Escolar Documentos
Profissional Documentos
Cultura Documentos
CHAPTER 07
FORMWORK
7.1 Introduction
In the modern construction world, concrete is the most widely used construction material. As
concrete is a plastic material in green state it has to be kept in an enclosure till it hardens. This
enclosure is known as formwork or shuttering.
One of the easiest and most obvious ways of judging whether a concrete job is satisfactory or
not is by its finished appearance. The formwork and the way it is made and used play a greater role in
the finished appearance than anything else. It is made from expensive materials by skilled carpenters
and the total cost of fabricating, erecting and striking formwork is often comparable with the concrete.
Apart from the appearance considerations, formwork usually needs to be used many times
and this can only be done if it is carefully and properly handled, cleaned and stored- be it of timber,
steel or other material as otherwise time and money will be wasted and the job will not progress
smoothly.
The formwork must withstand the worst combination of the following loads.
Total weight of formwork, reinforcement and concrete.
Construction loads including dynamic effects of placing, compacting.
Wind loads (mainly for column)
Easy of Handling
Form panels and units should be made so that they can be easily handled by hand or mechanical
means. In addition to all form work must also be designed and constructed to include facilities for
adjustment, leveling, erecting and striking without damage to the formwork or concrete.
The material of the formwork should not wrap or get distorted when exposed to sun, rain, and
water during concreting.
Formwork must be capable of gradual and easily remove
To get successful form work,
It must be accurately set out.
The shuttering should be built accurately. So that the desired size, shape, position and finish
can be attained.
The formwork should be strong enough to support all dead and live loads without collapse or
danger to site personnel and to the structure.
Using sheet materials and sealing the joints must fill with punch sheet, wetted cement paper,
polythene strips to prevent grout leakage.
The formwork should be designed to erect and dismantled easily.
The most commonly used materials for formwork are timber, plywood and steel. In our site we used
timber and plywood for formworks. The selection of materials for formwork depends on several
factors.
Economy of materials
Number of times used
Durability
The availability of sizes and shapes of materials
The shape formwork required to be constructed
The ease of handling, constructing, erecting, concreting, removing, etc.
Therefore depending on the situation we have to select the most suitable material.
7.3.1 Timber
This is the most common material used for formwork construction. It is easy to work with and is also
cheap. The moisture content of timber should be between 15%- 20%. So if the timber is dry, it will
absorb moisture from the wet concrete that could weaken the resultant concrete member.
We used 1x 2, 2x 2, and 4 x 4 timber for form work
7.3.2 Plywood
Plywood is extensively used material for the formwork construction due to its lightweight,
availability, large sizes and due to the ease of fabricating. The selected should be of a superior
grade and the thickness should be related to the anticipated pressure. In our site we used 12mm
thick coated plywood sheets (1800x900x12mm).
7.3.3 Steel
NATIONAL DIPLOMA IN ENGINEERING SCIENCES
INSTITUTE OF ENGINEERING TECHNOLOGY, KATUNAYAKE
Steel is also used as a material for formworks but it is not common as plywood or timber. It is mainly
due to its economy and availability. The steel shuttering are very expensive and they cannot be
fabricated at the site. So we have to use the prefabricated steel shuttering with limited number of
sizes. But it is more suitable when the same sizes of formworks are to be constructed repeatedly. Also
in the case of circular sections we have to use steel shuttering.
mould oil
After set the formwork, Then a piece of plywood sheet was placed on the top of the
formwork the column formwork was checked for vertical using two plumbs, which were hanging
from the top of the formwork. The horizontal distance between the formwork and string line can be
measured at the top and the bottom to ensure the vertically of the formwork. The props should be
adjusted until the distances between formwork and string at top and bottom are equal. Finally all the
clamps and props must be checked for tightens. Then it can be concreted.
Obviously four timber framed plywood panels one for each face are used forming
the squire or rectangular shaped column side, and should be strengthened and securely hold
these box together during the placing of concrete.
7.6 Formwork for Beams and Slabs
First 1000 Finished Floor Level (FFL) was marked on columns. Beam bottoms were prepared by
referring drawings. In this case G.I. pipes, 2x2 timber planks and plywood sheets were used. Then,
the previously prepared beam bottom supports were fixed to the column by referring the 1000FFL
level. After that, beam bottom was placed by using adjustable screw jacks. Then, sideboards of beam
were fixed to bottom by considering the slab thickness and plywood thickness.
Next, 4 x 4 timber beams were placed, parallel to the shorter span of the slab and square
scaffoldings and U-base jacks were used to hold 4x 4 timber rafters. On top of timber beams 2 GI
pipes end 2 x2 timber planks were laid and fixed by nails. The plywood sheets were laid over the
GI pipes & timber planks and fixed them with sideboards of the beams
After that, mould oil was applied all over the slab as a release agent. And reinforcement bars
were placed. By drilling the sideboards of the beams the form ties & threaded bars were fixed using
P.V.C. pipes. Then, G.I. pipes were fixed to the sideboards of the beam and tightened with the form
ties. The joints were sealed using masking tape. Some formwork was left opened in order to remove
the dust or any other foreign materials on the slab.
After the arranging the reinforcement, the slab and the beams were leveled using dumpy
level.
Floor level
Z
Beam
Y
15
Staff
3000 mm
Column
Dumpy Level
1000 FFL Line
X
Floor level
Generally supports (false work) of the formwork raised or lowered to get the required reading and by
this process the formwork for the slab and the beams can be easily leveled
Slab formwork
After laying scaffolding or pipe supports, (4x 4) timber joints can be placed
over the U jacks with are placed on scaffolding frame or pipe supports. Then 2 GI pipes can
be laid over the (4 x 4) timber joints. Interval between GI pipes should be 250 300mm.
GI pipes can be leveled by loosening or tightening scaffolding or pipes jacks. After
completing the leveling of GI pipes, plywood sheet can be laid over the GI pipes with the
help of the (2 x 2) timber and (2 x 4) timber, which is at the edge of the side board.
Beam bottom
2x2 timber
Plywood
Wire nail
24 hours
7 days
14 days
21 days
6mm Plywood
16 mm bar
Base Reinforcement
Form Tie
Welding
1x2 Timber
Additional rebar
P-Cone
16 mm bar
16 mm bar
400
Plywood Template
150 150
6mm tk plywood
(900 x 1800 )
225
16 mm bar
450
450
Pipe supports
225
450
450
2400
300
Plywood Template
300
250
2000
500
500
500
225
250
450
225
450
2" x 2" timber
250
12mm tk plywood
(900 x 1800 )
pipe support
500
250
500
12mm tk plywood
(900 x 1800 )
250
500
2000
500
pipe support
250
500
550
500
Kicker
F.B.L +5.000
450
12mm tk plywood
(900 x 1800 )
300
2" G.I. pipes
Kicker
F.B.L. + 5.00
300
530
1930
450
7.10 Scaffolding
Scaffolds are temporary working platforms erected around the perimeter of a building or
structure to provide a safe working place at a convenient height. They are usually required when the
working height is 1.5m or more above the ground level.
Scaffolding
A Scaffolding set has fallowing items
steel ladder
Figure 5.2.4
RMD jack can bear heavy load more than normal jacks. RMD jacks have its own fabricated
method.
GI pipes 50mm diameter
Timber (2 X 2, 2 X 4)
Couplers
Base plate
upvc pipe
Maximum load on Adjustable U head, fabricated U head & Base plate is 40-45 KN with 250
mm maximum length. Some of above parts are shown in the