Escolar Documentos
Profissional Documentos
Cultura Documentos
: 2131600023
Jebel Ali Power Station K Phase III
Volume II
(GENERAL PROJECT REQUIREMENTS)
Part G05.4
Civil Works
April 2016
Date
Originator
11/04/2016 Mlderink
Checker
Schultz
Approver
Rner
Description
Issued for Tender
General ....................................................................................................................... 7
1.1
1.2
1.3
1.3.1
1.3.2
1.3.3
1.3.4
Other Standards.......................................................................................................... 9
1.4
1.4.1
1.4.2
1.4.3
Tolerances................................................................................................................. 14
1.4.4
1.4.5
1.5
1.5.1
General ..................................................................................................................... 17
1.5.2
1.5.3
NA ............................................................................................................................. 18
1.5.4
Samples..................................................................................................................... 18
1.5.5
2.1
2.2
3.1
3.2
4.1
QA/QC ....................................................................................................................... 22
5.1
5.2
5.3
5.3.1
5.3.2
5.3.3
5.4
Safety Precaution...................................................................................................... 25
5.4.2
5.4.3
5.4.4
Backfilling .................................................................................................................. 26
5.4.5
5.4.6
5.4.7
5.4.8
5.4.9
5.5
5.5.1
General ..................................................................................................................... 28
5.5.2
6.1
6.2
6.2.1
6.3
6.3.1
6.4
6.4.1
Program .................................................................................................................... 32
6.4.2
Qualification ............................................................................................................. 32
6.4.3
Staking-Out Tolerances............................................................................................. 32
6.4.4
Cut-off ....................................................................................................................... 32
6.4.5
6.4.6
Concreting................................................................................................................. 33
6.5
QA/QC ....................................................................................................................... 33
6.5.1
6.5.2
7.1
7.2
7.3
7.4
7.4.1
General Requirements.............................................................................................. 36
7.5
7.6
7.7
7.8
7.8.1
7.8.2
Cement ..................................................................................................................... 39
7.8.4
Water ........................................................................................................................ 39
7.8.5
Aggregates ................................................................................................................ 39
7.8.6
7.8.7
7.8.8
7.8.9
Concreting Operations.............................................................................................. 44
7.9
QA/QC ....................................................................................................................... 47
7.9.1
Trial Mixes................................................................................................................. 47
7.9.2
7.9.3
7.9.4
7.9.5
Grouts ....................................................................................................................... 52
10
10.1
10.1.1
10.1.2
Masonry .................................................................................................................... 53
10.1.3
Plaster ....................................................................................................................... 54
10.2
Execution .................................................................................................................. 55
11
11.1
11.2
11.2.1
General ..................................................................................................................... 56
11.3
Materials ................................................................................................................... 57
11.3.1
General ..................................................................................................................... 57
11.3.2
11.3.3
Galvanizing................................................................................................................ 58
11.4
11.4.1
Tolerances................................................................................................................. 58
11.4.2
Connections .............................................................................................................. 58
11.4.3
Painting ..................................................................................................................... 61
11.4.4
Erection ..................................................................................................................... 61
11.5
QA/QC ....................................................................................................................... 63
12
12.1
General ..................................................................................................................... 64
12.2
Design /Engineering.................................................................................................. 64
12.2.1
12.2.2
Chequered Plates...................................................................................................... 64
12.2.4
12.2.5
Ladders ..................................................................................................................... 65
12.2.6
13
Waterproofing .......................................................................................................... 67
13.1
General ..................................................................................................................... 67
13.2
13.3
14
14.1
14.2
Warranties ................................................................................................................ 69
14.3
14.4
14.4.1
14.4.2
14.4.3
14.5
14.5.1
Sunshades ................................................................................................................. 73
14.6
14.6.1
14.6.2
Fasteners .................................................................................................................. 74
15
15.1
15.1.1
General ..................................................................................................................... 76
15.1.2
15.1.3
15.1.4
15.1.5
15.1.6
16
16.1.1
16.1.2
Ventilation louvers.................................................................................................... 80
17
Glazing ...................................................................................................................... 81
17.1
17.1.1
17.2
17.2.1
General ..................................................................................................................... 81
17.2.2
17.2.3
17.2.4
QA/QC ....................................................................................................................... 82
18.1
18.2
Material .................................................................................................................... 83
18.3
19
Flooring ..................................................................................................................... 84
19.1
19.2
19.2.1
19.2.2
19.3
19.3.1
General ..................................................................................................................... 86
19.3.2
20
Tiling ......................................................................................................................... 87
20.1
20.1.1
20.1.2
20.2
20.2.1
20.2.2
Placing....................................................................................................................... 88
21
Painting ..................................................................................................................... 90
22
22.1
General ..................................................................................................................... 91
22.2
Materials ................................................................................................................... 91
22.2.1
General Requirements.............................................................................................. 91
22.2.2
22.3
22.3.1
General ..................................................................................................................... 93
22.3.2
22.3.3
22.3.4
22.3.5
23
23.1
23.2
Sub-grade .................................................................................................................. 95
23.3
Sub-Base ................................................................................................................... 95
23.4
23.5
23.5.1
23.5.2
23.6
23.8
23.9
23.10
23.10.1
23.10.2
23.10.3
23.11
23.11.1
23.12
23.13
23.14
23.15
23.16
23.17
General
The Tenderers are requested to propose high energy efficiency buildings and shall propose energy
saving constructions for slabs, walls, windows, doors and roofs according to local or international
standards whichever is more stringent and with special reference to Green Buildings Regulations and
Specifications. The requirements stated herein are to be followed together with all the relevant detailed specifications in civil-, electrical-, mechanical- and I&C-disciplines.
1.1
This specification covers the general technical requirements of civil works. The design and execution
shall be state of the art, functional and complete in all parts.
1.2
Civil Design/Engineering
The design and engineering shall be state of the art in accordance with all relevant codes and standards, functional and complete in all aspects. .
Before starting the design works, the Contractor shall submit to the Employer/Engineer for review the
project design manual containing design data, and detailed design criteria for all civil works. Design
works shall commence only after review of the project design manual by the Employer/Engineer.
The reinforced concrete design and working drawings of main structures (concrete buildings and steel
structures including shop drawings and connection details) shall be submitted by the Contractor for
approval by the Employer/Engineer. Soft copies of all designs and structural calculations shall be submitted along with all models and diagrams.
All main routings (culverts /tunnels /trenches /duct banks /ducts) shall be submitted by the Contractor
for approval by the Employer/Engineer.
1.3
The design, all materials, civil works constructions and installations, tests and investigations , must be
as a minimum conform to the latest edition of the following Codes and Standards (listed in alphabetical
order) as far as these standards, codes and regulations are available in an English language edition.
1.3.1
American Standards:
(ANSI)
(ASTM)
(ACI)
(AISC)
(AISI)
(AWWA)
(UBC)
(AWS)
(AASHTO)
(NPC)
(ASCE)
(PCA)
(NCMA)
(OSHA)
1.3.2
European Standards:
European Norm
(EN)
British Standards
British Standard
(BS)
(BS CP)
German Standards
Deutsches Institut fr Normung eV
(DIN)
(VDI)
1.3.3
(CIRIA)
1.3.4
Other Standards
Other internationally accepted standards which ensure a quality equivalent to or higher than the
standards listed above may be used for specific works, but only if these are submitted in an English
language edition and approved by Employer/Engineer.
Japanese Industrial Standards
(JIS)
(CUR)
1.4
1.4.1
The design of all structures shall be such that differential and total settlements or other movements
shall not exceed the limits given by specifications or with the applicable codes, and standards and full
provision shall be made for all expansion and other joints.
Safety against uplift has to be guaranteed during all execution stages, especially when ground water
lowering is terminated. The factor of safety (FoS) against uplift shall be not less than 1.2.
Structural members subjected to flexure shall be designed to have adequate stiffness to limit deflections or any deformations that affect strength or serviceability of a structure adversely as per the specified criteria or the limits prescribed by the machinery manufacturers (whichever is less).
The superstructures and foundations subjected to vibrations (the primary source of these vibrations
being the unbalanced forces generated by rotating or reciprocating equipment) shall be designed such
that vibrations will be neither intolerable nor troublesome to personnel, and will not cause damage to
the machine or structure.
The natural frequency of the whole of the superstructures and foundations or parts thereof and all
structures adjacent thereto shall not coincide with the operating frequency of the vibrating plant. The
differences between frequencies and the dynamic analysis of the superstructures and foundations
shall be in accordance with the relevant design standard.
The dimensions of all the buildings shall be such as to provide adequate space for the safe installation
and proper operation, maintenance and repair of all plant and equipment.
Throughout the works all floor slabs above rooms containing electrical equipment shall be watertight.
No drain pipes or water pipes are permitted to pass through these rooms. If this cannot be avoided
civil design shall consider double slab with enough accessible space in between.
1.4.2
The following design loads shall be considered for the design of buildings and structures:
Area
Live load for building roofs
(A/C equipment and foundations to be considered additionally)
Sloping Roof-sheet metal construction
Operation Floors- Ground Floor
Operation Floors- Upper Floor
Switchgear Rooms, etc.
Battery Rooms
Workshop Floors- Ground Floor
Workshop Floors- Upper Floor
Light platforms, Walkways, Stairways :
Concrete
Steel
Additional dead load for suspended ceiling, pipes, AC system, etc.
Traffic Loads
Roads and pavements, gutters
Underground water tanks, septic tanks, etc. covered by road areas
Value
2.5
Unit
kN/m2
1.5
kN/m2
35.0
kN/m2
17.5
kN/m2
10.0
kN/m2
15.0
kN/m2
25.0
kN/m2
15.0
kN/m2
5.0
kN/m2
5.0
kN/m2
1.0
kN/m2
SLW 60, DIN 1072
SLW 60, DIN 1072
SLW 60, DIN 1072
Areas designated for different loadings on the same floor shall be clearly and permanently marked.
Exposure Category
=D
Importance factor, I
= 1.15
1.4.3
Tolerances
Deflection
Simple / continuous beam
1/300 L
1/300 L
1/1000 L
1/500 L
1/300 L
1/300 L
LL : live loads
Remarks
Cantilever
beam
1/250 L
1/200 L
1/350 L
DL + LL + W
DL + LL + W
DL + LL
1.4.4
1.4.4.1 General
Due to very severe climatic conditions in the project area, special measures are necessary to protect
the different materials from corrosion. In this context the following materials need protection
measures:
Outside protection by tanking membranes and protection boards, with membranes extending 15 cm above ground level.
Outside protection and coatings as specified in Tender Document Volume II, Part G05.5 Corrosion Protection and Painting
1.4.5
The following steel structures shall be hot dip galvanized and painted according to Tender Document
Volume II, Part G05.5 Corrosion Protection and Painting:
Steel structures and structural members inside buildings /open air arrangement
All secondary steels (pipe racks, platforms, stairs, railings, ladders) and equipment supports/skids
All bolts /nuts (if not of stainless steel). Embedded parts of bolts/anchors inside concrete need
not to be painted.
All anchor bolt s and inserts shall have a concrete cover of at least 100 mm.
610 g/m
460 g/m
335 g/m
Note:
Small areas of galvanised coating damaged by welding, cutting, or during transport shall be repaired
by applying at least two coats of zinc-rich paint.
1.5
1.5.1
General
Only approved construction materials shall be used. Material that has not been approved by Employer/Engineer must be removed and disposed of at the Contractors own expense. For this purpose,
Contractor shall establish at site a quality control procedure for material delivery and notify Employer/Engineer for inspections and witnessing of sampling for testing. All sampling works shall be
done by the third party specialist/technician. All tests reports along with analysing of results and comparison with the specified/standards criteria shall be submitted as soon as possible results are available.
1.5.2
Only new /unused materials shall be used and no recycled material is allowed. All materials must be
proofed and tested by an independent approved third party firm accredited by DM with design certification from the manufacturer. All proposed materials intended to be used for construction shall have
a record of previous approvals (mainly from local authorities) and usage in similar projects and under
the same environmental and harsh weather conditions. Services of testing shall be extended to earth
works/soil properties, concrete, steel and other materials whenever called by Employer/Engineer on
the account of the Contractor.
For testing of these works, sampling, handling, transport to the laboratory, reporting and analysing of
the test results shall be by Third Party specialized laboratories. The reporting and analyzing of the test
results shall be submitted to the Employer/Engineer.
1.5.3
NA
1.5.4
Samples
The Contractor shall provide samples of all materials, embedded parts and installations, for the Employer/Engineers review before start of construction. Three samples of each main construction material shall be submitted for Employer/Engineer selection.
All approved samples shall be collected and stored in a sample room and all approvals shall be consecutively recorded.
1.5.5
2.1
Refer to Tender Document Volume I, Part G03 General Project Requirements. Due to the limited
space on the plot area, it is not allowed to use it for long term storage of any equipment and/or material.
Areas allocated by Employer, for the site installations shall be utilized in an optimized manner for offices workshops and stores. All site offices shall be built as multi storey buildings.
The Contractor, if requiring additional area, shall look for sufficient lay down areas, storage space and
facilities, labour camps, parking places off site. The Contractor shall be responsible for obtaining all No
Objection Certificates (NOC) of various authorities without additional cost borne by the Employer
All construction areas, storage areas and any other temporary site installations shall be surrounded by
temporary fences as per local authorities requirements. All underground services crossing the access
roads to the construction areas shall be protected by Contractor by means and structures approved by
Employer/Engineer.
2.2
All works for site installation must be executed in accordance with latest Health, Safety and Environmental rules (HSE)
Basic cleaning includes all floors, walls, ceilings, built-in fittings and equipment, including the furnishings. The basic cleaning operation must result in a degree of cleanness which permits the fully
equipped buildings and rooms and associated outdoor installations and secured surfaces to be taken
over without complaint. The Contractor shall be responsible that all cleaned areas and facilities will be
conserved at a complete clean stage till to the final handing over to the Employer.
Site Supervision/Survey/Investigations
3.1
Site Supervision:
The Contractor shall establish at Site a team of experienced civil engineers dedicated for review and
checking of civil design and drawings only. Team leader shall be an Engineer from home office organisation of the Contractor with minimum 10 years experience in the field and shall be responsible for
the correctness of design and its conformity with the specifications. Documents and drawings shall be
forwarded to the Employer/Engineer for his approval only after being reviewed and signed by the assigned team leader. The same team shall be also capable to make minor changes and corrections in
design drawings during the construction stage.
Contractor shall establish another team of experienced civil engineers dedicated for checking of site
works of civil sub-contractor. As above, team leader shall be an Engineer from home office organisation
of the Contractor with minimum 10 years experience in the field and shall be responsible for the conformity of the sub-contractors works with the design and the specifications and for the quality of
workmanship. The Employer/Engineer shall be called for inspection only after the assigned team
leader confirms his checking by signing in the inspection sheets.
Prior to release for pouring of concrete for floors, walls and roof of buildings, structures and foundations at site, each sub-contractor is responsible for checking of formwork and reinforcement as well as
his latest requirement concerning the location/projection of anchor bolts and embedded items, the
location and size of equipment pads and foundations, the location and slope of piping, conduits, cables,
wiring and accessories, location and size of floor, wall and roof penetrations. After checking for correctness of the concerned disciplinary Contractor shall sign a "Free for Casting Certificate" which permits the Civil sub-contractor to proceed with casting of concrete and/or constructing after release of
the same by the Employer/Engineer.
The Contractor shall submit individual inspection sheets to the Employer/Engineer 24 hours prior to
the commencement of the works such as excavation, backfilling, concreting and structural steel erection etc., Works shall commence only after Employer/Engineers approval the inspection sheet. Employer/Engineers approval shall, however, not relieve the Contractor of any of his obligations under
this Contract. Form of the inspection sheet shall be proposed by the Contractor and approved by the
Employer/Engineer.
It is to be noted that should the Contractor repeatedly fail to notify or inform the Employer/Engineer
of inspections, sampling or testing (if any) then the Employer/Engineer may carry out independent
checks without informing the Contractor and reject parts of the works should the results of such inspection or testing merit. As far as is practicable the Employer/Engineer shall have free access to the
site, fabrication areas and suppliers work at all times without notice. Should he discover unsatisfactory
work then he will invite a formal joint inspection. Either after such an inspection or if the Contractor
declines the invitation the Employer/Engineer shall issue instructions with regard to the faults and
their reparation.
The Employer/Engineer may select the sampling point at no cost. The Employer/Engineer may instruct
tests at no cost provided either the overall frequency governed by the specification is not exceeded
and the notification given to the Contractor is equal to that currently being provided by the Contractor
3.2
To enable the Contractor to carry out his survey and construction work, he will be furnished by the
Employer with the bench marks showing their description, number, co-ordinates and levels to an extent necessary for the work. These information are preliminary and the Contractor is responsible to
check, verify and correct, if required, these data before starting his work and he must forward a written
notification concerning the discrepancies to the Employer/Engineer and obtain his approval.
All surveys required for construction of the works shall be performed by the Contractor as construction
work proceeds. Survey points distributed at different locations established by contractor shall be durable and suitably protected to avoid any damage through out the construction period.
Levelling bolts according to DIN 18708 shall be installed by contractor for the RCC foundations and
structures immediately after construction and protected from damages till handing over.
In all buildings and major foundations at least 4 levelling bolts shall be installed at 1.00 m above floor
surface.
The position and the total number of surveying points shall be finally decided by the Employer/Engineer in co-operation with the Contractor, on the basis of the settlement report.
Measurements of all levelling bolts are to be executed:
This section applies to the methods and techniques of ground water control. All costs for ground water
control for keeping the construction pits and areas at least 500 mm below formation level dry shall be
included in the lump sum.
The method and technique shall be based on the British Standard BS.8004 or any equivalent agreed
with the Employer/Engineer. NOC shall be obtained from Dubai Municipality prior to installation of
dewatering system.
The scope of supply includes the installation of all equipment, plants, pipes, machinery and its removal
after completion including operation and maintenance of the equipment during the construction period. All equipment, instruments, machinery, tools, pipelines, required for execution of the water control shall be in good repair and shall be kept in good working condition throughout the operation period.
Where necessary, cofferdams, sheet piles, pump sumps, equipment and channels, troughs, inlet gutters, pipes and any other works required for the water control and discharge shall be part of the scope
of supply. The dewatering system shall be designed and installed in such a way that alteration and
extensions can be made at any time throughout the operating time, if necessary. Reserve units shall
be kept ready for service when failure of any of the installed units occurs.
The Contractor shall submit to the Employer/Engineer, the detailed method of the envisaged pumping
system for dewatering, the pump capacity and the standby reserve units.
The Contractor must ensure that any dewatering works will not cause any interference to his own work
and to those of other Contractors working elsewhere on site or at structures under construction or
existing structures and facilities. Any damage occurring during the above mentioned period shall then
be made good by the Contractor at his own expense.
Routing and location of water discharge lines shall be submitted to the relevant authorities and to the
Employer/Engineers review. The disposal of water shall be in accordance to the local environmental
laws and regulations. If applicable according to the local laws and regulations the pumped water has
to be treated accordingly before disposal.
The Contractor shall maintain ready-for-service and regularly clean all dewatering equipment and accessories and shall keep all access clear so that they can safely be used without risk of accident. Any
requirements made by the Employer/Engineer in this matter shall be carried out immediately.
4.1
QA/QC
The Contractor shall keep records of all data of importance occurring during operation of the water
control system. The records shall be submitted to the Employer/Engineer for information and checking
every working day. For that purpose, the lowering of the water table shall be controlled by piezometers. The numbers and position of them shall be submitted to the Employer/Engineer's for approval.
The Contractor shall provide and maintain these piezometers at his own expenses during the dewatering works or as long as the Employer/Engineer requires it.
5.1
The exiting ground level of the site area is about + 3, 00 m DMD and plot area is partially covered with
trees that shall be treated as per Tender Document Volume III, Part P20 Civil Works. Due to the high
ground water level the site area shall be backfilled up to a level of + 4.00 m DMD by selected fill material with properties specified here down and approved by Employer/Engineer. Elevated plant area shall
be coordinated with surrounding structures/facilities/services/roads and shall be well designed for
smooth transition at road connections. Soil embankments shall be protected against soil movement
by suitable stone pitching of size at least 200 mm laid on a well prepared and compacted surface and
above a 100 mm thick concrete blinding layer. Joints of stones shall be filled and grouted with blended
cement and additives that will guarantee a durable construction with minimum maintenance. The final
finished ground level of buildings shall be +4.20 m DMD.
This work consists of clearing, grubbing and stripping the area of the work of stumps, bushes, roots,
down timber, rotten wood, rubbish, debris, humus, swamp material and any other vegetation or unacceptable materials as ordered by the Employer/Engineer.
Disposal of excess soil and unusable waste materials shall be the responsibility of the Contractor. The
Contractor shall transport the materials to a suitable dumping area and obtain the necessary approval
from the municipal authorities at his own expense. Stacking of all materials shall follow the Green
Buildings Regulations regarding segregation
Burning and blowing off of any material and use of explosives is not permitted.
Prior to start clearing or filing works, contractor shall locate any existing underground services and
protect or relocate as per Employer/Engineer approval at his own cost.
5.2
The Contractor shall satisfy himself as to the ground conditions on the site including the nature of the
strata to be excavated, obstructions, possibilities of flooding and such like and shall allow for all provisions necessary to carry out the work in the most suitable manner when submitting his tender.
Generally all buildings and structures must be founded on bearing strata which means that all excavation work for foundations shall meet the requirements of structural analysis based on the results obtained from the soil investigation and of the available information and instruction given in writing by
the Employer/Engineer.
Excavation shall be done to the required dimensions including required working spaces and shall be
finished according to the specified lines and slopes. All necessary precautions shall be taken to cause
the minimum possible alteration or disturbance to the material lying under and adjacent to the excavation final lines.
5.3
The fill materials used are to be examined and approved. Excavated materials can be used if they fulfil
the requirements.
5.3.1
Select Fill
5.3.2
Ordinary Fill
5.3.3
Special fill
Special fill material shall be gravel or crushed rock (for other properties see under 'Select fill').
The intention is to use special fill e.g. as sub-base material for tanks and roads.
5.4
The works shall be excavated either by hand or by use of excavating plant and tools acceptable to the
Employer/Engineer. Method statement for earth works shall be submitted for approval by Employer/Engineer.
5.4.1
Safety Precaution
5.4.2
The construction and lay down areas are limited. Excavated material from the Works selected by the
Employer/Engineer for re-use shall be placed immediately in its final position, if possible, or otherwise
may be stockpiled or deposited on Site or carted away as directed by the Employer/Engineer. It is the
responsibility of the Contractor to determine the location of an off-site disposal area. Stockpiling is
accepted for short periods only and in any case it shall not obstruct the construction and progress of
site works.
The Contractor shall not have the right either to additional payment or to claim because of work involved in stockpiling materials, re-use of for carting to the waste disposal areas. Necessary approvals
shall be obtained from concerned authorities for waste disposal areas.
5.4.3
Preparation of Foundations
For all types of foundations and immediately after excavation the formation level of foundations shall
compacted up to 98% (degree of compaction) , and then protected by means of a lean concrete layer,
7.5 cm in thickness over a layer of plastic sheet. No concrete is to be poured until formation level is
inspected and agreed by the Employer/Engineer. Plate load test shall be conducted at site under areas
agreed by Employer/Engineer in order to verify the parameters considered in design.
For all foundation works, formation level shall be at least 1.0m below the finished ground level.
5.4.4
Backfilling
Foundations and structures shall be backfilled as shown on the drawings with agreed material compacted in layers by suitable equipment until optimum stability has been obtained to the satisfaction of
the Employer/Engineer. Compacting shall be carried out with special care by means of pneumatic or
mechanical rollers or other compactors of a type previously agreed by the Employer/Engineer.
Density requirements shall be as follows by tests per modified AASHTOT-180 Method D, at optimum
moisture content
Embankment - 95%
- 98%
- 98%
Backfilling of foundation work with agreed materials shall be carried out only after foundations have
been inspected by the Employer/Engineer.
5.4.5
Soil Replacement
The material to be used for replacement of soil shall not contain soluble or swelling components such
as clays, or organic matters. Sand gravel mixtures of agreed grain size distribution shall be used in
exchange.
The fill material shall be placed in horizontal layers of no more than 25 cm thickness. The fill moisture
content shall be controlled and adjusted in order to achieve a maximum of compaction. Fresh water
shall be used for watering of soils. The foregoing shall be confirmed by Tests mentioned in Tender
Document Volume III, Part G05.6 Inspection and Testing. One Modified AASHTO or Proctor and three
(3) density tests shall be made at every second fill layer prior to continuation of filling work. The testing
location will be indicated by the Employer/Engineer. The results of the tests shall be made available to
the Employer/Engineer within 24 hours of the tests. Filling work may be continued in case all tests
performed show satisfactory results.
5.4.6
Pipe beds shall be constructed to guarantee the uniform transmission of loads. The bearing section for
supported profiles shall cover at least an arc of 90.
Pipes shall be bedded in an earth foundation of uniform density and carefully shaped by means of a
template supported at the desired grade, to fit the lower part of the pipe exterior.
Where a firm foundation is not possible at the grade established due to soft, spongy or other unstable
soil, all such unstable soil under the pipe and for a width of at least one diameter on each side of the
pipe shall be removed and replaced with suitable selected materials as agreed by the Employer/Engineer, properly compacted to provide adequate support for the pipe.
5.4.7
During construction the Contractor shall provide all protection for existing utilities and services as may
be required by his construction operations. Permanent protection of certain items shall be as included
under other clauses or as instructed by the Employer/Engineer.
In addition to the requirements as specified, herein the Contractor shall comply with the following
requirements.
Use all necessary precautionary and protective measures required to maintain existing utilities, services and appurtenances that must be kept in operation. In particular the Contractor shall take adequate measures to prevent undermining of utilities and services presently in services.
Protect existing or new utilities and services where required by the Contractors operations and/or as
directed by the Employer/Engineer. The Contractor shall be responsible for bracing and supporting
utilities and services to prevent settlement, displacement or damage.
5.4.8
Loose or soft soils in the natural or existing stage unsuitable for foundation purposes can be improved
by deep vibratory techniques in order o maintain the settlement of structures within the allowable
limits. The technique by vibro compaction or vibro displacement, material and design/details of the
deep vibration are subjected to Employer/Engineer approval. All works shall be executed by an approved specialist in this field of works. Contractor is responsible to prove that those works does not
affect the operating power plant in any aspect.
By any approved technique, all layers between foundation level and bearing soil are to be compacted
to a relative density of at least 80% and prepared for an admissible soil pressure of at least 250 kN/m2.
And settlement of structure/foundation is limited to 1.5 cm.
The final foundation level shall be covered with at least 50 cm crushed stone or gravel fill and compacted to 95% relative density with a 10 ton vibrating roller (at least two layers performing 6 passes);
All water used in construction and soil improvement shall be fresh water.
5.4.9
Dust Control
The Contractor shall use all means necessary to control dust on roads, construction areas and borrow
pits. Surfaces shall be regularly on daily basis and when required, watered to prevent dust becoming a
nuisance for the public and have impact on the nearby installations and services or interfering with the
proper execution of the works. Waste oil is not permitted for the use as dust control. Temporary roads
and access ways may be covered with suitable gatch materials to reduce the development of dust.
Sand and dust (especially cement dust) shall be contained with in the construction site. Method statement for dust control shall be approved by Employer/Engineer.
5.5
5.5.1
General
The Control of working and tests operations shall be carried out by the Contractor in the presence of
the Employer or Engineer.
The Contractor shall prepare sheets for statistical analysis of the field and laboratory tests, and shall
submit the sheets to the Employer/Engineer for approval. Controlling will consist of field and laboratory tests, such as:
One (1) test analyzing the chemical ingredients of the water used for performance of the work
and the soil.
One (1) test for bearing capacity of soil for static load as per ASTM D 1194 - 57.
Three (3) tests for density of soil in place of sandcone method for each second layer of "Backfilling
and/or replacement of material and/or roadwork" are required as per ASTM D 1556 - 64.
5.5.2
Before starting the compaction works, the Contractor has to prove by tests whether he is able to improve the underground to the above requirements. The test program and vibro pattern is to be proposed by the Contractor and to be agreed by the Employer/Engineer, and shall contain a trial compaction, dutch cone tests (before and after the treatment) and big scale load tests comprising at least 4
compaction points covered by a concrete footing.
By the vibro compaction or vibro replacement, the soil is improved to meet the following Dutch cone
resistance requirements below the foundation level (in addition to other requirements):
from 0 to 3 metres:
from 3 to 5 metres:
10 MN/m2
from 5 to 7 metres:
15 MN/m2
beyond 7:
20 MN/m2
The resistance for the first 3 m shall be 10 MN/m2, when the tests are done from a level more than 2
m above the foundation level. The results are judged to be successful if not more than 10% of the
measured values are below the above requirements. The tests will be performed in the most unfavourable location of a probe group. The number of sounding tests shall be at least 5 for one structure.
Big scale plate load tests shall be performed, for quality control purposes, at least two for each structure . These tests shall cover an area of 4 compaction points/stone columns in addition to the spacing
(in both directions) and shall be loaded to twice the permissible soil pressure.
All test results shall be compiled in test reports, where values obtained are compared with requested
values (in diagrams as far as possible, Es- values derived via settlement calculation from test results).
A method statement and quality control program shall be prepared by the Contractor and agreed by
the Employer/Engineer prior to start of vibro works containing at least the above requirements and
information about the following:
Description of large scale load test including load steps/waiting time
Data recording of probe number and depth, date and time of execution, installation time for every
probe, gravel consumption (if applicable), power consumption versus time or depth (automatically
recorded) etc.
Piling Works
These specifications cover the requirements for the materials, the installation and the realization of
bored cast-in-place concrete piles and driven cast in place piles with grouting at the base. The scope
shall include the preparatory works for piling, design, construction works, testing, pile head cutting,
pile head treatment (waterproofing, grouting), cleaning, etc.
6.1
Documents to Be Submitted
The following documents shall be submitted by the Contractor to the Employer/Engineer in due time
and are to be approved before starting the piling works:
Design calculations of the proposed type of piles and detailed drawings including the typical reinforcing
details.
Design of the concrete mix as per Clause 7 specified herein.
Method statement for preparation, construction and testing.
Detailed description of the plant and equipment along with the pre-qualifications of the piling works
subcontractor.
Piles record book and concrete control record.
6.2
The piling works and design shall be in accordance with the latest editions of internationally accepted
standards. Copies of codes and standards used for design and construction shall be furnished by contractor if requested by Employer/Engineer.
Two (2) types of piles foundation can be proposed and quoted by the Contractor: cast-in place driven
piles or cast-in-place bored piles. Grouting of the rock below the piles shall be considered if dictated
by soil conditions. The pile bases shall be embedded in the rock level, determined by the soil investigations made at the beginning of the works by the Contractor. The net vertical pile capacity computed
from the soil investigation report is used to determine the maximum test load in case of piles testing.
The net compressive stress within concrete shall not exceed 5 MPa. The net tensile stress within steel
reinforcement shall not exceed the allowable values furnished in the standards and norms.
6.2.1
Bored cast in place piles are drilled up to the depth indicated by the pile drawing submitted by the
Contractor and agreed by the Employer/Engineer. For each pile, the Contractor draws up the geotechnical profile of the drilling with description of the strata and samples taken for each stratum as mentioned in the piling record item of these specifications. A representative sample from each stratum will
be kept in tight packing until the end of the works.
A suitable type of drilling equipment shall be provided in order to penetrate obstacles (e.g. boulders)
which may be met during the execution of the piles.
Jebel Ali Power Station K Phase III
RFx No.:
2131600023
Page:
30/105
Date:
April 2016
6.3
6.3.1
The piles shall be longitudinally reinforced on the whole length with high steel yield epoxy coated bars.
The minimum ratio of longitudinal bars is 0.8% of the pile cross section, with a minimum of 6 bars not
less than 12 mm in diameter. The minimum spacing between longitudinal bars is 15 cm (DIN 1045).
Helical binding shall be used with a minimum diameter of 10 mm and a maximum pitch of 15 cm.
Reinforcing cage shall be stable and bars properly tied with the helical stirrup at all joints with plastic
coated wires. It shall be perfectly centred within the borehole by the aid of concrete spacers distributed every 1000 mm centres along the vertical bars and has same properties as for the pile. The
concrete cover to reinforcement shall be not less than 75 mm and not more than 100 mm. The reinforcement cage is put into the hole in only one operation. The cage must remain stable during concreting and removal of the temporary casing. The handling of the cage during loading, unloading and
installation within the holes has to be made with care in order to reduce the deformation and to avoid
the breaking of the binding wires. Cages shall be held firmly in position by the aid of rigid hangers.
Proprietary PVC pipes shall be used to protect part of main bars that will be anchored inside the foundations/pile caps. Connections for main rebar splicing area shall be properly design to avoid settlement
during concrete pouring operation.
Concrete mix design for piling works shall be submitted for review by the Employer/Engineer.
The concrete shall be as per Clause 7. The water/cement ratio shall not exceed 0.40.
6.4.1
Program
The program of piling work is to be submitted for approval by Employer/Engineer four weeks before
the start of the piling works. Sequence of piling shall be stated including adequate notice of his intention to work outside normal hours and at weekends. Daily reports shall be submitted showing the
actual accumulated progress and the plan for next day.
6.4.2
Qualification
The piles installation shall be undertaken using proven techniques and equipment and shall be implemented by specialist personnel who have extensive experience in carrying out such work. The Contractor shall provide qualified personnel i.e. a foreman for every piling crew, who shall always be present
during the works, as well as a professional engineer, well experienced in piling works, for supervision.
6.4.3
Staking-Out Tolerances
The maximum allowed deviation of the piles centre from the theoretical location shown on the setting
out drawing is 50 mm in any direction. The maximum permitted deviation of the completed pile from
the vertical is 20 mm per meter (2.0%). Contractor shall establish the reference bench marks, grids and
coordinates which shall be used for inspection and setting of piles.
6.4.4
Cut-off
6.4.5
Working Platform
The areas where piling operations are to be carried out is to be levelled and kept clear of water to
provide a dry stable working platform for the plant and equipment operation which shall be 1 to 1.5
metres above the designed cut off level.
After completion of the piling works the project site is to be cleaned and all excavated material due to
these works is to be removed by the Contractor.
6.4.6
Concreting
Before starting the concreting, the bottom of the hole has to be cleaned. All loose or disturbed soil will
be removed from the base of the hole. This operation is to be executed immediately before starting
the concreting. It means after the introduction of the steel reinforcement cage and not only at the end
of the drilling.
All concrete is to be placed by tremie pipe and concrete pump; the starting of the concreting by this
method has to be particularly well executed. The good quality of concrete at the base of the pile is of
main concern with this operation. Concrete operation shall stop only after visually seeing a good quality of fresh concrete at platform level.
After concreting of each pile, the concrete volume will be checked in relation with the theoretical borehole volume; for this purpose, a concrete-curve is drawn up for each pile, truck by truck. A complete
concrete curve is established from the measurements of concrete consumption every meter on the
length of the pile for 1 pile each 50 piles. The concrete-curves (truck by truck and meter by meter)
have to be daily provided to the Employer/Engineer and joined to the piling record.
If the concrete consumption is not normal (under-volumes or more than 30% of over-volumes), special
procedures will be taken by the Contractor in agreement with the Employer/Engineer.
The length of the tremie pipe is equal to the length of the pile. Before concreting, the pipe will reach
the bottom of the hole and is then raised in 15 cm steps. The pipe must never be located less than 1.5
meter below the level of workable concrete within the pipe.
At all times, a sufficient quantity of workable concrete shall be maintained within the pipe to ensure
that the pressure from it exceeds that of the water.
During the extraction, the base of temporary casing must be located at least 1 meter below the level
of fresh concrete and workable concrete shall be added to cover the drop due to casing removal. Temporary casing shall be removed by vibration, not disturbing the consistency of the concrete.
For each group of 5 piles, 6 representative cube samples will at least be taken, 3 will be tested after 28
days, and the others will be stored for other tests to be specified by the Employer/Engineer such as
durability and chloride/sulphate contents of supplied concrete.
All costs relative to these control tests are under the scope of the Contractor
6.5
QA/QC
6.5.1
Piling Record
For each pile, a piling record book giving the main checked values during execution shall be drawn up
and updated by the Contractor with all the work hazards and incidents. That record book shall be submitted daily for review by the Employer/Engineer as the execution proceeds.
This record book shall include for each pile details on:
Location, reference number (corresponding to the number fixed on the drawing), type and diameter of the pile;
Date and hour of start and end of each operation drilling, reinforcement setting, concreting;
Records shall be submitted in duplicate to the Employer/Engineer every following working day
until 9 a.m.
The Contractor shall submit for review by the Employer/Engineer a proposal of piling record and concrete quality control sheets including all the details mentioned above.
6.5.2
The Contractor shall execute static loading tests for preliminary piles in the following quantity:
up to 10 piles:
up to 30 piles:
and for working piles, it shall be 2% of the total piles (each type) executed at Site but not less than
3 piles.
The pile(s) to be tested shall be agreed by the Employer/Engineer. The procedure to be followed is
provided by ASTM D 1143 or by BS 8004 art. 7.5.5 and local authorities requirements.
The maximum test load shall be 2.5 times the working load for preliminary piles and 1.5 times the
working load for work piles. Total settlement measured from the start time of loading up to the end of
loading (all increments and cycles of loading and off loading) shall not exceed 7 mm for preliminary
piles and 5 mm for working piles. (Integrity tests are to be performed on 100% of the piles.
The loading materials and equipment, the measurement devices and procedures have to be submitted
for the Employer/Engineer's approval by the Contractor.
Concrete Work
7.1
This specification covers the technical requirements of all concrete works (reinforced concrete, mass
concrete and precast concrete. The scope covers all temporary works as shuttering, scaffolding and
testing of all materials.
7.2
Civil Design/Engineering
American standards (ACI and ASTM) mainly ACI 305R, 318, 318R, British Standards (BS) mainly BS
8110 part 1 "Structural use of concrete",
the provisions of German Standards DIN, mainly DIN 1045, "Concrete and reinforced concrete
structures, design and construction,
the specification of the CIRIA Guide to construction of reinforced concrete in the Arabian Peninsula.
In order to protect the concrete against high concentrations of chlorides and sulphates, all measures
should be taken to achieve as dense a concrete as possible.
The concrete design and working drawings of main structures, and if required also of secondary structures, shall be submitted by the Contractor for approval by the Employer/Engineer.
7.3
Dimensional tolerances
The permissible tolerances must comply with the DIN 18201, DIN 18202, DIN 18203.
7.4
7.4.1
General Requirements
The precondition for obtaining concrete with special properties is that it should be made with the
appropriate composition, that it is placed in such a way that segregation does not occur and further
that it is fully compacted and given appropriate curing.
All reinforced concrete must meet the durability requirements. The water-cement ratio must not exceed 0.40 and all mixes shall contain microsilica.
Water-reducing and retarding admixtures shall conform to ASTM C 494. Accelerating admixturesshall not be used. Type F or Type G high range water reducers shall conform to ASTM C 1017
andshall be "Rheobuild 561" or Rheo-build 716" as manufactured by Master Builders or equal.
High-range water reducers shall be naphthalene-sulfonated polymer based material. No admixtures containing chlorides shall be used.
Chemical admixture suppliers shall provide certified test reports with each shipment indicatingcompliance with the appropriate specification. The test reports shall include the chloride content of the admixture, specific gravity and solids content.
Silica fume may be either a condensed form as manufactured by Master Builders, Microsilica Ltd.
or a slurry form F-100 as manufactured by ELKEM Chemicals or other approved products.
When microsilica is batched as a slurry, the liquid portion shall be included as part of the mix water.
Microsilica shall meet the following requirements:
SiO2 (min) % 90
C (max) % 6.0
In order to avoid any problem, which may occur due to the improper use of microsilica, all the possible
problems related to the use of microsilica shall be coordinated with a specialist of microsilica supplier.
Mainly the following shall be coordinated:
Admixtures used in production of concrete shall be the same as used in establishing the required
concrete mix and shall be used in accordance with the manufacturers directions.
Concrete should be as stiff as possible, in order that there will be no concentration of cement
slurry or water in the top layer. The concrete should be kept moist for at least 7 days after placing.
7.5
RCC columns, beams and slab soffits are to be fair faced without secondary finishes except coating.
Special attention shall be given for shuttering works in order to reduce board marks and loss of concrete slurry from the mix.
Floor slabs and foundations shall be treated and prepared in order to receive the subsequent finishing
or top layers works (tiles, cement screed, waterproofing, epoxy screed, etc.).
7.6
Bar-bending Schedules
The Contractor shall prepare bar bending schedules based on the detailed reinforcement drawings and
following the international standards for formats and details. These shall be presented to the Employer/Engineer for information at an early stage in the contract, certainly before finalization of his
order for reinforcement for that particular part of the work. .
Reinforcing steel used in reinforced concrete shall comply with the following standards:
British Standards:
BS 4449
BS 4482
BS 4483
BS 4461
7.7
All reinforced concrete structures shall be designed to BS 8110 where crack widths are not to exceed
0.3 mm, or BS EN 1992-1. Water retaining structures (including cable trenches, manholes, cable pits
and basements) shall be designed to BS 8007 or BS EN 1992-3, where crack widths are not to exceed
0.2mm,
7.8
7.8.1
Quality of Materials
All materials used for concrete and reinforced concrete structures shall be of the best quality, free
from defects likely to undermine the strength and duration of service of the works. The materials furnished must at least comply with the agreed standards, and with all requirements described in this
specification.
7.8.2
Storage of Materials
All materials shall be stored and handled in a manner that will prevent contamination and/or deterioration. Deteriorated and/or contaminated material shall not be used for the concrete and shall be
removed from the site at the expense of the Contractor.
7.8.3
Cement
The cement used for concrete, reinforced concrete, mortar, grout and plaster works shall be Portland
Cement in accordance with ASTM standards type II. If the aggregate is determined to be potentially
reactive, the alkalis as (Na2O + 0.658 K2O) in the cement shall be 0.6 percent or less. Cement shall be
obtained from sources approved by Dubai Municipality.
7.8.4
Water
Water used for mixing and curing shall be potable and supplied from approved sources .
7.8.5
Aggregates
7.8.5.1 Material
The aggregates for concrete shall be crushed mountain rock subject to Employer/Engineers approval.
The aggregate (fine and coarse aggregates) shall be supplied from an established pit or quarry approved by Dubai Municipality. The aggregate source shall have a minimum five (5) years history of
satisfactory performance in structural concrete and consistency of supply.
Samples of the proposed aggregates for concrete mixes shall be collected and tested to confirm its
compliance with the specified properties:
ASTM C
142
ASTM P
214
ASTM C
289
ASTM C
127
ASTM C
128
Coarse Aggregate
(20 mm and 10 mm)
Unit weight
Soundness
5 Cycles
MgSO4
Clay, Silt,
Dust
Abrasion
No Limit
12 %
Gravel
Crushed Rock
1%
3%
30%
Fine Aggregate
5 mm and Dune Sand
No Limit
15%
3%
5%
30% (5 mm 0nly)
Gradation
Clay lumps
(Max.) 2 %
(Max.) 3 %
Deleterious
expansion
due to AlkaliSilica reaction
Potential reactivity
Chemical
method
0.10% @
16 days
0.10% @
16 days
Absorption
and specific
gravity
coarse aggregate
Absorption
and specific
gravity fine
aggregate
No limits applicable. Report the concentration of dissolved silica Sc and reduction in alkalinity Rc.
ASTM C
40
Organic impurities
ASTM C
87
BS 1377
Coarse Aggregate
(20 mm and 10 mm)
Elongation
< 25 %
index
Flakiness in< 25 %
dex
Section 105.1
Total sulfates < 0.4 %
Section
3.2
Test 9
(Crush all
material to
pass 2 m
sieve)
BS 812
Total chloride
as cl
Fine Aggregate
5 mm and Dune Sand
< 25 %
< 25 %
< 0.4 %
<0.03%
<0.06%
Type
Grading
Specific Gravity
Magn Sulfate soundness
Clay Silt and dust content
Shape (Elongation and flakiness)
Los Angeles Abrasion
Moisture content
Drying shrinkage
Organic impurities
10% fines value for concrete
Coarse Agg
Daily
7 days
30 days
daily
3.5 days
Initial stage only
2 days
Initial only
30 days
7 days
Fine Agg
Daily
7 days
daily
Initial stage only
2 days
Initial only
30 days
-
7.8.6
All reinforcing bars, fabrics and steel embeddings used in substructures shall be from sources approved
by DM. Reinforcing bars for piling works and substructures shall be epoxy coated as per ASTM A775
and shall be used as described under piling works section .The average thickness of the coating shall
be 250 m . Samples shall be collected from material delivered to the site and tested.to Any non compliance of the epoxy coated bars with ASTM A775 shall be a cause of material rejection.
7.8.7
Concrete mixes
L:
S1: Reinforced concrete in contact with groundwater, substructures, piles and pre-cast works.
Plain concrete used for lean concrete, blinding, protection and flooring screeds , backfill etc.
Concrete Class
Cube Strength At
28 Days In Mpa
Maximum Free
Water/Cement
Ratio
Max. Nominal
Aggregate Size In
mm
Min. Cement
Content InKg/M3
L
S1
S2
20
40
35
0.4
0.4
25
20
20
280
400
380
7.8.7.2
Consistency of Concrete
The amount of water used in the concrete shall be adjusted as required to ensure such a consistency
that it can be readily transported placed and compacted without segregation of the materials or bleeding of free water at the surface. Addition of water to compensate for stiffening of the concrete before
placing shall not be permitted. Consistency of the concrete shall be checked by slump tests and shall
not exceed the values given by BS 1881, Part 2 or DIN 1045, Part 1.
Quantity, strength class and consistency of the concrete, stating whether it is suitable for plain or
for reinforced concrete, and number of the type of concrete
Concrete mix particulars (cement type, aggregate, additives and admixture etc.)
Ready mix concrete supplier shall be a well established, locally based and approved by Authorities;
ISO-certified company and has long experience in the same field.
7.8.8
Transport of Concrete
Immediately after mixing, the concrete shall be conveyed to the place of use as rapidly as possible
using methods which will prevent the segregation, loss or contamination of materials. The concrete
7.8.9
Concreting Operations
Concrete shall not be dropped into place from a height exceeding 2 meters. Trunking and chutes to
Employer/Engineer approval shall be used for any concrete to be deposited from a height exceeding 2
m.
Concrete which has partially hardened shall not be exposed to injurious vibration or shock, except for
controlled re-vibration where specified. When concreting of a certain large structural element is specified strictly as to be poured continuously, then the concreting operations shall be organized for day
and night working, in long shifts, as necessary.
50 mm
75 mm
Slabs (internal)
30 mm
40 mm
Immediately after the compaction of the concrete has been finished, the Contractor shall ensure adequate protection from the weather. Excessive drying can lead to crack formation as a result of plastic
contraction. The concrete surface shall be completely covered with a layer of 0.3 mm thick PVC-plasticfoil material, and kept constantly moist for at least 7 days.
Where large sections of concrete are poured, special precautions t shall be taken to reduce and dissipate the heat generated by the setting and hardening of the concrete (e.g. built-in cooling water pipe
system).
The minimum amount of reinforcement in accordance to the applicable codes and standards shall be
present to prevent shrinking cracks. This is applicable also for flooring screeds and mortars.
No load of any kind, however light, shall be allowed on concrete which has not properly set and the
Contractor shall prevent any load to be imposed on the concrete structures until it has been declared
by the Employer/Engineer to be ready to carry loads.
7.9
QA/QC
7.9.1
Trial Mixes
Fresh concrete temperature shall be checked at different intervals and process of hydration and heat
generation shall be evaluated by the specialist.
All above tests shall be conducted for fresh concrete delivered to the site.
All sampling and testing shall be carried out by an approved independent third party laboratory accredited by DM.
The following criteria shall be the basis of mix design:
Absorption (I.S.A.T.)
10 mins:
0.05 ml/m2/sec
30 mins:
0.02 ml/m2/sec
60 mins:
0.005 ml/m2/sec
120 mins:
0.003 ml/m2/sec
<800 coulombs
Air content
< 1%
< 2%
Test cubes from trial mixes shall be made and tested in accordance with BS 1881, Part 3 or DIN 1048,
Part 2. Number of samples and cubes shall be agreed by Employer/Engineer.
As per BS 5328, three separate batches of concrete should be made, workability of each batch determined and three test cubes shall be made from each batch for each age (e.g. for 7 and 28 days) at
which tests are required. The strength shall conform to target mean strength as per BS 5328, - Requirements for designed mixes.
The appropriate strength requirements may be considered to be satisfied if none of the strengths of
the cubes is below the required characteristic strength and if the average strength of the nine cubes is
not less than recommended by BS 5328, trial mixes.
All test results will have to comply with specification requirements before approval given to the mixes
design.
7.9.2
No more than 5% of the test results my fall below the 28 day specified strength. Making and curing of
test specimens shall be in accordance with BS 1881 Parts 108, 109, 110 and 111.
All mixes can only be placed following approval by the Employer/Engineer. The mean strength shall
exceed the characteristic strength by a margin of 1.64 times the standards deviation expected from
the batching plant. However, no standard deviation less than 3.5 N/mm2 shall be used as a basis for
designing a mix.
If the results are less than those specified, the Employer/Engineer must suspend all concreting work
and order further tests. Any concrete found not to comply with the specification shall be broken out
and replaced to the satisfaction of the Employer/Engineer.
7.9.3
Strength of Concrete
Type of tests:
Cutting cores: The procedure used shall comply with the requirements of DIN 1048, Part 2 or an
agreed equivalent standard.
Gamma radiography: The testing shall be carried out in accordance with the requirements of Part
3 of BS 4408 or equivalent.
Ultrasonic test: Such tests may be used to obtain approximate indications of the strength of the
concrete in the structure (BS 4408, Part 5).
Electromagnetic cover measuring: Such tests may be used to verify the position of the reinforcement and shall be in accordance with the requirements of design (BS 4408, Part 1).
Rebound hammer test: Such tests may be used to obtain approximate indications of the strength
of the concrete.
Load tests of structures or parts of structures: If the results of the above mentioned check tests
show that the quality of the materials is inadequate or if other defects are revealed, the Employer/Engineer may require a loading test to be made.
If the result of the test is not satisfactory, the part of the defective works concerned shall be taken
down or cut and reconstructed by Contractor to comply with specification.
All the costs for the above mentioned tests shall be borne by the Contractor.
7.9.4
Reinforcement Certificates
Each consignment of steel reinforcement shall be accompanied by a test certificate from the manufacturer showing that the steel has been tested and analyzed and the date of such tests and analyses and
that such tests and analyses comply in all respects with the standards.
The following tests shall be carried out on reinforcement
BS 4449/4461
BS 18
BS 4449/4461
7.9.5
The formwork drawings and details shall be prepared by a specialist approved by Employer/Engineer.
Erection of formwork and its supporting structures shall be under the direct supervision of the designer/material supplier. Concrete shall not be placed unless a written release is obtained from the
designer/supplier.
Back propping/props shall be installed immediately after striking of formwork to minimise deflections.
It shall remain in position for long periods as much as possible.
All materials shall be of good conditions and not showing any defects (buckling or deformation). It shall
be used as per the design loads.
All supporting vertical elements shall rest on well prepared and sound surfaces. Direct supports on soil
are not allowed. Erection and installation shall follow the safety requirements.
Marine plywood and white wood shall be new and free of any defects. It shall be placed in line and
level as per the structural elements dimensions. Shutter accessories like tie rods shall be placed strait
and not inclined. Tie rods passing through walls of fluids retaining structures, manholes and cable
trenches shall be provided with approved GI cast iron waterstopper.
Pre-cast Concrete
Grouts
Only non-shrink grouts, which is either cementitious or epoxy grouts, shall be used. Grouts deriving
their non-shrink properties from metal oxidising (i.e. an increase in volume of metal due to oxidation)
shall not be allowed. Compressive and flexural strengths of the non-shrink grouts shall be as follows:
Properties of Grouts
Type of
Consistency
Grout
Cement type
Epoxy type
flowable
High flow
7 days
45
80
7 days
8
25
28 days
65
28 days
10
All grouts for rotating machines including turbines and generators shall be responsibility of the equipment supplier/contractor, who shall be responsible for its execution and guarantee. The Contractor
shall ensure that the proposed type of grout is suitable for the thickness of the gaps between concrete
and base plates as well as for the dimensions of the pockets.
Generally epoxy grout should be used for reciprocating machinery, heavy cranes, prime movers, e.g.
turbines, diesel engines, high output pumps, chimneys, boilers, large transformers, etc. cementitious
grouts shall be used mainly for base plates of steel structures, small pumps, crane rails, etc. The Contractor shall propose the type of the grout for Employer/Engineers approval.
Samples from grouts mixed at site shall be collected and tested to verify its compliance with approved
materials
10
10.1
The scope of work covered by this division shall be deemed to comprise the supply and installation of
all brickwork and concrete blocks, solid partition walls shown on plans and as specified inclusive mortar
and plasterworks or as fair-faced masonry works. It shall also include the supply of the appertaining
materials and structural parts, scaffolding, offloading on site and all operations in connection with masonry works.
10.1.2 Masonry
This Clause covers all brick work, concrete block work, damp-proof courses, natural stone and mortar.
Any related concrete work and the reinforcement shall comply with relevant Clause of this specification. Unless otherwise specified, the following standards shall apply:
BS
DIN
6073
Masonry
5628
1053
Masonry works
4103
Alternatively, masonry may be design in line with the Uniform Building Code (UBC).
Dubai Municipality Advisory Notes shall be considered.
Locally available bricks of the strength in accordance to the applicable Codes and Standards or locally
fabricated concrete masonry units shall be used. The size of concrete blocks shall normally 400 mm
long, 200 mm high and 100mm, 150 mm, 200 mm in width. Their average compressive strength shall
not be less than 10.0 N/mm2. Samples of concrete blocks shall be tested as per BS 6073and approved
10.1.3 Plaster
This Clause covers all internal and external plastering for buildings and structures, etc., including all
metal accessories. Works and materials shall generally comply to DIN 18350, with cement and water
as stated under Concrete and Reinforced Concrete.
All surfaces to be plastered shall be clean and free from dust, grease, loose mortar and any traces of
salts, and shall be brushed down by wire brush to remove any loose material. Joints in block work shall
be raked out to a depth of 10 mm minimum. Smooth concrete surfaces shall be roughened by hacking
or brush hammering. All surfaces to be plastered shall be thoroughly sprayed with potable water before plaster is applied.
Junctions between different material (other than between the main reinforced concrete member and
the brick or block walls) shall be reinforced. The reinforcement shall be embedded completely in the
undercoat of plaster. Plaster lathwork, chicken wire, expended metal shall be of non-corrosive stainless steel material.
Where junctions are between main concrete elements (beams, columns etc.) and brick or block work,
definite breaks shall be carried out through the plaster finish by stop beads or similar. Plaster accessories such as stoppers, corner beads etc. shall be provided. Joints shall be sealed with approved material.
All surfaces to be plastered initially shall be hopper sprayed to form a key coat. The key coat shall be
cured for a minimum of 4 days by water, and all free water shall disappear before the application of
the finished coats.
Only proprietary ready mix plaster materials approved by Employer/Engineer shall be used for the
under and final coats. Manufacturer shall provide his standard guarantees for work under this section.
Jebel Ali Power Station K Phase III
RFx No.:
2131600023
Page:
54/105
Date:
April 2016
10.2
Execution
All execution works must be in accordance with standards and normal practices to the state of the art.
All plastered surfaces shall be even and straight, smooth and free of working joints and shall be sound.
Before laying the blocks, it shall be continuously sprayed by fresh water to avoid absorption of water
existing the mortar mix. All wall cavities shall be kept clear and cleaned from mortar droppings.
All materials and methods of application shall be submitted for approval by Employer/Engineer.
11
Steel Work
11.1
Civil Design/Engineering
All steel works, design and construction shall be carried out in accordance with relevant British or German standards.
However the complete works shall be covered by one standard only in the respect of the static analysis,
the final design drawings and the profiles to be used. In the case of structural steelwork, care should
be taken that all parts in the assembly fit accurately together and corresponding parts should preferably be interchangeable. Forcible correction to fit the members together will not be allowed.
The Contractor shall submit to the Employer/Engineer for approval the country of origin and manufacturer of the steel he proposes to supply.
The contractor has to design, prepare and submit the complete shop drawings to the Employer/Engineer to get the approval before start of the fabrication. All structural steel structures, design, shop
drawings and connection details shall be approved by a third party designer prior to start execution.
11.2
11.2.1 General
The design and construction of steel structures shall be based on:
Eurocode 4, Design of Composite Steel and Concrete Structures (DIN V ENV 1993-1-1, DIN V
ENV 1993-1-2, DIN V ENV 1994-1-1 and DIN V ENV 1994-1-2) or
Basis for the execution of all works shall be DIN 18 800, Structural Steel Work:
11.3
Materials
11.3.1 General
As far as possible standard profiles shall be used according the static calculation.
Minimum plate thickness for steel structures shall be 6 mm for webs and 8 mm for flanges respectively.
Welding shall be in accordance with Structural Welding Code of American Welding Society (AWS D1.1)
ASTM A-325 for high strength friction bolts and ASTM A-307 for other bolts may be considered
11.3.2
Steel Specifications
All miscellaneous steel shall conform to grade DIN EN 10 027 S 235 or equivalent standards as BS,
ASTM, JIS, etc.
The following listing summarizes material standards and specifications, as well as minimum material
requirements for design, manufacture and erection:
MEMBER
STANDARD
MATERIAL
Built-up Members
DIN EN 10 027-1
MEMBER
STANDARD
MATERIAL
Formerly DIN 17100 Formerly St, USt & RSt37-2, St37-3, St52-3 or
and EN 10 025
Fe360B, BFU, BFN, C & D1, and Fe 510
DIN 1024 Series DIN
all steel brands S235 and S355,
1025 Series
Hot Rolled Members
Tubes
DIN EN 10 210-1,2
Stud Bolts
DIN 32 500, Part 3 &
St 37-3 per DIN 17 100, (fy 350 N/mm)
DIN 18 800-1
11.3.3
Galvanizing
11.4
Execution /Workmanship
11.4.1 Tolerances
Care shall be taken to ensure that the tolerances specified on the drawings or the relevant standards
BS 449 Part 2 or DIN 18203 Part 2 are executed. Also, refer Clause 1.4.3.
11.4.2 Connections
Field connections shall be friction-type or bolted type connections with ASTM A-325 or equivalentbolting with heavy hexagonal head bolts. Connections at building expansion joints must be slotted with
shoulder bolts with locknuts. The slots shall be of sufficient length to permit movement of sliding,
member in both directions from the neutral position, of 25 mm.
Co-ordination of the design of the structural steel members with the design of related concrete
structures
Complete erection of the steel structure in accordance with the agreed erection drawings
The size of construction members shall be of the maximum admissible size for the transport to and
handling at site. Fabricated steel structures shall be pre-assembled in the workshop to such an extent
to ensure proper field erection, and shall be dismantled (non welded/bolted members only) for transportation, during which the contractor shall reasonably protect the steel structure from damages. The
steel structure shall be suitable packed, cover or coated, and any damage and corrosion during transportation shall be the responsibility of the contractor.
Torque wrenches shall be used for tightening of bolt connections. Structural steel members delivered
to the site shall be evenly supported and stacked on timber to avoid deformation.
Bolts, nuts, washers, rivets and other identical items of structural steel required to be incorporated
into concrete shall be delivered to the Site well in advance.
Bolts, pins, packings, tools, insulation material, electrical parts, motors, parts with electrical devices,
attached instruments, welding equipment and material shall be stored inside closed stores.
All metal parts shall be interconnected to the Stations earthing system as specified in electrical specifications.
Tolerances shall be kept in accordance with the relevant stipulation of DIN 18203 Part 2 or BS 449.
11.4.2.1 Cutting
Cutting may be by shearing, cropping, sawing or machine flame cutting. Hand flame cutting is subject
to review by the Employer/Engineer.
Cut edges on rolled products must be given a finishing operation by a metal cutting method (e.g. by
planning, milling, grinding or filing). Notches and cracks are to be eliminated in the same way.
Jebel Ali Power Station K Phase III
RFx No.:
2131600023
Page:
59/105
Date:
April 2016
11.4.2.3 Bolting
The threaded portion of each bolt shall project through the nut at least three full thread. Agreed high
strength friction grip bolts, preferably the type with indicated load are to be used where specified and
are to be tightened strictly in accordance with the manufacturer's instructions and the pertaining regulations. The surfaces in contact shall not be painted and shall be free from oil, dirt, loose rust, burrs
and other defects which would prevent solid seating of the parts or interfere with the development of
friction between them.
When connections are made using high strength friction grip bolts the "provisional directions for the
calculation, execution and structural design of friction grip bolted fastenings (high strength friction grip
fastenings)" prepared by the German Committee for Steel Construction are to be observed.
11.4.2.4 Welding
The execution and testing of welding shall be in accordance with the
British Standards BS 5135 or German Standards DIN 18800 and DIN EN 10025. All welds, unless otherwise stated are to be continuous minimum 6 mm fillet weld and shall be dressed smooth, free from
porosity, cracks, holes and finished to match adjacent surfaces. When welding operations are completed, all welding flux shall be removed without delay. After welding, the components should possess
the shape planned for them preferably without any subsequent dressing. The cooling of welds must
not be accelerated by any special measures.
Site welding is to be restricted to the absolute minimum and if cannot be avoided, procedure shall be
submitted for Employer/Engineer approval considering protection of the surrounding erected equipments and services.. The examination of welded work and the inspection of welds during and after
manufacture is to be carried out by responsible specialist welding engineers. Welding shall be carried
out by expert tradesmen and in strict accordance with the current code of practice.
For site welding, all welders shall be obliged to pass qualification tests to determine their ability to
perform such type of work. They shall provide necessary certificate from specialized agencies. For steel
structures, the Contractor shall carry out X-ray tests, ultrasonic testing or magnetic particle testing as
approved by Employer/Engineer for at least of 10 % of all welds by approved experienced representatives of a firm licensed for welding and testing.
11.4.3 Painting
Surface treatment and painting before and after delivery to site shall be in accordance with the Tender
Document Volume II, Part G05.5 Corrosion Protection and Painting.
Parts to be encased in concrete shall not be painted or oiled. Surfaces inaccessible after shop assembly
shall receive the full specified protective treatment before assembly.
11.4.4 Erection
The Contractor must prepare and submit to the Employer/Engineer for approval a delivery and erection schedule of all structural steel work on site. This schedule must show the supply fabrication, delivery, assembly, erection and painting of the steelwork. Approval by the Employer/Engineer of any of
the construction and erection methods or plant shall not in any way relieve the Contractor from his
responsibilities under the contract.
The Contractor shall supply all suitable plant, hoisting gears and tackles for the erection of the steelwork and shall provide all temporary tie ropes, struts, shores and scaffolding..
The positioning and levelling of all steelwork and the accurate placing of every part of the structure
shall be in accordance with the approved drawings.
During erection, the work shall be securely bolted or otherwise fastened and if necessary temporarily
braced, so as to make adequate provision for all erection stresses and conditions. Neither permanent
bolting nor welding shall be done until proper alignment has been checked by Employer/Engineer at
site.
The Contractor shall supply all necessary false work and staging, tools, temporary connections, erection plant, service bolts, nuts, washers, anchorage cables, bracing and all other materials necessary to
carry out the work and shall remove the same as the progress of the erection permits.
Encased steelwork and steel in foundations shall be solidly encased in concrete, with a minimum cover
of 100 mm. All erection works shall be executed in a safe manner and bolts shall not be left without
complete tightening.
After completion of erection works, bolt tightening shall be checked to verify the required torque values for the different sizes of connection bolts use are achieved.
11.4.4.1 Footings
Foundation bolts and plates or steel stubs shall be provided for all columns and shall be firmly keyed
and grouted into concrete foundation blocks.
The Contractor shall set column bases and beam plates on non corrosive steel wedges or angle screeds,
to accurate elevations approximately 4 cm clear of masonry or concrete. Wooden wedges shall not be
used.
11.4.4.4 Rejection
Any steelwork which in the opinion of the Employer/Engineer is not in accordance with the requirements of the Standards or with the Specification, shall be rejected and removed from the site at the
Contractors expense.
11.5
QA/QC
The manufacturer's test certificate (mechanical tests and the chemical composition) for all steelwork
shall be supplied to the Employer/Engineer. The Contractor shall provide free of charge any supplementary tests reasonably required by the Employer/Engineer. At least three (3) samples of each profile
section/manufacturer/batch shall be collected and tested at an independent testing station in accordance with BS 5400 - BS 4872 or DIN EN 10025, DIN 18800 and DIN 18801. If the results of the tests are
unsatisfactory the whole quantity of steel which the sample represents shall be rejected at the expense
of the Contractor. No steelwork shall be delivered from the manufacturer's works until it has been
tested and the results comply with the requirements of the relevant BS or DIN.
Apparatus, equipment and tools required for testing (e.g. for X-rays) shall be part of the scope of supply, with following tests at least required for welds:
X-ray tests for each heavy load bearing structure member: min. for 10 % of all welds
Also refer to other clauses of this specification for welding and in general for testing, the most stringent
of which shall apply.
12
12.1
General
This sub-clause refers to the specification covering the provision of all materials and labour in relation
to the supply, manufacture, on site of articles made of steel or cast iron.
All steel structures and parts specified under this sub-clause shall be hot dip galvanized and painted
according to Tender Document Volume II, Part G05.5 Corrosion Protection and Testing.
The list of small items to be furnished shall contain but not be limited to the following:
Structural steel stairs, platforms and walkways, railing for stairs, platforms, walkways and protection around floor openings, corner and edge protection for concrete steps and concrete covers,
support of any equipment foundation, anchors, ties, hangers, inserts or any embedded steel parts.
Steel pipes and plain round bars for making guardrails and ladders
12.2
Design /Engineering
12.2.5 Ladders
Ladders shall be provided by the contractor to all heights and accesses as required in the design, e.g.
to reach roofs, basements, emergency exits, etc. Side-rails of ladders shall consist of 75 x 10 mm flat
bars, or suitable channel sections as per design requirements. Rungs shall be of 25 mm diameter bars
with anti slip surface, tenoned into the side rails and securely welded. Rungs shall be 0.4 m long between side-rails and spaced 28 cm.
Ladders shall be securely fastened at top and bottom into the wall and shall have intermediate clips or
flats and fastenings spaced not more than 2.0 m apart. Clips or flats shall be riveted or welded to the
side.
13
Waterproofing
13.1
General
This clause is applicable for substructures waterproofing, roof waterproofing and all above ground wet
areas as HVAC rooms and toilets.
Roof waterproofing shall comprise of a 4 mm thick APP bitumen membrane with non-woven polyester
reinforcement of a minimum 400 g/m2 torch applied laid over the concrete cast to slopes towards the
rain water down spots and roof drains/roof outlets, covered with a minimum 50 mm extruded polystyrene insulation board of a minimum density of 40 kg/m3, separation/geotextile layer of 180 gm/m2
followed by mortar and precast concrete tiles. Thickness of insulation board can be increased to meet
HVAC design requirements and DM Green Buildings Regulations.
Wet areas of suspended slabs shall be waterproofed with two layers of 4 mm thick SBS modified bituminous membrane separated with a minimum of 50 mm of mortar to the Employer/Engineer approval.
For Waterproofing of sub structures and foundations , basements and underground tanks, Trenches,
cable pits, drainage manholes, cable ducts these shall be tanked and protected externally with 4mm
thick SBS modified bituminous membrane having non-woven polyester reinforcement of a minimum
of 260 g/m2. Minor structures, like buried protection slabs, light pole foundations, and fence foundation shall be painted with two coats of coal tar epoxy coating and protected with 1,000 gauge polythene sheet.
Provided membrane for substructures shall be protected from damage by concrete screed or protection board as approved by the Employer/Engineer. All roof and substructure membranes shall be terminated in a groove covered with aluminium flashing (1mm thick) and sealant to form a water tight
construction. Fasteners shall be made of aluminium or SS 316.
All components of the system shall be obtained from the same supplier. The application of the waterproofing system shall be carried out by the manufacturers standard applicators approved by Employer/Engineer and in accordance with the manufacturers instructions and specifications. Shop
drawings/ typical details and method of application shall be submitted by contractor for approval.
The waterproofing systems shall be guaranteed for 10 years for material, workmanship and other liabilities which may be caused by leaks/failure of the system. The guarantee provided by the Contractor
shall be supported by manufacturers guarantee for the same period.
All roofs and wet areas shall be tested by flooding with water with a minimum 50 mm height for 36
hours. The Test shall be repeated after completion of tiling and related ancillary works.
13.2
Roof drains
Roof drains (wall or floor type) of approved heavy duty and corrosion protected cast iron material shall
be installed. The roof drains shall be capable of receiving the terminations of the waterproofing membrane.
13.3
For concrete and structural steel buildings and sheds, gutters and rainwater pipes shall be provided
and connected with the main storm water system through a catch pit constructed directly under the
down pipes. The materials shall be powder coated aluminium of suitable gauge, but at least 0.75 mm
for gutter and 2 mm for pipe, with a finish matching the colour of the cladding/external finishing. Heavy
duty hot dip galvanized and powder coated pipe clips shall be installed at 2.0 m intervals .
Clean outs shall be provided where ever required and as per approved design drawings and calculations of the rainwater collection system. All connections shall be made watertight and tested for leakage in presence of Employer/Engineer representative.
14
14.1
All structural steel buildings, such as machine hall, etc. shall have insulated sandwich cladding for roofs
and walls. All roof sunshades may be provided as single sheets. The roof and wall cladding specification
described below sets out the general requirements for cladding and the use of standard trapezoidal
cladding for main structures such as the turbine halls. However , any other requirements called by
local authorities regarding quality of material, quality of insulation and fire fighting protections shall
be followed by Contractor. Fire tests certificates attested by local authorities or local independent laboratory shall be provided along with materials submittal.
14.2
Warranties
warranty in form acceptable to the Employer/Engineer, jointly signed by Contractor and the Subcontractor for the work, warranting against defective materials, products, workmanship, water and air
tightness, coatings, installation design, performance and breakage due to defective engineering, fabrication and installation for a period of Ten years shall be submitted by contractor.
14.3
In addition to the standards already listed under clause Structural Steel, following standards shall
apply to the works covered by this clause:
DIN
4102
Fire Ratings
BS
476
BS
1161
BS
1494
BS
6105
DIN
4108
DIN
4109
14.4.1
The roof and wall cladding shall meet the following performance criteria:
Classification
Physical and Environmental
Test
Humidty Resistance
ASTM D 2247-68
Abrasion Resistance
(falling sand method)
ASTM D 968
Kesternich Pollution
Resistance Test
DIN 50018
Aesthetic
Procedure
Test samples exposes
to 100% relative humidity at 38C for
1000 hours
The test determines
the number of litres of
sand /under controlled conditions) required to abrade
though the samples
coating system exposing bare metal
Samples exposed to
30 test cycles:
each cycle consists of
8 hours at 40C in controlled sulphur dioxide
atmosphere at 100%
relative humidity, followed by 16 hours of
drying at ambient
temperature
Test samples continuously exposed to 5%
salt fog at 35C for
1000 hours. All samples scribed to expose
the underlying metal
before testing. All panels were inspected in
accordance with
ASTMD 714 to evaluate results
Test samples exposed
for minimum of
800,000 Langleys of
solar radiation on
equatorial mount (following the sun) with
reflecting mirrors for
No blistering
Edge delamination 1-2
mm
No effect
Test
Procedure
concentration of sunlight
Eight minutes of water
spray each sunny hour
An exposure of
800,000 Langleys is
equal to approx. 6
years exposure 48 angle in Florida, United
States
The above performance criteria shall be substantiated by test results certified by recognized independent testing authority.
Roof and wall claddings shall normally be constructed of agreed composite wall panels, comprising of
profiled hot dip galvanized steel sheeting in composite insulated (injected rigid foam) panel form. The
foam insulation shall be at least 50 mm thick (PIR) and the internal lining shall match the required
appearance.
Deflection of the roof shall be less than 1/200 of the span, except where roof slopes are below 5 degrees when their limiting deflections shall be 1/300 of the span. Deflection of the wall area shall be
less than 1/150 of the span.
External and internal flashings shall be manufactured from materials matching the external and internal sheeting in gauge, colour and finish.
Fixing of panels shall be done only with high grade (316) stainless steel self tapping screws, complete
with stainless steel (or aluminium) washers incorporating neoprene sealing washers and PVC colour
caps. Screws shall be fixed through the profile crown.
Flashings and side laps shall be fastened with No 14 x 12 stainless steel stitcher screws. Where applicable, black synthetic rubber profile filler blocks shall be used in conjunction with flashings to adequately seal ridge, eaves, gables and drip. This filler block shall be permanently fixed before covering.
All materials and fixing accessories including detailed shop drawings shall be submitted for Employer/Engineer approval.
For fire resistance, sheeting shall comply with BS 476 parts 3, 5, 6, 7 - class 0 or local authorities
requirements whichever is stringent.
14.5
Panels must be factory manufactured units, produced on a continuous online injection facility with the
bonding foam completely filling the space between the panels. Temperature control of the metal substrates, of the chemical dispensing area and of the online conveyor press is obligatory to maximise the
uniformity of the foam density and the foam substrate adhesion.
The insulation foam shall be a factory injected rigid closed cell fire retardant CFC free, polyisocyanurate
(PIR) foam with a minimum depth of 50 mm between the inner and outer sheets.
The heat transition value U of the panels shall in acc. to DIN 4108
Roof and wall cladding shall provide an acoustic attenuation factor in acc. to DIN 4109
Properties and tests for the insulation foam shall be as follows:
Test
Test Requirements
Density
ISO 845
40 kg/m3
Compression Strength
ISO 844
C 10 = 1.5 kg/cm2
Modulus Of Compressibility
ISO 844
37 kg/cm2
Tensile Strength
ISO 1926
2.8 kg/cm2
Thermal Conductivity
ISO 2581
0.019 W/m2K
Flame Resistance
ISO 3582
ISO 1663
Panels shall provide an effective cover width of 1000 mm and shall be manufactured in exact lengths
to suit the structure and minimise jointing. Panels shall have encapsulated side-tapes to ensure maximum side lap joint uniformity.
External steel sheeting shall be of a hot dip galvanized steel sheet (total of both surfaces-G90275 g/m2) of at least 0.75 mm thickness. The external coating system shall be a multi-layer system
consisting of:
Prime Coat: Epoxy primer of a nominal thickness of 8 m.
Base Coat : Two components polyamide cured epoxy, nominal thickness of 100 m
External Weather Coat: Two components polyurethane pigmented colour coat, nominal thickness of
40 m
The inner skin of the panel shall be of hot dip galvanized sheets of at least 0.5 mm thickness, corrosion
protected with a polyester coating of white colour.
Contractor shall propose first class wall/roof metal cladding systems from manufacturer with excellent
reputations for approval by the Employer/Engineer.
14.5.1 Sunshades
Sunshade shall be made of single sheet non-insulated hot dip galvanized steel sheet (total of both
surfaces 275 g/m2) of at least 1.0 mm thickness with trapezoidal profile protected on both sides by a
multi-layer coating system as below:
Base Coat : Two components polyamide cured epoxy, nominal thickness of 100 m
External Weather Coat: Two components polyurethane pigmented colour coat, nominal thickness of
40 m
14.6
Shop drawings shall be submitted to the Employer/Engineer for his review and acceptance in accordance with the general conditions of contract. The Employer/Engineer approval will not relieve the contractor from his responsibilities under the contract. No work shall be fabricated until the shop drawings, structural calculations and other related submittals, documentation, certification and samples
have been reviewed and approved by the Employer/Engineer. Shop drawings shall incorporate plans,
elevations and sections and full size details of the work covered under this section. The full size details
shall highlight all other materials adjoining the work, their thickness or gauge, areas to be sealed and
sealant material, areas to receive gaskets, tapes, flashings, direction and magnitude of thermal expansion, direction and magnitude of applicable building movement, type of construction including joinery,
fasteners, weld, anchorage assemblies , rainwater goods, sealing of penetrations etc.
Details describing the design, material and installation procedures of anchorage and structural framing
element shall be structurally documented, specified and fully described in the shop drawings.
14.6.2 Fasteners
Main fasteners (self tapping of self drilling/self tapping screws) are applied to the external side of the
sheet through the centre of every other through, at every purlin, except at the end laps and end of
sheets. Fasteners should be placed in every through at end laps and sheet ends.
All holes should be drilled, not punched, and swarf shall be removed immediately. If left, the swarf will
corrode and the corrosion will stain the coating.
Selection of the correct fastener for each application is important. Fastener of incorrect type size and
material can result in leaks, corrosion and premature failure.
15
15.1
15.1.1 General
With regard to thickness of material, sub-construction, stiffening, doors and gates must satisfy the
structural requirements. The fire protection, heat insulation and sound insulation regulations are to
be observed by suitable construction. All security and emergency exit doors to be in accordance with
the Local Safety Regulation.
For fire rated doors, certificates issued by an accredited testing laboratory must be submitted.
The sub-construction must not show any pressure marks on the surfaces; the type of construction used
shall not be liable to warping.
The locks, roses and lock sets must suit the lock cylinders. The cylinders are to be matched to the door
leaf thickness.
Manufacturer of all locking system and ironmongery shall be approved along with his standard guarantees of 5 years for material under this section.
The general master key shall operate all locks (25 nos.)
The main key shall open all locks of one main compound (15 nos. per each compound)
The sub-key shall open all locks of a certain group within the main compound (5 nos. per each
group)
The single key shall open the lock of a single room (5 nos. per each door)
Necessary attention shall be paid to later extensions of the master key system, which shall be suitable
for the entire plant including all final stages.
The profile cylinders shall be resistant to the prevailing corrosive atmosphere and shall suit all plant
requirements and shall be of types such as half, double, asymmetrical, short-cylinder, etc. The material
of the cylinders shall be of massive brass, nickel-plated with six security pawl studs.
The keys shall have an engraved indication of the applicable key system and the compound/group/ or
door number.
The Contractor shall provide key cabinets sufficient to store all keys coming with the master key system. All keys shall be labelled with the corresponding door number.
16
17
Glazing
17.1
All work shall comprise labour, equipment, and the supply of the appurtenant materials and structural
components including transport, loading, off-loading and storage at the site unless otherwise specified. Manufacturer shall provide his standard guarantees for work and material under this section.
17.2
17.2.1 General
All materials and structural components covered by standards shall meet the quality and dimensional
requirements thereof.
Any glass shall be tempered and glass thicknesses specified shall be deemed as minimum thicknesses
within the allowable tolerance unless another glass thickness is specified. If requested so to do, the
Contractor shall furnish samples and state the names of the suppliers of materials and structural components.
opening size
as per requirements
wind loading
3000 N/m2
type of glazing
as stated above
type of glass
float 6 mm tempered
light transmittance
0.76
0.12
shading coefficient
0.84
thermal transmittance
1,1 W/m2K
17.2.4 QA/QC
All materials to be supplied and installed shall be in accordance with the relevant standards and certificates of quality testified by an independent authority or institute shall be submitted to the Employer/Engineer for approval prior to execution of the works.
The Employer/Engineer will make selection of samples for testing material. The Contractor to the
sealed air space not to leak shall give five (5) years guarantee, e.g. when the inside surface starts to
dim and becomes dirty.
18
Suspended Ceilings
18.1
This specification covers the scope of suspended ceilings that shall be provided as specified for electronic/control rooms, corridors, etc. The Contractor shall submit detail drawings and specification of
the suspended ceiling system before installation of the work.
The suspension system shall be of sufficient strength and rigidity to carry the panels. The panels shall
be secured with locking clips to the grid. The rod hangers shall be made of galvanized steel of 4 mm
diameter (minimum). The joints between the panels and the light fixtures and the air supply shall be
smooth and regular. Power driven fasteners shall be used for fixing the rod hangers in the reinforced
concrete ceiling.
18.2
Material
For all areas where suspended ceiling shall be installed ceiling panels shall be 0.8 mm thick, stove
enamelled, aluminium sheets. In general the size of the panels shall be 600 mm x 600 mm. Panels of
closed appearance of 75 mm or 150 mm wide and length up to 6 meters could also be proposed for
certain areas. Perforated type shall be used for corridors while plain type shall be used for other
rooms/areas.
The panels shall provide the following minimum sound absorption coefficients :
18.3
The Contractor shall be responsible for the integration of the various disciplines (HVAC, lighting, fire
detection, etc.) and shall take into account the location of diffusers and lighting fixtures. Suspension
system supporting the false ceiling panels shall be independent of all services. All services shall be have
its own hanging and supporting structures.
Representative prototypes and mock up samples shall be provided for Employer/Engineer approval.
Those prototypes shall be fitted with all the equipment and components.
19
Flooring
19.1
This specification covers the scope of flooring works that shall be executed under this contract.. All
work under this division shall comprise all required labour, equipment, and the supply of the appurtenant materials and structural components. Finished floor levels shall be uniform for all areas/rooms at
each level in one building.
All materials and structural components to be supplied and installed by the Contractor and, therefore,
ultimately incorporated in the work shall be new and unused. They shall be suitable for their intended
purpose and appropriately be matched to each other.
All materials and structural components, patterns and colours shall be subject to a review and selection
by the Employer/Engineer.
19.2
Raised floor
19.2.2.1 Material
Composite panels made of high density (700 kg/m3) waterproof chipboard and aluminium sheets for
protection of the interior face. The panel edges shall be slightly chamfered (5) and protected by an
aluminium profile or other conductive material.
Loading
5 kN/m2
The maximum allowed deformation shall be 2 mm under 5 kN point load.
Minimum height of the free space between sub-floor and raised floor surface shall be confirmed by
electrical calculations respecting the standard and specified clearances.
Flooring pedestals and stringers shall be zinc plated and shall consist of:
Steel tube of 1 (one and quarter inch) minimum
Base plate of 120 mm x 120 mm x 3 mm
Head cap to be screwed to the steel tube with top plate of 85 mm diameter and 3 mm thickness.
The screw thread on the steel tube shall allow for 40 mm adjustment for unevenness of the ground.
Lock nut shall be provided under the head cap
19.2.2.2 Installation:
The whole system shall be constructed in such a way as to allow conductivity of electrostatic charges
and shall be connected to the earthing system.
Penetrations for cables and pipes shall be arranged with a ready made garment.
Pedestals shall be mechanically fixed to the concrete by 4 screws and further it shall be glued with
epoxy based material.
Floor system shall be rigid and capable to withstand seismic forces. At the perimeter it shall be supported on GI and painted angles fixed to the concrete walls/solid block wall or equipment supports.
Stringers shall be extended and properly connected to edge angles.
Base board or skirting shall be provided to match the floor panels.
19.3
19.3.1 General
Prior to the start of his operations under this division, the Contractor shall verify that all conditions are
suitable for the timely and effective performance of his work. Work shall be carefully laid out to ensure
symmetry about centrelines of the area involved and to obviate the use of less than half pieces of tiles,
slabs, etc. Floor pedestals shall not fall or clash with cables.
The work shall be executed with the highest degree of precision and according to the drawings and
specifications. Method statements and coordinated shop drawings shall be submitted for all flooring
works. Preparation of Surface
Where no adequately even surface is available for work involving thin beddings, special provisions shall
be made to compensate for this, e.g., rendering coat, screed to the approval of Employer/Engineer.
Any filler or levelling compound shall be applied so that it will bond firmly and durably to the base, will
not crack and will adequately withstand pressure.
20
Tiling
20.1
Tiling work shall include all required labour, equipment, and the supply of the appurtenant materials
and structural components including off-loading and storage at the site.
Tiling and flooring shall be applied where indicated as per the finish schedule stated on the approved
drawings. All materials and structural components to be supplied and installed by the Contractor shall
be new and unused. They shall be suitable for their intended purpose and appropriately be matched
to each other. Before starting the work, the Contractor shall submit duplicate samples of the patterns
and colours of the material for Employer/ Engineers material approval.
Tiling materials shall cover the followings:
Ceramic tiles minimum 8 mm thick for walls and 12 mm thick for floors supplied with all corner
pieces and base boards
Acid proof tiles minimum 8 mm thick for walls and 12 mm thick for floors supplied with all corner
pieces and base boards
In general, tiles shall have the following properties: sharp, straight, parallel, non-crumbling edges, free
from soluble salt and other detrimental constituents; free from cracks and blisters; rear and side surfaces capable of bonding effectively for placing, laying and jointing.
All tiles shall be of first class quality. Floors which are not covered by tiles shall be properly prepared
and covered by an epoxy screed layer of 6 mm thickness and coated as specified under G.5.5.
20.2
Prior to the start construction under this division, the Contractor shall verify that all conditions are
suitable for the timely and effective performance of his work.
Work shall be carefully laid out to ensure symmetry about centrelines of the area involved and to
obviate the use of less than half pieces of tiles, slabs, etc.
The work shall be executed with the highest degree of precision and according to the approved drawings and specifications.
20.2.2 Placing
For interior finishing works, all tiles, shall only be set and laid after the fixing of window and door
frames and trims, stop rails, plumbing installations and the application of plaster unless otherwise
specified.
All tiles shall be set or laid plumb, in true alignment and horizontal or at the slope specified, without
any projections, with regard to any specified reference and level lines.
Where floor drains are provided, the plans of the finished floor shall be sloped towards the drains.
Intersections and returns shall be formed accurately. Cutting of tiles, where necessary, shall be done
along the outer edges of the floor and done without marring the tile surfaces. Tiles shall fit closely and
neatly around all plumbing fixtures and around electrical outlets, pipes, fittings etc. so that cover plates
21
Painting
Refer to Tender Document Volume II, Part G05.5 Corrosion Protection and Painting.
All painting works shall be executed by an approved specialist subcontractor.
The Contractor shall verify that all site conditions are suitable for the timely and effective performance
of his work. Contractor has to protect all finished surfaces from any damages or contaminations.
Samples of all coating systems including the surfaces preparation, texture and colour shall be provided
and approved by Employer/Engineer for further reference. All surfaces shall be smooth and free of any
marks.
Colour of all paintings shall be approved by the Employer/Engineer in accordance to the accepted colour scheme for the project.
22
22.1
General
This specification covers the scope of plumbing and drainage installation work for the buildings where
applicable. The work under this division comprises the design, supply and installation of the complete
plumbing and drainage system s fixtures and shall be carried out in compliance with local rules and
regulations and in accordance with the specifications and drawings defined hereafter.
The Contractor shall prior to commencement of the works, prepare and submit detailed drawings,
indicating the layout and schematic diagram of all piping, fittings and valves, the position of fixtures,
floor drains, , etc. Piping shall be indicated by diameter, slope and invert level.
Outside the building, connection points to general water distribution and drainage system shall be
provided.
The scope also covers external drainage which comprises design, supply and installation of various
kinds of drainage culverts, pipes, and the like, including all accessories such as inspection shafts, etc.
Works shall be completed in all aspects as per Tender Document Volume III, Part P16 Waste Water
System and Sump Pumps.
All work also includes supply, transportation, loading, unloading and storage at Site and placing according to drawings and specification of all materials and components connected therewith.
All earthwork in connection with the work specified hereunder shall be carried out as described under
"Earth Work". Connections of drainage pipes to inspection chambers/pits/manholes or other structures shall be of flexible construction as per DM standard details.
22.2
Materials
All materials and structural components to be supplied, erected, or installed by the Contractor and,
therefore, ultimately incorporated in the work shall be new and unused, and of selected quality approved by the Employer/Engineer.
All materials and accessories for piping, valves, and fittings shall be of the best grade and quality to
suit the requirement. Manufacturer shall provide his standard guarantees for work and material under
this section.
All materials shall be in accordance with ISO, BS, ANSI, DIN or other accepted standards subjected to
approval by Employer/Engineer.
copper pipes with insulation for potable water pipes inside the buildings
UPVC pipes class E for external storm water drainage and sewer lines
Jebel Ali Power Station K Phase III
RFx No.:
2131600023
Page:
91/105
Date:
April 2016
Sanitary fixtures such as specified and shown on approved drawings including all accessories and
fittings.
In battery rooms, acid/chemical resistant eye was and sink/shower shall be provided to the approval
of Employer/Engineer.
22.3
Execution of Work
22.3.1 General
All parts of drainage installations shall be suitably adapted to each other so that the required performance is achieved, safety in operations ensured and corrosion processes largely reduced.
The Contractor shall arrange for any approvals and acceptance required from local authority for the
execution of the works.
All plumbing piping works shall be pressure tested prior to any coverings. All drainage pipes shall be
tested against leakage. All testing works shall be in accordance with international standards and local
authorities requirements.
All water supply and drainage lines shall be connected at interface points (refer to Tender Document
Volume I, Part G03 General Project Requirements). Pressure regulating valve shall be installed for
each building for potable and service waterline at the interface between outside pipelines and inside
building connections.
For external drainage works and prior to laying of pipes, the respective pipe trenches shall be subject
to thorough inspection by the Employer/Engineer with respect to alignment, slope, dimensions and
suitability of bottom to meet the requirements of proper pipe laying.
In general, each pipe trench deeper than 1.25 m shall be secured by means of planks, sheet piling,
struts and bracings, whatever is required according to the soil conditions ground water, nearby roads
and vibration resulting from traffic. The spacing of bracings shall allow mechanical excavation of the
trench where required.
The width of a trench shall not be greater than necessary to permit satisfactory jointing and thorough
tamping of the bedding material under and around the pipe, unless otherwise authorised due to unsuitable material encountered.
23
23.1
This specification covers the scope of roads, walkways and corresponding facilities including gravel
surfacing. Paving and surfacing required for this work includes but is not necessarily limited to supply,
storage and transport of materials, equipment, mixing and placing, all tests, workmanship and finishing
of roads and surfacing. Reinforcing of the exiting access roads at both entries are part of the scope
(Refer to Vender Document Volume III, Part P20 Civil Works)
The actual thickness of road-courses shall be calculated based on the final results of the soil investigation, heaviest loads that will be transported, intensity of traffic, design life. At all paved and asphalted
roads and access entries to buildings 4 PVC sleeves of adequate thickness and diameter not less than
300 mm with concrete surround at maximum every 100 m distance shall be provided.
All road works shall be executed by a specialist company approved by Employer/Engineer.
The followings clauses brief the quality and technical requirements of road construction materials and
surfacing.
23.2
Sub-grade
The area of the Works shall be cleared of any material or obstructions which in the opinion of the
Employer/Engineer might adversely affect the stability of the fill or pavement, and the top layer removed to a depth of 300mm (or more if the design so requires).
The formation shall be compacted to a dry density of at least 95% of the maximum dry density as
determined in BS 1377: Test 13 (BS heavy compaction) and a CBR of 30%.
Tests shall be conducted for each 50 m length of any part of road.
23.3
Sub-Base
Sub-base material shall be crushed rock having suitable properties and confirming to the following
grading:
BS Sieve
mm
75
37.5
10
5
0.6
0.075
When Tested to BS 882 the material shall have a minimum "ten percent fines" value of 5. The material
passing the 0.425 sieve shall have a plasticity index of less than 6.
Jebel Ali Power Station K Phase III
RFx No.:
2131600023
Page:
95/105
Date:
April 2016
23.4
Wet Mix road base material of 150 mm thick shall consist of crushed gravel or crushed rock and shall
be suitably proportioned to confirm to the following grading:
BS Sieve
mm
50
37.5
20
10
5
2.36
0.6
0.075
The fraction passing the 0.075 mm sieve shall not be greater than two-thirds of the fraction passing
the 0.425 mm sieve.
Material constituents shall comply with the following maximum limits:
For material passing the 0.425 mm sieve:
Liquid limit
25%
Linear shrinkage
3%
Plasticity index
6%
50 mm
25%
Water absorption
2%
Flakiness index
35%
Elongation index
35%
Mg SO4 soundness
15%
The material shall be spread evenly by mechanical means (paving machine or spreader box) on the
sub-base in layers not exceeding 150 mm compacted thickness. Wet mix shall be mixed by approved
mechanical plant. Water for adjusting the moisture content shall be added at the mixer. After mixing,
the material shall be removed from the mixer and transported to the placing location without delay.
The moisture content at the time of laying shall be within 0.5% of the optimum value determined in
accordance with the Vibrating Hammer Method described in BS 1377, Test 14
The base l shall be compacted to a dry density not less than 98% relative compaction and until movement of the surface ceases and the surface is closed. The completed layer shall have an in-situ CBR of
not less than 90%.
The final surface shall be shaped and finished true to line and level within a tolerance of + 10 mm to
the levels shown on the drawings. Before placing the next construction layer or applying prime coat,
the road base shall be mechanically swept; then cleaned with compressed air to remove loose material. As soon as possible after cleaning of the surface, the road base shall be sealed by the application
of a prime coat as specified.
Quality control tests for sub base layer shall be conducted for each 50 m length of any part of road.
Samples of sub base material delivered to the site shall be collected and tested as directed by employer/Engineer at site.
23.5
Aggregate shall be hard, clean, durable crushed rock or gravel, and sand all in accordance with BS 4987.
Laboratory tests shall be made at regular intervals to confirm the suitability of aggregate.
Coarse aggregate is defined as that fraction retained on a 3.5mm BS sieve. It shall have physical properties which do not exceed the following test values when tested in accordance with BS 812:
Wearing Course
Aggregate crusing value
Flakiness index
Elongation index
Water absorption
Base Course
20 25 %
25 30 %
25 30 %
2%
Coarse aggregate may contain up to 15% of pieces with one uncrushed face in each grading size when
tested in accordance with Test Method DM-30l. Aggregate obtained from quarried rock shall be
deemed to satisfy this requirement.
Separate coarse and fine aggregate fractions shall be tested for soundness in accordance with ASTM C
88. After 5 cycles of immersion in magnesium sulfate solution and drying, the loss of weight expressed
as a percentage of the initial weight shall not exceed 12%.
Wearing course shall be of 40mm minimum finished thickness, the aggregate grading shall be as
follows:
BS Test Sieve
mm
28
20
14
10
6.3
3.35
1.18
0.075
Bitumen shall be of Grade 60/70 penetration with properties corresponding to an interpolation between Grade 50 and Grade 70 as defined in BS 3690. The specific gravity and temperature/viscosity
relationship shall be provided.
The frequency of testing of the penetration index shall be two tests per delivery of bitumen. The PI
range shall be -1 to +1.
Quality control tests for bitumen layers (after completion) shall be conducted for each 50 m length of
any part of road. Samples of mixed materials delivered to the site shall be collected and tested on daily
basis and as directed by employer/Engineer at site.
Preparation and testing of Marshall Specimens: ASTM D 1559 using 75 blows per face.
The values for specific gravities of the aggregates to be used in calculating the voids shall be taken as
the mean of the Bulk, Apparent and Effective Specific Gravities as defined in the American Asphalt
Institute publication "Mix Design Methods for Asphaltic Concrete."
Binder
Wearing
Course
Course
Voids in mix
7 - 10
5-8
14 - 20
14 -20
1000
Flow (mm)
2-4
2-4
270
320
48 - 60
48- 60
After a design mix has been agreed and adopted as a job mix, the maximum permitted deviations from
the job mix shall be as follows:
Permitted Deviations:
Sieve size:
6.3 mm or larger
5%
3.35 mm
4%
0.6 mm to 1.18mm
3%
0.075mm to 0.3mm
2%
Bitumen
0.2%
Voids in mix
1%
23.6
The level of the acid-soluble chloride (as NaCI) (BS 812: Part 117) in the sub-base and road-base layers
shall not exceed 3.5% and 0.5% by weight respectively.
The level of acid-soluble sulphate (as SO3) (BS 812: Part 118) in the sub-base and road-base raiders
shall not exceed 2.0% and 0.5% by weight respectively.
Potable water shall be used for compaction purposes.
23.7
Hard Shoulders
The material used for any hard shoulders shall comply with the specification for wet-mix road base.
23.8
All materials involved in road construction shall be tested upon delivery to the site to verify its compliance with specifications.
Field tests as CBR, compaction of road layers, coring for asphalt layers and verifying marshal properties,
physical and mechanical properties of aggregates etc. shall be conducted as specified above and as per
sequence approved by Employer/Engineer. All testing shall be conducted by approved third party laboratory. For asphalt materials and coring testing shall be carried out by DCL.
23.9
Where new pavement is required to join into existing road construction, the joint shall be formed and
treated in accordance with the drawings.
Unless shown otherwise on the drawings, each layer of existing bituminous course shall be cut back to
a clean vertical face and coated with hot bitumen of a grade suitable for the purpose immediately
before laying adjacent new bituminous material.
23.10.3 Gates
Gate frames are to be hollow steel sections according to the requirements of the design. The gates
shall be fitted with adjustable hinges and bronze bushes with greasing points. The in-fill of the gates
shall be of chain link wire mesh or tubular sections to the approval of Employer/Engineer. The gates
shall be lockable and the drop-bolts of inactive leafs shall be locked in the closed position by the active
gate to prevent opening.
23.11 Landscaping
The Work includes supply and placement of gravel as specified below.
23.11.1.2
23.11.1.3
Gravel
Gravel will be 20 mm uniform sized crushed rock. Quality specification shall be as in the Clause Concrete and Reinforced Concrete- Aggregates. Thickness of gravel layer shall be 10 cm and the top level
shall flash with the surrounding walkways or curb stones.
Gravel shall be distributed evenly at the areas specified. Material shall be brought to the area of placing
in quantities required for that portion of work only. Excessive dust shall be avoided during unloading
of the material and the passage for the other contractor to their working areas shall not be blocked by
the dumped material.
Before laying of gravel the subsoil shall be tamped so that it would not mix with the gravel placed.
23.11.1.4
23.11.1.5
23.13 Kerbs
Kerbs, channels, edgings and quadrants shall be cast generally to BS 140 but to the dimensions shown
on the drawings where these differ from preferred dimensions list in BS 340. They shall be cast to the
required road bending curve/radius. In general kerbs shall be 200 mm thick and 300 mm in depth and
shall be laid with a 6 mm gap and pointed with I to 3 polymer modified cement mortar above road
level only. Concrete bedding and backing to kerbs shall be cast in-situ to the dimensions shown on the
drawings and as per Dubai Municipality details.
Flush kerbs shall be similarly laid and jointed or may be cast in-situ. The outside comer of the kerbs
shall be chambered.
In the case of precast kerbs one joint in ten shall be left unpainted and 6 mm compressible insert
provided, and a construction joint formed in the haunching at this point for expansion. Similarly expansion joints are to be formed in in-situ kerbs at 4.0 in intervals.
All raised kerbs shall be alternately painted black and white in the plant area and at junctions.