Escolar Documentos
Profissional Documentos
Cultura Documentos
Refrigeration:
What is a Refrigerant?
Fluids suitable for refrigeration purposes can be classified into primary and
secondary refrigerants.
Primary refrigerants are those fluids, which are used directly as working
fluids, for example in vapour compression and vapour
absorption refrigeration systems.
Secondary refrigerants are those liquids, which are used for transporting
thermal energy from one location to other. Secondary refrigerants are also
known under the name brines or antifreezes
2.
Low condensing pressure (to avoid heavy machine plant scantling and
reduce the leakage risk)
3.
4.
Low specific volume in vapour state (reduces size and increases efficiency)
5.
6.
7.
8.
9.
No action with oil ( the fact that most refrigerants are miscible may be
advantageous e.e. the removal of oil films, lowering pour points etc,
provided separators are fitted
10.
11.
Non toxic
12.
The superheated vapour enters the compressor where its pressure is raised. The
temperature will also increase, because a proportion of the energy put into the
compression process is transferred to the refrigerant
Cycle 3-4:
The high pressure superheated gas passes from the compressor into the condenser.
The initial part of the cooling process (3-3a) de-superheats the gas before it is then
turned back into liquid (3a-3b). The cooling for this process is usually achieved by
using air or water. A further reduction in temperature happens in the pipe work and
liquid receiver (3b 4), so that the refrigerant liquid is sub-cooled as it enters the
expansion device
Cycle 4-1:
The high-pressure sub-cooled liquid passes through the expansion device, which
both reduces its pressure and controls the flow into the evaporator
Thermostatic Expansion Valve (TEV)
The thermostatic expansion valve performs following functions:
1) Reduce the pressure of the refrigerant: The first and the foremost
function of the thermostatic expansion valve is to reduce the pressure of the
refrigerant from the condenser pressure to the evaporator pressure. In the
condenser the refrigerant is at very high pressure. The thermostatic expansion
valve has an orifice due to which the pressure of the refrigerant passing through it
drops down suddenly to the level of the evaporator pressure. Due this the
temperature of the refrigerant also drops down suddenly and it produces cooling
effect inside the evaporator.
2) Keep the evaporator active: The thermostatic expansion valve allows
the flow of the refrigerant as per the cooling load inside it. At higher load the flow of
the refrigerant is increased and at the lower loads the flow is reduced. It wont
happen that the load on the evaporator is high and the flow of the refrigerant is low
thereby reducing the capacity of the evaporator. The thermostatic expansion
valve allows the evaporator to run as per the requirements and there wont be any
wastage of the capacity of the evaporator. The TEV constantly modulates the flow to
maintain the superheat for which it has been adjusted.
2.
3.
4.
If no further action is taken, pressure above and below the Bellow will be
equalised and hence no superheat is obtained.
5.
Operation:
1.
Refrigerant Liquid from Condenser enters into TEV via Dryer, it expands to
Evaporation Pressure, and some flash gas is formed.
2.
3.
Mixture of this expanded gases and some part of liquid, passed into
Evaporator, where complete Evaporation takes place.
4.
Evaporator outlet pressure plus Spring pressure tends to close the valve,
and is opposed by the pressure above the Bellow, trying to open it.
5.
6.
7.
8.
9.
2.
3.
2.
3.
Lub Oil LP cut-out: Oil pressure usually set at 2 bar above crankcase
pressure.
4.
5.
6.
7.
8.
9.
2.
3.
4.
5.
CFC: Chlorofluorocarbon
HFC 134a has Ozone Depletion Potential, ODP 0 and Global Warming
Potential, GWP 0.28.
Defrosting:
A method of removal of frost, built-up on Evaporator coils. Defrosting should be done
before snow thickness exceeds .
Reasons for defrosting:
1.
2.
3.
Defrosting Systems:
1.
2.
3.
Electric defrosting
4.
5.
Hot brine thawing: Best and fastest method, used powerful brine heater
with separate thawing system. Watertight trays under the pipes, collected
the dripping water.
2.
3.
By shutting off brine : Allow the snows to be melted by the heat of the
air in circulation. Very slow operation and tends to throw back great deal of
moisture into cargo space.
Brine cooling:
2.
Steam is released to brine heater and brine flow is restricted by brine inlet
valve, until brine temperature has risen above 0
3.
(ii)
Indication:
Compressor is running hot and performance of the compressor falls off due
to high superheat temperature at the suction side of compressor.
Causes:
Leakage of refrigerant at the shaft seal, flange couplings, valve gland etc.
Action:
The liquid level in the condenser is too high (high condenser gauge reading).
This will reduce the available condensing surface, with corresponding increase in the
saturation temperature and pressure.
High pressure switch of the refrigerant compressor activates and stops the
compressor.
Causes:
It may be due to the reason that excessive refrigerant has been charged in
the system.
Action:
cylinder to the liquid line charging valve, starting the compressor, and then operating
the charging valve.
Purge the air from the system and maintain effective cooling.
Remove ice from the regulator by using any of the defrosting methods.
the corrosion in the system. It may cause lubrication problems and breakdown of the
lubricating oil in the refrigerant compressor.
Action:
Renew silica gel in case of minor moisture.
collect refrigenant and remove all air and moisture by vacuum pump if the amount
is huge.
4. Air in the System
Indication:
This may cause the refrigeration compressor to overheat, with a high discharge
pressure and normal condensing temperature.
There are possibilities of small air bubbles in the liquid sight glass of the
condenser.
Condensing pressure of the refrigerant in the condenser may be high.
If there is excessive air, it may reduce the cooling capacity of the system, making
the compressor to run for the extended period of time.
It may cause the gauge pointer of the condenser to jump indefinitely.
Causes:
During charging, air may enter in to the system.
If Freon-12 is used air may leaks in to the suction line because the working
pressure of the Freon-12 refrigerant is less than the atmospheric pressure.
Action:
Air in the system can be removed by collecting the system gas in the condenser,
leaving the condenser cooling water on and venting out the air from the top of the
condenser because air will not be condensed in the condenser but remains on top of
the condenser above the liquid refrigerant.
Connect the collecting cylinder to the purging line of the condenser, open the
valve, and collect air in the cylinder.
After purging the air from the system dont forget to shut the purging valve.
Check the level of the refrigerant in the system. If required, charge the system with
fresh refrigerant.
Restart the compressor with all safety precautions.
5. Oil in the Refrigeration System
Indication:
Temperature is not dropping in the cold rooms as normal, due to fact that oil act as
insulation in the evaporator.
It may cause excessive frost on the suction line.
Refrigerant compressor runs for the extended period of time.
Lubricating oil level in the compressor will drop.
Refrigerant level will fall if oil has caused blockage.
Causes:
This may happen if the oil separator is not working properly.
Oil may carry over from the compressor and may not come back to the
compressor due to blockage in the system.
Defective piston rings or worn out liner of the compressor may cause the oil to
carry over along with the refrigerant.
Compressor may take high capacity current during starting.
Action:
Check the oil separator for proper functioning.
Check the drier for proper cleaning and if its require cleaning clean it
Evaporator coil should be drained to remove any trace of oil.
If there is oil in the cooling coils, increase the condenser and evaporator
temperature differentials and remove excess frost on the suction pipe.
Heat pipes with blow torch.
6. Flooding of Refrigerant in the System
This is seen as liquid getting back to the suction of the refrigerant compressor. It may
be due to a faulty or incorrectly adjusted expansion valve and also due to solenoid
valve leakage. It may also result from overcharging of therefrigeration system.
Flooding may lead to an iced up evaporator.
7. Evaporator Coil Icing:
Icing of the evaporation coils which may happen due to:
1. Cause:Too low temperature setting
Action: Increase the coil temperature by adjusting TEV or its sensor.
2. Cause: The coil capacity is less
Action: Install large capacity evaporator coils
3. Cause: Defrost is not operational
Action: Check if the defrost system is functioning at regular intervals.
2.
3.
4.
Indication:
1.
2.
3.
Noisy operation.
4.
11.
Indication:
1.
2.
3.
Noisy operation.
4.
5.
6.
7.
1.
Starved Evaporator
2.
3.
Remedy:
1.
2.
Renew Dehydrator.
Secondary Refrigerant:
Calcium Chloride Brine ( 3 lb. of Ca Cl + 1 gal. of water ) with density
Freezing up of Evaporator. (c) Entrance of air and water vapor resulting from LP
side leakage.
Fridge compressor sump oil filling:
1.
Stop condition: (i) Tight shut both inlet and outlet valves of compressor.
(ii) Open filling plug and fill to required level. (iii) Air purge to be done when
plant resume.
2.
During running:
itself.
air ingress.
2.
(Thorzone)
3.
4.
5.
2.
Gas charging.
Now a days gas charging is preferred over liquid charging because it is more
safe and simple.
1. Connect gas bottle or charging cylinder, vacuum pump and charging point in the
reefer system to the valve block.
2. The discharge of the vacuum pump is to be connected in the empty recovery
bottle
3. First open the valve between vacuum pump and charging bottle located in the
valve block without opening the main valve of the charging cylinder. This will remove
all the air inside the pipe. Once vacuum is reached, close the valve of charge
cylinder in the valve block
4. Now open the valve of the charging point pipe in the valve block and run the
vacuum pump until the vacuum is reached. This will remove the trapped air from this
pipe. Then shut the valve in the valve block
5. Now keep the system idle for 5 minutes to check there is no pressure drop. This
will ensure there are no leakages in the system
6. Now open charging bottle pipe valve and the charging point pipe valve located in
the valve block. This will set the line for charging. Ensure that the vacuum pump
valve is shut7. Now open the main valves in the charging cylinder and charging point
of the reefer system
8. Do not overfill the system. Make sure the receiver has 5 % space for expansion
Ensure that no refrigerant is leaked out in the environment as these effects the
ozone layer in the atmosphere.
Gas bottle is kept on weighing scale for measuring the amount of charged supplied
to the system.
Air Conditioning:
Relative Humidity:
Ratio of amount of water vapour in given volume of air, to maximum amount of water
vapour that can be present before precipitation occurs.
Control of temperature:
Comfortable temperature range is about 22C and RH about 60%, (usually 40 ~
70%).
All zone temperature:
1.
2.
Ozone Depletion:
1.
2.
3.
Release of industrial waste and other process breakdown ozone layer and
so disturb natural balance.
4.
5.
1.0
Halon1211
3.0
CFC 12
1.0
Halon1301
HCFC 22
0.05
Air Cond. controls Humidity, Temperature and Flow Rate of fresh air.
1.
2.
3.
4.
The spring, acting on the valve spindle, opens the valve and the air passes
to the reduced pressure
5.
6.
If the opening increases, the higher pressure obtained on other side, acts
to close down the valve to normal lift, and hence correct reduced pressure
maintained.
7.
2.
Psychrometric chart
This chart is used for finding the relative humidity of air which has been measured
using a wet and dry bulb thermometer. This is a pair of thermometers, one of which
has its bulb wrapped in a damp cloth. The drier the air,the greater the evaporation of
water off the cloth and therefore the lower the reading on the wet bulb thermometer.
Dew point:
When a mixture of dry air and water vapour has a saturation temperature
corresponding to the partial pressure of the water vapour it is said to be saturated.
Any further reduction of temperature (at constant pressure) will result in some vapour
condensing. This temperature is called the dew point, air at dew point contains all
the moisture it can hold at that temperature, as the amount of water vapour varies in
air then the partial pressure varies, so the dew point varies.
Air Compressor
2.
3.
Less air drawn in, due to high-pressure air leaking back into cylinder.
2.
3.
2.
3.
4.
2.
3.
Total no. of Air Compressors must be sufficient to fill the empty Air Bottle
to maximum pressure within 1 hour.
Bursting Disc:
1.
2.
3.
Rolled Copper Alloy and relief pressure is set while the disc is at softest
condition.
4.
5.
2.
3.
4.
HP suction valve
2.
Intercooler choked.
3.
2.
3.
(Relief Valves opening pressure are set at 10% above stage pressure.)
Reduce air temperature and volume, and increase air density for next
stage.
2.
3.
4.
Water and excess oil can be drained out, preventing fouling of Intercooler
and pipes, Air Bottle corrosion, and starting airline explosion.
5.
6.
Volumetric Efficiency:
VE = (Volume of Air drawn into Cylinder) / (Stroke Volume of LP Piston)
and
VE = (Volume of Air discharged as free air) / (Stroke Volume of LP Piston)
Why Multistage Air Compressor is built?
1.
2.
Inter-stage cooling reduces air temperature and volume after 1st stage
compression, thus increase mass of air for 2nd
3.
2.
3.
4.
5.
Reduction in size.
6.
2.
2.
2.
3.
Relief valves on LP and HP stages. (Set to lift at 10% rise above normal
stage pressure.)
4.
5.
6.
7.
8.
Delivery air HT cut out and alarm on Aftercooler outlet. (Max. 93C)
Air Filter:
1.
2.
Removes contaminants from air. Dirt and dust act as abrasives and
increase wear.
3.
2.
3.
4.
Cylinders, cylinder cover, Inter & After coolers are hydraulically tested to:
Air receiver:
There must be two identical main air receivers and one emergency bottle
for every vessel.
Fusible plug:
reservoir at ship side, when relief valve (safety valve) is not directly fitted on
the reservoir.
2.
3.
Spring loaded safety valve: setting pressure: 32 bar (for 30 bar working
pressure), with 10% rise in accumulation of pressure. May be fitted directly
or with extension.
4.
5.
6.
Pressure gauges.
7.
Access doors.
8.
Main starting air valve, auxiliary starting air valve, filling valve, service air
or whistle air valve.
Fusible plug.
2.
3.
4.
5.
Boiler :
Boiler Automatic Burning System:
1. With correct water level, steam pressure transmitter initiates cut-in at about 1.0
bar below working pressure.
2. Steam pressure transmitter initiates Master Relay to allow Air On signal to force
draught fan.
3. Air feedback signal confirms Air On and allows 30-sec. delay for purge period.
4. Then Master Relay allows Electrode to strike Arc.
5. Arc striking feedback signal confirms through electrode relay and allows 3-sec.
delay.
6. Then Master Relay allows burner solenoid valve for Fuel On operation.
7. Fuel On feedback signal allows 5-sec. delay to proceed.
8. As soon as receiving Fuel On feedback signal, Master Relay checks Photocell,
which is electrically balanced when light scatter continuously on it.
9. Result is OK and cycle is completed.
10. If not, fuel is shut-off, Alarm rings and cycle is repeated.
11. Steam pressure transmitter initiates cut out automatically at about 1/15 bar above
W.P.
The use of exhaust gas from main engine to generate steam is means of
2.
3.
4.
5.
6.
point.
3. Sample water is cooled down to about 25C.
4. Flush out sample stream for 5 minutes before taking.
5. Test apparatus should be cleaned with sample water.
6. Sample water is tested as soon as possible after drawing.
Alkalinity Tests:
1. P Alkalinity finds presence of Hydroxyl, Phosphate and half of Carbonates,
excluding Bicarbonates.
2. T Alkalinity gives total quantity of all Alkaline Dissolved Salts in boiler water.
3. M Alkalinity finds presence of remaining Carbonates and Bicarbonates.
4. Total Alkalinity is < 2 x P Alkalinity. 5. Desired value is 150 300 ppm for P
Alkalinity. Increase of Alkalinity Level: Causes: 1. Alkalinity treatment has been done
recently. 2. Using of Alkaline rich makeup feed water. 3. Incorrect strength of reagent
used. Effect: Caustic Embrittlement. Decrease of Alkaline Level: Causes: 1. Feed
water is contaminated with acid. 2. Direct water loss from boiler. 3. Incorrect strength
of reagent used. Effect: Corrosion. Chloride Test: 1. Gives quickest indication of any
salt-water leakage into boiler. 2. Must be carried out daily. 3. Chlorides of Calcium,
Magnesium and Sodium are extremely soluble. 4. Chloride level is proportional to
TDS level in boiler water. 5. Rate of blow-down is governed by chloride level. 6.
Chloride Level should be 0 300 ppm, and blow-down if > 300 ppm.
Increase of Chloride Level:
Causes:
1. SW leaking into system.
2. Incorrect strength of reagent used. (Silver Nitrite and Potassium Chromate).
3. Due to treatment chemical and hardness salt reaction.
Effects:
1. Increase in TDS level causes Foaming/Priming.
2. Drop in Alkalinity causes Corrosion.
Phosphate Test:
1. Presence of Phosphate in sample means no hardness salts.
2. NaPO added to boiler water, precipitate all scale forming hardness salts of
Boiler Corrosion:
(1) Electro-chemical Corrosion:
1.
Hydrogen ions (H) are generated by acid concentration under hard dense
deposits and can penetrate grain boundaries of tube metal,
2.
Hydrogen attack can occur very rapidly, causing the tubes cracked, failed
and ruptured.
3.
4.
Pitting (Air Bubble pitting and Scab pitting) occur when pH value is
between 610 in the presence of dissolved Oxygen.
2.
3.
4.
NH:
1. Attacks Copper based Alloy, in the presence of O.
Base line:
A horizontal line drawn at the top of the keel plate. All vertical moulded
dimensions are measured relative to this line
Moulded beam:
Measured at the midship section is the maximum moulded breadth of the
ship
Moulded Draft/ Draught:
The distance from the bottom of the keel to the waterline. The load draft is
the maximum draft to which a vessel may be loaded
Moulded Depth:
Measured from the base line to the heel of the upper deck beam at the
ships side amidships.
Sheer:
Curvature of decks in the longitudinal direction. Measured as the height of
deck at side at any point above the height of deck at side amidships
Camber / Round of Beam:
Curvature of decks in the transverse direction. Measured as the height of
deck above the height of deck at side
Rise of floor / Deadrise:
The rise of the bottom shell plating line above the base line. This rise is
measured at the line of moulded beam
Half siding of keel:
The horizontal flat portion of the bottom shell measured to port or
starboard of the ships longitudinal centre line. This is useful dimension to
know when dry-docking.
Tumble home:
The inward curvature of the side shell above the summer load line.
Freeboard:
The vertical distance measured from the waterline to the top of the deck
plating at the side of the deck amidships. Normally exposed to weather
and sea.
Flare:
The outward curvature of the side shell above the waterline. It promotes
dryness and is therefore associated with the fore end of ship
Extreme Beam:
The maximum beam taken over all extremities.
Extreme Draft:
Taken from the lowest point of keel to the summer load line. Draft marks
represent extreme drafts.
Extreme Depth:
Depth of vessel at ships side from upper deck to lowest point of keel.
Half Breadth:
Since a ships hull is symmetrical about the longitudinal centre line,
often only the half beam or half breadth at any section is given.
SCANTLING
The dimensions of the structural items of a ship, e.g. frames, girders,
plating , etc.
strong>INTERCOSTAL
Composed of separate parts, non-continuous
CENTER OF FLOATATION
It is the center of the waterplane area and is the axis about which a ship
changes trim.
CENTER OF BUOYANCY
It is the center of the underwater volume of the ship where the force of
buoyancy acts.
CENTER OF GRAVITY
It is the point at which the whole weight of the object may be regarded as
acting. If the object is suspended from this point, it will remain balanced
and not tilt.
TONNAGE MEASUREMENT
This is often referred to when the size of the vessel is discussed, and
the gross tonnage is quoted from Lloyds register.
1.
DISPLACEMENT TONNAGE
LOAD LINE
The marking on the ship side that relate to the loading condition of the
ship termed as the load line mark.
Load line mark
through the centre of the ring. The centre of the ring is placed
amidships and at a distance equal to the assigned summer freeboard
measured vertically below the upper edge of the deck line.
Margin Plate:
1.
2.
3.
Keel plate:
Keel is a horizontal plating of increased thickness, which runs
along the centre line, for complete length of bottom shell plating.
Types of keel:
(1) Bar keel (2) Flat plate keel (3) Duct keel.
Bar keel:
Duct keel:
1.
2.
Bulkhead
Class A bulkhead
It must be insulated so that the unexposed sides will not rise more
than 139C above the original temperaturewithin the time, as follows:
Class A- 60 , 1 hour:
Class A- 30 , 30 minutes.
Class B bulkhead:
It must be insulated so that the unexposed sides will not rise more
than 139C above the original temperaturewithin the time, as follows.
Class B- 15 , 15 minutes:
Class B- 0 , 0 minute.
Class C bulkhead:
Collision Bulkhead:
Corrugated bulkhead:
Non-watertight bulkhead:
Wash bulkhead:
Aft peak bulkhead needs only to extend to first deck above load
water line.
2.
3.
4.
Functions of bulkhead:
1.
2.
3.
4.
5.
To restrict volume of water, which may enter the ship, if shell plating
is damaged.
Construction of bulkhead:
Aft peak bulkhead needs only extend to first deck above load water
line.
Panting:
Racking:
Slamming or Pounding:
When ship is heaving and pitching, the fore end emerges from water
and re-enter with a slamming effect.
It is called pounding.
Hogging:
Sagging:
2) For ventilation
Transverse stresses:
Transverse bulkhead
Margin plates
Local stresses:
Causes:
Hull vibration.
Dynamic forces:
1.
2.
3.
1.
2.
3.
1.
2.
3.
2.
3.
Bulbous Bow:
Bow Thruster:
Cofferdam:
Double Bottom:
The double bottom consists of outer shell and inner skin, 1m and 1.5
m above the keel and internally supported by
1.
2.
3.
4.
5.
Wing Tank:
Purpose:
Deep Tank:
If DB tanks alone are used for this purpose, the ship might
be unduly stiff.
This tank is usually designed to carry dry cargo, and in some cases
may carry vegetable oil or oil fuel as cargo.
If the tank extends full breadth of the ship, a middle line bulkhead,
called Wash Plate must be fitted to reduce free surface effect.
Strength of Deep Tank structure is greater than that required for dry
cargo hold bulkhead.
Freeboard:
Main deck is the highest deck that is water sealed. Water falling
on upper decks may run down companion ways, but it cannot go any
further down into the ship than the main deck.
Reserved buoyancy:
Purpose:
Marking of freeboard:
Marking of minimum allowable freeboard, in conjunction with an overall
seaworthiness evaluation, is to ascertain that the vessel:
1.
2.
3.
4.
5.
has enough reserved buoyancy above the water line, so that vessel
will not be in danger of foundering andplunging when in heavy seas.
Hatchways:
These constructions must be in accordance with standards, such as
heights of coamings, covers, and fittings exposed. They have standard of
strength and protection.
Machinery Casing:
Machinery space openings on exposed portion of freeboard
deck (superstructure deck), must be provided with Steel Casing, with any
opening fitted with Steel Doors. Fiddley Opening is to have permanently
attached Steel Covers.
Tonnage:
Gross Tonnage:
Gross tonnage is the total of the Underdeck tonnage & the tonnage
of the following spaces:
1.
2.
3.
4.
5.
Exempted spaces:
1.
2.
Chain lockers and space for working anchor and steering gear.
3.
4.
2.
3.
2.
3.
4.
Tonnage Deck: The tonnage deck is the second deck, except in single
deck ships.
Water tightness of steel hatch cover:
Rubber jointing is used, and the hatch being pulled down
by cleats and cross joint wedges. Cleats are placed about 2 m apart with
minimum of two cleats per panel. Cross joint wedges should be 1.5 m
apart.
Hose test and chalk test:
1.
2. Cover or door seals, painted with chalk powder, and close the cover or
door tightly.
3. Open the cover or door, and check whether the chalk painted is cut off
or not.
2.
3.
Shut fuel supply to engine, remove No. 1 fuel pump delivery valve
assembly and put a bent pipe.
4.
Open fuel supply and when fuel lever is put to running position, oil
will flow out at bent pipe.
5.
Turn engine towards TDC in its running direction slowly until fuel
cease to flow.
6.
Shifting the coupling flanges between pump and drive side of the
engine.
Crankshaft:
1.
2.
Stresses in Crankshaft:
1.
2.
3.
4.
5.
6.
Types of crankshaft:
Solid forged
Semi-built
Fully-built
Welded crankshaft.
Welded Crankshaft:
Welds are placed and welded at the middle of all main journals, to
make complete crankshaft.
2.
3.
4.
5.
6.
7.
8.
Cold roll the crank pin fillets, to increase bending and corrosion
fatigue
9.
Finish machining.
2.
3.
4.
5.
6.
When major structure has been disturbed, such as: after fire
breakout, propeller bending or impounding with something,
ship grounding, before and after docking.
Causes of misalignment:
1.
2.
3.
4.
5.
6.
7.
8.
9.
Bending of crankshaft.
2.
3.
4.
2.
1.
2.
2.
2.
Foundation Chock:
Purpose:
1.
2.
3.
4.
5.
2.
3.
4.
Non-fretting permanently.
5.
6.
7.
8.
9.
Withstand temperature up to 80
Used for camshaft driving, on any length between shaft centres with
very small friction loss.
2.
3.
4.
5.
6.
7.
A roller chain consisting of side plates, bushing and rollers, and pin
joints, which mesh with tooted sprockets.
8.
9.
2.
3.
4.
5.
Effects:
1.
2.
3.
4.
5.
6.
7.
Before 4000 running hrs and after lengthy voyage, chain tension is
checked at mid span of slack side, in transverse direction.
2.
Total length of 10 links drawn tight and measured, and chainstretch calculated
links.
3.
4.
5.
6.
7.
Rubber clad guide bars, rollers and side plates, checked for crack or
damage.
2.
3.
2.
Class requires only a few links [6 links] for spares. The whole set
required for gear train.
3.
Even if the chain breaks, engine can still be operated after repair.
4.
5.
1.
2.
3.
Check that cylinder no: 1 crank throw is in TDC; (with D-1 pin gauge)
4.
5.
6.
Turn the whole camshaft using tackle until D-2 pin gauge mark is in
line with original marking. Fixed markings are on roller guide
housing [after removing cover] and on camshaft.
7.
Methods of reversing:
1.
2.
3.
4.
Reversing Interlocks:
1.
2.
3.
4.
Reversing Servomotor.
5.
Telegraph
6.
Turning Gear.
7.
Overspeed Trip.
engine requires turning of Inlet Valve cam, Exhaust Valve cam, Fuel
cam and arrangement for Starting air Distributor, with their correct
timings.
2.
Lost motion:
Angular period between TDC points for Ahead and Astern running will
be the lost motion required for Astern running.
1.
2.
Some 2/S, large bore, exhaust ported engines are Direct Reversing.
2.
Both Fuel Injection timing and Air Starting timing must be changed.
3.
4.
2.
Inlet Valve cam, Exhaust Valve cam, Fuel cam and arrangement for
Starting air Distributor, with their correct timings, must be changed.
3.
4.
2.
3.
4.
5.
6.
7.
Fuel Pump cam and Air Start cam will now operate the Engine in
reversed direction.
8.
9.
2.
By CPP.
3.
Tacho Generator:
In Sulzer RTA, also used for overspeed trip, using output current.
2.
3.
4.
5. Two-stroke engine: No load reversal takes place, which does not help
the oil flow into loaded part of bearing.
Different approaches adopted to overcome cross-head bearing
problems:
1.
2.
3.
4.
5.
6.
7.
8.
Thrust block:
Thrust block is cleaned by draining oil. And lift the top cover
2.
Place screw jack between casing and the back of the coupling, and
push the thrust shaft aft until the collar is hard up on the
3.
4.
5.
6.
Alternative method:
2.
3.
2.
3.
Tilting of pads, allow oil to form wedge shaped film, between faces
of collar and pads.
4.
Wedge shaped oil film prevents metallic friction and enables the
thrust pads to carry loads.
Disadvantages:
Each pad in a set must be exactly the same thickness, and even a
thou difference might result in a single pad carrying the entire load,
thus increasing the risks of failure.
2.
By applying maximum cooling after opening out the cooling coil out
into bilge.
3.
4.
Then the ship proceeds to the sheltered sea and renew the plumber
block bearing.
2.
3.
4.
5.
Remove the lower bearing halve with chocks from the stool.
6.
Refitting Procedure:
1.
After repairing, place back the lower halve with chocks on the stool.
But foundation bolts should not be placed.
2.
3.
4.
5.
6.
7.
Allowances:
Gap method: Equal to or less than 0.10 mm per meter for 1 to 2
pieces of shafts.
Checked with a feeler gauge between the two coupling flange faces, at
least at four places to check whether the bearing is in line with shaft or
not.
Sag method:
Place a straight edge over the two flanges, at least four places around, to
check whether the bearing is in line with shaft or not , or out of the
shafting vertically and horizontally.
CPP:
Two main types: Hub Servo and External Servo.
Hub Servo Type:
1.
2.
Functioning Principle:
Movements of piston effect blade pitch:
1.
2.
3.
4.
5.
6.
When piston rod moves axially by pressure oil, crank pin ring rotates
in circular motion, transmitted via piston,piston rod, slot, sliding shoe,
and crank pin.
7.
Failure Arrangements:
1.
Safety springs, fitted in main servo, push the servo piston forward,
to allow propeller pitch to full ahead position, in the event of hydraulic
system failure. The springs are powerful enough to overcome friction,
but RPM of 70% maximum should not be exceeded.
2.
3.
2.
3.
4.
5.
6.
Pilgrim Nut:
1.
2.
3.
4.
5.
2.
Steel jacking ring on landing face of the nut, is loaded with hydraulic
pump to predetermined pressure, and this forces the propeller hard on
its cone.
3.
4.
Pilgrim nut is taken-off the end of the shaft, reversed so that jacking
ring is facing outward, and screw back the nut onto shaft, leaving
some clearance between it and propeller boss.
2.
Studs are screwed into aft face of the boss and a strong back
plate is fitted over the studs.
3.
Stud nuts are fitted so that the plate contacts with jacking ring.
4.
Shaft Generator:
Shaft Generators are fitted on diesel engine propulsion ships, especially
those sailing for long period at a constant ship speed.
Lloyds Requirements:
1.
2.
Running condition:
1.
2.
More suitable for shaft with CPP, [constant shaft speed and variable
blade pitch].
2.
3.
Disadvantages:
1.
2.
3.
ME driven Generator:
1.
2.
3.
4.
Spaces for storage of cylinders or tanks for extinguishing gas should not
be used for other purposes.
The space should be located no more than one deck below the open deck.
Spaces where entrance from the open deck is not provided or which are
located below deck are to be fitted with mechanical ventilation.
The exhaust duct (suction) should be lead to the bottom of the space.
Such spaces should be ventilated with at least 6 air changes per hour.
Weighing of CO bottle:
1. Bottles should be weighed yearly by special
weighing device designed for this purpose.
2. It has a reference mark to determine 10% loss of
weight.
CO Quantity Calculation: (by Regulation):
The CO2 from the pilot cylinders will open the systems main stop valve.
The main stop valve has a piston which gets depressed due to the Co2 gas
pressure and allows the pilot gas to flow to the bank of CO2 cylinders.
This pilot gas operates the cylinders valves. All these valves have an
actuator which gets operated by the pilot pressure.
Before releasing Co2 into the fire affected space, it should be made sure
that everybody is out of the place and total head should be counted.
The place is fully enclosed i.e all skylights & ventilators are closed air-tight
and pumpsumps supplying fuel oil should also be stopped in order to prevent
re-ignition.
Separate levers for each and every space are present inside the main
controlling cabinet. The operating of a particular lever activates the pilot
bottles, which helps in releasing the complete bank of bottles designated for
that place.
With the opening of the master valve, Co2 is flooded inside the fire
affected space, which then smothers the fire with the help of blanket effect.
For detection of fire in cargo hold, a sample of air is drawn from all the
cargo holds by an extractor fan.
The sensors will detect any presence of smoke in the sample. As soon as
the sensor detects smoke in the sample, it activates the CO2 alarm system
of the ship.
2.
3.
Stop valve and pull handle are in lock release cabinet and alarm switch.
4.
5.
6.
2.
3.
4.
Recharge if 5 % loss.
5.
6.
7.
8.
9.
1.
2.
3.
4.
5.
6.
7.
8.
2.
3.
4.
Advantages:
1. Can permeate throughout the space.
2. After discharging, it leaves no residues and no damage to other parts.
3. No hazard for electrical equipment.
Disadvantages:
1. Only suitable for confined space, and needs total sealing of the space.
2. Fatal to life.
3. Re-ignition can occurs after fire is completely died out.
4. No cooling effects, only extinguished by smothering and inhibition.
Cut out power supply by circuit breaker & taking out fuse. Mark &
disconnect supply wire. Took Megger reading & recorded.
2.
Take out the motor, open up & dismantle. (Make sure marking on both
cover & body)
3.
4.
Cover by canvas, dry with positive ventilation & 500 watt lamp
5.
6.
7.
8.
9.
10.
Heater
2.
Cooling fan.
3.
4.
Preferential trip.
5.
6.
2.
2.
Centrifugal brake.
3.
Magnetic brake.
4.
5.
6.
Megger:
A Megger is an ohmmeter to measure insulation resistance in million of ohms. (Pole
to pole, pole to earth). Good insulation has high resistance; poor insulation, relatively
low resistance. The actual resistance values can be higher or lower, depending upon
such factors as the temperature or moisture content of the insulation (resistance
decreases in temperature or moisture).
Purpose of Megger Test:
1.
2.
Circuit breakers
2.
3.
4.
Preferential trip
5.
6.
Fuse
7.
Earth lamp
8.
9.
10.
Dead front panel safety device provided on the Main switch board
individual panels wherein you cannot open the panel until the power of that
panel is switched off.
Where arrangements are made for the supply of electricity from a source
on shore or other location a suitable connection box has to be installed in a
position in the ship suitable for the convenient reception of flexible cables, it
should contain a circuit breaker or isolating switch, fuses, and terminals of
adequate size to receive the cable ends.
For three phase shore supplies with earthed neutral terminals are to be
provided for connecting hull to shore earth
Preferential trip:
If a generator overload condition develops, its preference overload trip will operate
to energise the timing relay. The timing relay then operates to disconnect nonessential services in a definite order and at definite time intervals.
Essential
Top polarity
5 sec:
5 sec:
(propulsion, navigation)
15 sec:
Static electricity:
Spontaneous combustion:
The ignition of material brought about by a heat producing exothermic chemical actin
within the material itself, without exposure to an external source of ignition. (Wet oily
rags, wet saw dust)
Armature reaction.
When a D.C generator or a motor is operating with load, sparking between the
carbon brushes and the commutator results due to Armature Reaction. Armature
reaction takes place when the armature current flows in the armature.
When current flows in armature, the armature core is magnetising by this current.
Magnetising effect of the armature current can be divided into two effects:
To compensate the Armature reaction, modern Electrical Machines are provided with
Interpoles
Neutralising Winding.
2.
3.
4.
5.
Dash pot
Mechanical device to produce a time delay action. Operation of switch gears, arc
lamps, motor starters, Electro magnetic bake, etc. Time delay is adjusted by oil
viscosity used.
The earth fault detector consists of three incandescent lamps which are
connected in star. These three lamps are supplied from the secondaries of
three single phase step down transformers. The primaries of three
transformers are connected in star. The star point of the primaries is
connected the frame of the ship. The primaries of these transformers are fed
from the red phase, yellow phase and blue phase of the ship supply.
Giving visual signals and buzzer will sound when there is an Earth fault in
the system on board.
Three incandescent lamps which are connected in star. These three lamps
are supplied from the secondaries of three single-phase step down
transformers.
The primaries of these three transformers are connected in star. The star
point of the primaries is connected the Frame of the ship. The primaries of
these transformers are fed from the Red phase, Yellow Phase and Blue Phase
of the ship supply main.
No Earth Fault in the system, Lamps will glow with equal brightness.
When earth fault occurs one of the phases, the lamp on that phase will
become dark and other two lamps will burn with extra brightness.
Earth fault can be traced by switching off the branch circuit breaker one by
one. When the branch circuit with the fault is switched off, the earth lamp
will return to its normal glow.
Emergency lights.
2.
Navigation lights.
3.
4.
5.
Ships whistle.
6.
7.
8.
9.
10.
Steering gear.
11.
Single phasing:
Single phasing is the term used to denote the condition arising in a threephase circuit when one phase becomes open circuited.
The open circuit in a phase, often from a blown fuse, faulty contact or
broken wire, will prevent a motor from starting but running motor may
continue to operate with a fault.
1.
2.
This system avoids the risk of loss of essential services e.g. steering gear
If the neutral was earthed and a short circuit on one phase causes the fuse
in that phase to blow the system would now be singled phasing and may
burn out motors
In an insulated neutral, one earth fault does not interrupt the supply but
an earth leakage detection system will give warning.
Low earth fault currents in insulated systems gives a much less fire risk.
Disadvantages
On the insulated system the voltage to earth is 1.73 Vph e.g. 440v vs
250v
Back E.M.F
When the armature conductors are moving across the magnetic field,
these conductors will cut the magnetic lines of force and therefore generate
an E.M.F. The direction of this generated E.M.F is opposite to the applied
voltage of the motor. Since the generated E.M.F in the motor is opposite to
the applied voltage to the motor, this E.M.F is called Back E.M.F.
Ir
Eb
2.
The alternator output is transformed, rectified and output effect through magnetic coil
against spring which are voltage reference and apply to dc exciter shunt field and
rotor of alternator.
3.
The direct current derived from the alternator output through transformer & rectifier,
is applied to a bridge which has fixed resistances on two arms and variable
resistances (zener diode voltage references) on the other two. When change in
applied voltage, by Whetstone bridge produce an error signal. The error signal can
Diode
1.
2.
Transistor
Used small signal power from a side circuit controlling the larger power in
other circuit. (Power gain or amplification)
Thyristor
E.g.
Exciter:
Equaliser
An equaliser is a connection between the generators of different capacities running
in parallel so that the running load is divided proportionately between the two.
2.
Emergency lighting.
3.
4.
Maintenance of motors:
1.
2.
3.
4.
5.
6.
Galvanometer:
It is an instrument for measuring the small electric current with its magnitude and
direction.
Resistor:
It is a device, which conducts electricity but converts part of the electrical energy into
heat.
Resistivity:
It is a resistance of a material and expressed in ohms/unit length.
Rheostat
It is a resistor, which is provided with means for readily adjusting its resistance.
First of all the circuit breaker to be break out. Then extinguished with the
fire with CO2 portable extinguisher.
2.
3.
4.
After tracing and renewing all fittings, the switchboard can be put back
into service.
Fire Prevention:
1.
2.
3.
Causes of Fire:
1.
Loose contact.
2.
Incorrect fuse.
3.
Residual magnetism:
When starting up a generator, the necessary magnetism is provided by the iron
cores of the field poles. This magnetism is known as residual magnetism.
2.
Lap wound.
Wave wound
Failure to excite:
1.
2.
Universal motor:
1.
Series wound.
2.
Single phase.
3.
4.
Synchronising:
1.
Synchroscope
2.
Synchronising lamp:
Preparations:
Dry docking survey is to be done every 2 years interval , 2 times in 5
each year cycle , called annual docking and special docking survey.
Special survey is carried out every 5 years interval.
As a Chief Engineer of a vessel , he must study the time of dry docking
due , verify annual or special , and prepare documents & defect list to be
repaired , at least 3 months priority for easy and efficient supports from
ship company.
Preparation of Documents:
Paints
Issue assignments for the work to be done before entering dry dock and to
be undertaken by E/R staffs under 2nd Engineer supervision.
Repair List
A. Repair list to be provided as:
1.
2.
B. The following dock yard repair items to be mentioned details with their
specifications as follow:
Dimensions
Dimensions
Piping repairs
Structural Repairs
steels
Machinery Repairs
Machinery Survey
1.
Rudder
2.
Propeller
3.
4.
Stern tube
5.
Tail shaft
To show location of repair items to dock yard crew and check their work
assessment . To co-operate in some places. ( Drain of water to correct tank
etc )
To check and record measurement taking for Rudder pintle clearance and
stern tube wear down .
If repair works for rudder , propeller , tail shaft withdrawing , stern tube
repair and renewal shaft seal , provide an Engineer and crew to check and
note down the work done by dockers. C/E himself require to be stand by
there.
To note daily work done by dock yard and enter to Chief Engineer log.
Cleaning of E/R tank top & bilge wells , Clear drain tanks.
Prepare cooling water connections for fridge and air conditioning plant
Valves from bilge and ballast system , cooling water system , steam line
and air lines. to be overhauled.
Certificates onboard:
1.Certificate of Registry
2. International Tonnage Certificate
3. International Load Line Certificate
4. International Load Line Exemption Certificate
5. Certificates for Master, Officers and Ratings
SOLAS Certificates:
1.
2.
3.
4.
5.
6.
Exemption Certificate
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
MARPOL Certificates:
MARPOL Annex I:
1. International Oil Pollution Prevention Certificate (IOPP Certificate)
2. Statement of Compliance with CAS (as a supplement to ships IOPP
Certificate)
MARPOL Annex II:
1. International Certificate of Fitness for the Carriage of Dangerous
Chemicals in Bulk
2. Certificate of Fitness for the Carriage of Dangerous Chemicals in Bulk
3. International Pollution Prevention Certificate for the Carriage of Noxious
Liquid Substances in Bulk (NLS Certificate)
4. Certificate of Fitness for Offshore Support Vessels
MARPOL Annex IV:
1. International Sewage Pollution Prevention Certificate
2. Result of calculation of moderate rate of discharge in accordance with
MEPC.157(55)
MARPOL Annex V:
1. Garbage Management Plan
2. Garbage Record Book
MARPOL Annex VI:
1. International Air Pollution Prevention Certificate
2. Engine International Air Pollution Prevention Certificate
incl. Technical File and Record Book of Engine Parameters if applicable.
3. International Energy Efficiency Certificate
Fire Hose:
1.
At least one fire hose for each of the hydrants and hose shall be used only
for extinguishing fires and testing purposes. (Passenger Ship)
2.
One for each 30m length of ship and one spare, but not less than 5 in
all. (Cargo Ship = or > 1000GT) and ship carrying dangerous goods shall be
provided 3 hoses & nozzles in addition to those required above and cargo
ship <1000GT, shall be provided no less than 3 fire hoses & nozzles.
3.
4.
Nozzle for ER 12mm, 16mm and 19mm size and shall be approved for duel
purpose (jet/spray) incorporating shut-off valve.
5.
Fire hoses shall have a length of at least 10 m, but not more than:
15 m in machinery spaces;
1.
0.40 N/mm.
2.
0.30 N/mm.
3.
0.27 N/mm.
4.
Para 2.1.6)
Diameter of Fire Main and Water Service Pipe need only be sufficient for
effective distribution of the maximum required discharge of 140 m/ hr from
2 Fire Pumps operating simultaneously. (SOLAS Ch II-2 Reg 10 Para 2.1.3)
Fire pumps:
Requirements:
1.
A.
0.40 N/mm.
B.
0.30 N/mm.
C.
0.27 N/mm.
D.
10 Para 2.1.6)
2.
In Cargo Ships = or > 1000 GT: at least 2 fire pumps and <1000 GT: at
least 2 power driven pumps, and 1 of which shall be independently
driven fire pump shall be provided.
2.
3.
4.
5.
Total suction head and net positive suction head shall be such that,
minimum 25 m/hr capacity, 2 water jets of 40 ft horizontal throw, shall be
obtained, under all conditions of list, trim, roll and pitch.
6.
It is self-cooled.
Fuel service tank must have sufficient capacity for at least 3-hour
operation,
full load.
full load.
7. If motor driven:
Power operated emergency fire pump, with source of power and sea
connection, must be located outside machinery space.
Sprinkler System:
1. By Regulation, passenger ships carrying more than 36 persons shall be
provided with Automatic Sprinkler System.
2. Generally used only to protect living quarters, passageways and public
spaces.
Operation:
1. Each sprinkler head provided with a quartzoid valve, which seals the
outlet of water pipe.
2. Valve is partially filled with special fluid, so that a rise in room
temperature will expand the liquid and the valve will burst.
3. Water under pressure; will flow out from Sprinkler System. ( 5 8 bars
pressure is maintained in FW pressure tank by air pressure.)
4. Sprinkler head can cover a floor area of about 12m with water pressure
of 5 8 bars.
5. Pressure drop in tank activates the pumps to take over and supply
water from FW holding tank. When holding tank become empty, SW
pumps come into action automatically.
Regulations
1. No: of heads not more than 200 per section.
2. Heads are spaced not more than 4 meters apart.
3. At least 2 sources of power supply to Automatic alarm system and SW
pump.
Advantages:
1. Self fire detection, and immediate and automatic operation at all time
2. Not harmful to human.
3. No need to seal the space.
4. No need to clean the media, after use.
Various sprinkler head colour: Red
Yellow
Green
Blue
Purple
Quartzoid valve will burst at:
68C
79C
93C
141C
182C
Inert gas:
1. The gas which does not support combustion is inert gas, such as CO,
N, and boiler flue gas containing < 11% O.
2. Tankers of 20,000 DWT and above, provided with Fixed Inert Gas
System.
a) To prevent accumulation of explosive mixtures in cargo tanks, during
ballast voyage and during tank operations.
b) To minimise risks of ignition by static electricity generated by the
system itself.
3. Inert gas is used only in fixed installations and large bore piping are
used due to low pressure of the gas.
4. Main function is essentially fire-preventive by providing an inert
atmosphere.
5. Inert gas installation is not acceptable in machinery spaces.
N ~ 80% by volume:
CO ~ 14%:
O ~ (2 5)%:
CO ~ 0.01%:
SO ~ 0.005%:
Soot ~ 50 mg / m
Extinguishing Media:
Water: Cooling and smothering by steam.
Foam: Combined effect of cooling and smothering.
CO: Smothering and inhibition.
Dry Power: Extinguished by inhibition ( breaking chain reaction.)
Inert Gas: Fire-preventive, by providing an inert atmosphere.
When fire breaks out:
Cargo deck area: Fixed deck foam system for cargo deck area.
Paint Locker:
2.
3.
Means of escape.
Life buoys
2.
Life jackets
3.
Immersion suits
4.
Firemans outfit:
Consists of:
Entrance Doors
2.
3.
Skylight Doors
4.
Ventilator Flaps
Fire Detectors:
1.
Heat Detector
2.
Flame Detector
3.
Smoke Detector
4.
Heat Detector:
2.
3.
Two bi-metal coils are attached to a vertical support bracket and upper
coil is better insulated from heat than lower coil.
2.
3.
If rate of temperature rise is sufficient, the gap will close and alarm given.
4.
Flame has a characteristic flicker frequency of about 25 Hz, and this fact is
used to trigger an alarm.
2.
3.
Signal from cell goes into amplifier, which is tuned to 25Hz, then into time
delay unit and alarm circuit.
4.
5.
6.
7.
Smoke Detectors:
1.
Light Scatter
2.
Light Obscuration
3.
2.
3.
4.
5.