Escolar Documentos
Profissional Documentos
Cultura Documentos
STRUCTURAL
INVESTIGATION
STOCKS & PARTNERS
The following contains an investigation that was carried out
on CPA Haus to assess the structural aspect of the property
in response to earth tremors due to adjacent Paga Ring
Road Project rock blasting.
Contents
BACKGROUND: .............................................................................................................................................. 2
INTRODUCTION ............................................................................................................................................. 3
METHODOLOGY ............................................................................................................................................ 3
THE BUILDING ........................................................................................................................................... 4
SITE TOPOGRAPHY .................................................................................................................................... 4
DESKTOP STUDY ............................................................................................................................................ 4
BUILDING CLASSIFICATION TO PNGS 1001 1982: PART 4 EARTHQUAKE LOADINGS .......................... 4
ULTIMATE LOADING OF FOUNDATIONS SUBJECT TO LATERAL LOADS .................................................... 4
CONCRETE STRUCTURES & GROUND VIBRATION..................................................................................... 5
FIELD TESTS, OBVERSATIONS & FINDINGS.................................................................................................... 5
DCP & Schmidt Hammer Tests .................................................................................................................. 5
DCP Test ................................................................................................................................................ 6
Non-Destructive Testing of Concrete using Schmidt Hammer Test Method ....................................... 7
Field Observations .................................................................................................................................... 8
Excavation Pits ...................................................................................................................................... 8
Structural Inspection of Building........................................................................................................... 9
CONCLUSIONS ............................................................................................................................................. 10
Foundations ............................................................................................................................................ 10
Schmidt Hammer Test............................................................................................................................. 10
Concrete Inspections & Excavation Pits .................................................................................................. 10
RECOMMENDATIONS ................................................................................................................................. 12
Concrete Works ...................................................................................................................................... 12
Foundation & Retention Works .............................................................................................................. 12
BIBLIOGRAPHY ............................................................................................................................................ 13
PHOTOS ....................................................................................................................................................... 14
___________________________________________________________________________________________________________
Registered Office:
Section 59 Lot 20, Corner Koani & Gabaka Street, Gordons
P. O. Box 892, Port Moresby, NCD, Papua New Guinea |
P (675) 323 7030 | F (675) 323 9712 | M (675) 7686 3354
Email :ljstocks@stockspartners.com.pg
BACKGROUND:
Formerly home to the United States (US) Embassy, the CPA (Certified Practising Accountants) Haus
stands on five (5) floors, inclusive of the roof level, along Armit Street on the Paga Hill of Port Moresby
(POM). At the foot of Paga Hill is the current construction of Paga Ring Road Project (PRRP), it is one of
Papua New Guineas (PNGs) largest road infrastructure, worth an estimated total value of over K500
million. The project also uses surface and underground blasting to excavate hard rock from the Paga Hill
side rock face. It involves placing explosives in drill holes and detonating them to cause explosion in
order to fracture huge rocks to sizeable end use. As implied from reports by the occupants of CPA Haus,
it is understood that the building experienced horizontal movement due to rock blasting from the PRRP.
During rock blasting, there are two primary energies released, gas energy (air displacement) and shock
energy from which ground vibrations occur and constitute predominantly the energy felt by buildings.
This report will investigate the foundation and superstructure of CPA building due to movement
experienced in the building structure seemingly from the nearby PRRP blasting activity and will further
recommend remedial works accordingly.
Key phrases with definitions:
Rocking of a building translational movement of a building as a single rigid body about its foundations
in contrast to a building under swaying action.
Swaying of a building inter-storey horizontal movement of a building during earthquakes or human
activities such as rock blasting
___________________________________________________________________________________________________________
Registered Office:
Section 59 Lot 20, Corner Koani & Gabaka Street, Gordons
P. O. Box 892, Port Moresby, NCD, Papua New Guinea |
P (675) 323 7030 | F (675) 323 9712 | M (675) 7686 3354
Email :ljstocks@stockspartners.com.pg
INTRODUCTION
Stocks & Partners Limited were commissioned by CPA on the 15th of February, 2016 to investigate the
cause of significant building sway and discomforting movement.
Buildings become subject to forces both inherent and external and their stability similarly is a
characteristic of their sound engineering design or a possible weakness in the founding medium or a
combination of both. The objective of this investigation is to identify which of these may be the cause or
may be a contributing factor.
Civil constructions, such as road works and in this instance the PRRP, invariably impact on the
surroundings. Among these impacts is structural damage as a result of blast induced vibrations from
blasting practices and consequent occupant discomfort.
METHODOLOGY
For the purpose of this report, in order to investigate the type of the foundation and superstructure of
CPA Haus due to the movement experienced in the building structure seemingly from the nearby PRRP
blasting activity, the following work had to be carried out:
Investigation of the existing foundations using Dynamic Cone Penetrometer (DCP) testing and
field observation pits;
Non-destructive testing and Investigation of the existing concrete structures using a Schmidt
Hammer;
Visual assessment of quality and condition of both structural elements and architectural
finishes;
Removal of concrete cover to ascertain reinforcement in block walls and reinforced concrete
(RC) columns.
These tests and investigations are done to determine compliance with our local building codes (PNGS
Parts 1 to 4 respectively), the respective Australian Standards, and acceptable construction practices in
Papua New Guinea.
The CPA Haus is located approximately 680m from nearest blast sites of the PRRP. It was reported by
occupants of the building that the structure had undergone noticeable horizontal movement during
blasting works on the PRRP, hence, raised concerns of the integrity and serviceability of the structure
and foundation material. This subsequently raises the need to investigate the existing foundations and
existing structure and assess the integrity of the structure as a result of the blasting work and
recommend any remedial measures required.
___________________________________________________________________________________________________________
Registered Office:
Section 59 Lot 20, Corner Koani & Gabaka Street, Gordons
P. O. Box 892, Port Moresby, NCD, Papua New Guinea |
P (675) 323 7030 | F (675) 323 9712 | M (675) 7686 3354
Email :ljstocks@stockspartners.com.pg
THE BUILDING
The building stands approximately 11.0m from basement finish floor level to roof level on RC columns
and concrete masonry blockwalls. The structural members supporting the suspended floors consist of
RC beams and RC floor slabs. Its floor dimensions are approximately 8.0m wide x 15.0m long. CPA Haus
mainly serves as an office complex; however, it also provides room for training as required by the CPA
Board annually.
SITE TOPOGRAPHY
The building sits just below the access road and is constructed on an extremely steep slope. The site
steps down twice from the road before reaching basement level after which a retaining wall occurs
which retains the surrounding fill to achieve a relatively even lower part of the site. Interestingly this
lower part of the site, beside the building, a concrete bunker exists possibly dating back to the Second
World War and has an entrance through the retaining wall. The bunker when inspected was found to be
a separate structure to the main building.
DESKTOP STUDY
BUILDING CLASSIFICATION TO PNGS 1001 1982: PART 4 EARTHQUAKE
LOADINGS
To appreciate the lateral forces induced by ground vibrations, in accordance with the PNGS loading code
as stipulated in the heading above, CPA Haus shall be classified as:
In Seismic Zone No. 4 for Building Construction in PNG in accordance with Fig. 3.2;
Buildings accommodating more than 1000 people for a period of more than 8 hours per day on
average in accordance with Clause 3.4.3 (c);
Having a combination of ductile moment-resisting frames complying with Clause 3.4.4.1 in the RC
columns/ beams/ slabs and cantilever shear walls of limited ductility complying with Clause 3.4.4.4
in the reinforced masonry walls as the horizontal load-resisting systems respectively;
Founded on material that is described as firm in accordance to Clause 3.4.2 determined from the
DCP Test and visual inspection of excavated pits.
5
vertical and horizontal loads; the resultant loading is taken as inclined at an angle to the vertical. In such
cases the displacement of the soil from underneath the foundation is only counteracted by the passive
resistance of the soil medium on the opposite face of the foundation. If horizontal loads become severe
which result in movement of structures, then the stability of the foundation against sliding and
overturning must be checked, i.e. presence of engineered backfill and proper construction practice is
questionable on the foundation to provide the needed passive resistance. It is commonly stated in
foundation engineering textbooks that soil bearing capacities reduce after an earthquake/ lateral load is
encountered, i.e. soils become displaced and are loosely compacted.
PNGS 1001, Part 4, Clause 16.14 refers to footings that need to be checked and designed for tension
(uplift) which if founded partially on sound rock and partially on fill in a set of circumstances that may
present us with a scenario in which the building may potentially be rocking on its foundation.
Referring to photo 1, the possibility exists for the building to be partially founded on sound rock and
partially founded on weaker weathered rock and backfill towards its extremities. This scenario as
discussed above presents the circumstances for potentially a rocking foundation to the CPA building.
This lateral movement felt from a shock wave from blasting work, the lack of diagonal cracking in a
blockwall, the findings of the inspection pits at the extremities, confirming backfill to footings would
point to verification of our assertions of that the building may be rocking on is foundations.
___________________________________________________________________________________________________________
Registered Office:
Section 59 Lot 20, Corner Koani & Gabaka Street, Gordons
P. O. Box 892, Port Moresby, NCD, Papua New Guinea |
P (675) 323 7030 | F (675) 323 9712 | M (675) 7686 3354
Email :ljstocks@stockspartners.com.pg
6
DCP Test
All aspects of the Investigations were carried out in accordance with AS1289 F3.2-1984 with on-site
works comprising of four (4) DCP Tests of which only three (3) tests had their data recorded and
analyzed. Test 1 encountered refusal before a depth of 100mm. Test points 2 & 3 were carried out at
the northern boundary flowerbeds of the property, adjacent to the residential property across and test
4 was carried out on foundation level of footings by means of an excavation of the southeastern
founding material. Results are tabulated below:
Table 1: DCP Test Results for Test Point 2
Depth(m)
ABC (KPa)
CBR (%)
Remarks
0.100
0.200
0.300
0.400
0.500
0.600
0.700
0.800
0.900
1.000
1.100
1.200
1.300
1.400
41
41
41
68
68
399
399
372
255
207
172
301
412
358
1
1
1
3
3
96
96
84
40
27
18
55
103
78
ABC (KPa)
CBR (%)
Remarks
0.100
0.200
0.300
0.400
0.500
0.600
0.700
0.800
0.900
1.000
1.100
1.200
1.300
1.400
1.500
1.600
1.700
1.800
1.900
2.000
2.100
2.200
2.300
41
41
41
41
114
41
41
41
134
172
92
190
240
255
223
271
207
190
172
271
240
271
464
1
1
1
1
8
1
1
1
11
18
5
22
35
40
31
45
27
22
18
45
35
45
129
Probe terminated
ABC (KPa)
CBR (%)
Remarks
___________________________________________________________________________________________________________
Registered Office:
Section 59 Lot 20, Corner Koani & Gabaka Street, Gordons
P. O. Box 892, Port Moresby, NCD, Papua New Guinea |
P (675) 323 7030 | F (675) 323 9712 | M (675) 7686 3354
Email :ljstocks@stockspartners.com.pg
7
0.100
0.200
0.300
0.400
0.500
0.600
0.700
41
92
172
114
190
172
301
1
5
18
8
22
18
55
Diorite
Probe rebounded
In test points 2 and 3, located on Northern flowerbeds on which tests were carried out commencing
from natural surface, it appears that within the initial 500mm depth the soil profile is soft and becomes
firm as the depth increases into the soil.
In test point 4, which was carried out 2600mm below natural surface, i.e. at founding level of footings, it
was noted that the probe started giving firm readings at the 300mm depth mark. At a depth of 700mm,
refusal of the rod was encountered, which indicated the presence of bed rock (a hard foundation) being
found at this depth.
Element
Solid block wall
RC Column
RC Column
Solid block wall
Solid block wall
Trial 1
23
27
23
25
23
Trial 2
22
27
25
25
23
Trial 3
20
26
25.5
25
23
Mean
21.7
26.7
24.5
25
23
Final MPa
27.80
33.05
30.73
31.25
29.15
Deviation MPa
+6.1
+6.35
+6.23
+6.25
+6.15
Remarks
Higher
Higher
Lower
Higher
Higher
___________________________________________________________________________________________________________
Registered Office:
Section 59 Lot 20, Corner Koani & Gabaka Street, Gordons
P. O. Box 892, Port Moresby, NCD, Papua New Guinea |
P (675) 323 7030 | F (675) 323 9712 | M (675) 7686 3354
Email :ljstocks@stockspartners.com.pg
8
6-GFL
7-GFL
8-GFL
9-GFL
10-BFL
11-BFL
12-BFL
13-GFL
14-GFL
RC stair side
RC stair top
RC stair side
RC stair side
RC Column
RC Column
RC Column
RC Column
RC Column
22
35
20
22
23
24
22.5
22
22.5
22.5
34
20
22
23
24
22.5
22.5
21
23
34
20
22
22
24
22.5
23
22.5
22.5
34.33
20
22
22.67
24
22.5
22.5
22
28.63
41.00
26
28.1
28.77
30.2
28.63
28.63
28.1
+6.13
+6.67
+6.0
+6.1
+6.1
+6.2
+6.13
+6.13
+6.1
Higher
Higher
Higher
Higher
Lower
Lower
Lower
Lower
Lower
25
25
25
25
32
32
32
32
32
Although these test results indicate that in some instances the concrete strength are lower than
expected, the majority of RC column strengths are below the code required mark to current design
standards in terms of the buildings serviceability (i.e. deflection limits, vibration limits and corrosion
protection requirements respectively) and stability criteria (i.e. overturning limit and sliding limit
requirements respectively) if the building is to be occupied without remedies to its current status of the
RC columns.
During the tests and random inspections, it appeared that honeycomb were predominant on all eleven
(11) inspection/ test spots of the RC elements. There were also courses of the solid blockwall that
turned out to be inadequately core filled after being cut into and inspected. These are clear indications
of poor workmanship and improper construction management at the time the then American Embassy
was constructed.
Field Observations
Excavation Pits
A total of three (3) observation pits were manually excavated by Maxscope Construction for inspection
of the founding material and footings (substructure). Two (2) of the pits had excavations terminated at
depths of 1500mm and 2000mm respectively due to the presence of large rocks (varying diameters of
600 to 1000mm) which prevented manual excavation. Only one (1) pit was excavated down to footing
level, however, rocks/ boulders were observed & encountered throughout the depth.
Excavations of the inspection holes were carried out at the exterior of the basement level (eastern side),
the excavation at the corners of blockwalls and in front of a column revealed that the underlying
substructure material is predominantly composed of backfilled diorite and boulders respectively. To
foundation depth, in all three excavations, voids (failure planes) were repeatedly encountered
throughout each excavation depth in between backfill materials. It was also noted that the backfill
material appeared not to be properly graded, i.e. the fill material had an uneven distribution of varying
particle sizes of the material will not allow natural cohesion of the soils.
___________________________________________________________________________________________________________
Registered Office:
Section 59 Lot 20, Corner Koani & Gabaka Street, Gordons
P. O. Box 892, Port Moresby, NCD, Papua New Guinea |
P (675) 323 7030 | F (675) 323 9712 | M (675) 7686 3354
Email :ljstocks@stockspartners.com.pg
9
Structural Inspection of Building
The street side of the basement level as shown in SK-03, Building Section A, has been constructed
against ground, hence, the blockwalls and columns form a retaining wall structure along the roadside of
the building whereas the Eastern face is above ground and has a door for entrance. This eastern side
structure is retained by a 4.0m high stone pitched retaining wall which did not indicate any form of
distress which would be indicated by cracking as a means of stress relief.
The superstructure RC columns and block walls were also inspected from outside for possible signs of
distress and misalignments in building height. Concrete cover to existing RC columns and blockwalls
were removed to inspect the size, spacing and type of reinforcing bars in the structural elements whilst
gathering other important information. From the observations, it was apparent that:
o
o
o
o
o
o
o
There were no course cracks (i.e. stepped cracks on mortar infill between unit
blocks) throughout the masonry block walls both inside and outside;
Masonry wall structures have adequate cover to steel (i.e. protection of steel from
atmospheric corrosion);
The masonry walls are reinforced with bar spacing of vertical bars were greater than
600mm;
Masonry walls in some instances have unfilled cores which is an indication of
inadequate vibration and compaction of fresh concrete during construction;
RC columns are 320mm by 320mm in cross section, have adequate cover to steel
and are adequately reinforced for bending with 8Y20 vertical reinforcing bars,
however, it is just under-reinforced for shear with R10 ties at 200mm center spaces
(minimum shear reinforcement should be spaced at half the depth of the RC
column). However, It is still able to withstand stresses from the normal service
loads;
Honeycombs were noted at all Schmidt Hammer testing points on RC columns as
indicated in clause 3.1.2;
During removal of the external paint render for Schmidt hammer testing on RC
columns, it was noted that the paint on the external concrete face could be scraped
off with lessor effort than the internal surfaces this can possibly be attributed to
weather over time.
___________________________________________________________________________________________________________
Registered Office:
Section 59 Lot 20, Corner Koani & Gabaka Street, Gordons
P. O. Box 892, Port Moresby, NCD, Papua New Guinea |
P (675) 323 7030 | F (675) 323 9712 | M (675) 7686 3354
Email :ljstocks@stockspartners.com.pg
10
CONCLUSIONS
Foundations
It can firstly be concluded as indicated from the DCP test results that the underlying subsoil from a
depth of 1000mm below natural surface, is firm for building construction, however, building sliding and
overturning (consequently rocking of foundation) may raise issues of stability of any construction
founded at such depths.
Secondly, it can be concluded that all footings located at the Eastern side of the building footprint are
founded on a layer of fill material incorporating rock/ boulders as revealed during the excavation of
foundations. In contrast, footings on the car park side are expected to be keyed into the Paga rock bed.
Furthermore, it has been estimated that the natural rock profile of the portion of Paga Hill where CPA is
located is about 3500mm below basement level and closer to the roadside of the building. However, this
is only taken as a basis of understanding the rock profile of the Paga hill in that portion as it is still
unclear where it is exactly located in relation to current exiting surfaces.
11
the blast energy, suspected to be at the top of the Paga Hill, transferred through the rock medium of the
hill is suspected as the likely cause for the building together with its footings to have rocked on its
foundations. This is in contrast to swaying which is the usual or expected displacement behavior of a
building founded such that the effects of sway are evident. And therefore, the absence of diagonal
cracks in the concrete masonry walls and prevalent hairline cracks in the RC columns respectively lead to
the likely conclusion that rocking rather than sway had occurred.
Thirdly, the block wall strip footings were also discovered after full excavation to footing level, of having
inadequate rectangular cross-section construction, a profile expected and designed to provide an
adequate bearing area and even stress distribution at its base. Refer SK-03 for illustration.
It appears that the backfill material was inadequately compacted and does not compose of the proper
engineered backfill material so as to give the needed passive earth pressure during lateral loading of
foundations as intended. This is due to the fact that no subsequent signs of vertical cracks on the stone
pitch retaining wall (which they are highly vulnerable to in lateral loading) were observed. Where
designed for such these offer a form of load pick up mechanism and provide resistance to the backfill
and continuous hydrostatic pressure.
___________________________________________________________________________________________________________
Registered Office:
Section 59 Lot 20, Corner Koani & Gabaka Street, Gordons
P. O. Box 892, Port Moresby, NCD, Papua New Guinea |
P (675) 323 7030 | F (675) 323 9712 | M (675) 7686 3354
Email :ljstocks@stockspartners.com.pg
12
RECOMMENDATIONS
As per conclusions and discussions above, Stocks & Partners would like to recommend the following
remedial works to be carried out accordingly by a nominated contractor in stages as presented below:
Concrete Works
To counteract the high likelihood of corrosion of steel, all RC columns shall be coated with an
additional protective layer of 50mm of grout constituting of high strength non-shrinkage grout
or similar approved product procured accordingly by contractor and installed in accordance to
the manufacturers specification. This shall be applied to the RC column reinforcement cover
over its full height (i.e. from foundation level to column top at roof).
END OF REPORT
___________________________________________________________________________________________________________
Registered Office:
Section 59 Lot 20, Corner Koani & Gabaka Street, Gordons
P. O. Box 892, Port Moresby, NCD, Papua New Guinea |
P (675) 323 7030 | F (675) 323 9712 | M (675) 7686 3354
Email :ljstocks@stockspartners.com.pg
13
BIBLIOGRAPHY
Faulkes, K. A, Hall, A. S, Rangan, B. V & Warner, R. F (1998). Concrete Structures. South Melbourne,
Australia: Addison Wesley Longman Australia Pty. Limited.
Starzewski, K & Wilun, Z. (1975). Soil Mechanics in Foundations Engineering, 2nd Edition, Volume 2
-Theory& Practice. 450 Edgware Road, London: Surrey University Press.
___________________________________________________________________________________________________________
Registered Office:
Section 59 Lot 20, Corner Koani & Gabaka Street, Gordons
P. O. Box 892, Port Moresby, NCD, Papua New Guinea |
P (675) 323 7030 | F (675) 323 9712 | M (675) 7686 3354
Email :ljstocks@stockspartners.com.pg
14
PHOTOS
Photo 1: DCP Test Point 4 carried out at excavated depth of over 2600mm in which hard rock was encountered at a depth of
650mm - 700mm. Bulging outline of rocks & boulders visible at bottom center portion of photo.
Photo 2: Air pockets observed throughout excavation depths of all inspection pits
___________________________________________________________________________________________________________
Registered Office:
Section 59 Lot 20, Corner Koani & Gabaka Street, Gordons
P. O. Box 892, Port Moresby, NCD, Papua New Guinea |
P (675) 323 7030 | F (675) 323 9712 | M (675) 7686 3354
Email :ljstocks@stockspartners.com.pg
15
Photo 4: Absence of cracks on masonry blockwall clearly indicates no sign of swaying of building.
___________________________________________________________________________________________________________
Registered Office:
Section 59 Lot 20, Corner Koani & Gabaka Street, Gordons
P. O. Box 892, Port Moresby, NCD, Papua New Guinea |
P (675) 323 7030 | F (675) 323 9712 | M (675) 7686 3354
Email :ljstocks@stockspartners.com.pg