Você está na página 1de 4

Calculation of Electrical Maximum Demand

Abstract:
The Electricity provider does charge the fixed charges on the basis of consumers maximum
Electrical Demand. Consumer shall restrict the power consumption under the contracted
maximum demand. This article furnishes calculation for Maximum Contract Demand.
1. Introduction:
The Electricity provider does record maximum demand in pre-defined interval (e.g. 30 minutes
or 15 minutes) through duly sealed and calibrated energy meter. Generally Maximum Demand
denotes in kVA for billing purpose.
Consumer need to sanction Maximum demand from Electricity Provider considering type of
industry and operation pattern of the equipments. Consumer shall pay fixed charges on the
basis of Maximum Demand obtained from the provider i.e. the maximum rate at which an
electrical power has been consumed during any period of defined consecutive minutes in the
billing month.
2. Analysis:
General Formula to calculate the Maximum Demand is described below:
Maximum Demand= Connected Load * Load Factor / Power Factor.
Where,
Connected Load = Total Connected load in the facility in kW.
Load Factor = Utility Factor * Diversity Factor.
Power Factor = System average Power Factor.
Example:
Total connected load of facility: 6500 kW
Load Factor: 0.4 (Considering steel plant type)
Power Factor: 0.95
Maximum Demand= 6500 * 0.4 / 0.95
= 2737 kVA
Utility Factor and Diversity Factor can be finding out by the Time Profile of load and usage of
the equipment. All equipments of facility may not operate at similar time and also may not
run with full load.
Hence, Diversity Factor in percentage = Installed load / running load.

3. Conclusion:
Consumer should sanction Maximum Demand after studying the load pattern of the electrical
installation. Obtaining higher Maximum Demand shall result higher minimum fixed charges plus
higher deposit, and if sanctioned Maximum Demand exceed than consumer shall confront
penalty.

Transformer testing and fault rectification.


Power transformer failure results in production loss, unavailability of critical services, and loss of
revenue. Routine testing and performing diagnostics can minimize loss and down time.
Reliable and continual performance of power transformers is the key to beneficial generation and
transmission of electric power.
Generally, reasons for failure include external factors such as lightning strikes, system overload, short
circuits, and internal factors such as insulation deterioration, winding failure, overheating, and the
presence of oxygen, moisture, and solids in the transformer oil.
To minimize unexpected outages, periodic transformer testing and diagnostics is necessary.
Three categories can be defined for transformer testing:

Performance acceptance test after installation and commissioning of the transformer.


Predictive maintenance plan-based test during normal operation of the transformer to verify
that electrical properties have not changed from design specifications.
Failure test for identify breakdown cause of the transformer.
These tests are required to determine electrical, thermal, and mechanical characteristics.

Visual Inspection
A daily checklist procedure should be established to perform the visual routine test. It should contain
oil temperature, winding temperature, oil level, humming (noisy operation), and oil leakage checks. An
annunciation window (an indicator that announces which electrical circuit has been active) displays
alarm and trip signals generated from the load.
Buchholz Relay
A Buchholz relay is a safety device normally mounted at the middle of the pipe connecting the
transformer tank to the conservator. It is a gas detection relay used to detect minor and major faults in
the transformer. A Buchholz relay operates by detecting the volume of gas generated in the
transformer tank. Gas produced by faults accumulates over time within the relay chamber. Whenever
the volume of gas exceeds a certain safe level, the float moves lower, closes the contact, and
generates an alarm. The fault alarm can be displayed on an annunciation window and the master trip
relay will cause the circuit breaker to open.

Thermal Imaging (Thermography)


Thermal imagers capture images of infrared energy or temperature. They can detect heat patterns or
temperature changes in equipment. The engineer can determine problems prior to an expensive down
time by analyzing these temperature changes. Conveniently, one can measure and compare heat
readings for each part of the equipment without disrupting the transformer's operation.
Prevention, diagnosis, and repair benefits can be obtained for transformers by introducing Infrared
thermography into your predictive maintenance plan.

Insulation Resistance Test


Insulation ages and deteriorates because of moisture, dust, and electrostatic stress. Insulation should
be monitored continually to avoid sudden failure of the equipment.
An insulation resistance test detects insulation quality within the transformer. The conductive
impurities or mechanical flaws in the dielectric can be analysis based on this test. The instrument
used to measure insulation resistance is known as the "megger." Normally meggers have a test
voltage of 500V, 2500V, or 5000V.
Each winding should be short circuited at the bushing terminals. The resistance value should be
measured between each winding and with respect to ground also. The winding should be discharged

after the test is completed by connecting to the ground.


The insulation resistance value measured is usually in the order of mega-ohms. Generally the value
should be greater than 1 megohm for every 1kV rating of the equipment.
Insulation resistance values decrease with increase in the temperature. Therefore the values should
be normalized for a standard temperature. It is necessary to have the insulation resistance as high as
possible.

Transformer Turns Ratio Test


Each winding of a transformer contains a certain number of turns of wire. The "transformer turns ratio"
is the ratio of the number of turns in the high voltage winding to that in the low voltage winding. The
ratio is calculated under no-load conditions.
The transformer ratio can change due to several factors like physical damage because of faults,
deteriorated insulation, contamination of oil etc. If a transformer ratio changes more than 0.5 percent
from the rated voltage ratio, it needs immediate attention.
The turns ratio will establish the proper relationship between the primary and secondary winding
impedances. The turns ratio is the square root of the impedance ratio, i.e.
iZpri/Zsec = (Npri/Nsec)2
Zpri = Primary Impedance
Zsec = Secondary Impedance
Npri = Number of turns on the primary coil
Nsec = Number of turns on the secondary coil

Dissolved Gas Analysis (DGA)


Transformer overloading, overheating, corona, sparking, and arcing can cause thermal degradation of
the oil and paper insulation within the tank. Thermal and electrical faults can accelerate the
decomposition of dielectric fluid and solid insulation. Gases generated by this process include
hydrogen, methane, ethane, acetylene, carbon monoxide, and carbon dioxide, all which will dissolve
in the transformer oil.
The DGA test involves extracting the gases from the oil and injecting it into a gas chromatograph. Gas
concentrations are detected using a flame ionization detector and a thermal conductivity detector.
Diagnostic and analysis of the specific proportions of each gas shall help to identify the fault type
(thermal conditions involving the oil or the paper, partial discharge, sustained arcing, etc.).
A DGA test study can minimize damage by taking precautionary actions at an early stage.

Magnetic Balance Test


The magnetic balance test is conducted on transformers to detect inter-turn faults and magnetic
imbalance. It gives an idea about the flux distribution in the core. It is only an indicative test and does
not reduce the need for other tests in diagnostics.
The magnetic balance test is carried out on a three phase transformer by applying a two phase supply
across the phases (i.e. one winding say U and V) with a lower than rated voltage. Other phases
should be kept open circuit. The sum of voltage measured between V-W and U-W should be equal to
U-V. A voltage measured in the secondary side will also be proportional to the voltage measured at
the primary.
A very low voltage will induce in defected winding because it will not allow flux to pass in the magnetic
path around the core. It may result in the sum of the two voltages not being equal to the applied
voltage.

Tan Delta Test


Degradation of the insulation takes place because of mechanical vibration, over temperature
operation, and gaseous and metallic impurities in the transformer. This may cause insulation ageing
and breakdown. It is very important to study the insulation quality of the machine. The dissipation
factor Tan or Power Factor Cos is considered to indicate the quality of insulation. It is also known as
the loss angle test or the dissipation factor test.
A clean insulation acts as a capacitor. The current should lead the voltage by 90 degrees in a pure
capacitor. The pure insulation should also conduct similarly. If the insulation is deteriorated, the
current will also have resistive factor. This will cause the angle of the current to be less than 90
degrees. This measured difference in the angle is described as the loss angle. The tangent of the
angle (i.e. opposite/adjacent) indicates the condition of the insulation. A greater loss angle value
points to a high contamination of the insulation.

Transformer Oil Break Down Test


The BDV test measures the dielectric strength of the oil using an oil tester. During this test, spherical
electrodes having a 2.5 mm gap shall be gradually applied voltage until the oil loses its dielectric
strength. This test should be performed for one minute, and the breakdown voltage displayed on the
oil tester meter should be considered the BDV. Normally it may be 60 kV and over for one minute or
as per ASTM D877-82 or IS-335.
A low value in this test indicates the presence of impurities in the oil. In this case it should be filtered
to remove impurities and moisture.

Followings are other tests that can be used to detect oil based faults:

Acidity test

Electric strength test

Color test

Polychlorinated Biphenyl Analysis (PCB) test

Fiber estimation

Furfuraldehyde analysis test

Metal in oil test

Resistivity test

Furan analysis

Frequency Response Analysis

Você também pode gostar