Scope:
The purpose of this statement is to define the rules and conditions designed to ensure
that demolition work is planned so as to enable personnel to be aware of all the
procedures and dangers involved and to decide on the safest method of work.
2. Relevant Process/Specifications:
Tender specifications
3. Tools/Equipments Required:
Air compressor, electrical and pneumatic jack hammers, electrical and pneumatic
grinders, relevant scaffoldings with platforms and hand tools.
5. Safety Measures:
Temporary electrical services required for the demolition works shall be made in
accordance with HSE rules and regulations.
Demolition survey shall be noted the location of all known services on and adjacent to
the site whether they are overhung or underground.
During demolition, a horizontal distance of 6 m radius shall be kept as a restricted area
to allow the fall of debris.
Where work cannot be done safely from the ground level, adequate scaffolding shall be
erected and shall be maintained in safe condition.
Outside the working hours, ladders providing access from ground to first landing shall
be removed and stored in a secured area.
Ensure shall be made that all debris shall be cleaned out on sequential basis.
6. Execution:
Prior to starting work, necessary approvals shall be made from the Company.
Existing services, pipelines and fittings still in are shall be protected in a proper way to
prevent any damage or clogging during demolition.
In case of demolition of existing building, adequate information shall be given well in
advance to allow and plan any shutdown is necessary during changeover.
Adequate protection and preservations shall be given to existing trees, hedges, shrubs,
lawns, pathways and roads.
In case of any obstructions or fall of debris on roads, the area shall be cleaned on
immediate basis.
During demolition of concrete structures, suitable temporary supports shall be made to
existing structure. All the demolished materials shall be separately stored and disposed
off at the approved dumping location.
Necessary excavations with proper shoring shall be made in case of any demolition to
be done under the grade level.
Adequate precautions shall be made to prevent fire or explosions caused by gas, vapor,
etc.
Periodically, water shall be sprayed to avoid dust during demolition.
In case of observations of any unidentified services or cables during the process, it shall
be informed immediately to the company and work shall be proceed further only after
getting proper approval.