Escolar Documentos
Profissional Documentos
Cultura Documentos
INTRODUCTION
The purpose here is to overview the line of balance technique (LOB) and examine its capacity
to schedule repetitive construction tasks. The repetitive nature of construction projects may also
be scheduled using the technique of multiple activity chart (MAC). Construction projects such as
large housing estates, high-rise commercial buildings, high-ways, tunnels, pipelines, bridges
and the like consist of numerous highly repetitive elements. Such projects are commonly
referred to as repetitive or linear construction projects. Critical path method (CPM) techniques
are less appropriate for scheduling repetitive projects. Other techniques such as multiple activity
charts and line of balance are preferred. A MAC may be described as a highly effective shortrange planning technique, particularly suited for scheduling repetitive tasks. LOB is effective in
medium to long-range scheduling.
Mattila & Abraham (1998) and Al-Harbi et al. (1996) described techniques that may be used for
scheduling repetitive projects:
Scheduling of repetitive tasks using CPM requires a large number of activities. Visualization and
interpretation of CPM schedules with a large number of activities is often difficult. (As an
exercise: Review CPM, LSMh, RPM, VPM scheduling methods).
Optimization methods treat scheduling of repetitive projects as a dynamic process. They look for
efficient solutions in terms of cost and time while maintaining the constraints related to the
production rate and continuity of work of committed resources. (Review: Optimization
methods).
The graphic methods plot repetitive activities as diagonal lines on an X-Y graph with time on the
horizontal axis and location on the vertical axis. The slopes of the lines represent production
rates of the activities. LOB, VPM and LSM techniques are very similar and are often treated as
being the same.VPM (OBrien 1975) is best suited to scheduling repetitive activities in high-rise
building projects while LSM (Mattila & Abraham 1998) is more applicable to truly linear
construction projects where activities are repetitive for the entire project duration, such as
pipeline or highway construction.
LOB embraces the features of both VMP and LSM, and in addition creates a control graph from
which the planner can determine how many repetitive segments and sub-segments will be
completed at specific times.
A technique of LOB will now be examined in detail and its link to MAC emphasized. First, the
main features of LOB will be given. The concept of delivery program in LOB will then be
introduced. LOB schedule processes may be developed for single and multiple crews.
Footings
Buffer zones
Location
Brickwork
20
40
Time in days
60
80
A uniform rate of progress of individual activities is rarely achieved. A more realistic scenario is
to expect rates of progress to vary from activity to activity. Activities of such varying rates of
progress are then linked together so that continuity of work of each crew is maintained. This is
illustrated in Figure 2.
Brickwork
Location
20
Time in days
40
60
80
Having established the delivery rate of completed houses, it is possible to use the delivery rate
graph to establish, at specific intervals, the planned production output of houses and their
individual activities. As construction gets underway, the planned volume of output will be used
as a control tool against which the actual production will be assessed. But first, lets define the
concept of lead-time.
100
50
50
45
37
25
10
20
A
30
C
40
50
Time in weeks
Footings
lead-time
Roof
lead-time
Lets use lead-times to plan production output levels. For example, how many houses and their
individual activities will be completed on week 20 using the rate of delivery graph in Figure 3?
When the last activity Clean-up is completed, lead-time is zero, which is the lead-time of a fully
completed house. A vertical line drawn at week 20, ( Line A in Figure 3), intercepts the rate of
delivery (number of completed houses) line. The intersection point represents the number of
completed houses, which is read off the vertical axis at 25. The volume of completed activities
on week 20 is determined in much the same manner. Lets take the activity Footing first.
Because its lead-time is eight weeks, a vertical line is drawn eight weeks to the right from week
20, which is week 28 (Line B in Figure 3). The interception point on the rate of delivery line
corresponds to 45 completed footings on week 20, read off the vertical axis. Similarly, since
the activity Roof has a lead-time of five weeks, a vertical line is drawn at week 20 + 5 = 25
(Line C in Figure 3) and corresponds to 37 completed Roof activities on week 20. This
process is then repeated for the remaining house activities (i. e., Brick work, Plumbing,
Windows, Plaster, Joinery, Electrical, Painting, Clean-up)
Table 1 shows the planned out (From Figure 3) and actual production level. The planned
production output of each activity is presented graphically in Figure 5. The actual production
output is then marked up on the same graph. In this format, the difference between the planned
and actual production output is clearly apparent.
0
10
Footings
Brickwork
Plumbing
Roof
Window
Plaster
Join.
Elect.
Painting
Clean-up
10
A: Footings
B: Brick work
C: Windows
D: Roof
E: Plaster
F: Plumbing
G: Joinery
H: Electrical
I: Painting
J: Clean-up
Planned output
(a)
Actual Output
(b)
45
40
37
37
36
32
32
32
28
26
47
43
39
37
33
30
32
34
25
22
Output
difference
(b) (a)
+2
+3
+2
0
-3
-2
0
+2
-3
-4
Worse
planned poutput
50
Production output
40
30
20
10
than
0
Activity
Analysis of the LOB in Figure 5 reveals that activities D and G are right on schedule while
activities E, F, I and J show deficits. Activities A, B, C and H show surpluses. Units actually
completed by activities A, B, C and H are 47, 43, 39 and 34 respectively against the respective
units indicated by the LOB i. e., 45,40, 37 and 32 (See Table 1). On the other hand activities E,
F, I and J are lagging behind by units indicated in Table 1. The LOB display enables
management to begin corrective action on activities E, F, I and J to ensure that they does not
impede the progress rate of the remaining units.
DEVELOPING A LOB SCHEDULE
The fundamental aspect of preparing a LOB schedule has already been and has been
illustrated in Figures 1 and 2. A LOB schedule shows graphically the arrangement of repetitive
activities from location to location for the entire project. Start and finish dates of such repetitive
activities are determined in a LOB table.
Development of start and finish dates
Lets demonstrate the process of calculating start and finish dates of repetitive activities in a
tabular form for the following project. The project in question is a high-rise commercial building
with 20 typical floors. Because no specific date has been given for the completion of the fit-out
of 20 typical floors, there is no need to be concerned with the required rate of delivery of
individual packages.
The building is designed as a concrete frame structure, comprising columns, walls and slabs.
LOB will be used to schedule activities associated with the fit-out of the 20 typical floors. The fitout work has been broken up into seven trade packages, each performed by one crew of
subcontractors. It is assumed that construction of structural floors proceeds well in advance of
the fit-out activities. A precedence schedule of fit-out activities related to a typical floor is given in
Figure 6.
Aircon.
Interior finish
Suspended ceiling
Internal bkw. Concrete facade
Strip form
Hydraulics
Table 2 shows in the first two columns a list of trade packages and their respective cycle
times by a MAC
Table 2: The LOB table of the fit-out project
TRADE PACKAGE
1.
2.
3.
4.
5.
6.
7.
Strip formwork
Air-conditioning ducts
Hydraulics
Internal brickwork
Concrete faade
Suspended ceiling
Interior finishes
DURATION
PER
CYCLE OF
WORK
(DAYS)
6
8
5
7
5
6
8
TOTAL
DURATION
IN DAYS
120
160
100
140
100
120
160
START OF WORK
PACKAGE IN
DAYS
FINISH OF WORK
PACKAGE IN DAYS
0
6
25
33
78
83
89
120
166
125
173
178
203
249
The total duration of the work associated with each repetitive trade package over 20 typical
floors is calculated in the third column. The table shows that cycle times of work of the
individual packages vary between five (5) and eight (8) days. To ensure continuity of work of
subcontractors, a succeeding package that has a slower rate of progress than its
immediately preceding package or the same rate will be scheduled as soon as the first
cycle of work of its preceding package has been completed. If everything goes according to
the plan, this succeeding package will not interfere with the work of the preceding one. However,
if a succeeding package has a faster rate of progress than the preceding one, its start
would need to be delayed sufficiently to prevent interference with the preceding package.
Lets now calculate start and finish dates of the trade packages in columns 4 and 5. Strip
formwork is the first package in the production cycle (see Figure 6). It starts on day 0 (see Table
2, Column 4). Since its total duration is 120 days, it will finish on day 120 (see Column 5, Table
2).
The start of the next two trade packages, Air-conditioning ducts and hydraulics, depends on
the completion of the preceding package, i. e. Strip formwork. Lets schedule the package
Air-conditioning ducts first. Because its duration per cycle of work (of 8 days) is longer than
that of the preceding package Strip formwork (of 6 days), it can be scheduled to start as soon as
the first Strip formwork activity has been completed, which will be on day 6 (after completion of
Strip formwork cycle). This package (Air-conditioning) will be completed on day 166.
The cycle of work of the package hydraulics of 5 days is faster than that of the preceding
package, Strip formwork of 6 days. It means that it cannot be scheduled to commence as soon
as the first Strip formwork activity has been completed because it would continually interfere
with it. Rather it would be scheduled from the finish date of the last Strip formwork activity.
This last strip formwork activity is scheduled for completion on day120 and therefore the last
Hydraulics activity will be completed five days later on day 125. The first Hydraulics will then
start on day 25 (125 total duration for Hydraulics) . Its progress will be uninterrupted and will
not interfere with its preceding activity.
The next package to schedule is Internal brickwork. Its start is dependent on completion of two
preceding packages, Air-conditioning and Hydraulics. Lets consider these two preceding
packages one at a time. With regard to Air-conditioning, the Internal brickwork package is
faster per cycle of work (7 vs 8 days). It will therefore be scheduled from the finish of the last Airconditioning activity. Because the last Air-conditioning activity is scheduled for completion on
day 166, the last internal brickwork activity will be finished seven days later, on day 173. The
start date of the internal brickwork package will then be day 33. With regard to Hydraulics,
internal brickwork is slower per cycle of work and will therefore start as soon as the first
Hydraulics activity has been completed, which is on day 30 (start of Hydraulics on day 25 +
Hydraulics cycle time of 5 days = 30 days). The package Internal brickwork will then be
completed on day 170 (= 140 + 30). This is three days before its other preceding package, Airconditioning, would be completed (on day 173). Clearly, the start and finish of the package
Internal brickwork is governed by its preceding package, Air-conditioning.
(Exercises:
1. Draw Figure 3 to scale. Assuming lead times in Figure 4 and the actual
production/output levels in Table 1, determine planned outputs and
difference in planned and actual outputs. Hence draw the LOB as in Figure
5.
2. Verify the scheduling in Table 2 for Trade Packages 5, 6 and 7.