Escolar Documentos
Profissional Documentos
Cultura Documentos
NITROGEN
HYDRO
PET
CNG
TABLE OF CONTENTS
Section 1
Compressor Manual
Section 2
Motor Manual
Section 3
Drawings
Section 1
Compressor Manual
V290M-WN
Compressor
Table of contents
V290M-WN Compressor Manual
Introduction .....................................................................................................................................4
Chapter 1 - Technical Data and Description ....................................................................................7
1.1
1.2
1.3
3.2
3.3
3.4
Installation Procedure......................................................................................................36
3.5
3.6
4.2
4.3
4.4
Running...........................................................................................................................45
4.5
4.6
5.2
5.3
Issue 1
01/2015
Page 1
V290M-WN
Compressor
JOB No: 5 - Piston/Cylinder End (Bumping) Clearances ............................................................66
JOB No: 6 - Packing Assembly - Remove and Re-fit..................................................................69
JOB No: 7 - Packing Assembly - Overhaul .................................................................................73
JOB No: 8 - Packing Assembly - Remove and Re-fit..................................................................75
JOB No: 9 - Oil Scraper Gland - Remove and Re-fit ..................................................................77
JOB No: 10 - Suction and Delivery Valves - Remove and Re-fit.................................................79
JOB No: 11 - Suction and Delivery Valves - Overhaul................................................................82
JOB No: 12 - Suction and Delivery Valves - Remove and Re-fit.................................................84
JOB No: 13 - Oil Filter - Remove and Re-fit ...............................................................................86
JOB No: 14 - Oil Pressure Relief Valve - Adjustment .................................................................87
JOB No: 15 - Lubricating Oil Pump and Drive - Inspect and Overhaul........................................88
JOB No: 16 - Intercooler - Inspection and Overhaul ...................................................................89
5.4
5.5
6.2
6.3
6.4
Drawings .........................................................................................................................95
Issue 1
01/2015
Page 2
V290M-WN
Compressor
Issue 1
01/2015
Page 3
V290M-WN
Compressor
Introduction
Important
This Instruction Manual covers Installation & Commissioning, Operation and Maintenance of the
Gardner Denver Industrial range of compressors.
It is ESSENTIAL that this document is read and understood by everyone who will work with this
equipment, as failure to do so may result in death, injury or damage to the compressor or its
associated equipment.
Disclaimer
While every care was taken in the preparation of these instructions, it cannot be guaranteed that
every aspect has been covered. Gardner Denver Belliss & Morcom cannot, therefore, accept
liability for direct or consequential damage that may arise resulting from non-conformity with this
Manual, from repairs carried out improperly, from using other than original spare parts, and from
non-observance of good operating and maintenance engineering practices. Should there be any
doubt whatsoever, or should any further information or explanation be required, Gardner Denver
Belliss & Morcom must be contacted.
This information is given in good faith, no warranty or representation is given concerning such
information, which must not be taken as establishing any contractual or other commitment binding
upon Gardner Denver Belliss & Morcom .
Gardner Denver Belliss & Morcom reserve the right to make changes to any information
contained within this manual without prior notice.
Warranty Statement
The compressor(s) and ancillary equipment supplied by Gardner Denver Belliss & Morcom are
covered under Warranty for the period agreed in the Supply Contract.
The equipment provided is well designed to afford many years of trouble free service. However,
should the need arise to implement a warranty claim then this can be done using Warranty Claim
Form obtainable from Gardner Denver Belliss & Morcom Service Department. A copy of this
form is provided in Appendices located at the end of this manual.
It should be noted that consumable parts that require replacement during normal compressor
operations are not normally covered under Warranty. Similarly, the Warranty does not cover
running adjustments.
Gardner Denver Belliss & Morcom are well known in the market place for the design,
manufacture and supply of high-quality air compressor equipment. These compressors are
constructed from the highest quality materials and are designed and built according to the latest
manufacturing techniques. The compressor design will give good service providing that it is
operated and maintained in accordance with the information contained within this Manual.
The information and notes presented in the 'Ancillary Devices Instruction Manuals will provide
operational and maintenance information for the control and instrumentation system, motor/drive
unit and where appropriate, any other device associated with the compressor package.
Targeted Personnel
Issue 1
01/2015
Page 4
V290M-WN
Compressor
This document is designed to provide competent operatives, who are fully conversant with
compressor operating and maintenance techniques, with an understanding of the compressor
elements and their operation and subsequent maintenance. It should be noted that the term
'competent' implies that the operative is a compressor engineer suitably trained in the installation,
operation and maintenance of the Gardner Denver Belliss & Morcom product.
This Instruction manual is not intended to supersede or take the place of the Gardner Denver
Belliss & Morcom product-training course. For further information regarding training courses or to
book a place, please contact Gardner Denver Belliss & Morcom Service Department. The
address, telephone/facsimile number is provided at the start of this documentation.
CAUTION!
THIS PICTOGRAM WITH THE REMARK CAUTION! IDENTIFIES THE
POSSIBILITY THAT IF NON-COMPLIANT THE COMPRESSOR AND/OR ITS
ASSOCIATED EQUIPMENT CAN BE DAMAGED.
Documentation Storage
Always store this Instruction Manual near the compressor so that it is available for reference at all
times. If the instruction manual is lost, Gardner Denver can supply a new copy for a small fee.
When requesting new or additional copies, of this document, please include your compressor
details with your order.
Issue 1
01/2015
Page 5
V290M-WN
Compressor
Point of Contact
For sales, service or spare parts enquiries, please contact :
Address :
Telephone :
Fax :
E-mail :
highpressure@gardnerdenver.com
Website :
www.gardnerdenver.com
Issue 1
01/2015
Page 6
V290M-WN
Compressor
Issue 1
01/2015
Page 7
V290M-WN
Compressor
Issue 1
01/2015
Page 8
V290M-WN
Compressor
Operating Data
Table 1-1: Operating Data
Compressor
Model
V290M-WN
Number of Stages
Inlet Pressure
Atmospheric
Cylinder Type
Direction of Rotation
Flow
Imperial
290
m3/hr
171
ft3/min
Stage 1
bar.g
58
lb/in2
Stage 2
20.7
bar.g
300.55
lb/in2
Delivery
90
bar.g
1350
lb/in2
Stage 1
4.4
bar.g
63.8
lb/in2
Stage 2
22.8
bar.g
330.6
lb/in2
Stage 3
99
bar.g
1435.5
lb/in2
Oil Pressure *
3.0 - 4.8
bar.g
43.5 - 69.6
lb/in2
Stage Pressures
bar.g
lb/in2
Sump Capacity
35
litres
9.8
11.8
UKgal
USgal
985
rpm
985
rpm
Vibration
2.5
mm/s
0.01
ft/s 2
90
db(A)
90
db(A)
115
db(A)
115
db(A)
4565
kg
10065
lb
5375
kg
11850
lb
1000
kg
2204
lb
Normal Pressure
bar.g
87
lb/in2
Maximum Pressure
10
bar.g
145
lb/in2
Instrument Air
Issue 1
01/2015
Page 9
V290M-WN
Compressor
Table 1-1: Operating Data (Continued)
Cooling
Design Ambient
0 - 35
32 - 113
153
l/min
34
41
UKgal/min
USgal/min
4-7
bar.g
58 - 102
lb/in2
bar.g
lb/in2
14
Compressor
Radiated Heat
kW
27321
Btu/h
110
kW
148
hp
76.5
kW
103
hp
Body
Motor
*Oil pressure will fluctuate with ambient conditions, compressor loading and with the type
and viscosity of the oil being used. Also; oil pressure peaks during start-up before settling
back as the oil reaches operating temperature.
** Cooling Water Flow rates are design estimates and may have to be adjusted to suit
ambient site conditions.
This machine is fitted with over-temperature monitoring safety switches for final air from
both the third stage cylinder and the aftercooler. Details of the settings for these devices
are given in Table 1-4:Protection device settings on page 7
b)
Compressor Data
Figures are quoted for new parts. The upper and lower limits arise due to accumulated
effect of manufacturing tolerances. All butt gaps are measured with the piston ring in the
cylinder.
Issue 1
01/2015
Page 10
V290M-WN
Compressor
c)
Mechanical Data
Table 1-2: Piston and Cylinder Data
Piston Data
Metric
Piston Stroke
Imperial
104
mm
253.06
253.00
mm
3.34
3.04
mm
Piston Ring
Radial Thickness
11.5
11.4
mm
0.65
0.50
mm
7.1
6.4
mm
Diametrical Clearance in
Cylinder bore
1.68
1.40
mm
Radial Thickness
9.00
8.95
mm
0.55
0.40
mm
Standout
body
1.22
1.20
mm
Bearer Ring
from
piston
Gap at joint
N/A
Bumping Clearance
Piston Top to Top Cover
3.5
mm
2.3
mm
196.047
196.000
mm
4.04
4.00
mm
Issue 1
01/2015
Page 11
4.09
in
V290M-WN
Compressor
Table 1-2: Piston and Cylinder Data (Continued)
Piston Ring
Radial Thickness
12.00
11.82
mm
0.35
0.20
mm
6.4
5.8
mm
Diametrical Clearance in
Cylinder bore
2.52
2.50
mm
Radial Thickness
8.0
7.9
mm
in
0.72
0.58
mm
piston
N/A
mm
Bearer Ring
Axial
Groove
Clearance
Standout
body
from
N/A
Gap at joint
Bumping Clearance
Piston Top to Top Cover
N/A
mm
2.0
mm
78.03
78.00
mm
1.76
1.70
mm
11.00
10.82
mm
in
0.35
0.20
mm
1.2
1.1
mm
0.96
0.95
mm
Piston Ring
Radial Thickness
Axial
Groove
Clearance
Bearer Ring
Diametrical Clearance in
Cylinder bore
Issue 1
01/2015
Page 12
V290M-WN
Compressor
Table 1-2: Piston and Cylinder Data (Continued)
6.00
5.95
mm
in
1.70
1.50
mm
piston
1.60
1.50
mm
N/A
mm
N/A
mm
2.1
mm
Radial Thickness
Axial
Clearance
Groove
Standout
body
from
Gap at joint
Bumping Clearance
d)
Connecting
End Bearing
Rod
Bearings
Imperial
0.031 - 0.076
mm
0.0012 0.003
in
0.10 - 0.15
mm
0.004 - 0.006
in
0.20
mm
0.008
in
0.07 - 0.10
mm
0.003 - 0.004
in
0.107 - 0.293
mm
0.004 - 0.011
in
0.4
mm
0.016
in
Bottom
New
Maximum
Issue 1
01/2015
Page 13
V290M-WN
Compressor
Table 1-4: Protection device settings
High air temperature (3rd St Delivery)
65 C (149F) (rising)*
* Switch is factory set to 65 C. for temperate (UK type) climates. The switch may be
adjusted up to a maximum of 75 C. to suit tropical climates during or after installation.
However, adjustments MUST only be performed by a competent, authorised person.
e)
Thread Size
Torque Nm
Crankcase Components:
Bearing End Cover
M20
128 140
M16
98 108
M8
15 20
M10
25 30
M10
45 55
M12
45 55
M20
128 140
Flywheel Retaining
M42
375 - 400
M20
200 220
M24
200 - 220
M6
10 - 15
Issue 1
01/2015
Page 14
V290M-WN
Compressor
Table 1-6: Component tightening Torques (Continued)
Thread
Size
Component
Torque Nm
M20
190 - 210
Valve Covers
M12
29 - 32
M16
90 - 110
Inlet Flange
M20
190 - 210
Outlet Flange
M16
98 - 108
M20
128 - 140
Cylinder to Cylinder
M24
200 - 220
Valve Covers
M20
190 - 210
Valve Nuts
M16
90 - 100
Inlet/Outlet Flange
M24
200 - 210
M20
128 - 140
M8
16 - 18
M16
Valve Covers
M20
190 - 210
Valve Nuts
M16
90 - 100
M20
190 - 210
1 5/8 BSF
555 - 610
1 3/8 BSF
510 - 560
Crankshaft Lock-nut
M160
1750
134 - 140
Issue 1
01/2015
Page 15
V290M-WN
Compressor
b)
Compressor Identification
All Gardner Denver compressors have a rating plate located on the crankcase. The
information stamped onto this plate identifies the compressor type, capacity and serial
number. The compressor designation indicates the following:
V - Denotes cylinder configuration
290 - Denotes nominal capacity in m3/hr
M - Denotes medium pressure three stage
W - Denotes water-cooled
N - Denotes oil free cylinder operation
3rd
Stage
Cylinder
Aftercooler
Inlet Filter & Silencer
1st Stage
Cylinder
2nd
Stage
Cylinder
Distance Piece
Access Cover
Seperator
Distance
Piece
Access Cover
Lubricating Oil
Pump &Filter
Intercooler
Issue 1
01/2015
Page 16
V290M-WN
Compressor
c)
Compressor Operation
The compressor operates by drawing air from atmosphere via an efficient air filter and
silencer system into the first stage cylinder where it is compressed to approximately 4 Bar
G. The heat, generated by compressing air, is dissipated by passing through the watercooled intercooler. The cooled air then flows through the 2nd stage suction separator,
which removes any free moisture, condensed during cooling.
Air then passes to the 2nd stage cylinder where the air is further compressed to
approximately 21 Bar G. The heat generated by compressing the air is dissipated in the
second stage intercoler. Air then flows through the 3 rd stage suction separator, which
removes any moisture condensed during second stage cooling.
The air then passes to the 3rd stage cylinder where the air is further compressed to its
final delivery pressure of 90 Bar G (max). The heat from compression is dissipated in the
watercooled aftercooler positioned after the 3rd stage cylinder. The final delivery
separator removes any moisture condensed during cooling. The compressed air is then
discharged into the delivery pipework.
d)
Issue 1
01/2015
Page 17
V290M-WN
Compressor
oil output is by-passed back to the sump by a spring-loaded pressure relief valve mounted
on the crankcase main bearing housing.
All the bearing surfaces in the crankcase are lubricated by the oil passing through the
bore of the crankshaft and connecting rods. The main roller bearings are splash lubricated
by the oil from the crosshead, and also by the general oil mist in the crankcase.
4 - Connecting Rods
The connecting rods have detachable bottom end caps to enble removal of the rods and
rods have split-shell bottom end bearings and bush type top end bearings. The bottom
end bearing shells are steel backed copper-lead, lead-tin plated. The pressed-in top end
bushes are lead bronze.
An oil passage connects the top and bottom bearings allowing oil under pressure (from
the oil pump via passages in the crankshaft) to lubricate both. Oil is sprayed, from an
annular groove around the top end bush and through two small holes, onto both slides of
the crosshead guide.
5 - Crossheads
The crossheads run in the main guides which are bolted to the cylinder mounting flange of
the crankcase. The crossheads are attached to the top of the connecting rods by gudgeon
pins (which are retained themselves by circlips). The top face of the crosshead is drilled
and tapped for reception of the piston rod. The piston rod is retained by a securing pin
which passes through the side of the crosshead into the slot in the end of the piston rod.
The piston rod is then clamped by a nut, which is tightened down against the top of the
crosshead. The securing pin is prevented from coming loose by a retaining plate.
e)
Issue 1
01/2015
Page 18
V290M-WN
Compressor
aluminium and the piston rings are made from composite material. Compression rings are
jointed to assist with replacement during servicing. Bearer rings are solid (un-cut) and are
located on the pistons between the piston upper and lower halves.
3 - Piston Rods and Packings
The piston rods are threaded at both ends. The piston rod bottom end has a cruciform slot
to accommodate a securing pin (to prevent rotation of the rod in the crosshead) and is
held in the crosshead by a locknut. The top end of the rod is shouldered and waisted
inside the piston. A self-locking nut secures the piston to the rod.
The piston/cylinder end clearances at the top and bottom are governed by the distance
the piston rod is screwed into the crosshead.
The oil-free cylinder compressor has separate packing gland assemblies. The packing
comprises multiple sets of sealing rings, each set of rings being housed in a container and
held against the piston rod by a garter spring. The containers are assembled to a base by
long studs and nuts, and the assembly held in its housing in the base of the cylinder by
studs and nuts. A soft iron ring is recessed into the top surface of the upper container to
prevent air leakage around the packing.
The separate scraper assembly is housed in the crosshead-guide loose plate and
comprises a number of segmented rings in a split casing, each ring is held in contact with
the piston rod by a garter spring.
An oil shedder is also fitted to the piston rod between the packing and the scraper
assemblies to prevent any oil-creep along the rod.
f)
Valves
Suction and delivery valves are similar in construction but differ in detail. Care must
always be taken when servicing the compressor to ensure that the correct valve is fitted
into the correct valve chamber.
All suction valves are controlled by plate depressors (or unloaders), their location being
identified by the presence of actuators on the valve covers. The actuators have small bore
instrument air pipes connected to them.
The valve assemblies are held in their seats by valve cages. The cages have 'O' rings
recessed into their upper circumference to prevent leakage of air. The first and second
valve covers have an additional 'O' ring seal between them and their cages. The valve
covers are the 'raised face' type.
To unload a working compressor, the suction valves are rendered inoperative by the valve
plates being pressed off their seats. This is accomplished by plate depressors (unloaders)
being operated by load control actuators.
A plate depressor is basically an inverted cup-shaped body with fingers protruding from its
rim, assembled with a spring-loaded central guide surmounted by a cylindrical cap. The
fingers operate through slots in the suction valve seat directly onto the valve plate.
Issue 1
01/2015
Page 19
V290M-WN
Compressor
In action the plate is depressed, against its spring, by the pneumatically operated
actuator. Compressed air fed to the load control actuator, by the load control solenoid
valve, acts on a multi-layer diaphragm, which is sandwiched between the two halves of
the actuator body. The diaphragm is in contact with the head of the spring loaded plunger
immediately under the disk. The plunger, guided in the lower half of the actuator body, has
its stem end in contact with the cap of the plate depressors. When the control air is
exhausted by the solenoid valve, springs return the plunger away from the valve plate.
g)
h)
i)
Issue 1
01/2015
Page 20
V290M-WN
Compressor
Issue 1
01/2015
Page 21
V290M-WN
Compressor
Safety Glasses.
Industrial Boots.
Safety Headwear
Commonplace Hazards
If a hazard is identified that is not identified within the Operating Authority 'Standing Safety
Instructions' a separate Risk Assessment must be made. Similarly If a hazard in the form
of a hazardous substance (Substance identified under COSHH regulations in the UK) is
identified, steps must be taken to assess the risk of injury to staff.
The compressor and its associated equipment are to be operated in accordance with
current statutory Health & Safety at Work policies. It is the responsibility of the operative to
familiarise him/herself with these policies. Any work practices that may pose a potential
health and safety hazard or any faulty/suspect equipment associated with the safe
operation and maintenance of the compressor must be brought to the attention of the
supervisor or supervising authority.
b)
Proper Use
The compressor is built to stringent manufacturing guidelines to guarantee safe operation.
However, using compressed air can be linked to dangerous occurrences if compressed air
is not properly handled. Proper use also includes the following:
Issue 1
01/2015
Follow the guideline laid down within this instruction manual, observing all pertinent
regulations and notes for the compressor.
Maintaining the equipment at the mandatory inspection and maintenance intervals.
Correct repair of the compressor equipment.
Operation of the compressor in accordance with the original design parameters.
Operation is carried out in accordance with the relevant environmental and operating
regulations.
Page 22
V290M-WN
Compressor
c)
Organisational Measures
It is the customers responsibility to ensure that the operating manual is adequately
supplemented with internal regulations regarding supervision and notification duties, work
organisation, and personnel qualification etc.
No modifications may be carried out on the compressor or its peripheral devices without
the written consent of Gardner Denver. Unauthorised Modification of the equipment will
invalidate the WARRANTY.
When renewing compressor components, use only original spare parts and accessories
supplied by Gardner Denver.
d)
Issue 1
01/2015
Page 23
V290M-WN
Compressor
Operating Records - It is IMPORTANT that a regular log sheet be kept for the
compressor recording operating pressures, temperatures and oil pressure (a copy of a
Log Sheet is provided within the Appendices located at the end of this manual). Variances
from normal running performance should be brought to the immediate attention of the
Supervisor responsible for consideration and action.
Lifting Equipment - Before using any lifting equipment, it is IMPORTANT that the crane,
gantry, hoist or chain block and any slings employed must be certified capable of lifting
the weight of the compressor (or motor/compressor assembly). Any such lifting equipment
MUST have a current CITB Test Certificate (or an equivalent certificate applicable to the
country of installation).
e)
f)
Maintenance
In addition to the General Safety Precautions, the following safety precautions MUST be
observed when maintaining your machine.
Issue 1
01/2015
Before commencing any maintenance work on the compressor or its driving unit or
any ancillary, the driving unit must be rendered incapable of being started whilst
maintenance and adjustment work is in progress. In the case of an electric motor for
example, the machine must be isolated from the main electricity supply, the isolator
locked off and/or the fuses withdrawn. This is particularly important with auto
start/stop machines where the machine could be started automatically.
ii
iii
Isolate the compressor from the discharge main and the instrument air. Where a
compressor is isolated from the delivery of other machines by a non-return valve,
the non-return valve must not be used as the only source of isolation. The
compressor must also be positively isolated from the delivery by closure of an
isolating valve.
iv
Isolate the compressor from the cooling water supply and drain all relevant water
containing compartments.
vi
If the compressor motion work or rotational parts are to be worked on then piston
rod clamps MUST be fitted to prevent accidental movement. Also chocking the
crankshaft should be considered where necessary.
vii
ALL lifting equipment MUST be correctly rated for the loads being applied and
MUST be certified as being in good working condition. Always ensure that when
lifting equipment is used, only specified lifting or slinging points are used.
viii.
ix.
Bolts and nuts must not be under or over tightened. Refer to the appropriate torque
values given in Table 1-6.
Page 24
V290M-WN
Compressor
Issue 1
01/2015
x.
Ensure that ALL tools and spare parts are accounted for after reassembly, since
any items left on or within the compressor may cause serious damage upon
restarting.
xi.
DO NOT place the electrical isolating switch to the 'ON' position until all work has
been completed by all personnel working on the equipment. The site supervisor
must inspect and approve the work carried out before re-connecting the equipment
to the electrical supply.
xiii.
Before starting the compressor, bar over the machine by hand where possible to
ensure free rotation and that no metallic 'knocking' noise is evident. If any solid
resistance to rotation is found, investigate the cause.
Page 25
V290M-WN
Compressor
INTENTIONALLY BLANK
Issue 1
01/2015
Page 26
V290M-WN
Compressor
Issue 1
01/2015
Page 27
V290M-WN
Compressor
Location
The compressor should be located in a clean, well-lit, well-ventilated area with ample
space all around it to facilitate inspection and maintenance. Sufficient room must be
allowed for the removal of pistons and cylinders, crankshaft and motor, and as the
compressor and many of its components are heavy, there must be headroom sufficient to
permit the operation of a crane or hoist, which must be certified capable of lifting safely
the weight.
Statutory regulations and local by-laws governing the operation of heavy machinery must
be complied with, this may have some influence on the choice of location.
b)
Ventilation
Approximately 10% of the energy consumed by a compressor is lost as heat. This is the
heat generated by the motor, the mechanical losses of the compressor and straightforward heat radiation from the air manifolds.
For example, a 365kW water-cooled compressor would require some 486 m3/min of
ambient air circulation to limit the compressor room temperature rise to 6C. Natural
convection is normally adequate with the outlet vents at a high level to prevent the
temperature building down from the roof.
c)
Issue 1
01/2015
Foundations
For vibration isolator mounted compressors, all that is required is a floor of sufficient
strength to carry the weight of the compressor, motor and ancillaries. For solidly mounted
compressors the foundation dimensions must be determined for each installation,
consideration being given to the nature of the subsoil and local surroundings.
Page 28
V290M-WN
Compressor
WARNING!
THE FLOOR MUST BE LEVEL AND FLAT.
Foundation depth must be such that the subsoil reached is, in the opinion of an expert,
capable of taking the load of the working compressor and preventing the transmission of
vibration. Unless the foundation rests on bed-rock or hard-pan, a sub-footing should be
made of such a size and design as to provide a solid bottom. In extreme cases of poor
subsoil, piling may be required, and in such circumstances a competent foundation
engineer should be consulted.
If the compressor is to be mounted on a metal floor, it can be either bolted direct to the
floor, or beam or skid mounted. The beams or skids may be bolted or welded to the floor,
with due consideration being given to structural vibrations and floor strength.
A foundation plan (for good subsoil conditions) is furnished in advance of the shipment of
the compressor, and the foundation used must not be less than given in the plan.
When installing a solidly mounted compressor, it must be ensured that the crankcase feet
are ALL flat down and fully supported BEFORE tightening the "Holding Down" fasteners.
A detailed foundation drawing is available (on request) from Gardner Denver
d)
Pipework Installation
These paragraphs give recommendations with regard to delivery pipework and will help
the plant engineer plan the best possible installation.
Pipes must not be fixed inflexibly such that heavy thrust can act back onto the compressor
otherwise serious damage could result, examine carefully the anchoring point locations
and pipework support arrangements.
WARNING!
ALL INLET AND OUTLET CONNECTIONS TO COMPRESSORS
MOUNTED ON VIBRATION ISOLATORS MUST USE SUITABLE
FLEXIBLE PIPES. ALL FLEXIBLE PIPES MUST BE INSTALLED IN
ACCORDANCE WITH THE MANUFACTURER'S INSTRUCTIONS
1 - Inlet System
An efficient air intake filtration system is essential to ensure that debris is removed from
the air flow to the compressor thereby prolonging the life of the machine.
Standard Gardner Denver practice is to fit a machine mounted, combined filter/silencer,
however, in hot or dirty locations, or in the presence of difficult combinations (e.g. fumes,
alumina or cement dust), filtration may be improved by mounted the intake remotely and
ducting the air to the compressor. Special filter/silencer arrangements are available for
this type of installation.
Only dry type filters must be used with oil-free compressors.
Noise regulations should be taken into account when deciding silencer requirements and
locations.
2 - Delivery System
Issue 1
01/2015
Page 29
V290M-WN
Compressor
The flexible delivery pipe connects the aftercooler to the receiver (where fitted). It must be
of the correct specification for the pressure and temperature and nature of the medium
being compressed, and not smaller than the size specified below.
The pipe must be well supported to avoid strain on the compressor cylinders, and it's
configuration be such that any expansion effect, due to the air/gas temperature rise for
whatever reason, can adequately be dissipated within the natural elasticity of the pipework
leading from the compressor and cannot act back on the cylinder.
At the junction with the receiver, or pipe main, a shut-off valve should be fitted to isolate
the compressor as required. On automatic and multi-machine installations, non-return
valves should also be fitted to isolate standby units from system pressure.
A safety valve must be fitted, close to the compressor, in the delivery pipe. The valve must
be fitted before any shut-off valve, non-return valve or aftercooler to prevent damage in
the event of the compressor being run with the shut-off valve closed. The valve should be
a springloaded type and of sufficient size to pass safely the maximum compressor output.
A small blow-down valve should be fitted between the compressor and shut-off valve to
relieve residual pressure when required for maintenance purposes.
3 - Air Receiver
An air receiver of suficient capacity is required for use with this equipment. The receiver
should have a capacity equal to a one minute supply of compressed air (neglecting
temperature rise).
The air receivers should, ideally, be located in the coldest place possible, to ensure that
as much condensate as possible is precipitated from the air in the receiver. This means
that the receiver must be drained frequently, either by fitting an adequate drain or an
automatic drain trap.
To facilitate servicing of the drain trap whilst the receiver is in commission, a by-pass
should also be incorporated.
4 - Distribution Piping (air systems)
Water collectors of an automatic discharge type should be fitted at suitable points in the
pipe system. They should be fitted with three-way cocks (either in connection with the
traps or separately) so that pipes may be blown through to disperse condensation.
Delivery pipework must be arranged to prevent condensation running back from the
aftercooler or receiver into the compressor cylinders.
The pipe system for air distribution should be carefully considered if optimum results are
to be obtained. Moisture-laden air can cause rusting in low-lying parts of the pipe system
so, ideally, all distribution pipework should be internally galvanized and angled slightly
towards the drain points.
An effective way of eliminating possible water damage is to install a refrigerative air dryer
or, for dryer air, an adsorption dryer.
5 - Load Control Piping
Connect (with similar size piping) the load control system on the compressor to the control
air take-off points on the compressor panel, the connections on the compressor will
indicate the size.
Issue 1
01/2015
Page 30
V290M-WN
Compressor
Connect (with similar size piping) the compressor panel control air inlet point to the
compressed air/instrument air main - any isolating valve fitted here must be of the
lockable open type.
6 - Drain Valves & Drain Valve Piping
It is important that the drain pipes from the water separator drain traps are run individually
to open ends (e.g., over OPEN containers). They must NOT be piped together as there
would then be a risk of "blow-back" along adjacent pipes in the event of a trap
malfunctioning.
Drain valves are fitted to the separators of each compression stage. These valves exhaust
the collected moisture at high pressure and must be piped away to a safe area using solid
pipework.
MOST IMPORTANT - if the exhausts of any vent valves are piped away, it is essential
that these have direct outlets to atmosphere, they must NOT be connected into any other
pipe. It is also recommended that a silencer is fitted to the exhaust in order to reduce
noise levels.
e)
Cooling Water
An adequate source of clean, cool water for the compressor cylinders, intercoolers and
aftercooler should be provided.
Cooling water must be as free as possible from scale forming salts, with (if the water is not
clean) an efficient filter(s) placed in the intake pipeline. A Duplex type arrangement is
recommended as this will allow one filter to be cleaned whilst the other is in service.
The temperature of the cooling water supply to the compressor (NOT aftercooler) should
not be less than the ambient temperature. The methods of achieving this depend on the
cooling system employed:
The temperature of the cooling water supply should be in the range 20C to 35C
In situations where the ambient temperature is in excess of 35C., advice should be
sought from Gardner Denver.
The pressure in the cooling water pipeline at the compressor must be sufficient to promote
the flow required by the size and duty of the machine. This should take into consideration
all the friction losses in the overall pipework and valves and across the heat exchanger
units (as may be installed) as well as across the compressor.
Except for compressors made to special customer requirements, water pressure in the
jackets must not exceed 7 Bar g. It is recommended that thermometer pockets are fitted to
the water inlet and outlet pipes to the compressor and, the aftercooler. Temperature
differentials between these points will give a good indication of sufficient water flow, 10 to
12C being usual.
CAUTION!
FAILURE OF WATER FLOW IS A CAUSE OF MAJOR DAMAGE
AND MUST BE AVOIDED. ENSURE THAT COOLING WATER PIPES
TO AND FROM THE COMPRESSOR ARE CONSTRUCTED TO
AVOID THE FORMATION OF AIR LOCK
Issue 1
01/2015
Page 31
V290M-WN
Compressor
For compressors operating in cold environments, drain points are present on the cylinders
to empty the water jackets of the machine (when out of service) to prevent damage in the
case of frost. Open air vent cocks at the tops of the cylinders at the time of water
drainage. Certain water pipe connections should afterwards be disconnected to
completely drain the system.
CAUTION!
EXPOSURE TO FROST CONDITIONS WILL DAMAGE YOUR
MACHINE UNLESS THE PROPER FROST PRECAUTIONS ARE
TAKEN. IF ADVICE IS REQUIRED, PLEASE CONTACT GARDNER
DENVER.
f)
Electric Cabling
The electric cabling to the motor must be run such that small amounts of movement at the
motor terminals can be safely absorbed within inherent flexibility of the type of cabling
used.
Check that the motor nameplate details agree with those of the electricity supply on which
the motor is to be used.
Connect motor in accordance with the instruction supplied. Use cables of adequate size to
carry the full load current and also large enough to carry the starting current without
excessive voltage drop.
Ensure that the motor frame is properly earthed.
Electrical Suppy
Voltage - Steady state voltage with 90% to 110% of nominal value. Frequency Variations should be no lower than 99% or higher than 101% of the nominal frequency for
continual operation. Exceptionally limits can be extended to 98% to 102% for short
periods.
g)
Harmonics - Harmonic distortion not to exceed 10% of the total r.m.s. voltage between
live conductors for the sum of the second through to the fifth harmonic. An additional 2%
of the harmonic is permissible.
Voltage imbalance - Neither the voltage of the negative sequence component nor the
voltage of the zero sequence component shall exceed 2% of the positive sequence
component.
Voltage interruption - Supply interrupted or at zero voltage for not more than 3 s at any
random time in the supply cycle. There shall be more than 1 s between successive
interruptions.
Voltage dips - Voltage dips shall not exceed 20% of the peak voltage of the supply for
more than one cycle. There shall be more than 1 s between successive dips.
h)
Motor Starters
1 - Motor Protection Equipment
The following has been prepared to describe the minimum protection requirements for
motors used on the compressor.
Protection of the motor should consist of as a minimum the following :
Issue 1
01/2015
V290M-WN
Compressor
Phase imbalance
Phase failure
Gardner Denver reccomend the Group Schnieder (Telemecanique) thermal overload
motor protection relay. This provides the above levels of protection.
2 - Basic Starter Equipment Requirements
Equipment supplied within a starter control panel should as a minimum consist of the
following :
Mains Isolator
Star Delta Starter complete with thermal overload motor protection relay (above)
Motor short circuit protection (either fuses or mccb) should be provided by the
customer, unless otherwise specified.
3 - General
All equipment shall be selected for use on AC 3 phase circuits up to 600 Volts.
Control circuits may generally be either 110 Volts AC or 24 Volts DC. Check that
solenoids and other equipment fitted on the compressor are designed to operate at the
supplied control voltage.
All motor starting equipment should be rated for AC3 motor starting duties and be
selected in accordance with the motor rating information provided. All equipment should
conform to the latest ISO standards.
All thermal overload motor protection relays must be set at the phase current. (rated
current of the motor divided by 1.732).
i)
Drive Motor
The motor used to drive the compressor must comply with the following specification :
1 - Application
Motors should be designed, manufactured and tested in accordance with the following
standards:-BS
EN 60034 - Rotating electrical machines
BS 4999 - General requirements for rotating electrical machines
BS EN 50347 - General purpose three phase induction motors
The design of the motor should take into account the irregular turning effort required for
this application. The motor design should also take into account the rotor inertia needed to
meet the requirements of this type of load. The motor should be capable of continuous
operation (S1 duty) and be able to be started with electronic "soft start" equipment or a
start/delta starter.
Issue 1
01/2015
Page 33
V290M-WN
Compressor
The motor may be subjected to a maximum of three (3) starts in a one (1) hour period.
The compressor can be loaded and unloaded several times a minute via a two (2) or three
(3) step control.
2 - Rating
The motor shall be rated as follows:Power rating and speed as shown in Technical Data, Chapter 1
Drip protected (IP21S) to IEC 60034-6, suitable for 40C ambient, a maximum altitude of
1000 metres above sea level and limited to class F temperature rise. Maximum voltage
variation permissible shall be within 90% and 110% of nominal value. Whilst the motor will
be rated for operation at supply voltage, its insulation standard should be for 1000 volts
which includes consideration in respect of the winding inter-turn insulation. The dielectric
strength of the insulation should be rated for a voltage waveform with a rise time of not
less than 3 kV/ sec.
Direction of rotation - Motor to drive the compressor clockwise looking from the motor end.
Insulation class F.
Stability
Due consideration must be given to maintaining the compressor's stability during all lifting
procedures. The compressor is only in a stable condition when standing on a suitable,
level floor surface with all four crankcase feet firmly down. It MUST be noted that the
Centre of Gravity (C of G) for each machine will change depending on whether the
compressor is 'bareshaft' or fitted with a 'drive unit'.
WARNING!
THE CRANE, GANTRY, HOIST OR CHAIN BLOCK OR ANY SLINGS
EMPLOYED MUST BE CERTIFIED CAPABLE OF LIFTING THE
WEIGHT OF THE COMPRESSOR (OR MOTOR/ COMPRESSOR
ASSEMBLY).
Issue 1
01/2015
Page 34
V290M-WN
Compressor
Slinging Instructions
On all compressors two cradle slings are positioned, one under each of the two outer
cylinder crankcase flanges. A third sling is used to balance the compressor.
1
In the case of a compressor fitted with a flange mounted motor, a cradle sling is
passed under the motor, taking care to keep it clear of the fan housing.
If the compressor is fitted with a flywheel, a balancing sling is passed around the
shaft.
WARNING!
UNDER NO CIRCUMSTANCES USE THE MOTOR LIFTING HOLE
FOR BALANCING THE WEIGHT (THIS LIFTING POINT IS FOR THE
MOTOR ONLY WHEN DETACHED OR DETACHING FROM THE
COMPRESSOR).
Care MUST be taken to ensure that no small bore pipes or other components are trapped
by slings.
c)
Lifting Instructions
Because the type of lifting equipment for each installation will be different the following
instructions have been written with the intent of being a general guide rather than specific
instructions.
Issue 1
01/2015
Page 35
V290M-WN
Compressor
1
d)
Check whether the lift will be a straight lift, or will an angle rig be needed.
These factors will affect the lifting capacity required.
The slings must be free of kinks, knots, broken strands or loose connections
etc, and meet the regulation requirements.
Check the clearance available to make sure the lift can be carried out safely.
To prevent damage to the machine's finish or the edges of the machine from
cutting into the slings, use proper blocking and padding.
When involved in the lifting of heavy loads, we suggest you protect yourself by
wearing approved protective gear such as: safety helmets, steel toe cap safety
shoes, gloves, eye protection, etc.
Refer to the machine installation drawings and note the location of the machine
support points. Review all machine installation requirements carefully before
positioning the machine.
Unpacking
No special unpacking instructions can be given here as the compressors may be
transported fully boxed, crated, or on open bases, depending on destination and mode of
transportation. Boxed compressors have directions for lifting and opening on or with the
boxes. Some of the cylinder valves will have been replaced with silica-gel bags. The
displaced valves and the accessories are packed in a separate container, which should be
located and safeguarded until after the installation of the compressor.
Safety Precautions
The following additional safety precautions should be observed before installing the
compressor onto its foundation.
Personnel must be a safe distance from the compressor during positioning, guide ropes
may be used to assist, but not 'hands-on'. The compressor must be lowered slowly, in
small stages with no sudden jerks whilst observing for any indications of potential
problems. Once in position the compressor must be properly secured with suitable
foundation bolts or antivibration mounts (AVM's).
If the floor is to be drilled for foundation bolts, the compressor must be moved away whilst
work proceeds.
Each time the compressor is moved check for stability and correct sling placement.
DO NOT apply load tension to the slings if the compressor is held to the floor.
Issue 1
01/2015
Page 36
V290M-WN
Compressor
b)
Move the compressor into position and mark on the floor the position of the holding
down bolt holes in the anti-vibration mounting plate.
Remove the compressor and attached mounts and drill the floor for appropriate
size holes for the Rawl-bolt shells.
Insert shells, reposition compressor and bolt onto floor by means of the mounting
holding down bolts.
OR:
The anti-vibration mountings may be held down by bolts or anchors of a similar
diameter to the holes in the mounting plate. Use of these will eliminate the need to
move the compressor to drill the floor holes. The appropriate instructions supplied
with the bolts should be followed precisely.
c)
Finally, check the bolts holding the compressor onto the anti-vibration mountings
and use these bolts to finish levelling the compressor (See Levelling and
Alignment).
Issue 1
01/2015
Adjust the pressure within the pneumatic AVM's around the machine until the
desired level is achieved. Do not inflate AVM's unless the static weight of the
compressor is placed on them.
Ensure that the final levelled height of each mount is within the makers limits and
that each mount is levelled until it carries its correct proportion of the overall
machine weight.
If any mount is compressed solid, levelling must be carried out on the free mounts
to redistribute the load.
Using a spirit level on any horizontal surface, check that the compressor is level in
both planes (i.e. parallel to and at right angles to the crankshaft).
Page 37
V290M-WN
Compressor
b)
Issue 1
01/2015
Remove the 'mouldable' wrapping from around the piston rods and clean the rod
surfaces.
Remove control piping from cylinder valve covers marked with adhesive labels and
remove the covers.
Extract the silica gel bags from the valve chambers; ensuring that where more than
one bag is present, ALL bags are removed.
Using a plastic or soft metal scraper, remove rust resistant paint from the seating
in the valve chambers.
Fit components in their correct order, ensuring that suction and delivery valves are
fitted in the correct valve chambers. Where plate lifters are fitted to suction valves,
care must be taken to ensure correct assembly.
Tighten the valve covers and refit the control air pipes
Remove and store the adhesive labels and warning plates with the silica gel bags.
Check that all gauges and small-bore pipework are undamaged, and are properly
connected.
10
Ensure that all external nuts and bolts on the compressor and its ancillary
equipment are tight, including all holding down bolts and bolts of all pipework
flanges and supports.
11
Remove the crankcase access covers (and wooden blocks where fitted), and
crosshead access aperture covers, and check to ensure that the interior of the
crankcase is clean and free of foreign matter.
12
13
Fill the oil sump (in the bottom of the crankcase) with the recommended grade of
lubricant to level indicated by the window nut on the front of the crankcase. Initially
fill to near the top of the window, the level will fall towards the bottom of the
window when the compressor is started, rising to about half-way when the oil has
reached its sustained running temperature.
Page 38
V290M-WN
Compressor
c)
14
Wearing suitable (oil resistant) protective gloves, liberally coat clean oil onto all the
main guide slides - turning the crank to different positions to achieve full face
coverage (keep hands out of the crankcase when the shaft is being turned).
15
As the compressor may have been in transit/storage for some time, prime the
suction side of the lubricating oil pump by disconnecting the suction pipe top fitting.
Then using the recommended grade of lubricant pump oil 'in' to 'wet' the gears and
fill partially the suction side of the pump body. This promotes a quick pick up of oil
pressure on start up of the compressor.
16
17
Ensure that the compressor pressure instrument isolating cocks are open.
18
Ensure that the pipes of the rubber filling plugs are removed to vent the gauge
cases and allow correct gauge indication.
19
Ensure that the pressure signal pipelines of the load control system are open (i.e.,
make certain that any isolating valves are fixed open).
20
Fill slowly and carefully (to avoid trapping air) in the cooling water spaces of the
compressor - do not rush this operation. Open the air vent cocks, at the tops of the
cylinder covers to rid the system of trapped air. The operation is carried out in
association with any other water-cooled ancillary items in the overall cooling water
system of the installation.
Issue 1
01/2015
Page 39
V290M-WN
Compressor
d)
Trial Run
When commissioning, the trial run must include certain vital checks, and these should be
carried out as follows:
Issue 1
01/2015
Ensure that the factory delivery mains and air using equipment are safe to
pressurise - and all delivery isolating valves in the system are open.
Ensure that the load control sensing pipework is open to the compressed air main.
Ensure that the isolating cocks of all pressure gauges are open.
Ensure that the by-pass valves situated at the drain traps are closed.
Start compressor in the unloaded condition and allow to run up to full speed,
observe oil pressure is quickly established (this will be high with a cold machine)
and observe compressor running generally.
Page 40
V290M-WN
Compressor
6
After a 3 minute run, stop and electrically isolate the compressor. Remove the
crankcase main doors and check the temperatures of the motion work bearings
and guides. This should be done using a thermometer fitted with a suitable surface
probe.
WARNING!
TAKE CARE DURING EXAMINATION, AS SOME OF THE
PARTS WILL HAVE BECOME HEATED.
All should be cool except the bottom end bearings, which can be a little warmer
than other bearings - also one side (the 'working face' side) of main guides may be
slightly warmer than the opposite side.
Run the compressor for a further 10 minutes and repeat checks as in step 6.
When satisfied that all is in order, restart the compressor. When the compressor
has settled on speed place the load control to the load condition whereupon the
compressor will commence compressing.
10
The load control must be set for no higher pressure than that for which the compressor is
supplied. (See Section 1.1.1 Technical Data).
During the first commissioning run on load, make careful observation of the general
operation of the compressor.
Observe the compressor gauges, until the desired unloading set-point (as set on the load
control pressure switches) is reached, at this point the compressor will unload
automatically as described in Load Control System.
Check that the loading/unloading sequence is in accordance with requirements - adjust
the control as necessary.
b)
Issue 1
01/2015
Completion of Commissioning
1
Run the compressor until it attains operational temperature and check that the oil
pressure settles at a satisfactory level, approx. 3.5 Bar or above; this will depend
upon ambient temperature, oil viscosity at running temperature, and on-load/offload running pattern.
After a settled period of running (approx. 24 hours) check the tightness of all
external bolts and nuts - particularly cylinder and valve cover fasteners, also
compressor and compressor driver fixings.
During this run adjust the cooling water flow control valve to achieve the required
temperature rise. When on sustained full load, the optimum temperature rise is
about 10 to 12 C.
Page 41
V290M-WN
Compressor
INTENTIONALLY BLANK
Issue 1
01/2015
Page 42
V290M-WN
Compressor
Issue 1
01/2015
Page 43
V290M-WN
Compressor
These instructions are designed to providing experienced operatives, who are fully conversant with
compressor operating techniques, with operational information for the Gardner Denver range of
compressors.
NOTE: THE FOLLOWING OPERATING INFORMATION ASSUMES THAT THE
COMPRESSOR IS FITTED WITH A STANDARD GARDNER DENVER
CONTROL SYSTEM. HOWEVER, IF THE CONTROL EQUIPMENT IS OF
DIFFERENT MANUFACTURE, THE COMPRESSOR MUST BE OPERATED IN
ACCORDANCE WITH THE SUPPLEMENTARY OPERATING INFORMATION
SUPPLIED WITH THE CONTROL SYSTEM.
The compressor is designed and built for continuous running and will provide long term reliable
operation if regular periodic checks and servicing are carried out in accordance with the
information provided within Chapter 5 of this Instruction Manual.
CAUTION!
PROLONGED UNLOADED RUNNING OF THE MACHINE SHOULD BE
AVOIDED NOT ONLY BECAUSE OF POWER WASTAGE, BUT
UNNECESSARY COMPONENT WEAR CAN RESULT.
It is the customer's responsibility to:
1
Maintain the inlet filter system and air blast cooler in a clean condition as dictated by site
conditions.
Ensure that the specified, clean lubricant is added to ensure the correct crankcase oil
level is maintained
Starter System
Where the starter system has been supplied by Gardner Denver details are provided in
the supplementary material at the rear of this manual. Where the control system is
provided by others, details will be supplied by the manufacturer.
b)
Issue 1
01/2015
Page 44
V290M-WN
Compressor
4.4 Running
a)
Issue 1
01/2015
Running Checks
1
Allow the compressor to run up to full speed and then close the small drain cocks.
2
Check the oil pressure. This will fall initially as the oil temperature rises, but should
steady at between 3.0 to 4.0 BarG even in a hot environment.
3
Check the cooling water is flowing at the visible outlet or flow indicator. On multicompressor installations balance the flows in the parallel systems of the
compressors (including intercooler) to give equal water temperature rise across
both - ideally 11C.
4
Check all automatic drain traps for unusual discharge.
5
Check all temperatures and pressures periodically.
6
Check for undue noise, vibration or heat. If present, report immediately.
Page 45
V290M-WN
Compressor
b)
7
It is good practice to carry out these checks regularly and log the results.
Automatic Operation
Before Automatic Operation is selected, the compressor must be prepared for starting as
described in (Before Operating the Machine (Pre-Start Checks).
For details of operation, refer to the control panel manufacturers literature.
c)
Faults/Hazards
Should a fault develop, this will be detected by the appropriate sensing switch
Normal Stopping
Refer to the control panel manufacturers literature for details of the stopping procedure.
b)
Emergency Stopping
Pressing the 'EMERGENCY STOP' mushroom button stops the machine instantly in
whatever mode of operation it is operating
CAUTION!
THIS IS NOT RECOMMENDED FOR ROUTINE STOPPING AND
SHOULD ONLY BE USED IN THE CASE OF AN EMERGENCY
WHERE NORMAL STOPPING IS NOT POSSIBLE.
Issue 1
01/2015
Fault Finding
Page 46
V290M-WN
Compressor
Minor variations in pressure and temperature readings may occur, due to possible small
changes in the suction or delivery conditions. These factors should be considered when
checking and assessing instrument readings.
Table 4-1: Fault Finding
Possible Cause
Remedial Action
1.
2.
1.
2.
3.
1.
2.
3.
1.
1.
2.
3.
4.
1.
2.
1.
2.
1.
1.
1.
2.
3.
4.
Fault
Low first stage delivery pressure
(normal or low first stage air
delivery temperature).
High
first
stage
delivery
pressure (normal or high first
stage temperature). delivery
relief
Issue 1
01/2015
Page 47
depressor
V290M-WN
Compressor
Table 4-1: Fault Finding
Fault
Low
third
pressure.
stage
delivery
Possible Cause
Remedial Action
1.
2.
3.
High third
temperature.
stage
delivery
1.
2.
3.
4.
depressor
Issue 1
01/2015
1.
Open valve.
2.
3.
Remove restriction.
4.
5.
Seized closed, or partially closed nonreturn valve in delivery main (if fitted).
6.
1.
2.
1.
2.
3.
4.
5.
6.
Replace element.
1.
2.
3.
4.
5.
Page 48
Repair valve.
Repair or fit new valve.
V290M-WN
Compressor
Table 4-1: Fault Finding
Fault
Possible Cause
Remedial Action
6.
1.
2.
3.
4.
5.
6.
1.
2.
3.
1.
Issue 1
01/2015
Page 49
V290M-WN
Compressor
INTENTIONALLY BLANK
Issue 1
01/2015
Page 50
V290M-WN
Compressor
Issue 1
01/2015
Page 51
V290M-WN
Compressor
Maintenance Schedule
The following schedule, lists recommended maintenance tasks which are designed to
both prevent unplanned machine breakdowns and to help the maintenance teams to plan
maintenance activities. Where a maintenance activity requires greater explanation than
that given in the schedule a reference to the relevant associated maintenance instruction
is given.
All materials used for scheduled maintenance and repair MUST COMPLY with Gardner
Denver standards and the standards laid down by associated equipment manufacturers.
Only approved spares may be used.
When a system component associated with a mechanical or electrical device is changed
or renewed, the system must undergo a functional test before the equipment is returned to
service.
Gardner Denver are not responsible for premature failures of parts which are caused by
neglect, inappropriate servicing, use of none Gardner Denver parts, or any other similar
conditions over which we have no control.
Issue 1
01/2015
Page 52
V290M-WN
Compressor
b)
Supplementary Information
Any aspect of the Shift inspection requiring further attention MUST be reported for action as
required.
c)
Monthly Inspection
Supplementary Information
Any aspect of the Monthly inspection requiring further attention MUST be reported for action as
required.
Issue 1
01/2015
Page 53
V290M-WN
Compressor
d)
Six Monthly Service
The compressor is required to be shutdown for two days to perform this service schedule
Tasks
Supplementary Information
Check
valve
unloaders,
actuators
&
interconnecting small bore pipework for defects.
CRANKCASE INSPECTION
Examine crossheads and main guide slipper
paths, condition and clearances.
Rectify as required.
Any aspect of the Six Monthly service requiring further attention MUST be reported for action as required. On
completion of the service, re-commission the compressor and recording all operating pressures and
temperatures. Ensure that the working area is left in a clean and tidy condition.
Issue 1
01/2015
Page 54
V290M-WN
Compressor
e)
Annual Service - (or as stipulated by local regulations)
The compressor is required to be shutdown for five days to perform this service schedule. All Six
Monthly tasks are to be undertaken as part of this schedule.
Tasks
Supplementary Information
Report condition.
Any aspect of the Annual service requiring further attention MUST be reported for action as required. On
completion of the service close compressor using new gaskets and 'O' rings. Recommission the compressor
and recording all operating pressures and temperatures. Ensure that the working area is left in a clean and
tidy condition.
Crankcase Oil
Issue 1
01/2015
Supplementary Information
Page 55
V290M-WN
Compressor
Issue 1
01/2015
Page 56
V290M-WN
Compressor
List of Consumables
Crankcase Oil (see page 5-6 for reccommended oils)
A/R
A/R
WARNING!
TO AVOID SCALDING FROM HOT OIL, ALLOW THE COMPRESSOR TO COOL
BEFORE BEGINNING WORK.
2
3
Remove the crankcase doors, taking care not to damage the oil seals.
Wipe any excess oil off the doors using an industrial cleaning fluid and a lint free cloth. Place
the door in a clean location to avoid oil contamination when refitting.
Empty the oil sump using suitable pumping equipment and clean out the crankcase sump
(use lint-free cloths, to avoid fouling of the oil strainer).
Once all oil has been removed from the sump, remove the oil strainer. Use a thin spanner,
on the strainer body hexagon to unscrew the strainer whilst holding the external hexagon
fitting to prevent turning. This fitting is not screwed into the crankcase - it passes through a
clear hole. Re-fit the oil strainer, make sure that all sealing washers are fitted in the correct
locations.
4
5
Issue 1
01/2015
Page 57
V290M-WN
Compressor
Check that all tools and cleaning cloths have been removed from the crankcase sump.
Refill the crankcase sump with the required quantity of clean, new oil.
Refit the crankcase doors after checking, and if necessary replacing, the door seals.
Test run the compressor and check for oil leaks around the strainer seal and crankcase
doors. If all is satisfactory, return the machine to service.
Illustration 5-2 : Lubrication System
Oil Suction
Hose
Oil Filter
Cooling Water
Outlet
Issue 1
01/2015
Oil Cooler
Page 58
Cooling Water
Inlet
V290M-WN
Compressor
1 set
List of Consumables
Industrial cleaning fluid (White Spirit) & lint free cloth
1.
A/R
Before starting this operation, carry out the following safety steps :
a)
b)
c)
Carefully open the vent valves on the third stage cylinder to check de-pressurising has
been completed successfully.
d)
Ensure that the compressor is isolated from the delivery system and that the
compressor is positively isolated from the delivery non-return valve.
e)
f)
Post signs instructing personnel that the machine MUST NOT be used.
2.
Remove the distance piece access covers from the line of motion works NOT being worked
on. Wipe any excess oil off the covers using an industrial cleaning fluid and a lint free cloth.
Place the cover in a clean location to avoid oil contamination.
3.
Mark the position of the oil shedder on the piston rod and remove shedder.
4.
Loosely assemble the piston rod clamps onto the piston rod.
5.
Manually 'bar-over' the compressor to the desired position and hold steady.
6.
Whilst one person holds the crankshaft bar in position, the other must tighten the one piston
rod clamp firmly against the packing gland box and the other firmly against the scraper gland
box.
7.
Only when both clamps are tight in place can the crankshaft bar be carefully released and
safe work or inspection take place.
WARNING!
WHEN MAINTENANCE WORK HAS BEEN COMPLETED THE PISTON ROD CLAMP
MUST BE REMOVED.
8.
When returning the compressor to service, check that all above steps have been reversed,
all clamps and fittings have been removed and that the compressor is safe to run.
Issue 1
01/2015
Page 59
V290M-WN
Compressor
1 set
A/R
List of Consumables
Industrial cleaning fluid (White Spirit) & lint free cloth
a)
A/R
Before starting this operation, carry out the following safety steps :
a)
b)
c)
Carefully open the vent valves on the third stage cylinder to check depressurising has been completed successfully.
d)
Ensure that the compressor is isolated from the delivery system and that the
compressor is positively isolated from the delivery non-return valve.
e)
f)
Post signs instructing personnel that the machine MUST NOT be used.
Isolate and drain the cooling water from the compressor cylinders.
Remove cooling water pipes from the top cover and fit blanking plugs to prevent dirt
ingress.
Disconnect and remove all unloader pipes from the top cover unloaders.
Loosen and remove the top cover securing nuts from the cylinder fixing studs. (sixteen
normal plus six dome nuts with washers)
Remove four of the valve cage nuts and attach suitable eye nuts. The lifting eye
locations should be arranged so that when the cylinder head is lifted, with slings, from
these points, the natural hanging angle will be 45 Deg.
Attach a suitable sling to the eye-bolts, and using lifting equipment, take up the slack in
the sling.
Slowly lift and guide the top cover from the cylinder studs. Adjust the position of the
slings so that the head cover will not swing when lifted clear of the cylinder studs.
Lower the top cover onto a suitable, clean work-surface taking care not to damage the
machined face.
10
Clean the top cover using an industrial cleaning fluid and a lint free cloth.
11
Ensure that the piston and cylinder is clean and dry. Ensure that all liquid and loose
material is removed from the top of the cylinder and piston.
Issue 1
01/2015
Page 60
V290M-WN
Compressor
b)
c)
1.
Ensure that the cylinder top cover and cylinder top mating faces are clean.
2.
Check the condition of the cylinder top cover gasket. Renew if necessary.
3.
Ensure that all old gasket material is removed from the top cover and cylinder mating
faces. Fit a new gasket over the cylinder studs and onto the cylinder mating face.
4.
Attach a suitable sling to the eye-nuts fitted for cylinder head removal (See section a.
above), and using suitable overhead lifting equipment, raise and position the top cover
over the cylinder.
5.
Slowly lower and guide the top cover onto the cylinder, ensuring the correct positioning
of the cooling water and gas pockets.
6.
When in position, remove the sling and lightly secure the top cover to the cylinder with
the fixing nuts.
7.
Tighten the cylinder cover nuts (six centre nuts first), tighten the nuts down evenly and
progressively. Centre nuts are dome type and must have a copper washer fitted
underneath them. Nuts to be torque tightened to the appropriate torque figure.
8.
Remove the eye-bolts from the top cover and re-fit valve cage fasteners.
9.
10.
Secure the supply lines to the cylinder top cover with their fasteners.
11.
12.
Bleed off any trapped air in the cooling system using the plugs in the cylinder water
jacket.
13.
Test run the compressor and check for correct operation and freedom from leaks
around any of the disturbed components.
Before starting this operation, carry out the following safety steps :
a)
b)
c)
Carefully open the vent valves on the third stage cylinder to check depressurising has been completed successfully.
d)
Ensure that the compressor is isolated from the delivery system and that the
compressor is positively isolated from the delivery non-return valve.
e)
f)
Post signs instructing personnel that the machine MUST NOT be used.
2.
Isolate and drain the cooling water from the compressor cylinders.
3.
Remove cooling water pipes from the top cover/cylinder and fit blanking plugs to
prevent dirt ingress.
4.
Disconnect and remove all unloader pipes that connect to the top cover unloaders.
Issue 1
01/2015
Page 61
V290M-WN
Compressor
d)
5.
Remove cooling water pipes from the top cover and fit blanking plugs to prevent dirt
ingress.
6.
Check that there are no supply pipes or hoses fastened to the top cover.
7.
Disconnect and remove as necessary the 3rd stage delivery and suction pipes using
suitable lifting equipment.
8.
Loosen and remove the third stage top-cover fasteners (10 x M20 nuts).
9.
Pass a sling around the top cover inlet and delivery flanges and lift the top cover clear
of the 3rd stage cylinder and studs.
10.
Lower the 3rd stage top-cover onto a clean work surface taking care not to damage the
machined face.
11.
The third stage bearer and piston rings can now be accessed and removed.
To remove the third stage cylinder - Access the second stage piston
To gain access to the top of the second stage piston, carry out the operations described for
removing the third stage head then proceed as follows :
e)
Remove two of the uppermost studs from the 3rd stage cylinder and fit eye-bolts.
Loosen and remove the third stage cylinder fasteners (18 x M20 Nuts).
If possible remove the third stage bearer and piston rings at this point.
Carefully lift and guide the third stage cylinder clear of the studs and, if the third stage
rings could not be removed in the previous step, the third stage piston assembly.
With the third stage cylinder removed the third stage piston can be removed and
access gained to the top of the second stage piston and piston nut.
Fit lifting eyes in the locations shown in the photo above on the 3rd stage cylinder
block.
Ensure that all old gasket material has been removed from the cylinder/cylinder face.
Fit a new gasket in the correct location over the cylinder studs.
Lift the third stage cylinder in to position and carefully lower and guide the third stage
cylinder onto the studs and over the third stage piston base. Ensure that the third stage
piston base passes easily into the cylinder bore and is not damaged by jamming.
Ensure that the third stage cylinder is fully down on the second stage and loosely fit the
fasteners.
Remove the lifting eye-bolts and re-fit the studs from the eye-bolt locations.
Tighten the cylinder/cylinder nuts down evenly and progressively. Tighten to the
appropriate torque figure.
Fit the third stage pressure and bearer rings. Refer to JOB No: 4 - Piston rings
Remove and Re-fit.
Issue 1
01/2015
Page 62
V290M-WN
Compressor
f)
Ensure that the 3rd stage cylinder and top cover mating faces are clean. Ensure that
the cylinder face O ring is in good condition. If necessary replace the O ring.
Attach a suitable sling over the top cover suction and delivery flanges and using
suitable lifting equipment, raise and position over the cylinder. Lower the top cover so
that it passes over the studs.
When in position, remove the sling and lightly secure the top cover fasteners. (10 x
M20 Nuts)
Tighten the top cover nuts down evenly and progressively. Tighten to the appropriate
torque figure.
Re-establish water and electrical supplies to the compressor. Bleed off any trapped air
in the cooling system using the plugs in the cylinder water jacket.
Test run the compressor and check for correct operation and freedom from leaks
around any of the disturbed joints.
Issue 1
01/2015
Page 63
V290M-WN
Compressor
1 set
List of Consumables
Industrial cleaning fluid (White Spirit) & lint free cloth
a)
A/R
To Remove
Piston removal procedure is detailed as part of Job No.013 Piston Rod - Remove/Refit.
b)
Examination
Piston Pressure Rings For piston pressure ring dimensions refer to Chapter 1 Technical
Data. The pressure rings MUST be replaced with new ones when the radial thickness at any
point has worn to 65% or less of the original thickness.
Piston Bearer Rings For piston bearer ring dimensions refer to Chapter 1 Technical
Data. The bearer rings MUST be replaced by new ones, when the standout at any point has
worn to 0.5mm or less.
c)
Remove and discard the old piston and bearer rings. The old bearer rings may require
cutting in order to remove them; ensure that the piston is not damaged when cutting
rings. Carefully clean piston ring grooves.
Insert the new piston ring squarely into the cylinder bore and check that the ring gap is
correct. Refer to Chapter 1 Technical Data.
Fit bearer rings using an appropriate method. Some rings will require heating in order
to allow them to be fitted over.
4.
Fit the new piston rings by carefully springing them over the piston body.
5.
Fit new bearer rings. The first stage bearer ring is split and can be sprung over the
body of the piston in the same way as the piston rings. The second and third stage
bearer rings must be fitted by the following procedure.
Issue 1
01/2015
a.
Remove the second stage piston rod and piston from the compressor. See JOB
No: 13 - Piston Rods - Remove and Re-fit
b.
Split the piston and remove the old bearer ring. Carefully cut the old bearer ring if
necessary for removal. Ensure that the bearer ring groove is clean and smooth.
c.
d.
Once heating is completed, fit the bearer ring over the bearer ring groove and
carefully tap into position. Ensure that the ring is not damaged or bruised when
fitting.
e.
Page 64
V290M-WN
Compressor
6.
Ensure that the rings are correctly seated in the piston groove and that all ring gaps are
staggered.
7.
If the cylinder bore is cored or very lightly polished with no signs of honing marks it may
be necessary to re-hone the bore. (In some cases a flexi-hone can be used).
Illustration 5-3 : Typical Piston Ring Configuration
Issue 1
01/2015
Page 65
V290M-WN
Compressor
A/R
A/R
There are two ways of measuring the piston Top-Dead-Centre (TDC) clearance: Method 1 is used
when the cylinder top covers are removed and Method 2 is by removing the valves and checking
the clearance through the valve pockets. The Bottom-Dead-Centre (BDC) clearance is checked
using Method 2. For the second stage, only the bottom clearance is measured, for the third stage,
only the top clearance is measured.
Illustration 5-4 : Piston features
a)
Job Set Up
1.
Issue 1
01/2015
Before starting this operation, carry out the following safety steps :
a)
b)
c)
Carefully open the vent valves on the third stage cylinder to check depressurising has been completed successfully.
d)
Ensure that the compressor is isolated from the delivery system and that the
compressor is positively isolated from the delivery non-return valve.
e)
f)
Post signs instructing personnel that the machine MUST NOT be used.
Page 66
V290M-WN
Compressor
b)
c)
Method 1
1
2.
Place a sealing gasket of between 0.8mm - 1.0mm on to the cylinder mating face.
3.
Place the machined straight-edge across the top of the gasket on the cylinder.
4.
5.
Measure the clearance between the straight edge and the piston crown. Ensure that
the straight edge is held firmly against the gasket when measuring clearance. record
the with a feeler (thickness) gauge. The required clearances are detailed (Refer to
Crankase Component Clearances.) If the clearances are out side of the tolerance
band the clearance MUST be adjusted (see later in this procedure).
Method 2
1.
Remove either a suction or delivery valve from a top cylinder pocket (if measuring TDC
clearance) or a bottom cylinder pocket (if measuring BDC clearance).
2.
With the piston exactly at TDC or BDC, insert a feeler gauge through the valve pocket
and measure the clearance. Record the end ("bumping") clearances with the piston at
the top (Top-Dead-Centre) and bottom (Bottom-Dead-Centre) of its stroke. The
clearances are detailed in . If the clearances are outside of the tolerance band the
clearance MUST be adjusted (see later in this procedure).
CAUTION!
FEELER GAUGES MUST NOT BE INSERTED INTO THE VALVE
POCKET WHILST TURNING THE MACHINE OVER BECAUSE IF
TRAPPED, THE MACHINE COMPONENTS COULD BE STRAINED
OR DAMAGED.
d)
Remove the crosshead access cover and gasket from the crankcase.
2.
Bar over the crankshaft to reveal the crosshead locknut and the piston rod securing
pin.
3.
Bend back the locking plate tab retaining the securing pin and remove the pin. Ensure
that the securing pin is removed before slackening the crosshead nut. Otherwise, if the
piston rod turns in the crosshead while the securing pin is in position, the pin will distort
making it extremely difficult to remove
4.
5.
The piston rod has a slotted end at the crosshead (through which the securing pin fits)
it can only be turned in 90o steps, one step represents a linear movement of 0.8mm,
(the screwed end of the rod having 8 threads per inch, equivalent to 1 thread every
3.175mm).
6.
To adjust the top end clearance, screw the piston rod into or out of the crosshead.
Ensure that the top and bottom clearances are as close to equal as is possible. If equal
clearances are not obtainable then always, on final setting, make the TOP clearance
the larger of the two (by an amount equal to no more than one quarter turn only of the
piston rod in the crosshead i.e., by no more than 0.8mm).
Issue 1
01/2015
Page 67
V290M-WN
Compressor
7
Recheck that the piston rod slots are correctly aligned for clearance of the piston rod
securing pin.
Fit a new locking plate to the securing pin before fitting and fully tighten the pin.
10
Bend over the locking plate tab to prevent the securing pin from rotating.
11
12.
Issue 1
01/2015
Page 68
V290M-WN
Compressor
A/R
Due to their construction, these packing glands can only be satisfactorily examined and repaired
when they are removed from the compressor and disassembled on a suitable workbench.
a)
Job Set Up
1.
b)
c)
Before starting this operation, carry out the following safety steps :
a)
b)
c)
Carefully open the vent valves on the third stage cylinder to check depressurising has been completed successfully.
d)
Ensure that the compressor is isolated from the delivery system and that the
compressor is positively isolated from the delivery non-return valve.
e)
f)
Post signs instructing personnel that the machine MUST NOT be used.
Fit piston rod clamps to prevent possible uncontrolled movement of the crankshaft and
motion works. Refer to Job No:2.
Mark the position of the oil shedder on the rod surface and remove shedder with its two
clamping screws.
Remove the nuts from the small diameter gland assembly tie studs.
Remove the securing nuts from the gland cover and lower the cover down the piston
rod until it is resting on the oil scraper gland assembly.
Slide each container assembly down the piston rod until it is clear of the gland.
Slide the container a little way back up the piston rod to expose the packing rings and
in turn, unhook the garter springs and remove the packing ring segments.
Reassemble and carefully store each ring of segments and garter spring, immediately
on removal. Repeat this step until all of the packing rings have been removed.
Observe that each ring is marked with matching numbers and letters for use in
reassembly. Also the lowermost ring has a peg which locates into a hole in the
uppermost ring to form a container pair. The rings can be re-used depending upon
condition after inspection.
Issue 1
01/2015
Page 69
V290M-WN
Compressor
If the piston rod is out of the compressor, the gland can be assembled on the work-bench, then
fitted into place as a finished unit. If the rod is in place, the rings and their springs are assembled
around the rod by working through the distance piece apertures.
1
Check the piston rod surface for wearing or any sign of scoring. If evidence of wearing
or scoring is heavy the piston rod should be replaced.
Assemble each ring onto the piston rod with its garter spring.
Fit the rings as pairs into their respective containers (ensure peg is pointing upwards).
Slide each container assembly up the piston rod in turn, finally clamping the completed
gland assembly with the tie rod nuts.Refit and tighten the packing nuts and secure the
gland assembly to the cylinder bottom.
Refit the oil shedder to the piston rod in the position marked during removal and secure
with its clamping screws.
Issue 1
01/2015
Page 70
V290M-WN
Compressor
Illustration 5-5 : 1st Stage Packing
Issue 1
01/2015
Page 71
V290M-WN
Compressor
Illustration 5-6 : 2nd Stage Packing Parts
Issue 1
01/2015
Page 72
V290M-WN
Compressor
List of Consumables
Industrial cleaning fluid (White Spirit) & lint free cloth
A/R
Due to their construction, these packing glands can only be satisfactorily examined and repaired
when they are removed from the compressor and disassembled on a suitable workbench. To
remove the packing gland completely from the compressor, the piston rod must first be removed.
a)
b)
To Disassemble
1
Remove the nuts from the small diameter gland tie studs and separate and
disassemble the containers. As each container ring is lifted off the assembly, take
meticulous care of the precision ground and lapped faces between the containers and
the plates.
Observe carefully that the ring containers and the plates between them are staggered
sequentially, with number 1 being the top container ring.
Observe that the tie studs are unequally spaced to ensure the correct orientation of the
internal water passageways is maintained.
Observe and carefully record the construction and sequence of assembly for the rings,
noting that each ring of segments is marked with matching numbers and letters. In
addition note that there is a peg and hole location in the segmented ring set in the
containers with the peg pointing upwards.
As each container is lifted off the assembly, remove and store the packing rings
Observe the condition of the soft metal sealing ring in the top face of the uppermost
gland ring ensure that it is not damaged during handling and storage.
Unscrew the small diameter tie studs from the uppermost container ring.
To Inspect
1
The packing rings are checked for wear by re-assembling, with garter spring, squarely
around the piston rod, or on the Wear Check Tool and examining the butt clearances.
When parts are new the butts are each approx. 3mm wide; discard the ring when the
butts reduce to 0.5mm.
Examine the soft metal sealing ring on the top-most container of the gland ring to
ensure this is in good condition.
Issue 1
01/2015
Page 73
V290M-WN
Compressor
c)
To Reassemble
Scrupulous cleanliness of all parts is required on assembly, particularly of the lapped faces
between the containers and plates.
1
Identify and layout the gland components in sequential order in preparation for
reassembly.
Place piston rod/piston assembly onto a clean work-bench resting on the piston crown
with the piston rod pointing upwards so that the rod can be used as an assembly tool.
Thoroughly clean the rod surface and fit the thread guard cap to the rod end.
Thread the packing gland cover plate over the piston rod to rest on the piston.
Progressively build up the gland assembly in the correct numbered sequence of the
plates and containers refitting packing rings and O rings in their correct positions as
noted during dismantling. Refer to Illustration 5-6 : Stage Packing Assemblies for
guidance.
Firmly screw the tie studs back into their original positions in the top gland ring.
Carefully thread the tie rods back through the gland assembly until the top gland ring
rests squarely onto the top container.
Whilst clamping the assembly firmly to prevent, separation or misalignment, lift the
assembly sufficiently to fit the nuts to the tie studs.
10
Refit the gland assembly as described in JOB No: 6 - Packing Assembly - Remove
and Re-fit.
Issue 1
01/2015
Page 74
V290M-WN
Compressor
A/R
The piston rod oil shedder is clamped in halves to the piston rod by socket head screws. The
shedder is fitted so as to run clear of the packing gland and the scraper gland covers. If the
shedder becomes damaged renew as follows:
The oil shedder should only be fitted onto the piston rod when both the oil scraper gland and
packing gland are fully fitted in place.
Illustration 5-7 : Piston-rod Oil Shedder in situ.
Oil Shedder
a)
Job Set Up
1.
b)
Before starting this operation, carry out the following safety steps :
a)
b)
c)
Carefully open the vent valves on the third stage cylinder to check depressurising has been completed successfully.
d)
Ensure that the compressor is isolated from the delivery system and that the
compressor is positively isolated from the delivery non-return valve.
e)
f)
Post signs instructing personnel that the machine MUST NOT be used.
To Remove
1
Issue 1
01/2015
Fit piston rod clamps to prevent possible uncontrolled movement of the crankshaft and
motion works. Refer to JOB No: 2 - Fit Piston Rod Clamps
Page 75
V290M-WN
Compressor
2
c)
Mark the position of the oil shedder on the rod surface and remove shedder with its two
clamping screws.
To Refit
1
Place the piston in BDC position and assemble the shedder onto the piston rod with the
hollowed side placed downwards.
Position the shedder 2.5mm above the top face of the scraper gland and lightly but
firmly tighten the two screws.
Turn over the compressor to ensure that the oil shedder does not foul either the upper
packing gland or the lower scraper gland.
Two small diameter washers of the required thickness placed either side on top of the
scraper gland are helpful in setting the shedder position - remove the washers
immediately afterwards.
Issue 1
01/2015
Page 76
V290M-WN
Compressor
List of Consumables
Industrial cleaning fluid (White Spirit) & lint free cloth
a)
A/R
Job Set Up
1.
Before starting this operation, carry out the following safety steps :
a)
b)
c)
Carefully open the vent valves on the third stage cylinder to check depressurising has been completed successfully.
d)
Ensure that the compressor is isolated from the delivery system and that the
compressor is positively isolated from the delivery non-return valve.
e)
f)
Post signs instructing personnel that the machine MUST NOT be used.
Illustration 5-8 : Oil Shedder and Scraper Assembly
b)
To Remove
1
Issue 1
01/2015
Fit piston rod clamps to prevent possible uncontrolled movement of the crankshaft and
motion works. Refer to JOB No: 2 - Fit Piston Rod Clamps.
Page 77
V290M-WN
Compressor
c)
d)
2.
Lift the plate and slide the upper pair of scrapers up the rod.
3.
Unhook the garter springs and remove the scraper ring segments.
4.
Re-assemble and carefully store each ring of segments immediately upon removal.
5.
The segments are marked relative to each other, the lower ring pair having a peg and
locating hole arrangement for correct re-assembly. The rings can be re-used
depending upon condition.
6.
Lift the container and slide the lower pair of scrapers up the rod.
7.
Re-assemble and carefully store each ring of segments immediately upon removal.
The oil scraper rings are checked for wear by re-assembly, with garter spring, squarely
around the piston rod, or on the wear check tool and examining the butt clearances in
the case of ring W1 and W2.
2.
When parts are new the butts of W1 and W2 are each 0.8mm (0.032") wide.
3.
Discard the rings and their sealing rings when the butts reduce to 0.12mm (0.005")
each or a total of 0.36mm (0.015") or less, and replace with a new pair.
4.
The segments of the sealing ring have angle cut contact faces - there are no butt
clearances.
To Refit
1.
2.
There are oil drain slots cast in the bottom of the housing. Should the housing need to
be removed it must be refitted with these slots (in the case of the inclined cylinders)
positioned lower-must. "TOP" is staggered on the housing.
3.
4.
Bar over the compressor a couple of turns to check for correct operation.
5.
Issue 1
01/2015
Page 78
V290M-WN
Compressor
A/R
Grinding Paste
A/R
Each valve is installed in an individual pocket. They are fitted with metal-to-metal contact (i.e. no
gasket material) to the seat face in the cylinders.
a)
Job Set Up
1.
b)
Before starting this operation, carry out the following safety steps :
a)
b)
c)
Carefully open the vent valves on the third stage cylinder to check depressurising has been completed successfully.
d)
Ensure that the compressor is isolated from the delivery system and that the
compressor is positively isolated from the delivery non-return valve.
e)
f)
Post signs instructing personnel that the machine MUST NOT be used.
To Remove
CAUTION!
SERIOUS DAMAGE COULD RESULT FROM SUCTION VALVES
AND THEIR ASSOCIATED COMPONENTS, BEING FITTED IN
DELIVERY VALVE POCKETS OR VICE-VERSA. THEREFORE,
ENSURE VALVES ARE CORRECTLY IDENTIFIED WITH THEIR
POCKETS.
1
Remove the valve from its pocket (using a valve extraction tool where necessary).
Issue 1
01/2015
Page 79
V290M-WN
Compressor
c)
To Refit
CAUTION!
IT IS IMPORTANT AFTER FITTING VALVES (OR AFTER WORK OF
ANY KIND WHICH HAS BEEN DONE INSIDE THE CYLINDERS) TO
ENSURE THAT ALL IS CLEAR IN THE CYLINDERS BY BARRING
OVER THE CRANKSHAFT TWO OR THREE REVOLUTIONS.
1
Ensure that there are no bruises or burrs on the valve seat or pocket seat. A light
grinding-in operation may be needed, it is important to ensure that no grinding paste
enters the cylinder and that all is clean after completion.
The diametric clearance between the valve seat and the seating in the cylinder is small,
therefore the valve has to be fitted very carefully to ensure that it fits squarely on to its
seat. It is essential that the valve is squarely fitted on its seat and metal to metal
contact established.
Check that 'O' rings are in good condition and that their associate grooves are clean
before final assembly of valve cover/cage. Renew if necessary.
Refit the cover securing bolts and tighten evenly and squarely to the correct torque.
Issue 1
01/2015
Page 80
V290M-WN
Compressor
Illustration 5-8 : Oil Shedder and Scraper Assembly
Issue 1
01/2015
Page 81
V290M-WN
Compressor
List of Consumables
Industrial cleaning fluid (White Spirit) & lint free cloth
A/R
Gardner Denver are able to offer a valve exchange service, whereby re-furbished valves are
supplied in exchange for valves returned by customers. The refurbished valves supplied by
Gardner Denver are factory reconditioned and all parts are guaranteed . Use of this service may be
more cost effective than stripping and cleaning valves on customers own site. Please contact
Gardner Denver service department for details.
a)
To Remove
1
b)
Remove the suction delivery valve in accordance with JOB No: 10 -Suction and
Delivery Valves - Remove and Re-fit
To Inspect
CAUTION!
THE CORRECT HOLDING TOOL MUST BE USED WHEN
DISMANTLING AND ASSEMBLING VALVES. THE VALVES
THEMSELVES MUST NEVER BE GRIPPED IN A VICE.
1
Inspect the 'O' ring for each valve cover/cage. Renew if necessary.
There are locating pegs in all valve seats; these ensure correct relationship between
various components, except the valve coil springs.
Thoroughly clean all parts and examine for signs of fatigue or wear.
Check for distortion or damage to the sealing faces of valve seats, examine also the
guards.
Compare the height of displaced springs, with new spares, to determine any
deterioration in spring loading.
Issue 1
01/2015
Page 82
V290M-WN
Compressor
c)
To Overhaul
CAUTION!
CARE MUST BE TAKEN WHEN REASSEMBLING OVERHAULED
VALVE
COMPONENTS.
THE
COMPONENTS
MUST
BE
ASSEMBLED CORRECTLY. AN INCORRECTLY ASSEMBLED
VALVE WILL QUICKLY DETERIORATE IN SERVICE AND
CONSEQUENTLY MAY DAMAGE OTHER PARTS OR AFFECT THE
COMPRESSOR PERFORMANCE. PARTICULAR CARE MUST BE
TAKEN WHEN ASSEMBLING VALVES TO ENSURE THAT THE
SPRINGS REMAIN CORRECTLY IN THEIR LOCATIONS.
1
The valves have locating pins, which ensure that the various components are correctly
related radially. The pins are of differing diameters which ensures that the valve seat,
valve plate, valve damper plates, and valve guard are correctly fitted, one to the other.
If new locating pins are fitted to an old seat it is essential that they are of the correct
sizes and positioned exactly as on original valve seats, with correct standout height
above the valve seat top surface.
Lift Washers - when not of identical thickness - should be fitted with the thinner one
next to the valve seat (this thinner one is referred to as the lower lift washer).
Conical type springs are fitted with the large diameter end located in the holes in the
valve guard.
Issue 1
01/2015
Page 83
V290M-WN
Compressor
a)
Job Set Up
1.
b)
c)
A/R
Before starting this operation, carry out the following safety steps :
a)
b)
c)
Carefully open the vent valves on the third stage cylinder to check depressurising has been completed successfully.
d)
Ensure that the compressor is isolated from the delivery system and that the
compressor is positively isolated from the delivery non-return valve.
e)
f)
Post signs instructing personnel that the machine MUST NOT be used.
To Inspect
1
Check that the small vent hole in the side of the lower half case is clear (if this
becomes blocked then the diaphragm cannot deflect properly due to pressure buildup).
Under normal circumstances actuators give long and trouble free service. If there is
deterioration of any part, it is recommended that the complete actuator is replaced.
To Refit
1
Ensure that the suction valve is fitted correctly and that its securing cover is fully
tightened down squarely.
It is essential that the correct gap is present between the actuator and the valve,
otherwise the suction valve may not open or close fully.
Carefully screw the actuator (with its locknut screwed back) until the spindle just
contacts the valve unloader.
The unloader is spring loaded so take care to just contact it and NOT depress it.
Screw back the actuator about 1.5mm and pinch tighten the locknut.
Insert a hard wood dowel/rod through the control air connection hole in the top of the
actuator casing until it just touches the top of the diaphragm.
With the dowel/rod in position, mark it accurately in line with the actuator cover plate
top.
Using the dowel/rod depress the actuator (against the action of the spindle return
spring) until it just contacts the unloader, but do not depress it.
While holding the dowel/rod in position, mark it accurately again in line with the
actuator cover plate top. Then release the dowel/rod (it will rise under the action of the
actuator spindle return spring).
Issue 1
01/2015
Page 84
V290M-WN
Compressor
10
Remove the dowel/rod and measure the distance between the marks. If it is NOT
between 1.4mm and 1.6mm then adjust the actuator position, by screwing it in or, out
of the cover plate, as required.
11
When the gap is set correctly, tighten the locknut to the correct torque.
12
When all the actuators on the compressor are correctly set, fit the end fittings to the
actuators; reconnect the control air pipework to the actuators and to the associated
vent vale and test the compressor for correct operation.
Issue 1
01/2015
Page 85
V290M-WN
Compressor
a)
A/R
To Remove
1
To open the filter body undo the bottom bolt (using a clean bucket to catch spilled oil),
the filter body and element draw off vertically downwards.
When replacing the assembly (with a new filter pack) care should be taken that the seal
ring gasket at the top and the washer at the bottom are in their correct positions. A new
seal ring gasket is supplied as part of the filter element spare.
There is a spring fitted internally onto the bolt - this is installed to hold the filter element
up against the top cover and so form the seal; it also provides the automatic safety filter
bypass (for use should the element become heavily fouled).
Before assembly of the filter body to its cover, fill the body with clean compressor
lubricating oil.
Issue 1
01/2015
Page 86
V290M-WN
Compressor
a)
A/R
To Adjust
1
Slacken the locknut on the adjusting screw and adjust to obtain the required oil
pressure (screw IN to raise the pressure, screw OUT to decrease the pressure).
Normally adjustment is not necessary after initial setting by the manufacturer. If a fault
should occur and adjustment has no noticeable effect, the trouble could be a particle of
foreign matter trapped under the valve. Dismantling, cleaning and re-assembly is then
required (first noting the valve adjusting screw setting).
Issue 1
01/2015
Page 87
V290M-WN
Compressor
a)
A/R
To Overhaul
1
Remove the cap screws securing the oil pump to bearing housing and carefully
withdraw the pump, together with the filter body attached, its drive coupling can then be
inspected.
When refitting the oil pump renew the gasket if the old one has deteriorated.
Issue 1
01/2015
Page 88
V290M-WN
Compressor
a)
To Inspect
1
b)
A/R
To Overhaul
1
It is not expected that the inside (i.e., tube internals) will foul. Any untoward
accumulation of soft deposits at the tube entrance may be removed by blowing
backwards with compressed air, the cooler being off the compressor for this purpose.
Should the cooling water side become fouled then use a proprietary procedure as
recommended by local water treatment specialists - this to be compatible with the
materials of construction (see Chapter 1 - Technical Data and Description).
Issue 1
01/2015
Page 89
V290M-WN
Compressor
The following is the recommended list of tools required to perform maintenance tasks on this compressor:
Tool
Supplementary Information
Standard tool box tools including:A range of open-jaw, ring, and socket type
spanners
Circlip pliers
Eyebolts
Fitters tools
Long-nosed pliers
b)
Specialist service tools (which can be manufactured locally) or purchased direct from Gardner
Denver, can be used to aid compressor maintenance work. Contact Gardner Denver service
department for advice on special tools.
Avoid contact with the skin and wash off any contamination immediately.
Dispose of old oil and filter elements in accordance with local regulations.
For further details contact your local oil company representative, or local government
department dealing with factory wastes.
b)
Coolant
Coolant from closed loop systems ie. water with anti-freeze added, should be disposed of in a safe
manner. For further advice contact the local Water Authority.
Issue 1
01/2015
Page 90
V290M-WN
Compressor
Issue 1
01/2015
Page 91
V290M-WN
Compressor
Issue 1
01/2015
Page 92
V290M-WN
Compressor
Description
Qty
Part No.
Bonded Seal
44286/6
Bonded Seal
44286/4
Bonded Seal
44286/5
CC1033383
CC1035906
CC1035907
PSB032-024
PSB032-012
PSB008-057
Description
Qty
Part No.
CC1035982
CC1035983
CC1033537
CC1033593
CC1033818
CC1033819
Issue 1
01/2015
Page 93
V290M-WN
Compressor
V290M-WN SPARE PARTS 8000 HOUR SERVICE KIT-COMPRESSOR SPARE PARTS
Item
Description
Qty
Part No.
PSB008-085
CC1033383
PSB008-055
PSB008-056
Cylinder Gasket
PSB008-049
CC1036040
CC1026966
CC1026967
2-70-216-02
10
CC1036016
11
Actuator Diaphragm
PSB028-003
12
PSB032-014
13
PSB032-024
14
PSB032-012
15
CC1036124
16
CC1036126
17
CC1035904
18
CC1035905
19
CC1035906
20
CC1035907
21
PSB002-011
22
PSB025-001
23
PSB025-003
24
PSB025-006
25
ASB511-018
26
PSB008-057
27
PSB014-012
28
Cotter Pin
MB075-39
29
43445/13
30
43445/35
31
Intercooler Gasket
CC1033287
32
Intercooler Gasket
43445/28
33
Bonded Seal
44286/4
34
Bonded Seal
44286/5
35
Bonded Seal
44286/6
Issue 1
01/2015
Page 94
V290M-WN
Compressor
6.4 Drawings
The following drawings contain all items used in the construction of the compressor.
Drawing Ref
Description
V290M-WN
GENERAL ARRANGEMENT
2-77-2202
P&ID DRAWING
CC1034293
CC1069291
CC1069292
CC1069293
CC1039053
ANCILLAIRES
CC1071471
CC1042024
10
CC1039413
11
CC1039027
AFTERCOOLER ASSY
Issue 1
01/2015
Page 95
V290M-WN
Compressor
1. V290M-WN GENERAL ARRANGEMENT
Issue 1
01/2015
Page 96
V290M-WN
Compressor
2. 2-77-2202 P&ID DRAWING FOR V290
Issue 1
01/2015
Page 97
V290M-WN
Compressor
3. CC1034293 LOWER PARTS ASSY
Issue 1
01/2015
Page 98
V290M-WN
Compressor
Issue 1
01/2015
Page 99
V290M-WN
Compressor
4. CC1069291 CYLINDER ASSY CELL-V290
Issue 1
01/2015
Page 100
V290M-WN
Compressor
Issue 1
01/2015
Page 101
V290M-WN
Compressor
5. CC1069292 INTERSTAGE ASSY CELL-V290
Issue 1
01/2015
Page 102
V290M-WN
Compressor
6. CC1069293 FINAL ASSY CELL-V290
Issue 1
01/2015
Page 103
V290M-WN
Compressor
Issue 1
01/2015
Page 104
V290M-WN
Compressor
7. CC1039053 ANCILLAIRES
Issue 1
01/2015
Page 105
V290M-WN
Compressor
8. CC1071471 ANCILLARY ASSY CELL
Issue 1
01/2015
Page 106
V290M-WN
Compressor
9. CC1042024 INSTRUMENTATION UNLOADER PIPEWORK ASSY
Issue 1
01/2015
Page 107
V290M-WN
Compressor
10. CC1039413 COOLING WATER PIPEWORK
Issue 1
01/2015
Page 108
V290M-WN
Compressor
Issue 1
01/2015
Page 109
V290M-WN
Compressor
11. CC1039027 AFTERCOOLER ASSY
Issue 1
01/2015
Page 110
Section 2
Motor Manual
ENGLISH
TABLE OF CONTENTS
1. FOREWORD ................................................................................................................. 3
2. SHIPMENT, STORAGE AND HANDLING . .................................................................. 3
3. INSTALLATION...... ....................................................................................................... 4
4. OPERATION.................................................................................................................. 5
5. MAINTENANCE ............................................................................................................ 5
6. ADDITIONAL INFORMATION ...................................................................................... 5
7. EC DECLARATION OF CONFORMITY ....................................................................... 5
8. WARRANTY TERM ...................................................................................................... 6
1. FOREWORD
The installation, operation and maintenance of the motor must be always performed by qualied personnel
using proper tools and methods and following the instructions contained in the documents supplied with the
motor.
The instructions presented in this document are valid for WEG motors with the following characteristics:
Three-phase and single-phase induction motors (squirrel cage rotor);
Three-phase permanent magnet motors;
Three-phase hybrid motors (squirrel cage rotor + permanent magnets);
J
J
J
The objective of this manual is to provide important information, which must be considered during the shipment,
storage, installation, operation and maintenance of WEG motors. Therefore, we advise to make a careful and detailed
study of the instructions contained herein before performing any procedures on the motor. The noncompliance
with the instructions informed in this manual and others mentioned on the website www.weg.net voids the product
warranty and may cause serious personal injuries and material damages.
Electric motors have energized circuits and exposed rotating parts which may cause injuries to people.
Periodically and mainly before the initial star-up, measure the insulation resistance of the motor winding.
Check the recommended values and the measuring procedures in the website.
3. INSTALLATION
During the installation, the motors must be protected against accidental energization.
Check the motor direction of rotation, turning it without load before it is coupled to the
load.
Remove the transportation devices and shaft locking device (if supplied) before starting the motor installation.
Motors must be only installed in places compatible with their mounting features and in applications and
environments for which they are intended.
Those motors with feet must be installed on bases duly planned in order to prevent vibrations and assure perfect
alignment. The motor shaft must be properly aligned with the shaft of the driven machine. Incorrect alignment,
as well as improper belt tension, will certainly damage the bearings, resulting in excessive vibrations and even
causing the shaft to rupture. The admissible shaft radial and axial loads indicated in the general manual of the
website must be respected. Use exible coupling whenever possible.
When motors are tted with oil lubricated bearings or oil mist lubrication systems, connect the cooling and
lubrication tubes (where provided). Only remove the corrosion protection grease from the shaft end and ange
immediately before the motor installation.
Unless specied otherwise in the purchase order, WEG motors are dynamically balanced with half key and
without load (uncoupled). The driving elements, such as pulleys, couplings, etc., must be balanced with half key
before they are mounted on the shaft of the motors.
Observe the correct assembly position of the drains as indicated in the manual on the website www.weg.net.
Do not cover and block the motor ventilation openings. Ensure a minimum clearance of
(25%) of the diameter of the air intake of the fan cover from the walls. The air used for
cooling the motor must be at ambient temperature, limited to the temperature indicated on
the motor nameplate.
Motors installed outdoors or in the vertical position require the use of additional shelter to protect
them from water; for instance, use of a drip cover.
To prevent accidents, ensure that the grounding connection has been performed according to the
applicable standards and that the shaft key has been securely fastened before the motor is started.
Connect the motor properly to the power supply by means of safe and permanent contacts, always
considering the data informed on the nameplate, such as rated voltage, wiring diagram, etc.
For power cables, switching and protection devices dimensioning, consider the rated motor current, the
service factor, and the cable length, among others. For motors without terminal block, insulate the motor
terminal cables by using insulating materials that are compatible with the insulation class informed on the
nameplate. The minimum insulation distance between the non-insulated live parts themselves and between
live parts and the grounding must be: 5.5 mm for rated voltage up to 690 V; 8 mm for voltages up to 1.1 kV;
45 mm for voltages up to 6.9 kV; 70 mm for voltages up to 11 kV and 105 mm for voltages up to 16.5 kV.
In order to assure the degree of protection, unused cable inlet holes in the terminal
box must be properly closed with blanking plugs having and equal or higher degree of
protection to that indicated on the motor nameplate.
The motor must be installed with overload protection devices. When motor is tted with temperaturemonitoring devices, they must be connected during the operation and even during tests.
Ensure the correct operation of the accessories (brake, encoder, thermal protection, forced ventilation, etc.)
installed on the motor before it is started.
Motors tted with Automatic Thermal Protectors will reset automatically as soon as
the motor cools down. Thus, do not use motors with Automatic Thermal Protection in
applications where the auto-reseting of this device may cause injuries to people or damage
to equipment. Motors tted with Manual Thermal Protectors require manual reset after they trip. If
the Automatic Thermal Protector or the Manual Thermal Protector trip, disconnect the motor from
4 | Low and High Voltage Electric Motors
the power supply and investigate the cause of the thermal protector tripping. Wmagnet
motors must be driven by WEG variable frequency drives only.
For more information about the use of variable frequency drives, follow the instructions in the motor manual
on the website www.weg.net and in the manual of the variable frequency drive.
4. OPERATION
During operation, do not touch the non-insulated energized parts and never touch or stay
too close to rotating parts.
Ensure that the space heater is always OFF during the motor operation.
The rated performance values and the operating conditions are specied on the motor nameplate. The
voltage and frequency variations of the power supply should never exceed the limits established in the
applicable standards.
Occasional different behavior during the normal operation (actuation of thermal protections, noise level,
vibration level, temperature and current increase) must always be assessed by qualied personnel. In case
of doubt, turn off the motor immediately and contact the nearest WEG service center.
Do not use roller bearings for direct coupling. Motors tted with roller bearings require radial load to ensure
their proper operation.
For motors tted with oil lubrication or oil mist systems, the cooling system must be ON even after the
machine is OFF and until the machine is at complete standstill.
After complete standstill, the cooling and lubrication systems (if any exist) must be switched OFF and the
space heaters must be switched ON.
5. MAINTENANCE
Before any service is performed, ensure that motor is at standstill, disconnected from
the power supply and protected against accidental energization. Even when the motor is
stopped, dangerous voltages may be present in space heater terminals.
If motors are tted with capacitors, discharge them before any handling or service is performed.
Motor disassembly during the warranty period must be performed by a WEG authorized service
center only.
For motors with permanent magnet rotor (lines WQuattro and Wmagnet), the motor assembly and
disassembly require the use of proper devices due to the attracting or repelling forces that occur
between metallic parts. This work must only be performed by a WEG Authorized service center
specically trained for such an operation. People with pacemakers cannot handle these motors.
The permanent magnets can also cause disturbances or damages to other electric equipment and
components during maintenance.
Regularly inspect the operation of the motor, according to its application, and ensure a free air ow. Inspect
the seals, the fastening bolts, the bearings, the vibration and noise levels, the drain operation, etc.
6. ADDITIONAL INFORMATION
For further information about shipment, storage, handling, installation, operation and maintenance of electric
motors, access the website www.weg.net.
For special applications and operating conditions (for example, smoke extraction motors, totally enclosed
air over (TEAO), motors for high thrust applications, motors with brake) refer to the applicable manual on the
website www.weg.net or contact WEG.
When contacting WEG, please, have the full description of the motor at hand, as well as the serial number
and manufacturing date, indicated on the motor nameplate.
7. EC DECLARATION OF CONFORMITY
WEG Equipamentos Eltricos S/A
Av. Prefeito Waldemar Grubba, 3000
89256-900 - Jaragu do Sul SC Brazil,
and its authorised representative established in the European Community,
Low and High Voltage Electric Motors | 5
Single-phase
IEC frames 63 to 132
Nema frames 42, 48, 56 and 143 to 215
when installed, maintained and used in applications for which they were designed, and in compliance with
the relevant installation standards and manufacturers instructions, comply with the requirements of the
following European Directives and standards where applicable:
Directives:
Low Voltage Directive 2006/95/EC
Regulation (CE) No 640/2009
Directive 2009/125/EC
EMC Directive 2004/108/EC (induction motors are considered inherently benign in terms of
electromagnetic compatibility)
Standards:
EN 60034-1/2-1/5/6/7/8/9/11/12/14/30 and 60204-1
From 29/12/2009 on low voltage electric motors are no longer considered under the scope of the current
Machinery Directive 2006/42/EC.
CE marking in: 1996
Milton Oscar Castella
Engineering Director
8. WARRANTY TERM
WEG Equipamentos Eltricos S/A, Motor Unit, offers warranty against defects in workmanship and materials for their
products for a period of 18 months from the invoice issue date by factory or distributor / dealer, limited to 24 months from
date of manufacture. Motors of the HGF Line are covered for a period of 12 months from the invoice issue date by the
factory or distributor / dealer, limited to 18 months from the date of manufacture.
The paragraph above contains the legal warranty periods. If a warranty period is dened in a different way in the commercial,
technical proposal of a particular sale, that will override the time limits set out above.
The periods above are independent of installation date and provided that the following requirements are met: proper
transportation, handling and storage; correct installation in specied environmental conditions free of aggressive agents;
operation within the capacity limits and observation of the Installation, Operation and Maintenance Manual; execution of
regular preventive maintenance; execution of repairs and/or changes only by personnel with WEGs written authorization;
in the occurrence of an anomaly, the product must be available to the supplier for the minimum period necessary to identify
the cause of the anomaly and to repair it properly; the buyer must immediately notify WEG of any defects occurred and
they must be later conrmed as manufacturing defects by WEG. The warranty does not include assembly and disassembly
services at the buyers premises, costs of product transportation, as well as travel, lodging and meals expenses for the
technical assistance staff when requested by the customer. The warranty service will be provided exclusively at a WEG
authorized Technical Assistance or at the plant.
Components, parts and materials whose useful life is usually less than 12 (twelve) months are not covered by the warranty.
Under no circumstance will warranty services extend the warranty period of the equipment. However, new warranty
equivalent to the original one will be due only to the components repaired or replaced by WEG.
The present warranty is limited to the product supplied. WEG will not be liable for damages to people, third parties, other
equipment and facilities, loss of prots or other incidental or consequential damages.
6 | Low and High Voltage Electric Motors
Section 3
Drawings