Escolar Documentos
Profissional Documentos
Cultura Documentos
Sl.
No.
1
Zone
Direction
Zone-1
Forward
Zone-2
(for 400
kV and
above)
Forward
Forward
Zone-2
(for 220
kV and
below)
Zone-3
Zone-4
Reverse
2a
2b
Forward
Time Settings
(in Seconds)
Instantaneous (0)
Remarks
As per CEA
As per CEA
As per CEA
As per CEA
As per CEA
In 28th PCC, Powergrid informed that the revised settings will be discussed at their Engineering
Wing in a separate meeting scheduled to be held in March, 2015. Powergrid informed that they
will communicate their views.
It was decided that a Special meeting for finalization of Zone settings as per the revised protection
philosophy will be held in the month of April, 2015. All constituents are requested to submit the
zone settings as per revised philosophy by 30th March, 2015.
NTPC vide mail dated 18.03.2015 has communicated their views on revised protection philosophy
which is enclosed at Annexure-A.1.
Till date, only BSPTCL has submitted the revised zone settings. And it was observed that Z-3
settings were not as the above philosophy.
JUSNL, DVC, OPTCL, WBSETCL, NTPC and Powergrid (ER-I, ER-II & Odisha projects)
are requested to submit for finalization of zone settings.
Deliberation in the meeting
The Protection Philosophy was reviewed again on the basis of comments received from NTPC
and Powergrid also in agreement with the principles, which is as given below:
Sl.
No.
1
Zone
Direction
Zone-1
Forward
Zone-2
(for 400
kV and
above)
Forward
Forward
Zone-2
(for 220
kV and
below)
Zone-3
Zone-4
Reverse
2a
2b
Forward
Time Settings
(in Seconds)
Instantaneous (0)
Remarks
As per CEA
As per CEA
As per CEA
As per CEA
with minor
changes
As per CEA
As per CEA
Note: Zone-2:- Z2 Reach should not encroach the next lower voltage level.
Zone-3:- If Z3 reach encroaches in next voltage level, then Z3 time must be coordinated
with the fault clearing time of remote end transformer.
Zone-4:- If utility uses carrier blocking scheme, then the Z4 reach may be increased as per
the requirement. It should cover the LBB of local bus bar and should be coordinated with
Z2 time of the all other lines.
All the constituents agreed on the principles and ryder note as above.
Thereafter, PCC advised all constituents to submit their revised settings at the earliest as per the
above agreed philosophy so that the finalization of the zone settings can be done in the next
meeting.
All constituents agreed to submit revised settings within a month.
Powergrid was advised to submit the values of R, X, Ro, Xo parameters for various conductors
used in 132 kV, 220 kV and 400 kV lines so that values can be standardized for zone settings
computation.
Powergrid agreed.
During special meeting on 30.12.2014 members raised the issue regarding finalizing settings of
the Directional Earth Fault (DEF) and Back up O/C. Earlier it was decided that all DEF and Back
up O/C would be of IDMT characteristic because the operating time of IDMT relay will depend on
the magnitude of fault current. Therefore, Back up O/C relay can not be coordinated with Distance
Protection Relay, which are of definite time characteristic. So, they can be coordinated only with
other IDMT relay instead of line or back up O/C and E/F relay of auto-transformer. Now, the
question was how the back up E/F relay can be coordinated with Z3 of Distance relay.
It was viewed that some flexibility should be allowed in time setting because back up E/F relay
should operate prior to or later than Z3 relay will depend on the nature/ importance of the network
in the next line section/ next voltage level. It was decided that further deliberations were required
and all constituents were advised to submit their views on the issue in the next PCC meeting
In 27th PCC, members raised the issue regarding finalizing settings of the Directional Earth Fault
(DEF) and Back up O/C.
The house was informed that a separate meeting would be held after 29th TCC Meeting for
finalization of the protection settings. Meanwhile, constituents were advised to send their views on
revised settings.
Constituents agreed but the comments from the constituents are still awailed.
ii)
Back up O/C: As back up for VT fuse fail or loss of voltage. Settings: 150 % with 1.8
sec delay for definite time and for IDMT settings characteristics shall be such that at
150 %, it takes 1.8 sec.
DEF: 30% of neutral current with 1.5 sec delay. Some constituents calculate its settings
by creating a fault at 80 % of line and in co-ordination with Z2.
After detailed deliberations, PCC advised all constituents to submit their present settings of Back
up O/C and DEF and the philosophy used behind such settings within a week. Thereafter, the
detail of these settings will be studied and final settings for Back up O/C and DEF will be decided
in next meeting.
All constituents agreed.
DVC has submitted their present philosophy for DEF & DOC which is enclosed at Annexure-A.2.
****************
NTPC VIEWS
The present philosophy of Z1 and Z2 reach setting followed by NTPC is in
line with CEA recommendations. The proposal of extending Z1 reach of 132
Kahalgaon (NTPC)- Kahalgaon line to 100% is also acceptable as delayed
fault clearance affects our auxiliaries.
Z2 operation time being adopted is 0.4 s and 0.5-0.6s for long line
followed by short lines which is adequate keeping in view the fault
clearance time and LBB time.At the most Z2 time can be reduced to 350mS
with LBB time delay of 200mS. Presently, Z3 reach is set to cover 120% of
protected line plus longest line emanating from remote sub-station,
provided it does not reach into the next voltage level.
22
Annexure-A.2
400KV
220KV
220KV
ICT
Z3 = 800ms
67 / 67N =
1.0s 1.1s
Z3 = 800ms
67 / 67N =
900ms 1.0s
Figure 1
FAULT