was subsidized by the Japan Keirin Association through its
Promotion funds from KEIRIN RACE.
Executive Summary
Overview of the Dieng geothermal power plant
Surveys of geothermal resources on the Dieng Plateau started from 1970s. From 1985 to
1991, a geothermal power plant program(55MW2) was established using the ADB fund.
In 1994, California Energy InternationalCEIin the US led JV signed a contract for the
construction of the Dieng geothermal power plant( 4 ,150MW by 2001 ), and
No.1(60MW)was completed in 1998. Although 45 wells confirmed the potential for 350MW,
the construction of No.2, 3, 4 was postponed following the Asian financial crisis. Then,
Mid-American purchased CEI. After the intervention of an American investment
insurance company (OPIC), GEODIPA, a joint venture between the PLN and Pertamina
obtained the ownership of the Dieng geothermal power plant in August 2001.
Fig.1Location Map
Pertamina
National oil
company
67%
National electric
company
Joint-Venture
33%
PT GEO DIPA
Dieng geothermal power plant
Yogyakarta
mechanism
well
silica
pipe
Ground
Well
turbine
calcium carbonate
mixture of fluids
varying in pH
S-1
Scaling
Flush point
Fluid
Fluid
Nozzle
Condensate water
Turbine Exhaust
System
Tank
Coil tube
Lubricator
Turbine
LG
Generator
To Flash Steam Cooler
INCOLOY 825
Calorimeter
Main
Steam
System
Injection unit
Scale
Separator
To Cooling
Tower
Jet
Condenser
Circulating
Water System
FX233
Electromagnetic
Flowmeter
Strainer
Circulating
Water Pump
Injection pump
Injection pump
Rewind drum
from
Production
Wells
million $
Namora-I-Langit
(65MW3)
Silangkitang
(50MW2)
Eastern Sibualbuali
S-2
Chapter 1
1.1
Although electricity demand in Indonesia was stagnant following the Asian financial
crisis in 1997 and the following plunge of the rupiah, it grew by 9.3% from 1999 to 2001.
Demand is expected to grow by an estimated 7% and according to an estimate by the
IEA, it will reach 300,000GWh by 2020. However, the massive debt(about 45trrion
Rp.).precludes the PLNAn electricity public corporation from raising sufficient funds
to develop the necessary new power sources to meet such demand In 2003, as the power
supply reserves declined to 5-10%, there are concerns of a serious power shortage
around Jakarta. In addition, in order to promote investment in power production, the
government has imposed considerably higher electricity charges. With several hikes,
the electricity rates in Rp. have approximately tripled compared to what they were at
the times of the financial crisis.
riots and oppression in industry, which have had a serious effect on the national
economy and the lives of the Indonesian citizen.
To deal with the drastic increase in electricity demand, the Indonesian government
drew up policy of securing supplies by opening up the electricity sector to private
enterprise. As a result, many foreign companies started to participate in the IPP project,
however the 1997 financial crisis resulted in the suspension of a lot of projects. Since
2001, negotiations aiming to reduce costs of power purchases of the PLN have been
resumed in an effort to rekindle interest in the many projects, which remain incomplete.
If the PLN depends solely on its own funds, it will be impossible for the PLN to improve
the installed capacity corresponding to the growing power demand, so active private
investment is necessary.
Indonesia is rich in geothermal resources and at present, it accounts for about 2.5% of
the total installed capacity. However, while geothermal resources offer the potential for
20, 000MW of electricity, only 4% (787MW) has been developed in the past 20 years.
Furthermore, in the 1990s, together with other IPP projects, contracts for geothermal
development projects that amount to 3,417MW were signed, but 7 of them were
suspended because of the financial crisis. Although negotiations for re-starting these
projects are under way, little progress has been made.
The project plant, the Dieng geothermal power plant, is located on the Dieng Plateau
in central Java
explosions and eruptions of volcanic gas have caused a great deal of damage over the
course of history. Volcanic activity remains active as can be seen by the recent eruption
of hot mud in1993 and a steam explosion and a volcanic earthquake in 1998.
When it comes to the exploitation of geothermal resources on the Dieng Plateau,
various surveys have been conducted since the 1970s. From 1985 to 1991, a survey
regarding the construction of the Dieng geothermal power plant was carried out
primarily by the PNL with the ADB, and a power generation program constructing
55MW2 was established. In December 1994, California Energy International in the
US (CEI)-led JV signed a contract for the construction of the Dieng geothermal power
plant, which is committed to build 150MW by 2001 at a cost of US $192 million. Under
the plan, 4 plants were supposed to be constructed, but after the completion of No1
(60MW) in 1998, the construction and the exploration activity for No.2 was postponed.
At that time, 48 wells had been drilled, and the project organizer confirmed that the
potential was 350MW. After that, a US firm, Mid-American, purchased CEI, but an
American investment insurance company (OPIC) intervened and mediated when the
project came to a deadlock. Consequently, the ownership was shifted to the Indonesian
government(PT GEO DIPA , a joint venture between the PLN and Pertamina).
During those years, No.1 also temporary stopped operation, but resumed operations
again. The geothermal resources of the plant contain a lot of Si in steam, making scales
cling to steam production wells, steam tubes and steam turbines. As a consequence, at
present, it only generates 40MW of electricity compared to the expected 60MW output.
Despite there have been several measures taken, such as the injection of acid (which is
also done in Japan) none have been effective in solving the problem. Agency for the
assessment and application of technology (BPPT) asked Tohoku Electric Power Co. Inc
to examine the scale problem in the plant through its overseas projects.
1.2
The purpose of this survey is to understand the extent of the scale problem n the Dieng
geothermal power plant and its causes and to provide a basis for a detailed examination,
which will lead to setting up appropriate countermeasures.
I also interviewed local people concerning PT GEO DIPA, the project entity, and
collected information about the possibility of our participation in the O&M project, the
matter of participation, and the possibility of capital contribution for the extension plan
and the necessary procedures which will accompany it.
1.3
Survey summary
Chapter 2
2.1
The Dieng geothermal power plant is located on the Dieng Plateau, about 80km north
west of Yogyakarta, an ancient city of Indonesia. Dieng came from Di Hyang in
Sanskrit, which means the place where gods live. As the name suggests, there are a lot
of Buddhist ruins in the area.
The Dieng Plateau is situated 2,000m above sea level. It is dotted with lakes created
by volcanic activity and geysers emitting steam, which smells of sulfur. It is well known
as a tourist destination together with Buddhist ruins.
Yogyakarta
Fig.2-1-1Location Map
4
Fig.2-1-3A fumarole
Fig.2-1-4
Fig.2-1-5
2.2
The office of the Dieng geothermal power plant is located in Dieng town, about 15
minutes drive from the power plant. The plant general manager works at the office with
a number of employees. Five employees are always stationed at the plant and are
engaged in operation control and patrolling of the steam production facilities and the
generating facilities.
The central control room, which
Generally, most of non-condensed gas included in production fluid is CO2. For this
reason, the concentration of non-condensed is a matter of great importance, when
considering CO2 emission credits.
Although the rated output of the Dieng geothermal power plant is 60MW, at present, it
operates at around 42MW. The prime cause of this low output is the stoppage of
production wells due to silica scale.
In the Dieng geothermal power plant, scale, which clings to the injection pipe, was a
large problem in the initial phase of the commercial operation, but it was solved by
measures taken afterward. Now, scale clings to geothermal fluid production wells and
the steam turbines. The main component of the scale is silica.
3.2
3.2.1
The source of the silica, component in the scale, is considered to be silica dissolved in
mist and in steam. I will explain more later using an example of Tohoku Electric Power
Co., Inc Uenotai geothermal power plant. The prime cause is considered to be that the
turbine nozzles boil the components of the steam mist and then the silica in the steam
mist precipitates and dries.
10
3.2.2
Though its route varies, scale precipitates because material that dissolves in the
solvent becomes super saturated.
Silica in geothermal fluids is balanced with quartz in a fluid reservoir at high
temperature and at high pressure, but in the process of eruption which bring it to
ground level, it changes to amorphous silica.
The solubility of silica depends on its crystal form. The solubility curb of amorphous
silica can be expressed as follows.
1400
ppm
Silica concentration
(ppm)
1200
1000
800
600
400
200
0
0
50
100
150
200
Temperature
( deg. C)
250
300
11
In the case of water-dominated fluid reservoirs, production fluid is produced with hot
water, in the state of so-called two phase flow. The more production fluid which goes
up to the ground, the less the pressure on the fluid becomes. Fluid tends to vaporize at
certain points known as the flush point.
Inside the wells, there are certain points where the internal diameter is considerably
larger, making them the flush points. Most of the time, the scale precipitates there, but
the flush points are not stationary due to other factors such as pressure in fluid
reservoirs.
The scale precipitates occur wherever the flush point may be.
Ground
Well
Scaling
Flush point
Fluid
Fluid
Multi feed points to the situation in which production fluid is taken at several points
varying in depth.
alkaline, it becomes neutral when the fluids mix. As mentioned before, the solubility of
silica is also affected by pH, and the solubility is the lowest in neutral area if
temperatures and pressures remain constant. When production fluid, super saturated
in acid and alkaline is mixed with it, it becomes super saturated, creating a huge
amount of scale. For this reason, scale precipitates. When there is a lot of precipitate,
one side of the feed point is closed off even though it results in the decline in the amount
of steam production.
Ground
Well
Scaling
FluidAlkaline
FluidAlkaline
Fluid (Acid)
Fluid (Acid)
13
Although silica scale clings to steam turbines in the Dieng geothermal power plant, it
is not yet posing a serious problem. However, since the reservoirs contain a lot of silica,
there is no denying that it will become a serious problem when supplemental
geothermal fluid production wells are drilled and put into operation.
In term of scale clinging to the steam turbines, similar problems have occurred in
Tohoku Electric Power Companys Uenotai geothermal power plant just after the start
of commercial operations. In this case, setting up turbine washing equipment worked
well. For this reason, I include the outline of the measures taken by Tohoku Electric
Power Company bearing in mind that it may be applied to the Dieng geothermal power
plant in future.
(1) Background
The Uenotai geothermal power plant [output 28.8MW(up from 27.5MW in February
in 1997)] is located in Yuzawa city in Akita prefecture.
started in March
4th
Commercial operations
Energy in charge of steam facilities and Tohoku Electric Power Co. in charge of
generating facilities.
Just after the start of operations, an opening angle of governing values rapidly
increased during the rated output operation and then the output of the generators
declined. After an inspection of the dismantled steam turbines, the cause was
ascertained to be scale, which was clinging to the first-stage nozzles at the mouth of
the steam turbines and the strainer before main stop valve. Left untouched, the steam
turbines would have needed to be dismantled for inspections and cleaning every three
months, so equipment for scale prevention was developed.
(2) The formation of scale
Silica, a component of scale, is considered to originate from silica dissolving in mist
and in steam and each precipitates as follows.
14
a. Precipitation by flush
In the main stop valvesub-stop valvestrainer, the pressure is slightly decreased,
resulting in the flush of a hot water mist. Most of the silica scale clinging to the
main stop valvesub-stop valvestrainer is caused by such a flushing mechanism.
It is assumed that silica precipitates and clings when the mist is super saturated
with the silica over a period of time.
b. Precipitation by boiling
The numerical simulation and an experiment using geothermal steam confirms
that at the steam outlet near the first-stage nozzle, the temperature of nozzle is
higher than that of steam.(Amagasa 1995) Thus, at the outlet, mist coming into
contact with and clinging to the surface of the nozzle boils and evaporates, leading
to precipitation of the dissolved components, including silica, which then dry.
Most of the silica scale found in the first-stage nozzle at the mouth of the turbine
in Uenotai was considered to have occurred by boiling.
15
the steam turbines. Furthermore, in order to prevent erosion of the steam turbine,
the moisture meter was installed at the mouth the team turbine.
Results of the water injection test
The water injection test was conducted over 7months on site by changing time
(1hour to 14days) and volume of injecting water (1.11to4.2t/h) with the following
results.
During water injections, scale keeps growing when there is less than 2.0t/h of water,
but it is contained when there is more than 2.0t/h of water.
Results of the water injection test over periods as long as 2 weeks show that an
opening angle of the governing valve continues to decline, and in some cases, the
refractory scale, including silica, is cleaned.
According to the open inspection of the steam turbine after the water injection test,
when the moisture level is below 2%( designed allowable value), there is little
erosive effect on the turbine even though water is injected for long periods of time.
Soon after the start of water injection, the opening angle of governing valves always
sharply decline. This is considered to be because soluble scale, such as NaCl, is
removed.
The use of the water injection equipment
Following various analyses based on the test results, stable operation is maintained
in the power plant today by injecting water for approximately 2hours about every 2
weeks.
(4) Conclusion
To remove scale in the Uenotai geothermal power plant, turbine-washing equipment
was installed and a water injection test was conducted. The results confirmed that
water was effective for the prevention of and cleaning of scale at 2.0t/h.
16
To Turbine Ground
Nozzle
Turbine Exhaust
System
Generator
To Flash Steam Cooler
Calorimeter
Main
Steam
System
To Cooling
Tower
Jet
Condenser
Scale
Separator
Circulating
Water System
FX233
Electromagnetic
Flowmeter
Strainer
Circulating
Water Pump
from
Production
Wells
4.1.2
Although silica scale is clinging to the turbine in the Dieng geothermal power plant,
the situation is not yet serious and problems such as a decline in output have yet occur.
However, once becomes a serious problem, the Uenotai geothermal power plant's
example could be of great help.
In such cases, the problem is how much water should be injected and at what
frequency.
This depends on the allowed moisture level which will differ according to what is made
from. Since the allowed moisture level is 2% in the Uenotai geothermal power plant, the
verification test was conducted while monitoring figures. Then, the optimum volume of
water and frequencies were confirmed. Therefore, if this equipment is installed in the
Dieng geothermal power plant, the optimum volume of water injection and frequencies
should be confirmed through similar steps taken by the Uenotai geothermal power
plant although the equipment itself is simple and doesnt require specific know-how.
17
10
Difference of
temperature
Steam
temperature at the
surface
of nozzle
Metal temperature at the surface of nozzle
-5
-10
0
10
20
30
40
50
60
70
80
90
100
Width
of a nozzle
Fig.4-1-2Steam temperature at the surface of nozzle
Metal temperature at the surface of nozzle
Scale
Steam
back
ventral
20
40
60
18
80
100
H7.03.29 - 04.06
H7.04.10 - 04.17
H7.04.24 - 05.08
H7.05.11 - 05.25
No.
No.
No.
No.
Period
2.0
2.1
1.2
1.2
Flow
rate
(t/h)
04.27
05.11
03.30
04.12
mm/dd
19
83 mmHg
90 mmHg
84 mmHg
83 mmHg
73 %
87 %
73 %
75 %
Early period
05.07
05.25
04.06
04.17
mm/dd
83 mmHg
84 mmHg
84 mmHg
83 mmHg
70 %
85 %
75 %
80 %
Latter period
1996
5.6
5.4
kscg
5.2
5.0
4.8
4.6
4.4
4.2
5
11
June
86
13
15
17
19
21 23 25
( day )
27
29
87
July
11
13
1996
70
65
60
55
50
Injection
Injection
45
Injection
40
5
June
86
11
13
15
17
19
21 23 25
( day )
27
29
11
13
11
13
July
87
Fig.4-1-5The opening angle of governing valves
1996
Condenser
Vacuum
640
630
mmHg
620
610
600
590
580
570
5
June
86
11
13
15
17
19
21 23 25 27
( day )
29
July
87
Fig.4-1-6Condenser Vacuum
20
4.2
4.2.1
As previously mentioned, the largest problem in the Dieng geothermal power plant
today is scale in geothermal fluid production wells, and chemical injection is being
considered as a countermeasure.
Here I include some alternative considerations to chemical injections.
At present, several geothermal power plants within the jurisdiction of Tohoku Electric
Power Co. have scale in wells, just like the Dieng geothermal power plant. The
component of scale differs depending on the region with calcium carbonate scale as well
as silica scale being the most common. If the main component is calcium carbonate,
injecting clean water dissolves the scale relatively easily and the volume of steam soon
recovers. On the other hand, once silica scale precipitates, it is not able to be dissolved
unless quite strong acid is used and clean water alone will be insufficient.
Therefore, in the case of silica scale, it is important to prevent precipitate from
occurring. From this point of view, innovative measures are being considered at this
point in time.
To prevent scale in turbines, precipitation can be prevented by injecting clean water into
the steam, which increases the moisture level. The basic principal is that this prevents
super saturation from occurring, which can prevent scales in wells.
Since the reaction rate of silica is fast and the stratum contains a lot of silica,
production fluid maintains balance (a saturated state) with silica included in the
stratum that is near the feed point. (A silica thermometer, which estimates
temperatures from the concentration of silica in fluid, is famous and is widely used as a
geochemical thermometer.)
In the case of sales in wells, unless precipitates occur due to the mixture of fluids
varying in pH, the cause is super saturation by flush. First and foremost, the
fundamental problem is that the production fluid is saturated with silica.
Therefore, if the production fluid in a saturated state is diluted with water, it wont
become super saturated even though flush occurs to some extent. In other words,
21
Steam
Two phase
Scaling
Flush point
Two phase
Measures
Water
injection
22
Since calcium carbonate easily dissolves in water, the method of injecting water into
wells proves effective in each geothermal power plant in Japan as a measure against
calcium carbonate scale. Facilities for silica scale are exactly the same as facilities for
calcium carbonate.
Facilities consist of an injection unit, a rewind drum, a lubricator, a coil tube, a tip
nozzle and among others.
An injection unit, which injects condensed power plant water into wells through a coil
tube, comprises of pump, pipe, various measuring instruments, and electric system.
A lubricator is a facility that fixes a coil tube and stores steam seal and a tip nozzle.
Using this, it is possible to install and collect a tube without stopping production.
Based on experience in each geothermal power plant, the best material for tubes is
INCOLOY 825, which is especially corrosion resistant..
Condensate water
Tank
Coil tube
Lubricator
INCOLOY 825
Injection unit
Injection pump
Control
panel
Tip nozzle
Injection pump
Rewind drum
23
LG
4.2.2
Prevention of scale, which works for other sites, is not always applicable because of the
regional feature. However, even if scale precipitates, it wont be a fatal obstacle for
operations of a power plant as long as scale can be removed relatively easily at low cost.
For this reason, I include how to remove scale as follows.
Generally, work over is used when scale precipitated in wells is removed. work over
removes scale by drilling with bit after the installation of rig, just like usual drilling. It
is effective when scale precipitation occurs only inside wells, but a problem is its cost.
Because rig is installed just like drilling , it requires relatively long construction periods
with a large scale facility. The construction cost is quite high. To solve this problem,
Coiled Tubing method is used in recent years. In Coiled Tubing method, a thin tube
without seams is used as if it is a wire, so drilling pipes dont need to connect and the
construction is completed for a shot period of time. With the short construction period
and simple facility, the cost is low. Furthermore, the construction is carried out while
letting steam emit, therefore the work efficiency can be judged immediately. It also
doesnt have to interfere other wells or induce emission.
Meanwhile, a drawback
load is low. If scale is solid or it has a casing trouble, a full examination is necessary
before adopting this method.
A table of comparison based on experiences in the jurisdiction of Tohoku Electric
Power Co. can be expressed as follows.
Table 4-2-2-1A table of comparison with 2,000m class production well
Rotary drilling
Coiled tubing
WaterMud
AirProduction fluid
High
Nothing
Need not
Need
Wide
Narrow
Need
Need not
2,700m
2,600m
6 hours
3 hours
100 t
45 t
60 days
10 days
0.6
Drilling fluid
Possibility of interference
Separator/Silencer
A range of ground facilities
removal
Induce emission
24
Fig.4-2-2-2Coiled Tubing
25
4.2.3
The cause of the scale problem at the Dieng geothermal power plant is not the special
mechanism but oversaturation. Tohoku Electric Power Co. now prevents scale from
occurring in its jurisdiction by injecting clean water. If this method proves effective, it
can be applied to the Dieng geothermal power plant.
With its efficiency, work over by coild tubing seems appropriate to the Dieng
geothermal power plant, which cant stop operations for a long period of time. However,
scale in wells at the Dieng geothermal power plant is considered to be hard because its
main component is silica; therefore, whether this method is applicable or not should be
decided after the experimental use.
4.3
As described before, the Dieng geothermal power plant has a huge after cooler, but a
huge cooling tower also catches our eyes. Since the total number of cooling fans amounts
to 18, cooling capability is quite high. The cooling tower was capable of cooling
circulating water from 36.1 to 18. Consequently, the vacuum level is 93.3 kPa and
the operation was carried out in a high vacuum. (almost the design value). If the
vacuum level is high, it is possible to get the large output even though the amount of
steam is the same because the adiabatic heat drop becomes large. However, the balance
with the power spent for that purpose is important. In other words, the optimum point
needs to be decided comparing the increased output because of being high vacuum and
the power that is spent for cooling fans.
Although it depends on equipment, including the deterioration level of the equipment,
the number of cooling fans is not always proportionate to the vacuum level. In addition,
the vacuum level in the condenser is not completely proportionate to the output. The
vacuum level also varies depending on whether the load is rated or partial.
Therefore, it is impossible to judge from generalization, but considering all cooling
fans in the cooling tower are operated at the partial load in the Dieng geothermal power
plant, it should be clarified how vacuum level in the condenser and net output changes
when stopping fans one by one.
26
Condenser VacuukPa
17
16
15
The number of operating cooling fan
14
Correction Coefficient
-5
-4
-3
-2
-1
0
1
98.7
97.4
96.0
94.7
93.3
92.0
90.6
89.3
27
87.9
Chapter 5
5.1
Geothermal power generation uses natural energy. It is effective for prevention of the
global warming because basically, CO2 emissions are small. For this reason, it is
positioned as a power source for CDM/JI based on the Kyoto Mechanism. As long as
conditions are met, geothermal power generation will generate CO2 credits, creating
added values.
The most fundamental condition is whether a country ratifies the United Nations
Framework Convention on Climate Change (UNFCCC) and the Kyoto Protocol.
Furthermore, whether the Designated National Authority(DNA) is set up within the
country is also a basic condition.
The Indonesian government ratified the Kyoto Protocol on December 4th in 2004.
Although it took some times to make deliberations within the country, the DNA was
officially established in Indonesia. Indonesia is now listed on the DNA list of UNFCCC.
The following describes detail information related to CDM.
(1) Ratification and participation in the UNFCCC
Indonesia signed the UNFCCC in 1992 and ratified it in accordance with the
ordinance No6.
(2) Ratification of the Kyoto Protocol
The ratification of the Kyoto Protocol had been delayed in Indonesia not by the
national resolution but by procedures related problems. Indonesia ratified the Kyoto
Protocol on December 3rd and was taken effect on March 3rd in 2005.
(3) The establishment of the DNA
The DNA was established in Indonesia in July 2005, which means Indonesia meets
conditions to participate in CDM project activities as Non AnnexParties depicted in
the Marrakesh Agreement, which includes detailed regulations of the Kyoto Protocol.
Now, Indonesia is eligible to approve CDM projects.
The DNA is a national CDM committee (NCCDM) consisting of the following 9
ministries and agencies.
28
Ministry of Environment
Ministry of Energy and Mineral resources
Ministry of Forestry
Ministry of Industry
Ministry of Foreign Affairs
National Development Planning Board)
Ministry of Home Affaires
Ministry of Transportation
Ministry of Agriculture
The deputy minister of MOE (Environmental Conservation) is appointed to the
chairman of the NCCDM.
The NCCDM comprises of standing organizations, secretariat and engineering
team. If necessary, it can seek assistance to expert advisors and stockholders
forum.
(4) Procedure for the approval of the project
Documents, which should be submitted to the DNA
The following documents should be submitted
a.
b.
c.
d.
e.
f.
Others
29
30
Project
Proponent
Secretariat
Received
application
document
Expert
Group
Evaluation
Internal
Coordination
Meeting of the
commission
Sectoral
Working
Group
5days
21days
Secretariat
Received
Evaluation
Reports
5days
31
1day
Decission-making
Meeting of the
Commission
Stakeholder Forrum
Special Meeting
Technical
Group
Evaluation
Expert
Group
Evaluation
letter of
approval
Proposed Project
does not meet
the criteria
Project
Proponent
5.2
doesnt
Although Indonesia officially established the DNA in July in 2005, staff members
were officially positioned in December. However, due to swift actions taken by the
DNA, the following 5 projects were officially approved as of January in 2006.
The project utilizing solar heat
, The project concerning cements
The project utilizing palm oil
The project utilizing methane from excrement of domestic animals
Feces and
urine
In terms of above 5 projects, Indonesia got approval from the environmental minister
and applied for the registration to the UNFCCC before the establishment of the DNA.
For this reason, the government immediately approved these projects since it was
considered that projects had been already approved (examined).
32
5.4
(1) Methodology
At present, when it comes to geothermal power generation development,ACM-0002
and AM-0019 are registered as new methodology of the UNFCC.
ACM-0002,which is based on Darajat unit III in Indonesia, evaluates generated
power as replacement to the average grid electricity by connecting to grid. Under this
methodology, geothermal power generation is not simply approved as a shift from
fossil fuel power generation.
In addition, AM-0019 is based on Lihir Project in Papua New Guinea. In this
methodology, geothermal power generation could be a replace from fossil fuel power
generation.
The registration for the DNA
When it comes to geothermal power generations, Darajat unit III project of Amoseas
Indonesia Inc.Chevrons capitalhad been applied for registration to the UNFCCC
together with the above mentioned projects. However, its PDD is being modified at
present because there was a complaint regarding how to calculate the CO2 emission
factor in the methodology. Therefore, no projects concerning geothermal power
generation have been applied to the DNA.
Chevron is in charge of
calculating
public through the DNA as official values in Indonesia. Thus the same emission
factors can be used if it connects to the same grid this year
33
The Indonesias comprehensive energy policy (February in 1998) raises the following
five items as basic policies.
Diversification of energy
Intensifying exploration of energy resources
Energy saving
Energy price (price adjustment)
Concern for the environment
(1) Water resources
Water reserves in Indonesia are assumed 8,200kW. Hydraulic power generation
34
facilities are 301.5million kW at the end of 2000 and much remains to be undeveloped,
but in Java island where demand is high, most places are already developed. Water
reserves are concentrated in Sumatra, Kalimantan, Irian Jaya, but large scale
development cannot be hoped because areas that need electricity are small and spotted.
However, small-scale water development is expected to play a large role as social
development projects.
(2) Oil
Indonesia has 5 billion barrels of oil reserves as of the end of 2001, The central part of
Sumatra has the largest oil production, followed by the north west coast of Java island,
East Kalimantan and the sea near the Natuna .
Indonesia is the only OPEC member in Asia and one of the largest oil producing
countries, but there are
35
they have been reviewed again due to the shortage of power supply in recent years.
New energy such as wind and sunlight is expected to contribute to local power supply.
The metrological agency investigates and sorts out basic data concerning new energy
and the Ministry of Energy and Mineral Resources (MEMR)gets involved in research
and development.
36
6.2
6.2.1
At present, an extension plan is under way in the Dieng geothermal power plant.
According to the schedule, No2 will start commercial operations in 2008 and No3 will be
put into operations in 2009.
This extension project includes not only the Dieng geothermal power plant but also
Patuha region that is close to Bandung. It is a large scale project including the
construction of
Bandung
2006
2007
2008
2009
2010
37
6.2.2
Project Participants
Pertamina
National oil
company
67%
National electric
company
Joint-Venture to develop
geothermal plants
PT GEO DIPA
30%
JointVenture
PT Citra
Drilling company
PT Bumigas
PT Rekayasa
EPC company
Financier
70%
Consortium
Fig.6-2-2-1Project Participants
38
33%
Planning
company
6.2.3
Power sales revenues from PLN is first deposited in the escrow account, then 60% goes
to Bumigas, 30% goes to the O&M company and 10% goes to PT GEO DIPA.
Bumigas, which receives 60%, puts this money towards covering the capital cost of the
project including interest payment.
Meanwhile, 30% of revenues is given to the O&M company, but this rate is rather high
considering the level of personnel costs. On the other hand, despite interest is set at 6%,
the capital cost is relatively low. In other words, the initial capital cost is low.
Indonesia adopts so- called External form standard taxation, imposing 6% tax on
revenue from power sales and it is coved by PT GEO DIPA, which receives 10% of
revenues. Remaining 4% is supposed to be accumulated in PT GEO DIPA as debt
reserves.
Electricity sales
National electric
company
USD
Payment
10%
Escrow
account
PT GEO DIPA
60%
30%
Planning
company
PT Bumigas
39
6.2.4
(1) Overview
The total project cost is about 500 million $. Although the cost changes depending on
the number of wells, it is calculated one unit will cost around 100 million $.
In terms of revenues stems from power sales to PLN, 60% is planning to go to Bumigas,
30% will go to O&M and remaining 10% will be earmarked to taxes and others.
There are a lot of hot springs, geysers and sulfur geysers in the Dieng geothermal
region, which suggests geothermal resources are plenty. It is estimated that geothermal
resources are at least 300MW. During the development of No1, it was turned out that
the temperature of reservoirs is 270 to 340 and the depth is 2,000 to 2600m. The
potential is high.
It is obvious that the most important thing to evaluate profitability of the project is the
accuracy of assumed income and expenses. Income is calculated by multiplying
generated electricity by electric price. Geothermal development is said to be risky
because an accurate projection is difficult. In other words, since steam production
depends on nature in geothermal power generation, production risk is high compared to
fossil fuel power generation. However, in the extension project, confirmed geothermal
resources will be used, so production risk is considered to be low.
Meanwhile, even if power is generated as expected, income will decrease unless
generated power is sold as planned, so a long term contract with the PLN, so-called the
credibility of PPA, is extremely important. In addition, interest on finances is inverse
proportion to the reliability of the project. When the reliability is high, interest is low
and income from the project becomes high. On the other hand, if the credibility is low,
interest goes up, resulting in low profitability of the project.
At a time of the financial crisis, which occurred from 1997 to 1998, PLN couldnt fulfill
its duty to buy electricity at promised prices. Consequently, it lost credibility in
international society. However, after that, the PLN re-negotiated various kinds of
long-term power sales contracts focusing on practicality. As a result, the PLN seems to
40
41
$
Discount
7 New Wells
rate
6.85% 109,182,789
10.00% 84,932,799
15.00% 59,508,206
91,811,116
73,509,870
53,480,513
120
million $
110
3 New Wells
100
No New Wells
90
80
70
60
50
5.00%
7.00%
9.00%
11.00%
13.00%
Discount rate
15.00%
17.00%
42
$
Discount
rate
5%
6.85% 109,182,789
10.00% 84,932,799
15.00% 59,508,206
Decline rate
6%
7%
106,294,469 104,482,108
82,774,984
81,353,901
58,075,470
57,102,958
8%
102,027,463
79,645,600
56,104,568
million $
110
100
90
rate:5%
rate:6%
rate:7%
rate:8%
80
70
60
50
5.00%
7.00%
9.00%
11.00%
13.00%
Discount rate
15.00%
43
17.00%
$
Discount Makeup well steam flow rate
rate
45t/h
25t/h
6.85% 109,182,789 103,928,283
10.00% 84,932,799
81,252,194
15.00% 59,508,206
57,345,119
million $
120
110
100
90
80
70
60
50
5.00%
7.00%
9.00%
11.00%
13.00%
Discount rate
15.00%
17.00%
44
d. Conclusion
I made a sensitivity analysis using parameters such as the number of wells, which
are drilled, the rate of decline and steam production when supplemental wells are
drilled. Comparing these parameters, the IRR has larger impact on the economic
efficiency of the project
When the rated output is maintained with the rate of decline at 5 % and the volume
of the production steam at 45t/h, it is worth 117million dollars if the assumed discount
rate is 6%. On the other hand, it is worth only 60million dollars if it is assumed that
the discount rate is 15%.
For this reason, projects organizers, who intend to invest into this project, need to
judge how much risk is involved in this project and how much return they hope.
When they hope around 15 % of the IRR, the value of this project has become
significantly low and it is difficult to promote it.
Judging from the construction cost of the plant, the expected IRR is considered to be
around 10%.
6.2.5
As describes above, the extension plan in this region can be judged good as a whole,
however, the necessary project cost amounts to over 60 billion yen. It is considered that
raising this amount of money depending solely on private loans involves a great deal of
risk, so financers that offered financial contributions to Bumigas have not implemented
it.
Thus, the initial plan of completing finance close in November 2005 and starting the
construction of Dieng No2 is likely to be delayed.
45
6.3
6.3.1
Overview
This region offers high potential for geothermal development and is being promoted
followed by the Dieng & Patuha extension plan.
Medan
Namora-I-Langit
Silangkitang
Sarulla
area
Eastern Sibualbuali
46
6.3.2
Development plan
In Sarulla region, 3 geothermal sites mentioned above have been confirmed, but the
current development plan only covers Silangkitang and Namora-I-Langit.
Under the plan, No.1 and No.2 of Silangkitang (50MW) will start commercial
operations in 2009, followed by No.1,2,3 of Namora-I-Langit (65MW), which will be put
into commercial operations in 2010.
Meanwhile, the Indonesian government has a strong desire to start power generation in
this region at the earliest possible time due to growing power demand in the country.
Therefore, there is another plan to start commercial operations of No.1 of Silangkitang
in FY 2007 with 25MW2.
Table 6-3-2-1A development schedule (Commercial operation start)
2009
2010
Silangkitang No.150MW
Silangkitang No.250MW
Development structure
20% of
47
Pertamina
PT Bukaka Teknik
National oil
National electric
Utama Tbk.
67%
Joint-Venture
33%
PT GEO DIPA
45%25%
20%
55%
PT Geo Sarulla
) : A future plan
Fig.6-3-3-1Project Participants
6.3.4
48
Chapter 7
7.1
Conclusion
This survey was carried out to understand the extent of the scale problem at the
Dieng geothermal power plants and its causes and to provide a basis for a detailed
examination which will lead to setting up effective countermeasures.
The survey has confirmed that the silica scale that precipitates in wells is posing a
problem at the Dieng geothermal power plant and injecting chemicals is being
examined as a countermeasure.
Once silica precipitates, it is not able to be dissolved unless quite strong acid is used,
so its countermeasures need to focus on preventing precipitate from occurring. In this
sense, the development of effective chemicals is expected.
However, even if effective chemicals to prevent scale are developed, the problem is
their cost. There are various kinds of chemicals, known as inhibitors, which work for
calcium carbonate scale, but they are not actively used because of the price.
Taking these points into account, Tohoku Electric Power Co. is trying to contain silica
scale in wells within its jurisdiction by injecting clean water. If effectiveness of this
method proves, it can be applied to geothermal power plants around the world that
have similar problems and we could do international technology transfer.
In addition, although it is not yet posing a serious problem, considering the
components of steam, silica scale clings to steam turbines might become a serious
problem at the Dieng geothermal power plant. However, there is no particular problem
in the Dieng plant, so the scale in turbines can easily removed by installing turbine
washing equipment.
7.2
When it comes to the CDM, the Designated National Authority (DNA) started to
function in December 2005 in Indonesia. We confirmed that so far the government has
approved 5 projects, but no geothermal power generation projects have obtained the
49
government approval. (One is modifying the PDD to recalculate the Emission Factor)
Once its approved as a CDM project, economic added value will be created. In this
sense, the development of the relevant project is worth watching, but the CDM is not
fully understood in Indonesia. For this reason, there is a need for us to support the
CDM in the case of new geothermal development and our active involvement is
expected.
7.3
Together with this survey, we interviewed local people concerning PT GEO DIPA, the
project entity, about the possibility of our participation in the O&M project, the matter
of participation, the possibility of capital contribution in the extension plan and
necessary procedures which will accompany it. We collected detailed information on
the Dieng & Patuha extension plan as well as the geothermal development plan in
Sarulla region.
In terms of the extension plan of the Dieng geothermal power plant, undisclosed
material on geothermal reservoir evaluation has confirmed that stem is sufficient to
build a new power plant. We realized its high potential.
Furthermore, in the Sarulla region, 50MW-worth of steam,
development of No.1 of Silangkitang, has already been confirmed. We made sure that
the construction could be carried out with low risk and at low price.
As mentioned, though geothermal recourses are rich at the surveyed site, the
development has not been made progress since the Indonesian government cannot
raise sufficient funds.
For this reason, if we make proposals to convince the Indonesian counterpart that
our participation will be beneficial to raise necessary funds, the project would be
taking a great step forward.
50
7.4
Suggestions
This survey has made us understand the high potential of geothermal resources in
Indonesia. At the same time, we realized that the construction of geothermal power
plants has not made progress since the Indonesian government cannot raise sufficient
funds.
The most effective way to break this situation is considered to be that advanced
countries provide development funds. Therefore, Japans active involvement, including
the support of the CDM, will promote the construction of geothermal power plants in
Indonesia.
Here, I include promising project plans.
First Stage(now
Preliminary
Research
Discussion with
parties concerned
Involvement of
Japanese company
Implementing
F/S
evaluation
drawing up PDD
validation
evaluation of
geothermal recourses
economic evaluation
Closing of
Finance
Final Stage
Forth Stage
Third Stage
Second Stage
implementation
investment in SPC
request to JBIC for
financing
Start of
Construction
construction consultant
plant export
completion
Start of
Commercial
Operation
Fig.7-4-1Project Flow
First Stage
This survey.
Second Stage
With the cooperation of Indonesian parties concerned, Japanese company will
conduct F/S by using public fund in FY2006. Specifically, Japanese company will draw
up PDD in CDM F/S and carry out validation. In addition, Japanese company will sort
out information that is necessary on requesting for financing to government-affiliated
financial institutions while examining Japanese companys investment possibilities of
SPC in F/S.
51
Third Stage
As a result of F/Sif Japanese company concludes that the project is promising, we
will invest in SPC in order to reap the benefit of the project. Japanese company will
also make a request to government-affiliated financial institutions for financing on
better conditions so that
company.
52
Appendix
Calculation Sheet
NPV
PV
500
600
600
700
700
0.82
100
200
70
0.67
0.72
10,062,017
0.77
10,592,379
50
60
Output
10,784,404
9,558,209
0.63
7,192,942
2013
6,859,276
0.59
11,653,987
3,000,000
7,221
2,442,971
7,325,531
24,429,709
473,040
5.16
2014
473,040
5.24
10
20
30
40
50
60
70
8,193,154
0.55
10
14,873,796
7,329
2,479,615
7,435,414
24,796,155
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Makeup wells:7
Makeup well steam flow rate45t/h
Decline rate5%
(Initial decline rate20%)
10
20
30
3,000,000
7,114
2,406,868
7,217,272
14,224,064 11,437,425
7,009
2,371,298
7,110,613
0.88
Initial
wells steam flow rate
45t/h
5%
(20%)
0.94
109,182,789
1.00
2012
473,040
5.09
23,712,984 24,068,679
14,013,856
0
300
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
100
400
200
300
500
400
Discount rate
Cashflow
6.85
0
13,155,874
Capital expenditure $
2011
473,040
5.01
6,905
6,803
t/h
Steamt/h
flow rate
13,806,755
2,336,255
2,301,729
453,543
Tax,others
2,267,713
22,677,130
O&M cost
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
7,005,530
2007
23,362,546
2006
6,902,000
2005
23,017,287
4.45
6,800,000
Year
13
0.45
12
0.48
5,945,785
0.52
6,236,328
2018
5,403,598
0.42
14
12,786,505
3,000,000
7,779
2,631,774
7,891,678
26,317,735
473,040
5.56
2019
6,310,971
0.40
15
15,956,571
6,379
2,663,667
8,010,053
26,636,669
471,697
5.65
4,909,029
0.37
16
13,262,136
3,000,000
9,530
2,711,319
8,130,204
27,113,189
473,040
5.73
2020
4,679,355
0.35
17
13,507,607
3,000,000
8,134
2,751,989
8,252,157
27,519,886
473,040
5.82
2021
5,432,293
0.32
18
16,755,221
8,256
2,793,268
8,375,939
27,932,685
473,040
5.90
2022
Discount rate.85
7,023,048
15,553,207
7,664
2,592,880
11
7,550
7,439
3,000,000
2,554,562
2,516,810
7,775,052
25,928,803
12,323,357
7,660,150
7,546,945
3,000,000
25,545,619
25,168,097
2017
473,040
5.48
12,096,903
2016
473,040
5.40
2015
473,040
5.32
Output
NPV
PV
500
600
600
700
700
Makeup wells:12
Makeup well steam flow rate
25t/h
Decline rate5%
4
0.82
10,062,017
10,592,379
2011
3,000,000
7,114
2,406,868
7,217,272
9,558,209
0.67
7,192,942
0.63
14,224,064 11,437,425
7,009
2,371,298
7,110,613
2013
6,859,276
0.59
11,653,987
3,000,000
7,221
2,442,971
7,325,531
24,429,709
473,040
5.16
2014
471,643
5.24
10
20
30
40
50
60
70
6,505,133
0.55
10
11,809,374
3,000,000
5,865
2,472,295
7,435,414
24,722,948
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
10
20
30
2012
473,040
5.09
23,712,984 24,068,679
473,040
5.01
50
100
200
70
6
0.72
5
0.77
60
Output
10,784,404
Initial
wells steam flow rate
12
25t/h
5%
(20%)
103,928,283
0.88
0
14,013,856
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
0
300
100
400
200
300
500
400
0.94
Discount rate
1.00
0
13,155,874
Cashflow
6,905
6,803
Capital expenditure $
Steamt/h
flow rate t/h
13,806,755
2,336,255
2,301,729
453,543
7,005,530
6,902,000
6,800,000
2,267,713
23,362,546
23,017,287
22,677,130
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
Tax,others
2007
6.85
2006
4.45
2005
O&M cost
Year
2018
473,040
5.56
2019
473,040
5.65
473,040
5.73
2020
473,040
5.82
2021
473,040
5.90
2022
Discount rate.85
5,944,143
6,158,353
13
5,668,399
0.45
5,403,598
0.42
14
3,000,000
5,150,837
0.40
15
3,000,000
4,909,590
0.37
16
3,000,000
4,679,355
0.35
17
3,000,000
4,459,649
0.32
18
3,000,000
12
0.48
11
0.52
3,000,000
8,256
2,793,268
3,000,000
8,134
2,751,989
8,014
2,711,319
3,000,000
7,895
2,671,250
11,945,651
7,779
2,631,774
8,375,939
7,664
2,592,880
8,252,157
10,955
8,130,204
2,554,562
8,010,053
5,499
7,891,678
2,499,788
7,775,052
7,660,150
7,546,945
2016
473,040
5.40
2015
469,841
5.32
24,997,884
Output
NPV
PV
Makeup wells:3
Makeup well steam flow rate
45t/h
Decline rate5%
4
0.82
10,062,017
10,592,379
2011
2012
473,040
5.09
3,000,000
7,114
2,406,868
7,217,272
9,558,209
0.67
7,192,942
0.63
2013
8,391,669
0.59
14,257,538
-1,790
2,397,920
7,325,531
23,979,199
464,317
5.16
2014
441,101
5.24
10
20
30
40
50
60
70
7,376,627
0.55
10
13,391,480
-17,145
2,312,194
7,435,414
23,121,943
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
10
20
14,224,064 11,437,425
7,009
2,371,298
7,110,613
23,712,984 24,068,679
473,040
5.01
30
40
50
100
200
70
6
0.72
5
0.77
60
Output
10,784,404
Initial wells
steam flow rate
45t/h
5%
(20%)
102,969,672
0.88
0
14,013,856
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
300
0
100
400
200
300
400
500
500
600
600
700700
0.94
Discount rate
1.00
0
13,155,874
Cashflow
6,905
6,803
Capital expenditure $
Steamt/h
flow rate t/h
13,806,755
2,336,255
2,301,729
453,543
7,005,530
6,902,000
6,800,000
2,267,713
23,362,546
23,017,287
22,677,130
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
Tax,others
2007
6.85
2006
4.45
2005
O&M cost
Year
6,516,759
6,029,036
5,702,025
0.45
13
12,627,677
2,265,104
7,775,052
22,651,036
2018
4,978,946
0.42
14
11,781,654
-16,195
2,184,126
7,891,678
21,841,262
392,579
5.56
4,054,717
0.40
15
10,251,889
3,000,000
36,473
2,366,491
8,010,053
23,664,906
419,071
5.65
2019
4,469,520
0.37
16
12,074,767
-24,851
2,242,235
8,130,204
22,422,355
391,200
5.73
2020
3,887,759
0.35
17
11,222,555
-16,032
2,162,076
8,252,157
21,620,756
371,640
5.82
2021
2022
353,058
5.90
3,372,663
0.32
18
10,402,552
-15,459
2,084,781
8,375,939
20,847,814
Discount rate.85
12
0.48
11
0.52
-25,168
32,546
13,506,768
2,349,083
2,474,922
3,000,000
7,660,150
7,546,945
11,694,810
-16,796
23,490,834
24,749,223
2017
413,241
5.48
2016
434,991
5.40
2015
465,167
5.32
Output
NPV
PV
Makeup wells:0
Decline rate5%
(Initial decline rate20%)
10,062,017
10,592,379
100
200
70
6
0.72
5
0.77
2011
2012
449,915
5.09
-16,418
2,289,207
7,217,272
9,558,209
0.67
8,428,462
0.63
14,224,064 13,402,012
7,009
2,371,298
7,110,613
23,712,984 22,892,074
473,040
5.01
2013
7,390,858
0.59
12,557,150
-16,368
2,207,368
7,325,531
22,073,682
427,420
5.16
2014
406,049
5.24
10
20
30
40
50
60
70
6,464,969
0.55
10
11,736,462
-15,783
2,128,455
7,435,414
21,284,548
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
10
20
30
40
50
60
Output
10,784,404
0.82
5%
(20%)
91,811,116
0.88
0
14,013,856
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
0
300
100
400
200
300
400
500
500
600
600
700
700
0.94
Discount rate
1.00
0
13,155,874
Cashflow
6,905
6,803
Capital expenditure $
Steam t/h
flow rate t/h
13,806,755
2,336,255
2,301,729
453,543
7,005,530
6,902,000
6,800,000
2,267,713
23,362,546
23,017,287
22,677,130
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
Tax,others
2007
6.85
2006
4.45
2005
O&M cost
Year
2018
330,729
5.56
2019
314,193
5.65
298,483
5.73
2020
283,559
5.82
2021
269,381
5.90
2022
Discount rate.85
4,904,632
5,639,669
4,250,562
0.45
13
9,413,273
-14,150
1,908,242
7,775,052
3,669,097
0.42
14
8,682,165
-13,644
1,840,022
7,891,678
3,152,713
0.40
15
7,971,275
-13,156
1,774,241
8,010,053
2,694,642
0.37
16
7,279,791
-12,686
1,710,812
8,130,204
2,288,797
0.35
17
6,606,931
-12,232
1,649,651
8,252,157
1,929,707
0.32
18
5,951,936
-11,795
1,590,676
8,375,939
12
0.48
11
0.52
0
10,165,440
-14,674
-15,218
0
1,978,991
2,052,363
10,939,536
7,660,150
7,546,945
2016
366,459
5.40
2015
385,746
5.32
20,523,625
Output
0.72
10,062,017
0.77
10,592,379
Makeup wells:0
Decline rate8%
(Initial decline rate20%)
100
200
10
20
30
40
50
2011
2012
408,624
5.09
7,217,272
-29,479
2,079,112
8,701,999
0.67
7,247,522
0.63
12,949,894 11,524,211
-21,950
2,226,506
7,110,613
22,265,063 20,791,116
444,156
5.01
2013
5,988,934
0.59
10,175,266
-27,527
1,941,474
7,325,531
19,414,744
375,934
5.16
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
0
300
100
400
200
300
400
500
500
600
8%
(20%)
Output
60
14,013,856
13,806,755
600
73,269,947
10,784,404
0.82
70
0.88
6,905
6,803
700
700
Steam t/h
flow rate t/h
NPV
PV
0.94
Discount rate
1.00
13,155,874
Cashflow
6.85
Capital expenditure $
453,543
7,005,530
2,336,255
6,902,000
2,301,729
23,362,546
23,017,287
22,677,130
6,800,000
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
2,267,713
2007
2006
2005
Tax,others
4.45
O&M cost
Year
10
20
30
40
50
60
70
4,906,281
0.55
10
8,906,830
-25,705
1,812,949
7,435,414
18,129,488
345,859
5.24
Output
-22,414
0
6,590,001
12
0.48
3,179,550
-24,003
0
7,713,442
11
0.52
3,976,518
2017
2,497,856
0.45
13
5,531,738
-20,931
1,476,207
7,775,052
14,762,066
269,316
5.48
2018
1,916,162
0.42
14
4,534,203
-19,545
1,378,482
7,891,678
13,784,817
247,771
5.56
2019
1,421,157
0.40
15
3,593,235
-18,251
1,287,226
8,010,053
12,872,263
227,949
5.65
2020
1,001,246
0.37
16
2,704,946
-17,043
1,202,012
8,130,204
12,020,119
209,713
5.73
2021
646,325
0.35
17
1,865,706
-15,915
1,122,439
8,252,157
11,224,387
192,936
5.82
2022
177,501
5.90
347,598
0.32
18
1,072,121
-14,861
1,048,133
8,375,939
10,481,332
7,660,150
1,580,860
7,546,945
15,808,595
16,929,316
1,692,932
2016
292,735
5.40
2015
318,190
5.32
Discount rate.85
NPV
PV
600
500
600
700
700
0.88
0.82
100
200
70
0.67
0.72
10,062,017
0.77
10,592,379
7,542,286
0.63
6,859,276
0.59
11,653,987
3,000,000
7,221
2,442,971
7,325,531
24,429,709
2014
473,040
5.24
10
20
30
40
50
60
70
6,540,619
0.55
10
11,873,796
3,000,000
7,329
2,479,615
7,435,414
24,796,155
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
10
2013
473,040
5.16
20
30
7,192,942
40
Total
steam flow rate
50
60
Output
10,784,404
Makeup wells:12
Makeup well steam flow rate45t/h
Decline rate8%
(Initial decline rate20%)
0.94
3,000,000
7,114
2,406,868
7,217,272
11,224,064 11,437,425
3,000,000
7,009
2,371,298
7,110,613
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
0
300
12
45t/h
8%
(20%)
102,027,463
1.00
2012
473,040
5.09
23,712,984 24,068,679
14,013,856
100
400
200
300
500
400
Discount rate
Cashflow
6.85
0
13,155,874
Capital expenditure $
2011
473,040
5.01
6,905
6,803
t/h
Steamt/h
flow rate
13,806,755
2,336,255
2,301,729
453,543
Tax,others
2,267,713
22,677,130
O&M cost
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
7,005,530
2007
23,362,546
2006
6,902,000
2005
23,017,287
4.45
6,800,000
Year
13
0.45
12
0.48
5,945,785
0.52
6,236,328
2018
5,403,598
0.42
14
12,786,505
3,000,000
7,779
2,631,774
7,891,678
26,317,735
473,040
5.56
2019
5,150,837
0.40
15
13,023,303
3,000,000
7,895
2,671,250
8,010,053
26,712,501
473,040
5.65
4,909,590
0.37
16
13,263,652
3,000,000
8,014
2,711,319
8,130,204
27,113,189
473,040
5.73
2020
4,679,355
0.35
17
13,507,607
3,000,000
8,134
2,751,989
8,252,157
27,519,886
473,040
5.82
2021
4,459,649
0.32
18
13,755,221
3,000,000
8,256
2,793,268
8,375,939
27,932,685
473,040
5.90
2022
Discount rate.85
5,668,399
12,553,207
3,000,000
7,664
2,592,880
11
7,550
7,439
3,000,000
2,554,562
2,516,810
7,775,052
25,928,803
12,323,357
7,660,150
7,546,945
3,000,000
25,545,619
25,168,097
2017
473,040
5.48
12,096,903
2016
473,040
5.40
2015
473,040
5.32
Output
NPV
PV
600
500
600
700
700
100
200
3002008
100
2012
3,000,000
7,114
2,406,868
7,217,272
7,542,286
0.67
7,192,942
0.63
11,224,064 11,437,425
3,000,000
7,009
2,371,298
7,110,613
23,712,984 24,068,679
473,040
5.09
2013
6,859,276
0.59
11,653,987
3,000,000
7,221
2,442,971
7,325,531
24,429,709
473,040
5.16
10
Initial
wells steam flow rate
20
30
40
Total
steam flow rate
50
60
70
10,062,017
10,592,379
Output
10,784,404
6
0.72
5
0.77
2011
473,040
5.01
2014
473,040
5.24
10
20
30
40
50
60
70
6,540,619
0.55
10
11,873,796
3,000,000
7,329
2,479,615
7,435,414
24,796,155
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Makeup wells:10
Makeup well steam flow rate
45t/h
Decline rate7%
4
0.82
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
10
45t/h
7%
(20%)
104,482,108
0.88
0
14,013,856
400
200
500
300
400
0.94
Discount rate
1.00
0
13,155,874
Cashflow
6,905
6,803
Capital expenditure $
t/h
Steamt/h
flow rate
13,806,755
2,336,255
2,301,729
453,543
7,005,530
6,902,000
6,800,000
2,267,713
23,362,546
23,017,287
22,677,130
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
Tax,others
2007
6.85
2006
4.45
2005
O&M cost
Year
2019
473,040
5.65
2020
473,040
5.73
2021
473,040
5.82
2022
470,265
5.90
2,554,562
8,321
3,000,000
2,512,959
6,669
0
3,000,000
7,664
2,592,880
7,775,052
3,000,000
7,779
2,631,774
7,891,678
3,000,000
7,895
2,671,250
8,010,053
3,000,000
8,014
2,711,319
8,130,204
3,000,000
8,134
2,751,989
8,252,157
4,979
2,776,883
8,375,939
5,945,414
7,765,449
13
5,668,399
0.45
14
5,403,598
0.42
15
5,150,837
0.40
16
4,909,590
0.37
17
4,679,355
0.35
18
0.32
5,385,544
12
0.48
11
0.52
7,660,150
7,546,945
15,063,013
2017
473,040
5.48
Discount rate.85
2016
473,040
5.40
2015
472,316
5.32
25,129,586
Output
NPV
PV
600
500
600
700
700
100
200
0
300
2008
0.88
0.82
7,542,286
0.63
2013
8,625,009
0.59
14,653,987
7,221
2,442,971
7,325,531
24,429,709
473,040
5.16
2014
473,040
5.24
10
20
30
40
50
60
70
6,540,619
0.55
10
11,873,796
3,000,000
7,329
2,479,615
7,435,414
24,796,155
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
10
Initial
wells steam flow rate
20
30
7,192,942
40
Total
steam flow rate
50
60
70
0.67
0.72
10,062,017
0.77
10,592,379
Output
10,784,404
Makeup wells:9
Makeup well steam flow rate45t/h
Decline rate6%
(Initial decline rate20%)
0.94
3,000,000
7,114
2,406,868
7,217,272
11,224,064 11,437,425
3,000,000
7,009
2,371,298
7,110,613
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
9
45t/h
6%
(20%)
106,294,469
1.00
2012
473,040
5.09
23,712,984 24,068,679
14,013,856
100
400
200
300
500
400
Discount rate
Cashflow
6.85
0
13,155,874
Capital expenditure $
2011
473,040
5.01
6,905
6,803
t/h
Steamt/h
flow rate
13,806,755
2,336,255
2,301,729
453,543
Tax,others
2,267,713
22,677,130
O&M cost
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
7,005,530
2007
23,362,546
2006
6,902,000
2005
23,017,287
4.45
6,800,000
Year
Output
13
0.45
12
0.48
7,353,984
0.52
6,236,328
2018
5,403,598
0.42
14
12,786,505
3,000,000
7,779
2,631,774
7,891,678
26,317,735
473,040
5.56
2019
5,150,837
0.40
15
13,023,303
3,000,000
7,895
2,671,250
8,010,053
26,712,501
473,040
5.65
2020
6,003,844
0.37
16
16,219,866
7,019
2,706,343
8,130,204
27,063,432
472,172
5.73
2021
4,679,010
0.35
17
13,506,612
3,000,000
9,129
2,751,989
8,252,157
27,519,886
473,040
5.82
5,667,564
12,551,359
3,000,000
9,512
2,592,880
11
5,702
7,439
0
2,545,319
2,516,810
7,775,052
25,928,803
15,242,019
7,660,150
7,546,945
3,000,000
25,453,189
25,168,097
2017
473,040
5.48
12,096,903
2016
471,328
5.40
2015
473,040
5.32
4,459,649
0.32
18
13,755,221
3,000,000
8,256
2,793,268
8,375,939
27,932,685
473,040
5.90
2022
Discount rate.85
NPV
PV
0.75
Makeup
wells:7
Makeup
well steam flow rate45t/h
45t/h
5%
Decline
rate5%
(20%)
(Initial
decline rate20%)
8,029,113
5,869,208
0.51
2013
5,436,671
0.47
11,653,987
3,000,000
7,221
2,442,971
7,325,531
24,429,709
473,040
5.16
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Makeup
wells steam flow rate
10
20
30
50
100
200
70
0.56
0.62
8,701,502
0.68
9,430,199
Output
60
9,884,203
3,000,000
7,114
2,406,868
7,217,272
14,224,064 11,437,425
7,009
2,371,298
7,110,613
Total
steam40flow rate
0.83
Initial
wells steam
flow rate
45t/h
5%
(20%)
0.91
84,932,799
1.00
2012
473,040
5.09
23,712,984 24,068,679
14,013,856
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
0
300
100
400
200
300
400
500
500
600
600
700
700
Discount rate
Cashflow
10
0
13,155,874
Capital expenditure $
2011
473,040
5.01
6,905
6,803
Steamt/h
flow rate t/h
13,806,755
2,336,255
2,301,729
453,543
Tax,others
2,267,713
22,677,130
O&M cost
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
7,005,530
2007
23,362,546
2006
6,902,000
2005
23,017,287
4.45
6,800,000
Year
10
20
30
40
50
60
70
6,307,942
0.42
10
14,873,796
7,329
2,479,615
7,435,414
24,796,155
473,040
5.24
Output
13
0.32
12
0.35
4,319,261
0.39
4,663,880
2018
3,703,795
0.29
14
12,786,505
3,000,000
7,779
2,631,774
7,891,678
26,317,735
473,040
5.56
2019
4,201,864
0.26
15
15,956,571
6,379
2,663,667
8,010,053
26,636,669
471,697
5.65
2020
3,174,850
0.24
16
13,262,136
3,000,000
9,530
2,711,319
8,130,204
27,113,189
473,040
5.73
2021
2,939,649
0.22
17
13,507,607
3,000,000
8,134
2,751,989
8,252,157
27,519,886
473,040
5.82
4,955,731
15,553,207
7,664
2,592,880
11
7,550
7,439
3,000,000
2,554,562
2,516,810
7,775,052
25,928,803
12,323,357
7,660,150
7,546,945
3,000,000
25,545,619
25,168,097
2017
473,040
5.48
12,096,903
2016
473,040
5.40
2015
473,040
5.32
3,314,931
0.20
18
16,755,221
8,256
2,793,268
8,375,939
27,932,685
473,040
5.90
2022
Discount rate
NPV
PV
500
600
600
700
700
8,701,502
9,430,199
2011
2012
473,040
5.09
3,000,000
7,114
2,406,868
7,217,272
8,029,113
0.56
2013
5,436,671
0.47
11,653,987
3,000,000
7,221
2,442,971
7,325,531
24,429,709
473,040
5.16
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
5,869,208
0.51
14,224,064 11,437,425
7,009
2,371,298
7,110,613
23,712,984 24,068,679
473,040
5.01
Makeup
wells steam flow rate
Makeup
wells:12
12
Makeup
well steam flow rate
25t/h
5%
25t/h
(20%)
Decline
rate5%
10
20
30
40
Total
steam flow
rate
50
100
200
70
6
0.62
5
0.68
60
Output
9,884,203
0.75
Initial
wells
steam flow
12
25t/h
5%
(20%)
81,252,194
0.83
0
14,013,856
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
0
300
100
400
200
300
500
400
0.91
Discount rate
1.00
0
13,155,874
Cashflow
6,905
6,803
Capital expenditure $
t/h
Steam t/h
flow rate
13,806,755
2,336,255
2,301,729
453,543
7,005,530
6,902,000
6,800,000
2,267,713
23,362,546
23,017,287
22,677,130
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
Tax,others
2007
10
2006
4.45
2005
O&M cost
Year
10
20
30
40
50
60
70
5,008,328
0.42
10
11,809,374
3,000,000
5,865
2,472,295
7,435,414
24,722,948
471,643
5.24
3,000,000
4,318,068
4,605,566
2018
2019
473,040
5.65
2020
473,040
5.73
2021
473,040
5.82
2022
473,040
5.90
3,000,000
7,779
2,631,774
7,891,678
3,000,000
7,895
2,671,250
8,010,053
3,000,000
8,014
2,711,319
8,130,204
3,000,000
8,134
2,751,989
8,252,157
3,000,000
8,256
2,793,268
8,375,939
3,999,839
0.32
13
3,703,795
0.29
14
3,429,443
0.26
15
3,175,213
0.24
16
2,939,649
0.22
17
2,721,397
0.20
18
2,592,880
7,775,052
473,040
5.56
Discount rate
12
0.35
11
0.39
3,000,000
10,955
5,499
12,319,953
2,554,562
2,499,788
3,000,000
7,660,150
7,546,945
11,945,651
7,664
25,545,619
24,997,884
2017
473,040
5.48
2016
473,040
5.40
2015
469,841
5.32
Outpu
t
NPV
PV
500
600
600
700
700
8,701,502
9,430,199
10
20
2012
473,040
5.09
3,000,000
7,114
2,406,868
7,217,272
8,029,113
0.56
2013
6,651,247
0.47
14,257,538
-1,790
2,397,920
7,325,531
23,979,199
464,317
5.16
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
5,869,208
0.51
14,224,064 11,437,425
7,009
2,371,298
7,110,613
23,712,984 24,068,679
Makeup
wells steam flow rate
Makeup
wells:3
Makeup
well steam flow rate
45t/h
5%
45t/h
(20%)
Decline
rate5%
2011
473,040
5.01
Total
steam flow
30
40
50
100
200
70
6
0.62
5
0.68
60
Output
9,884,203
0.75
Initial
wells
steam flow
45t/h
5%
(20%)
81,014,645
0.83
0
14,013,856
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
0
300
100
400
200
300
500
400
0.91
Discount rate
1.00
0
13,155,874
Cashflow
6,905
6,803
Capital expenditure $
Steamt/h
flow rate t/h
13,806,755
2,336,255
2,301,729
453,543
7,005,530
6,902,000
6,800,000
2,267,713
23,362,546
23,017,287
22,677,130
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
Tax,others
2007
10
2006
4.45
2005
O&M cost
Year
10
20
30
40
50
60
70
5,679,295
0.42
10
13,391,480
-17,145
2,312,194
7,435,414
23,121,943
441,101
5.24
Output
4,734,040
4,508,855
2018
2019
419,071
5.65
2020
391,200
5.73
2021
371,640
5.82
2022
353,058
5.90
-16,195
2,184,126
7,891,678
3,000,000
36,473
2,366,491
8,010,053
-24,851
2,242,235
8,130,204
-16,032
2,162,076
8,252,157
-15,459
2,084,781
8,375,939
4,023,567
0.32
13
3,412,725
0.29
14
2,699,643
0.26
15
2,890,603
0.24
16
2,442,355
0.22
17
2,058,089
0.20
18
2,265,104
7,775,052
392,579
5.56
12
0.35
11
0.39
-25,168
32,546
13,506,768
2,349,083
2,474,922
3,000,000
7,660,150
7,546,945
11,694,810
-16,796
23,490,834
24,749,223
2017
413,241
5.48
2016
434,991
5.40
2015
465,167
5.32
Discount rate
NPV
500
600
100
200
2011
2012
449,915
5.09
-16,418
2,289,207
7,217,272
8,029,113
0.56
6,877,351
0.51
14,224,064 13,402,012
7,009
2,371,298
7,110,613
23,712,984 22,892,074
473,040
5.01
2013
5,858,003
0.47
12,557,150
-16,368
2,207,368
7,325,531
22,073,682
427,420
5.16
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
10
20
30
Output
40
Initial wells
steam flow 0
Makeup
wells:0
Decline
rate5%
5%
(20%)
(Initial
decline rate20%)
5%
(20%)
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
0
300
100
400
200
300
500
400
50
60
8,701,502
9,430,199
600
73,509,870
9,884,203
6
0.62
5
0.68
70
4
0.75
0
14,013,856
700
700
Steamt/h
flow rate t/h
PV
0.83
Discount rate
0.91
Cashflow
1.00
0
13,155,874
Capital expenditure $
6,905
6,803
13,806,755
2,336,255
2,301,729
453,543
7,005,530
6,902,000
6,800,000
2,267,713
23,362,546
23,017,287
22,677,130
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
Tax,others
2007
10
2006
4.45
2005
O&M cost
Year
10
20
30
40
50
60
70
4,977,405
0.42
10
11,736,462
-15,783
2,128,455
7,435,414
21,284,548
406,049
5.24
Output
-14,674
-15,218
3,562,925
4,217,665
2017
2018
330,729
5.56
2019
314,193
5.65
2020
298,483
5.73
2021
283,559
5.82
2022
269,381
5.90
2,999,359
0.32
13
9,413,273
-14,150
1,908,242
7,775,052
2,514,914
0.29
14
8,682,165
-13,644
1,840,022
7,891,678
2,099,086
0.26
15
7,971,275
-13,156
1,774,241
8,010,053
1,742,724
0.24
16
7,279,791
-12,686
1,710,812
8,130,204
1,437,861
0.22
17
6,606,931
-12,232
1,649,651
8,252,157
1,177,559
0.20
18
5,951,936
-11,795
1,590,676
8,375,939
348,136
5.48
12
0.35
11
0.39
1,978,991
2,052,363
10,165,440
7,660,150
7,546,945
19,789,906
20,523,625
10,939,536
2016
366,459
5.40
2015
385,746
5.32
Discount rate
NPV
100
200
2011
2012
408,624
5.09
-29,479
2,079,112
7,217,272
7,309,877
0.56
5,913,743
0.51
12,949,894 11,524,211
-21,950
2,226,506
7,110,613
22,265,063 20,791,116
444,156
5.01
2013
375,934
5.16
4,746,837
0.47
10,175,266
-27,527
1,941,474
7,325,531
19,414,744
10
20
30
Output
40
50
Makeup
wells:0
8%rate5%
Decline
(20%)
(Initial
decline rate20%)
8%
(20%)
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
300
0
100
400
200
300
400
500
500
600
60
8,701,502
9,430,199
600
60,335,226
9,884,203
6
0.62
5
0.68
70
4
0.75
0
14,013,856
700
700
Steamt/h
flow rate t/h
PV
0.83
Discount rate
0.91
Cashflow
1.00
0
13,155,874
Capital expenditure $
6,905
6,803
13,806,755
2,336,255
2,301,729
453,543
7,005,530
6,902,000
6,800,000
2,267,713
23,362,546
23,017,287
22,677,130
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
Tax,others
2007
10
2006
4.45
2005
O&M cost
Year
10
20
30
40
50
60
70
3,777,365
0.42
10
8,906,830
-25,705
1,812,949
7,435,414
18,129,488
345,859
5.24
Output
-22,414
-24,003
2,309,755
2,973,866
2017
2018
247,771
5.56
2019
227,949
5.65
2020
209,713
5.73
2021
192,936
5.82
2022
177,501
5.90
1,762,582
0.32
13
5,531,738
-20,931
1,476,207
7,775,052
1,313,397
0.29
14
4,534,203
-19,545
1,378,482
7,891,678
946,211
0.26
15
3,593,235
-18,251
1,287,226
8,010,053
647,543
0.24
16
2,704,946
-17,043
1,202,012
8,130,204
406,032
0.22
17
1,865,706
-15,915
1,122,439
8,252,157
212,113
0.20
18
1,072,121
-14,861
1,048,133
8,375,939
269,316
5.48
12
0.35
11
0.39
1,580,860
1,692,932
6,590,001
7,660,150
7,546,945
15,808,595
16,929,316
7,713,442
2016
292,735
5.40
2015
318,190
5.32
Discount rate
NPV
PV
500
600
600
700
700
8,701,502
9,430,199
100
200
70
6
0.62
5
0.68
3,000,000
7,114
2,406,868
7,217,272
6,335,692
0.56
5,869,208
0.51
11,224,064 11,437,425
3,000,000
7,009
2,371,298
7,110,613
2013
5,436,671
0.47
11,653,987
3,000,000
7,221
2,442,971
7,325,531
24,429,709
473,040
5.16
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Makeup
wells steam flow rate
Makeup
wells:12
12
Makeup
well steam flow
rate
45t/h
8%
45t/h
(20%)
Decline
rate8%
10
2012
473,040
5.09
20
30
2011
473,040
5.01
23,712,984 24,068,679
40
Total
steam flow
50
Output
60
9,884,203
0.75
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
0
300
12
45t/h
8%
(20%)
79,645,600
0.83
0
14,013,856
100
400
200
300
500
400
0.91
Discount rate
1.00
0
13,155,874
Cashflow
6,905
6,803
Capital expenditure $
Steamt/h
flow rate t/h
13,806,755
2,336,255
2,301,729
453,543
7,005,530
6,902,000
6,800,000
2,267,713
23,362,546
23,017,287
22,677,130
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
Tax,others
2007
10
2006
4.45
2005
O&M cost
Year
10
20
30
40
50
60
70
5,035,649
0.42
10
11,873,796
3,000,000
7,329
2,479,615
7,435,414
24,796,155
473,040
5.24
Output
3,000,000
4,319,261
4,663,880
2018
2019
473,040
5.65
2020
473,040
5.73
2021
473,040
5.82
2022
473,040
5.90
3,000,000
7,779
2,631,774
7,891,678
3,000,000
7,895
2,671,250
8,010,053
3,000,000
8,014
2,711,319
8,130,204
3,000,000
8,134
2,751,989
8,252,157
3,000,000
8,256
2,793,268
8,375,939
3,999,839
0.32
13
3,703,795
0.29
14
3,429,443
0.26
15
3,175,213
0.24
16
2,939,649
0.22
17
2,721,397
0.20
18
2,592,880
7,775,052
473,040
5.56
12
0.35
11
0.39
3,000,000
7,550
7,439
12,323,357
2,554,562
2,516,810
3,000,000
7,660,150
7,546,945
12,096,903
7,664
25,545,619
25,168,097
2017
473,040
5.48
2016
473,040
5.40
2015
473,040
5.32
Discount rate
NPV
PV
500
600
600
700
700
Makeup wells:10
Makeup well steam flow rate
45t/h
Decline rate7%
8,701,502
9,430,199
100
200
70
6
0.62
5
0.68
2011
3,000,000
7,114
2,406,868
7,217,272
6,335,692
0.56
5,869,208
0.51
11,224,064 11,437,425
3,000,000
7,009
2,371,298
7,110,613
5,436,671
0.47
11,653,987
3,000,000
7,221
2,442,971
7,325,531
2014
473,040
5.24
10
20
30
40
50
60
70
5,035,649
0.42
10
11,873,796
3,000,000
7,329
2,479,615
7,435,414
24,796,155
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
10
2013
473,040
5.16
24,429,709
20
2012
473,040
5.09
23,712,984 24,068,679
473,040
5.01
30
40
50
60
Output
9,884,203
0.75
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
0
300
10
45t/h
7%
(20%)
81,353,901
0.83
0
14,013,856
100
400
200
300
500
400
0.91
Discount rate
1.00
0
13,155,874
Cashflow
6,905
6,803
Capital expenditure $
t/h
Steam t/h
flow rate
13,806,755
2,336,255
2,301,729
453,543
7,005,530
6,902,000
6,800,000
2,267,713
23,362,546
23,017,287
22,677,130
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
Tax,others
2007
10
2006
4.45
2005
O&M cost
Year
8,321
6,669
4,318,991
5,807,444
2017
2018
473,040
5.56
2019
473,040
5.65
2020
473,040
5.73
2021
473,040
5.82
2022
470,265
5.90
3,000,000
7,779
2,631,774
7,891,678
3,000,000
7,895
2,671,250
8,010,053
3,000,000
8,014
2,711,319
8,130,204
3,000,000
8,134
2,751,989
8,252,157
4,979
2,776,883
8,375,939
3,999,839
0.32
13
3,703,795
0.29
14
3,429,443
0.26
15
3,175,213
0.24
16
2,939,649
0.22
17
3,286,404
0.20
18
3,000,000
7,664
2,592,880
7,775,052
473,040
5.48
Discount rate
12
0.35
11
0.39
3,000,000
2,554,562
2,512,959
12,322,587
7,660,150
7,546,945
25,545,619
25,129,586
15,063,013
2016
473,040
5.40
2015
472,316
5.32
Output
NPV
PV
500
600
600
700
700
6
0.62
8,701,502
5
0.68
9,430,199
7,217,272
3,000,000
6,335,692
0.56
5,869,208
0.51
7,325,531
6,836,193
0.47
14,653,987
7,221
2,442,971
2014
100
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Makeup wells:9
Makeup well steam flow rate
45t/h
Decline rate6%
10
20
40
50
60
70
5,035,649
0.42
10
11,873,796
3,000,000
7,329
2,479,615
7,435,414
24,796,155
473,040
5.24
200
10
2013
473,040
5.16
24,429,709
20
30
7,114
2,406,868
11,224,064 11,437,425
3,000,000
7,009
2,371,298
7,110,613
23,712,984 24,068,679
50
60
Output
70
14,013,856
13,806,755
2012
473,040
5.09
30
9,884,203
0.75
2011
473,040
5.01
0
0
300
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
9
45t/h
6%
(20%)
82,774,984
0.83
6,905
6,803
100
400
200
300
500
400
0.91
Discount rate
1.00
13,155,874
Cashflow
10
453,543
Capital expenditure $
7,005,530
2,336,255
6,902,000
2,301,729
23,362,546
23,017,287
22,677,130
Steamt/h
flow rate t/h
6,800,000
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
2,267,713
2007
2006
2005
Tax,others
4.45
O&M cost
Year
5,702
0
15,242,019
12
0.35
5,342,235
7,439
3,000,000
12,096,903
11
0.39
4,663,880
2017
3,999,250
0.32
13
12,551,359
3,000,000
9,512
2,592,880
7,775,052
25,928,803
473,040
5.48
2018
3,703,795
0.29
14
12,786,505
3,000,000
7,779
2,631,774
7,891,678
26,317,735
473,040
5.56
2019
3,429,443
0.26
15
13,023,303
3,000,000
7,895
2,671,250
8,010,053
26,712,501
473,040
5.65
3,882,907
0.24
16
16,219,866
7,019
2,706,343
8,130,204
27,063,432
472,172
5.73
2020
2,939,432
0.22
17
13,506,612
3,000,000
9,129
2,751,989
8,252,157
27,519,886
473,040
5.82
2021
2,721,397
0.20
18
13,755,221
3,000,000
8,256
2,793,268
8,375,939
27,932,685
473,040
5.90
2022
Discount rate
7,660,150
2,545,319
7,546,945
25,453,189
25,168,097
2,516,810
2016
471,328
5.40
2015
473,040
5.32
Output
NPV
PV
500
600
600
700
700
6,967,363
7,894,057
Makeup
wells:7
Makeup
well steam flow rate
45t/h
5%
45t/h
(20%)
Decline
rate5%
2011
2012
473,040
5.09
3,000,000
7,114
2,406,868
7,217,272
6,149,455
0.43
2013
3,809,709
0.33
11,653,987
3,000,000
7,221
2,442,971
7,325,531
24,429,709
473,040
5.16
2014
473,040
5.24
10
20
30
40
50
60
70
4,228,061
0.28
10
14,873,796
7,329
2,479,615
7,435,414
24,796,155
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
4,299,752
0.38
14,224,064 11,437,425
7,009
2,371,298
7,110,613
23,712,984 24,068,679
473,040
5.01
Makeup
wells steam flow rate
10
20
30
Total
steam40flow rate
50
100
200
70
6
0.50
5
0.57
Output
60
8,650,201
0.66
Initial
wells steam flow rate
45t/h
5%
(20%)
59,508,206
0.76
0
14,013,856
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
0
300
100
400
200
300
500
400
0.87
Discount rate
1.00
0
13,155,874
Cashflow
6,905
6,803
Capital expenditure $
Steamt/h
flow rate t/h
13,806,755
2,336,255
2,301,729
453,543
7,005,530
6,902,000
6,800,000
2,267,713
23,362,546
23,017,287
22,677,130
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
Tax,others
2007
15
2006
4.45
2005
O&M cost
Year
2018
473,040
5.56
2019
471,697
5.65
473,040
5.73
2020
473,040
5.82
2021
473,040
5.90
2022
Discount rate
2,648,822
2,990,169
13
2,907,006
0.19
2,078,165
0.16
14
3,000,000
2,255,121
0.14
15
1,629,843
0.12
16
3,000,000
1,443,487
0.11
17
3,000,000
0.09
18
1,556,994
12
0.21
11
0.25
8,256
2,793,268
3,000,000
8,134
2,751,989
9,530
2,711,319
3,000,000
6,379
2,663,667
12,096,903
7,779
2,631,774
8,375,939
7,664
2,592,880
8,252,157
7,550
8,130,204
2,554,562
8,010,053
7,439
7,891,678
2,516,810
7,775,052
7,660,150
7,546,945
2016
473,040
5.40
2015
473,040
5.32
25,168,097
Output
NPV
PV
6,967,363
7,894,057
Makeup
wells:12
12
Makeup
well steam flow rate
25t/h
5%
25t/h
(20%)
Decline
rate5%
2011
2012
473,040
5.09
3,000,000
7,114
2,406,868
7,217,272
6,149,455
0.43
2013
3,809,709
0.33
11,653,987
3,000,000
7,221
2,442,971
7,325,531
24,429,709
473,040
5.16
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
4,299,752
0.38
14,224,064 11,437,425
7,009
2,371,298
7,110,613
23,712,984 24,068,679
473,040
5.01
Makeup
wells steam flow rate
10
20
30
Total
steam40flow rate
50
100
200
70
6
0.50
5
0.57
60
Output
8,650,201
0.66
Initial
wells steam
flow rate
12
25t/h
5%
(20%)
57,345,119
0.76
0
14,013,856
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
0
300
100
400
200
300
500
400
500
600
600
700
700
0.87
Discount rate
1.00
0
13,155,874
Cashflow
6,905
6,803
Capital expenditure $
Steamt/h
flow rate t/h
13,806,755
2,336,255
2,301,729
453,543
7,005,530
6,902,000
6,800,000
2,267,713
23,362,546
23,017,287
22,677,130
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
Tax,others
2007
15
2006
4.45
2005
O&M cost
Year
10
20
30
40
50
60
70
3,356,961
0.28
10
11,809,374
3,000,000
5,865
2,472,295
7,435,414
24,722,948
471,643
5.24
Output
3,000,000
2,648,090
2,952,782
2018
2019
473,040
5.65
2020
473,040
5.73
2021
473,040
5.82
2022
473,040
5.90
3,000,000
7,779
2,631,774
7,891,678
3,000,000
7,895
2,671,250
8,010,053
3,000,000
8,014
2,711,319
8,130,204
3,000,000
8,134
2,751,989
8,252,157
3,000,000
8,256
2,793,268
8,375,939
2,346,284
0.19
13
2,078,165
0.16
14
1,840,566
0.14
15
1,630,030
0.12
16
1,443,487
0.11
17
1,278,216
0.09
18
2,592,880
7,775,052
473,040
5.56
12
0.21
11
0.25
3,000,000
10,955
5,499
12,319,953
2,554,562
2,499,788
3,000,000
7,660,150
7,546,945
11,945,651
7,664
25,545,619
24,997,884
2017
473,040
5.48
2016
473,040
5.40
2015
469,841
5.32
Discount rate
NPV
PV
500
600
600
700
700
6,967,363
7,894,057
Makeup
wells:3
Makeup
well steam flow rate
45t/h
5%
45t/h
(20%)
Decline
rate5%
100
200
2011
2012
473,040
5.09
3,000,000
7,114
2,406,868
7,217,272
6,149,455
0.43
4,299,752
0.38
2013
4,660,814
0.33
14,257,538
-1,790
2,397,920
7,325,531
23,979,199
464,317
5.16
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Makeup
wells steam flow rate
10
20
14,224,064 11,437,425
7,009
2,371,298
7,110,613
23,712,984 24,068,679
473,040
5.01
Total
steam flow rate
30
40
50
60
70
6
0.50
5
0.57
Output
8,650,201
0.66
Initial
wells steam
flow rate
45t/h
5%
(20%)
57,596,125
0.76
0
14,013,856
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
0
300
100
400
200
300
500
400
0.87
Discount rate
1.00
0
13,155,874
Cashflow
6,905
6,803
Capital expenditure $
t/h
Steam t/h
flow rate
13,806,755
2,336,255
2,301,729
453,543
7,005,530
6,902,000
6,800,000
2,267,713
23,362,546
23,017,287
22,677,130
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
Tax,others
2007
15
2006
4.45
2005
O&M cost
Year
10
20
30
40
50
60
70
3,806,694
0.28
10
13,391,480
-17,145
2,312,194
7,435,414
23,121,943
441,101
5.24
Output
2,903,188
2,890,778
2018
2019
419,071
5.65
2020
391,200
5.73
2021
371,640
5.82
2022
353,058
5.90
-16,195
2,184,126
7,891,678
3,000,000
36,473
2,366,491
8,010,053
-24,851
2,242,235
8,130,204
-16,032
2,162,076
8,252,157
-15,459
2,084,781
8,375,939
2,360,203
0.19
13
1,914,848
0.16
14
1,448,886
0.14
15
1,483,922
0.12
16
1,199,296
0.11
17
966,666
0.09
18
2,265,104
7,775,052
392,579
5.56
12
0.21
11
0.25
-25,168
32,546
13,506,768
2,349,083
2,474,922
3,000,000
7,660,150
7,546,945
11,694,810
-16,796
23,490,834
24,749,223
2017
413,241
5.48
2016
434,991
5.40
2015
465,167
5.32
Discount rate
NPV
500
600
100
200
2011
2012
449,915
5.09
-16,418
2,289,207
7,217,272
6,149,455
0.43
5,038,313
0.38
14,224,064 13,402,012
7,009
2,371,298
7,110,613
23,712,984 22,892,074
473,040
5.01
2013
4,104,955
0.33
12,557,150
-16,368
2,207,368
7,325,531
22,073,682
427,420
5.16
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
10
20
30
Output
40
Makeup
wells:0
Decline
rate5%
5%
(20%)
(Initial
decline rate20%)
5%
(20%)
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
0
300
100
400
200
300
500
400
50
60
6,967,363
7,894,057
600
53,480,513
8,650,201
6
0.50
5
0.57
70
4
0.66
0
14,013,856
700
700
Steamt/h
flow rate t/h
PV
0.76
Discount rate
0.87
Cashflow
1.00
0
13,155,874
Capital expenditure $
6,905
6,803
13,806,755
2,336,255
2,301,729
453,543
7,005,530
6,902,000
6,800,000
2,267,713
23,362,546
23,017,287
22,677,130
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
Tax,others
2007
15
2006
4.45
2005
O&M cost
Year
10
20
30
40
50
60
70
3,336,235
0.28
10
11,736,462
-15,783
2,128,455
7,435,414
21,284,548
406,049
5.24
Output
-14,674
-15,218
2,184,992
2,704,086
2017
2018
330,729
5.56
2019
314,193
5.65
2020
298,483
5.73
2021
283,559
5.82
2022
269,381
5.90
1,759,408
0.19
13
9,413,273
-14,150
1,908,242
7,775,052
1,411,094
0.16
14
8,682,165
-13,644
1,840,022
7,891,678
1,126,570
0.14
15
7,971,275
-13,156
1,774,241
8,010,053
894,646
0.12
16
7,279,791
-12,686
1,710,812
8,130,204
706,048
0.11
17
6,606,931
-12,232
1,649,651
8,252,157
553,089
0.09
18
5,951,936
-11,795
1,590,676
8,375,939
348,136
5.48
12
0.21
11
0.25
1,978,991
2,052,363
10,165,440
7,660,150
7,546,945
19,789,906
20,523,625
10,939,536
2016
366,459
5.40
2015
385,746
5.32
Discount rate
100
200
2011
2012
408,624
5.09
-29,479
2,079,112
7,217,272
5,598,596
0.43
4,332,378
0.38
12,949,894 11,524,211
-21,950
2,226,506
7,110,613
22,265,063 20,791,116
444,156
5.01
2013
3,326,312
0.33
10,175,266
-27,527
1,941,474
7,325,531
19,414,744
375,934
5.16
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
10
20
30
Output
40
50
Makeup
wells:0
Decline
rate5%
8%
(20%)
(Initial
decline rate20%)
8%
(20%)
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
0
300
100
400
200
300
400
500
500
600
60
6,967,363
7,894,057
600
45,534,018
8,650,201
6
0.50
5
0.57
70
4
0.66
0
14,013,856
700
700
Steamt/h
flow rate t/h
NPV
PV
0.76
Discount rate
0.87
Cashflow
1.00
0
13,155,874
Capital expenditure $
6,905
6,803
13,806,755
2,336,255
2,301,729
453,543
7,005,530
6,902,000
6,800,000
2,267,713
23,362,546
23,017,287
22,677,130
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
Tax,others
2007
15
2006
4.45
2005
O&M cost
Year
10
20
30
40
50
60
70
2,531,877
0.28
10
8,906,830
-25,705
1,812,949
7,435,414
18,129,488
345,859
5.24
Output
-22,414
-24,003
1,416,476
1,906,645
2017
2018
247,771
5.56
2019
227,949
5.65
2020
209,713
5.73
2021
192,936
5.82
2022
177,501
5.90
1,033,921
0.19
13
5,531,738
-20,931
1,476,207
7,775,052
736,935
0.16
14
4,534,203
-19,545
1,378,482
7,891,678
507,827
0.14
15
3,593,235
-18,251
1,287,226
8,010,053
332,423
0.12
16
2,704,946
-17,043
1,202,012
8,130,204
199,378
0.11
17
1,865,706
-15,915
1,122,439
8,252,157
99,628
0.09
18
1,072,121
-14,861
1,048,133
8,375,939
269,316
5.48
12
0.21
11
0.25
1,580,860
1,692,932
6,590,001
7,660,150
7,546,945
15,808,595
16,929,316
7,713,442
2016
292,735
5.40
2015
318,190
5.32
Discount rate
NPV
PV
500
600
600
700
700
100
200
70
6,967,363
7,894,057
2011
3,000,000
7,114
2,406,868
7,217,272
4,852,473
0.43
4,299,752
0.38
11,224,064 11,437,425
3,000,000
7,009
2,371,298
7,110,613
10
3,809,709
0.33
11,653,987
3,000,000
7,221
2,442,971
7,325,531
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Makeup
wells steam flow rate
2013
473,040
5.16
24,429,709
20
30
2012
473,040
5.09
23,712,984 24,068,679
473,040
5.01
40
Total
steam
flow rate
50
60
Output
8,650,201
6
0.50
5
0.57
Makeup
wells:12
12
Makeup
well steam flow rate
45t/h
8%
45t/h
(20%)
Decline
rate8%
4
0.66
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
0
300
12
45t/h
8%
(20%)
56,104,568
0.76
0
14,013,856
100
400
200
300
500
400
0.87
Discount rate
1.00
0
13,155,874
Cashflow
6,905
6,803
Capital expenditure $
Steamt/h
flow rate t/h
13,806,755
2,336,255
2,301,729
453,543
7,005,530
6,902,000
6,800,000
2,267,713
23,362,546
23,017,287
22,677,130
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
Tax,others
2007
15
2006
4.45
2005
O&M cost
Year
10
20
30
40
50
60
70
3,375,274
0.28
10
11,873,796
3,000,000
7,329
2,479,615
7,435,414
24,796,155
473,040
5.24
Output
3,000,000
2,648,822
2,990,169
2018
2019
473,040
5.65
2020
473,040
5.73
2021
473,040
5.82
2022
473,040
5.90
3,000,000
7,779
2,631,774
7,891,678
3,000,000
7,895
2,671,250
8,010,053
3,000,000
8,014
2,711,319
8,130,204
3,000,000
8,134
2,751,989
8,252,157
3,000,000
8,256
2,793,268
8,375,939
2,346,284
0.19
13
2,078,165
0.16
14
1,840,566
0.14
15
1,630,030
0.12
16
1,443,487
0.11
17
1,278,216
0.09
18
2,592,880
7,775,052
473,040
5.56
12
0.21
11
0.25
3,000,000
7,550
7,439
12,323,357
2,554,562
2,516,810
3,000,000
7,660,150
7,546,945
12,096,903
7,664
25,545,619
25,168,097
2017
473,040
5.48
2016
473,040
5.40
2015
473,040
5.32
Discount rate
NPV
PV
0.76
0.66
100
200
70
0.43
0.50
6,967,363
0.57
7,894,057
4,852,473
0.38
3,809,709
0.33
11,653,987
3,000,000
7,221
2,442,971
7,325,531
24,429,709
2014
473,040
5.24
10
20
30
40
50
60
70
3,375,274
0.28
10
11,873,796
3,000,000
7,329
2,479,615
7,435,414
24,796,155
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
2013
473,040
5.16
10
Initial
wells steam flow rate
20
30
4,299,752
Total
steam flow rate
40
50
60
Output
8,650,201
Makeup wells:10
Makeup well steam flow rate45t/h
Decline rate7%
(Initial decline rate20%)
0.87
3,000,000
7,114
2,406,868
7,217,272
11,224,064 11,437,425
3,000,000
7,009
2,371,298
7,110,613
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
300
0
10
45t/h
7%
(20%)
57,102,958
1.00
2012
473,040
5.09
23,712,984 24,068,679
14,013,856
100
200
400
300
400
500
500
600
600
700
700
Discount rate
Cashflow
15
0
13,155,874
Capital expenditure $
2011
473,040
5.01
6,905
6,803
Steamt/h
flow rate t/h
13,806,755
2,336,255
2,301,729
453,543
Tax,others
2,267,713
22,677,130
O&M cost
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
7,005,530
2007
23,362,546
2006
6,902,000
2005
23,017,287
4.45
6,800,000
Year
13
0.19
12
0.21
2,648,656
0.25
3,723,346
2018
2,078,165
0.16
14
12,786,505
3,000,000
7,779
2,631,774
7,891,678
26,317,735
473,040
5.56
2019
1,840,566
0.14
15
13,023,303
3,000,000
7,895
2,671,250
8,010,053
26,712,501
473,040
5.65
1,630,030
0.12
16
13,263,652
3,000,000
8,014
2,711,319
8,130,204
27,113,189
473,040
5.73
2020
1,443,487
0.11
17
13,507,607
3,000,000
8,134
2,751,989
8,252,157
27,519,886
473,040
5.82
2021
1,543,595
0.09
18
16,611,030
4,979
2,776,883
8,375,939
27,768,830
470,265
5.90
2022
Discount rate
2,346,284
12,553,207
3,000,000
7,664
2,592,880
11
8,321
6,669
3,000,000
2,554,562
2,512,959
7,775,052
25,928,803
12,322,587
7,660,150
7,546,945
25,545,619
25,129,586
2017
473,040
5.48
15,063,013
2016
473,040
5.40
2015
472,316
5.32
Output
NPV
PV
Makeup wells:9
Makeup well steam flow rate
45t/h
Decline rate6%
6
0.50
6,967,363
5
0.57
7,894,057
100
200
70
14,013,856
13,806,755
2011
7,110,613
7,217,272
3,000,000
7,114
2,406,868
4,852,473
0.43
4,299,752
0.38
11,224,064 11,437,425
3,000,000
7,009
2,371,298
2013
4,790,414
0.33
14,653,987
7,221
2,442,971
7,325,531
24,429,709
473,040
5.16
2014
473,040
5.24
10
20
30
40
50
60
70
3,375,274
0.28
10
11,873,796
3,000,000
7,329
2,479,615
7,435,414
24,796,155
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
10
20
30
2012
473,040
5.09
23,712,984 24,068,679
473,040
5.01
50
60
Output
8,650,201
0.66
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
0
300
9
45t/h
6%
(20%)
58,075,470
0.76
6,905
6,803
100
400
200
300
400
500
500
600
600
700
700
0.87
Discount rate
1.00
13,155,874
Cashflow
15
453,543
Capital expenditure $
7,005,530
2,336,255
6,902,000
2,301,729
23,362,546
23,017,287
22,677,130
Steam t/h
flow rate t/h
6,800,000
2010
473,040
4.94
2009
473,040
4.87
2008
473,040
4.79
2,267,713
2007
2006
2005
Tax,others
4.45
O&M cost
Year
5,702
0
15,242,019
12
0.21
3,276,169
7,439
3,000,000
12,096,903
11
0.25
2,990,169
2017
2,345,939
0.19
13
12,551,359
3,000,000
9,512
2,592,880
7,775,052
25,928,803
473,040
5.48
2018
2,078,165
0.16
14
12,786,505
3,000,000
7,779
2,631,774
7,891,678
26,317,735
473,040
5.56
2019
1,840,566
0.14
15
13,023,303
3,000,000
7,895
2,671,250
8,010,053
26,712,501
473,040
5.65
1,993,332
0.12
16
16,219,866
7,019
2,706,343
8,130,204
27,063,432
472,172
5.73
2020
1,443,381
0.11
17
13,506,612
3,000,000
9,129
2,751,989
8,252,157
27,519,886
473,040
5.82
2021
1,278,216
0.09
18
13,755,221
3,000,000
8,256
2,793,268
8,375,939
27,932,685
473,040
5.90
2022
Discount rate
7,660,150
2,545,319
7,546,945
25,453,189
25,168,097
2,516,810
2016
471,328
5.40
2015
473,040
5.32
Output
CDM
1970 19851991
ADB55MW2
1994 California Energy InternationalCEI JV
2001 4 150MW 1998 60MW 1
45 350MW
2 CEI Mid-American
OPIC 2001 8 PLN
67%
33%
60MW 42MW
s-1
O&M
LG
FX233
45t/h/
14,000
13,000
12,000
2 2008 3 2009
11,000
10,000
9,000
8,000
7,000
6,000
5,000
5.00%
7.00%
9.00%
11.00%
13.00%
15.00%
17.00%
300MW5
600
120
IRR 6.85%
CO2
70 CO2
3
330MW 30
1
1 50MW
CDM
s-2
65MW3
50MW2